Cover with focus picture 1 Cover with focus picture 2 Cover with focus picture 3 High Output Electrification of Western Presented By Anne Watters Project Overview 191 route miles of which 12 miles are electrified London to Bristol - completed by 2016 Bristol to Cardiff - completed by 2017 Project Overview Where is being electrified • Crossrail is responsible for Stockley Junction to Maidenhead. • Electric trains team is completing Maidenhead to Cardiff. - Initial test site of 20 miles of electrification - September 2015 - First phase is Maidenhead to Bristol - complete and ready for December 2016 - Second Phase is Bristol to Cardiff - to be complete and ready for December 2017 Quantities to Be installed Routes 1-9 (Maidenhead to Cardiff) • 3 New national Grid Supply points (+1 Crossrail) • 30 AT distribution sites • Approximately 1000km of single-track • 16000 pile foundations • Circa 14000 OLE Structures • 150+ structures to gauge clear • 4 major Tunnels • 1 UNESCO World Heritage site at Bath Changes to OLE Installation Moving From Traditional installation to High Output plant systems HOPS – High Output Plant System • 3 Consists to install foundations, steelwork & wiring • 6 shifts a week • Minimal disruption to the operational railway - ALO – adjacent line open working – Allowing trains to still run on adjacent lines - 7 Hour Possessions - Managing down the schedule 4 costs HOPS – Performance Criteria • The Invitation to Tender (ITT) detailed a number of key requirements of the equipment; - Performance based specification. Work with the adjacent line open to traffic Construct an average of one tension length of OLE per shift Transit in traffic at 60mph Easily maintained and reduced whole life cycle costs HOPS – Consist 1a Foundations - Piling Production of HOPS Production of HOPS HOPS – Consist 1b Foundations - Concrete Production of HOPS HOPS – Consist 2a Main Steelwork HOPS – Consist 2b SPS, Auxiliary wiring & Main line wiring HOPS – Consist 3 Final Works • Running Cross-overs / Contenary wire • Cutting in SI / neutral section • Installing Jumpers • Panning • Final Heights and Staggers records HOPS – Staffing 92 Staff working on the HOPS consists • OLEC 1 – 38 people • OLEC 2 – 16 people • OLEC 3 – 26 people • OLEC 4 – 6 people • OLEC 5 – 6 people Two Ways to OLEC competence • New Starters (Expected to be over 65 of 92 Staff) - Completing the training courses - Completing the Logbooks In Germany & High Marnham - Being assessed in High Marnham • Existing OLE Linesmen with additional Series 1 training - Recording activities in Log books / endorsed by Line manager - Additional Training and log book sign of on Series 1 Changes to Design Introduction of a new OLE Basic Design system Series 1 • Interoperability • Use of High speed trains with Multiple Pantographs • Simplified connections to speed up installation Importance of OLE Design Series 1 – Designed by Furrer & Frey • Mono-anchor Booms • Single insulator cantilevers / registrations • Reduced number of components • Reduced flaking of wires HOOBs & Logistics Main Elements • Materials supply and disposal • Piles + masts + wiring + material disposal • Infrastructure facilities • Operations bases • Swindon • Materials handling facilities, workshops • Haulage + Train Movements • 24-hour cycle, intensity of activity, “Logistics: the foundation of high output OLE….” Logistics Questions
© Copyright 2024