SAMPLE Please review the attached screening memo for customer requirements, system

SAMPLE
Please review the attached screening memo for customer requirements, system
modifications, or special operating requirements for your generation system. After
reviewing the screening memo, please also find the attached Interconnection Service
Agreement (Exhibit F) for your use. Other forms are available at
https://www.nationalgridus.com/masselectric/business/energyeff/4_standard-interconnection.asp. Please
use the checklist below to ensure that you provide all necessary documentation:
Legend: [ ] = Required; [C] = Complete; [NA] = Not Applicable; [NR] = Not Required
1. [ ] Please verify that the legal information, as entered in the attached Interconnection
Service Agreement, is correct.
2. [ ] Exhibit F - Interconnection Service Agreement - must be signed and emailed to
National Grid (Note: initials are required on every page at the bottom).
3. [ ] Exhibit G - Agreement between the Company and the Company's Retail Customer (if
applicable) - must be signed and emailed to National Grid (Note: initials are required on
every page at the bottom).
4. [ ] Schedule Z - must be signed and emailed to National Grid.
5. [ ] MA System of Assurance of Net Metering Eligibility documentation (if applicable).
6. [ ] The Certificate of Completion, signed by the local wiring inspector or an electric
permit signed by the local wiring inspector must be emailed to National Grid.
7. [ ] Final relay settings, breaker(s) setting (curve) and testing plan. The testing plan shall
include the testing company letter-head, be in a suitable format to be used by National
Grid, in the field, to witness the test and should include the testing steps in chronological
order. Each step should have a pass/fail field, a description of the action(s) required field
and a description of the anticipated result field.
8. [ ] National Grid reserves the right to schedule a Witness Test upon receiving a
Certificate of Completion, final relay settings and testing plan. National Grid anticipates
one site visit per interconnection application. If more are required there will be an
additional fee for each visit.
9. [ ] The customer will have to pay for the witness test by check. A check for X dollars
should be sent to the address listed below after the witness test procedure is approved
and before the witness test is conducted.
10. [ ] The customer must demonstrate that the system has passed a commissioning test, to
be conducted by the contractor.
a. [ ] National Grid must receive a signed memo attesting to the following:
i. The system passed the "2 seconds shutdown when utility disconnect is
open” test
ii. The system passed the “5 minutes before restart after utility disconnect is
closed" test
iii. A visual inspection of the system confirms that the system matches the
one line diagram
iv. The relay settings identified in the Interconnection Standards are adhered
to and listed in the signed memo.
b. [ ] A complete AS BUILT 1-line diagram must be provided. The 1-line and the
Memo should be signed and dated on the day of the inspection.
11. [ ] The customer must provide clear pictures of the following, in close up and wide angle
format.
a. [ ] The utility revenue meter
i. [ ] If a phone line is required, this picture must show the phone line.
b. [ ] The generator(s) or inverter(s)
c. [ ] The EXTERNAL AC Utility Disconnect Switch
d. [ ] The current limiting device (fuse or circuit breaker)
e. [ ] The customer owned production meter (if installed)
SAMPLE
SAMPLE
f.
[ ] The PCC (Point of Common Coupling, as identified in the Interconnection
Service Agreement)
12. [ ] Permanent Plaques (visible at eye level), as described below (Pictures must clearly
and legibly show the lettering on the plaques).
a. [ ] A permanent plaque on the external AC Utility Disconnect Switch labeled “AC
Utility Disconnect Switch”.
b. [ ] A permanent plaque or directory shall be installed at the utility revenue meter
with a warning about the generator(s) installed.
i. [ ] If the external utility disconnect switch is not adjacent to the utility
revenue meter, an additional permanent plaque shall be provided at the
utility revenue meter and the PCC locating the switch.
c. [ ] A permanent plaque or directory shall be installed at the PCC with a warning
about the generator(s) installed.
i. [ ] If the PCC is at a pad mounted transformer, the plaque must be on the
right door of the transformer.
ii. [ ] If the PCC is at the weatherhead or is the revenue meter socket, the
plaque at Utility Revenue Meter is sufficient.
iii. [ ] If the PCC is at a primary meter, the plaque must be on the pole where
the primary meter is mounted.
iv. [ ] If the external utility disconnect switch is not adjacent to PCC, an
additional permanent plaque shall be provided at the PCC locating the
switch.
d. [ ] A permanent plaque on the Customer-owned production meter labeled
“Customer-Owned Production Meter”.
e. [ ] If the new service equipment for the generator and all existing service
equipment are not grouped and adjacent, a permanent plaque shall be provided
at each piece of service equipment locating all other pieces of service equipment.
f. [ ] All plaques as described in NEC 705.10, 705.12 (7), 690.56, 692.4 and 705.70
shall be installed when applicable.
13. [ ] The customer is responsible for providing National Grid with evidence of insurance in
compliance with section 11 of the agreement and the Interconnection Standards. Please
provide an original insurance certificate naming "National Grid USA and its Subsidiaries
& Affiliates" as additional insured. The original must be mailed to the address in the
service agreement.
14. [ ] Phone line installed and phone number provided. Phone number:
.
15. [ ] QF certificate documentation (FERC Form No. 556).
16. [ ] Information as required in the Impact Study.
17. [ ] Information as required in the Customer Requirements section of the Screening
Memo.
18. [ ] Installation of Net Meter. (Note: Net meter installation could take up to three weeks
for installation after documentation and phone line provided.)
19. [ ] Authority to Interconnect Letter to be provided by National Grid after all
requirements satisfied, and after net meter has been set.
The National Grid’s Electric System Bulletin ESB756 “Requirements for Parallel Generation
Connected to a National Grid-Owned EPS” applies to this distributed generation system. In
Massachusetts, Appendix C of ESB756 should be referenced for all distributed generation
projects that operate in parallel with National Grid’s EPS. ESB756C is available at:
www.nationalgridus.com/non_html/shared_constr_esb756.pdf.
SAMPLE