Process development at Veidekke

Process development at
Veidekke
Emile Hamon Business developer
Emile Hamon
• From Sweden, wife and 2 children
• Visiting CIFE fellow at Stanford, 4 months
• Business developer at Veidekke, one of Scandinavia’s leading
construction companies (CIFE member) (employed since
2010, consultant with Veidekke since 2004)
• Backgound: M.Sc, Civil Engineering, Worked as Logistics and
Management Consultant, Consultant and advisor to housebuilding companies.
• Specialised on Lean Construction methods, Building Systems,
Process development, VDC
Topics for this presentation
• Veidekkes Production System
– Project room
• VDC
– Visual planning
– On site logistics and safety plan
• MI – employee involvement
• VMAX – industrialized building
system for houses
VPS
– Veidekke’s Production System
VPS – Veidekkes Production System
”The framework”
A project management system
VPS – Veidekkes produktionssystem
Continuous improvements
System was introduced in March 2012 and so far we have
received over 200 suggestions of improvements
Project room
For each new project a project room is created for content
management, sharing and search for information
• Share files and documents
• Same structure as VPS
• Apps for:
–
–
–
–
–
–
–
Shortcuts to all Veidekke’s systems (VPS, economy systems etc)
Weather forecast
Schedule (task, completion)
Calendar (logistics, meetings)
Daily record / Notebook
Project members
Phonebook
VDC – Virtual Design &
Construction
VDC – Virtual Design & Construction
Visualisera beslut
Genomför
kollisionskontroller
ICE - Kort tid mellan
fråga och svar
Dynamiska
APD-planer - HMS
i ett tidigt skede
Objektsbibliotek som
byggs upp över tiden
Modellerna ut på arbetsplatserna 3D, 4D och 5D
SmartBoards för
interaktiva möten
Dynamiska APD-planer
• Kartotek med ca 200 3D objekt
• Uppdelat på följande kategorier:
Dynamiska APD-planer
Återsamlingsplats
Dynamisk APD-plan är
ett visualiseringsverktyg – där vi snabbt
och lätt kan
kommunicera HMS med
beställare och andra
intressenter!
Etablering
Första hjälpen och bår
Nästa steg är att
fortsätta jobba
med APD-planen
per våning
Leveransmottagning
VDC-modellerna används på veckomötet för att
öka förståelsen för vad som ska byggas!
VDC – Virtual Design & Construction
• Skapa delaktighet från dag 1 – Ingen kör sitt eget race
• Mötesteknik (ICE) där alla sitter och projekterar tillsammans
• Genom samordning av modellerna säkerställer vi att alla ligger
i fas
• Rätt förutsättningar för produktionen i och med bättre kvalitet
på handlingar
• Produktionspersonal säkerställer bland annat HMS, rätt
produktionsmetoder och erfarenhetsåterföring
• Tillförlitliga handlingar genom kollisionskontroller
• Effektivare projekteringsprocess – kortare tid mellan fråga och
svar
• Gå från 2D till 3D, 4D och 4D+
MI – Medarbetarinvolvering
/ Employee involvement
(influenced by Last Planner)
Teamwork when planning the
project i essential
Look a head schedule with
names exactly who does what
Infoline get out
the message to
all involved!
We visulize all
relevant information
• Production
schedule
• Weekly schedule
• On site logistics
plan
• PPC
• Delivery
schedule
Assembly and work
instruction
Four planning levels
Master schedule, Production
Schedule, Look a head schedule
och Weekly schedule
PPC on the weekly
schedule
Dynamic on site logistics plan
Weekly meeting where everyone gets
involved in the weekly schedule – will
I meet my deadlines or not?
Medarbetarinvolvering
MI utgår ifrån att byggprocessen är komplex
och att en tidplan förändras under projektets
gång:
• Planläggning bedrivs därför med kort tidshorisont – dag till
dag planering
• Sker förberedelserna av arbetet med så kallad
förhindersanalys av aktiviteterna
• Mäts PPU, vilket är ett mätetal som visar hur bra vi är på
att planera
• Jobbar systematiskt med involvering och åtaganden
19
15.01.2013
Master schedule
What will be done
Will
When and how it should be done
Tactic
Can
Seven flows / prerequisites
When and if work can we executed as
planned
Weekly schedule
It will be executed as planned
Will
Client
Prodcution schedule
More detailed then Master
schedule
Look a head schedule
15.01.2013
20
Metoden
Strategisk Nivå
Taktisk Nivå
Operativ Nivå
Huvudtidplan
Produktionstidplan
Rullande tidplan
Veckotidplan
• Övergripande
planering
• Milstolpar
• Kontraktshandling
• Mer detaljerad
• Byggmetoder
• Kritiska linjen
• Testa logiken
• Identifiera eventuella
hinder
• Vem är ansvarig för vad
• Veckovis uppdatering
• Resursstyrning
• Detaljerade
arbetsbeskrivningar
• Decentraliserad
planering av bemanning
• Mäta PPU
• Orsaker till avvikelser
Justering av tidplan genom att
mäta och analysera PPU samt
avstämma och beakta
erfarenheter från produktionen
A weekly meeting
– Everyone gets the same information at the same time!
MI involves workers and sub contractors in the
planning of the project on a weekly basis
All relevant project
information is visualized!
25
15.01.2013
MI
It gives you a motivated crew!
26
MI is about
working
smarter!
Not harder!
27
15.01.2013
- In Lean production you have a
standard that you always try to
improve – we had to set that
standard in order to start the
improvement process…
Assembly and work instructions
- for safer and more efficient work
Assembly and work instructions
- for safer and more efficient work
You always need to challenge your standard in
order to improve!
VeidekkeMAX
Industrialized building system
VeidekkeMAX
Process platform
– Lean Construction
VPS
– Veidekkes produktionssystem
VDC
MI
– Virtual Design & Construction – Medarbetarinvolvering
Technical platform
- VMAX
Hildedal
Hildedal Park
J. Lessing
Influenced by the Swedish car industry’s use of technical
platforms we developed a technical platform from which we
can configure unique houses
VeidekkeMAX
Traditionally
installation work
involves many
different trades and
the tasks often are on
the critical path
The installation
module gives us few
or no hand overs and
we speed up the
whole process as we
shorten the critical
path activities
Traditional
Fast track
Fast track – Short construction time
means that capital gets to work quicker
VeidekkeMAX