May 2006 What is involved in the project? Y ukon Energy is considering development of the Carmacks-Stewart Transmission Project to connect the Whitehorse-Aishihik-Faro and Mayo/Dawson power grids. The project would include a new 138 kV transmission line generally along the Klondike Highway as well as new transmission substations at Carmacks and Pelly Crossing, and changes to the substation at Stewart Crossing. A process is underway to select a preferred transmission route based on various factors including environmental, socio-economic, engineering and cost. Public consultation to identify areas to be avoided and/or used will be a key factor in determining the final route for the 180 kilometre line. A 500 metre wide study area corridor has been identified to guide assessment of route alternatives; however parts of the final route could potentially be sited outside this study area. If the project proceeds, the final right of way for the transmission line would be 60 metres in width (see photo below). Poles will be wood and could be either a single or H frame. What Regulatory Approvals and Reviews are necessary? • Regulatory permits/approvals are required for land use, river crossings and other activities. • Before such permits/approvals can be issued, environmental and socio-economic assessment is required under the Yukon Environmental and Socio-Economic Assessment Act (YESAA). • An Executive Committee screening assessment of the project will be required by the Yukon Environmental and Socio-Economic Assessment Board (YESAB). A 138 kV H-Frame transmission pole – Whitehorse-Aishihik-Faro Transmission Line The 60 metre right of way provides for access, minor realignments of the individual pole structures and line within the right of way during construction, and control of other activities or tree growth that would affect the reliability and safety of the line. • YESAB’s recommendations will be accepted, rejected or varied by decision making bodies within the Yukon government, First Nations with affected settlement lands and the federal government. What are the benefits? If developed as currently planned, the project will enable the Minto mine and the proposed Carmacks Copper mine to access surplus grid power rather than rely on diesel generation. This will benefit all Yukon ratepayers, the mines, governments and others. The line will allow Pelly Crossing, a community relying on diesel generation, to have access to hydro power. Connecting the two existing power grids will provide long-term benefits. The project will encourage economic development along the corridor and enhance overall system reliability and flexibility. 1 Project Overview N o decisions have been made at this time to proceed with the project. Any decision to proceed will occur only after meaningful consultation occurs with the affected First Nations, all environmental and other permits and approvals are obtained, and arrangements are concluded with major mine customers and the Yukon government as required to ensure that Yukon ratepayers are protected against adverse rate impacts. Proposed Carmacks-Stewart Transmission Project The Carmacks-Stewart Transmission Project is currently expected to be developed in two stages: Stage 1: Carmacks to Pelly Crossing, including the Carmacks substation and the Pelly Crossing substation and approximately 108 kilometres of line. Ancillary transmission projects related to this stage are currently anticipated to include: Minto Mine Spur: A 30 kilometre line at 25 or 35 kV, funded entirely by the mine, connecting the Minto mine currently under development west of the Yukon River with the project in the vicinity of Minto Landing. Carmacks Copper Spur: A 11 kilometre line at 138 kV, funded entirely by the mine if it is developed (it is currently in permitting/environmental assessment process), connecting the Carmacks Copper mine site west of the Yukon River with the project in the vicinity of McGregor Creek. Local distribution facilities: Connections at 25 or 35 kV to local distribution systems at Carmacks and Pelly Crossing will be developed by the local distributor, Yukon Electrical— consideration also to connection to local distribution at Minto Landing. Stage 2: Pelly Crossing to Stewart Crossing, including changes to the Stewart substation and approximately 72 kilometres of line. Routing for the project, which generally is expected to follow the Klondike Highway, will in certain areas be adjacent to or cross settlement lands for three Northern Tutchone First Nations (Little Salmon/Carmacks First Nation, Selkirk First Nation, and the First Nation of Nacho Nyak Dun). Yukon Energy has had initial discussions with these First Nations to inform them of the project and inquire as to their respective interests and concerns. A Memorandum of Understanding (MOU) has recently been concluded between Yukon Energy and these three First Nations addressing consultation on route selection, impacts, mitigation, benefits and other matters. 2 Route Options from Carmacks to McGregor Creek After Tantalus Butte, the currently identified route to Five Finger Rapids/Tatchun Creek will generally follow the study area along the east side of the Klondike Highway, avoiding or spanning poor drainage locations and any steep slopes. Two route alternatives have been identified in the Five Finger Rapids/Tatchun Creek area (separate 500 metre study areas identified for each option – each option at its northern end crosses Little Salmon/Carmacks settlement land): 2A: east option at Tatchun Creek • Avoids prime recreational viewing site of Five Finger Rapids. • Avoids crossing gravel pits. • Is east of Tatchun Creek campground, as recommended by the Dept. of Environment. • Route is straighter, shorter and less costly. 2B: highway option at Tatchun Creek Yukon Energy has obtained land for a new transmission substation at Carmacks, located north of the Yukon River and adjacent to the Carmacks airport and west of the existing 138 kV transmission line from Carmacks to Ross River. Two route alternatives have been currently identified moving west from the new Carmacks substation around Tantalus Butte (separate 500 metre study areas identified for each option): 1A: east option at Tantalus Butte • Route is straighter, shorter and less costly. • Avoids both privately owned lands and Little Salmon/Carmacks settlement lands. • Avoids viewpoints of the Yukon River. 1B: highway option at Tantalus Butte • Route is longer, adjacent to the Klondike Hwy, and more costly. • Crosses privately owned land as well as Little Salmon/Carmacks settlement land. • Will likely be aesthetic concerns from people who use the Yukon River. • Close proximity to Five Finger Rapids and Tatchun Creek Campground. • Potentially crosses gravel pits. • Route is longer, adjacent to the Klondike Highway and more costly. After Tatchun Creek the proposed route to McGregor Creek follows generally the east side of the Klondike Highway to reduce aesthetic impacts and crosses Little Salmon/Carmacks settlement land north of the Tatchun Creek area. Shortly before McGregor Creek, the proposed route crosses to the west of the highway to avoid two small Little Salmon/Carmacks First Nation settlement land parcels and to be in an optimum area for any tap connection to the proposed Carmacks Copper Mine. 3 Route Options from McGregor Creek to Pelly Crossing North of McGregor Creek, the proposed route soon crosses back to the east side of the Klondike Highway and generally remains there on Crown land until McCabe Creek to minimize impact on views. The proposed route crosses to the west side of the highway about three kilometres prior to McCabe Creek due to very steep slopes squeezing the transmission line right-of-way to overlap the highway right-of-way. The proposed route must cross Selkirk First Nation settlement lands throughout much of the remaining area from about McCabe Creek until close to Pelly Crossing. Route and tap/substation location alternatives will be identified in the Minto Landing area in consultation with the Selkirk First Nation and the Minto Mine, taking into consideration: • Location of additional step-down station (138 kV to lower voltage) for servicing the Minto Mine, and possibly the community of Minto Landing. • Potential options range between the Minto Landing community area (on Crown land) and the new barge landing site south of Minto Landing (on First Nation settlement land) for road access from the highway to the Minto Mine. In order to avoid poor drainage, lakes and the Lhutsaw Wetland Protected Habitat on the east side of the highway between Minto Landing and Pelly Crossing, the proposed route north of Minto Landing to Pelly Crossing is generally located on the west side of the Klondike Highway, proceeding north along as straight a line as possible. Three route options have been identified in the Pelly Crossing area for discussion with the Selkirk First Nation and others. These options typically (particularly Options 3A and 3C) go outside the 500 metre study area along the highway and cross Selkirk First Nation settlement lands. 3A: east option at Pelly Crossing • Avoids privately owned land and existing infrastructure within the community, as well as campground, road pullout, airport and the more scenic Pelly River crossing areas. • Longer line length than going through the community. Option is straighter and has fewer corner towers. • Substation tap located south of community. Additional distribution line required to service the community. 3B: option through community at Pelly Crossing • Shorter line length than option 3A, steeper terrain, more corner towers. • Various infrastructure constraints within the community, including housing development on north side of Pelly River and airstrip, as well as certain geographic constraints. • Substation tap can be closer to the community; minimize additional distribution line to service the community. 3C: west option at Pelly Crossing • Avoids privately owned land and existing infrastructure within the community. • Constraints include steep slopes, a creek and the airstrip on north side of Pelly River. • Further engineering feasibility is still required. • Substation tap located south of community. Additional distribution line required to service the community. 4 Route Options Pelly Crossing to Stewart Crossing From Pelly Crossing to Jackfish Lake terrain constraints and cost efficiency of long tangent lines result in the proposed route currently being located on the west side of the Klondike Highway across Selkirk First Nation settlement lands. Options on the east side of the highway might be considered, if so desired, to avoid some of these settlement lands. At Jackfish Lake two options have been identified: 4A: Option east of Jackfish Lake • East side of highway, away from Jackfish Lake Park Reserve. • Requires crossing the highway before the park to avoid aesthetic and recreation concerns (preferred route from Yukon Renewable Resources’ perspective). 4B: Option through Jackfish Lake Park Reserve • Slightly straighter/shorter line route; avoids crossing highway; goes though park reserve. • Potential for recreation and aesthetic concerns with this option. North of Jackfish Lake, after about five kilometres the proposed route falls within crown lands all the way to the Stewart Crossing substation. From Jackfish Lake to Crooked Lake, the currently identified route follows along the east side of the Klondike Highway before crossing to the west side. There are a few sections where steep slopes squeeze the transmission right-of-way very close to or within the highway right-of-way. At Crooked Creek, the proposed route crosses the highway well to the south-east of the roadside pull-out and bridge over Crooked Creek, and crosses the North Crooked Creek to avoid conflict with views. The proposed route then crosses back to the west side of the highway to avoid settlement lands of the First Nation of Nacho Nyak Dun (NND), and stays very close to the highway to avoid a section of poor drainage/bog. At Stewart Crossing, the proposed route is sited directly into the existing transmission substation, avoiding built-up areas of the community and keeping the Stewart River crossing for the route away from the community, bridge and highway. Two alternatives have been identified west of the highway for this last segment of the route: 5A: East option at Stewart: • Route adjacent to west side of 500 metre study area; in close proximity to existing housing and NND settlement lands. • Slightly shorter line length. 5B: West option at Stewart: • Route is further west than 5A and outside the 500 metre study area; avoids conflict with community and NND settlement land parcels. • Encounters poorly drained soils and boggy conditions. • Requires additional terrain analysis and engineering feasibility. 5 Public Involvement Stages – Carmacks-Stewart Transmission Project Anticipated Time Line Fall 2005 – Present ROUND 1 Intro to project/ preliminary issues and route alternatives Studies to define 500 m project study area completed 2005 Fall/Winter Information to First Nations, general public and YESAB. 2006 March Letter of Intent signed with Minto Mine May 2006 ROUND 2 Consultation on route alternatives and issues June 2006 ROUND 3 Consultation on impacts and mitigation measures for preferred route July 2006 Filing of project proposal submission to YESAB Fall 2006 ROUND 4 Consultation on YESAB submission March/April May/June A specific route has not yet been chosen – consultation is a key factor in selecting the final route. July 1. Opportunities for early involvement – BEFORE route decisions are made. 2. Opportunities for involvement at all stages providing real options and alternatives for route selection, and an opportunity for First Nation and public involvement after filing. 3. Unique status of Northern Tutchone First Nations as a Decision Body of proposed routes crossing settlement land, and as an interested party or expert on proposed routes through First Nations traditional territory. Comments? Questions? Yukon Energy Corporation Box 5920, Whitehorse, Yukon, Y1A 6S7 (867) 393-5331 (phone) (867) 393-5323 (fax) [email protected] www.yukonenergy.ca Waste stripping construction begins at Minto Mine site MOU discussions with Northern Tutchone First Nations The second round of public involvement is aimed at all interested publics. It provides information on the project and identifies options and issues regarding routing of the proposed transmission line. Route Selection Consultation Principles 6 2002/2003 Late Fall December Consultation on route alternatives & issues (May) and on impacts and mitigation (June) Project proposal submission filed with YESAB Project agreements with Northern Tutchone First Nations finalized Recommendations from YESAB Decision Body approves on 2007 project; Stage 1 construction to First Quarter Pelly Crossing begins March/April Minto Mine production set to begin (use diesel) 2008 Carmacks Copper Mine Summer/Fall production target start Stage 1 of transmission line complete to Pelly Construction of Stage 2 of 2009 transmission line to Stewart Summer/Fall complete
© Copyright 2024