INSTRUCTIONS FOR HOW TO FIT THE ODME S 663 MKI AND MKII PRESSURE SWITCH KIT. Goal: To modify all old Seres MK-I and MK-II systems in order to eliminate the “FRESH WATER FAILURE” alarm, With out affecting the performance of the ODME system. In order to reach this Goal the following parts should be removed first from the system: 1 x S-PRE001 PRESSOSTAT, MK1&2 Located inside Oleo Meter cabinet. 1 x S-DEBB001 SART FLOWMETER INDICATOR,MK1&2 Located on the MK-I/MK-II Hydraulic Panel. 1 x All copper piping from Sart Flow Meter until the Oleo meter Cabinet Figure 1: Pressure Switch PRE001 inside the Oleo Meter cabinet which should be removed Figure 2: Pressure Switch PRE001 which should be removed Figure 3: Sart Flow Meter Indicator which should be removed CAUTION Before any dismantling job make sure that both 3-Phase as well as 1-Phase Power supply to ODME is cut off. Step 1 Go to Engine Room Open the Oleo Meter cabinet and remove the PRE001, the Pressure Switch Support from the Oleo Meter left side wall as well as the 6mm metal pipe connecting the pressure switch with the bulkhead penetration plate. Make sure that this hole is clear as you are going to use it later in order to pass the pressure switch cable for the new pressure switch. Step 2 Drill two holes in the right side of the Oleo Meter cabinet as it is shown in figure 4 in order to Support the Zener Barrier. After done with the holes fix the Zener Barrier in the right wall side of the Oleo Meter cabinet with the help of the screws and aluminum straight-plate holder that you will find inside your MK1&2 Pressure Switch Modification Kit as shown in figure 5. Step 3 After you done with the Zener Barrier support please prepare yourself in order to extend the PRE001 Pressure Switch Cables so that they will have sufficient length in order to connect to The Zener Barrier Terminals No: 1 and 2 as it is shown on figure 6. Figure 4: Zener Barrier Location Figure 5: MK1&2 Pressure Switch Modification Kit Figure 6: MK1&2 Pressure Switch Modification completed from Oleo Meter side 5, Kimonos Str., 122 44 Egaleo – Athens – Greece. Telephones: +30-210-5986179, +30-210-5986213, +30-210-5310551, +30-210-5310674, +30-210-5310775 Fax: +30-210-5911161, E-mail: [email protected] , [email protected] Internet: http://www.darlas.gr Established in Athens-Greece as a Societal Anonym (SA), Reg. No: 16494/01 /B/88/343, Fully Paid Capital: € 58 694.06 Bankers: National Bank of Greece SA, Egaleo Branch (105), IBAN: GR16 0110 1050 0000 1054 7023 795. Page 1 of 4. INSTRUCTIONS FOR HOW TO FIT THE ODME S 663 MKI AND MKII PRESSURE SWITCH KIT. Step 4 Go to Pump Room and find the Hydraulic Panel. Locate the Sart Flow meter as it is shown on Figure 7. Close the 1.2 Bars air input to the Sart Flow Meter. Unscrew the two in and out air pipes from Sart Flow Meter back side. After removing the air pipes unscrew the two Allen screws located in the backside of the Sart Flow Meter in order to be able to dismantle the Red Indicator as shown in Figure 8. Figure 7: Hydraulic Panel, Sart Flow meter Indicator shown in red. Figure 8: Hydraulic Panel with Sart Indicator Being Removed. Figure 9: MK-III Pressure Switch Fitted in Place. Step 5 Being in the Pump Room find the copper air pipe, which connects/drives the air from the measuring vessel penetration plate to the Sart Flow Meter and remove this pipe, as you are going to use the penetration plate hole for passing through it the pressure switch cable. Please see figure 10 below. Figure 10: Sart Flow Meter to M.V. Penetration Plate air pipe for removal. Figure 11: Pump before modificationScrews to be removed and fitted back. Figure 12: Pump after modification with the new pressure switch shown in place. Step 6 a) Unscrew one of the four (4) screws of the Travaini Pump in the output line of the pump in order to support the new pressure switch supplied with your kit. b) Also unscrew the venting screw located in front side of the flange – as shown above in figure 11 - as you are going to fit there the (6mm x ¼”) quick change connector for the plastic high-pressure tube, which is going to drive the new pressure switch that you will fit in the next steps. Please see figure 11 and 12 above. Step 7 Put now in place the support bracket supplied with your kit for the pressure switch as well as the the (6mm x ¼”) quick change connector. Support the pressure switch on the support bracket as shown in Figure 13 below and then connect the high-pressure tube supplied with Pressure Switch and sampling pump as shown in figure 13 & 14 below. 5, Kimonos Str., 122 44 Egaleo – Athens – Greece. Telephones: +30-210-5986179, +30-210-5986213, +30-210-5310551, +30-210-5310674, +30-210-5310775 Fax: +30-210-5911161, E-mail: [email protected] , [email protected] Internet: http://www.darlas.gr Established in Athens-Greece as a Societal Anonym (SA), Reg. No: 16494/01 /B/88/343, Fully Paid Capital: € 58 694.06 Bankers: National Bank of Greece SA, Egaleo Branch (105), IBAN: GR16 0110 1050 0000 1054 7023 795. Page 2 of 4. INSTRUCTIONS FOR HOW TO FIT THE ODME S 663 MKI AND MKII PRESSURE SWITCH KIT. Figure 13: Support Bracket and Pressure Switch in Place. Figure 14: Support Bracket and Pressure Switch in Place. Figure 15: Pressure switch cable route running from pressure switch to Oleo Content Meter Cabinet through the Measuring Vessel Penetration plate. Step 8 Now is the time to run the (3 x 0.75 mm2) cable from the pressure switch terminal block till the Zener barrier located Inside the Oleo Content Meter Cabinet fitted in the engine room. Please see figure 15 above. After you have done with the running and supporting with tire-ups the Cable you can connect it on the Zener Barrier Terminals No 3 & No 4 Special Note1: Please bear in mind that when No Water pressure in the circuit = pump stopped = pressure switch Contact Short circuit. In other words make sure to connect to the Zener Barrier the Pressure Switch contact which is Normally Closed when the Pump is stopped. Special Note2: Please also bear in mind that when you are upgrading the Oleo Meter from MK-II to MK-III/S3000 it will be necessary to either cut on the penetration plate the previous used 1.2 bar air supply pipe or to open a hole on the back side of the new MK-III/S3000 Oleo Meter as it was in the original MK-II Oleo Meter so that the pressure switch cable will not be damaged when you will install the new MK-III or S3000 Oleo Meter Cabinet. Please see figure 16 & 17 below. Figure 16: Oleo Meter Penetration Plate Arrow shows which pipe needs to be cut. Figure 17: Oleo Meter Cabinet Arrow shows the location where a new hole needs to be opened on the new MK-III or S-3000 Oleo-Meter. 5, Kimonos Str., 122 44 Egaleo – Athens – Greece. Telephones: +30-210-5986179, +30-210-5986213, +30-210-5310551, +30-210-5310674, +30-210-5310775 Fax: +30-210-5911161, E-mail: [email protected] , [email protected] Internet: http://www.darlas.gr Established in Athens-Greece as a Societal Anonym (SA), Reg. No: 16494/01 /B/88/343, Fully Paid Capital: € 58 694.06 Bankers: National Bank of Greece SA, Egaleo Branch (105), IBAN: GR16 0110 1050 0000 1054 7023 795. Page 3 of 4. INSTRUCTIONS FOR HOW TO FIT THE ODME S 663 MKI AND MKII PRESSURE SWITCH KIT. Step 9 Put Plastic Steel Putty in the hole that the pressure switch cable is passing through the measuring vessel penetration plate to the Oil Content Meter Cabinet so we can protect and avoid any gasses to pass from Pump Room to Engine Room. Please see figure 15 above Step 10 You are now done with your modification. Please put back the Measuring Vessel Cover so you can protect the measuring vessel from improper Painting. 5, Kimonos Str., 122 44 Egaleo – Athens – Greece. Telephones: +30-210-5986179, +30-210-5986213, +30-210-5310551, +30-210-5310674, +30-210-5310775 Fax: +30-210-5911161, E-mail: [email protected] , [email protected] Internet: http://www.darlas.gr Established in Athens-Greece as a Societal Anonym (SA), Reg. No: 16494/01 /B/88/343, Fully Paid Capital: € 58 694.06 Bankers: National Bank of Greece SA, Egaleo Branch (105), IBAN: GR16 0110 1050 0000 1054 7023 795. Page 4 of 4.
© Copyright 2024