Connecting to The Transmission Grid in Finland

Connecting to The Transmission Grid in Finland
18.3.2015, Vaasa Wind Energy
Petri Parviainen
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
Main grid development plan
400 kV main grid
400 kV under construction
main grid base line scenarios
Fenno-Skan 2 DC connection to Sweden
Forssa reserve power plant
Yllikkälä - Huutokoski B 400 kV
Hyvinkää - Hikiä 400 kV
Estlink 2 DC connection to Estonia
Ulvila - Kristinestad 400 kV
Hikiä - Forssa 400+110 kV -yhteys
Hirvisuo - Pyhänselkä 400 kV
Lieto - Forssa 400+110 kV
Hikiä - Orimattila 400 kV
Reinforcement of Helsinki region network
Reinforcement of north-south connections
Keminmaa - Pyhänselkä 400 kV
3rd AC interconnection to Sweden
Grid connection of nuclear and wind power
Keminmaa
Pyhänselkä
Hirvisuo
Tuovila
Kristinestad
2013-2023:
400 kV power lines 1500 km,
110 kV power lines 1000 km
EIA / Preliminary design
Petäjävesi
Detailed planning and permits
Implementation
Ulvila
Forssa Hikiä Koria
90 % of new power lines will be constructed
along or next to an existing right of way
Huutokoski
Lieto
Yllikkälä
Connecting to The Transmission Grid in Finland
Contents
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Basics
Substation connection
110 kV powerline connection
Connection of the power plant
Connection process
Requirement for power plants
Agreements
Connection fees
Transmission grid pricing
Contact us
Petri Parviainen Fingrid, 18.3.2015
Basics - connecting to the power transmission grid 1(3)
The new connection shall be defined taking into
account:
•
Power of required consumption and/or generation, connection
requirements, and location of the connection
•
Impacts on the system security of the grid and on the
environment
•
Disadvantage caused by increasing outages and
disturbances on regional power generation and consumption
•
Technical implementation options and costs
Technical solutions:
•
Voltage level (110, 220,400 kV)
•
Connection to a substation or transmission line
•
Protection and compatibility of electrical equipment
•
Energy measurement interfaces and data communications
The connection must conform to the terms of
connection
• Fingrid Oyj's general terms of connection
• Specifications for the operational performance of power plants
Petri Parviainen Fingrid, 18.3.2015
Basics - connecting to the power transmission grid 2(3)
Customers
Substation
Customers
Substation
B.
Transmission line
in main grid
Fingrid`s substation
Customers
Substation
110 kV
A.
B.
Fingrid`s substation
TWO OPTIONS TO CONNECT
A. Substation connection
Petri Parviainen Fingrid, 18.3.2015 B.
Powerline connection
Basics - connecting to the power transmission grid 3(3)
Petri Parviainen Fingrid, 18.3.2015
Substation connection
A substation connection is a connection to the Fingrid`s 400 kV, 220 kV or 110 kV substation
The connection shall be agreed in the Connection Agreement containing the fees, rights and
obligations
The customer is responsible for the construction of its own power line connection
Fingrid is responsible for the necessary technical arrangements at its substation or, if necessary,
Fingrid builds a new substation.
Production and/or loads more
than 25 MVA must be
connected to a substation
Petri Parviainen Fingrid, 18.3.2015
1 (1)
110 kV Powerline Connection
A transmission line connection is a branch line or substation
which is connected to a 110 kV transmission line
The connection shall be agreed on Connection Agreement
including the fees, rights and obligations
The maximum allowed unit size of a transformer connected to
a transmission line is 25 MVA
Lots of regulation to take into account ...
Petri Parviainen Fingrid, 18.3.2015
1 (2)
Connection of Power Plant
Power plants with a nominal power of more than 0.5 MVA connected to
the Finnish power system must fulfil The Specifications for the
Operational Performance of Power Plants (VJV),
A power plant:
– in excess of 250 MVA is connected to a 400 kV substation
– less than 250 MVA can be connected to a 110 kV substation
– the following can be connected to a 110 kV transmission line
 power plant of less than 5 MVA
 power plant of a maximum of 25 MVA when the short-circuit current fed
by the power plant to the main grid is at the most 1.2 times the rated
current of the power plant
 Customer is responsible for the disconnection relays of its power plant.
These relays must:
– trip the power plant during the high-speed automatic reclosing of the
transmission line ( data communication access will be provided to
the site by Fingrid and it is included in the connection fee)
– contain at least frequency, zero voltage and undervoltage relays
Real-time information required from the customer:
– active power, reactive power and state information of switching
devices
– Update cycle of real-time exchange shall be at least 3 min
– FEN network, protocols: elcom, ICCP, IEC 60870-5-104
Petri Parviainen Fingrid, 18.3.2015
1 (2)
Connection process
Customer
Contact and basic
information:
•
Company data
•
Power
•
Location
•
Preliminary
timetable
Planning,
Plans must be
delivered to Fingrid
for review
Connectivity
Planning
Construction,
Timetable,
Commissioning
protocol and delivery
to Fingrid
Construction
Delivery of final
technical
documentation to
Fingrid
(in 2 months after
commissioning)
Commissioning
Grid Code Compliance Process
Fingrid
Examination of
connection solutions
alternatives of the
connection
Review of plans
Implementation
Additional
instructions
Letter of intent
Connection
Agreement
Outage and switching
planning
Review by operation
specialist
Main grid contract
Petri Parviainen Fingrid, 18.3.2015
Connection and
operation
Outages
Commercial
operation
Energy accounting
Finnish Grid Code(VJV2013) and Wind Power
•
General Requirements & Definitions
–
–
•
Scope and Power Classes
VJV-reference Point
•
•
•
Technical Requirements
–
–
–
–
–
–
Voltage and Frequency Operational Range
FRT Requirement
Reactive Power Capacity
Voltage and Reactive Power Control
Active Power and Frequency Control
Power Quality
Petri Parviainen Fingrid, 18.3.2015
Modelling
Compliance testing
Compliance Process and Data Delivery
–
–
–
•
•
Stages 1 to 4
Timeline of Compliance Process
Data Exchange and Connection to 3rd Party
Networks
Derogations
Specific Study Requirements
Timeline of the Grid Code Compliance Process (VJV2013)
Schedule requirement
Stage 1 – As soon as
possible but no later than
after the selection of the
supplier of the main
components of the Power
Generating Facility
Stage 2 – No later than
3 months prior to the
start of the Compliance
Testing related to the
Specifications
Stage 3 – 9 months from
the date on which the WPP
supplied Active Power to
the Power System for the
first time
Stage 4 – 12 months from
the date on which the WPP
supplied Active Power to
the Power System for the
first time
3 mo.
9 mo.
3 mo.
Actions
Stage 1 – Delivery of
general data of the Power
Generating Facility,
determination
of VJV Reference Point,
and handling of potential
derogations
Stage 2 – Delivery of
project-specific
data of the Power
Generating Facility and
Compliance Testing
Planning
WPP supplies Active
Power to the Power
System for the first
time
Stage 3 – Accepted
execution of Compliance
Testing, and
documentation
of Compliance Testing
Petri Parviainen Fingrid, 18.3.2015
Stage 4 – Acceptance of
the compliance
monitoring process of
the Specifications
Grid Code Development
VJV2007 (effective before 12/2011)
• Requirements specified for conventional generation, vague Nordel requirements for
WPP
Update and extension to VJV2007 (12/2011-10/2013)
• Specified requirements for WPP, requirements set from 0.5 MW capacity upwards
VJV2013 (effective 11/2013)
• Requirements, process and responsibilities for all power plants specified in one
document
VJV2018 (after European Commission is in favor for ENTSO-E RfG)
• Requirements based on ENTSO-E RfG, estimated by the end of 2018
Petri Parviainen Fingrid, 18.3.2015
Agreements
SIgned memo or Letter of Intent:
• The required environmental studies of the project have been started
• The municipal planning process has been started or the planning requirement
resolution has been decided for the power plant
• The Letter of intent is non-binding.
Connection Argeement:
• The municipal planning or the planning requirement resolution of the WPP is
legally binding
• The customer shall submit plans of physical connection. If there is a need for
a connection line of the WPP, an application for redemption has been filed to
authorities
• Connection fee has to be paid, when signing the agreement, at once or in two
stages as follows:
– 15 % shall be paid at latest 14 days after signing the contract
– The rest of the fee at latest 6 months after signing the contract
• Agreement is valid after it has been signed and connection fees are fully paid.
• Customer has to build and commission the high voltage connection within 24
months from signing the agreement
• If customer fails to complete agreed payments or to complete the connection,
the agreement expires. All fees are non-refundable.
Petri Parviainen Fingrid, 18.3.2015
17
Connection fees in 2014
Connection to a substation in the 400 kV grid:
€2.0 million
Connection to a substation in the 220 kV grid:
€1.2 million
Connection to the 110 kV grid:
 radial line connection (up to 25 MVA)
€0.5 million
 present substation
€0.6 million
 new substation by a customer request, the customer pays the
total building costs *)
The fees are adjusted annually based on the actual construction costs of the transmission grid
The Connection Fee covers the operation and maintenance fees as well as grid modernisations
concerning the connection
*) If new connections are built to the substation in question for other customer or Fingrid during the
first 10 years from the commissioning of the substation, Fingrid will compensate to the first
customer the original construction costs deducted with current connection fee
Petri Parviainen Fingrid, 18.3.2015
Transmission Grid Pricing 2014
Output from
the main grid
Input into
the main grid
Production
Distribution
network
Input into
the main grid
Consumption
Production
Output from the main grid
Consumption
= Main Grid
connection point
= Distribution
connection point
Unit prices €/MWh
2014
Consumption fee, winter period
Consumption fee, other times
Output from the main grid
Input into the main grid
4,22
2,11
0,95
0,85
Petri Parviainen Fingrid, 18.3.2015
Fingrid - at your service
Grid connections
Fingrid Oyj, Kantaverkkopalvelut
Läkkisepäntie 21, 00101 HELSINKI
tel. 0303 95 5000
By e-mail
[email protected] or
[email protected]
Power plants
Petri Parviainen,
Helsinki area, Ostrobothnia,
Jarno Sederlund,
Eastern Finland, Lapland
Risto Ryynänen,
Uusimaa, South-East,
Mid-Finland
Niklas Löf,
Adviser, technical
coordinator and support
Petri Parviainen Fingrid, 18.3.2015
Antti Kuusela
Adviser, Power Plants
- Grid code for power plants
- Customer service
- Testing and modelling
- Commissioning tests
Powering Finland.