Kingston Ash Facility Failure: What caused it and why it matters X

Kingston Ash Facility Failure:
What caused it and why it matters
TVA Forensic Team’s “Creep of the Slimes/Static Liquefaction” Theory (Ash Dredge Cell 2 Failure) vs.
“It’s the Water, Stupid” Theory
(Clay Dike C Failure) by Barry Thacker, P.E.
Geo/Environmental Associates, Inc. TSK Presentation – 14 September 2009
X
The failure occurred around 1:00 a.m. EST, on Monday, December 22, 2008, when the north and central portions of Cell 2 at the Kingston Fossil Plant ash disposal site suddenly failed. An estimated 5.4 million cubic yards
estimated 5.4 million cubic yards of material, consisting primarily of hydraulic‐filled ash and intermediate stage containment dik
dikes, were released in a l
di
progressive sequence of flow slides over a period of approximately one hour. pp
y
Ultimately, the flow slide would extend northward approximately 3,200 feet b
beyond the limits of the d h l
f h
original ash pond over the Swan Pond Creek flood plain, g
a back water slough of the Emory River and into the former Emory River Channel of Watts Bar Reservoir.
KINGSTON ASH FACILITY FAILURE
(From Forensic Report)
TVA’S FORENSIC TEAM: First‐time in history phenomenon, denoted as “Creep
Creep of the Slimes/Static of the Slimes/Static
Liquefaction”, is modeled using undrained shear strength for a buried slimes layer and the overlying sluiced ash, and predicts failure of the dredge cells.
Dike C
Dredge
Cells
Missed clue #1?... How could
ash travel 2/3 of a mile to the
northwest from failure of a
dredge cell outslope with a
northeastern orientation?
N
Hint: Dike C had a northwestern‐
facing limb
OPINION BY AECOM AS TO CAUSE OF THE KINGSTON ASH FACILITY FAILURE (From Forensic Report): The north end of Dredge Cell 2 was on the verge of failure due to the high stresses and creep in the loose wet layer of weak slimes. The deformation of the slimes in turn caused p
y
the overlying collapsible wet ash to liquefy. Failure of the Kingston dredge cells was sudden and complex in nature due its geographic setting and being built within the Watts Bar Reservoir after the lake was formed. It took a forensic type study to determine the propensity of the ash to liquefy at low strain levels when the material cannot drain and thus becomes
of the ash to liquefy at low strain levels when the material cannot drain and thus becomes undrained, and to locate the slide plane in the unusual, creep susceptible, low undrained shear strength slime layer that underlies Cell 2. In AECOM’s opinion, subsurface conditions at the dredge cells were unusual and rarely found. The consequence of failure in the slimes led to the collapse of the dredge cell and loss of the saturated contents of the ash landfill due to the breach of perimeter Dike C.
NOTE: AECOM’s primary failure surface was analyzed at the location of a former knob, whereas the thickness of ash is greater beneath Dike C’s northwestern limb – X marks the spot.) Dike C
X
Initial Burst Location of Dike C (Based on “It’s the Water, Stupid” A l i )
Analysis)
AECOM RELIC SURVEY
SURVEY DATA
Initial Static Liquefaction Location of Dredge Cells (Based on TVA’ss Forensic Dredge Cells (Based on TVA
Forensic
Team )
CORROBORATING RESULTS OF ENGINEERING ANALYSIS USING FORENSIC EVIDENCE:
My buddy, Ray Bob, offered some of his observations about the forensic study. He is proud to describe himself as, “a snuff‐dippin’, coal‐minin’, 6‐foot‐6, 250‐pound, American Veteran”; and his friends call him “Tiny”. Tiny brought to my attention the Expected Failure Mode slide from the forensic study shown below that he says “Must
the forensic study shown below that he says, Must be one of them cartoons they make in be one of them cartoons they make in
Hollywood.” Tiny says to look real close at how
real close at how the ash from the “dredge sales” supposedly pp
y
“lickerfide” and ran over Dike C.
Tiny gave me two Dike C figures/photos from the AECOM forensic report, which are shown at right. According to Tiny, “Do ya seed whar I drawt ‘SEE‐DIK (THEN)’ and ‘SEE‐DIK (NOW)’? “ “If that‐there Hollywood cartoon from them forensic fellers was true, then the grass on top of the See‐Dik slope they say got flooded and pushed
they say got flooded and pushed seven‐hundurd feet to the northeast by the tidal wave of lickerfide ash from failurt of the dredge sales would at least be tarnished and flat, and not as fresh as a Daisy Duke.”
“At least in the Road Runner and Wile E. Coyote cartoons, they showt the coyote with matted fur, and seaweed stuck in his ear, after he gets hammered by the tidal wave ”
hammered by the tidal wave.”
Tiny gave me two photos of the relic cattails from the AECOM report as shown below, and informed me that you can’t push a rope, you have to pull a rope to get it to move. In his words, “Do ya seed whar I drawt ‘CATTAILS (THEN)’ and ‘CATTAILS (NOW)’? Thur is no way on God’s Green Earth them dredge sales could push a clump of cattails two‐thirds of a mile up the holler to the northwest without destroyin’ them. Do them forensic fellers expect us to believe that the dredge sales had the force to push See‐Dik seven‐hundurd feet to the northeast, yet not hurt a hair on the fur of a cattail’ss haid?... Yea, rite! The only way them cattails could not hurt a hair on the fur of a cattail
haid? Yea rite! The only way them cattails could
have moved that furr a piece up the holler to the northwest is by ridin’ on the back of the sluiced ash after the northwest limb of See‐Dik burst.”
“Don’t
Don t them forensic fellers knows that a cattail is as fragile as… ummmmm, a cattail
them forensic fellers knows that a cattail is as fragile as… ummmmm, a cattail”??
Relics from Dredge Cell 2 Outfall Pipe Found Northeast of Original Location –
illustrating that Cell 2 failed last after the bursting of Dike C undermined the toe of
bursting of Dike C undermined the toe of the northeastern outslope of Cell 2
N
Initial burst location of Dike C
Cell 2 Outfall Pipe (Original Location)
Dredge Cell 2
OPINION BY BARRY THACKER, P.E.: Dike C burst at its northwestern limb due to artesian pore water pressures in the underlying sluiced ash; then it was like Dominoes, the game, not the pizza. Piezometer locations and water level data provided by TVA/AECOM: For reference purposes, the ground surface at MW‐15 is at elevation 771 feet; thus, water levels in MW‐15 above elevation 771 feet represent artesian conditions in the sluiced ash. Trend in water levels in piezometers
i
after last measurement on 11/19/08 validates Thacker seepage model. f l
11/19/08 lid
Th k
d l
Note: The alluvium beneath Dike C where MW‐4B was screened was not
screened was not included in the Thacker model. LET’S NOW EXAMINE THE DETAILS: Missed Clue #2? Mitigation report prepared after a 2003 incident at the northwestern toe of the dredge cells concludes that a “blowout” was caused by “excessive seepage and piping”, yet y
p g
pp g ,y
internal drains were proposed to increase the rate of seepage – Is that logical?
2003 “Blowout” at toe of Northwestern Outslope of Dredge Cells
Hint: Hinge No 1
Hint: Hinge No. 1
Hint: Bottom Ash Lenses
In reviewing the input data used in the AECOM seepage modeling, I see that AECOM used a ratio of horizontal hydraulic conductivity (kh) to vertical hydraulic conductivity (kv) = 1. Maybe, the engineers at AECOM do not realize the impact the black, more pervious bottom ash lenses, shown in the photo at left from the AECOM report, have on the kh/kv ratio; or how a high kh/kv ratio can in some circumstances cause significant high kh/kv
ratio can in some circumstances cause significant
uplift pore water pressure in sluiced ash, hydraulic fill. Hinge (i.e. thin, potentially weak zone subject to failure by high pore water seepage pressures)
I learned that lesson decades ago from a gray‐haired engineer with the U.S. Mine Safety and Health Administration (MSHA) who referred
Administration (MSHA) who referred me to the results of the forensic study of the 1972 Buffalo Creek Slurry Impoundment failure, shown at right. Note: kh/kv = 100
One of the early practitioners in design of ash disposal facilities was Professor Arthur Casagrande of Harvard University. A 1971 design report he co‐authored states: “When fly ash p
f
y
p
g g
p
g g
is deposited from a slurry in a pond, considerable segregation develops according to grain size and specific gravity. The resulting stratification and loose structure produces relatively high horizontal permeability.“ I have found that kh/kv can vary from 1 to 100 at the same site, so I believe use of kh/kv = 100 for hydraulic fill in seepage analysis is prudent.
Sluiced ash is not a homogeneous deposit. When fly ash and bottom ash are co‐mingled during hydraulic filling, the resulting deposit can contain a gazillion lenses of bottom ash surrounded by fly ash.
From TVA‐00013627
(Northwestern outslope of of
dredge cells)
Outer Dike
kv = 2e-4 ft/min, kh/kv = 2
Outer Dike
Base Material
UPLIFT PRESSURE IN
FLY ASH DUE TO HIGH
Kh/Kv RATIO
70
75
60
Fly Ash
Clay Dike
65
Hydraulic fill should be modeled in seepage analysis using g
ratios where kh is the hydraulic conductivity y
y
high kh/kv
in the horizontal direction and kv is the hydraulic conductivity in the vertical direction. Doing so, yields a prediction of artesian pressures at toe as shown at right.
Fly Ash
kv = 7.5e-5 ft/min, kh/kv = 10
My independent assessment based on steady‐state seepage and stability analysis using effective stresses shows that the northwestern outslope of the dredge cells is unstable at kh/kv
/ = 50 with only the shallow surface drains installed after the 2003 “blowout”. y
Bas e Material
kv = 3.4e-5 ft/min, kh/kv = 2
Outer Dike
kv = 2e-4 ft/mi n, kh/kv = 2
Therefore, high kh/kv levels in the sluiced ash would explain why a new “blowout”
new blowout was reported in was reported in
2006 after the sluiced ash level raised.
170
160
Fly As h
kv = 7.5e-5 ft/min, kh/kv = 50
Des cri pti on: outer dike W t: 95
Cohes ion: 0 Phi : 36
Des cri pti on: fl y ash
W t: 105 Cohesion: 0
Phi: 31.5
Des cri pti on: c lay dike
W t: 110 Cohes ion: 0 Phi: 30
Des cri pti on: bas e material
W t: 95
Cohesi on: 0
Phi: 36
Des cri pti on: rockfil l
W t: 95
Cohes ion: 0
Phi: 36
150
ELEVATION
N - 700 FT
140
0.93
130
120
Outer Dike
110
100
90
Bas e Material
80
Fly As h
70
60
Clay Dike
50
40
30
20
0
10
20
30 40
50 60
70
80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400
DISTANCE, FT
(Documenting inspection from October 2008)
(for northwest outslope of dredge cells adjacent to Swan Pond Road)
My independent assessment shows that the northwestern outslope of the dredge cells is
outslope of the dredge cells is stable with adequate relief wells even at kh/kv = 100
Bottom ash lenses
Independent analysis of northeastern outslope
p
y
p of dredge cells based on steady‐
g
y
state seepage and effective stresses for kh/kv = 100 in sluiced ash:
Clay Dike
kv = 1e-6 ft/min, kh/kv = 2
Name: k100failure dredge overall.gsz
Rolled Ash Dike
kv = 2e-4 ft/min, kh/kv = 2
ELEVAT
TION - 700 FT
Description: compacted ash Wt: 100 Cohesion: 0 Phi: 36
Description: sluiced ash Wt: 100 Cohesion: 0 Phi: 31.5
Description: clay dike Wt: 120 Cohesion: 300 Phi: 26
1.84
8
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
Rolled Ash Outslopes (Dredge Cells)
Sluiced Ash
kv = 7.5e-5 ft/min, kh/kv = 100
Hinge No 2
Hinge No. 2
My independent assessment shows that the northeastern outslope of the dredge cells is stable as designed even at kh/kv = 100, in /
,
spite of the presence of Hinge No. 2.
Rolled Ash Dike C
Clayy Dike C
Sluiced Ash
0 10 20 30 40 50 60 70 80 90
110 130 150 170 190 210 230 250 270 290 310 330 350 370 390 410 430 450 470 490 510 530 550 570 590 610 630 650 670 690 710
DISTANCE, FT
Analysis of Dike C with saturated sluiced ash between Dike C and the northeastern outslope of the dredge cells: Dike C has no internal drains, so how does seepage drain from Dike C? (Not in a controlled manner, which can result in high pore water seepage pressure as shown above).
Name: k100predredge stability upper.gsz
ELEV
VATION - 700 FT
Sluiced Ash
kv = 7.5e-5 ft/min, kh/kv = 100
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
Description: rolled ash Wt: 100 Cohesion: 0 Phi: 36
Description: sluiced ash Wt: 100 Cohesion: 0 Phi: 31.5
Description: clay dike Wt: 120 Cohesion: 300 Phi: 26
Rolled Ash Dike
kv = 2e-4 ft/min, kh/kv = 2
Clay Dike
kv = 1e-6 ft/min, kh/kv = 2
Hinge No. 3
Rolled Ash Dike C
68
1.61
Clay Dike C
41
Sluiced Ash
0 10 20 30 40 50 60 70 80 90
110 130 150 170 190 210 230 250 270 290 310 330 350 370 390 410 430 450 470 490 510 530 550 570 590 610 630 650 670 690 710
DISTANCE, FT
‐ Pre
Pre‐dredge
dredge cell condition with minimum factor of safety greater than 1.5 cell condition with minimum factor of safety greater than 1.5 ‐
NOTE: Knowing how TVA overbuilds, I modeled the clay fill of Dike C with an apparent cohesion of 300 psf due to compaction.
Independent analysis reveals:
Clay Dike
kv =1e-6 ft/min, kh/kv = 2
Name: k100 previous dike c mid.gsz
Rolled Ash Dike
kv = 2e
2e-4
4 ft/min
ft/min, kh/kv = 2
ELEVATION - 70
00 FT
Description: compacted ash Wt: 100 Cohesion: 0 Phi: 36
Description: sluiced ash Wt: 100 Cohesion: 0 Phi: 31.5
Description: clay dike Wt: 120 Cohesion: 300 Phi: 26
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
‐ When sluiced ash When sluiced ash
in dredge cells is at El. 809 feet, the minimum factor of safety for Dike C is only slightly greater than 1.0 ‐
Sluiced Ash
kv = 7.5e-5 ft/min, kh/kv = 100
1.04
Rolled Ash Outslopes (Dredge Cells)
Rolled Ash Dike C
Clay Dike C
Bottom ash lenses
Sluiced Ash
0 10 20 30 40 50 60 70 80 90
110 130 150 170 190 210 230 250 270 290 310 330 350 370 390 410 430 450 470 490 510 530 550 570 590 610 630 650 670 690 710
DISTANCE, FT
Clay Dike
kv = 1e-6 ft/min, kh/kv = 2
Name: k100failure dike c mid.gsz
Rolled Ash Dike
kv = 2e-4 ft/min, kh/kv = 2
ELEVATION - 700 FT
Description: compacted ash Wt: 100 Cohesion: 0 Phi: 36
Description: sluiced ash Wt: 100 Cohesion: 0 Phi: 31.5
Description: clay dike Wt: 120 Cohesion: 300 Phi: 26
‐ Condition on 22 D
December 2008 with b 2008 ith
sluiced ash in dredge cells at El. 816 feet ‐
Sluiced Ash
k =7
kv
7.5e-5
5 5 ft/
ft/min,
i kh/k
kh/kv = 100
0.96
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
Rolled Ash Outslopes (Dredge Cells)
Rolled Ash Dike C
Clay Dike C
Sluiced Ash
0 10 20 30 40 50 60 70 80 90
110 130 150 170 190 210 230 250 270 290 310 330 350 370 390 410 430 450 470 490 510 530 550 570 590 610 630 650 670 690 710
DISTANCE, FT
Voilà, steady‐state seepage and stability analysis based on effective stresses predicts failure of Dike C with computed F.S. less than 1.0 on 22 December 2008 as shown above.
For an imaginary piezometer (MW‐4C) installed through the clay‐portion of Dike C at the elevation 765 bench, and screened in the sluiced ash at elevation 740 feet (shown above), modeling predicts water levels for kh/kv = 1, 10, and 100 in the sluiced ash as shown below:
modeling predicts water levels for kh/kv
= 1 10 and 100 in the sluiced ash as shown below:
In summary: Note: Ash could have travelled two‐thirds of a mile to the northwest without help from “Left‐
T
Turn Laverne” (Knoxville personality) only if L
” (K
ill
lit ) l if
that was the direction sluiced ash exploded from the initial rupture of Dike C.
Plausible scenario (Continued):
Prior to final raising of Dike C in 1976, the ash delta covered the majority of the pond as shown below; thus, coarser grained ash would have deposited in pool near northwestern limb of Dike C. Finer‐
grained particles of ash that deposited
grained particles of ash that deposited after Clean Air Act modifications at the Kingston plant would then overly this coarser‐grained ash. From 1984 to 2008, dredge cells grew laterally and vertically, as shown above, causing steady‐state seepage conditions to develop intermittently in the sluiced ash upstream of Dike C within the 200‐foot
sluiced ash upstream of Dike C within the 200
foot setback zone during dredging and extended rainfall events as evidenced by large fluctuations in piezometers levels.
Illustration of large fluctuations in water levels in piezometers
MW‐13, MW‐14, and MW‐15 during dredging cycles. Artesian conditions were achieved in MW‐15 on 11/18/08, yet sluicing continued to Dredge Cell 2 during a period of relatively high ti
d t D d C ll 2 d i
i d f l ti l hi h
precipitation until failure occurred on 12/22/08. Note: the ground surface at MW‐15 is at elevation 771 feet . Note: The alluvium beneath Dike C where MW‐4B was screened was not included in the Thacker model. Tiny’s additional sketches:
Conclusion: High pore water seepage pressure resulted in an artesian condition within t i
diti
ithi
the sluiced ash beneath the clay‐portion of Dike C, which was the driving force behind the failure. Dike C ruptured at its most vulnerable location where it crossed the original Swan Pond Creek
original Swan Pond Creek. Excavation of the diversion channel by TVA to allow construction of Dike C in the 1950s may have provided drainage along much of its length for natural sand lenses within the alluvium
lenses within the alluvium that forms the bottom of the ash disposal facility;
however, no such drainage of natural sand lenses was provided beneath the northwestern limb of Dike C. Regardless, failure was inevitable because the increasing sluiced ash level of the dredge cells would have resulted in increased pore water pressure beneath Dike C due to Dike C’s lack of internal drainage provisions. Where did AECOM go wrong? While reviewing AECOM’s assertion that the faster filling rate of 6.1 feet per year during 2008 could result in excess construction pore water pressures, I found what I believe is an error in the way AECOM computes the coefficient of consolidation for ash as shown below at right
shown below at right. I believe that AECOM’s engineers incorrectly interpreted secondary consolidation as primary consolidation. This potential error is documented lid ti
Thi
t ti l
i d
t d
in a 1977 technical paper I co‐authored for the ASCE Conference on Geotechnical Practice for the Disposal of Solid Waste Materials. Based on my p
f
y
calculations, essentially complete pore pressure dissipation is predicted at a filling rate of 6.1 feet per year, especially when considering that AECOM’ss rate of consolidation data is for pore AECOM
rate of consolidation data is for pore
pressure dissipation in the vertical direction. As Professor Casagrande noted, fly ash has a relatively high horizontal permeability when placed by hydraulic filling. Therefore, I expect the actual rate of pore pressure dissipation is much faster than predicted from data
much faster than predicted from data generated during laboratory testing where drainage is allowed in only the vertical direction.
Even when excess pore water pressures are predicted during construction, I recommend assessing stability using effective stresses so actual pore water pressures can be verified during construction using piezometers. If pore water pressures reach design levels, then stop construction until pore water pressures dissipate to safe levels and/or add additional internal drainage provisions. Use of undrained shear strength parameters for design offers no such assurance and flexibility during construction. Approach used for mining‐
related hydraulic fill structures built by the Modified Upstream Construction Method: Forensic studies performed using effective stresses with estimate/measurement of pore Forensic
studies performed using effective stresses with estimate/measurement of pore
water pressures allow validation of the cause of failure based on comparison with computed factors of safety during previous stages of construction as illustrated in my white paper analysis of the Kingston failure, whereas forensic studies using undrained shear strengths offer no such validation. ff
h lid ti
For example, the most rapid construction of the Kingston dredge cells occurred when the outslopes
were built, not during filling of the cells with sluiced ash. Use of undrained shear strength limits assessing stability at these different phases of construction. Finally, as shown on Tiny’s sketches at left, AECOM analyzed stability of Dike C where the thickness of ash is less than at its northwestern limb.
Sluiced ash
thickness =
11’
‐ Results of AECOM stability analysis for Dik C
Dike C ‐
‐TVA design cross‐
section of Dike C ‐
According to Tiny, AECOM’s analysis was performed at a “frowny‐face knob.” The above cross‐
sections are shown at the same scale, yet note the different thickness of sluiced ash beneath Dike C. I assessed stability of Dike C at a “smiley‐face holler” location based on TVA’s design drawing, which as Tiny noted, “Is whur the sluiced ash is much thicker and failurt occurt.” Why the cause of failure at Kingston matters: Should engineers start looking for slimes beneath other hydraulic fill structures? Should engineering schools start offering “slimes‐busters” design classes? I am relieved that the method of estimating pore water pressures, performing stability analysis based on effective stresses, and confirming design pore water measurements during and after construction using piezometers according to Corps of Engineers’ criteria, appears prudent. Based on my analysis, if that method had been used at Kingston then unsafe water levels could have been identified
if that method had been used at Kingston, then unsafe water levels could have been identified and mitigation measures could have been taken to avert the failure; however, if this method is wrong, I want to know now. Who is right doesn’t matter; what is right counts.
Why I am convinced Dike C burst due to artesian pore water pressures:
Why I am convinced Dike C burst due to artesian pore water pressures: When I suspected in February 2009 that failure at Kingston was probably caused by artesian pore water pressures in the sluiced ash and informed my clients, one of them said, “We may have similar symptoms at the toe of one of our dredge cells.” Piezometers were then installed, revealing as much as 4 feet of artesian head. Internal drainage and buttress improvements were completed by May 2009; thus, the cause of failure theory in my June 2009 white paper report for Kingston had been validated and remediated at another ash disposal site. In defense of TVA, I found no evidence faulting it for actions taken during design and construction of the dredge cells. Results of my analysis show the dredge cells were safe until undermining of their foundation by failure of Dike C. Failing to recognize that the dredge cells caused increased pore water pressures beneath Dike C is a regrettable, yet understandable,
caused increased pore water pressures beneath Dike C is a regrettable, yet understandable, mistake that can only be corrected on future sites if the actual cause of failure at Kingston is recognized.... Also, if forensic experts couldn’t figure it out after the failure , then how can we criticize TVA for not recognizing the potential problem at Dike C before the failure?
In the debate over cause of failure, I admit I had an advantage because my theory that artesian pore water pressures caused the failure at Kingston had been validated and remediated at another dredge cell site, but examine the logic of the various theories by asking yourself these questions:
•
•
•
•
•
What is the difference between wet ash and dry ash?
Drains are installed to improve stability of earthen or waste structures by draining what?
Relief wells beneath TVA’s hydroelectric dams reduce uplift pressure of what?
Piezometers are installed to assess stability by measuring the level/pressure of what?
Clay cores are incorporated into dams to impede seepage of what?
• Liners reduce leakage of what?
Liners reduce leakage of what?
• Caps are installed upon abandonment to reduce infiltration of what? • What can build up pressure to cause explosive embankment blowouts?
• Two adjacent ash facilities have identical geometries, were built by the same hydraulic filling method and on
same hydraulic filling method, and on the same type of foundation. One is stable because it is well‐drained, while the other is on the verge of failure due to an uncontrolled build‐up of what?
Outlet pipe for remedial French drain discharging at same location as lower spillway pipe outfall
Lessons‐Learned:
• When humans first built walls, water accumulated behind some and they failed.
• Our ancestors didn
Our ancestors didn’tt adopt undrained adopt undrained “Creep
Creep of the Slimes/Static Liquefaction
of the Slimes/Static Liquefaction” theory theory
and design/build stronger walls, they put drains behind the walls to reduce the potential for water to accumulate.
• In my opinion, the Kingston failure validates current, prudent engineering practice for y p
,
g
,p
g
gp
the design of hydraulic fill structures using relatively high kh/kv values for hydraulic fill… and reinforces my fear of hinges and respect for water.
• What we should learn from the Kingston failure is that if Dike C had been raised with compacted ash and internal drains, similar to the construction of the northeastern outslope of the dredge cells, then failure of the Kingston Ash Facility would likely have been averted; but, monitor pore water pressures beneath hinges 2 pressures
beneath hinges 2
and 3, because pore water pressures here could increase as sluiced ash levels increase
Lessons‐Learned (continued):
• What we should also learn from the Kingston failure is that if shallow trench drains and relief wells had been installed at Dike C as mitigation similar to those installed at the
relief wells had been installed at Dike C as mitigation, similar to those installed at the northwestern outslope of the dredge cells, then failure of the Kingston Ash Facility would but, monitor pore water pressures beneath hinges 2 likely have been averted; and 3, because pore water pressures here could increase as sluiced ash levels increase
l
d hl l
However, merely building the dredge cells on a flatter outslope to resist an undrained “Creep of the Slimes/Static Liquefaction” failure would have made no difference in the outcome…
because, as the sign on my office wall says, “It’s the water, Stupid”