Inception report to Community Managed WASH Project (CMP) Implementation Manual Development

Inception report to
Community Managed WASH Project (CMP)
Implementation Manual Development
-Final12th March 2014, Addis Ababa, Ethiopia
Table of Content
1.
2.
Introduction ......................................................................................................................................................... 1
Objective, scope and inputs of CMP manual development ................................................................ 3
2.1 Objective and scope ................................................................................................................................... 3
2.2 Inputs .............................................................................................................................................................. 4
3. Methodology ........................................................................................................................................................ 5
3.1 Preliminary Document Review ............................................................................................................ 5
3.2 Meetings and Discussions ....................................................................................................................... 6
3.3. Inception workshop ................................................................................................................................ 7
4. Preliminary standpoints Main questions and ............................................................................................ 7
4.1 Principles and core elements of CMP ................................................................................................. 7
4.2 Fund Channelling and Financial Management ................................................................................ 7
4.3 Institutional Arrangement ...................................................................................................................... 9
4.4 Key issues raised ........................................................................................................................................ 9
5. Key challenges...................................................................................................................................................10
6. Team, work plan and deliverables ............................................................................................................11
6.1 Consultancy team and Taskforce .......................................................................................................11
6.2 Work plan and deliverables .................................................................................................................12
Annex 1:
Annex 2:
Suggestions for accommodating CMP in the Programme Operation Manual (POM)
of the OWNP.
Additional reflections of the consultants towards CMP in POM
1.
Introduction
The Government of Ethiopia (GoE) is being implementing the Universal Access Plan (UAP) and
Growth and Transformation Plan (GTP) for improved water supply, sanitation and hygiene (WASH).
The final aim of this plan is to achieve universal access to safe water for 98.5% of the country’s
population and 100% coverage of basic latrine by 2015. Despite the significant acceleration in
coverage and a relatively favorable policy environment, a considerable amount of work needs to
be done to achieve the Ethiopian Government (GoE) Growth and Transformation Plan (GTP)1.
For the substantial acceleration towards reaching the UAP/GTP targets, the government is
integrating innovative and less expensive models with the conventional ways of implementation.
An external evaluation undertaken by the Water and Sanitation Program in 2010 2, established that
CMP approach, previously called Community Development Fund (CDF) is highly efficient, cost
effective and sustainable compared to other WASH implementation modalities.
Up to this point, the key feature of CMP is that it transfers funds and project management
responsibilities for physical construction directly to communities via a micro credit institution. The
communities, through Water, Sanitation and Hygiene Committees (WASHCO), are responsible for
the full development process through planning, financial management, implementation and
maintenance. The unique feature in CMP approach is that the WASHCO manages not only
community-generated funds but also the government subsidy provided for capital expenditures.
This approach/model is pioneered and developed in Amhara Region. Because of the added values
of this approach, the Government of Ethiopia (GoE) has taken the initiative to scale up with the
intention of including CMP-based implementation into the National WaSH Program (WASH
GTP/UAP) for its wider application. CMP is now being scaled up into other regions such as
Benishagul Gumuz, Tigray, Oromiya and SNNPR.
In September 2013, the Ethiopian government launched its (multi-sectoral) Sector-Wide Approach
(or SWAp) for water, sanitation and hygiene (WASH) called the One WaSH programme. The plan
brings together four ministries- Water Resources, Health, Education, and Finance & Economic
Development- in a bid to transform the way water and sanitation services are delivered to the
people of Ethiopia. It is a further step in the gradual development of the essential policies,
guidelines, financing and coordinating mechanisms to deliver universal access to water and
sanitation, and to sustain services, across the country. It consolidates planning, budgeting and
reporting activities of WASH in a broad sector wide approach with the catchphrase “One plan –
one budget – one report”, highlighting the harmonizing of WASH efforts around the
country. OWNP reflects the ambition of contribution significantly in meeting both the Growth and
Transformation Plan (GTP) and Millennium Development Goals (MDG) targets. With One WASH,
management of water and sanitation is planned to be better, along with a consolidated WASH
account at the Ministry of Finance and Economic Development.
There are many innovations in the OWNP, one of which is the inclusion of Community Managed
Projects (CMP) as an approach and component part of the OWNP. CMP is an implementation
modality alongside the service delivery models of Self-supply (SS), Woreda-Managed Projects
1
WASH Implementation Framework (WIF), 2013
‘Mainstreaming the Community Development Fund Financing Mechanism’, Final Evaluation Report, Water
and Sanitation Program, April 2010
2See
1
(WMP), NGO projects and multi-village schemes.
The Woreda Managed Project (WMP) Approach Implementation Manual has already been tested
and implemented through the support from WB, DFID and AfDB. The Self-supply Implementation
Manual is under development by the Self-supply Working Group (SSWG) and is being tested in the
regions piloting and accelerating Self-supply. The initial Community Managed Project (CMP)
Implementation Manual has been developed and Implemented by COWASH and FinnWASH in 45
woredas using MFIs as financial intermediaries in transferring funds to the community and
communities have been procuring the goods, materials and services for their projects. In 2006 EFY
COWASH and FinnWASH will implement CMP in 70 woredas.
The main strategy set in the One WaSH plan is to develop and implement low cost technologies as
much as possible. According to the One WaSH National Program (OWNP) document the number of
communal and institutional water and sanitation facilities are needed to be constructed:
Item
Number of Water Schemes
Communal water points
Rehabilitation of water points
Town water supplies
Self Supply schemes
Schools
Health Facilities
55,865
20,010
777
42,529
22,985
7,772
The implementation strategy,
defined in the revised WASH
Implementation Framework
(WIF) and signed by the four
ministries of Water, Health,
Education and Finance would
follow
an
accelerated
demand responsive stepped
approach
in
which
awareness creation and
capacity building would be
followed by implementation.
Number of new Sanitation
Facilities
6,724,676
6,122
7,037
The WIF signed in March 2013 defines the CMP approach as follows:
In the CMP, the representative of the user-group (WASHCO or
Institutional WaSH Committee) – i.e. the Community is the Project
Manager. Allocated funds are transferred to a special CMP account
through a financial intermediary (e.g. micro-finance institution)
with WWT authorization, are withdrawn by community
signatories for approved expenditures on water point
construction/upgrading. The WASHCO is directly responsible for
contracting, procurement, quality control and financial
accountability – to the community and to the Kebele and Woreda
Administrations. There is no hand-over. The user-community
“owns” the project from the beginning. Basically CMP is
characterized that communities implement and manage projects.
In terms of technology simple and low cost schemes will be the priority area for implementation.
Higher levels of technology service are also for consideration, albeit this will not receive major
focus in the revised CMP Implementation Manual at this point of time. Sustainability of the
services through focused and improved operation and management (O&M) of schemes is also one
of the strategies.
It is assumed that 60-70 % of the communal and Self-supply targets can be implemented by using
the low-cost technologies. The CMP approach is specifically designed for low-cost technology
implementation. CMP approach is to improve the implementation efficiency, increase the
community contribution and ownership and accordingly improve the sustainability and
functionality of the WASH facilities.
2
In this ambition, the OWNP and the innovations in financing in the sector also face some serious
challenges. Ethiopia is home to the CMP approach, based on over 10 years of piloting and now in a
nationwide scaling-up phase, which is widely cited as a good example for its use of MFIs to route
money to communities to build their water schemes.
With the OWNP however, the Ministry of Finance and Economic Development (MoFED) has
requested that the Public Funds in CMP shall be transferred to communities through Woreda
Finance Office and the use of MFIs is not accepted. Furthermore, the Public Finance and
Procurement Directives do not recognize community-groups as eligible organizations to receive
and use Public Funds. Therefore the existing CMP Implementation Manual for Communal and
Institutional Water and Sanitation implementation is to be revised to follow the Public Finance
and Procurement Systems. These amendments will facilitate the application of CMP
implementation modality in the enactment of One WASH National Program.
The State Minister of MoWIE has requested the preparation of the CMP Implementation Manual
that is based on the Public Finance and Procurement Management Systems of Ethiopia. The
question is whether -or to what extent- this can be complied to, and how this would impact the
CMP modality. Questions and concerns arise, such as: Can CMP maintain core modality of
community institutional representatives (such as WASHCOs or PTAs) procure and manage their
CMP schemes?; In aligning CMP to Public Systems, what would the future difference between
CMP and WMP?; If CMP would adjust or compromise on various essential key characteristics of
communities management and ownership , is there a ‘risk’ that along the way, CMP goes offbudget with donors preferring to fund CMP through MFIs but then government funding not being
routed this way?
These questions impact the objective, scope and input of CMP manual development, described in
the next section.
2.
Objective, scope and inputs of CMP manual development
2.1
Objective and scope
The objective of this assignment is to review the existing CMP manuals and guidelines and prepare
a revised Community Managed WASH Project (CMP) implementation manual based on the
National WASH Implementation Framework, current improvements of the approach, components
of WASH and feedback from national and regional level consultations of the relevant partners.
The scope of the consultancy is to focus on considering institutional WASH (sanitation and hygiene
facility construction and its management for and by school and health institutions), community
sanitation and hygiene components, and worked-out funding modalities in which the communities
through Water, Sanitation and Hygiene committees (WASHCos) are responsible for the planning,
financial management, implementation and maintenance of their WASH facility. Community
contracting includes concepts of pricing and legalization, supply chains and financial viability of
WASHCos.
The CMP Implementation Manual is to provide clear guideline if and how (to what extent)
communities and their representative bodies such as WASHCOs and PTAs can implement the
water supply and sanitation facilities themselves using the Public Funds transferred to them from
3
the Woreda Finance Office. There is need for innovation and finding solutions towards this
management model.
In the CMP Inception workshop, the MoWIE’s request was not to detail a CMP accommodating
higher level of technical service (including service associated with piped water supplies and drilled
boreholes). In this initial stage, the revised CMP implementation manual is to focus on low-cost
simple technologies, acknowledging rapid and high increase in coverage levels.
2.2
Inputs
The inputs would be based on meetings, review of existing CMP implementation guideline,
formats and related documents, reports and follow-up discussions with (Regional) CoWASH teams
and partners who are currently implementing CMP both at national and regional level. Focus
group discussions and in-depth and interviews with selected national regional, zonal and woreda
CMP staff will be part of information gathering and analysis.
The following inputs were proposed as per the ToR:
I.
Review the existing CMP implementation guideline and other WASH implementation manuals
including WIF as to revise the implementation manual to address sanitation and hygiene part
of WASH. This revision will be done at the level of community based sanitation and hygiene
works, as well as for institutional WASH. Illustrate and example other possible funding
mechanisms other than what is stated in the current CMP implementation guideline with their
cons and pros of each recommended funding modalities;
II. Review the current CMP formats and develop the revised formats with short size;
III. Prepare trainers’ guide for each manual, which will help to make the trainings more active and
live (participatory learning). The training guide is to e.g. highlight different trainings to be
provided at different levels, propose who are trainees, identify contents of the training, and
describe training modality. The guide coming into about will support the future preparation of
the actual training manuals;
IV. Align these implementation modalities of the WIF and current CMP implementation
approaches with One WASH Program Approach;
V. Review the existing spare part supply systems implemented with different organizations in the
country as well as international experiences and recommend the best option(s) to be
integrated with CMP implementation modalities;
VI. Review different approaches to set the minimum amount to be contributed by communities
and the required follow up by WWO experts in continuing the O&M fund contribution for each
scheme type;
VII. Review the existing artesian payment systems and indicate the minimum payment scheme for
the required activities for each type of scheme; investigate the advantage of partial contract
agreement where WASHCOS give only labour contract over full contract agreement where
WASHCOS give labour and all procurement to be made by artisans/contractors;
VIII. Review the different regions experience on WASHCO legalization and recommend the best
lessons that should be replicated in other regions;
IX. Investigate if there is any means to “legalize” the community procurement in the
WASH implementation and seek examples where community procurement is done, how well it
has worked and how it can be made possible in GoE financed WASH implementation;
X. Assess the funding modality (MFI as financial intermediary in fund transfer) and document that
the use of MFIs in the fund transfer is legal and recommended.
4
As mentioned, at request of the MoWIE, the initial input ‘Review experiences of CMP applications
including levels of service associated with piped water supplies and drilled boreholes and
recommend on the methodologies on how CMP address higher schemes’ is not priority at this
stage and will not be detailed in the revised CMP implementation manual.
3.
Methodology
Desk review, in-depth interviews, discussions, report writing and presentations will be taken up as
to assure a high-quality review of the existing CMP manuals and guidelines and prepare a revised
Community Managed WASH Project (CMP) implementation manual.
The added value of accommodating fieldwork as part of this assignment was discussed in the
Inception workshop. For time constraints as well as for acknowledging one of the team members’
substantial CMP implementation- and research exposures in the field over the past years (which
includes discussions with regional, zonal and woreda WASH offices and WASHCO members), no
field visit will be undertaken. Instead, in a later stage, a complementary workshop in a Region will
be arranged as to review and discuss the draft CMP Implementation manual.
With regard to ownership and sustainability, the MoWIE has assigned the MoWIE Rural Water
Supply Team Coordinator (Ato Tamene Hailu) supporting to the Community-Managed Approach as
part of One WaSH National Programme.
The MoWIE promised effort to involve MoFED along the process of drafting and approval of the
revised CMP Implementation manual, which includes invitation of MoFED to the Inception and
Manual review workshops.
The upcoming section provides an overview of the activities undertaken in the inception report
phase by the consultants, as to acquire pertinent information and to arrive at a full understanding
of the tasks to be addressed. Additionally, brief highlight on consultative meetings with the key
stakeholders and review of primary and secondary have been undertaken is presented here
under.
3.1
Preliminary Document Review
The Consultant has been given access, through the COWASH Project, Ministry of Water, Irrigation
and Energy to relevant documentation and supporting materials necessary to commence the
study. These documents have been reviewed where required, but primarily, in overview since it
will be studied, reviewed and updated in greater detail later.
The following documents are part of the review:
 CMP Fund Management Guideline, 2012
 CMP Fund Management Guideline Annexes,2012
 CMP Implementation Manual for Manual Drilling,2012
 CMP Implementation Manual for Institutional Sanitation,2012
 CMP Implementation Manual for Institutional Sanitation Annexes,2012
 CMP Communication Strategy,2011
 Communication and Training Methodology Guide,2011
 Mainstreaming cross cutting issues in CMP, 2011
5






















CMP and gender step by step guide
WASHCO legalization Proclamation for Benishangul Gumz Region
WASHCO legalization Regulation for Benishangul Gumz Region
Rural Water Supply O & M management manual for point water supply
Report on Mainstreaming CMP in to OWNP in line with Public Finance regulation of Ethiopia,
2013
Generic CMP Financial management Guideline , 2012
Guideline For The Implementation of High Technology Water Supply Options In CMP, 2013
Concept Paper on Women and Youth Led Supply Chain RWASH, 2013
COWASH M &E Framework , 2011
COWASH M&E Tools, 2011
RWSEP Reinvestment Finance Study, 2005
Evaluation and Mainstreaming of CDF, 2010
OWNP POM Zero Draft, 2014
OWNP Program Document, 2013
WIF Summarized and Signed Document, 2013
Public Procurement Directive of FDRE, 2010
Financial administration of the Federal Government, Regulation, No. 190/2010
Federal Government Accounting Guideline No 5/2010
Wash Implementation Framework, March 2003
One WASH National Program Document, August 2013
Ministry of Water Resources, Ministry of Health, Ministry of Education, Ministry of Finance and
Economic Development: WaSH Implementation Framework, August 2011
Ministry of Water Resources: National Water Resources Management Policy, 1999
Of this elaborate list, main focus will be on reviewing the existing guidelines of CMP: the CMP
Fund Management Guideline; CMP Implementation Manual for Manual Drilling; CMP
Implementation Manual for Institutional Sanitation; and Generic CMP Financial Management
Guideline. Whilst reviewing these guidelines, the consultancy team will focus on questions and
challenges brought forward in section 4 and 5 of this inception report.
3.2
Meetings and Discussions
Besides document review, the team held discussions with COWASH, MoWIE, SNV, World Bank,
UNICEF and POM experts who currently consider or implementing CMP both at national and
region level, as to understand their perceptions and concerns. Meetings and discussions were held
with the following sector experts:









Ato Abiy Girma
Ato Nuredin Mohamed,
Ato Tamiru Degeffa,
Mr. Arto Suominen
Ato Yohannes Melaku
Ato Tesfaye Bekalu
Dr. Samuel Godfrey
Mr. Bruck Aregai
Yemareshet Yemaneh
National WASH Coordination Office, National Coordinator
Director, Water Supply and Sanitation Directorate, MOWIE
Coordinator, national WASH Program Management Unit
Chief Technical Advisor, COWASH, MoWIE
CMP Specialist, COWASH MoWIE
Senior Water and sanitation Specialist, World Bank
Chief, WASH Section UNICEF
Senior WASH Expert, SNV
Consultant/POM
6
Key staff in regional bureaus of Oromia, Amhara and Benishangul Gumuz regions will be consulted
and invited in drafting and review of inception report and revised CMP implementation manual.
Bilateral consultation meeting with Finland Embassy is yet to be scheduled and highly valued for
drafting the revised CMP manual.
3.3.
Inception workshop
The final Inception report has been concluded after valuable inputs from a participatory, half-day
Inception Workshop taking place on February 6 2014 (Desalegn Hotel). The State-Minister MoWIE
H.E. Kebede Gerba opened the CMP Inception workshop, and representatives of MoWIE, Finland
Embassy, SNV, Federal and Regional CoWASH Staff, MWA, IRC, UNICEF, Amhara and BenishangulGumuz regions and WB provided input, suggestions and directions towards basic and essential
components of CMP, which are incorporated into this final CMP Inception report or will be taken
into account in the upcoming revised CMP Implementation Manual.
4. Preliminary standpoints Main questions and
4.1
Principles and core elements of CMP
The key questions with regard to core elements of CMP are the following:
 What makes a rural WASH intervention a Community Managed Project (CMP) project?
 What are the key principles that should not be violated and compromised?
 How to create an enabling environment at community level for them to operationalize CMP?
Bearing these questions into account, suggestions and guidance was provided to the Program
Operation Manual (POM) of the One WASH National Programme (OWNP) as how to accommodate
CMP. These suggestions need review (are they viable?) and endorsement. Reference is made in
Annex 1. Annex 2 provides additional reflections of the consultants towards CMP in POM.
One main exemption will be to allow the implementers of the CMP projects to procure goods and
services in accordance with the Government Procurement Directive and Manual. Without this
exemption, the CMP model would intrinsically fall. It is yet to be decided by the Taskforce/relevant
stakeholders if CMP receives green for this exemption, or if the consultants shall write an
Implementation Manual based on the assumption that the exemption will be granted. Another
question that needs to be answered is whether an exemption still is required where WASHCOs are
legally recognized.
Governed by the suggested and MoFED’s yet to be accepted core-guiding principles of the POM
(Annex 1), detailed guidance for operationalization of CMP will be provided in the upcoming
revised CMP Implementation Manual.
4.2
Fund Channelling and Financial Management
One of the most critical elements of project management is fund channelling and financial
management. As shown above, what makes CMP a distinct implementation modality is that
community representatives access funds and manage the entire project process including
procurement of services.
7
Major questions in channelling of funds and financial management of CMP that need to addressed
and agreement needs to be found on are:
I.
How can channelling to communities be arranged with in the public finance management
system of the Government of Ethiopia?
II. How can the WASH grant be channelled to community representatives in order implement
CMP effectively?
III. How to establish adequate financial control mechanism to ensure fiduciary accountability and
monitoring at all level?
IV. How to establish enabling environment and capacities (‘minimum capacity building package’)
so that community representatives can effectively manage rural WASH projects?
To address these questions, the following steps are suggested for CMP to operate in Rural WASH
Programme.
The first step in RWASH plan development is creation of awareness of the community.
Communities will be sensitized and trained to identify their development priorities. Based on
communities’ demand, Woreda WaSH Team (WWT) will develop a Woreda Strategic WASH Plan.
The Woreda WASH plan will identify physical and financial targets of RWASH. The WWT will
decide the implementation modality of the proposed WASH plan, guided by the WaSH
Implementation Framework (WIF) and the One WASH Approach. For each WASH project in the
Woreda WASH plan, the WWT will consider the most appropriate model for implementation out
of the four RWASH modalities.
In areas where the WASH intervention is determined to be CMP -determining factors towards this
choice may still need to defined-, the following framework should be adopted as to align to the
CMP implementation model, in line with the Public Finance and procurement management
System:
 The annual Woreda WASH plan will be the basis for the annual Woreda WASH budget;
 The CMP investment grant should be separately budgeted in the Woreda WaSH budget;
 After Woreda’s approval of the Woreda WASH plan and budget, the CMP investment grant as
part of the WASH Budget, will be channelled from BoFED to WoFED;
 Communities and institutions, through the WASHCOs, will prepare and submit CMP project
application for WASH grant;
 WWT will appraise communities’ application. The final design and cost estimate will be
decided in the appraisal stage and separate financing agreement for each project will be
signed by the WWT and the WASHCO;
 After signing the project financing agreement, WoFED will open individual accounts for the
respective WASHCOs in Commercial Bank of Ethiopia (CBE);
 WASHCOs delegate bank signatories for withdrawal and will implement the project;
 WASHCO will procure the required services and goods for the CMP project using the
Government procurement system;
 The WASHCO chair will report quarterly on expenditures and bank balances and submit the
receipts of the CMP expenses to WoFED at the end of the project at which the project account
will be closed;
 Woreda WASH team provide technical support, capacity building and monitoring of works to
the WASHCOs and Kebeles;
8
 Kebele Administration provides financial and procurement oversight and support to the
WASHCOs.
For institutional (schools and health institutions) WASH facility construction the same principle will
be applied with ‘Parent Teacher Associations’ (PTA) as implementers in schools and the ‘Health
Facility Committees’ for health instituties. Status of these bodies compared to WASHCOs still need
to be clarified/ agreed upon.
Through this line of order, the CMP service delivery modality aligns to the Public Finance &
Procurement Management System of Ethiopia and the One WASH programme institutional
arrangements.
4.3
Institutional Arrangement
Currently CMP is supported federally through COWASH project and Regional support teams at
regional level. Both at federal and regional level the required Technical Assistance (TA) is
facilitated through these arrangements while the Water Supply and Sanitation Directorate and the
Water Supply Core Process at regional level are to provide oversight and coordination.
As technical assistance is required and should be maintained to effectively implement CMP, it is
essential to critically think about institutionalizing CMP in WASH structures. CMP should follow the
WASH structures as agreed on WIF and One WASH National Program (OWNP) document. Towards
this, a number of issues need to be addressed in due course of implementing the OWNP:
a) It is essential to look as how CMP expertise is or can be included in WaSH structures at all
levels;
b) Even within existing WASH structures, within the Program Management Units (PMU), no
unit/focal person is responsible for CMP. A key issue to address is what is the best way to
strengthen the Program Management Units (in all sector institutions) by including responsible
CMP expertise/unit?
c) Within the operational structures of MoWIE and regions there are no units responsible for
CMP. What is the best way to create CMP capacity and expertise at federal and regional level?
4.4
Key issues raised
In principle, there seems general consensus by sector partners that CMP is an effective
implementation arrangement and can significantly contribute to addressing sector capacity
limitations and ensuring sustainable WASH service. Both government and donor partners
appreciate moving fund channelling and management of CMP towards the public finance and
management rules of the GOE and OWNP. All sector partners recognize the need for organizing
CMP with in WIF and public finance management rules of the GOE so that it can be implemented
nationwide. Partners also recognize that the understandings reached in WIF should be the basis
for any future action including the development of the CMP implementation guideline.
Preliminary discussions highlight the following key issues that needed immediate consensus:
I.
PMU initially questioned the need for a separate CMP implementation guideline in the
presence of POM. While it is a valid point to have one programme implementation manual, it
is also important to understand that the POM is a guiding document with principles and
9
arrangements that does not provide detailed procedures for operationalization of CMP. This,
the CMP Implementation Manual need to provide for;
II. There are differing views on the type of technologies and level of service provision that can be
implemented through CMP. While some partners favour not to be exclusive and see the
(gradual) inclusion of higher service-level provision and higher technology levels, some
partners see CMP only being effectively implemented by communities when it involves for
simple and low cost technologies;
III. There is a general understanding for streamlining CMP with in the existing WASH structures.
Up to date, no units supporting CMP are embedded within the existing WASH structures.
Strengthening the structures and creating capacities and expertise is critical. Concerns are
raised whether this is practical, feasible and replicable over the 70+ woredas where CMP is to
be implemented;
IV. Creating ‘enabling environment’ at community/user level is seen critical for effective
implementation of CMP. The sector has to determine the minimum capacity support required
for the CMP to work effectively;
V. The issue of assuring quality construction, ensuring the reliability of the schemes and sources
(especially at higher levels of technical service) and effective auditing and spot check within
community contracting should be addressed in order to make CMP an effective and viable
implementation modality;
VI. When CMP would be modified in essential conception principles (for example, communities
not being in the position to contract or procure on behalf of their CMP scheme) as to align to
OWNP or certain donors’ requirements, CMP risks drifting off from its original and
connectional implementation modality. The initiator and major donor Government of Finland
might consider withdrawing from financial or technical support to a greatly amended CMP
model in Ethiopia.
All these areas of discussion need to be addressed and a consensus on practices and priorities has
to be reached first and foremost for the consultancy team being able to develop a CMP
implementation guideline acceptable by all major OWNP implementing partners. This leads us to
the next section highlighting some key challenges in drafting a revised CMP Implementation
manual.
5.
Key challenges
The teams’ initial -and by donor’s confirmed- understanding on the ToR is that ‘solutions’ for the
revised CMP Implementation manual were already identified and agreed upon. The assignment
was to focus on writing the manual based on already identified solutions and decisions.
However, preliminary discussions in the inception phase show that modalities and communitymanaged implementation still need to be identified and solutions have to be negotiated.
Discussions with Government and partners reveal that the process is not as straightforward as
assumed, and the fundamental question arises whether it is possible to deliver a CMP manual that
meet the requirements of the ToR, and solve disparities within the given consultancy timeframe.
10
Besides this fundamental challenge in delivering the assignment against ToR and consultancy
timeframe, intrinsic key challenges in mainstreaming and effectively implementing CMP with in
the OWNP and the public financial and procurement rules of the GOE are:
I.
Making CMP work effectively using channel 1b. The detailed arrangements have to be
worked out how the fund will be channelled to community representatives and community
institutions, such as WASHCOs and Parent-teacher Associations (PTAs). Related to this,
bank availability and accessibility in woredas or the capacity of WASHCOs to report
quarterly to Woreda Bureaus needs to be sorted out;
II.
Developing and mainstreaming decentralised roles and responsibilities of all actors
including WoFED, WWT, Woreda Water Office, Kebeles and Community representatives.
This has to be developed in line with their mandates and in accordance with WIF;
III.
Building capacities of all actors from federal to community level. What kind of capacity or
so-called ‘minimum capacity building package’ is required for CMP to be implemented
effectively under the new arrangement?
IV.
High social cohesion is required to make CMP work. Certain livelihood systems -such as
pastoralist communities or communities in conflict- are challenging for implementing and
sustaining CMP modalities.
V.
What kind of fiduciary control and safeguard can be put in place that are acceptable to
public finance management structures without compromising the core elements of CMP
and its effectiveness?
VI.
What kind of procurement flexibilities can be built in to the system without violating
public procurement directives of GoE?
Solutions to these questions need to identified first, as to get to an agreed upon revised
implementation manual.
In the Inception workshop, the MoWIE suggested two solutions regarding procurement flexibilities
to be built into the system:
i)
Review extension and delegation to communities, kebeles and woredas, optimizing
kebele structures (e.g. exampling in Tigray) that effectively manage CMP;
ii)
Give the mandate to communities to delegate tasks to Woredas to handle procurement
6.
Team, work plan and deliverables
6.1
Consultancy team and Taskforce
SVN and COWASH have jointly employed a consultant team to carry out the preparation of
CMP Implementation Manual. The following expertise has been employed:
 Inge Klaassen
 John Butterworth
 Eyob Defere
 Editor
11
Participants of the Inception workshop did not find it necessary to establish a Task Force to review
the CMP Implementation Manual preparation. Instead, a similar workshop as the Inception
Workshop would be sufficient to oversee the appropriate preparation and drafting of the CMP
Implementation Manual so that it fulfils the requirements of the Public Finance and Procurement
Management Systems.
6.2 Work plan and deliverables
i) Inception report and presentation: an inception report with oral presentation including:

Summary of desk review

Objectives and questions 
Methods and justification of the proposed methodology for diagnostic

List of key informant interviews

Key implementation challenges and risks

Implementation work plan and time table
ii) Presentations of draft findings from diagnostic, mapping and recommendations
iii) Final report on the revised CMP implementation manual. The report will include detailed
results from the diagnostic and key recommendations (region specific).
iv) Copy of the final version of the actual revised CMP implementation
Regarding the timeline of the CMP consultancy: at the end of 2013 the revised ToR for CMP
Implementation, clearly serving the One WASH National Program -with inputs from an Economist was agreed upon. Contractual engagement of the consultancy team effectively started at the
beginning of the year 2014. The start-up meeting for the consultancy could only be scheduled
after the festive season, which was arranged for by mid January 2014 in the COWASH office,
MoWIE. From 15- 31st January, desk-review and interviews took place. As discussed in the
Inception workshop -and afterwards worked out further by the consultancy team and key
stakeholders- the onward timeframe as to fulfil the assignment and the above-mentioned
deliverables is the following:
 3rd February 2014: Draft Inception report, shared range of Stakeholders
 6th February 2014: Presentation Inception Report, half-day workshop with relevant Stakeholders
 17th March 2014: Zero Draft CMP Implementation Manual, shared with CoWASH, SNV, UNICEF,
Embassy of Finland (client)
 24th March 2014: Consultants receive comments from CoWASH, SNV, UNICEF, Embassy of
Finland
 31st March 2014: Draft CMP manual shared with wider group of stakeholders
 7th-14th April 2014: Workshop Review of CMP Implementation Manual with relevant
Stakeholders
 21st April 2014: Final draft CMP implementation manual (taking into account feedback of
relevant Stakeholders). To be send to the editor
 10th May 2014: Final, edited revised CMP Implementation Manual
However, consensus towards core CMP implementation modalities and the conceptual borders of
the management model needs to be defined first, otherwise meeting these milestones against
deadline are under pressure. A revised work process and work plan may need to be negotiated.
12
ANNEX 1:
SUGGESTIONS FOR ACCOMODATING CMP IN THE PROGRAMME OPERATION
MANUAL (POM) OF THE OWNP.
The following section provides suggestion how CMP can accommodate in the Programme
Operation Manual (POM) of the OWNP. They still need to be reviewed and agreed upon in terms
of viability and compliance to the OWNP framework:
2.4
Rural WASH Implementation Modality (reference is made to page 15)
The Rural WASH- water supply sub components have four alternative implementation modalities
that are described in detail here below.
Community Managed Projects (CMPs):
Community Managed Project (CMP) is a Rural WASH (RWASH) implementation modality under
which community representatives will be responsible for planning, and implementation of the
project and management of the investment funds.
In the CMP, the representative of the user-group (WASHCO or Institutional WaSH Committee) is
the Project Manager. The role of Government is limited to channelling of funds, administration,
facilitation and training, supporting capacity building of communities, monitoring and management
of the Woreda WaSH Program instead of managing the implementation of large numbers of
individual projects.
The core principles of CMP are the following:
 Channelling from MoFED to BoFED-WoFED will follow the Channel 1b and the Public
Finance and Procurement Management System of Ethiopia;
 Woreda Finance Office opens an account to each WASHCO and deposits the CMP grant at
which and the community -through the WASHCO representatives-will access the fund for
the implementation of the CMP project;
 The WASHCO is directly responsible for contracting, procurement and supervision of the
scheme construction and/or rehabilitation. As such, the WASHCOs will be responsible for
core implementation management the CMP project;
 The WASHCO is financially accountable to the Kebele and Woreda Finance Office;
 Investment fund for physical construction is directly transferred to the WASHCOs via
Woreda Finance Office through a regulated, Commercial Bank of Ethiopia (CBE) account;
 The CMP implements low-cost technologies. The type of technologies will be defined in a
separate and more detailed CMP Implementation Guideline that operationalizes the One
WASH National programme.
How does CMP operate in Rural WASH PROGRAM?
The first step in RWASH plan development is creation of awareness of the community.
Communities will be sensitized and trained to identify their development priorities. Based on
communities’ demand, Woreda WaSH Team (WWT) will develop a Woreda Strategic WASH Plan.
The Woreda WASH plan will identify physical and financial targets of RWASH. The WWT will
decide the implementation modality of the proposed WASH plan, guided by the WaSH
Implementation Framework (WIF) and the One WASH Approach. For each WASH project in the
Woreda WASH plan, the WWT will consider the most appropriate model for implementation out of
the four RWASH modalities.
13
In areas where the WASH intervention is determined to be CMP, the following actions will be
taken:
 The annual Woreda WASH plan will be the basis for the annual Woreda WASH budget;
 The CMP investment grant will be separately budgeted in the Woreda WaSH budget;
 After Woreda’s approval of the Woreda WASH plan and budget, the CMP investment grant
as part of the WASH Budget, will be channeled from BoFED to WoFED;
 Communities and institutions, through the WASHCOs, will prepare and submit CMP
project application for WASH grant;
 WWT will appraise communities’ application. The final design and cost estimate will be
decided in the appraisal stage and separate financing agreement for each project will be
signed by the WWT and the WASHCO;
 After signing the project financing agreement, WoFED will open individual accounts for the
respective WASHCOs in Commercial Bank of Ethiopia (CBE);
 WASHCOs delegate bank signatories for withdrawal and will implement the project;
 WASHCO will procure the required services and goods for the CMP project using the
Government procurement system;
 The WASHCO chair will submit the receipts of the CMP expenses to WoFED at the end of
the project at which the project account will be closed;
 Woreda WASH team provide technical support, capacity building and monitoring of works
to the WASHCOs and Kebeles;
 Kebele Administration provides financial and procurement oversight and support to the
WASHCOs.
For institutional (schools and health institutions) WASH facility construction the same principle
will be applied with ‘Parent Teacher Associations’ (PTA) as implementers in schools and the
‘Health Facility Committees’ for health facilities.
Through this line of order, the CMP service delivery modality aligns to the Public Finance &
Procurement Management System of Ethiopia and the One WASH programme institutional
arrangements.
Governed by these core-guiding principles of the POM, a more detailed guideline for
operationalization of CMP will be provided in a separate document.
14
Annex 2:
Additional reflections of the consultants towards CMP in POM
Community Managed Project (CMP) is a Rural WASH (RWASH) implementation modality under
which community representatives will be responsible for planning, and implementation of the
project and management of the investment funds.
The WASHCO is directly responsible for contracting, procurement and supervision of the scheme
construction and/or rehabilitation. As such, the WASHCOs or representative of the Community will
be responsible for core implementation management the CMP project and become the Project
Manager.
In the OWNP, fund Channelling of CMP is requested to follow Channel 1b, from MoFED to BoFEDWoFED and financial management will follow the Public Finance and Procurement Management
System of Ethiopia, which will need to be looked into for compliance and practicality.
The role of Government is limited to channelling of funds, administration, facilitation and training,
supporting capacity building of communities, monitoring and management of the Woreda WaSH
Program instead of managing the implementation of large numbers of individual projects. Role of
Woreda WASH Team will be approving, funding, facilitating, supporting communities and
monitoring and supervision of the WASH project.
Woreda Finance Office opens an account to each WASHCO and deposits the CMP grant at which
and the community -through the WASHCO representatives-will access the fund for the
implementation of the CMP project. Investment fund for physical construction is then directly
transferred to the WASHCOs via Woreda Finance Office through a regulated, Commercial Bank of
Ethiopia (CBE) account. The WASHCO is financially accountable to the Kebele and Woreda Finance
Office.
In general, procurement under the One WASH will be carried out in accordance with the
Procurement Directives of June 2010 and Public Procurement Manual of December 2011 issued by
the Ministry of Finance and Economic Development.
15