REPUBLIC OF IRAQ MINISTRY OF OIL SOUTH OIL COMPANY TENDER DOCUMENTS ENGINEERING, PROCUREMENT AND CONSTRUCTION OF SUBSTITUTION THE VALVES FOR ZB-1 DEPOT WITH COMPLETE CONTROL SYSTEM (TURN KEY PROJECT) JUNE - 2014 (REV.0) ]1[ 1- INTRODUCTION This project consist of engineering procurements and construction to substitution all the valves, consist of all control systems accessories and integrated control room building , the proposal must cover all engineering design details , supply all the valves and control room materials , installation in zb-1 depot and supervision for startup & commissioning . The battery limits should be covered all area shown in attached plot plan, The project should be done as (turnkey project) . Bidder should visit the site (ZB1-Depot) before submitting his offer and consist the technical offer the max shorten plan to avoidance any shut down . 2- LOCATION Iraq-Basrah –ZB-1 Depot 3- ENVIRONMENTAL CONDITION Ambient temp. Humidity (November to March) % Max rain fall per day mm Max wind velocity Wind velocity for design : : : : : -5 , 60 °c 80 - 90 200 140 km/hr. 160 km/hr. 4- Codes and Standards: Design, fabrication and installations of the equipment systems shall be in accordance with goods industrial practices and in compliance with the latest editions and revisions of the following codes and standards as applicable: -American national standards institute, ANSI -American petroleum institute API, API 6D -American society of mechanical engineers (ASME) B31.3 -AASHTO-ACT-318-2011M-ASTM - FLANGES MATERIAL . - FLANGES DIM. A105 - N ASME B16.47 SERIES A , ASME B 16.5 - FITTINGS ASTEM / ASME A 234: GRAD WPB FOR CARBON STEEL OR A860 / MSS-SP75: GRAD WPHY ( 42 – 70 )FOR HIGH YIELD STEEL - STRUCTURE A – 36 ]2[ - STUDS & NUTS A 193 / 194 H - All piping to be acc. to API 5 L PSL2 ,A1 - Low voltage switchgear IEC 60439- 1 - Low voltage circuit breakers IEC 60947- 2 - Low voltage components IEC 60947- 4 - Degree of protection IEC 60529 - ACI codes ( American Concert Institute ) for concrete works > - ASTM –for testing Materials . - ASCE , IBC , UBC . - المواصفات القياسية العراقية. - MSS-SP44 - FIRE TEST API 6FA & ISO 10497 - EN – 10204-3.2 MILL TEST FACTORY 5 - Technical offer requirements The offer shall include the following documents:123456789- Process flow diagram for the complete project. P&I diagram. Data sheets for all equipment's and device Necessary catalogue Execution period Execution plan and Description Vendor list according to SOC requirement. API & ISO certificate Bidder should submit a three years' experience of similar past Executed projects as a part of their technical offer 10- Bidder should submit time schedule for procurements, Shipping, Installation and commission. 11- The bidder should take into consideration a suitable plan to avoid any shut down which is very important in technical evaluation. 12- The design code for all the valves from the commitment of the contractor to avoidance as possible to change the inter connecting pipes. 13- The announcement should done as tow stages technical and commercial . 14- Referring to the structural testing materials laboratory that is must be an approved and international laboratory. 15- Assembly drawing for valves body and gear box include dimensions, manufacturers names, material list of parts and all standards . 16 . Quality assurance plan for all equipments . ]3[ 6- SCOPE OF WORK The project is an EPC turnkey- lump sum type The scope of work of zb-1 depot shall include: 1. Basic & detailed design approved by soc . 2. Supply of all materials and equipment. 3. Hazop study, safety integrity level (SIL) & surge analysis shall be carried out by bidder, any additions required after HAZOP study & surge analysis or during detail engineering shall be within bidder scope of supply at no additional cost so bidder shall take this into consideration at bidding stage and we don’t have as built drawing . 4. 5. Integrated Control room building. Control panel for each booster pump and tank devices with remote operation( controlling ,operating, alarming and Start / Stop ,Auto / Manual selecting). 6. Station control Panel for control and operation to all booster pumps , All valves in zubair /1 depots operation and select the receiving & pumping rout & auxiliary system . 7. Marshaling penal for connection cable . 8. Each control panel include enunciator showing All Alarm& trip signal( for modern control & system PLC&HMI touch screen ) 9. 4 HMI with monitoring size 26”(PC) for operation 10. Engineering workstation and maintenance laptop, with All PLC s software including a backup copy &open license . 11. Replace All control cable and Junction box(New cables should be Hydrocarbon Resistance cable type) 12. Erection & installation shall be done by bidder. 13. Commissioning, start up (including operating procedure) and test run activities to demonstrate proper performance of the depot and achieve the required performance guarantees. 14. Start-up and commissioning spare parts, chemicals and lubricants first fill for operation after commissioning shall be provided by the bidder. A price list of recommended spare parts for two years operation shall be provided by bidder. SOC shall select the required spare parts for the bidder to procure. 15. . Bidder shall submit a vendor list for each group of equipment and materials & shall subject to SOC for study and approval. 16. Supply material, Man powers and construct valve support for all project items according approved drawings and method of statement. 17. Re prepare the site according approved method of statement and repair all damages. The works include all testing, QA/QC, and safety activity and requirements 18 . All civil work, electrical , instruments and mechanical should be from contractor responsible. 19. All necessary catalogs for spare part and for maintenance. 20. All cable shall be hydrocarbon resistance with armored. 21. Make all survey works that is required. 22-Make all required soil Investigations. 23- Submit calculations and design drawings for each item for approval. 24. Submit Method of statement for each items of works and no works will be proceed before get approval ,include QA/QC , Safety Plan , And note that the works includes all damages that is happening because of the works and re preparing all area that is changes because of the work items ( Roads , Walkways ….etc ) 25. For any change works complete as built drawings is required. 26. the responsibility of the contractor is redesigning and construction basins according to the new valves especially in operation and maintenance . moreover the responsibility of the contractor is cutting or replace the pipes if required and shouldn’t change the philosophy of the operation and should be approved by SOC ]4[ SOC can change or refused any items that is not obeying requirements. 27. Submit rigging Plan for related items. 28- the mobilization of the all valves substituted from the contractor responsibilities to the yard is fixed later out of zubair depot . 29 . Reducing oil levels in the tanks to the required level in order to replacing valves and desludging if they are found after our pumps are stopped of the ability of sucking oil that’s from responsibility of contractors. 30.Dismanting and removing of all the valves from the contractor responsibilities 7) MAIN PROJECT ITEMS:- Supply and install all the valves with all accessories. - Civil work for valves foundation, pipes and valves supports, walkway, services platforms , control room building ....etc. - Supply and install main Control system and instrumentation. - Electrical system:, cabling, earth system, motor operating valves panels ..…etc - All the valves shall be ball valves excluded (drain valves , some of receiving and pumping valves) 8 ) Origin of Materials Origins for materials to be) USA, west European( UK , GERMANY , FRANCE , ITALY , NORWAY , SWEEDN , CANADA, NETHERLAND , BELGIM , AUSTRIA, DANMARK , FINLAND , and Japan (. And should be accepted to SOC. related, certificates and catalogue to be submitted with the offer . and acc. To attached vendor list. 9 ) Third Party Inspection:3rd party activates are obligation of SOC acc. to contract between SOC and the third party inspection that have the right to inspect all the materials and reject the defected one during the manufacturing period and all inspection certificate should be acc. EN 10204 type 3.2 table A1 summery of inspection documents and inspection team of SOC should be visited the valves factory to follow 3rd party activities. 10) Testing The contractor should submit test plan for all valves and control system equipment's, tests program before suitable time for study at least two months before the first scheduled test . the following tests should be witnessed by SOC engineers and 3rd party .( all the cost will be beard by contractor ). 11) factory test ]5[ All factory testing should be acc. (ITP) inspection test plan which is prepared by manufacturer and submitted to SOC to approval before manufacturing (by inspection team and 3rd party) and schedule time. 12) Spare parts :Spare parts for 2 years operation to mechanics, electric and control for all project equipment's (list to be submitted with technical offer with priced list) 13) Valves All valves to be ball valve full bore flange type acc. API 6D face to face, Dim. Acc.to international standard and site Dim. Valves testing - acc. to API 598. Body : carbon steel RF FLANGED , stem : 17-4 – PH + ENP OR SS 410 ( 13% CR ) + ENP ,Seats& BALL : A182 F6 + ENPOR A 182 F316 + ENP All valves should be motorized type and ball valves excluded ( drain valves , some of receiving and pumping valves …. etc ) with following specification: Motorized valve 3ph, 380V,50Hz , Pf=0.85-0.9 , Insulation Class :F, The scope work includes the design , export packing , shipping and delivery to SOC , Replacement of old valves with all modification that may be need , erection / installation , local testing and commissioning for all valves including civil works. The tendered is allowed to visit our site in Zubair/1 , to obtain by himself on his own responsibility all information that may be necessary for preparing of offer and detailed design. The cost of visiting our site shall be at the Tenderer's own expense. The Tenders shall be submit technical offer without commercial in the first stage The valve operation shall have tow speeds- 0 – 90% fast speed and go to 100% Dribble slow speed for valve open / closed operation as per process needs this is applicable as service only . The size, torque, speed and duration for closed and open power (capacity of the actuator) and wiring diagram of the actuator according to the valve design and specification. Motorize 3-phase (380 V – 50 Hz) induction type motor syncropack or Automatic actuator valve actuator ingress protection : IP68 – I I2 GE EXDIIBT4 / T3 Ambient Temp. : ( - 20 – 70 oC) THERMO START TRIP : 132 C OPERATING CIRCUIT USING REVESRING CONTRACTOR OR SOLID STATE STARTER MODEL UTILIZING THYRISTER DREIVE AND Their ASSOCIATED CONTRAL ELECTRONIC Control voltage (24V AC/DC) (110 V AC/DC), for auxiliary limit switch control voltage (240V AC/ 110 V DC), with (open-close-stop) push-button and (local remote) switch- (full open + full close) limit switch contacts for indication for control room. Duty: Input Signals: Feedback signal: Setting: Open-Close, short-time duty, according to IEC 60034 (S2- 15 min) class A and B Open-stop-close Open-stop-close, selector switch local-remote, collective fault and 4-20mA position feedback signal Non-intrusive, settable at motor control without need of special tools ]6[ Explosion certified : Enclosure: Anti-condensation heater: Lighting suppressions External earth stud Valve mounting: Motors: Motor protections: Motor connections: Local controls: Hand Wheel: Corrosion Protection: Final color : Internal connection IECEX, II2G EXd zone 1 group IIC, temperature class T4/ T3 IP 68, according to EN 60529 against submersion up to 9 M head of water for 96 hours allowing 10 operations Yes Yes According to ISO 5210 with plug sleeve connection to valve shaft 3 Phase 380V AC (+/- 10%), 50 Hz (+/- 2%) insulation according to IEC 85 class F (155oC) 3 thermal monitoring devices or direct embedded thermal trip in the motor windings Internal by plug and socket Type AUMATIC or syneropack motor controls (contactors), push buttons OPEN-STOP-CLOSE-RESET, lockable selector switch LOCAL-OFF-REMOTE, Bluetooth interface and LCD graphic display with plain text and in world languages including Arabic, diagnosis symbols, graphs and five indication lights for status information. Side mounted hand wheel for manual operation. Clockwise operation of hand wheel shall cause clockwise movement of output drive. Hand wheel shall be marked with an arrow and the word "CLOSE". Hand wheel engagement shall be of spring loaded push mechanism type and required manual declutching. Actuator must provide a switch signal when in manual mode. Under manual operation, hand wheel shall drive the worm shaft. Self-locking shall be maintained in hand operation. Hand wheel shall automatically disengage when the electric motor is energized. According to EN ISO 12944-2, classification of environments C$. actuators shall be corrosion protected (KS) with a primer coating and a two layer powder coating consisting of an epoxy primer coating and polyurethane top coating with thickness at least 140 µM. Silver grey similar to RAL 7037 Actuators to be connected with SIMA master station or pack scan can operate 240 valves. - MOV shall have two stroke speeds.0 to 90% fast speed and 90 to 100% dribble/ slow speed for valve open/close operation as per process needs. This is only for the liquid service. The speed shall be adjustable in field with hand held calibrator unit. - numbering and marking for each piece acc to API standard including the necessary data such as current , power, torque , class , type of materials …..etc ]7[ 14) Mechanical list ( quantity req. for each) approximately . valve to be supplied with flanges. Gaskets and studs with 2 / nuts, designed acc. to API standard, dimensions acc. to ANSI standards. Tanks (1st stage) .No Valve )inch(D Class Type .Qty 1 2 3 4 5 Inlet & outlet Balance Agitator Main Shared 36 36 32 36 42 150 150 150 150 150 Gate Gate Gate Gate Gate 10 10 8 5 5 6 7 Drain Rain 4 6 Total 150 150 Gate Gate 40 10 8 Notes For two tanks For all the tanks 1st and 2nd stage 88 Tanks (2nd stage) Notes Qty. 20 20 20 5 10 20 10 105 Type Gate Gate Gate Gate Gate Gate Gate Class 150 150 150 150 150 150 150 D(inch) Valve No. 36 Input &outlet 1 36 Balance 2 20 ,18 Agitator 3 36 Main 4 6 Drain 5 4 Drain 6 6 Rain 7 Total 8 • Booster Pumps (1st stage) Notes Qty. 5 Type Gate ]8[ Class 150 D(inch) 42 Valve Suction No. 1 5 5 5 20 Gate Gate Ball 150 150 150 36 36 16 Total Discharge Recycle Bypass 2 3 4 5 Type Gate Gate Ball Ball Class 150 150 150 150 D(inch) 42 36 36 16 Total Valve Suction Discharge Recycle Bypass No. 1 2 3 4 5 Class 600 600 600 300 D(inch) 30 30 12 20 Total Valve Suction Discharge Recycle strainer No. 1 2 3 4 5 • Booster Pumps (2nd stage) Notes Include 1st and 2nd dicharge Qty. 5 11 5 5 26 (1-1) Main Pumps (Turbine) Notes Qty. 3 3 3 6 15 Type Gate Gate Gate Gate Relief valves Notes Qty. 10 39 4 10 13 2 78 Type Gate & Ball Gate - Suggested Valve ]9[ Class 600 150 150 600 150 150 D(inch) 12 12 6 12 12 6 Total Valve Relief Relief Relief felexflo felexflo felexflo No. 1 2 3 4 5 6 7 Notes Qty. 10 10 8 28 Type Gate Gate Gate Class 150 150 150 D(inch) 36 36 32 Total Valve No. Input &outlet 1 Balance 2 Agitatior 3 4 )2-1( Main Valves (Receiving & Pumping) Notes hydraulic Qty. Type Class D(inch) 600 600 150 600 150 600 300 600 600 600 600 300 150 150 600 600 300 600 300 600 300 48 42 42 30 36 36 36 32 30 26 24 24 24 22 20 20 20 18 18 16 16 1 600 14 3 7 600 300 12 12 7 6 7 1 3 8 2 hydraulic 2 2 1 2 1 5 1 7 1 2 1 1 6 3 Gate or Ball 80 Total ]11[ Valve No. 1 2 3 4 5 6 7 8 9 10 Receiving 11 & 12 Pumping 13 14 15 16 17 18 19 20 21 22 23 24 25 The final total valves Notes Include (felexflo) Include (felexflo) Include (felexflo) Qty. 7 6 22 8 119 2 2 16 9 5 1 2 1 1 8 10 8 10 1 1 6 3 10 1 26 7 52 36 60 440 Class 600 600 150 600 150 300 600 150 600 150 600 600 300 150 600 150 300 150 600 300 600 300 150 600 600 300 150 150 150 D(inch) 48 42 42 36 36 36 32 32 30 24 26 24 24 22 20 20 20 18 18 18 16 16 16 14 12 12 12 6 4 Total Note : This is not final total valves , it can be changeable (increase or decrease) . ]11[ No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 (-1 Vendor list item Body valves Actuator valves control valves and self regulating valves(a) relief valves Electric and instruments vendors walton weir pacific Cameron dafram alfa valvole valvitalia petrol valve lcm italia pbv grove valves petrol valves tyco cort kit2 Cleveland industrial valve Mokvold w.k.m Rotork ( UK ) AUMA ( GERMANY ) fisher masoneilan yamataky mokveld alfa valvole farris masoneilan dresser anderson crosby greenwood broady triangle sempell alfa valvole mokveld panalarm ashcroft honey well yamatake abb ronan fisher rosemount foxboro siemens ]12[ cables bicc(uk) general cable (spain) delta(uk) nexans (france) cic (france) batt cables (uk) motor control centre and m.v. switch gear abb(italy) siemens (germeny) eaton(usa) schneider (france) areva (france) ge (usa) fuji (japan) siemens allen bradly GE Schneider yokogawa(netherland) prestigious discovery telemechanics plc control ]13[ BREAK DOWN LIST ITEM 1 2 3 4 5 6 7 8 9 10 DESCRIPTION UNIT QTY basic & detailed design engineering, and fabrication drawing acc. standard. final, data sheets , assembly details & plant installations to be submitted in 5 hard copies & 5 electronic copies . Piping, fitting, valves, complete, list Inter connecting piping Electrical system consisting of the followings:- Actuators - Motor operating valve panels - Cable control cabling with accessories PLC control panel(all control panels are redundant) Electrical supply system including: A. factory acceptance test acc to ITP for 8 persons for 5 days. Complete with full accommodation, transportation and all expenses. set 1 lot 1 B. training course for 24 trainees for two weeks at warehouse manufacturers ( including design , maintenance ,mechanical ,electrical and instrument , operation engineers , inspection team ) complete with full accommodation , transportation and all expense. - civil works( all project) lot 1 lot 1 lot 1 lot 1 lot 1 set 1 -Interconnecting pipe work(for all project) 12 13 14 - demobilizing works for all the project items - the commissioning for the project spare parts for two operation years (mechanical, electrical and instrumenention.) list should be submitted total price USD ]14[ set lot lot set UNIT PRICE TOTAL PRICE general conditions to be adhered by contenders 1- Technical & commercial offers to be submitted in duplicate by the manufactures or through their general manager or their official deputies commercial manager sales manager at the same time in a sealed separate envelope which should be offer ref. , batch no. tech. or commercial offer , receipt no. , and the closing date . 2- Contenders should give detailed pricing as per the attached itemized price list . Failure to do so will lead ignoring the offer . 3- Commercial offer to be in u.s.d $ and based on : full supply and manufacturing and equipments outside iraq as per scope of work and itemized prices list . 4- Offers to be submitted before or within the closing date period otherwise they will be neglected. 5- Offers submitted should be valid for a period not less than (90) days from closing date. 6- Offers contender should be clearly such as delivery terms, execution period, country of origin, port of shipment, entry point, and beneficiaries. Full name and address, the advising bank and all other necessary information required for contracting purposes. 7- Relevant catalogues, diagrams and data sheets to be submitted if necessary separately but should refer to our enq. no. tender name and offer ref. 89- Delivery of materials & equipment cip zb-1 depot . The complete execution period should be submitted from the date of l/c opening.. 10- Performance bond a performance bond of (5%) of total a mount of supplied equipments under the scope of supply subjected in the form of bank guarantee to be issued by supplier or manufacturers bank through the bank nominated later in favor of s.o.c this performance bond will be effective after (12 months) from commissioning date . 11- Insurance the contractor is required to insure all the equipments and materials for value of 110% of the total value of the materials and equipments for the sake of the buyer , the insurance will allow for a (3) weeks claims after the arrival of this materials and equipment to um qasser and unloading them . 12- bid bond the contractor should submit the bid bond from a well known iraqi bank covered from a foreign bank . 13- all bank charges inside iraq are to the buyers account and all bank charges outside iraq shall be to the contractors account. Including all the bonds services. ]15[ ]16[
© Copyright 2024