CM Fee and General Conditions Worksheet

Minneapolis Park and Recreation Board
Minneapolis Sculpture Garden Reconstruction and Cowles Conservatory Renovation
CM Fee and General Conditions Worksheet
July 21, 2014
Qty
Description
PRECONSTRUCTION PHASE
Project Director
Project Manager
Project Superintendent
Hours/
Weeks
Rate
Subtotal
Hours
Hours
Hours
Total
$0.00
$0.00
$0.00
$0.00
Total Pre-Construction Services
CONSTRUCTION PHASE
Project Director
Project Manager
Project Superintendent
Saftey Engineer
Site Office Trailer
Barriers, signage
Saftey program/protection and safety
Motor Vehicle Expenses
Site Office Phone/Fax
Site Office Equip & Supplies
Reproduction & Printing
Other - describe
Hours
Hours
Hours
Hours
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Total Construction Services
INSURANCE, BOND, & CM FEE
Full insurance package expressed in dollars per $1,000 of construction
costs. (Include type and limits of coverage.)
Performance Bond
Construction Manager Fee
$
$
$
$0.00
Total Insurance, Bond, CM Fee
TOTAL FOR ALL CM SERVICES & FEES
$0.00
Do NOT include project general conditions such as utilities, dumpsters, temporary toilets, safety
equipment, hoisting, snow removal, periodic and final clean, etc. as they are intended to be reimbursed at
actual cost without profit markup.
Include 2015 equipment rental rate schedule.
Comments: