Connecting to The Transmission Grid in Finland 18.3.2015, Vaasa Wind Energy Petri Parviainen 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Main grid development plan 400 kV main grid 400 kV under construction main grid base line scenarios Fenno-Skan 2 DC connection to Sweden Forssa reserve power plant Yllikkälä - Huutokoski B 400 kV Hyvinkää - Hikiä 400 kV Estlink 2 DC connection to Estonia Ulvila - Kristinestad 400 kV Hikiä - Forssa 400+110 kV -yhteys Hirvisuo - Pyhänselkä 400 kV Lieto - Forssa 400+110 kV Hikiä - Orimattila 400 kV Reinforcement of Helsinki region network Reinforcement of north-south connections Keminmaa - Pyhänselkä 400 kV 3rd AC interconnection to Sweden Grid connection of nuclear and wind power Keminmaa Pyhänselkä Hirvisuo Tuovila Kristinestad 2013-2023: 400 kV power lines 1500 km, 110 kV power lines 1000 km EIA / Preliminary design Petäjävesi Detailed planning and permits Implementation Ulvila Forssa Hikiä Koria 90 % of new power lines will be constructed along or next to an existing right of way Huutokoski Lieto Yllikkälä Connecting to The Transmission Grid in Finland Contents 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Basics Substation connection 110 kV powerline connection Connection of the power plant Connection process Requirement for power plants Agreements Connection fees Transmission grid pricing Contact us Petri Parviainen Fingrid, 18.3.2015 Basics - connecting to the power transmission grid 1(3) The new connection shall be defined taking into account: • Power of required consumption and/or generation, connection requirements, and location of the connection • Impacts on the system security of the grid and on the environment • Disadvantage caused by increasing outages and disturbances on regional power generation and consumption • Technical implementation options and costs Technical solutions: • Voltage level (110, 220,400 kV) • Connection to a substation or transmission line • Protection and compatibility of electrical equipment • Energy measurement interfaces and data communications The connection must conform to the terms of connection • Fingrid Oyj's general terms of connection • Specifications for the operational performance of power plants Petri Parviainen Fingrid, 18.3.2015 Basics - connecting to the power transmission grid 2(3) Customers Substation Customers Substation B. Transmission line in main grid Fingrid`s substation Customers Substation 110 kV A. B. Fingrid`s substation TWO OPTIONS TO CONNECT A. Substation connection Petri Parviainen Fingrid, 18.3.2015 B. Powerline connection Basics - connecting to the power transmission grid 3(3) Petri Parviainen Fingrid, 18.3.2015 Substation connection A substation connection is a connection to the Fingrid`s 400 kV, 220 kV or 110 kV substation The connection shall be agreed in the Connection Agreement containing the fees, rights and obligations The customer is responsible for the construction of its own power line connection Fingrid is responsible for the necessary technical arrangements at its substation or, if necessary, Fingrid builds a new substation. Production and/or loads more than 25 MVA must be connected to a substation Petri Parviainen Fingrid, 18.3.2015 1 (1) 110 kV Powerline Connection A transmission line connection is a branch line or substation which is connected to a 110 kV transmission line The connection shall be agreed on Connection Agreement including the fees, rights and obligations The maximum allowed unit size of a transformer connected to a transmission line is 25 MVA Lots of regulation to take into account ... Petri Parviainen Fingrid, 18.3.2015 1 (2) Connection of Power Plant Power plants with a nominal power of more than 0.5 MVA connected to the Finnish power system must fulfil The Specifications for the Operational Performance of Power Plants (VJV), A power plant: – in excess of 250 MVA is connected to a 400 kV substation – less than 250 MVA can be connected to a 110 kV substation – the following can be connected to a 110 kV transmission line power plant of less than 5 MVA power plant of a maximum of 25 MVA when the short-circuit current fed by the power plant to the main grid is at the most 1.2 times the rated current of the power plant Customer is responsible for the disconnection relays of its power plant. These relays must: – trip the power plant during the high-speed automatic reclosing of the transmission line ( data communication access will be provided to the site by Fingrid and it is included in the connection fee) – contain at least frequency, zero voltage and undervoltage relays Real-time information required from the customer: – active power, reactive power and state information of switching devices – Update cycle of real-time exchange shall be at least 3 min – FEN network, protocols: elcom, ICCP, IEC 60870-5-104 Petri Parviainen Fingrid, 18.3.2015 1 (2) Connection process Customer Contact and basic information: • Company data • Power • Location • Preliminary timetable Planning, Plans must be delivered to Fingrid for review Connectivity Planning Construction, Timetable, Commissioning protocol and delivery to Fingrid Construction Delivery of final technical documentation to Fingrid (in 2 months after commissioning) Commissioning Grid Code Compliance Process Fingrid Examination of connection solutions alternatives of the connection Review of plans Implementation Additional instructions Letter of intent Connection Agreement Outage and switching planning Review by operation specialist Main grid contract Petri Parviainen Fingrid, 18.3.2015 Connection and operation Outages Commercial operation Energy accounting Finnish Grid Code(VJV2013) and Wind Power • General Requirements & Definitions – – • Scope and Power Classes VJV-reference Point • • • Technical Requirements – – – – – – Voltage and Frequency Operational Range FRT Requirement Reactive Power Capacity Voltage and Reactive Power Control Active Power and Frequency Control Power Quality Petri Parviainen Fingrid, 18.3.2015 Modelling Compliance testing Compliance Process and Data Delivery – – – • • Stages 1 to 4 Timeline of Compliance Process Data Exchange and Connection to 3rd Party Networks Derogations Specific Study Requirements Timeline of the Grid Code Compliance Process (VJV2013) Schedule requirement Stage 1 – As soon as possible but no later than after the selection of the supplier of the main components of the Power Generating Facility Stage 2 – No later than 3 months prior to the start of the Compliance Testing related to the Specifications Stage 3 – 9 months from the date on which the WPP supplied Active Power to the Power System for the first time Stage 4 – 12 months from the date on which the WPP supplied Active Power to the Power System for the first time 3 mo. 9 mo. 3 mo. Actions Stage 1 – Delivery of general data of the Power Generating Facility, determination of VJV Reference Point, and handling of potential derogations Stage 2 – Delivery of project-specific data of the Power Generating Facility and Compliance Testing Planning WPP supplies Active Power to the Power System for the first time Stage 3 – Accepted execution of Compliance Testing, and documentation of Compliance Testing Petri Parviainen Fingrid, 18.3.2015 Stage 4 – Acceptance of the compliance monitoring process of the Specifications Grid Code Development VJV2007 (effective before 12/2011) • Requirements specified for conventional generation, vague Nordel requirements for WPP Update and extension to VJV2007 (12/2011-10/2013) • Specified requirements for WPP, requirements set from 0.5 MW capacity upwards VJV2013 (effective 11/2013) • Requirements, process and responsibilities for all power plants specified in one document VJV2018 (after European Commission is in favor for ENTSO-E RfG) • Requirements based on ENTSO-E RfG, estimated by the end of 2018 Petri Parviainen Fingrid, 18.3.2015 Agreements SIgned memo or Letter of Intent: • The required environmental studies of the project have been started • The municipal planning process has been started or the planning requirement resolution has been decided for the power plant • The Letter of intent is non-binding. Connection Argeement: • The municipal planning or the planning requirement resolution of the WPP is legally binding • The customer shall submit plans of physical connection. If there is a need for a connection line of the WPP, an application for redemption has been filed to authorities • Connection fee has to be paid, when signing the agreement, at once or in two stages as follows: – 15 % shall be paid at latest 14 days after signing the contract – The rest of the fee at latest 6 months after signing the contract • Agreement is valid after it has been signed and connection fees are fully paid. • Customer has to build and commission the high voltage connection within 24 months from signing the agreement • If customer fails to complete agreed payments or to complete the connection, the agreement expires. All fees are non-refundable. Petri Parviainen Fingrid, 18.3.2015 17 Connection fees in 2014 Connection to a substation in the 400 kV grid: €2.0 million Connection to a substation in the 220 kV grid: €1.2 million Connection to the 110 kV grid: radial line connection (up to 25 MVA) €0.5 million present substation €0.6 million new substation by a customer request, the customer pays the total building costs *) The fees are adjusted annually based on the actual construction costs of the transmission grid The Connection Fee covers the operation and maintenance fees as well as grid modernisations concerning the connection *) If new connections are built to the substation in question for other customer or Fingrid during the first 10 years from the commissioning of the substation, Fingrid will compensate to the first customer the original construction costs deducted with current connection fee Petri Parviainen Fingrid, 18.3.2015 Transmission Grid Pricing 2014 Output from the main grid Input into the main grid Production Distribution network Input into the main grid Consumption Production Output from the main grid Consumption = Main Grid connection point = Distribution connection point Unit prices €/MWh 2014 Consumption fee, winter period Consumption fee, other times Output from the main grid Input into the main grid 4,22 2,11 0,95 0,85 Petri Parviainen Fingrid, 18.3.2015 Fingrid - at your service Grid connections Fingrid Oyj, Kantaverkkopalvelut Läkkisepäntie 21, 00101 HELSINKI tel. 0303 95 5000 By e-mail [email protected] or [email protected] Power plants Petri Parviainen, Helsinki area, Ostrobothnia, Jarno Sederlund, Eastern Finland, Lapland Risto Ryynänen, Uusimaa, South-East, Mid-Finland Niklas Löf, Adviser, technical coordinator and support Petri Parviainen Fingrid, 18.3.2015 Antti Kuusela Adviser, Power Plants - Grid code for power plants - Customer service - Testing and modelling - Commissioning tests Powering Finland.
© Copyright 2024