Virginia State Corporation Commission eFiling CASE Document Cover Sheet Case Number (if already assigned) PUE-2009-00043 Case Name (if known) Application of PATH Allegheny Virginia Transmission Corporation for Approval and Certification of Electric Transmission Facilities Under Va. Code Section 56-46.1 and the Utility Facilities Act, Va. Code Sections 56-265.1 et seq. Document Type RPNS Document Description Summary Cover Letter, Response to Commission Staff Motion to Dismiss Application, Service List, Affidavit of Lawrence A. Hozempa, and Order Total Number of Pages 41 Submission ID 1518 eFiling Date Stamp 10/26/2009 2 :38:08PM HUNTON & WILLIAMS LLP RIVERFRONT PLAZA, EAST TOWER 951 EAST BYRD STREET RICUMOND, VIRGINIA 232194074 HUNTON& WMAMS TEL FAX 804 - 788 - 8200 804-788-8218 RICHARD D . GARY DIRECT DIAL: 804-788-8330 EMAIL; rgary@hunton .com October 26, 2009 FILE NO: 27364 .71 Via Electronic Filing Hon. Joel H. Peck Clerk State Corporation Commission Document Control Center Tyler Building, ls'Floor 1300 East Main Street Richmond, Virginia 23219 Application of PATH Allegheny Virginia Transn-dssion Corporation For Approval and Certification of Electric Transmission Facilities Under Va. Code § 56-46.1 and the Utility Facilities Act, Va. Code §§ 56-265 .1 et seq . Case No. PUE-2009-00043 Dear Mr. Peck: Enclosed is PATH Allegheny Virginia Transmission Corporation's Response to Commission Staff Motion to Dismiss Application, Case No. PUE-2009-00043 . Richard D . Gary RDG/tms Enclosure Service List cc: Hon. Mark C. Christie Hon. James C. Dimitri Hon. Judith W. Jagdmann Hon. Alexander Skirpan, Jr. C. Meade Browder, Esq. Wayne N . Smith, Esq. Frederick Ochsenhirt, Esq. Randall B. Palmer, Esq. Charlotte P. McAfee, Esq . ATi,AMI'A i0SAN617,TFIS MI-LEAN AUSTIN' NlIkM! RANOKOK BFIjiN(i NORFOLK ',RRUSSEI,~ RALPACH (HAKLMITF RJOINIOND w"k, whu n I on. Cox-, DALLA~ h0l!SION !,ONDON SAN~RA-Nciv") SIM~AFCA~ V~ASH~NOION BEFORE THE STATE CORPORATION COMMISSION OF VIRGINIA APPLICATION OF PATH ALLEGHENY VIRGINIA TRANSMISSION CORPORATION Case No. PUE-2009-00043 For approval and certification of electric transmission facilities under Va. Code § 56-46 .1 and the Utility Facilities Act, Va. Code §§ 56-265 .1 et seq. RESPONSE TO COMMISSION STAFF MOTION TO DISMISS APPLICATION PATH Allegheny Virginia Transmission Corporation ("PATH-VA") urges the Virginia State Corporation Commission ("Commission") to deny the Commission Staff s Motion to Dismiss Application ("Motion").' First and foremost, the construction and operation of the 1 Respondent, River's Edge Community Association, Inc. filed a Motion to Dismiss ("RECA Motion") on October 19, 2009 joining the request of the Staff and adding several allegations that are not relevant to a motion to dismiss. One allegation however, asserts that PATH-VA shows "contempt!'for local elected officials (RECA Motion at 3). PATH-VA categorically denies that assertion . In fact, PATH-VA held numerous open houses in Virginia and communicated directly with local officials in meetings, by telephone and over electronic mail . Specifically, PATH-VA met with local officials (including Mayor Elaine Walker and Supervisor Sally Kurtz) on four separate occasions, including August 14, 2008, December 9, 2008, January 5, 2009, and February 25, 2009, to discuss various aspects of the PATH Project . Delegate Joe May attended two of these meetings and sent a representative for the two meetings that he did not personally attend . The January 22, 2009 Public Open House resulted from discussions held during these meetings . The Piedmont Environmental Council also joined the Staff through its Filing in Support of Staff Motion to Dismiss (October 23, 2009) . (continued . . . ) Potomac-Appalachian Transirtission Highline ("PATH Project") is essential to address reliability violations of the North American Electric Reliability Corporation ("NERC") Reliability Standards that are anticipated to arise as early as June 2014 and continue thereafter. This need for the PATH Project existed when the Application was filed, and exists today. If not addressed, these anticipated violations of the NERC Reliability Standards could result in transmission line overloads and in voltage drops and voltage collapse, affecting electric service in Virginia. (See, e.g., Application, Exhibit 3, Section 1. B ; prefiled testimony of Lawrence A. Hozempa at 17-20; and McGlynn prefiled Exhibit PFM-6.) The public interest will not be served by summarily dismissing this Application and delaying the approval of the Virginia portion of the PATH Project . The public interest will instead be served by moving forward to approve the Virginia portion of the PATH Project in order to address the anticipated reliability violations . In addition, simply dismissing the Application at this point, when discovery is virtually complete and much of the testimony has been prepared and exchanged, would result in an unnecessary waste of time and resources . The Motion is premised entirely on the Maryland Public Service Commission's ("MD PSC") Order No. 82892, dated September 9, 2009 ("Order") (attached) that found that the MD PSC applicant, The Potomac Edison Company ("Potomac Edison"), could not file an application Respondents Alfred T. and Irene A. Ghiorzi filed a Motion to Dismiss and for Reimbursement of All Fees and Expenses on October 20, 2009, joining the Staff s and RECA's Motions. The Ghiorzis' Motion includes the allegation that PATH-VA "is not an appropriate new entrant" to provide transmission service in Virginia. The Ghiorzis filed a Motion to Dismiss on June 6, 2009 in this proceeding and asserted this same point. The Hearing Examiner's Ruling of July 31, 2009 denied that Motion and found that PATH-VA is a Virginia public utility that may file an application to begin operations in Virginia (Ruling at 3). Respondent Charles R. Rodriguez filed a Motion to Dismiss on October 21, 2009, joining Staffs, RECA's and the Ghiorzis' motions . In his motion, Mr. Rodriguez asserts that he has been put to great expense and inconvenience in this proceeding thus far, and reiterates RECA's allegation of contempt shown by PATH-VA in its outreach efforts and interaction with locally elected officials . for a Certificate of Public Convenience and Necessity ("CPCN") on behalf of its affiliate, PATH Allegheny Transmission Company LLC, ("PATH-Allegheny"), to construct the PATH Project because PATH-Allegheny technically is not an "electric company" under Maryland law and that Maryland law authorizes the MD PSC to issue a CPCN for construction of a transintission line only to an electric company (Order at 6). Importantly, the MD PSC did not in any way address or adjudicate the need for the PATH Project, its proposed route in Maryland or its terminus at Kemptown Substation in Frederick County, Maryland . In fact, the MD PSC specifically noted "that our decision that PATH is not eligible to construct a transmission line in Maryland should not be read to foreshadow any views on the merits of the proposed transmission line project" (Order at 6-7) .2 The MD PSC requested a response from Potomac Edison within 30 days describing its future intention as to approval of the PATH Project in Maryland (Order at 12-14). On October 9, 2009, counsel for Potomac Edison submitted a letter to the MD PSC stating as follows : At this time, the Company continues to consider its filing options, including whether to re-file an application with the Commission, and intends to inform the Commission of its decision as soon as possible. The foregoing response of Potomac Edison to the MD PSC should not be interpreted to support the Staff s assertion of the "absence of a known Maryland termination . . . for the PATH Project" (Motion at 3). In fact, this assertion in the Staff's Motion is erroneous and baseless. As demonstrated in the attached Affidavit of Lawrence A. Hozempa, the proposed terminus for the PATH Project has not changed and the line will terminate at the proposed Kemptown Substation in Frederick County, Maryland, consistent with the Application filed in Virginia. 'The West Virginia Public Service Commission has scheduled the PATH Project for hearing beginning February 8, 201 0. The fact that another application has not been filed in Maryland does not change the fact that the terminus of the PATH Project remains at the Kemptown Substation . The ongoing consideration by Potomac Edison with regard to whether it will file another application with the MD PSC for authority to construct the PATH Project in Maryland requires significant analysis of a myriad of issues, not the least of which is the financial ability of Potomac Edison to construct the project as was discussed in Potomac Edison's briefs prior to the issuance of the Order by the MD PSC. In addition, such decision-making involves consideration of whether PATHAllegheny should seek authorization to construct the PATH Project in Maryland through an application to the Federal Energy Regulatory Commission ("FERC"), pursuant to Section 216 of the Federal Power Act. The option was clearly demonstrated in Potomac Edison's briefs leading up to the Order . As supported by the attached Hozernpa Affidavit, there has been, and there will be, no change to the terminus of the PATH Project at the proposed Kemptown Substation . In connection with the PATH Project, 152.3 acres have been purchased for the Kemptown Substation, which will be located at the point where existing 500 kV transmission lines of Baltimore Gas and Electric Company and Potomac Electric Power Company are in close proximity. This site has been selected for the Kemptown Substation because PJM Interconnection, L.L.C. ("PJM") has directed that the PATH Project terminate at the point where it is interconnected with these existing transmission lines. Thus, the underpinning of the Motion - Staff's asserted lack of an "identified terminus of the line" (Motion at 3) - is flawed, as the terminus of the line will be, as set out in PATH-VA's application, at the Kemptown Substation in Maryland . Staff argues in support of its Motion that the action by the Maryland Commission renders incomplete the Application filed in Virginia. This simply is not true. The Application filed in Virginia remains the same, and in fact has already been found to be complete by this Commission in its June 12, 2009 Order for Notice and Hearing . That Order stated that the Commission, "upon consideration of the Application and applicable statutes and rules, finds that the PATH-VA Application in Case No. PUE-2009-00043 included the information necessary for the notice required by §§ 56-46 .1 B and 56-265.2 of the Code and that the filing conforms to the Commission's Rules of Practice and Procedure . . .... The Order and Notice specifically referenced the following proposed route for the PATH Project: "The PATH Project is a proposed 765 kV transmission line that would originate at the existing Amos Substation near St. Albans, West Virginia; cross the Virginia counties of Frederick, Loudoun, and Clarke; and terminate at the proposed Kemptown Substation near New Market, Maryland ." The plan to construct the PATH Project in Virginia, as identified in the Application and referenced in the Order and Notice, was sufficient to support the docketing of the Application and remains the same today as it was then. Accordingly, the Commission has already found the Application to be complete - and it remains SO. In addition, and as discussed above, if the Commission were to grant the relief the Motion seeks, which is based on the incorrect assumption that the terminus of PATH is not known, the tremendous effort that has been expended by PATH-VA and all other parties in this proceeding would be wasted . For example : PATH-VA has filed an Application accompanied by the detailed testimony and exhibits of 15 witnesses ; " PATH-VA has responded to 28 sets of interrogatories and requests for production of documents propounded by the Staff and the Respondents ; " Specific notice by first class mail has been sent to 774 landowners ; " Advertisements have been published pursuant to the Commission's Order for Notice and Hearing issued on June 12, 2009; " Public hearings have been held in the Winchester County and Loudoun County areas where the PATH Project will traverse and another public hearing is scheduled in Lovettsville in Loudoun County on November 19, 2009 ; " Testimony has now been filed on behalf of more than a dozen Respondents and Staff testimony is due to be filed on December 1, 2009 ; and " The hearing on the merits is scheduled to begin on January 19, 2010 . In short, this Application is well down the Virginia procedural schedule. Potomac Edison's decision with regard to a possible re-filing of an application for approval of the PATH Project in Maryland will be announced in the near future. Irrespective of whether Potomac Edison re-files with the MD PSC or PATH-Allegheny pursues authorization for the PATH Project in Maryland before FERC, the application to the MD PSC or FERC most assuredly will re-confirin the terminus of the PATH Project at the Kemptown Substation. Accordingly, the Virginia application for the PATH Project should not be dismissed based on the erroneous assertion of the Staff that there is no known terminus in Maryland, and it is not necessary or proper to certify the Staff's question to the Commission on the completeness of the Virginia Application, a matter on which the Commission has already specifically ruled. WHEREFORE, the Staff s Motion should be denied, and the issue should not be certified to the Commission . Respectfully submitted, PATH ALLEGHENY VIRGINIA TRANSMISSION CORPORATION B Dated: October 26, 2009 Richard D. Gary Charlotte P. McAfee Humon & Williams LLP Riverfrom Plaza, East Tower 951 East Byrd Street Richmond, VA 23219-4074 (804) 788-8328 ; fax (804) 788-8218 [email protected] [email protected] Randall B. Palmer Jeffrey P. Trout Allegheny Energy 800 Cabin Hill Drive Greensburg, PA 15601-1689 724-838-6894 [email protected] [email protected] 62L Couns6f' CERTIFICATE OF SERVICE I hereby certify that on this 26th day of October, 2009, a true copy of the foregoing Response was delivered by hand or mailed, first-class, postage prepaid, to the attached service list, which was copied from the Commission's electronic service list in Case No. PUE-200900043 on October 26, 2009 and to the following : C. Meade Browder, Jr., Esq. Office of Attorney General 900 E. Main Street 2nd Floor Richmond, VA 23219 Wayne N. Smith, Esq. Frederick Ochsenhirt, Esq. State Corporation Commission 1300 East Main Street Tyler Building, 10t" Floor Richmond, VA 23219 Counsel SERVICE UsT CAsE No. PUE-2009-00043 As OF OCTOBER 26~ 2009 Benson, W. T. Esquire Piedmont Environmental Council PO Box 460 Warrenton VA 20188 Burger, John D. 39605 Wenner Rd Lovettsville VA 20180 Cadden, Kevin F. 1602 Aerie Lane McLean VA 221 01 Cardamon, Don C. 12226 Harpers Ferry Rd Purcellville VA 20132 Crowley, James K. PO Box 344 40267 Quarter Branch Rd Lovettsville VA 20180 Dellano, Josephine B. 2567 E 21 st St Brooklyn NY 11235-2918 Dunagin, James 13226 Crest Lane Purcellville VA 20132 Dunlap, Daniel C . 39593 Sugar Maple Lane Loveftsville VA 201 80 Fisher-Guarino, Taina G . 11771 Folly Lane Lovettsville VA 20180 Fognano, Kenneth M . 12915 Shady Lane Purcellville VA 20132 Ghiorzi Baus, Angela 313 Ross St Morgantown WV 26501 Ghiorzi, Irene A. 39558 Wenner Rd Lovettsville VA 20180 Ghiorzi, Theresa 39558 Wenner Rd Lovettsville VA 201 80 Griffin, J. D. 29 N Braddock St PO Box 444 Winchester VA 22604 Hall, Patricia A. 39540 Quarter Branch Rd Lovettsville VA 20180 Hodgson, Gordon M. 11820 Berlin Turnpike Lovettsville VA 201 80 Hoffman, James S. 39883 Catoctin View Lane Lovettsville VA 20180 Hyatt, Franklin J. 39687 Wenner Rd Lovettsville VA 20180 Johnson, Lauren 190 Hannah Court Winchester VA 22603 Kershner, Robert J. 11688 Purcell Rd Loveftsville VA 20180 Lawson,Keith 11760 Berlin Tpk Lovettsville VA 20180 MacHorton, J . G. 12910 Crest Lane Purcellville VA 20132 Marmet, Robert G. Esquire Piedmont Environmental Council 45 Horner St PC Box 460 Warrenton VA 20188 Matarazzo, William 39625 Sugar Maple Lane Lovettsville VA 20180 Meiser, Hala A. 8700 Lothbury Court Fairfax VA 22031 Mohler, Nicholas L. 11 479 Potomac Heights Lane Lovettsville VA 201 80 Murphy, Timothy 12031 Morningstar Place Lovettsville VA 20180 Palmer, Randall B. Esquire Allegheny Energy 800 Cabin Hill Drive Greensburg PA 15601-1689 Randles, Kenneth 39998 Catoctin View Lane Loveltsville VA 201 80 Rittner, Dawn 12001 Morningstar PI Lovettsville VA 20180 Roberts, John R. County Attorney County of Loudoun 1 Harrison St., SE/5th Fl. Leesburg VA 20175-3102 Rosenthal, Dawn L. 39763 Rivers Edge Lane Lovettsville VA 20180 Silverman, Deanna 12011 Morningstar Place Lovettsville VA 20180 Trout, Jeffrey P. Esquire Allegheny Power 800 Cabin Hill Dr Greensburg PA 15601 Ulmer, Tylee M . 37964 Long Lane Lovettsville VA 20180 Vanderhye, Robert A. 801 Ridge Dr McLean VA 22101-1625 Wallington, Mary L. 11583 Scott Morgan Lane Lovettsville VA 20180-1868 Zwicker, David 12220 Harpers Fe" Rd Purceliville VA 20132 STATE CORPORATION COMMISSION COMMONWEALTH OF VIRGINIA APPLICATION OF PATH ALLEGHENY VIRGINIA TRANSMISSION CORPORATION Case No. PUE-2009-00043 For certificates of public convenience and necessity to construct facilities : 765 kV Transmission Line through Loudoun, Frederick, and Clarke Counties AFFEDAVrF 1, Lawrence A. Hozempa, the undersigned afflant, do hereby make the following statements based on personal knowledge, and under oath on behalf of The Potomac Edison Company, PATH Allegheny Virginia Transmission Corporation CPATH-VA"), PATH Allegheny Transmission Company, LLC and PATH West Virginia Transmission Company, LLC: I. I am over 18 years of age and am I am employed by Allegheny Energy Service Corporation as a Consulting Engineer in the Transmission Planning Department assigned to perform certain tasks for, among other affiliates, PATH-VA and Allegheny Power. 2. On May 19, 2009, PATH-VA filed an application with the State Corporation Commission of Virginia for certification of proposed 765 kV electric transmission facilities (the "PATH Projeef), which was docketed as Case No. PUE-2009-00043 . The Application included my prefiled direct testimony in support of the need for the PATH Project. 3. On October 19, 2009, the Staff of the State Corporation Commission filed a Motion to dismiss PATH Allegheny Virginia Transmission Corporation's C'PATH-VA~') application for certification of electric transmission facilities, docketed as Case No. PUF,200900043. The Motion asserted that the Application should be dismissed as incomplete because of the status of the Maryland PATH Project proceeding. Staff specifically stated that "there now exists such a level of uncertainty as to the termination point of the PATH Project that the Staff cannot discharge its duty to analyze the application and advise the Commission on whether the project should be approved and, if approved, where it should be routed." 4. The current status of the application before the Maryland Commission does not change the contents of the PATH Application before the Virginia State Corporation Commission or the pre-filed testimony in support of that Application. The plan is to continue to move forward with the route detailed in that Application and in the supporting testimony. The terminus of the PATH Project is still the proposed Kemptown Substation near New Market, Maryland, as set forth in the Application PATH-VA filed with this Commission. There has been no change to the terminus and therefore there is no uncertainty as to the termination point. [Continued on the next page.] Further, the afflant sayeth not STATE OF WEST VIRGENTIA COUNTY OF,-,~&,~o I do hereby certify that on this db' day of &4he 2009, Lawrence A. Hozempa personally appeared before the unders~g~n notary public and made oath to the foregoing . Notary My commission expires : 2, Alq ORDER NO. 82892 IN THE MATTER OF THE APPLICATION OF THE POTOMAC EDISON COMPANY ON BEHALF OF PATH ALLEGHENY TRANSMISSION COMPANY, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT THE MARYLAND SEGMENTS OF * 765 kV ELECTRIC TRANSMISSION LINE AND * SUBSTATION IN FREDERICK COUNTY, MARYLAND BEFORE THE PUBLIC SERVICE COMMISSION OF MARYLAND CASE NO. 9198 In this Order, the Public Service Commission ("Commission")' finds that the Potomac Edison Company d1b/a Allegheny Power ("Potomac Edison" or the "Company") may not seek authorization to construct a transmission line on behalf of its non-electriccompany affiliate, PATH Allegheny Transmission Company, LLC ("PATH") .2 As set forth below, we find first that § 7-207(b)(3) of the Public Utility Companies ("PUC") Article authorizes us to issue a Certificate of Public Convenience and Necessity ("CPCN") only to an "electric company,"3 a status PATH undeniably lacks, and that the law does not allow us to ignore or circumvent this requirement by granting a CPCN to Potomac Edison "on behalf of' PATH when Potomac Edison will neither construct nor operate the proposed line. Second, as a result of this holding, we find that no application to construct the proposed transmission line has properly been filed with the Commission, and thus that any time periods pertaining to possible federal siting authority have not yet begun to run and will not begin to run until a proper electric company has filed a complete application ' Commissioner Brenner dissents from Section II of this Order and writes separately on the issues covered there. He joins the remainder of this Order. 2 There are a number of different entities that use one variant or another of the "PATH" name. Unless otherwise noted, the abbreviation 'TATH" refers to all or any one of them, as appropriate. ' See PUC § 1-101(h) . with the Comniission. Third, because the issue would have been presented had this application been properly filed, we hold that our authority under § 7-207(b)(3) of the PUC Article encompasses all components of a project integral to the proposed transmission line, including, where appropriate, substations . We make no decisions here about whether the substation proposed in this application would or would not qualify as integral to the proposed transmission line for these purposes, Based on these holdings, we need not and do not structure or schedule any further proceedings to consider this application. We ask the Company to inform the Commission within 30 days of its intention to submit a new, conforming application and, if possible, the anticipated timeframe of any such filing . 1. Background On May 19, 2009, Potomac Edison filed a Motion for Expedited Decision that the Company may file for a Certificate of Public Convenience and Necessity (" CPCN ") on behalf of PATHAIIegheny Transmission Company, LLC and an Applicationfor a CPCN to construct the Maryland segments of a 765-kV transmission line and a substation in Frederick County, Maryland ("Motion") at the same time it submitted an Application of The Potomac Edison Company on Behalf of Path Allegheny Transmission Company, LLC for a Certificate of Public Convenience and Necessity to Construct the Maryland Segments of a 765 KV Electric Transmission Line and a Substation In Frederick County, Maryland ("Application") . The Commission considered the Motion, and specifically whether the Application could be filed in the form PATH lodged it, at the Commission's Administrative Meeting on June 3, 2009. After hearing from the Commission's Technical Staff ("Staff"), the Company, the Office of People's Counsel ("OPC"), the Board of County Commissioners of Frederick County, Maryland ("County"), the Sierra Club, the Sugarloaf Conservancy, Inc., as well as from a number of citizens from Frederick County who opposed the proposed substation, the Commission found that several preliminary matters must be briefed, argued and resolved before the Commission could set the Application for hearing : 1) Does § 7-207(b)(3) of the Public Utility Companies Article, Annotated Code of Maryland ("PUC") authorize the Commission to issue a CPCN for a transmission line designed to carry a voltage in excess of 69,000 volts to any entity other than an electric company? Does the Company, a Maryland electric company, have standing to seek a CPCN for a line that would be constructed and owned by its affiliate, PATH Allegheny Transmission Company, LLC, which is not a Maryland electric company? If the Commission were to issue the requested CPCN to the Company, under what authority could the Company assign or otherwise delegate the construction or ownership of any approved transmission line to an affiliate? 2) Must the Company obtain the County's approval regarding the siting of the substation, or has the PUC preempted the County's zoning authority? If the County is not pre-empted, may the Application be considered by the Commission concurrently with the County zoning process? 3) What, if any, sources of federal siting authority might apply to any aspect of the proposed project? For each source of federal siting authority identified : (a) is there a time period that must elapse before that authority could be invoked; (b) if so, has that time period begun to run; and (c) if so, when did the time period begin to run?4 4) Should the Commission set an intervention deadline immediately and allow discovery to start prior to ' Although the Commission directed the parties to address this issue, ultimately, individual parties will decide what federal avenues they will attempt to pursue and it would be up to federal authorities to determine what, if any, jurisdiction they have in this matter . deciding the preliminary matters? What core discovery could be started prior to a ruling on these preliminary matters? The Commission set a briefing schedule and scheduled oral arguments for July 3 1, 2009. Pursuant to that schedule, Staff, OPC, the Company, several organizations and numerous citizens submitted both Initial Briefs and Reply Briefs . The County submitted Initial Comments on Issues 2 and 3 and declined to comment on Issues I and 4. In submitting its comments, the County asserted that it was not submitting to the jurisdiction of the Commission to determine the issues. After reviewing and considering the briefs of all parties and the testimony and comments received at the July 31st hearing, the Commission finds that the Application cannot be accepted as filed. 11. § 7-207(b)(3) of the PUC Article Does Not Authorize The Commission To Grant A CPCN To Potomac Edison "On Behalf Of" PATH The first, and threshold, question before us is whether the PUC Article authorizes us to issue a CPCN for the proposed transmission line to Potomac Edison "on behalf of' PATH. Potomac Edison concedes, to its credit, that the proposed line would be built, owned and operated not by Potomac Edison itself, but by a family of entities created for those purposes. 5 Potomac Edison acknowledges as well that the PATH companies do not qualify as an "electric company" under the PUC Article6 and that the Maryland entity, PATH Allegheny, "couldn't come here on its own to seek a CPCN to build a transmission line ,,7 In light of these undisputed facts, Potomac Edison submitted the Application "on See Initial Brief of Potomac Edison at 4-5 . See Transcript of Hearing, July 31, 2009 ("Transcript"), at 12 ("CHAIRMAN NAZARIAN : But [PATH Allegheny] is not an electric company, right? MS. HERMAN : PATH Allegheny is not an electric company ."). An electric company is defined as "a person who physically transmits or distributes electricity in the State to a retail electric customer ." PUC § 1-101(h). ' See Transcript at 12 ("CHAIRMAN NAZARIAN: PATH Allegheny couldn't come here on its own to seek a CPCN to build a transmission line, correct? MS. HERMAN : Correct."). behalf of' the PATH entities and asks us to issue (after the appropriate review) a CPCN in that fashion . Potomac Edison argues that we can grant this Application because neither § 7-207(b)(3) of the PUC Article nor the Commission's regulations expressly forbids it. When pressed, Potomac Edison also falls back on § 2-113 of the PUC Article, the section defining the Commission's general supervisory and regulatory authority over public service companies, and argues that the operational and financial benefits from the PATH entity structure justify a "liberal" construction of our statutory authority. In this context, however, the law does not permit us the sort of flexibility Potomac Edison seeks . Indeed, § 7-207(b)(3) of the PUC Article leaves no interstitial void for § 2113 of the PUC Article to fill: it limits the Commission's authority to issue CPCNs for transmission lines designed to carry a voltage in excess of 69,000 volts to "electric company[ies]": Unless a certificate of public convenience and necessity for the construction is first obtained from the Commission, an electric company may not begin construction of an overhead transmission line that is designed to carry a voltage in excess of 69,000 volts or exercise a right of condemnation with the construction. 8 The term "electric company" is defined in the PUC Article and, unlike the Panda case on which Potomac Edison relies,9 there is no factual dispute here about whether PATH could satisfy that definition . To the contrary, we know here that the family of entities created to construct, own and operate the proposed line cannot qualify as an electric company. The only way to read this sentence to allow a non-electric company such as PATH to construct a 69kV or greater transmission line is to ignore the term or to give it a meaning different than the meaning the General Assembly gave it. Moreover, the General Assembly knew ' PUC 7-207(b)(3) (emphasis added) . 9 See Re Potomac Elec. Power Co., 83 Md. P.S.C. 191 (1992) . precisely bow to modify our authority to allow non-electric companies to build things - in 1999, as part of legislation restructuring Maryland's electricity markets, the General Assembly amended the companion provision defining our authority to issue CPCNs for generating stations to allow a "person," rather than just an electric company, to construct one .10 So although we agree with Commissioner Brenner that we should interpret and apply the PUC Article flexibly and with the best interests of the ratepayers in mind, that principle does not permit us to expand the scope of our authority if we disagree with the lines the legislature has drawn . It may be that the structure of PATH entities would allow them to construct and operate the line more efficiently and cost-effectively, but that possibility does not permit us to ignore or waive the statutory limitations on our authority . For these reasons, we find that § 7-207(b)(3) of the PUC Article does not authorize the Commission to issue a CPCN to "Potomac Edison on behalf of PATIL" and that the Application Potomac Edison submitted on May 19, 2009 is neither complete nor properly filed. And as such, any time periods that must expire before PATH might seek authority to construct the proposed project under federal law have not yet begun to run." Potomac Edison could, of course, file an application for a CPCN on its own behalf, and that filing would trigger the Commission's CPCN review process, and we ask the Company to advise the Commission within thirty days of its intention to do so and, if so, an estimate of when it plans to file a proper application. We note as well that our decision that PATH is not eligible to construct a transmission line in Maryland should not be read to foreshadow any * See Chapters 3 and 4, Acts 1999, amending PUC § 7-207(b)(1)(i) . * See, e.g., Section 216 of the Energy Policy Act of 2005, codified at 16 U.S.C. §824p which grants the Federal Energy Regulatory Agency ("FERC") the authority to issue a construction permit for an applicant's transmission line if the Commission "withheld approval for more than I year after the filing of an application seeking approval pursuant to applicable law . . . ... 16 U.S.C.§824p(b)(1)(C) (i) views on the merits of the proposed transmission line project. 111. The Commission's CPCN Authority Encorwasses Electric Substations That Are Integral To Transmission Lines Designed To Carry a Voltage In Excess of 69,000 Volts Notwithstanding our holding above, we will address the relative scope of our CPCN authority vis-A-vis Frederick County's zoning authority for two reasons, First, the question of whether our CPCN authority encompasses the siting, specifications and conditions of the proposed Kemptown 12 substation is fully briefed and argued. Had we decided that Potomac Edison could seek a CPCN on behalf of PATH, as Commissioner Brenner would, we would need to decide the question and would do so on the very same record . Second, because Potomac Edison and the PATH entities are seeking approval to construct portions of the proposed transmission line in other states simultaneously, we expect that Potomac Edison will seek authorization to build the proposed transmission line project in the near future, at which point the identical issue would surface again. As a general rule, the Commission does not and will not issue advisory opinions, and this Order should not be read as setting a precedent that the Commission will decide on an advisory basis issues not presented in a live case or controversy . But because these precise issues are likely to come before us in the context of this same project, 13 we offer the following guidance for the parties for the near-future life of this proposed project. Although it is dramatically more complicated in engineering terms, the Maryland portion of the proposed project consists of two primary components : a 765-kV " We recognize that the proposed substation, which has been labeled "Kemptown" in the regional transmission planning process, is physically located in Mount Airy, Maryland, not the town of Kemptown itself For the sake of consistency between the application and this decision, we will refer to the substation by its planning name. As the Company proceeds, however, it should be mindful of the potential for public confusion that this nomenclature apparently has created and should tailor its public outreach accordingly . 13 Cf. City of Los Angeles v. Lyons, 461 U.S. 95 (1983) (exception to mootness doctrine applies where claims are capable of repetition yet evading review). transmission line and, at the terminus of the line, a new substation . Nobody disputes the Cormi-tission's authority (assuming a proper application) to consider and issue a CPCN for the transmission line portion of the project . With regard to the substation portion of the project, however, Frederick County argues that the Maryland General Assembly has directly delegated authority to site or locate electricity substations to local governments, and thus that the proposed Keniptown substation cannot be sited or constructed as proposed without the County's approval. The Company and Staff argued, to the contrary, that the proposed substation is integral to the transmission lines and, therefore, the transmission line CPCN process supersedes the County's independent siting authority . We hold that the Commission's overarching authority to site transmission lines includes the location, specifications and conditions of substations that are integral to a proposed transmission line project that requires a CPCN. A substation is integral if, and to the extent, we find that the construction of a proposed transmission line designed to a voltage in excess of 69,000 volts cannot be constructed without it. We offer no opinion on whether the proposed Kemptown substation is integral to the proposed transmission line that determination must be made from a factual record that had not yet been developed in the life of this case, and will be for the Hearing Examiner or the Commission to make if Potomac Edison submits a new and proper application . In the course of considering whether to issue a CPCN that encompasses this proposed line and substation, or any other project, we would have the authority - as we do with respect to the lines themselves - to determine the appropriate location, specifications and conditions of the project. And although our CPCN authority would, in this regard, supersede what normally would be a local land use decision, we will weigh heavily the expertise and recommendations of local authorities such as Frederick County in our review and analysis. This is not entirely an issue of first impression. In Howard County Co. v. Potomac Electric Power Co., 319 Md. 511 (1990), the Maryland Court of Appeals held that the Commission's authority to site transmission lines preempted county zoning ordinances . Although the Court did not address the specific issue of local zoning authority over a substation, the principles underlying that decision counsel in favor of construing the Commission's substantive authority over transmission line projects to encompass all integral elements of those projects, including substations that are, as a factual matter, functionally necessary for the construction and operation of the line at issue. In Howard County, two counties attempted to apply their zoning ordinances to one of the last links in the 500 kV transmission loop around Washington, DC and Baltimore. One county issued a special exemption that would expire in three years for its 3 .7 mile section of the line, but the second county denied a request for a special exemption to allow construction of its 6.8 mile section. The Court began its analysis from the fact that the Commission, as the state-wide regulator of electricity, has "final authority" over the siting of transmission lines: In this case it is clear that, in the field of public utility service, the General Assembly intended to grant broad powers to the PSC to execute its principal duty of assuring adequate electrical service statewide . While §§ [1-101] and [2-113] of [the Public Utility Companies Article] outline the general scope of authority vested in the PSC, § [7-207] states with particularity that the PSC shall have final authority over the granting of construction permits for overhead transmission lines in excess of 69,000 volts. 14 14 Id. at 524. Against that broader regulatory backdrop, the Court analyzed the tension, and possible conflict, between the Commission's broader regulatory mission and local zoning decisions, and concluded that the Commission's CPCN authority preempts county zoning authority for transmission lines : As in County Council v. Montgomery Ass'n, [274 Md. 52, 333 A.2d 596 (1975)], the imposition of conflicting conditions associated with the construction of high-voltage overhead transmission lines could generate like complications if counties were permitted to require utilities to obtain special exception status under local ordinances. Not only could counties impose special conditions upon utilities seeking to construct transiiiission lines, but an individual county could effectively thwart the line's construction even after the utility had been granted a certificate by the PSC. And as this case demonstrates, the county regulations require consideration of some of the same factors which are implicated during the PSC proceedings for a certificate . For example, both counties in the present cases require a showing of a "public necessity" or "need" for the construction, as does § [7-207] ; both counties require that the local authorities consider potential impacts on esthetic qualities, either architectural or historic, as does § [7-207) ; both require minimization of impacts on the environment or character of the surrounding areas, as do §§ [7-207] and [2113]; and Montgomery County requires a consideration of aviation hazards, as does § [7-207] . Both counties require assessment of other more specific considerations toward granting a special exception . County regulations may legitimately serve to protect strictly local interests . However, a local governing body that has the power to altogether exclude from its jurisdiction a transmission line which provides electrical service statewide is essentially regulating the public utility in a manner that may be antithetical to the interests of the rest of the state. The legislature could not possibly have intended this result. The purpose of (the Public Utility Companies Article], and § [72071 in particular, is to control the transmission of electric power . That the legislature delegated this authority to a state agency with statewide powers, perspective, and expertise is indicative of the intent that electric utility companies respond to a centralized authority in the transmission of high-voltage electricity . The legislature, however, did not intend that 10 local interests be ignored by the PSC, as evidenced by the right of counties to actively participate in the certification proceedings. Under §§ [7-207] and [7-2081 the counties may present recommendations during the PSC public hearings, thus eliminating the potential for dual application procedures which may result in irreconcilably conflicting results, such as those presented in this case. Even so, the PSC is entitled to recognize the broader public interest of providing safe and reliable electrical service to larger areas . The counties' argument that the zoning regulations govern disparate aspects of the utility is not well founded because the regulations specify some of the same considerations included in § [7-207] ; more significantly, the local laws grant to county government the power to negate prior PSC decisions as shown in this case. When such an exercise of local authority obstructs the fundamental purpose of [the Public Utility Companies Article], we must conclude that these local powers were not intended to exist concurrently with those of the pSC.15 Unlike our decision in Section 11, the precise contours of our authority over a particular project are not defined in the statute. Put another way, there is a fair question about where, in the context of a proposed transmission line project, the "transmission line" begins and ends . The answer to that question is a factual one and could vary from project to project, depending on the size and scope of the proposed line, the way in which it interconnects with the broader electricity grid, and other issues of construction and engineering that will differ with each proposal . As a matter of principle, however, we are persuaded that the General Assembly has directed us to decide whether and bow to site a transmission line . To the extent a local authority could, in effect, veto the Commission's CPCN decision by denying approval of a necessary substation (or other component), we hold that our broader regulatory authority " Id. at 527-28 . II over the transmission line supersedes the local land use authority . Our CPCN authority wins out only with regard to the components of a proposed project that are integral to the transmission line itself. We need not and do not answer the specific factual question about whether this proposed substation (or any other component of the proposed PATH line) is integral to the proposed PATH transmission line - if and when an electric company submits a new application, we will address that question on an appropriate record . We expressly do not hold that our CPCN authority supersedes local siting authority for a electric substations, but only as to substations or other elements integral to proposed transmission line projects that are subject to our CPCN authority. As we reconcile these conflicting sources of regulatory authority, we recognize as well the critical role of local authorities and citizens in the review and analysis of transmission line projects. Should Potomac Edison file a new application, we encourage Frederick County to participate in our evening public hearings16 and as a party in the evidentiary proceedings themselves. 17 And beyond the statutory requirement that we consider the County's recommendation in deciding the CPCN,18 we recognize that land use decisions fall within the core expertise and competency of local authorities such as Frederick County, not this Commission . As such, we will give appropriate - which is to say, significant - weight to the views and recommendations of local authorities in the course of deciding whether, where, and on what terms to site the various components of a PUC § 7-207(d)(2). PUC § 7-207(e). 'PUC § 7-207(e)(1) . 12 transmission line falling within our authority. IV. Discover-yAntervention Deadline The Company, Staff and OPC all have indicated that they support setting an intervention deadline immediately . The parties further agreed that the Commission should allow discovery to start prior to deciding the preliminary issue set forth above. Given the very early stage of the proceedings, they suggested that none of the intervening parties would have been harmed if the Commission allowed discovery to begin. Having found that no application is properly on file, however, the Commission will defer any decisions on discovery and/or intervention deadlines until the Company has an opportunity to determine and exercise its next course of action . The Cormnission asks the Company to file a letter within 30 days from the date of this Order, informing the Commission whether it plans to file on its own behalf, and if so, when . IT IS THEREFORE, this day of 9h September, in the year Two Thousand and Nine, by the Public Service Commission of Maryland, ORDERED : (1) That the Motion for Expedited Decision that the Company may file a Certificate of Public Convenience and Necessity on behalf of PATH Allegheny Transmission, LLC is denied ; (2) That, for the reasons set forth above, the Application for a CPCN to construct the Maryland segments of a 765-kV transmission line and a substation in Frederick County, Maryland has not properly been filed, and thus cannot be considered ; and; and (3) That the Potomac Edison Company shall notify the Commission within 30 days whether it intends to re-file an appropriate application and, if so, when it intends to submit the application. /s/ Douglas R. A Nazarian /s/ Harold D. Williams /s/ Susanne Brogran /s/ Lawrence Brenner Commissioners IN THE MATTER OF THE APPLICATION OF THE POTOMAC EDISON COMPANY ON BEHALF OF PATH ALLEGHENY TRANSMISSION COMPANY, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT THE MARYLAND SEGMENTS OF A 765 KV ELECTRIC TRANSMISSION LINE AND A SUBSTATION IN FREDERICK COUNTY,MARYLAND BEFORE THE PUBLIC SERVICE COMMISSION OF MARYLAND CASE NO . 9199 Commissioner Brenner, Dissenting in Part: In this case, we are called upon to interpret Public Utility Companies Article ("PUC Article") § 7-207(b)(3) to determine whether The Potomac Edison Company ("Potomac Edison"), an "electric company" as defined by PUC Article I - 10 1 (h), may apply for a Certificate of Public Convenience and Necessity ("CPCN") for transmission facilities on behalf of its affiliate, PATH Allegheny Transmission Company, LLC ("PATH-Allegheny") . Because I believe our statutory responsibilities allow us to accept CPCN applications in the form most beneficial to the public and because the application currently before us is consistent with the language and intent of our statute, I would permit Potomac Edison to request a CPCN on behalf of PATH-Allegheny, and therefore I respectfully dissent solely from Section 11 of the majority opinion.' ' The merits, or lack thereof, of the proposed transmission facilities are not relevant to this initial procedural phase, and I have not considered the substance of Potomac Edison's application in its present or any future form. 1. We Have a Broad Mandate to Interpret Statutory Language in the Manner Most Consistent with the Interests of Maryland Ratepayers. Maryland law has granted this Commission broad discretion to interpret our governing statutes . We are obliged to interpret PUC Article § 7-207(b)(3) in a manner that is not counter to the interests of Maryland utility customers unless that interpretation contradicts an explicitly stated legislative intent. 2 The Court of Special Appeals articulated the significant discretion allotted to regulatory agencies as follows: fajlthough an administrative interpretation or construction of a state unemployment compensation statute is clearly not binding on the courts, where a state agency charged with administration of the state's unemployment compensation statute has construed or interpreted the statute in a particular way, the courts of the state, in recognition of the agency's expertise in the field, will give such interpretation great deference unless it is in conflict with legislative intent or relevant decisional law, or is clearly erroneous, arbitrary, or unreasonable . 3 Additionally, our enabling legislation requires us to exercise this broad discretion to "promote adequate, economical, and efficient delivery of utility services in the State without unjust discrimination ."4 To this end, the General Assembly provided us with numerous explicit powers as well as all "implied and incidental powers needed or proper to carry out [our] functions ."5 Therefore, in the absence of an explicit legislative statement to the contrary, I believe we must interpret statutory language in the manner most consistent with the best interests of Maryland ratepayers. Even more urgently, we must avoid an interpretation ' Aviation Admin. v. Noland, 386 Md. 556,572 (2005) ("An administrative agency's interpretation and application of the statute which the agency administers should ordinarily be given considerable weight by reviewing courts .") 3 Westinghouse Elec. Corp. v. Callahan, 105 Md. App . 25, 35 (1995) (quoting 76 Am.Jur.2d Unemployment Compensation § 17 at 761 (1992) . See also, Eddie Adamson v. Correctional Med. Sens., Inc., 359 Md. 238, 265 (2000) ("While it is true that an agency's view of the law does not bind this Court's interpretation of the statutory scheme, we have noted before that an agency's expertise in its field is Farticularly persuasive.") PUC § 2-113(a) . PUC § 2-112(b) . that harms Maryland ratepayers with no countervailing benefit to any constituency. As discussed below, I believe Potomac Edison has established that accepting its application to review for a possible CPCN on behalf of its affiliate will have no negative effect upon the rates paid by the public and may result in direct savings to ratepayers if the proposed transmission facilities are ultimately approved . 2. Allowing Potomac Edison to Apply for a CPCN on Behalf of PATHAllegheny Furthers the Public Interest Consistent with Our Broad Mandate. Potomac Edison's application was filed on May 19, 2009, and included the following pre-filed written testimony of Mr. Mark Joensen, the Director of Finance for the holder of Allegheny Energy, Inc.'s ("Allegheny Energy") interests in PATHAllegheny : . . . the [PATH LLC] structure allows for separate equity interests through the subsidiaries (AET PATH and AEPTHQ created by Allegheny and AEP and also allows PATH-WV and PATHAllegheny to seek more advantageous debt financing on a project finance basis for their respective interests in the PATH project . We expect to achieve more favorable terms by issuing debt at the level of PATH-WV and PATH-Allegheny, since the exposure of each will be limited to the specific transmission assets and operations of that entity. Finally, the creation of PATH LLC and its subsidiaries permits Allegheny and AEP to efficiently allocate the financial costs and economic benefits of the PATH 6Project in accordance with their underlying business agreements . The PATH Project is a j oint venture between American Electric Power Company, Inc. and Allegheny Energy to construct approximately 276 miles of transmission line through Maryland, Virginia and West Virginia . To this purpose, PATH consists in part of two operating companies - PATH-Allegheny and PATH West Virginia Transmission Company LLC. These two companies were created to finance, construct, own, operate and maintain the Project. ' Direct Testimony of Mark Joensen at 10. Additionally, Mr. Joensen stated that Allegheny Energy created the PATH-LLC corporate structure to, inter alia, "allow for business services to be provided efficiently to PATH by Allegheny, AEP, and third-party vendors",7 and "provide for the efficient ownership, oversight and management of the PATH Project by the joint owners, with a division of the investment in the project consistent with Allegheny and AEP's business agreement."8 Currently, no party disputes these proffered benefits to the Maryland public. If the evidentiary hearing on the merits reveals these claims to be specious, this Commission is free to issue the CPCN exclusively to Potomac Edison, Conversely, if discovery reveals that the administration of the CPCN through PATH-Allegheny will result in tangible benefits to Maryland consumers, I believe our statutory mandate militates that we issue the CPCN in the manner currently requested . The narrow interpretation urged by the majority, while consistent with the language of PUC Article § 7-207(b)(3), is not mandatory in light of the wide discretion we have to condition the issuance of any CPCN. If Potomac Edison had applied for a CPCN on its own behalf, and the evidentiary hearing on the merits revealed that the creation of a single-purpose affiliate like PATH-Allegheny would significantly benefit Maryland ratepayers, our authority pursuant to PUC Article §§ 2-112, 2-113 and 7-207 would permit us to grant the application conditioned upon the establishment of the corporate structure presented to us currently . In summary, I believe 1) our broad discretion, 2) our mandate to interpret our statutory language in a manner that would inure to the greatest benefit of Maryland Id. at 6. Id. at 7. ratepayers, and 3) the likely savings that would result from constructing, operating and owning the transmission lines through an affiliate of Potomac Edison, require us to interpret PUC Article § 7-207(b)(3) broadly in the absence of an explicit prohibition. As discussed below, I find no prohibition of the broad interpretation urged by Potomac Edison and our Staff. 3. PUC Section 7-207 Does Not Prohibit an Electric Company from Applying for a CPCN on Behalf of an Affiliate. PUC Article § 7-207(b)(3) states that (u]nless a certificate of public convenience and necessity for the construction is first obtained from the Commission, an electric company may not begin construction of an overhead transmission line that is designed to carry a voltage in excess of 69,000 volts9 or exercise a right of condemnation with the construction. PUC Article § 1-101(h)(1) defines an electric company as "a person who physically transmits or distributes electricity in the State to a retail electric customer." Potomac Edison clearly falls within this statutory definition. I find nothing in § 7-207(b)(3) or elsewhere in Maryland law that expressly prohibits Potomac Edison from requesting a CPCN on behalf of an affiliate . Although this provision prohibits an electric company from constructing an overhead transmission line without first obtaining a CPCN, it does not dictate how the lines will be constructed, operated or owned, thereby leaving to our discretion the most beneficial means of accomplishing this . This broad interpretation will have little practical effect on the administration of the CPCN because Potomac Edison and PATH-Allegheny are both wholly-owned subsidiaries of Allegheny Energy . Allegheny Energy will therefore have complete control over the operation of the CPCN-covered activities regardless of which entity is 9 It is undisputed that the transmission line at issue would exceed this statutory threshold. the official recipient of the certificate. Imposing potentially increased debt financing costs without changing the actual administration of the CPCN would be window dressing that furthers no legislative purpose . Although we could construe § 7-207(b)(3) narrowly, we are not required to do so, and I can discem no benefit from doing so. To the contrary, as noted above, narrowly defining "electric company" may underntine our statutory mandate to ensure that this transmission line, if it is approved and built, is in the best interest of Maryland ratepayers. Additionally, as Potomac Edison has alluded to on a number of occasions in its briefs, section 215 of the Federal Power Act of 2005 authorizes FERC to "issue one or more permits for the construction or modification of electric transmission facilities in a national interest electric transmission corridor designated by the Secretary" whenever it finds that a transmitting utility doesn't qualify for a State permit because it does not serve end-use customers in the state. 10 Therefore, if we reject Potomac Edison's application, PATH-Allegheny might re-apply directly at the federal level. Unlike another basis for preemptive federal "backstop" siting authority, there is no minimum time period that must ran before PATH-Allegheny may do so. This is at least a possible outcome, and neither the majority nor any party to this proceeding contends that the public interest would be better served if this Commission loses its siting and construction authority over this line. " '0 16 U.S .C . § 824p (b) . " I agree with Section III of the majority's opinion that, if the Kemptown substation is found after hearing to be integral to the transmission lines, our CPCN authority pre-empts the authority of the local government (Frederick County in this case), but we and the County may lose jurisdiction over the substation if FERC takes over the permit process . The unnecessarily cramped reading of this statute urged by only one Intervenor (and supported somewhat reluctantly by Office of the People's Counsel ("OPC")), 2 does not benefit any party to these proceedings, including the Sierra Club, who will almost certainly oppose this CPCN just as strongly if Potomac Edison re-files its application on its own behalf. Rather than potentially inflict higher electric bills on Maryland consumers and potentiaUy abdicate our responsibility to consider whether to permit the PATH project solely to maintain the purity of the definition of "electric company", I would adopt the position set forth in Commission Staff s brief and interpret "electric company" to also include an electric company filing on behalf of an affiliate wholly owned by the same parent. 13 This would not be the first time we've defined an "electric company" broadly to further an underlying public interest . In Re Potomac Elec. Power Co., 83 Md. PSC 19 1, 195 (1992) ("Pepco" case), we exercised our broad authority to conclude that a nonutility was a "jurisdictional electric company" and therefore subject to the CPCN provisions of PUC law. We did so because of the public interest involved and the plausibility of the interpretation necessary to achieve that public interest . I see no reason to unnecessarily limit our interpretation in the present case. PATH-Allegheny has voluntarily submitted to the jurisdiction of this Commission for the purpose of administering the requested CPCN 14 , and no party disputes that we already possess subject matter jurisdiction over the overhead lines anyway. Contrary to " The strongest language OPC offers against the current application is that "OPC recognizes and understands the arguments of the Company, PATH-Allegheny and Allegheny (Energy] regarding the potential benefits of the corporate structure of PATH LLC as well as the benefits to residential ratepayers of the Commission's oversight and jurisdiction regarding the Application and, if the CPCN is granted, the PATH Project . OPC continues, therefore, to be willing to consider other alternatives or mechanisms that will satisfactorily resolve the legal issues raised hereinabove ." OPC Initial Brief at 3. 13 Staff Initial Brief at 4. " Affidavit of James R. Haney, Appendix B to Potomac Electric's Application, at 3. the arguments offered by the Sierra Club, I do not see this as an impermissible extension of our subject matter jurisdiction . As discussed above, I believe we should adopt a broad interpretation of "electric company" to ensure that we can evaluate the most publicly beneficial manner of constructing this transmission line . By requiring the affiliates of the electric company or the transferee of the CPCN (see infra) to submit to our jurisdiction on matters related to the subject of the CPCN, as PATH-Allegheny has here, we can allay any concern that a broad definition of "electric company" or a broad interpretation of Potomac Edison's right to transfer its CPCN would remove the administration of a CPCN from our regulatory oversight. Requiring such a submission is no different than any other condition we might attach to the granting of a CPCN to protect the public interest, 15 especially when we already possess subject-matter jurisdiction over the proposed line. 4. The Public Utility Companies Article Does Not Prohibit Potomac Edison from Transferring Its CPCN to Its Affiliate. In their Briefs, both Sierra Club and OPC opine that this Commission should not permit Potomac Edison to transfer its CPCN to PATH-Allegheny because doing so would allow Potomac Edison to accomplish indirectly what this Commission could not order directly. However, I find the reverse reasoning to be more persuasive : the PUC Article does not prohibit Potomac Edison from transferring its CPCN to PATH-Allegheny (with Commission approval) . Therefore, we should interpret PUC Article § 7-207(b)(3) broadly because a narrow reading would only force applicants to reach the same result indirectly . If this Commission feels bound by the precise language contained in PUC " Md. Code Ann ., Cis . & Jud . Proc. § 6-102(a) states that a judicial body "may exercise personal jurisdiction as to any cause of action over a person domiciled in, served with process in, organized under the laws of, or who maintains his principal place of business in the State." However, section 6-102(b) provides that the former provision "does not limit any other basis of personal jurisdiction of a court of the State", and Maryland case law holds that an individual or entity may voluntarily submit to the jurisdiction of Maryland courts . See e.g., Beyond Sys., Inc. v. Secure Medical, Inc., 168 Md. App . 186, 189 (2006) (noting that lack of personal jurisdiction may be cured by waiver or consent). Article § 7-207(b)(3), it should feel similarly unbound by the absence of any language prohibiting or limiting the transfer of CPCNs, subject to Commission approval. This Commission has previously approved the transfer of CPCNs after determining the transfer to be in the public interest . For example, Request of Clipper Windpower, Inc. for Consent to Transfer of the Criterion Wind Energy Project, case No. 8938 (2007), described how an applicant could transfer its interests : [T]he Applicant shall not transfer ownership or control of the project so as to divest the Applicant of its ability to control the construction or operation of the project without the written consent of the PSC which shall not be unreasonably withheld, conditioned or delayed . A proposed successor shall be approved if it has sufficient financial ability (or has such financial ability guaranteed by a parent company) and experience (or will engage an operator with experience) to operate the project in compliance with this CPCN and has satisfied .the PSC that it is otherwise reasonably capable of complying with the terms and conditions of the CPCN." In the absence of any statutory limit upon CPCN transfers, we should not unnecessarily create one, especially when the transfer furthers the public good. Therefore, I would permit the transfer of Potomac Edison's CPCN to an affiliate, wholly-owned by the same corporate parent. We can evaluate whether future proposed transfers of other CPCNs to affiliates are in the public interest on a case-by-case basis. A CPCN is no different than any other license. It is simply a "right or permission granted by some competent authority to carry on a business or to do an act which, 16 Proposed Order of Hearing Examiner, Case No. 8938, App . B at 72 (2003) (adopted by the Commission in Order 78354). Issues of transfer and/or delegation also have arisen within CPCN proceedings themselves. See e.g., Notice of Entry into a Letter Agreement Regarding Development and Ownership of the Electric Power Generation Facility near Rock Springs, Maryland, Case No. 8821 (2001) (assigning and delegating to initial applicant via letter agreement any and all of second applicant's assets, rights, claims, duties, obligations, and other interests in the project) ; See also, Supplemental Information Amending Application for a Certificate of Public Convenience and Necessity, Case No. 8821 (1999) (amending initial CPCN application to include a second applicant); Letter Requesting that the Commission Take Certain Ministerial Actions in Connection with [Panda's] Plans to Transfer the Transmission Facilities, case No. 8488 (1996) . without such license, would be illegal . ,,17 Under Maryland law, the approving government agency may authorize the transfer of a license unless the text of the licensing statute explicitly prohibits the transfer . The Maryland General Assembly clearly knows how to prohibit transfers, but such a prohibition is noticeably absent from PUC Article § 7-207(b)(3) ." Not only do Commission precedent and Maryland license law support the transferability of CPCNs, but other states also approve such transfers when in the public interest .19 Additionally, although Maryland's PUC Article does not directly address the transferability of CPCN licenses, it does strongly suggest that they may be transferred subject to Commission approval. PUC Article § 5-202(l) provides that, without prior authorization of the Commission, a public service company may not assign, lease, or transfer a franchise or right under a franchise, Section 5-202(2) applies the same requirement before a public service company may "enter into any agreement or contract that materially affects a franchise or right under a franchise". The transfer of a CPCN or a transmission line may come within the scope of these provisions and, when they do, § 17 14 Md. L. Encyc. Licenses § 1 ; See also, Robert T. Foley Co. v. Wash. Suburban Sanitary Comm'n, 283 Md. 140, 153 (1978)(finding that the State agency's approval of developers' applications to connect new housing units to existing district water and sewer service gave rise to a license); Md. Code Ann ., Bus. Reg. § 17-201 (listing 26 types of licenses) . " See, 51 Am. Jur. 2d Licenses and Permits § 97; Md. Code Ann ., Bus . Reg. § 17-1009 ("A State junk license is not transferable."); Md. Code Ann ., Envir . § 7-241 ("A low-level nuclear waste facility permit is not transferable."); Id. § 9-1014(a) ("A water quality laboratory certification is not transferable.") 19 See e.g., California Public Service Commission Website : "When a certificated nondominant carrier transfers its CPCN to its existing parent, subsidiary, or affiliate, the carrier should send the Communications Division a letter stating so. The tariff should be updated as if this was only a company name change."; The Application of Phyllis J. Johnsondlbla Lady Bug Tours, for temporary approval to allow the Mountain Guides, Inc., db/a Scenic Mountain Tours, to assume operational control of certificate ofpablic convenience and necessity, PUC No. 46968 (Public Service Commission of Colorado, Decision No. CO 1 -0057) ; In the Matter of the Transfer of Operating Authority of Touch America Services, Inc., to Touch America, Inc. (Utah Public Service Commission, Docket No. 0 1 -2310-01 (200 1) (approving transfer of CPCN from subsidiary to parent) 10 5-104 allows us to approve the transfer if it "is consistent with the public convenience and necessity ." Therefore, if Potomac Edison had applied for a CPCN in its own name and thereafter sought to transfer that CPCN to PATH-Allegheny pursuant to § 5-202(l) or (2), we would evaluate whether that transfer was consistent with the public convenience and necessity pursuant to § 5-104(a). This is precisely what Potomac Edison is asking us to do initially, and, for the reasons stated above, I believe the public interest is best served by accepting and conducting a thorough review of the application in its current form. In summary, Potomac Edison's right to transfer its CPCN to PATH-Allegheny, subject to our approval, is supported by 1) this Commission's own precedent, 2) established Maryland license law, 3) the practice of other states, 4) public policy, and 5) our own authority pursuant to PUC Article §§ 2-112, 2-113, 5-202 and 5-104. Therefore, if this Commission prohibits Potomac Edison from applying for a CPCN on behalf of its affiliate, I believe we should evaluate the public interest in the inevitable transfer to PATH-Allegheny during the course of the CPCN review process, 5. Conclusion Based upon the above, I would review Potomac Edison's application as filed, reserving our right to either 1) permit or order the transfer of the CPCN to PATHAllegheny, or 2) issue the CPCN exclusively to Potomac Edison based upon which outcome the evidence demonstrates to be most consistent with the public convenience and necessity. /s/ Lawrence Brenner Commissioner 11
© Copyright 2024