Z Permit To Work System PTWS Manual Document issued on: Status: Effective Date: Approval: 24 Mar 14 Final 1 May 14 Master document posted on Z Intranet and Internet Uncontrolled when downloaded or printed Review Requirements Annual review. Re-issued only if revised. This document is published and downloadable from the Z intranet and internet and available for reference by all staff and contractors. Document Title: Z PTW Manual Version 3.2 24 Mar 14 Document Author: Tracy Evans-Tracy HSSE Project Specialist Document Holder: Joromi Guantero HSSE Assurance Manager Document Custodian: Julie Rea HSSE Manager Document Owner: Mike Bennetts CEO Revision History Version Date Summary of Revisions Draft Version 1.0 April 2011 Draft for comment Draft Version 2.0 May 2011 Final Draft BRM Review July 2011 Final 1.0 July 2011 Revision 1.1 August 2011 Minor revisions to forms Revision 1.2 December 2011 Revisions to Forms Revision 2.0 October 2013 Draft for comment - revision to process based on PTWS principles. The permitable activities and forms have not yet been reviewed. Revision 2.1 November 2013 Revisions to this document following consultation with Z impacted parties and contractors. Revision 3.0 13 Feb 2014 Final revision following all consultation rounds Revision 3.1 28 Feb 2014 Changes following BRM Review and changes to wording for permitable and medium risk electrical activity Revision 3.2 24 Mar 2014 Minor changes following Updated PTWS Orientation Training for clarity. No intent changes Document Custodian: HSSE Manager Uncontrolled when printed 2 Document Title: Z PTW Manual Version 3.2 24 Mar 14 Contents 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Purpose, Principles and Authority.................................................................................................................. 5 1.1 Purpose ............................................................................................................................................. 5 1.2 Principles ........................................................................................................................................... 5 1.3 Authority............................................................................................................................................ 5 1.4 PTWS risk management cycle as per AS/NZS 31000:2009 ....................................................... 5 1.5 Permit To Work ................................................................................................................................. 6 Applicability ...................................................................................................................................................... 6 Roles and Responsibilities ............................................................................................................................... 7 3.1 Roles and responsibilities table ..................................................................................................... 7 3.2 CEO - Owner .................................................................................................................................... 7 3.3 HSSE Manager - Custodian ........................................................................................................... 7 3.4 PTWS Administrator ......................................................................................................................... 8 3.5 PTWS Orientation Trainer ................................................................................................................ 8 3.6 Senior Permit Issuer .......................................................................................................................... 8 3.7 Permit Issuer ...................................................................................................................................... 9 3.8 Permit Holder ................................................................................................................................. 10 3.9 Authorised Gas Tester .................................................................................................................. 12 3.10 Z Site Representative .................................................................................................................... 13 Permitable Activities ...................................................................................................................................... 13 4.1 Permitable Activities (high risk) ................................................................................................... 13 Non-permitable Activities ............................................................................................................................ 15 5.1 Medium Risk Activities .................................................................................................................. 15 5.2 Low Risk Activities .......................................................................................................................... 16 5.3 Deliveries ......................................................................................................................................... 16 System Documents ........................................................................................................................................ 16 6.1 Work Clearance Form .................................................................................................................. 17 6.2 Safe Work Method Statement/Job Safety Analysis ................................................................ 17 6.3 Permit............................................................................................................................................... 19 6.4 Permit Attachments ...................................................................................................................... 19 6.5 Contractor Prequalification Process ......................................................................................... 20 System Rules .................................................................................................................................................... 20 7.1 Permit Validity ................................................................................................................................ 20 7.2 Remote Permitting ........................................................................................................................ 21 7.3 Self-Permitting ................................................................................................................................ 22 7.4 Contractor Permitting .................................................................................................................. 22 7.5 Blanket Permits............................................................................................................................... 22 7.6 Derogations and standard operating procedure approval process ................................. 22 7.7 Changes in Conditions................................................................................................................. 23 Training and Competency Requirements ................................................................................................ 23 8.1 Permit Issuers .................................................................................................................................. 23 8.2 Permit Holders ................................................................................................................................ 25 8.3 Authorised Gas Tester .................................................................................................................. 25 8.4 Worker Qualification ..................................................................................................................... 25 Audit & Review of PTWS ................................................................................................................................ 25 9.1 Audits ............................................................................................................................................... 25 9.2 Review and Assurance ................................................................................................................ 25 9.3 Reporting ........................................................................................................................................ 26 9.4 Records ........................................................................................................................................... 26 Glossary ........................................................................................................................................................... 26 Attachments ................................................................................................................................................... 28 Document Custodian: HSSE Manager Uncontrolled when printed 3 Document Title: Z PTW Manual Version 3.2 24 Mar 14 Intent and Why of the Permit to Work System At Z, we reckon everybody should do work in a safe manner on our sites so everybody can go home safely. The Permit to Work System (PTWS) provides a practical framework to our staff and contractors to assist in reaching our Zero Harm Workplace. The PTWS is intended to provide an effective means of identifying significant hazards and managing significant risk activities. In other words, a set of eyes on significant risk activities; consulting with contractors and workers to verify the controls required have been identified and established appropriate to the level of risk. The PTWS is also a formal means of communication for all parties involved in the management, supervision, and actual carrying out of the activities. The PTWS supports Z‟s HSSE Strategy: 6 Pillars to working safely and the HSSE Management System Manual. It is integral to Z's part of a safe system of work and is key to effectively manage the wide range of activities Z is involved in. A Permit is not simply permission to carry out a dangerous job. It is an essential part of a system which through consultation with affected parties, determines how that job can be carried out safely, and helps communicate this to those doing the job. It should not be regarded as an easy way to eliminate hazard or reduce risk. The issue of a permit does not, by itself, make a job safe - that can only be achieved by those preparing for the work, those supervising the work and those carrying it out. In addition to the PTWS, other controls may need to be taken - e.g. process or electrical isolation, or access barriers - and these will need to be identified in task risk assessments before any work is undertaken. The PTWS is intended to ensure that authorized and competent people have thought about foreseeable risks and that such risks are eliminated otherwise minimized by using suitable control measures. Those carrying out the job should think about and understand what they are doing to carry out their work safely, and take the necessary control measures and requirements for which they have been trained and made responsible. Human factors, such as people not implementing procedures properly, are often a cause of incidents, in turn attributable to root causes such as a lack of training, instruction, communication or understanding of either the purpose or practical application of the PTWS. This document is intended to provide clear understanding of Z's PTWS requirements. Document Custodian: HSSE Manager Uncontrolled when printed 4 Document Title: Z PTW Manual Version 3.2 24 Mar 14 1. Purpose, Principles and Authority 1.1 Purpose 1.2 To provide a framework where all non-routine work is completed in a safe manner to prevent harm to workers and others impacted by the work. The purpose of this document is to set out Z Energy Limited„s (Z) Permit to Work System (PTWS) requirements. Principles The principles of the PTWS are aimed at adding value in terms of risk reduction to keep workers safe and eliminate otherwise minimise HSSE risks to an acceptable level for activities that fall within its application. This will be achieved through the following principles for Z‟s PTWS: Lead focus is for all parties is to keep workers safe 1.3 1.4 Criteria based on severity level of risk for health, safety and environment including acute, chronic, and catastrophic consequences Whole of business focus Trained competent personnel involved Reporting permit process Clear and simple criteria Smart and accessible systems – user friendly Currency of information vital Verification and assurance built in Authority All Z employees, site representatives, contractors and workers, are authorised to stop the work if there is a Health, Safety, Security or Environmental (HSSE) concern about the work. This PTWS document shall be effective as of 1 May 2014. PTWS risk management cycle as per AS/NZS 31000:2009 1. Establish the context of the work activity 2. Identifying hazards 3. Assess the risk 4. Determine the necessary controls to eliminate otherwise minimize the risk using the Document Custodian: HSSE Manager Uncontrolled when printed 5 Document Title: Z PTW Manual Version 3.2 24 Mar 14 hierarchy of controls 1.5 5. Implement the controls ensuring competent persons carry out the activity and issue the permit 6. Evaluate the risk to achieve as low as reasonably practicable 7. Implement additional controls (treatment) if the risk is not acceptable. 8. Consult and communicate with all relevant parties throughout the risk process and conduct of the activity, including authorities where applicable 9. Monitor and review the outcomes of the PTWS Permit To Work The terms „permit-to-work‟, „permit‟ or „work permit‟ refer to the paper or electronic certificate or form which is used as part of an overall system of work, and which has been devised by Z to meet its specific needs. Whether it is manually or electronically generated, the permit is a detailed document which authorizes certain people to carry out specific work at a specific site at a certain time, and which sets out the main controls needed to complete the job safely 2. Applicability 2.1 This document applies to all workers conducting work for and on behalf of Z, such as employees, contractors, sub-contractors, franchisees, and retail site staff, as well as visitors, on premises operated by Z. 2.2 The PTWS is mandatory and applies to all non-routine work being completed at workplaces under Z operational control, Retail sites, Mini Tanker Zee sites, work conducted under a Z Construction Contract, or when working on Z owned equipment at sites owned or operated by others. 2.3 A permit is required for all permitable activities (as defined in section 4 of this document). No permit is required for other works unless specifically stipulated by Z Energy (although contractors are required to complete work clearance forms for such work on a daily basis). 2.4 The PTWS is to be used in parallel with site safety rules. Manned sites, in particular, may have site specific safety requirements. In the event of any inconsistency the more prescriptive standard shall apply. 2.5 The Z Life Saving Rules (LSR) are mandatory and apply to all work completed for Z. The LSR are used in parallel with the Permit to Work System. The Z LSR can be found at: http://z.co.nz/ptwinfo 2.6 The requirements of this document shall apply in addition to any applicable NZ laws and regulatory requirements, including the latest codes of practice as issued by the regulator. This document takes precedence only where its requirements exceed those of applicable laws and regulatory requirements. Document Custodian: HSSE Manager Uncontrolled when printed 6 Document Title: Z PTW Manual Version 3.2 24 Mar 14 3. Roles and Responsibilities There are roles and responsibilities within the PTWS as set out below. 3.1 Roles and responsibilities table Role Issue permits Self permits Appoints PI PTWS assurance activities system Stop work if necessary HSSE Manager X X X Administrator X X X Trainer X X Senior Permit Issuer X X Permit Issuer X X X Permit Holder X X X X Authorised Gas Tester X X X X Z Site Representative X X X X Workers X X X X Z Staff X X X X Key: X = is not responsible and cannot undertake the task/role = is responsible and can undertake the task/role 3.2 CEO - Owner The C E O is the Z Energy senior manager with overall ownership and responsibility for Z‟s HSSE practices. The CEO is the senior manager accountable to ensure an appropriate permit-to-work system is introduced and made operational, and provide sufficient resources to enable the permit-to-work system to be properly implemented. 3.3 HSSE Manager - Custodian The HSSE Manager, or delegate, is responsible for maintaining and confirming the implementation of this PTWS. The responsibilities of the HSSE Manager are as follows: Implement and monitor the PTWS in accordance with the requirements of this document Monitor and evaluate the PTWS outcomes to ensure appropriate safe work systems are established and maintained for all work done under the PTWS Implement a PTWS orientation program that is designed to familiarise Z Assets Document Custodian: HSSE Manager Uncontrolled when printed 7 Document Title: Z PTW Manual Version 3.2 24 Mar 14 Project Management Office, Z Environmental Manager, Z Maintenance Manager, Z HSSE Specialists, Site Systems Manager, Permit Issuers, Permit Holders and Authorised Gas Testers on the requirements of the PTWS 3.4 Appoint the PTWS Administrator, PTWS Orientation Trainer, and Senior Permit Issuer Audit and Review the PTWS periodically to seek to ensure its effectiveness and currency with accepted industry practice Report to the BRM and the CEO on the effectiveness of the PTWS. PTWS Administrator The PTWS Administrator is the person who is responsible for administering the PTWS documentation and records requirements. The Administrator is appointed by the HSSE Manager, and is a Z employee. Responsibilities of the Administrator are as follows: 3.5 Maintains a register of Permit Issuers and Authorized Gas Testers confirmed competent by the PTWS Orientation Trainer, and other necessary documentation to verify the requirements of this document have been met PTWS Orientation Trainer The PTWS Orientation Trainer is the person who is responsible for conducting the PTW Orientation training and managing the training and competency requirements of the PTWS. The Trainer is appointed by the HSSE Manager, and is a Z worker. Responsibilities of the Trainer are as follows: 3.6 Providing Z PTWS orientation training and testing for Permit Issuers Maintaining the PTWS orientation documents Verifies Permit Issuers are competent as per the requirements in this document, including revalidation every three years of Permit Issuer competencies. Senior Permit Issuer The Senior Permit Issuer is the person who is responsible for monitoring the operational performance of the PTWS, for conducting periodic operational reviews of the implementation of the PTWS, and for providing assurance to the HSSE Manager that the PTWS meets Z requirements and is implemented correctly. The Senior Permit Issuer is appointed by the HSSE Manager, and is a Z employee. Responsibilities of the Senior Permit Issuer are as follows: Confirms six monthly operational audits are conducted of the performance Document Custodian: HSSE Manager Uncontrolled when printed 8 Document Title: Z PTW Manual Version 3.2 24 Mar 14 standard attained by the Permit Issuers, Permit Holders and Authorized Gas Testers, and the PTWS as a whole is effectively implemented 3.7 Solicits and receives feedback from the users of the PTWS and consults with the HSSE Manager, as necessary on the operation of the PTWS Facilitating the sourcing of an adequate number of Permit Issuers who are qualified to issue Permits to meet the operational requirements of Z Providing technical support and advice to ensure the PTWS is implemented as intended Reviewing and issuing Permits as required Permit Issuer The Permit Issuer (PI) is responsible for taking all necessary steps to prepare, authorise and issue the Permit to Work after identifying the work and work site/area hazards and the controls to address such hazards. It is not necessary for the PI to remain on site for the duration of the work as the Permit Holder is responsible for verifying that the control measures are maintained throughout the work and that the work party and the work stays within the limits and conditions specified on the Permit (area, scope of work, time). Permit Issuers are required to manage their own permit numbering. The required format is PI initials and date. The PIs are appointed by the Administrator. The PI must be trained on the PTWS and successfully complete the competency training detailed further in this document before issuing any Permit at any location. PI‟s are likely to be experienced and competent third party personnel, Z Assets Team members, HSSE specialists, Christchurch Airport Depot staff, or contractors. The PI‟s responsibilities include, but are not limited to the following: Successfully completing the Z PTWS Orientation about the Z permit process. Critically reviewing the Safe Work Method Statement (SWMS)) that was prepared by the Permit Holder as part of the preparation of the permit Discussing the SWMS with the Permit Holder on site Confirming the PH is aware of requirements of the Z PTWS Issuing a permit that accurately details the scope of works and that the documented controls combined are adequate to confirm the work can be completed in a safe manner Confirming that the hazards associated with the work and the work site/area and other work that is or will be performed on or about the Document Custodian: HSSE Manager Uncontrolled when printed 9 Document Title: Z PTW Manual Version 3.2 24 Mar 14 location during Permit controlled work have been identified and assessed and that the identified controls are adequate to perform the work in a safe and environmentally sound manner 3.8 Confirming that all relevant parties have provided their input into the permit and agree with the hazards and controls identified in the permit before it is issued Verifying that all necessary supporting documentation, SWMS and drawings are attached or referred to in the Permit are readily available while the work is being performed Reviewing the permit with the Permit Holder and verifying with the Permit Holder that he/she knows the exact location of the work, the Permit conditions, emergency procedures in the event of an emergency during the work, the hazards that have been identified and the controls that must be taken during the work Specifying on the Permit any additional controls that need to be taken during the work Identifying any conflicts between the proposed work and other activities in the area of the work that is being authorized by the permit, and if necessary crossreferencing the Permits Signing and issuing the permit Cancelling or suspending permits that have been issued when necessary Reviewing the work with the Permit Holder when the Permit Holder returns the permit if required Sign off on the permit once the work is complete Reporting incidents and near miss incidents involving the work covered by the permit to the Administrator Conducting or participating in any investigation of an incident related to the work covered and providing the investigation report to the Administrator, as applicable Retaining copies of the permit form and associated documents for a minimum of 6 years, and 40 years for any permits involving asbestos work or health monitoring. Permit Holder The Permit Holder (PH) is responsible for taking all necessary steps to perform the work in a safe and environmentally sound manner in accordance with the permit. The PH is typically the Contractor who is responsible for performing the work. The person or contractor responsible for undertaking the work is responsible for: planning their permitable activity requirements and including them in their works programme, Document Custodian: HSSE Manager Uncontrolled when printed 10 Document Title: Z PTW Manual Version 3.2 24 Mar 14 engaging a competent PI a minimum of 10 working days (or as negotiated with the PI) in advance of the date the permit is required (except in an emergency situation – in which case phoning 111 may be the best option), providing to the PI for review the required documentation for the permit a minimum of 5 working days in advance of the date the permit is required, ensuring the permit holders are trained and competent in their responsibilities as a PH, and providing sufficient supervision to ensure the Z PTWS requirements are met. The PH‟s responsibilities include, but are not limited to the following: Preparing a Safe Work Method Statement/Job Safety Analysis (SWMS/JSA) and any other documents required Completing a Work Clearance Form each day prior to works commencing Identifying the need for a permit as per the works programme or in completing the Work Clearance Form, and contacting the local PI engaged to arrange for getting the permit(s) issued Discussing the job fully with the PI before signing to accept the Permit Providing input into the controls necessary to manage risks as their area of expertise relates to the scope of work Reviewing the risks and controls daily through a prestart / toolbox meeting and ensuring all workers are been trained and have signed into the SWMS for the works. Explaining to the work party the details of the work and any potential hazards and their associated control measure identified to mitigate the risks. Enforcing compliance with the PTWS and permit, including without limitation, verifying that the control measures are maintained throughout the work and that the work party and the work stays within the limits and conditions specified on the Permit (area, scope of work, time) Being present personally at the work site at all times during the Permit controlled work. If the PH must leave the work site permanently during performance of the work, the permit shall be cancelled and all work shall stop until such time a new permit is issued Prominently displaying the Permit and attachments at the work site where all Contractor employees can see them Stopping the work and seeking advice from the PI if conditions at the site change Taking the necessary steps to ensure the work area is left in a safe and tidy condition, before handing back the permit to the PI on completion or suspension of the work, as applicable Document Custodian: HSSE Manager Uncontrolled when printed 11 Document Title: Z PTW Manual Version 3.2 24 Mar 14 3.9 Submitting the signed completed permit on completion of the work Authorised Gas Tester The Authorised Gas Tester (AGT) is appointed by the Permit Holder for all permits where atmospheric testing is a requirement. The AGT is responsible for taking the necessary steps to confirm that the atmosphere in, on and about the work area is such that the work can be performed in a safe manner. The AGT shall be adequately trained and experienced to perform the gas testing and in the operation of the gas testing device. The competency requirements are detailed further in this document. The AGT shall be formally trained in the use of their own/company gas detector device and have current certification to demonstrate this. The AGT certification must form part of the SWMS/JSA. The AGT shall have ready access to and be competent to use calibrated gas testing equipment that is maintained in good working condition in accordance with the manufacturer‟s recommendations / instructions. The Authorised Gas Tester roles and responsibilities may be performed by a Contractor‟s qualified technician, supervisor or foreman or the PI. The AGT may be the PH or the PI or another Z or Contractor employee, except for confined space work where the AGT cannot hold or carry out any other role. The Authorised Gas Tester‟s responsibilities include, but are not limited to the following: Successfully completing the training concerning performance of gas testing and necessary gas testing equipment training Conducting gas tests (oxygen, toxic and LEL/flammability, etc.) immediately prior to Permit issuance and at the frequency specified on the Permit and SWMS/JSA to verify that a hazardous atmosphere is not present Prior to each use, calibrating and inspecting the gas testing equipment and confirming it is the appropriate equipment, is calibrated, and is fit for purpose. Equipment that is not calibrated and fit for purpose shall not be used and shall be marked as “DO NOT USE” and removed from the work site Providing the PI with the results of all gas test taken as part of the permit issuance process. The PI shall record the gas tests results on the permit prior to issuance The AGT must continue to take ongoing gas readings and record them on the Permit documentation. Immediately stopping the work and instructing personnel to withdraw from the work area to a safe area whenever a gas test or change in conditions Document Custodian: HSSE Manager Uncontrolled when printed 12 Document Title: Z PTW Manual Version 3.2 24 Mar 14 indicates that it is unsafe for the work to continue or is not covered by the permit and immediately report the condition to the PH. The PH must immediately inform the PI. 3.10 Z Site Representative The Z Site Representative (for manned operating sites only; i.e. retail sites, Christchurch airport depot) is the member of the site staff who: C onfirm that the contractor/workers performing the work when arriving to site each day has completed and signed a Work Clearance Form (WCF), has a permit if required (as identified on the WCF), and has completed the appropriate contractor induction requirements (ID card verification) where applicable. Provide a hazard brief for the site and significant activities that will be happening on site for the day. Check work activity onsite and if any work practices appear inconsistent with Z‟s LSR intervene with the relevant party and inform their supervisor. Site Representatives are authorised to stop the work if there is a HSSE concern about the work. Confirm when the persons performing the work and/or contractor leaves the site they sign the Work Clearance Form (WCF). The Site Representative must advise the persons performing the work and/or the contractor of any new hazards as they know of them. 4. Permitable Activities 4.1 Permitable Activities (high risk) Permits are required for the below permitable activities at all times, including a Safe Work Method Statement (SWMS) and any other supporting certificates / documentation. Note any work that is described as excluded in the permitable activity descriptions is only excluded being permitted. All other relevant documentation for the work must still be completed. Hot work in a hazardous zone Hazardous zones are as per the Classification of Hazardous areas AS/NZS 2430.3:2004. Hot work is any work that may produce a source of ignition. This includes using any equipment that is not rated for use in a hazardous zone. It also includes any work that may result in a spark entering a hazardous zone. For example: welding, blow-torches, flame cutting, any work involving an open flame, sparking from jack hammers or concrete saws, drilling, grinding, use of portable electric heaters, electrical tools/equipment that are not explosion proof or Document Custodian: HSSE Manager Uncontrolled when printed 13 Document Title: Z PTW Manual Version 3.2 24 Mar 14 intrinsically safe, sandblasting operations, operation of internal combustion engines. Confined space entry (CSE) - all work that meets the definition in AS/NZS 2865. For example: Manhole risers or tank sumps, all underground and aboveground tanks and vessels, car wash clarifier pits, excavations >/= 1.5 meters, trenches, tank vaults, storm water management systems, crawl spaces beneath buildings, service bay pit, oil-water separators, grease traps, canopy space where canopy is double skinned, any water or waste handling systems large enough for human entry. The above description is written to reflect Z works and Z requirements for permits for CSE. The AS/NZS 2865:2009 definition for CSE is detailed at section 10 - Glossary of this document and must be used to determine CSE activities being undertaken that a permit will be required for. All requirements set out in AS/NZS 2865:2009 are to be followed by the Contractor. It is the responsibility of the Contractor to ensure this. Excavations and trenching >/= 1.5 m Live Electrical Work - Modifications/alterations to energised conductors within switchboards and all work on electrical lines and equipment where the line is energised. Not including energising equipment and/or circuits for testing which is covered in medium risk activities. Abnormal work or maintenance, where a standard operating procedure has not already been approved for, that involves overriding or disabling a safety critical device; including leaving a site operating with a disabled safety critical device. Hazardous substance exposure of high residual risk or greater – including but not limited to: known asbestos and lead work. This includes any physical modification or demolition of specific building structures/materials (i.e. tanks, building insulation) that contain asbestos, lead, among other hazardous substances. Energized high pressure system work to hydrant lines. Not including energizing equipment and lines for testing or samples. Live Product Line work - includes all work on live energized product lines where either product or vapours are still present (i.e. modifications to existing fuel lines). Not including energizing equipment and lines for testing or samples. Work at height exceeding1.8 metres (measured from the lowest point of the worker‟s body) excluding work less than 5 meters when working from a scaffold erected by a competent person, or from a scissor lift, or boom lift, or a permanent ladder, where the fall protection is permanently engineered into the plant/equipment. Note all regulatory requirements must be met in the use of a scaffold, scissor lift, boom lift, and permanent ladder. Shop roof construction and/or installation. Canopy construction and/or installation Document Custodian: HSSE Manager Uncontrolled when printed 14 Document Title: Z PTW Manual Version 3.2 24 Mar 14 Working on single skin canopies. Working on a non-trafficable secondary surface, i.e. ceiling cavities, brittle roofs, skylights, among others. Tank removal and/or installation. Demolition – excluding soft strip out (except where Asbestos has been identified). Crane work – Any crane work including a hiab and excluding standard stock deliveries to a stock receiving area. Any other activity that has a high or critical residual risk when risk assessed using the Z risk assessment matrix at Attachment 5. Any other activity as determined by Z Energy‟s senior management and/or senior permit issuer. 5. Non-permitable Activities 5.1 Medium Risk Activities Medium risk activities as detailed below are required to be undertaken under the supervision of a Z prequalified contractor or Mini Tankers Zee or Retail Site Retailer, and in accordance with their HSSE Management Plan for the project/contract or Operational Manuals. Contractors who are not prequalified must work under a prequalified contractor. A SWMS or Job Safety Analysis (JSA) or Standard Operating Procedure (SOP) is required for Medium risk activities at all times. Restricted Space Includes any manhole risers or tank sumps, interceptors, grease traps, or ceiling spaces that do not meet the definition of a confined space Excavation between 0.5 meters and 1.5 meters High pressure system work to a compressed air system Work at Height 0.5 meters or greater that is not specified as a permitable activity. Non-powered hoist use involving a suspended load Work offsite in roadways – traffic management plan required and obtained. For example; for connection of services including sewer, electrical power, water. Work on low voltage equipment and circuits Includes fault finding/trouble shooting/diagnostics on electrical equipment where the equipment will be energised to allow this. For all repairs and replacement of parts “Lock Out Tag Out” is to be applied. All other de-energised prescribed electrical work including additions and alterations to final circuits, the installation of new and replacement equipment. Document Custodian: HSSE Manager Uncontrolled when printed 15 Document Title: Z PTW Manual Version 3.2 24 Mar 14 5.2 Erection of structures such as architectural load bearing structures Pump out of product from tanks Drilling of monitoring wells or soil borings Hazardous substance exposure of medium residual risk – including but not limited to: cutting MDF /SMF, glues, urea, formaldehyde. Hot work outside of the hazardous zone – including but not limited to: welding, grinding, and portable heat sources. Any other activity that has a medium residual risk when risk assessed using the Z risk assessment matrix at Attachment 5. Any other activity as determined necessary by Z Energy‟s senior management and/or senior permit issuer. Low Risk Activities All other works that are not set out as Permitable and Medium risk activities do not require a Permit or a SWMS/JSA unless specifically required by Z Energy. However, a hazard identification and risk assessment is required to be completed and appropriate control measures undertaken to eliminate or otherwise reduce risk. A record is to be maintained as evidence of this process. The works do require a Work Clearance Form to be completed daily by the contractor. The Work Clearance Form may form part of or all of the hazard identification and risk assessment required for low risk activities. 5.3 Deliveries Delivery only services – this is only for standard deliveries of stock to a stock receiving area. Suppliers are responsible for: completing a hazard identification and risk assessment for the delivery services including implementing any controls identified to eliminate or otherwise reduce risk, having competent delivery staff trained in manual handling, and drivers who hold a current driver‟s licence for the specific delivery task requirements. 6. System Documents Documentation for the PTWS is available at www.z.co.nz/ptwinfo. The primary PTWS documents are as follows: Work Clearance Form, which must be completed daily by all Contractors for all work and workers prior to commencing. Attachment 4 contains the Work Clearance that shall be used Safe Work Method Statement must be completed by all Contractors for permitable activities prior to performing the work. Document Custodian: HSSE Manager Uncontrolled when printed 16 Document Title: Z PTW Manual Version 3.2 24 Mar 14 6.1 Job Safety Analysis, or equivalent document must be completed by all Contractors for Permitable and Medium risk work prior to performing the work Permit (work permit, permit-to-work), which must be completed by the appropriate PI for all Permitable work. Attachment 7 contains the Permit form that shall be used unless applicable law requires a specific Permit or that the Permit contains particular information. Certificates, which where applicable must be used in conjunction with the Permit; refer Attachment 8 Permit Certificates A-H. Work Clearance Form A Work Clearance Form (WCF) is completed by the person performing the work or Contractor performing the work in conjunction with the Site Representative for manned sites. Work Clearance is a process of hazard identification and is used to verify that all activities on site are undertaken with the knowledge of the Site Representative. The Site Representative is to advise the person performing the work or Contractor if there are any operational or site conditions that may have an impact on performing the work safely (e.g. product delivery). The Work Clearance process is also designed to stop the work or trigger the need for a Permit if certain conditions are not met. The WCF is also used by the Permit Holder to renew a Permit on a daily basis provided the Permit validation period has not expired. If the Permit validation period has expired, the Permit Holder must stop the work and consult the Permit Issuer. A WCF is required daily for all work. It is to be completed prior to the start of the work activity for the day, and closed by sign out with the Site Representative at the end of the day‟s activities. Where more than one worker is involved in the activity a tool box talk is to be conducted with all the workers prior to starting the work to discuss the hazards identified on site and the required control measures. A WCF must be completed at unmanned and closed locations, but a signature by the Site Representative is not required. The unmanned or closed status shall be noted on the Work Clearance Form. A minimum of two copies of the WCF are required: 1. One site copy to remain on site 2. One Contractor copy to be filed by the Contractor The WCF is at Attachment 4. 6.2 Safe Work Method Statement/Job Safety Analysis Document Custodian: HSSE Manager Uncontrolled when printed 17 Document Title: Z PTW Manual Version 3.2 24 Mar 14 SWMS/JSAs are the document that details specific safety requirements for the job. SWMS/JSAs are required for Permitable and Medium risk works. The requirements are: 1. The Contractor who is to perform the work shall complete the SWMS/JSA. 2. For permitable activities, the Permit Issuer shall review the SWMS prior to authorising the Permit. 3. For medium risk activities, the SWMS/JSA shall be reviewed by the contractor‟s supervisor, or representative, prior to the work starting. 4. The PI shall document on the Permit any additional controls that the Contractor must undertake to manage hazards and associated risks present on the site. The Permit shall align with and compliment the Contractor‟s SWMS/JSA. 5. The Permit Holder shall ensure that the SWMS/JSA and permit are followed. A template for a SWMS is included at Attachment 6 A SWMS/JSA is a process of breaking down work activities into individual tasks, identifying associated hazards against these tasks, risk assessing them, and then determining appropriate methods of eliminating otherwise, isolating or minimising the identified hazards for the tasks to be undertaken. The steps in completing a SWMS/JSA are: 1. Completing a task list, e.g. break down of work activities into tasks. 2. Completing a hazard identification assessment for all tasks. 3. Identify through risk assessment the tasks/hazards that are high risk. 4. Identifying control measures to be implemented to eliminate otherwise isolate, or minimize the hazards and risks identified. 5. Ensure the control measures reflect the hierarchy of controls and the degree of risk. 6. Include the Z permit requirements for the task/hazard. 7. Assess the residual risk for the hazards identified a. If the residual risk is high return to step 4 and reassess the control measures to reduce the risk. b. If the risk is medium consider further control measures to reduce the risk and/or monitoring and review requirements. 8. For high risk work assign a responsible person and describe how the control measures are to be implemented, monitored and reviewed; and assign a person Document Custodian: HSSE Manager Uncontrolled when printed 18 Document Title: Z PTW Manual Version 3.2 24 Mar 14 responsible for ensuring this occurs. Persons performing the identified work and/or Contractors must prepare SWMS/JSAs taking into account: circumstances at the workplace that may affect the way in which high risk work is carried out, and the requirements detailed in any relevant Site Specific Safety Plan for the work and/or the HSSE requirements for the workplace, and be expressed in a way that is readily accessible and understandable to persons who use it. Compliance with SWMS/JSA - If work is not carried out in accordance with the SWMS/JSA for the work, the contractor or site representative must ensure that the work: 6.3 is stopped immediately or as soon as it is safe to do so, and resumed only in accordance with the SWMS/JSA. Permit A Permit is a document used to describe the work to be performed, tools to be used and hazards associated with the planned work. A Permit is issued for a particular task or activity, not for multiple activities over a period of time. It identifies the requirements to be in place to eliminate, otherwise isolate or minimise the hazards/risks associated with the task or activity. Together the contactor‟s SWMS/JSA and the Permit shall cover all of the risks and identify the necessary control measures to ensure the risks are as low as reasonably practicable. A Permit is required for Permitable activities at all times. A Permit is required for Medium risk works where required in the main contractors HSSE Management plan for the project/contract. The Permit must be accepted by the PH and authorised by the PI prior to the work commencing. Once the work is complete, the PH signs the Permit and submits the completed Permit. The PI must sign the Permit as evidence of having verified the job is complete and that the Permit is closed. The Permit and all associated documents (i.e. Work Clearance Form, SWMS/JSA, etc.) shall be available at the work site readily accessible to all Contractor employees. 6.4 Permit Attachments Document Custodian: HSSE Manager Uncontrolled when printed 19 Document Title: Z PTW Manual Version 3.2 24 Mar 14 Various activities require attachments to the permit, in order to allow for further detail of the tasks to be recorded should it be required. Attachments are separate forms which are completed by the PI, PH or AGT during the works. The appropriate Attachment Forms are to be included as part of the Permit. Attachment A – Hot Work Certificate Attachment B – Confined Space Certificate Attachment C – Work at Height - roofs, canopies and temporary structures Attachment D – Excavation Certificate Attachment E – Isolation Certificate Attachment F – Tank Removal / Installation Certificate Attachment G - Demolition Certificate Attachment H - Overhead Crane Certificate 6.5 Contractor Prequalification Process Contractors are required to demonstrate, via the Z prequalification process, that they have the necessary HSSE management systems in place to manage HSSE risks in their given field. A typical contractor prequalification process may consist of the following components: A review of the Contractor‟s HSSE plan and supporting documentation A HSSE capability and competency questionnaire to be completed by the Contractor An evaluation of the Contractor‟s previous HSSE performance An HSSE audit of the Contractor‟s performance The prequalification records are held in Z‟s prequalification vendor‟s software system which is accessible by Z and the contractor themselves. The prequalification is renewed every two years. 7. System Rules 7.1 Permit Validity A Permit is valid for a specific task or activity, on a specific site, within a specific period of time. The normal working hours for the project /contract are to be used as the basis for determining the specific period of time. Permits may only be issued for a maximum of five (5) consecutive calendar days, as Document Custodian: HSSE Manager Uncontrolled when printed 20 Document Title: Z PTW Manual Version 3.2 24 Mar 14 the benefits of a discussion with a PI and daily handover and signing of the Permit may erode over a period of time. Site conditions may also change over time and require further discussion. A Permit that is issued for work that extends beyond one day must be renewed at the commencement of each day. Provided site conditions have not changed and the Permit validation period has not expired, the Permit Holder is able to renew a Permit by completing a new Work Clearance Form on a daily basis. If the Permit validation period has expired, the Permit Holder must stop the work and consult the Permit Issuer. The Permit Holder must renew the Permit via the Work Clearance Form each day. Permits may be applied for in advance of the work, but the Permit shall be issued immediately prior to the performance of the permitted work. Exception to this is in the case of Remote Permits which may be issued up to 24 hours in advance. 7.2 Remote Permitting Whilst face-to-face communication between Permit Issuer and Permit Holder is recommended and must be used wherever possible, there may be situations where this is not practical, e.g. work on remote sites of a low risk nature for a very short timeframe or an emergency situation where timely assistance from emergency services is not available. In these instances other measures shall be taken to verify that risks are identified and adequately communicated. A remote Permit can ONLY be issued if ALL of the following criteria are satisfied: The PI has knowledge of the site or has reliable drawings and site data The PI has a detailed knowledge of the task and activities to be permitted The PI has experience working with the Contractor and individual PH. The Z senior permit issuer or delegate confirms remote permitting is appropriate and the above criteria have been met. In situations such as this, the following process is to be conducted: The PI and the PH complete the Permit over the phone, taking into account the site conditions and referring to the Site Operator / Retailer if required The completed Permit is sent to the PH on site who reviews the specified conditions and confirms their understanding of the conditions and their ability to comply with these conditions by signing the Permit The completed, signed Permit is then faxed or scanned and emailed back to the Permit Issuer. The Permit Issuer must verify that they have a copy of the SWMS/JSA that has been completed by the Contractor for the activity. Document Custodian: HSSE Manager Uncontrolled when printed 21 Document Title: Z PTW Manual Version 3.2 24 Mar 14 7.3 The contents of the SWMS/JSA must also be discussed in light of the Permit conditions. A second PI must also approve the remote permit and at least one of the PI‟s must be the Z senior permit issuer or delegate. The communication between all parties, (PH, and two PIs) can be done remotely from each other. Where possible the use of technology options should be considered to improve communications between all parties, i.e. video conferencing. Self-Permitting No one is allowed to issue a Permit to themselves, as this would defeat one of the prime objectives of a PTWS of having a discussion about the safety of a project. 7.4 Contractor Permitting A PI who has met the competency requirements to be a Z PI may issue a Permit to another person in the same Contractor organisation. The administrator will review a sample of these permits each quarter to ensure the permit requirements are being maintained. 7.5 Blanket Permits Blanket Permits are not permitted. Long-term routine work is more effectively controlled by means of standard operating procedure or work instruction than by the use of Blanket Permits. 7.6 Derogations and standard operating procedure approval process On occasions an approved standing operating procedure (SOP)may be more appropriate for repetitive, routine activities. A SOP can be developed and for work to be conducted against the SOP rather than a permit. This could evolve from projects that require the same implementation of minor work in a hazardous area on the forecourt of all retail sites. When the potential for the work to be conducted under an SOP is identified the following process is to be followed: 1. The relevant Z representative for the work in consultation with the identified contractor for the work is to conduct a risk assessment and develop the SOP, and SWMS/JSA (which may be one document). 2. The competency of personnel and the equipment required to undertake the work are to be detailed in the document(s) as well as the requirement to complete a Work Clearance Form daily. 3. If the work is for a project rather than ongoing routine work, the project timeline for the work is to be detailed. 4. A permit issuer is to be engaged to review and confirm the developed document(s) are appropriate to manage the foreseeable risks. 5. The final documents are then to be provided to the Z senior permit issuer for review Document Custodian: HSSE Manager Uncontrolled when printed 22 Document Title: Z PTW Manual Version 3.2 24 Mar 14 and submission to the CEO. 6. The CEO will review the documents and consider their acceptability for a PTWS derogation to be approved. The Z derogation procedure is available at: http://matters.gel.local/HSSE/HSSE/Published_Documents/HSSE_Procedures 7.7 Changes in Conditions In the event of any of the following circumstances occurring during the course of an activity under Permit control, the Permit Holder must suspend the work and refer directly back to the Permit Issuer on the appropriate course of action: The specified equipment or tools to be used are not available The type of work changes The process conditions change (e.g. unexpected release of product / gas nearby) An emergency in the area Weather conditions change and increase the risk profile of the works Conflicting work is being undertaken by another Permit Holder or Contractor In the event that a tanker arrives to complete a delivery of product on site, work is to stop and be assessed for additional risk. Hotwork is to stop and stay stopped for a minimum of 30 minutes after the delivery has been completed. 8. Training and Competency Requirements 8.1 Permit Issuers PI candidates must: 1. Attend the Z PTWS Orientation session and score a minimum of 90% on the qualifying test. If a 90% score is not achieved, the PI candidate may retake the test. Candidates may take the test up to 3 times. The PTWS Orientation session is provided by Z. 2. PIs must also successfully complete the NZ Qualification Authorities (NZQA) Unit Standard (US) 17590 Permit Issuer, to further understand their responsibilities as a permit issuer and the common hazards to be covered in a permit. This course must be completed prior to the PI being confirmed to undertake permit issuing without supervision by a competent PI. 3. Following the successful completion of the Z PTWS Orientation and qualifications as identified below for specific permits, the PI can complete permits under supervision. Document Custodian: HSSE Manager Uncontrolled when printed 23 Document Title: Z PTW Manual Version 3.2 24 Mar 14 For each type of permit the permit issuer is able to complete the PI must complete two successful permits under supervision and be deemed competent by the supervisor to issue permits unsupervised. The supervisor will be a competent and experienced PI who has been identified as suitable to supervise PI on probation. Note the supervisor is to confirm that the PI has demonstrated for the permitable activities supervised: a practical understanding of the relevant hazards and risks the ability to communicate effectively the permit requirements to the PH, and the correct PTW process and documentation. To ensure PIs have competency in the risks associated with particular permitable activities, PIs must have approximately 4 years work experience in a relevant supervisory role for the permits they will be confirmed to issue, and have successfully completed and hold a current qualification in the following NZQA USs to issue specific permits: Permit Type Qualification Confined Space US 3058 Gas testing in high risk industries US 25510 Atmospheric testing US 17599 Confined Space planning US 18426 Hazard Identification Hot Work US 3058 Gas testing in high risk industries US 25510 Atmospheric testing US 25043 Energy isolation Work at Height US 17600 Safe work practices for working at heights US 25045 Employ height safety equipment in the workplace Excavation US 14611 Excavation hazards and traffic control US 10543 Protect underground services during excavation and reinstatement Electrical / Mechanical Isolation US 25043 Energy isolation The above mentioned training is to be revalidated at the set intervals specified by the approved training organization or 3 yearly whichever is the minimum timeframe. Document Custodian: HSSE Manager Uncontrolled when printed 24 Document Title: Z PTW Manual Version 3.2 24 Mar 14 8.2 Permit Holders It is the responsibility of the PH Company to ensure the PH is familiar with the Z PTWS. It is recommended that PHs successfully complete the NZQA US 17588 to further understand their responsibilities and the permit process. 8.3 Authorised Gas Tester An authorized Gas tester must successfully complete and hold a current qualification to the NZQA US 3058 Gas testing in high risk industries and US 25510 Atmospheric testing, and be trained in the use of their own/company gas detector device The above mentioned training is to be revalidated at the set intervals specified by the approved training organization or 3 yearly whichever is the minimum timeframe. 8.4 Worker Qualification Personnel undertaking works for Z are to be adequately trained by their employer and training records are to be available upon request by Z. The minimum training requirements for specific roles with an HSSE focus for the activities are detailed in the Z Contractor Management System Standard for Construction and Maintenance Performance available at: http://z.co.nz/ptwinfo 9. Audit & Review of PTWS 9.1 Audits Audits of permitable activities documentation, as a minimum, should be carried out as part of the Z HSSE audit program every six months. These audits are to be arranged by the HSSE Assurance Manager. The Asset Manager or Asset HSSE Specialist i s to peer review the audit and it is to be reviewed by the HSSE Assurance Manager of Z. 9.2 Review and Assurance The HSSE Manager in conjunction with the Risk and Assurance Manager, shall annually review the effectiveness of the PTWS and modify it where necessary as part of continuous improvement of HSSE management. Factors to be taken into account include: Changes in legislation Industry guides Review of Incident Reports Inspection & Audit findings Feedback from users Document Custodian: HSSE Manager Uncontrolled when printed 25 Document Title: Z PTW Manual Version 3.2 24 Mar 14 9.3 Reporting The results of audits, reviews and assurance are to be reported to the Business Risk Meeting by the HSSE Manager. 9.4 Records Permits & supporting documentation must be retained according to legislative and Z requirements. Permits are to be kept by the PI for six years minimum, and 40 years for any permits involving asbestos work or health monitoring. Training and competency records for Permit Issuers must be retained according to legislative and Z requirements. 10. Glossary Term Competent person Confined Space (as per AS 2865: 2009) Contractor Crane Hazard Document Custodian: HSSE Manager Definition A person who has acquired through training, qualification or experience the knowledge and skills to carry out the task, and where required has met the regulatory requirements to carry out the task. An enclosed or partially enclosed space that is not intended or designed primarily for human occupancy, within which there is a risk of one or more of the following: (a) An oxygen concentration outside the safe oxygen range. (b) A concentration of airborne contaminant that may cause impairment, loss of consciousness or asphyxiation. (c) A concentration of flammable airbourne contaminant that may cause injury from fire or explosion. (d) Engulfment in a stored free-flowing solid or a rising level of liquid that may cause suffocation or drowning. Also refer to AS 2865: 2009 section1.5.5 notes 1-5 which provide examples of enclosed or partially enclosed spaces that may meet the definition criteria for a confined space. Any contractor company or subcontractor company engaged to carry out works for Z and any workers of such companies. Crane means a powered device: i. That is equipped with mechanical means for raising or lowering loads suspended by means of a hook or other load handling device; and ii. That can, by the movement of the whole device or of its boom, jib trolley or other such part, reposition or move suspended loads both vertically and horizontally; and Includes all parts of the crane down to and including the hook or loadhandling device, and all ropes, wires, chains or other devices used to move the hook, or device; but does not include lifting tackle that is not an integral part of the crane An activity, arrangement, circumstance, event, occurrence, phenomenon, process, situation, or substance (whether arising or caused within or outside a Uncontrolled when printed 26 Document Title: Z PTW Manual Version 3.2 24 Mar 14 Term High Pressure HSSE Inspection Isolation JSA Low Voltage equipment Electricity (Safety) Regulations 2010 Monitoring Non-routine work Permit Permit Validity Period PH PI PTWS Review Risk Safety critical device Document Custodian: HSSE Manager Definition place of work) that is an actual or potential cause or source of harm; and include: i. a situation where a person‟s behaviour may be an actual or potential cause or source of harm to the person or another person; and ii. without limitation, a situation described in subparagraph (i) resulting from physical or mental fatigue, drugs, alcohol, traumatic shock, or an-other temporary condition that affects a person‟s behaviour. High pressure covers pressures higher than normal, especially higher than atmospheric pressure. Z hydrant operating pressures - below 1000kpa (145psi) and test pressures below 1300kpa (190psi) Health, Safety, Security, Environment Checking the Permit controls in practice using a using a checklist or equivalent document. A physical barrier between a source of energy (mechanical, electrical, hydraulic or static head) or process materials and a place of work. Job Safety Analysis Low voltage means any voltage exceeding 50 volts AC or 120 volts ripplefree DC but not exceeding 1000 volts AC or 1500 volts ripple-free DC. For example: 50V alternating current and 120V direct current up to 1000V AC and 1500V DC Routine checking of Permits and controls in the course of the work Work that is NOT performed regularly in a controlled environment with an approved Standing Operating Procedure or equivalent document. For example non-routine work is a work activity that is, but not limited to, any of the below: • Performed infrequently • Outside of normal duties • Does not have an approved standing operating procedure • Performed in a different way from the standing operating procedure • Has never been performed before The terms „permit-to-work‟, „permit‟ or „work permit‟ refer to the paper or electronic certificate or form which is used as part of an overall system of work, and which has been devised by Z to meet its specific needs. Whether it is manually or electronically generated, the permit is a detailed document which authorises certain people to carry out specific work at a specific site at a certain time, and which sets out the main control measures needed to complete the job safely. The period during which a Permit may remain active, and after which the work site controls must be reassessed. Permit Holder Permit Issuer Z‟s Permit to Work System Examining the fundamental design of the system to see whether it should be changed in the light of experience. The probability and consequences of a hazard resulting in harm or damage. An essential safety device designed to prevent injury or incident; including devices required to de-energize a hazardous energy source. For example: A part, assembly, installation, or production system with one or more essential characteristics that, if not conforming to the design data or quality requirements, would result in an unsafe condition that could cause loss Uncontrolled when printed 27 Document Title: Z PTW Manual Version 3.2 24 Mar 14 Term Site Representative Soft strip out SWMS Work Worker Workplace WCF Z Zee 11. Definition or damage to the end item or major components, loss of control, or injury to personnel. Person responsible for the overall safety of a particular site. This could be the Site Operator or a designated employee. Non-structural deconstruction, including removal of all appliances, windows, doors, and other finishing materials. Safe Work Method Statement The works, including temporary works, to be executed in accordance with the Z contract. A person is a worker if the person carries out work in any capacity for Z or at a Z workplace, including work as: A Z employee A contractor or subcontractor An employee of a contractor or subcontractor An employee of a labour hire company who has been assigned to work for Z or at a Z workplace An apprentice or trainee A student gaining work experience A volunteer A place where work is carried out for Z or on behalf of Z and includes any place where a worker goes, or is likely to be, while at work. This includes a vehicle, vessel, aircraft or other mobile structure, and any waters and any installation on land, on the bed of any waters or floating on any waters. Work clearance form; a document used to identify and review the hazards inherent in the work being undertaken. Z Energy Limited Contractor for Mini Tankers providing Direct Machine Refuelling and other refuelling services Attachments All Attachments to the PTWS Manual are held separately in a stand-alone document for ease of updating. The Attachments are available at: http://z.co.nz/ptwinfo Attachment 1 – Permit To Work System Flowchart Attachment 2 – PTWS – Activity Table Attachment 3 – (Typical) Retail Site Hazardous Areas Map Attachment 4 – Work Clearance Form - roofs, canopies and temporary structures Attachment 5 – Z Risk Assessment Matrix Attachment 6 – Safe Work Method Statement Template Attachment 7 – Permit to Work Form Attachment 8 – Permit Certificates A-H Attachment 9 – Identification of a Confined Space Decision Tree Document Custodian: HSSE Manager Uncontrolled when printed 28
© Copyright 2025