Islamabad Club, Islamabad SALIENT FEATURES SALIENT FEATURES OF TENDER 1. Employer : Islamabad Club, Islamabad. 2. Name of Work : SUPPLY & INSTALLATION OF DIESEL GENERATORS AND ALLIED WORKS. (2 Nos. 500 KVA Prime Rating) (01 No. 400 KVA Prime Rating) 01 No. ATS Panel 01 No. Synchronizing Panels 01 No. 1600A, 4 Pole Manual change over panel 01 No. 2000A ACB panel 01 No. M.O.R panel 02 No. 6000 liter fuel tank 1 set of 2500 hours spare parts 3. Type of Contract : Item Rate Based. 4. Day & Date of Issue of Tender(s) : 13-05-15 onwards. Allied work as per B.O.Q (No tender shall be issued on the date of opening of tenders.) 5. Place of issue of Tender(s) : Islamabad Club Murree Road Islamabad. 6. a) Day & Date of Submission of Tender(s) & Opening of part 1 of tender. : 28-05-15 last submission at 1530Hrs. Opening at 1600Hrs. : The Financial Proposal shall remain (in sealed from) in the custody of the Islamabad Club and would be opened after receipt of the technical evaluation report in the presence of qualified bidders who would be duly informed of the time, date and venue of opening of the same. b) Day & Date of opening of financial proposal, i.e part 2 of tender 7. Place of Submission & opening of Tender(s) : Office of the Secretary, Islamabad Club, Islamabad. 8. Validity of Tender(s) : 90 Calendar Days from the date of submission of tender. 9. Amount of Earnest Money : Rs. 500,000/= only in the form of Bank Guarantee/Pay Order/ Demand Draft/ Deposit at Call issued by a Scheduled Bank in favor of Secretary, Islamabad Club, Islamabad. The Earnest Money of the successful bidder shall be released within 15 days after the submission of Performance Bond pursuant to the signing of the Agreement whereas the same of unsuccessful bidders shall be released to them within 45 days of the submission of tender. 10. Time of Completion : 6 Calendar Weeks Including supply, installation, testing and commissioning after issuance of letter of award. SEM Engineers 1 Islamabad Club, Islamabad SALIENT FEATURES 11. Date of Commencement of Work(s) : 03 Calendar days after receipt of Letter of the Award by Contractor. 12. Certificate of Substantial Completion : To be issued by the Consultant. 13. Maintenance or Defect Liability Period : 18 Calendar Months from the date of issue of Certificate of Substantial Completion. 14. Certificate of Final Completion : To be issued by the Consultant within 90 calendar days after satisfactory completion of Maintenance Period. 15. Amount of Mobilization Advance : 45 % of the Contract amount against an Irrevocable Guarantee from a Scheduled Bank of Pakistan having credit rating of AA and above. 16. Recovery of Mobilization Advance : @ 100% from first interim payment on delivery of the material at site. 17. Amount of Performance Bond : 10% of the Contract Amount issued by an AA rated Insurance Company as per specimen attached valid till satisfactory completion of Maintenance Period. The Performance Bond and its encashment, if any, shall not be considered as total discharge of the Contractor’s liabilities for claims accruing to the Owner due to default or breach of any of the terms and conditions of the Contract Documents. 18. Contract Agreement : The Contractor shall, after the award of work, enter into and execute a Formal Agreement as per specimen attached, with such modification as may be necessary. 19. Stamp Paper Requirement : The Contractor shall submit, at his own cost, all Bonds and the Agreement required as per provisions of the Contract, of the appropriate value(s) of non-judicial stamp papers in accordance with the GOP regulations. 20. Retention Money : 5% of value of work done will be deducted. 50% of retention money will be released on Substantial Completion of Work & balance within 30 calendar days after issuance of Certificate of Final Completion. 21. Liquidated Damages due to delay Completion of the Job : Rs. 50,000/ per calendar day subject to maximum of Rs. 1,500,000/= : - 22. Interim Payment stages - 70 % at the delivery of material at site, 20 % at the completion of installation with testing of D.G sets, 5 % after commissioning of D.C sets. 5 % (retention money) to be released as per item # 20 hereinabove. 23. Work Schedule & Site Organization : Prior to award of work, Contractor will be required to submit detailed Work Schedule and Site-Organogram to be approved by Architect/ Consultant, which will be part of the Contract. 24. Progress Report : By each week or as determined by the Consultant, the Contractor is required to submit the report in such form and substance as may be prescribed by the SEM Engineers 2 Islamabad Club, Islamabad SALIENT FEATURES Architect /Consultant explaining the progress of Works during the period, milestones ahead to start the following periods, procurement status, manpower, employed, tools and plant on site, and areas of problems along with their solutions for approval. Payments may be withheld on noncompliance of submission of Progress Report. 25. Billing Process : 26. Order of Preference 27. Time for Payment Contractor shall submit his bills along with status/ progress of work and relevant details in hard copies. Billing shall be done as per item 22 and in compliance with other conditions hereinabove. In case of non-compliance to above, bills shall not be entertained. In case of any ambiguity in between B.O.Q, Specifications & drawings, B.O.Q shall have precedence. : 07 days from the receipt of Consultant’s interim Certificate to the Employer. SEM Engineers 3
© Copyright 2024