Project Control Process - Gate review Objectives • Three Gate objectives are proposed in order to track project progress: – 1. To formally approve the completion of a stage: To provide assurance that all planned activities for a stage were completed and met the project plan within stated limits. – 2. To ensure closure of any variance that required the involvement of management, ( that could not be resolved by the project team ). – 3. To make or to formally document a decision about the next stage. Project Control Process - Gating Overview Gate N-1 Review problem resolutions Gate N Review Completion of technical activities Completion of technical products (GPCR) Collection of project data Presentation - Approval of next Phase Project Control Process - Gates by IS Life-Cycle SALC Account Management Initial Investigation Supplier Evaluation and Selection Gate 1 RSD Account Management Installation, Adaptation, Interfacing, Integration, Acceptance & handover Launch & Operation Detailed Design, Developpment and Testing Launch & Operation Gate 2 Initial Investigation and High Level Design Gate 2a Gate 0 Gate 1&2 Gate 3 : Gates that require a formal gate review by Gate Review Committee : Gates that require an ISPO authorisation Gate 4 Project Control Process - Gate approved means • work completed as planned, with no significant variances, • all mandatory products have been completed, and • recommendation for next phase is approved. Else Project must stay at the current stage, bridge the gaps and gate again Project Control Process - IS Variance Policy “Variance Situation” - when the project actual or the projected data, exceeds an approved variance limit. Progress Variance: Is apparent when technical and management products identified on GPCR are: Absent, Of very low quality, Not Reviewed/Signed-off or Late. Quality Variance: Is Apparent when major non-conformance are detected, when IS life-cycle is not followed, Significant I/R are reported by the independent UAT. Effort Variance: Is apparent when either too many/too little effort is reported (TRS). Scope Variance: Is apparent when scope is decreased by the project team to meet a date. Opposite can also appear “ creeping requirements”. Cost Variance: Is apparent when % spent (expense or capital) is approaching limit and no immediate action is foreseen to submit an amendment to CRB Project Control Process - Gate Review Presentation “Standard Presentation” - Gate review presentations must all follow the standard. Slide 1 - Project Name, Number, Title, Current Stage, Gate # review, project manager name, Customer name Slide 2 - HR (IS, Users, External) current, next stage, deviations Slide 3 - Schedule, current, next stage, deviations Slide 4 - Costs (Capital, Expenses), current, next stage, deviations Slide 5 - Architecture & technology diagram Slide 6 - GPCR completed/outstanding items, current, next stage Slide 7 - project Risks and recommendation to proceed
© Copyright 2024