Overhead Electrical Diagram

Service Construction Requirements
Single Phase Residential Installation: Overhead Mast Pipe
Once all of the following requirements have been met, you can anticipate our crews beginning the construction of your
service within two weeks. However, inclement weather, power outages, and customer-requested design changes
can cause delays.
Service Application
Date completed
Complete and return the service application including a sketch of your building site. Show
all existing and proposed underground facilities such as water lines, septic tanks, drain fields
along with phone, electric, gas and cable TV lines.
Electrical Permit
Date completed
An electrical permit is required. If you will be doing the work yourself, you must apply for the
permit. If you are planning to hire an electrical contractor, the contractor will apply for the permit.
Permit applications may take two or more weeks for processing.
Easements
Date completed
We require a signed easement before a service is installed. Easements may also be
required from adjoining property owner(s). This process can take a number of months.
Construction Fees
Date completed
Construction fees must be paid in full before we will proceed with construction of your
service. Cost estimates for the work performed will be based on rough grade restoration.
Service Equipment
Date completed
Before we can make the service connection, the meter socket, disconnect panel
and related items must be installed per Cloverland specifications and applicable
electrical codes.
Electrical Inspection
Date completed
An electrical inspector must approve the service. If you are completing the work yourself, it is up
to you to schedule the inspection; otherwise, the electrical contractor will do it for you. Once
your service is approved, the electrical inspector will notify our member services department and
provide us with an official release.
Service Route
Date completed
The service route from the transformer to the service location must be cleared per
Cloverland specifications.
Electrical Inspectors
STATE INSPECTORS
LOCAL INSPECTORS
Alger, Delta, Schoolcraft, Luce & West Mackinac Counties
Pat Debone (906) 786-2063
Clark Township, DeTour Village and DeTour Township
Duke Masse
(906) 297-3964
Fred Bryner
(906) 484-1220
Chippewa & East Mackinac Counties
Jon Merihugh
(906) 495-1390
Hendricks Township
Currently covered by state inspectors.
Schoolcraft County
Mike Rozeck
(906) 249-5106
Garfield, Newton and Hudson Townships
James Zdebski
(906) 477-6207