Weekly Progress Report Date: 6/12/15 Days of Construction: 26 McCormick Road Utility Tunnel Project Vaults Vault 1- The first tunnel section is planned to be installed 6/13 from vault 1 to 2. THe slab is poured and the wall rebar is being installed. Vault 2- The slab is poured and excavation between Vault 2 and 3 is underway. Tunnel section installation between 2 and 3 is scheduled to begin next week. The chilled water lines will be removed Asap. Vault 3- Excavation is complete and the Slab is scheduled to be poured early next week Vault 4- Excavation and lagging in Vault 5- lagging and excavation in Progress, slab will be poured next week progress Tunnel Sections There are two tunnel sections at Faulconer’s yard. the bottom sections are being waterproofed before they are brought onsite. The First tunnel section is planned to be installed 6/13 from Vault 1 towards Vault 2. The tunnel sections from Vault 1 to 2 will have to be installed one at a time and backfilled to facilitate the placement of the crane. Faulconer is planning on installing another tunnel section on Monday, 6/15 and one on Tuesday, 6/16. Updates UVA utilities relocated a COC water line this week between Vault 1 and 2. The temporary Chiller is on-line. There were some issues with the start-Up, but they have been resolved. Faulconer is now able to remove the Chilled water lines next to Vault 2. The UVA dept. Of engineering has asked for a tour with the Civil engineering students of the site. I am working with Faulconer and Dewberry to facilitate that next friday. Progress
© Copyright 2024