Safe & Sound An HNTB Publication Number 94 — 2010 A look at Missouri’s innovative design-build bridge program Florida is on track to realize its vision for a high-speed rail system by 2015 Innovative lift retrofits 75-year-old Huey P. Long Bridge with widening truss panels Nation’s first system of managed lanes works to preserve mobility in Atlanta HNTB is a professional firm of engineers, architects and planners providing planning, design, management and consulting services. hntb.com OPENING PERSPECTIVE Ken Graham Chief Executive Officer HNTB Infrastructure If there is one need as great as establishing a sustainable surface transportation funding source, it is the need for innovative solutions to help agencies cope until such funding comes through. The use of alternative delivery methods is one of those solutions, offering organizations a wide range of options for bidding, contracting, financing and designing large infrastructure projects. Matching projects with the most efficient and effective method of delivery is critical to success, and many organizations are turning to design-build — one of the fastest, most creative ways to deliver large, complex projects today: •Thirty states have authorized design-build for transportation procurement. •This year, its use in U.S. non-residential construction is expected to equal traditional design-bid-build use and, in the coming years, surpass it. •By overlapping the design, permit and construction phases, design-build can shorten timelines by one-third and reduce costs by 6 to 10 percent. Groundbreaking projects, such as the Missouri Department of Transportation’s Safe & Sound Bridge Improvement Program, are shining examples of design-build’s effectiveness. In just five years, MoDOT will have rebuilt 554 of its worst bridges in the nation’s first design-build system improvement project. design-build project delivery is one of the fastest, most creative ways to deliver large, complex projects today. As Safe & Sound’s design engineer, HNTB developed universal design standards for the massive project, rather than designing each span individually. In addition, a mass production strategy was implemented, dividing the design process into three phases and assigning a team to each phase. Each team performed the same work repeatedly, creating efficiencies and speed. Using the design-build model, MoDOT will reduce the program’s price tag by millions of dollars and minimize public inconvenience by limiting bridge closures to 45 days. Today’s transportation agencies must be ultra-efficient in their operations, stretching their dollars further than ever before. Alternative methods of delivery, including design-build, offer need-it-now solutions that can help agencies accelerate project delivery, produce sweeping, statewide improvements while saving time, money and resources in the process. The HNTB Companies (800) 693-HNTB (4682) HNTB Offices Arlington, VA Atlanta, GA Austin, TX Baton Rouge, LA Biloxi, MS Boston, MA Brownsville, TX Charleston, WV Charlotte, NC Chelmsford, MA Chicago, IL Cincinnati, OH Cleveland, OH Columbus, OH Dallas, TX Denver, CO Detroit, MI Downers Grove, IL El Paso, TX Hagatña, Guam Harrisburg, PA Hartford, CT Houston, TX Indianapolis, IN Jacksonville, FL Kansas City, MO Lake Mary, FL Lansing, MI Los Angeles, CA Louisville, KY Madison, WI Miami, FL Milwaukee, WI Minneapolis, MN New Orleans, LA New York, NY Newark, NJ Oakland, CA Omaha, NE Orange County, CA Overland Park, KS Philadelphia, PA Portland, ME Portland, OR Raleigh, NC Sacramento, CA Salt Lake City, UT San Antonio, TX San Diego, CA San Francisco, CA San Jose, CA Seattle, WA St. Louis, MO Tampa, FL Wayne, NJ DESIGNER is an HNTB publication and is published by the Corporate Communications and Brand Stewardship Department of the HNTB Companies, P.O. Box 412197, Kansas City, MO 64141. Patricia Mosher, vice president [email protected] Susan Rhode, editor [email protected] To change your address or be added or removed from the Designer mailing list, send your request to [email protected]. XX% Cert no. XXX-XXX-XXXX We are proud to print this publication entirely on Forest Stewardship Council™-certified paper. FSC® certification ensures that the paper used for this publication contains fiber from well-managed and responsibly harvested forests that meet strict environmental and socioeconomic standards. E Recycled with 30% post-consumer waste. HNTB is an equal opportunity employer M/F/V/D. © 2010 HNTB Companies. All rights reserved. Reproduction in whole or in part without written permission is prohibited. Page 02 04 >>Contents 08 >>Safe & sound 04 The Missouri Department of Transportation is relying on an innovative standardization process and design-build delivery to replace 554 bridges throughout the state. >>Lane change 08 More than two years in the making, the Georgia Department of Transportation’s system of managed lanes provides a first-of-itskind solution to metro Atlanta’s mounting mobility challenges. >>A mighty lift 12 An innovative span-by-span erection method is used to widen New Orleans’ Huey P. Long Bridge, increasing traffic capacity and safety with minimal closures to car and rail traffic. 12 >>Moving at high speed 16 The first of 11 federally designated U.S. high-speed rail corridors could be operational in Florida by 2015. >>Room to fly 20 Redmond, Ore.’s, new, airline-friendly municipal airport proves that building green can reduce long-term maintenance costs without sacrificing quality. >>2010 ACEC awards 22 22 16 The Bob Kerrey Pedestrian Bridge in Omaha, Neb., was one of three HNTB projects honored in the American Council of Engineering Companies annual awards program. >>Our transportation bill of health 23 Our industry must work together now to develop a long-term, well-funded, sustainable transportation plan that will support our country’s needs in the future. On the Cover: The Missouri Department of Transportation is replacing more than 550 bridges statewide as part of the Safe & Sound Bridge Improvement Program, using design-build delivery and an innovative management approach to deliver projects with greater speed and efficiency. 20 HNTB DESIGNER Number 94 Page 03 A majority of the bridges slated for replacement in the Safe & Sound Bridge Improvement Program are on county roads in rural areas across Missouri. Design-build delivery allows the project team to design and construct new bridges with an average closure time of just 45 days, minimizing disruption to local traffic. Page 04 HNTB DESIGNER Number 94 Safe & Sound A mass replacement of Missouri’s deficient bridges fosters the nation’s first design-build system improvement project spokesman Kent Grisham. “Instead of 554 bid-build packages, Even in a so-called mega transportation project, designers and MoDOT could let the design-build project as one, allowing us to contractors have the luxury of working on a single site, albeit an start construction while design was in process and accelerating the immense one. When the Missouri Department of Transportation time from design to project delivery. The faster MoDOT can get the initiated its Safe & Sound Bridge Improvement Program, however, bridges rebuilt, the fewer dollars they’ll spend on maintenance and the 802 structures identified for rehabilitation or replacement were the less time people will spend in detours around construction.” dispersed in mostly rural locations in all 114 counties throughout MoDOT identified the remaining 248 bridges as needing only the state, creating a mega project comprised of far-flung, smaller rehabilitation and proceeded with a modified design-bid-build projects. Speed was a top priority and teamwork and innovative process grouping the projects by type, size and location to accelerate management would be critical to the program’s success. completion. These projects MoDOT announced the project were processed through regular in fall 2006, but when the economy Washington monthly lettings and more than faltered, the agency scrubbed its half of them have been completed. design-build-finance-maintain approach, which was deemed unaffordable. It re-launched the Standardizing Bridge Design-Build Project for speed program in September 2008, awarding a $487 million design-build To tackle the enormous project, Oregon contract in May 2009 for replacement HNTB and The LPA Group, 113 counties of 554 bridges to KTU Constructors, KTU’s design subcontractors, 147 feet average bridge length a joint venture of Kiewit Western (a planned to develop project 28 feet average bridge width subsidiary of Kiewit Corporation), standards in mid-2009, taking 66 years average bridge age Traylor Brothers and United the predominantly rural 207 cored slab bridges Contractors. bridges’ distinct designs and The design-build model not only standardizing them in 10-degree 31 spread core slab bridges reduced the project price, but also skew increments up to a 40-degree 193 box beam bridges allowed MoDOT to minimize skew, in five-foot increments, 66 spread box beam bridges public inconvenience by accelerating rather than designing each span 37 steel girder bridges construction and limiting bridge individually. 15 box culverts closures to just 45 days, on average. “Our intent was to develop the 5 flat slab bridges “Using a design-build approach, standardized designs as a design 600 standards sheets MoDOT is getting the project built build team and review them 45-day average bridge closure more quickly than a typical bidwith MoDOT as we went along,” build project would allow,” said KTU said Jim Peterson, HNTB design Safe & Sound By the numbers HNTB DESIGNER Number 94 “Using the design-build process for a system improvement project is highly innovative. The Additional Applicable Standards process, whereby competing teams were allowed during procurement to propose alternative design standards used with Federal Highway Administration approval in other states, gave us more design options that accommodate speed.” Ken Warbritton Safe & Sound project director Missouri Department of transportation >> Missouri Georgia Louisiana Page 05 Collaboration has been key to the program’s success — both in the management and design office and in the field. Team members were co-located in a single location to increase efficiency on all aspects of the program. Page 06 manager. “When it came time to size a bridge on a particular site, we planned to use the appropriate standards as needed for each of the bridges as we designed all the way through 2010.” However, when MoDOT asked KTU, which had committed to replacing all of the structures by Dec. 31, 2013, to have some “early start” bridges constructed in 2009, the accelerated pace necessitated a different approach: The KTU/HNTB/LPA team designed 12 independent, non-standardized bridges, four of which were built in 2009. From those early designs, the team used lessons learned to develop designs and standards that could be applied to a majority of the remaining bridges. “We tried to break each bridge into certain elements we could standardize,” Grisham said. “Through teamwork, we spent the first six months of the design process developing these standards. That process was innovative because it created a means for getting a project of this magnitude down to a manageable amount of work.” After the 12 initial designs were complete and standard development in full swing, the remaining 542 bridges were divided between the two designers. HNTB took responsibility for the program’s 37 steel bridges and 143 multiple-span concrete bridges. Included in HNTB’s work were the eight railroad bridges and 22 sites that required maintenance and traffic plans for either staged construction or crossovers. By the end of 2009, the design team had developed approximately 600 standards sheets that specified length, skew, beam type, strand patterns and non-dimensional substructure, among other benchmarks. Companion variable tables allowed plans to use nondimensional details and gave the contractors all the information they needed to construct the bridge on a specific site. Size, plan, repeat “Structure type and construction methods were determined in the proposal phase,” said Ken Warbritton, MoDOT’s Safe & Sound project director. “But we have stressed speed in construction, which calls for shipping prefabricated materials to the sites and staging of precast, prestressed members. The design work had to be completed quickly so the contractors would know what materials were needed at each site and could fabricate them ahead of time.” Originally, HNTB envisioned distributing work on the 184 bridges among three squads, with each team managing cradle-to-grave design for its assigned bridges. As the company evaluated options, however, it was clear this traditional project approach wouldn’t support the aggressive design schedule. To drive the schedule, the project team divided the design process into three phases, assigning a team to each. At any given point, HNTB had eight to 10 bridges in the constructability review design phase, 10 in type, size and location design phase and 10 in the final design phase. Focusing each team on repeating the same kind of work many times over created efficiencies that Peterson said allowed work to “fly out the door.” “The Safe & Sound program presents challenges because of the geographic distance it covers and the factors that are unique to each site,” Peterson said. “To manage it rapidly, efficiently and effectively, we had to change our ‘single huge site’ mentality and think about this as a small project we had to produce 184 times. “From the time we started working on each bridge, our internal schedule took 39 work days to signed-and-sealed plans. These are the same types of bridges we’d normally design in three to four months, and even that is quick. By focusing the teams on completing the same processes repeatedly, regardless of the site, we were able to cut the design time in half.” HNTB DESIGNER Number 94 By mid-2010, HNTB had produced nearly 170 signed-andsealed plans and remaining bridges were ready to turn over to the standards application team. “We’ve come to believe we can gain a number of efficiencies in mass production, and the owner should see those efficiencies in the bid price,” Peterson said. All eyes on Missouri As the first program of its kind in the United States, and because of its early success, Safe & Sound already serves as a model for alternative project delivery. Other states are watching the program’s outcomes and considering its merits. “Using the design-build process for a system improvement project is highly innovative,” Warbritton said. “The Additional Applicable Standards process, whereby competing teams were allowed during procurement to propose alternative design standards used with Federal Highway Administration approval in other states, gave us more design options that accommodate speed.” “Seeing MoDOT go forward with its design-build program is showing other states that it’s possible to do statewide logistics projects, rather than just focusing on projects in a specific geographic locale,” Grisham said. n CONTACT: JIM PETERSON, HNTB Design Manager (414) 410-6768 n [email protected] HNTB DESIGNER Number 94 Side-by-side management Managing the sprawling, fast-paced Safe & Sound program presented the potential for logistical chaos. “We literally had to worry about what we had to do in any given hour to keep the project on schedule,” said Jim Peterson, HNTB design manager. “The only way to make this project successful was hyper-teamwork, and that called for nearly 100 percent co-location.” HNTB quickly moved as much of its assigned engineering team as possible to the KTU office in Lee’s Summit, Mo., maintaining a staff of 40 in the project office at the project’s peak. “Co-locating staff in our office meant nearly hourly communication between designers and constructors and no wasted effort, said KTU spokesman Kent Grisham. “The ability to collaborate on an hourly basis is important in a design-build project, and helped us work smarter and more efficiently from both a design and construction standpoint.” n Page 07 Lane Change Signaling a shift in how it responds to congestion, the Georgia Department of Transportation is the first state organization to implement not one managed lane, but a system of managed lanes — 310 centerline miles of urban interstate at full build-out. The pioneering plan, more than two years in the making, promises to preserve metro Atlanta’s mobility in the face of skyrocketing population and employment growth. Page 08 HNTB DESIGNER Number 94 575 75 400 285 78 Washington Building general-purpose lanes for congestion relief on urban freeways is fast becoming passé. Intended to add new capacity, these lanes fill up as they meet latent demand, becoming nothing more than billion-dollar temporary fixes. With this traditional approach now cost-prohibitive and Oregon unsustainable, departments of transportation are considering other options, and many are coming to the same conclusion: If we can’t build our way out of congestion, we’ll manage our way out. Many cities are looking to managed lanes as the solution. At last count, 23 U.S. metropolitan areas now are operating or implementing managed lanes, considering managed lane proposals or studying their feasibility. 575 985 20 85 75 20 400 316 675 285 20 Missouri Michael Malone /Sun Sentinel BIRTHING A TREND Calling managed lanes the “wave of the future,” Robert Poole, director of transportation policy for the Reason Foundation, explains the growing attraction. “Managed lanes recognize that people have very different values of time, and that they often are willing to pay to get someplace quickly and reliably,” he said. “And, unlike general-purpose lanes, they are sustainable. Variable pricing keeps them free-flowing.” Further, managed lanes have a built-in funding source, so they more cost-effectively deliver additional capacity while supporting the initial capital expenditure and long-term operating and maintenance costs, according to Cherian George, head of the Americas/managing director for Fitch Ratings Global Infrastructure and Project Finance team. “Depending on the way in which the asset is delivered, a managed lane may have excess revenue available for other purposes, including managing and investing in the surrounding general-purpose lanes,” he said. Managed lanes began much like high-occupancy lanes did — as isolated spot projects. But, just as HOV lanes have evolved to more effective HOV systems, so are managed lanes evolving into networks. “We are witnessing the birth of a trend,” said Jack Finn, chair HNTB toll services. Finn is referring to 2G — the second generation of managed lanes. The first generation, demonstration projects funded by the Federal Highway Administration’s Value Pricing Program, generally involved low-cost and/or conversion projects. “2G is more systematic. It is typically new capacity focused on partnerships, such as public-private partnerships, that leverage limited state and local dollars,” Finn said. “The industry is HNTB DESIGNER Number 94 85 78 20 Mapping Atlanta’s 75 Managed Lanes Several types of managed lanes are being used to ensure mobility in the growing metropolitan Atlanta. 675 Georgia Louisiana 85 75 Interchanges discovering that each managed lane becomes significantly more effective when it connects with other managed lanes, giving motorists the ability not only to go from point A to point B, but also to points C, D and E.” According to Poole, plans for managed lane systems have been accepted and approved in some of the country’s most congested cities, including Houston, Dallas, Seattle and San Diego. 1 Bi-Directional Managed Lane 2 Bi-Directional Managed Lanes 1 Reversible Managed Lane 2 Reversible Managed Lanes Elevated – Outside Interchanges LEADING THE PACK 1 Bi-Directional Managed Lane 2 Bi-DirectionalD.C., Managed Two corridors in Washington, theLanes Capital Beltway and 1 Reversible Managed Lane I-95/I-395, will feature initial managed lane systems, while San 2 Reversible Managed Lanes Elevated Outside Francisco is considering an– expansive network of managed lanes throughout the Bay Area. Leading the pack, however, is the Georgia Department of Transportation. It now is implementing one of the nation’s first comprehensive systemwide evaluations of urban-area managed lanes. The Atlanta Regional Managed Lane System Plan, approved by Georgia’s transportation board last December, will preserve the region’s free-flow mobility during peak traffic hours just as traffic >> Page 09 threatens to strangle the state’s economic competitiveness and quality of life. “Transportation is no longer an entitlement,” said Todd Long, director of planning for GDOT. “Rather, it’s a commodity for which the user receives value in return for a fee. Implementing a system of managed lanes — where some motorists pay a fee to use the facility — would create the means to meet motorists’ demand for reliable travel time, every time.” Although there is no official target date for full system build-out, when the MLSP is completed, GDOT will have 310 centerline miles of freeway managed lanes. Award-Winning Plan The Georgia Department of Transportation received the 2010 Transportation Planning Excellence Award for its Atlanta Regional Managed Lane System Plan. The Transportation Planning Excellence Awards is a biennial program developed by the Federal Highway Administration and the Federal Transit Administration to recognize outstanding initiatives across the country that develop, plan and implement innovative transportation planning practices. The American Planning Association co-sponsors the award. FACT: The Managed Lane System Plan will save the Atlanta metro region $47 billion in reduced traffic delay over 35 years. Page 10 TAKING THE POLICY WHEEL In 2003, Georgia’s state lawmakers approved groundbreaking public-private initiatives legislation, which are now referred to as public-private partnerships or P3s. Subsequently, GDOT began receiving unsolicited proposals from the private sector, each attempting to prescribe policy for Atlanta freeways. “Those proposals, which suggested everything from high-occupancy toll lanes and truck-only lanes to express toll lanes, put GDOT at a disadvantage because it did not have a strong negotiating position,” said Tim Heilmeier, HNTB project director of GDOT’s P3 program. The department responded by conducting a comprehensive investigation of managed lane investments. HNTB, GDOT’s P3 technical adviser and program manager, assisted in defining the $16 billion program, writing the master plan’s scope and working with GDOT’s office of planning to execute it. “The Georgia Department of Transportation is very pleased with the services we have received from HNTB as technical advisers for our public-private partnership program, which includes our Managed Lane System Plan,” said GDOT Commissioner Vance Smith. “Having the MLSP puts GDOT in a proactive position,” Long said. “It sends a great message to the marketplace: This is our plan, and this is what we are going to do. People can organize around that.” KEEPING IT REAL In the works for more than two years, the MLSP is an exhaustive, pragmatic look at policy, planning, finance, delivery and implementation options. HNTB used traffic and revenue studies to keep the ambitious plan grounded in fiscal reality. “Based on a variety of scenarios that included revenue bonds, Transportation Infrastructure Finance and Innovation Act loans and concessionaires’ equity, we used proprietary HNTB tools to determine present-day dollar cumulative revenue streams and to calculate how much in present-day monies a 50-year revenue stream would generate,” Heilmeier said. Before, a DOT might have determined a project’s cost and how much a given policy would collect in present-day dollars, but it would not have considered such things as debt service coverage ratios or mezzanine debt structures that, once added to the equation, often create funding gaps. While the MLSP’s policy framework does not optimize finances, it does take into account the implementation side of the house, which, Managed Lane System Benefits Improves mobility Increases average travel speeds Decreases delay Increases access to major activity centers Increases system efficiency Maximizes throughput Decreases travel time variations Improves transit on-time performance Minimizes environmental impacts Improves air quality/decreases pollutants Reduces impact to the built environment Provides a financially feasible system Leverages and optimizes public cash outflows Incorporates a market-driven approach Creates a flexible infrastructure for varying lane management Accommodates future lane management possibilities until now, has never been done in a systemwide planning study, according to Andrew Smith, HNTB project manager for the MLSP. “We were not optimizing a minimum public sector contribution or targeting a certain dollar value,” he said. “Our goal was to attempt to balance and optimize financeable costs and public sector contributions with the overall general reduction in travel costs to citizens.” The result is a comprehensive roadmap for GDOT that establishes: • Infrastructure and system development in 20 corridors • The architecture and recommended schedule for a complete system build-out • Funding requirements and limitations • Appropriate policies • The network’s anticipated cost and revenue potential • Access points • Each managed lane’s capacity limits High-occupancy toll lanes emerged as the MLSP’s recommended eligibility policy. Under the desired HOT3+ policy, high-occupancy vehicles with three or more occupants could travel the managed lanes at no charge, along with motorcycles, alternative fuel vehicles and emergency vehicles. Vehicles with one or two occupants would access the managed lanes by paying a toll. However, system level policies will be revisited, and potentially revised, on a corridor-by-corridor basis as projects evolve and implementation realities are understood. FILLING THE P3 PIPELINE “The MLSP serves as a blueprint for GDOT’s managed lane projects, but it’s also driving GDOT’s P3 procurement pipeline,” Heilmeier said. HNTB DESIGNER Number 94 GDOT plans to leverage those P3s to accelerate construction of priority corridors. “It’s a challenging time for DOTs as resources are extremely limited and maintaining existing systems often takes priority over expansion,” Heilmeier said. “But, when they put a P3 project in place, for 50 years someone else has to take care of it — and assume most of the risk. That kind of transaction is appealing. And, if a DOT can deliver a billion-dollar project for, say, only $300 million of its own money, that really resonates these days.” Of the managed lane project’s $16 billion price tag, GDOT expects the private sector to contribute $9 billion in toll revenue bonding and equity. The rest will come from traditional federal and state programs. MANAGED LANES ACROSS AMERICA SR 167 HOT Lane Seattle I-15 HOT Lanes Salt Lake City Puget Sound Region I-394 HOT Lanes Minneapolis Seattle Portland Minneapolis PAYING DIVIDENDS GDOT’s unprecedented investment in the MLSP is paying dividends. By 2016, the department plans to have three managed lane facilities in operation: the Interstate 85 HOV-to-HOT Lanes Project, the Interstate 75 Northwest Corridor Project and the I-75 project in Henry County. Funded through the U.S. Department of Transportation’s Congestion Reduction Demonstration Program, the I-85 project converts 15 miles of existing high-occupancy vehicle lanes to HOT lanes. To keep the lanes free-flowing and provide reliable travel time, tolls will vary dynamically based on demand or the number of vehicles using the HOT lanes. The revamped lanes are scheduled to open in summer 2011. The Northwest Corridor Project will involve the addition of reversible managed lanes along I-75 and I-575. It will include two lanes on the west side of the existing general purpose lanes along I-75, between I-285 and I-575. The managed lanes will consist of a mix of roadway at-grade, on walls and as an elevated highway. In addition, one managed lane will be added along I-75 between I-575 and Hickory Grove Road and along I-575 to Sixes Road. These lanes will be at-grade and located in the median along the inside of the existing general purpose lanes. GDOT hopes to open the facility to traffic in 2016. MAINTAINING A COMPETITIVE EDGE To maintain its state’s competitiveness, GDOT must enhance its transportation networks with strategic, sustainable assets. “Through the MLSP, HNTB has shown us how to proactively exercise our management, delivery and financial toolboxes to provide congestion relief and make our state economically competitive,” Long said. “The impact of GDOT’s MLSP is not only a roadmap for metro Atlanta but a template that can be applied to any congested urban area in the United States.” n New York City Sacramento Alameda County Santa Clara County Denver Chicago Washington D. C. Salt Lake City San Joaquin Virginia Los Angeles Research Triangle Park Charlotte San Bernardino County Orange County Riverside County San Diego Dallas Austin I-15 Managed Lanes San Diego State Route 91 Express Lanes Orange County LEGEND Managed Lanes in Operation Atlanta Houston Orlando San Antonio Ft. Myers I-25 HOT Lanes Denver Katy & Northwest Freeway Managed Lanes Houston Miami I-95 Express Toll Lanes Miami Managed Lanes Being Implemented Proposals Being Considered Feasibility Studies “I am very excited about the P3 program in Georgia and the benefit the program will bring to our citizens. During these economic times, we must look for methods to deliver the infrastructure that Georgia needs as a growing state. By forming a partnership with private industry, Georgia will receive a substantial return on our investment in the form of managed lanes, which will provide congestion relief and a more reliable trip time for our citizens.” Vance Smith Commissioner Georgia Department of Transportation CONTACT: ANDREW C. SMITH, HNTB Project Manager (404) 946-5708 n [email protected] HNTB DESIGNER Number 94 Page 11 A vertical-lateral move sets two massive truss panels into place in the first of three lifts to widen the existing Huey P. Long Bridge. The unconventional span-by-span erection method has eliminated the need for falsework, avoided time-consuming secondary member fit-up, and minimized impact to traffic both on and below the 75-year-old structure. >> Page 12 A Might HNTB DESIGNER Number 94 hty Lift HNTB DESIGNER Number 94 Page 13 T he phrase “lateral movement” often carries a negative connotation. A lateral movement in football can be a sign of desperation. A lateral career move means no advancement — and no pay increase. But, a lateral movement in bridge work, such as the one that occurred this past June during the Huey P. Long Bridge Widening Project, is something to be celebrated. Located in Louisiana’s Jefferson Parish, the 1935 bridge is one of three primary Mississippi River crossings in the Greater New Orleans area. It is a three-span cantilever steel truss with an adjacent 530-foot simple-span through truss. Lifting the new truss into place was a swift but tedious process. The vertical lift took approximately 8 hours, and closures to car and rail traffic were limited to just the weekend for the lift. Teamwork and collaboration were key to the project’s success. Page 14 The New Orleans Public Belt Railroad has ownership of the bridge, which carries two railroad tracks and four 9-foot, shoulderless highway lanes. When the project is completed, the Louisiana Department of Transportation and Development will own the land under the new bridge approaches and will maintain the highway portion. After the superstructure is widened, it will feature three 11-foot travel lanes in each direction, 2-foot inside shoulders and 8-foot outside shoulders — providing a safer, more reliable Mississippi River crossing. What makes the project unique is how the bridge is being widened. “We’re adding a truss panel to each side of an existing truss, creating a triple-barrell truss bridge,” said Steve Underwood, project manager for MTI, the joint venture of Massman Construction Co., Traylor Bros. Inc. and IHI Inc. The team is serving as contractor for phase three. Typically, if a bridge needed to be widened, sections of it would be replaced until the entire bridge was complete. Or, more commonly, a new bridge would be erected next to the existing one. In the case of the Huey P. Long Bridge, neither option was realistic. The railroads would not agree to close the existing bridge for an extended period, and purchasing right-of-way for a new bridge was cost prohibitive. PLANNING THE LIFT As construction engineer for phases three and four of the project, part of HNTB’s role was to figure out how to get the new truss panels retrofitted onto the bridge. HNTB team members Steve Hague, Hans Hutton and John Brestin took one look at the superstructure and knew the trusses needed to be lifted into place rather than using the traditional stick-build method. “None of us knew exactly how we would do it, but we knew lifting it was the answer,” Brestin said. To execute the successful lift, three obstacles had to be overcome: 1.It would have to work around the existing superstructure’s two primary truss panels and bracing. 2.Secondary members couldn’t be used to brace the truss panels during the lift because they would be in the way. 3.Once in place, the new widening panels would have to rest at the same elevation as the existing panels. HNTB and MTI explored countless erection alternatives before Hutton’s concept of a u-shaped stabilizing frame finally stuck. “In essence, it’s a really big through-plate girder,” said Hutton, HNTB senior project engineer. Lifting the preassembled truss panels from their bottom corners would have put the top truss chords in compression, causing them to buckle. Hutton’s concept addressed the challenge of bracing the top chord and relocated the brace to the bottom of the frame, leaving the top open to accommodate the existing superstructure. In effect, the stability frame would hang from the widening panels themselves while supplying the necessary support. “There was skepticism at first,” Hutton said, “but as we talked, MTI presented ideas that evolved the concept, and it became a team effort.” After two independent models verified the innovative concept, MTI went to work bringing it to life on barge platforms assembled just downstream from the bridge. The stabilizing frame consists of two vertical space frames each erected on opposing main floor beam sleeves. Hillman rollers, mounted to all four interior surfaces of the sleeve assembly, allow the space frames and attached truss panels to slide laterally. “Figuring out how to move the panels horizontally while keeping them stable is what we scratched our heads about,” Brestin said, “but the team didn’t give up until we found the best solution.” “Being able to lift such large and relatively slender loads and providing the appropriate bracing and detailing to make it work was a great effort on behalf of the construction engineer,” said Tim Todd, resident engineer for Louisiana TIMED Managers, the construction management team that is a joint venture of PB Americas Inc., GEC Inc. and the LPA Group Inc. The client is the Louisiana Department of Transportation and Development. HNTB DESIGNER Number 94 “Some people questioned the concept of widening an existing truss bridge by adding two more trusses without altering the foundation. But, we had a strong team. And, that team said it could be done. Here is the proof. There’s a way to engineer just about anything if you really put your mind to it.” Brian Buckel Chief Construction Engineer LADOTD The stability frame will be reused for the remaining two lifts, even though the truss panels in each of those spans are different. STICKING THE LANDING While MTI was constructing the stabilizing frame, teams from Modjeski and Masters, the engineer of record, and Interstate Steel Corporation designed and fabricated the widening trusses. The lift process began on Friday, June 18, when the massive barge assembly, carrying its payload of truss panels and stabilizing unit, was floated into position under the bridge. By Saturday, strand jacks, supported on the top of the widening pier trusses, picked up the system by all four corners and raised it until each side cleared two 150-foot-tall piers. From there, floor beams fitted with brackets captured the bottom chord of the existing trusses and held the new panels in position. The vertical lift took approximately eight hours. Once the floor beams were steady, six synchronized horizontal jacks moved each frame and truss panel 13 feet inward until the panels hovered about six inches above their respective bearings. According to HNTB, such a lateral movement never had been done before. “Lifting two independent trusses connected to a stabilizing frame and moving them laterally is definitely a first,” Brestin said. Todd agreed. “I have seen entire bridges lifted but nothing of this size and retrofit while keeping the structure active to railroad traffic,” he said. By early Sunday morning, the widening truss panels were resting firmly on their bearings. Crews attached temporary horn beams from the existing trusses to the new panels, stabilizing them from the top chords. Then, crews braced the bottom chords against the existing trusses. Once these members were in place, MTI disconnected the stabilizing frame, and four strand jacks lowered it onto an awaiting barge. “Everyone would think the coolest aspect of this project, so far, would be the first big lift, and it was certainly impressive, but watching everyone work together to get to that point, was, in my opinion, even better,” Underwood said. “The teamwork on this job has been extraordinary.” MONITORING THE LIFT To detect any movement of the truss panels as they were lifted, MTI worked with Applied Geomechanics Inc. to develop a first-ofits-kind lift monitoring system. A network of lasers and tilt meters sent information to an AGI software program, which displayed on a computer screen the widening panels’ exact geometry. HNTB DESIGNER Number 94 Huey P. Long Bridge Project Schedule Phase Project Timing Phase I Main support widening (piers) April 2006 – May 2009 Phase II Railroad modifications October 2006 – June 2008 Phase III Main bridge widening (truss) Began early 2008 Phase IV New approaches construction Began June 2008 “We could tell the altitude of the trusses, longitudinally and laterally, in real time,” Brestin said. “That way, we could adjust any of the four jacks before the next stroke.” Underwood said the team plans to use the monitoring system during the remaining two lifts, including the suspension span scheduled for November and the through truss section in spring 2011. ASSESSING THE BENEFITS The span-by-span erection method produced numerous benefits over the traditional stick-build method. Using the traditional method would have offset the widening truss panels by as much as 11 inches from their final locations, which meant fit-up of the truss’ secondary members would have been laborious. With the span-by-span erection, fit-up wasn’t needed. The span-by-span method eliminated the need for all falsework, protective barriers and the risk of oceangoing vessels hitting them. In addition, building the trusses on barge platforms next to the shore was much easier and safer than if crews were in the middle of the Mississippi River, dodging ships and dangling from angle wings. What’s more, there has been minimal impact to vehicular traffic and no impact to railroad traffic. With the span-by-span method, each of the three lifts requires a maximum of 54 hours of river closure instead of the hundreds of six-hour closures the stick-build method would have required. The widened bridge will give residents a more efficient hurricane evacuation route, and it will encourage development on the river’s west bank, which was difficult to access before the project. Estimates project the wider bridge will nearly double its current 50,000 daily travel count. The bridge is scheduled for completion in 2013. n CONTACT: John Brestin, HNTB Project Manager (816) 527-2608 n [email protected] Page 15 Moving at High Speed Page 16 HNTB DESIGNER Number 94 Florida is moving closer to realizing its vision of a high-speed rail system. Having secured a Final Environmental Impact Statement, a Record of Decision and a $1.25 billion federal commitment for high-speed rail earlier this year, the Sunshine State plans to have its first express high-speed trains in operation by 2015. Floridians could see their long-time vision of a high-speed rail system materialize by 2015. That is when phase one of the state’s two-phased high-speed rail program could be whisking passengers between Tampa and Orlando at speeds of at least 168 mph. The 84-mile trip — 90 minutes by car — would take well under an hour. “Florida could be home to the first express high-speed rail trains operating in the United States,” said Kevin Thibault, executive director of the Florida Rail Enterprise, the entity responsible for implementing the state’s vision. The full Tampa-Orlando-Miami system is one of 11 federally designated high-speed rail corridors in the country. Most U.S. high-speed rail projects will be incremental improvements on existing freight railroad track, not true high-speed operations. California, the only other state currently planning to build dedicated, high-speed rail lines, anticipates revenue operation sometime after 2018. But, as Peter Gertler, chairman of HNTB’s high-speed rail services, points out: This is not a competition between two programs. Success breeds success. “The sooner there is a success somewhere, be it Florida or California, the more projects you’ll see popping up all over the country. That means everybody wins,” Gertler said. STIMULUS MONEY VALIDATES PLAN Talk of a high-speed rail system in Florida began in the 1970s and blossomed into a statewide vision in the 1980s. However, earlier initiatives stalled because no federal monies were available to help pay for them. Then came President Obama’s announcement of the 2009 Strategic Vision for High-Speed Rail in America and the American Recovery and Reinvestment Act, which awarded Florida $1.25 billion for the Tampa-Orlando segment, and promised more. “The grant, which required no state matching funds, demonstrated the Federal Railroad Administration’s confidence in Florida’s plans,” said Eugene Skoropowski, HNTB director of rail and transit services. “It is by far the largest share of a project to be allocated.” The stimulus money represents about half of phase one’s anticipated $2.6 billion construction cost. The remaining 50 percent likely will HNTB DESIGNER Number 94 Tallahassee Pensacola Pensacola Tallahassee Jacksonville Gainesville Florida’s High-Speed Rail Plan Ocala This map shows routes planned for high-speed rail service throughout Florida. Officials hope phase one will be complete by 2015, completing a vision Floridians have been working toward for nearly 40 years. Daytona Beach Orlando Tampa Disney Airport Cocoa/Port Canaveral Lakeland Tamp St. Petersburg Bradenton FortSt. Pierce Petersburg Sarasota come from additional federal and public funds. One of those is a new revenue stream from the state transportation trust fund, created to help Florida Fort Myers leverage rail funds in much the same way it leverages highway funds. Naples “When the federal government awarded the $1.25 billion to Florida, the project submission was for the full Tampa-OrlandoMiami system,” Thibault said. “As such, expect there will be a Phasewe 1 — Tampa to Orlando 2 Option 1 continuing partnership between the Phase federal government and the state I-95: Orlando to Miami through the balance of this project.” Phase 2 Option 2 Bradenton Sarasota West Palm Beach Fort Lauderdale Miami Turnpike: Orlando to Miami Proposed Routes MANAGING THE PROGRAMPossible Stations HNTB served as general engineering consultant to the Florida High-Speed Rail Authority from 2001 to 2004, a period during which the state was under a constitutional mandate to initiate the high-speed rail system. “We got a lot of work done in that timeframe, including advancement of environmental and procurement documents that positioned Florida very strongly when the program came back to life,” said Adrian Share, HNTB project director. >> Phase 1 — Tampa to Orlando Phase 2 Option 1 I-95: Orlando to Miami Phase 2 Option 2 Turnpike: Orlando to Miami Proposed Routes Possible Stations Page 17 Fort M “This project will help develop standards that may become the norm over time, similar to how highway standards developed. HNTB’s work in Florida will help shape what the future of U.S. high-speed rail will look like.” Eugene Skoropowski director of rail and transit services HNTB Corporation The program was put on hold in late 2004 when this same constitutional mandate was repealed. In early 2009, when the latest initiative began, HNTB still held a contract with the authority that was transferred to FDOT and used to assist with preparation of the ARRA application. In late 2009 the Florida Rail Act was passed, abolishing the authority and establishing the Florida Rail Enterprise. FDOT then selected HNTB as program management consultant. “HNTB has more than 10 years of experience serving as program manager on the Florida high-speed rail project and has done an excellent job in serving the department,” said Nazih Haddad, Economic Stimulus One 2010 study estimates Florida’s completed high-speed rail system could create more than 27,000 jobs and nearly $3 billion worth of new business annually in the Orlando area alone, with surrounding areas picking up $1.7 billion each year in economic activity. Construction of the Tampa-Orlando leg likely will produce approximately 5,000 jobs during the four-year construction period. Ongoing operations and maintenance will permanently employ 600 to 1,000 Floridians. ORLANDO 27 Orange County Convention Center Multi-Modal Station ORLANDO INTERNATIONAL AIRPORT 17 Orlando Airport Multi-Modal Station 192 75 19 41 Walt Disney Station 98 4 275 Kathleen Road Station* TAMPA USF/Polk Parkway Station* PA TAMPA IONAL INTERNATIONAL AIRPORT 4 75 275 Page 18 Downtown Tampa Multi-Modal Station 98 27 of these two sites will be * One the Lakeland/Polk County Station Florida Rail Enterprise chief operating officer. “HNTB is nationally recognized as a leader in high-speed rail planning and engineering.” Adding partners Deutsche Bahn of Germany, Prointec of Spain and Interfleet Technology of the United Kingdom, HNTB has assembled a world-class team, bringing nearly 40 years of highspeed rail experience to Florida. As program management consultant, HNTB and its partners will provide overall program support and oversight for planning, design, public outreach, vehicle and systems integration, operations, construction, project controls and procurement of all contracts. Another part of HNTB’s role is to be integrally involved in the development of procurement documents for what will be a complex and sophisticated public-private partnership concession agreement. These documents are being developed through a collaborative workshop effort that includes the project owner, legal and financial advisers. In addition, HNTB is completing 30 percent design of phase one — everything from track alignment to bridges and stations — by January 2011. The firm also will update phase one’s overall cost estimate for further budgetary evaluations with the Florida Rail Enterprise and the FRA. “The revised cost estimate, due in September, is intended to increase the FRA’s comfort level as to how much money is still needed to complete phase one,” Haddad said. ALIGNMENT TARGETS INTERSTATE MEDIAN The Tampa-Orlando corridor will be developed on new, dedicated track with about 70 miles of the system located in existing right-ofway of Interstate 4. Putting high-speed rail in an interstate median has never been done anywhere in the world. Florida won the ARRA grant money, in part, because it had a head start on phase one of its high-speed rail system. Despite major I-4 reconstruction over the years, FDOT had preserved the rightof-way envelope and invested hundreds of millions of dollars to prepare the median for rail installation. “With so much work already in place, the Tampa-Orlando segment was the obvious starting point,” Share said. “It is a relatively low-cost build that will give the state a quick win and momentum going into phase two.” In May 2010, the Tampa-Orlando corridor received the first Record of Decision in U.S. history for a high-speed rail express HNTB DESIGNER Number 94 project. The landmark approval allowed Florida to begin design, acquire additional land and begin construction. With the interstate median as the targeted alignment, part of completing 30 percent preliminary design means HNTB must develop the first-ever design criteria for U.S. high-speed rail and coordinate those criteria with the FRA and Federal Highway Administration. “This project will help develop standards that may become the norm over time, similar to how highway standards developed,” Skoropowski said. “HNTB’s work in Florida will help shape what the future of U.S. high-speed rail will look like.” PRIVATE SECTOR WILL PLAY MAJOR ROLE In 2011 the Florida Rail Enterprise is scheduled to ask private consortiums to submit bids and technical proposals to design, build, operate, maintain and finance phase one. “Florida has recent experience with large design-build-operatemaintain-finance agreements,” Gertler said. “They are comfortable with that business arrangement.” Greenfield developments, such as California’s and Florida’s highspeed rail programs, are attractive to private investors because they present more opportunity for innovation and creativity. Plus, revenue — and the potential to control it — is greater on exclusive track. The velocity of high-speed trains makes them incompatible with major freight operations, so dedicated high-speed passenger tracks make sense. “Having the private sector involved provides opportunities for risk-sharing and opens possibilities for additional revenues, such as those generated from potential transit-oriented development,” Haddad said. “They view the project as a bigger opportunity than just providing a transportation service.” The Florida Rail Enterprise expects to select a private vendor in 2011. Construction is slated for 2012. Based on a 2009 update, the cost of operating phase one will be approximately $164,000 per day with initial revenues slightly higher at $170,000 per day. “These conservative estimates demonstrate an immediate, positive return on investment,” Thibault said. “Given the very modest relative investment the state will have to make to construct the system, the return on investment will be a perpetual, positive funding stream.” WORK EXPANDS TOWARD MIAMI Florida is seeking $8 million in federal high-speed rail funds to accelerate the planning and environmental work on phase two of its system — the 220-mile Orlando-Miami corridor, which will reach speeds in excess of 186 mph. The Florida Rail Enterprise is considering two alignments for this corridor: along I-95 or via Florida’s Turnpike. Either way, ridership potential is huge. The Miami-Orlando connection is the state’s most heavily traveled corridor. It would link Florida’s largest population centers with 20 round trips a day, many extending to Tampa. Moreover, the route will be bookended by two major airports, each serving more than 30 million passengers annually. Banking on the corridor’s anticipated success, Florida already has invested $2 million in state funds and has begun work on the Orlando-Miami segment. “With each day, Florida’s vision for a high-speed rail system comes into focus clearer and sharper than the day before,” Thibault said. “High-speed rail in Florida is no longer a dream on paper. It’s a growing reality.” n Ideal Conditions Florida’s many compelling attributes for a high-speed rail system include: • A narrow geography with limited room for highway expansion • Ideal distances between major metro areas • A massive tourist base • Flat terrain, making the system more affordable to build • Increasing pressure to relieve airports • A need for additional hurricane evacuation routes • A population predicted to surpass New York as the third most populous state • A need to provide additional transportation without further encroaching on the environment CONTACT: Adrian Share, HNTB Project Director (407) 547-3009 n [email protected] INITIAL REVENUES FORECAST TO cover COSTS Opening year rider forecasts indicate that revenues will likely cover operational costs. The Tampa-Orlando corridor would offer an initial base of service with several round trips daily and proposed stations at Tampa, Lakeland/Polk County, Walt Disney World, the Orange County Convention Center and Orlando International Airport. One-way fares will be in the $30 range for the TampaOrlando leg and $15 from Orlando to the attraction areas. Discounts are anticipated for frequent users. HNTB DESIGNER Number 94 Page 19 Room to Fly Redmond Municipal Airport’s new, greener terminal keeps overhead and maintenance costs low and reduces airline fees. Washington Oregon Redmond Growing demand for air travel in central Oregon found Redmond Municipal Airport bursting at the seams with passengers. A 136,000-square-foot expansion increased capacity and allowed for larger aircraft. Page 20 Roberts Field-Redmond Municipal Airport is proof you can build a new 136,000-square-foot terminal — complete with a sweeping staircase — and save money doing it. “With enough grant money to pay for half of the $40 million project and the help of innovative money- and energy-saving features, the airport was able to keep the terminal’s overhead and maintenance costs low and pass on a $3.50 per-square-foot savings to airlines,” said Barton Drake, HNTB project manager. Frugality without compromise to quality runs in Redmond’s blood. A group of community volunteers built the airport in one day for $200 in the 1920s. It later became central Oregon’s primary commercial airport. However, as the community grew, the existing terminal, built in 1993 to serve 18- and 19-seat aircraft, quickly became too small for the region’s travel demands. The airport recorded nearly 190,000 passenger boardings in Missouri 2005 compared with 72,000 in 1993. “At the peak of holiday travel season before we broke ground in 2008, the departure area was Louisiana so crowded there was no room for anyone to stand or even sit on the floor,” said Carrie Novick, Redmond Municipal Airport manager. “The question wasn’t whether to expand, but how to expand economically.” The expansion was possible with funding from the Federal Aviation Administration, the Transportation Security Administration, the State of Oregon and PacifiCorp, a regional utilities company in the Northwest United States. HNTB, principal architect for the project, combined innovative green design elements with airport employee recommendations to produce a larger terminal building with these energy- and moneysaving features: • Reuse of 22,000 square feet of existing construction. • A low-flow air displacement HVAC system that disperses air from diffusers at the “occupant level” rather than overhead. This allows for warmer air to be delivered for cooling in high bay spaces resulting in energy savings. • Rooftop solar panels that produce 93,146 kilowatt hours of electricity annually. • Hydronic heat that keeps concrete surfaces ice-free in the wintertime. • A V-shaped roof that traps and melts snow, protecting passengers and landscaping from mini avalanches while also saving shoveling time. • Oversized, motorized revolving doors that replace the terminal’s large, energy-consuming, sideways sliding entryway and allow passengers with baggage to comfortably negotiate the building entry. • Security revolving doors that eliminate the need for security staff. • Recycled material used in the manufacture of new carpeting. • Exposed concrete walls that retain winter solar radiation. • Expanded restrooms that feature self-flushing toilets, handsfree washroom systems, waterless urinals and floors clear of obstructions for faster cleaning. • High-performance glass that maximizes natural light, and automated light fixtures that turn off when natural light meets Georgialevels. required • Insulated walls and roofs that exceed energy code requirements by 33 percent. “With the project nearly complete, the project is on time, on budget, and we’re looking at less than 2 percent change orders,” Novick said. “That’s the result of a great design and a great team.” n CONTACT: BARTON DRAKE, HNTB Project Manager (425) 450-2531 n [email protected] HNTB DESIGNER Number 94 “With the help of innovative moneyand energy-saving features, the airport was able to keep the terminal’s overhead and maintenance costs low and pass on a $3.50 per-square-foot savings to airlines.” Barton Drake project manager HNTB corporation HNTB DESIGNER Number 94 Page 21 Bob Kerrey Bridge wins ACEC Grand Award Three HNTB projects are honored in the American Council of Engineering Companies Engineering Excellence Awards program H North Avenue Bridge Marquette Interchange Page 22 NTB Corporation received a Grand Award from the American Council of Engineering Companies for its work on the Bob Kerrey Pedestrian Bridge in Omaha, Neb. It also was recognized with Honor Awards for the North Avenue Bridge Reconstruction project in Chicago and the Marquette Interchange Reconstruction project in Milwaukee. The awards were announced April 27, 2010, at ACEC’s Engineering Excellence Awards Gala in Washington, D.C. “Being recognized by our peers is an outstanding achievement, and we are honored for the recognition we have received on behalf of our clients for these award-winning projects,” said Ken Graham, CEO of HNTB Infrastructure. HNTB teamed with APAC-Kansas, Inc., to deliver the Bob Kerrey Pedestrian Bridge, a 2,222-foot structure spanning the Missouri River to connect Omaha, Neb., and Council Bluffs, Iowa. It is one of the longest pedestrian bridges ever designed and constructed and was the final piece in a $2 billion infrastructure redevelopment effort by the City of Omaha to revitalize its downtown and riverfront. The project, which is owned by the City of Omaha, helped transform a once heavily industrial area into a popular urban destination. Milwaukee Transportation Partners, a joint venture of HNTB and CH2M Hill, Inc., served as the lead design team for the Wisconsin Department of Transportation’s Marquette Interchange Reconstruction project. The interchange stands at the junction of I-94/I-43/I-794 in downtown Milwaukee, and carries more than 300,000 vehicles daily — nearly half of the state’s commerce and tourism traffic. Reconstruction of the interchange included moving all exit and entrance ramps, increasing weaving distances and clear zones, and improving local street access to increase mobility and safety. HNTB served as prime consultant for the City of Chicago on the North Avenue Bridge Reconstruction project, providing overall project management, administrative services and subconsultant coordination. The reconstruction resulted in improved safety, congestion relief and economic viability along a critical transportation artery in Chicago that is used by more than 30,000 vehicles daily. n HNTB DESIGNER Number 94 It’s time to improve our nation’s transportation bill of health Throughout my career, I have seen firsthand how our nation’s transportation arteries — our highways, railways, airways and waterways — are suffering from years of neglect. Their ability to carry the goods and services we depend on — our life’s blood as a nation — has been obstructed. Everything from cars and coal to food and furniture comes to us through these critical transportation arteries. The impact of these deteriorating systems reaches far beyond our borders as American businesses rely on them to ship manufactured goods across the country for export around the world. But regardless of our dependence on them, we have failed to maintain their health. Below are just a few of the harsh realities of getting this system up to speed. • $186 billion in federal spending is what the American Society of Civil Engineers predicts will be required annually to substantially improve our roads — far more than the current combined federal and state spending of $70.3 billion per year for highway capital improvements. And every year we continue to underinvest in our system, the gap grows larger. •A $1.2 trillion industry is at stake, according to a recent report from the American Association of State Highway and Transportation Officials. The problem goes beyond the delivery of goods and services as the transportation industry generates 8 percent of the nation’s jobs and supports industries that make up 84 percent of the economy. It’s important for Americans to realize this as we look for ways to emerge from the worst economic downturn since the Great Depression. •A multimodal strategy will play a critical role in improving our freight transportation networks, lowering our consumption of fuel and improving our environment. And while we take baby steps, our global competitors are racing ahead. We invest less than 1 percent of the value of our gross domestic product in infrastructure, compared with China’s 9 percent. By addressing our transportation challenges through workable planning, prioritizing and funding solutions, we can generate jobs and bolster our economy as we boost our mobility. HNTB is working hand in hand with clients to explore how multiple funding options, including private financing of transportation projects, the implementation of new technologies and project delivery methods , commercialization of public infrastructure and tolling, can work together to fund improvements. Delays will only increase costs and deterioration of our infrastructure. These problems need to be fixed now, starting with the old thinking and obsolete regulations that got us where we are today. We must allow the innovative spirit of our industry to flourish by electing leaders who share a positive vision for our country’s infrastructure, understand the urgency and are willing to take the lead. Transportation leaders must work together with them to inform the public and gain the support of the American people. Now is the time to pool our experience, resources and energies to develop a long-term, well-funded, sustainable transportation plan. n Point of View Pete K. Rahn National Transportation Practice Group Leader HNTB Corporation As leader of HNTB’s national transportation practice group, Rahn develops and directs strategies that enhance HNTB’s service to state departments of transportation across the country. He joined HNTB after serving as director of the Missouri Department of Transportation and as cabinet secretary over the New Mexico State Highway and Transportation Department. He also has served as president of the American Association of State Highway and Transportation Officials. Editor’s Note: Collaboration among all involved with the development of our nation’s infrastructure is critical to the economic and social success of our country. Designer magazine is pleased to host this “Point of View” column, which we hope will serve as a forum to discuss important trends and issues, as well as express viewpoints important to HNTB’s clients and their success. We welcome your ideas and feedback. Contact Susan Rhode, editor, [email protected]. HNTB DESIGNER Number 94 Page 23 The New Big House A $226 million renovation and expansion of Michigan Stadium, home to the University of Michigan Wolverines, was completed in time for the 2010 football season. HNTB served as architect of record for the project, which added more than 3,000 stadium club and infill seats, 81 suites, new press facilities and new elevated concourses with spectator amenities to the historic facility. Known as “The Big House,” the stadium originally was built in 1927 and now seats 110,000 fans, making it the largest collegiate sports venue in the country. The HNTB Companies Engineers Architects Planners
© Copyright 2024