Labour and Employment Department

`
Checklists and
Timelines for various
Applications under
Electricity
Department
Table of Contents
Table of Contents
...................................................................................................................................... 2
A. Obtaining a New LT Electricity Connection....................................................................................... 3
B. Obtaining a new HT Electricity Connection ...................................................................................... 4
Important Links
Ease of Doing Business
...................................................................................................................................... 6
Page | 2
A. Obtaining a New LT Industrial Electricity Connection
Checklist
1. Identity proof of applicant
2. Proof of Legal Occupancy
3. Layout plan of premises
4. Non Agriculture Permission of the land
Timeline
Maximum Number of Days to complete application:
For release of power supply for ‘Category A’ connection up to 100 KVA (LT Industrial
Connection)
ACTIVITY
TIMELIMIT
Issue of Demand notice
(Including Site Survey and
Issuing of Feasibility Clearance)
Within 7 days of date of application
Release of connection
Within 7 days after compliance of Demand Notice/formalities by
prospective applicant
Maximum Number of Days
to complete application
15 Days
For release of power supply for ‘Other than Category A’ connection up to 100 KVA ( LT
Industrial Connection)
ACTIVITY
TIMELIMIT
Issue of Demand notice
(Including Site Survey and
Issuing of Feasibility Clearance)
Within 10 days of date of application
Release of connection
Within 60 days after compliance of Demand Notice/formalities by
prospective applicant.
Maximum Number of Days
to complete application
70 Days
Ease of Doing Business
Page | 3
B. Obtaining a new HT Electricity Connection
Checklist
1. Legal Occupancy Proof (Plot Allotment letter OR 7/12 and 8A Abstract, OR Sale deed
OR lease deed etc...)
2. Identity proof of applicant
3. Non Agriculture Permission of the land.
4. Site plan with key map indicating point of supply and demarking the supply area.
Note:i.GPCB consent wherever required (To be submitted before actual release of power supply )
ii. Copy of Registered Partnership deed in case applicant is partnership firm.
iii. Power of attorney on stamp paper in prescribed format for authorized signatory to sign
the application forms, agreement etc.
iv. Memorandum of Articles for Public/Private Ltd Co.
v. Company resolution giving authority to authorized signatory to sign documents viz.
agreement application form
Ease of Doing Business
Page | 4
Timeline
For release of power supply above 100 KVA and up to 4000 KVA
ACTIVITY
TIMELIMIT
Issue of Demand notice
(Including Site Survey and
Issuing of Feasibility Clearance)
Within 15 days of date of application
Release of connection
Within 45 days after compliance of Demand Notice/formalities by
prospective consumers.
Maximum Number of Days
to complete application
60 Days
For release of power supply Above 4000 KVA
ACTIVITY
TIMELIMIT
Issue of Demand notice
(Including Site Survey and
Issuing of Feasibility Clearance)
Within 30 days of date of application
Release of connection
Within 180 days after completion of Demand notice/formalities
by prospective consumers.
Total
210 Days
Ease of Doing Business
Page | 5
Important Links
1. Energy and Petrochemicals Department:
http://guj-epd.gov.in
Obtaining an Electricity Connection:
2. Gujarat Urja VIkas Nigam Limited:
www.gseb.com
Zonal Distribution Companies:
3. Madhya Gujarat Vij Nigam Ltd.:
www.mgvcl.in
4. Paschim Gujarat Vij Nigam Ltd.:
www.pgvcl.in
5. Dakshin Gujarat Vij Nigam Ltd.:
www.dgvcl.in
6. Uttar Gujarat Vij Nigam Ltd.:
www.ugvcl.in
Ease of Doing Business