Document 238527

May 2006
What is involved in the project?
Y
ukon Energy is considering development of the Carmacks-Stewart Transmission Project to connect the
Whitehorse-Aishihik-Faro and Mayo/Dawson power grids. The project would include a new 138 kV transmission line generally along the Klondike Highway as well as new transmission substations at Carmacks and
Pelly Crossing, and changes to the substation at Stewart Crossing.
A process is underway to select a preferred transmission route based on various factors including environmental,
socio-economic, engineering and cost. Public consultation to identify areas to be avoided and/or used will be a key
factor in determining the final route for the 180 kilometre line. A 500 metre wide study area corridor has been
identified to guide assessment of route alternatives; however parts of the final route could potentially be sited
outside this study area. If the project proceeds, the final right of way for the transmission line would be 60 metres
in width (see photo below). Poles will be wood and could be either a single or H frame.
What Regulatory Approvals and Reviews
are necessary?
• Regulatory permits/approvals are required for land use,
river crossings and other activities.
• Before such permits/approvals can be issued, environmental and socio-economic assessment is required under
the Yukon Environmental and Socio-Economic Assessment
Act (YESAA).
• An Executive Committee screening assessment of the
project will be required by the Yukon Environmental and
Socio-Economic Assessment Board (YESAB).
A 138 kV H-Frame transmission pole –
Whitehorse-Aishihik-Faro Transmission Line
The 60 metre right of way provides for access, minor
realignments of the individual pole structures and line
within the right of way during construction, and control
of other activities or tree growth that would affect the
reliability and safety of the line.
• YESAB’s recommendations will be accepted, rejected or
varied by decision making bodies within the Yukon government, First Nations with affected settlement lands
and the federal government.
What are the benefits?
If developed as currently planned, the project will enable the Minto mine and the proposed Carmacks Copper mine
to access surplus grid power rather than rely on diesel generation. This will benefit all Yukon ratepayers, the mines,
governments and others. The line will allow Pelly Crossing, a community relying on diesel generation, to have
access to hydro power. Connecting the two existing power grids will provide long-term benefits. The project will
encourage economic development along the corridor and enhance overall system reliability and flexibility.
1
Project Overview
N
o decisions have been made at this time to proceed with the project. Any decision to proceed will
occur only after meaningful consultation occurs with the affected First Nations, all environmental
and other permits and approvals are obtained, and arrangements are concluded with major mine
customers and the Yukon government as required to ensure that Yukon ratepayers are protected against
adverse rate impacts.
Proposed Carmacks-Stewart
Transmission Project
The Carmacks-Stewart Transmission Project
is currently expected to be developed in two
stages:
Stage 1: Carmacks to Pelly Crossing, including
the Carmacks substation and the Pelly Crossing
substation and approximately 108 kilometres of
line. Ancillary transmission projects related to
this stage are currently anticipated to include:
Minto Mine Spur: A 30 kilometre line at 25 or
35 kV, funded entirely by the mine, connecting
the Minto mine currently under development
west of the Yukon River with the project in the
vicinity of Minto Landing.
Carmacks Copper Spur: A 11 kilometre line at
138 kV, funded entirely by the mine if it is
developed (it is currently in permitting/environmental assessment process), connecting
the Carmacks Copper mine site west of the
Yukon River with the project in the vicinity of
McGregor Creek.
Local distribution facilities: Connections at
25 or 35 kV to local distribution systems at
Carmacks and Pelly Crossing will be developed
by the local distributor, Yukon Electrical—
consideration also to connection to local
distribution at Minto Landing.
Stage 2: Pelly Crossing to Stewart Crossing, including changes to the Stewart substation and approximately 72
kilometres of line.
Routing for the project, which generally is expected to follow the Klondike Highway, will in certain areas be
adjacent to or cross settlement lands for three Northern Tutchone First Nations (Little Salmon/Carmacks First
Nation, Selkirk First Nation, and the First Nation of Nacho Nyak Dun). Yukon Energy has had initial discussions
with these First Nations to inform them of the project and inquire as to their respective interests and concerns. A
Memorandum of Understanding (MOU) has recently been concluded between Yukon Energy and these three First
Nations addressing consultation on route selection, impacts, mitigation, benefits and other matters.
2
Route Options from Carmacks to McGregor Creek
After Tantalus Butte, the currently identified
route to Five Finger Rapids/Tatchun Creek will
generally follow the study area along the east
side of the Klondike Highway, avoiding or
spanning poor drainage locations and any
steep slopes.
Two route alternatives have been identified
in the Five Finger Rapids/Tatchun Creek area
(separate 500 metre study areas identified for
each option – each option at its northern end
crosses Little Salmon/Carmacks settlement
land):
2A: east option at Tatchun Creek
• Avoids prime recreational viewing site of Five
Finger Rapids.
• Avoids crossing gravel pits.
• Is east of Tatchun Creek campground, as
recommended by the Dept. of Environment.
• Route is straighter, shorter and less costly.
2B: highway option at Tatchun
Creek
Yukon Energy has obtained land for a new
transmission substation at Carmacks, located
north of the Yukon River and adjacent to the
Carmacks airport and west of the existing
138 kV transmission line from Carmacks to
Ross River.
Two route alternatives have been currently
identified moving west from the new
Carmacks substation around Tantalus Butte
(separate 500 metre study areas identified
for each option):
1A: east option at Tantalus Butte
• Route is straighter, shorter and less costly.
• Avoids both privately owned lands and
Little Salmon/Carmacks settlement lands.
• Avoids viewpoints of the Yukon River.
1B: highway option at Tantalus Butte
• Route is longer, adjacent to the Klondike
Hwy, and more costly.
• Crosses privately owned land as well as
Little Salmon/Carmacks settlement land.
• Will likely be aesthetic concerns from people
who use the Yukon River.
• Close proximity to Five Finger
Rapids and Tatchun Creek
Campground.
• Potentially crosses gravel pits.
• Route is longer, adjacent to the
Klondike Highway and more
costly.
After Tatchun Creek the proposed
route to McGregor Creek follows
generally the east side of the
Klondike Highway to reduce
aesthetic impacts and crosses
Little Salmon/Carmacks settlement land north of the Tatchun
Creek area. Shortly before
McGregor Creek, the proposed
route crosses to the west of the
highway to avoid two small
Little Salmon/Carmacks First
Nation settlement land parcels
and to be in an optimum area
for any tap connection to the
proposed Carmacks Copper Mine.
3
Route Options from McGregor Creek to Pelly Crossing
North of McGregor Creek, the proposed route soon crosses back to the east
side of the Klondike Highway and generally remains there on Crown land until
McCabe Creek to minimize impact on views. The proposed route crosses to the
west side of the highway about three kilometres prior to McCabe Creek due to
very steep slopes squeezing the transmission line right-of-way to overlap the
highway right-of-way.
The proposed route must cross Selkirk First Nation settlement lands
throughout much of the remaining area from about McCabe Creek until
close to Pelly Crossing.
Route and tap/substation location alternatives will be identified in the Minto
Landing area in consultation with the Selkirk First Nation and the Minto Mine,
taking into consideration:
• Location of additional step-down station (138 kV to lower voltage) for
servicing the Minto Mine, and possibly the community of Minto Landing.
• Potential options range between the Minto Landing community area (on
Crown land) and the new barge landing site south of Minto Landing (on First
Nation settlement land) for road access from the highway to the Minto Mine.
In order to avoid poor drainage, lakes and the Lhutsaw Wetland Protected
Habitat on the east side of the highway between Minto Landing and Pelly
Crossing, the proposed route north of Minto Landing to Pelly Crossing is
generally located on the west side of the Klondike Highway, proceeding
north along as straight a line as possible.
Three route options have been identified in the Pelly Crossing area for
discussion with the Selkirk First Nation and others. These options typically
(particularly Options 3A and 3C) go outside the 500 metre study area along
the highway and cross Selkirk First Nation settlement lands.
3A: east option at Pelly Crossing
• Avoids privately owned land and existing infrastructure
within the community, as well as campground, road pullout, airport and the more scenic Pelly River crossing areas.
• Longer line length than going through the community.
Option is straighter and has fewer corner towers.
• Substation tap located south of community. Additional
distribution line required to service the community.
3B: option through community at Pelly Crossing
• Shorter line length than option 3A, steeper terrain, more
corner towers.
• Various infrastructure constraints within the community,
including housing development on north side of Pelly
River and airstrip, as well as certain geographic constraints.
• Substation tap can be closer to the community; minimize
additional distribution line to service the community.
3C: west option at Pelly Crossing
• Avoids privately owned land and existing infrastructure
within the community.
• Constraints include steep slopes, a creek and the airstrip
on north side of Pelly River.
• Further engineering feasibility is still required.
• Substation tap located south of community. Additional
distribution line required to service the community.
4
Route Options Pelly Crossing to Stewart Crossing
From Pelly Crossing to Jackfish Lake terrain constraints
and cost efficiency of long tangent lines result in the
proposed route currently being located on the west side
of the Klondike Highway across Selkirk First Nation
settlement lands. Options on the east side of the highway
might be considered, if so desired, to avoid some of these
settlement lands.
At Jackfish Lake two options have been identified:
4A: Option east of Jackfish Lake
• East side of highway, away from Jackfish Lake Park
Reserve.
• Requires crossing the highway before the park to avoid
aesthetic and recreation concerns (preferred route from
Yukon Renewable Resources’ perspective).
4B: Option through Jackfish Lake Park Reserve
• Slightly straighter/shorter line route; avoids crossing highway; goes though park reserve.
• Potential for recreation and aesthetic concerns with this option.
North of Jackfish Lake, after about five kilometres the proposed route falls within crown lands all the way to the
Stewart Crossing substation.
From Jackfish Lake to Crooked Lake, the currently identified route follows along the east side of the Klondike
Highway before crossing to the west side. There are a few sections where steep slopes squeeze the transmission
right-of-way very close to or within the highway right-of-way.
At Crooked Creek, the proposed route crosses the highway well to the
south-east of the roadside pull-out and bridge over Crooked Creek,
and crosses the North Crooked Creek to avoid conflict with views. The
proposed route then crosses back to the west side of the highway to
avoid settlement lands of the First Nation of Nacho Nyak Dun (NND),
and stays very close to the highway to avoid a section of poor
drainage/bog.
At Stewart Crossing, the proposed route is sited directly into the existing transmission substation, avoiding built-up areas of the community
and keeping the Stewart River crossing for the route away from the
community, bridge and highway. Two alternatives have been identified
west of the highway for this last segment of the route:
5A: East option at Stewart:
• Route adjacent to west side of 500 metre study area; in close proximity to existing housing and NND settlement lands.
• Slightly shorter line length.
5B: West option at Stewart:
• Route is further west than 5A and outside the 500 metre study area;
avoids conflict with community and NND settlement land parcels.
• Encounters poorly drained soils and boggy conditions.
• Requires additional terrain analysis and engineering feasibility.
5
Public Involvement Stages – Carmacks-Stewart Transmission Project
Anticipated Time Line
Fall 2005 – Present
ROUND 1
Intro to project/
preliminary
issues and route
alternatives
Studies to define 500 m project
study area completed
2005
Fall/Winter
Information to First Nations,
general public and YESAB.
2006
March
Letter of Intent signed with
Minto Mine
May 2006
ROUND 2
Consultation
on route
alternatives
and issues
June 2006
ROUND 3
Consultation
on impacts and
mitigation
measures for
preferred route
July 2006
Filing of project proposal
submission to YESAB
Fall 2006
ROUND 4
Consultation
on YESAB
submission
March/April
May/June
A specific route has not yet been chosen – consultation is a key
factor in selecting the final route.
July
1. Opportunities for early involvement – BEFORE route
decisions are made.
2. Opportunities for involvement at all stages providing real
options and alternatives for route selection, and an opportunity
for First Nation and public involvement after filing.
3. Unique status of Northern Tutchone First Nations as a
Decision Body of proposed routes crossing settlement land,
and as an interested party or expert on proposed routes
through First Nations traditional territory.
Comments? Questions?
Yukon Energy Corporation
Box 5920, Whitehorse, Yukon, Y1A 6S7
(867) 393-5331 (phone)
(867) 393-5323 (fax)
[email protected]
www.yukonenergy.ca
Waste stripping construction
begins at Minto Mine site
MOU discussions with
Northern Tutchone First
Nations
The second round of public involvement is aimed at all
interested publics. It provides information on the project and
identifies options and issues regarding routing of the proposed
transmission line.
Route Selection Consultation Principles
6
2002/2003
Late Fall
December
Consultation on route alternatives & issues (May) and on
impacts and mitigation (June)
Project proposal submission
filed with YESAB
Project agreements with
Northern Tutchone First
Nations finalized
Recommendations from YESAB
Decision Body approves on
2007
project; Stage 1 construction to
First Quarter
Pelly Crossing begins
March/April
Minto Mine production set to
begin (use diesel)
2008
Carmacks Copper Mine
Summer/Fall production target start
Stage 1 of transmission line
complete to Pelly
Construction of Stage 2 of
2009
transmission line to Stewart
Summer/Fall
complete