Project Manual for B.F. Yancey Elementary School Wastewater Treatment Improvements IFB# 2015-06113-06 Bid Document May 15, 2014 Prepared by: WW Associates, Inc. 3040 Avemore Square Place Charlottesville, VA 22911 WWA Project No. 213003.05 For: County School Board of Albemarle County Building Services Department 2751 Hydraulic Road Charlottesville, Virginia 22901 INVITATION FOR BIDS for B.F. YANCEY ELEMENTARY SCHOOL WASTEWATER TREATMENT IMPROVEMENTS IFB# 2015-06113-06 PROJECT MANUAL TABLE OF CONTENTS BIDDING INFORMATION Invitation for Bids Instructions to Bidders Prebid Question Form Bid Form Certification of Crimes Against Children Page No. IFB-1 ITB-1 to ITB-8 GENERAL CONDITIONS & FORMS Construction Contract General Conditions Supplemental General Conditions Special Conditions Pages 1 thru 1-57 1-7 1-3 BF-1 to BF-3 AC Form # Contract Between Owner and Contractor AC-9 Post-Bid Modification AC-9b Standard Performance Bond for Construction Contracts AC-10 Standard Labor and Material Payment Bond AC-10.1 Construction Change Order AC-11 Change Order Estimate (General Contractor) GC-1 Change Order Estimate (Subcontractor) SC-1 Change Order Estimate (Sub-subcontractor) SS-1 Schedule of Values and Certificate for Payment AC-12 Affidavit of Payment of Claims AC-13 Architect/Engineer’s Certificate of Substantial Completion AC-13.1a Architect/Engineer’s Certificate of Completion AC-13.1 Contractor’s Certificate of Substantial Completion AC-13.2a Contractor’s Certificate of Completion AC-13.2 Adverse Weather Day Rectification Form TECHNICAL SPECIFICATIONS Section DIVISION 1 – GENERAL REQUIREMENTS 01400 General Requirements Section DIVISION 2 – SITEWORK 02010 02050 02200 02500 02660 Erosion & Sediment Control Demolition Earthwork Surfacing and Incidental Construction Water Distribution System Pages 1 thru 01400-12 Pages 1 thru Page 1 of 2 02010-2 02050-5 02200-12 02500-3 02660-9 02720 02730 02735 02831 02936 Storm Sewer System Wastewater Piping Systems Pipe Supports and Anchor Chain Link Fences and Gates Seeding Section DIVISION 3 – CONCRETE 03300 03450 Cast-in-Place Concrete Precast Concrete Tanks Section DIVISION 11 – EQUIPMENT 11400 11600 11700 Package Wastewater Treatment Plant Chemical Feed Equipment Drip Irrigation System Section DIVISION 13 – SPECIAL CONSTRUCTON 13100 Precast Concrete Building System Section DIVISION 15 – FLOOR DRAIN EQUIPMENT, PIPING AND FITTINGS 15000 Floor Drain Equipment, Piping and Fittings Section DIVISION 16 – ELECTRICAL 16010 16040 16110 16120 16130 16140 16150 16190 16420 16450 16470 16475 16510 Electrical General Provisions Testing and Placing in Service Raceways Wire, Cable and Wiring Switch and Outlet Boxes Wiring Devices Motors Supporting Devices Electric Service Grounding Panelboards Molded Case Circuit Breakers Lighting 02720-2 02730-16 02735-3 02831-4 02936-5 03300-7 03450-12 Page 2 of 2 11400-13 11600-7 11700-18 13100-5 15000-2 16010-2 16040-2 16110-2 16120-2 16130-1 16140-1 16150-1 16190-3 16420-1 16450-1 16470-1 16475-1 16510-1 NOTICE OF INVITATION FOR BIDS # 2015-06113-06 Sealed bids are invited for the construction of the B.F. Yancey Elementary School Wastewater Treatment Improvements. The project is generally described as construction of package type wastewater treatment facilities consisting of flow equalization, secondary treatment with nitrification/denitrification, effluent pumping station, drip irrigation system, related yard piping, electrical systems, necessary appurtenances, and an access road. The project includes storm water management. Erosion and sediment controls will be required for all improvements. Sealed bids will be received at the Albemarle County Purchasing Office, Room 248, Albemarle County Office Building, 401 McIntire Road, Charlottesville, Virginia 22902. The deadline for submitting bids is 3:00 P.M., as determined by the Purchasing Agent, on Wednesday, June 11, 2014. The bids will be opened publicly and read aloud immediately following the receipt of bids. The estimated construction cost range for this project is $400,000 to $600,000. The “Time for Completion” will be as detailed in the Bid Form. Bids to be considered shall be received in a sealed envelope marked as follows: County of Albemarle, Purchasing Office, Room 248, Albemarle County Office Building, 401 McIntire Road, Charlottesville, VA 22902 / Contract: B.F. Yancey Elementary School Wastewater Treatment Improvements / IFB No. 2015-06113-06. Procedures for submitting a bid, claiming an error, withdrawal of bids, and other pertinent information are contained in the Instructions to Bidders, which is part of the Invitation for Bids. Withdrawal due to error in bid shall be permitted in accord with Section 9 of the Instructions to Bidders and §2.2-4330A (i), Code of Virginia. The Owner reserves the right to reject any or all bids. A pre-bid conference will be held at the school site, 7625 Porters Road, Esmont, Virginia 22937, at 10:00 a.m. on Wednesday, May 28, 2014. Attendance is mandatory for those submitting a bid. The contract shall be awarded on a lump sum basis. Contractor registration in accordance with Title 54.1, Chapter 11, of the Code of Virginia, is required. See the Instructions to Bidders for additional qualification requirements. The Invitation for Bids for the above project, including the drawings and the specifications prepared by WW Associates, Inc and containing the information necessary for bidding, may be downloaded online from the Albemarle County Purchasing web site at www.albemarle.org/purchasing. Please note that Bidders are responsible to check the Purchasing web site and download any Addenda issued for this Bid. The Invitation for Bid documents may also be inspected at the County of Albemarle, Purchasing Office, Room 248, Albemarle County Office Building, 401 McIntire Road, Charlottesville, VA 22902, Telephone 434-296-5854 or email to [email protected]. The Invitation for Bid documents will also be available for inspection at WW Associates, Inc., 3040 Avemore Square Place, Charlottesville, VA 22911. The County of Albemarle does not discriminate on the basis of race, religion, color, sex, national origin, age or disability, or against faith-based organizations as defined under the Virginia Public Procurement Act on the basis of such organization’s religious or charitable character. End of Notice of Invitation for Bids IFB Format (September 2013) IFB-1 INSTRUCTIONS TO BIDDERS The Invitation For Bids (IFB) consists of the Notice, this Instructions to Bidders, the Bid Form, the Pre-Bid Question Form, the Construction Contract General Conditions, the Supplemental General Conditions (if any), the Special Conditions (if any), the Forms to be used, and the Scope of Work as described by the Plans and Specifications, other documents listed in the Specifications, and any addenda which may be issued, all of which request qualified bidders to submit competitive prices or bids for providing the described work on the project. 1. CONDITIONS AT SITE OR STRUCTURE: Bidders shall be responsible for ascertaining pertinent local conditions such as location, accessibility, general character of the site or building, and the character and extent of existing work within or adjacent to the site. Claims, as a result of failure to have done so, will not be considered by the Owner. See Section 7 of the General Conditions entitled “Conditions at Site.” 2. EXPLANATIONS TO BIDDERS: Bidders may not rely on any oral explanation in regard to the meaning of drawings and specifications or oral instructions given before the award of the contract. Discrepancies, omissions or doubts as to the meaning of drawings and specifications shall be communicated in writing to the Architect/Engineer for interpretation. Bidders should use the “Prebid Question Form” provided in the bid documents. Bidders must so act to assure that questions reach the Architect/Engineer at least seven (7) days prior to the time set for the receipt of bids to allow a sufficient time for an addendum to reach them before the submission of their bids. If an addendum is required for clarification or interpretation of the Bid Documents, the addendum will be issued not later than five (5) days prior to the date set for the receipt of bids except an addendum withdrawing the invitation for bid or one which includes postponement of the date set for the receipt of bids. Any interpretation made will be in the form of an addendum to the Invitation For Bids, which will be made available to all bidders, and its receipt shall be acknowledged, in writing, by the bidder on the Bid Form. 3. TIME FOR COMPLETION: (a) “Time for Completion” shall be designated by the Owner on the Invitation for Bids or other prebid documents and shall mean the number of consecutive calendar days following the issuance of the Notice to Proceed which the Contractor has to substantially complete all Work required by the Contract. In some instances, the Time for Completion may be stated in the form of a Contract Completion Date based on a stipulated date of Notice to Proceed. Unless otherwise specified, the Contractor shall achieve Final Completion within thirty (30) days after the date of Substantial Completion. (b) When the Notice to Proceed is issued, it will state a Contract Completion Date, which has been set by the Owner based on date of the Notice to Proceed and the Time for Completion. (c) The Contractor, in preparing and submitting his bid, is required to take into consideration normal weather conditions. No additional compensation will be paid to the Contractor because of adverse weather conditions; however, an extension of time for abnormal weather will be considered by the Owner as indicated in the General Conditions. ITB-1 County of Albemarle Instructions to Bidders (Rev. February 2013) 4. PREPARATION AND SUBMISSION OF BIDS: (a) Bids shall be submitted on the forms furnished, or copies thereof, and shall be signed in ink. Erasures or other changes in a bid must be explained or noted over the signature of the bidder. Bids containing any conditions, omissions, unexplained erasures, alterations or items not called for in the proposal, or irregularities of any kind, may be rejected by the Owner as being incomplete or nonresponsive. (b) Each bid must give the complete legal name and full business address of the bidder and be signed by the bidder, or the bidder's authorized representative, with his usual signature. Bids by partnerships must be signed in the partnership name by one of the general partners of the partnership or an authorized representative, followed by the designation/title of the person signing. Bids by corporations must be signed with the legal name of the corporation followed by the name of the state in which it is incorporated and by the signature and title of the person authorized to bind it in this matter. The name of each person signing shall be typed or printed below the signature. A signature on a bid by a person who identifies his title as “President,” “Secretary,” “Agent” or other designation without disclosing the principal firm, shall be held to be the bid of the individual signing. When requested by the Owner, satisfactory evidence of the authority of the officer signing on behalf of the corporation shall be furnished. Trade or fictitious names may be referenced by using “t/a ___” but bids shall be in the legal name of the person or entity submitting the bid. (c) Bids with the bid guarantee shall be enclosed in a sealed envelope which shall be marked and addressed as indicated by the advertisement. If a contract is for one hundred twenty thousand dollars ($120,000) or more, or if the total value of all construction, removal, repair or improvements undertaken by the bidder within any twelve-month period is seven hundred fifty thousand dollars ($750,000) or more, the bidder is required under Title 54.1, Chapter 11, Section 1100, Code of Virginia, as amended, to be licensed in Virginia as a "Class A Contractor." If a contract is for seven thousand five hundred dollars ($7,500) or more, but less than one hundred twenty thousand dollars ($120,000), the bidder is required to be licensed in Virginia as a "Class B Contractor." The bidder shall place on the outside of the envelope containing the bid and shall place in the bid over his signature whichever of the following notations is appropriate and insert his Contractor license/registration number: Licensed Class A Virginia Contractor No. or Licensed Class B Virginia Contractor No. If the bidder is not properly licensed in Virginia at the time the bid is submitted, or if the bidder fails to provide this information on his bid or on the envelope containing the bid and fails to promptly provide said Contractor license number to the Owner in writing when requested to do so before or after the opening of bids, he shall be deemed to be in violation of Section 54.1-1115 of the Code of Virginia, as amended, and his bid will not be considered. (d) The Board for Contractors has interpreted its regulations to mean “a licensed Contractor can bid on a contract which contains work outside his license classification(s) as long as he subcontracts those items for which he is not qualified to licensed contractors with the appropriate License Classification and the work of the second party is incidental to the contract.” Therefore, the Owner may, as a part of determining whether the bidder is “responsible,” require the apparent low IT B-2 County of Albemarle Instructions to Bidders (Rev. February 2013) bidder to submit a listing of his subcontractors along with the license number and classification or specialty of each. (e) 5. The bidder must also place its Employer Identification Number (SSN or FEIN) in the space provided on the Bid Form. BID GUARANTEE: (a) Any bid (including the Total Base Bid plus all Additive Bid Items) which exceeds one hundred thousand dollars ($100,000) shall be accompanied by a Bid Bond payable to the Owner as obligee in an amount equal to five percent (5%) of the amount of the bid. A Bid Bond may be required for projects having bids of less than one hundred thousand dollars ($100,000) if such requirement is stated in the Notice of Invitation for Bids. The Bid Bond must be issued by a surety company which is legally authorized by the Virginia State Corporation Commission to do fidelity and surety business in the Commonwealth of Virginia. The bid bond shall identify the name and address of an attorney-in-fact who is appointed to act on behalf of the surety within the Commonwealth of Virginia. The address of the attorney-in-fact shall be within the Commonwealth of Virginia. The attorney -in-fact shall affix to the bond a certified and current copy of the power of attorney. Such Bid Bond shall guarantee that the bidder will not withdraw his bid during the period of sixty (60) days following the opening of bids; that if his bid is accepted, he will enter into a formal contract with the Owner in accordance with the Contract Between Owner and Contractor included as a part of the IFB Documents; that he will submit a properly executed and authorized Standard Performance Bond and Standard Labor and Material Payment Bond on the forms included in the IFB documents; and that in the event of the withdrawal of said bid within said period, or failure to enter into said contract and give said bonds within ten (10) days after he has received notice of acceptance of his bid, or other forfeiture under the Bid Bond, the bidder shall be liable to the Owner for the difference between the amount specified in said bid and such larger amount for which the Owner may contract with another party to perform the work covered by said bid, up to the amount of the bid guarantee. This amount represents the damage to the Owner on account of the default of the bidder in any particular hereof. See §2.2-4336 of the Code of Virginia. (b) See §2.2-4338 of the Code of Virginia for provisions allowing alternative forms of bid security in lieu of a Bid Bond. (c) The Bid Bonds or other bid security will be returned to all except the three lowest bidders after the formal opening of bids. The remaining Bid Bonds or bid security will be returned to the bidders after the Owner and the accepted bidder have executed the Contract and the Performance Bond and the Payment Bond have been approved by the Owner. (d) If the required Contract and bonds have not been executed within sixty (60) days after the date of the opening of the bids, then the bond or other bid security of any bidder will be returned upon his request, provided he has not been notified of the acceptance of his bid prior to the date of such request. 6. WITHDRAWAL OR MODIFICATION OF BIDS: (a) WITHDRAWAL: Bids may be withdrawn by written or telefaxed notice received from bidders prior to the deadline fixed for bid receipt. The bidder has sole responsibility to ensure that such ITB-3 County of Albemarle Instructions to Bidders (Rev. February 2013) notice is received by the Owner in the appropriate office designated in the Instructions to Bidders, and the Owner shall not be responsible for ensuring accurate or prompt delivery. A withdrawal must be signed by the person signing the sealed bid or by other individual(s) who is authorized to act on behalf of the bidder. Such authorization must be provided in writing at the time of withdrawal, and stated on the face of the withdrawal notice. Withdrawn bids may be resubmitted by the bidder up to the deadline fixed for bid receipt. (b) 7. 8. MODIFICATION: Bids may be modified only in the following manner. E-mail modifications are not acceptable. All modifications must be made by withdrawing the bid and including all modifications, including but not limited to price, inside the sealed bid envelope. All modifications must be signed by the person signing the sealed bid or by other individual(s) who is authorized to act on behalf of the bidder. Such authorization must be provided in writing with the modification, and stated on the face of the modification notice, to be placed inside the sealed bid. No modifications will be accepted unless they are submitted inside a sealed bid envelope. Unless otherwise specified by the bidder, price modifications will be applied to the Total Base Bid amount shown on the Bid Form. Faxes, notations on the outside of envelopes, envelope "cuts" or other external writings will not be accepted. Delivery of modifications to the appropriate office designated in the Instructions to Bidders shall be the sole responsibility of the bidder, and the Owner shall not be responsible for ensuring accurate or prompt delivery. RECEIPT OF BIDS: (a) Bids will be received at or before the date and the hour and at the place stipulated in the Invitation for Bids as may be modified by subsequent Addenda. (b) It is the responsibility of the bidder to assure that his bid and any bid modifications are delivered to the place designated for receipt of bids by the date and hour (deadline) set for receipt of bids. Therefore, it is the bidder’s responsibility to take into account all factors which may impact on its bid deliverer/courier’s ability to deliver the bid and to implement whatever actions are necessary to have the bid delivered to the proper bid receipt location prior to the bid receipt deadline. No bids or bid modifications submitted or offered after the date and hour designated for receipt of bids will be accepted or considered. (c) The Purchasing Agent is the Owner's representative designated to receive bids at the time and place noted in the IFB and to open the bids received at the appointed time. (d) The official time used for the receipt of responses is determined by reference to the clock designated by the Purchasing Agent. The Purchasing Agent shall determine when the Bid Receipt Deadline has arrived and shall announce that the Deadline has arrived and that no further bids or bid modifications will be accepted. All bids and bid modifications in the possession of the Purchasing Agent and his assistants at the time the announcement is completed are deemed to be timely, whether or not the bid envelope has been physically date/time stamped or otherwise marked by the time the Purchasing Agent makes the deadline announcement. OPENING OF BIDS: (a) Bids will be opened at the time and place stated in the Invitation for Bids or as modified by subsequent Addenda, and their contents publicly announced. The Purchasing Agent shall decide IT B-4 County of Albemarle Instructions to Bidders (Rev. February 2013) when the specified time for bid opening has arrived. No responsibility will be attached to any officer or agent for the premature opening of a bid not properly addressed and identified. (b) 9. The provisions of §2.2-4342 of the Code of Virginia shall be applicable to the inspections of bids received. ERRORS IN BIDS: A bidder may withdraw his bid from consideration if the price bid was substantially lower than the other bids due solely to a mistake therein, provided the bid was submitted in good faith, and the mistake was a clerical mistake as opposed to a judgment mistake, and was actually due to an unintentional arithmetic error or an unintentional omission of a quantity of work, labor or material made directly in the compilation of a bid, which unintentional arithmetic error or unintentional omission can be clearly shown by objective evidence drawn from inspection of original work papers, documents and materials used in the preparation of the bid sought to be withdrawn. The bidder shall give notice of a claim to withdraw a bid, in writing, and submit his original work papers, documents and materials used in the preparation of his bid, to the Purchasing Agent within two business days after the conclusion of the opening of bids. §2.2-4330(B)(1) of the Code of Virginia. Failure of a bidder to give notice and submit his original work papers, documents and materials used in the preparation of his bid on or before the time, date and place required shall constitute a waiver by that bidder of his right to withdraw his bid due to a mistake. No bid may be withdrawn under this section when the result would be the awarding of the Contract on another bid of the same bidder or of another bidder in which the ownership of the withdrawing bidder is more than five percent (5%). No bidder who is permitted to withdraw a bid shall, for compensation, supply any material or labor to or perform any subcontract or other work agreement for the person or firm to whom the Contract is awarded or otherwise benefit, directly or indirectly, from the performance of the project for which the withdrawn bid was submitted. The person or firm to whom the Contract was awarded and the withdrawing bidder are jointly liable to the Owner in an amount equal to any compensation paid to or for the benefit of the withdrawing bidder without such approval. If a bid is withdrawn under authority of this section, the lowest remaining bid shall be deemed to be the low bidder on the project. 10. REJECTION OF BIDS: The Owner reserves the right to cancel the Invitation for Bids, to reject any and all bids at its sole discretion when such rejection is in the interest of the Owner, or to reject the bid of any bidder who is determined to be not responsive or not responsible. See §2.2-4319, Code of Virginia. 11. DETERMINATION OF RESPONSIBILITY: Each bidder shall be prepared, if so requested by the Owner, to present evidence of his experience, qualifications and financial ability to carry out the terms of the Contract. Prior to award of the Contract, an evaluation will be made to determine if the low bidder has the capability, in all respects, to perform fully the contract requirements and the moral and business integrity and reliability which will assure good faith performance, and who has been prequalified, if required. Factors to be evaluated may include, but are not limited to: ITB-5 County of Albemarle Instructions to Bidders (Rev. February 2013) (a) (b) (c) (d) (e) (f) sufficient financial ability to perform the contract as evidenced by the bidder's ability to obtain payment and performance bonds from an acceptable surety; appropriate experience to perform the Work described in the bid documents; any judgments entered against the bidder, or any officers, directors, partners or owners for breach of a contract for construction; any substantial noncompliance with the terms and conditions of prior construction contracts with a public body without good cause where the substantial noncompliance is documented; or a conviction of the bidder or any officer, director, partner, project manager, procurement manager, chief financial officer, or owner in the last five years of a crime relating to governmental or nongovernmental construction or contracting; any current debarment of the contractor, any officer, director or owner, from bidding or contracting by any public body of any state, any state agency, or any agency of the federal government. The Owner reserves the right to disqualify or refuse to accept the bid of any bidder who has been convicted, or entered a plea of guilty or nolo contendere, in any federal or state court to any charge involving any unlawful, corrupt or collusive practice involving a public contract whether federal, state, or local, or who has been determined in any judicial proceeding to have violated any antitrust, bidrigging or collusive practice statute in connection with any public contract, or against whom such formal criminal prosecution or other judicial proceeding has been initiated. A bidder who, despite being the apparent low bidder, is determined not to be a responsible bidder shall be notified in writing in conformance with the procedures in §2.2-4359 of the Code of Virginia. 12. AWARD OF CONTRACT: (a) Basis for Contract Award: The Contract, if awarded, will be awarded to the lowest responsive and responsible bidder, if any, provided his bid is reasonable and it is in the best interest of the Owner to accept it and subject to the Owner's right to reject any and all bids and to waive informality in the bids and in the bidding. The Bid Form may contain a multi-part Base Bid and may contain Additive Bid Items. Determination of the lowest responsible bidder, if any, will be based on the Total Base Bid amount entered on the Bid Form including any properly submitted bid modifications plus as many Additive Bid Items taken in sequence as the Owner in its discretion chooses to Award. Where the sum of the values entered in the multiple parts do not agree with the Total Base Bid amount, the Total Base Bid amount entered on the Bid Form, including any properly submitted bid modifications, shall take precedence. In the event that the Total Base Bid from the lowest responsible bidder exceeds available funds, the Owner may negotiate the Total Base Bid amount with the apparent low bidder to obtain a contract price within available funds, pursuant to §2.2-4318 of the Code of Virginia and Section 12(c) herein. (b) Informalities: The Owner reserves the right to waive any informality in the bids. (c) Negotiation With Lowest Responsible Bidder: If award of a contract to the lowest responsive and responsible bidder is precluded because of limitations on available funds, under the provisions of §2.2-4318 of the Code of Virginia (the Public Procurement Act), the Owner reserves the right to negotiate the Total Base Bid amount with the lowest responsive, responsible bidder to obtain a contract price within the available funds. This may involve changes in either the features or scope of the work included in the Base Bid. Such negotiations with the apparent IT B-6 County of Albemarle Instructions to Bidders (Rev. February 2013) low bidder may include reducing the quantity, quality, or other cost saving mechanisms involving items in the Total Base Bid. The Owner shall notify the lowest responsive and responsible bidder that such a situation exists and the Owner and bidder shall then conduct their negotiations in person, by mail, by telephone or by any means they find convenient. If an acceptable contract can be negotiated, the changes to the Invitation for Bid documents agreed upon in the negotiations shall be summarized in a “Post Bid Modification” and included in the contract. If an acceptable contract cannot be negotiated, the Owner shall terminate negotiations and reject all bids. 13. CONTRACT SECURITY: For contracts of more than $100,000, the Standard Performance Bond (Form AC-10) and the Standard Labor and Material Payment Bond (Form AC-10.1) shall be required, as specified in the Invitation for Bids documents. See the General Conditions and §2.2-4337 and §2.24338 of the Code of Virginia. The Owner reserves the right to require such bonds for contracts less than $100,000. If the Owner so elects, the requirement shall be set forth in the Invitation for Bids. The bonds shall identify the name and address of an attorney-in-fact who is appointed to act on behalf of the surety within the Commonwealth of Virginia. The address of the attorney-in-fact shall be within the Commonwealth of Virginia. The attorney-in-fact shall affix to the bond a certified and current copy of the power of attorney. 14. CERTIFICATION: The bidder, by his signature on the Bid Form, certifies that neither his organization nor any of its officers, directors, partners or owners is currently barred from bidding on contracts by the Commonwealth of Virginia, or any public body or agency of another state, or any agency of the federal government. See the statement “Disqualification of Contractors” in the Bid Form. 15. ETHICS IN PUBLIC CONTRACTING: The provisions, requirements and prohibitions as contained in Chapter 43, Article 6, §2.2-4367 et seq, Code of Virginia, pertaining to bidders, offerers, contractors, and subcontractors are applicable to this project. 16. BUILDING PERMITS: The Virginia Uniform Statewide Building Code shall apply to the Work and shall be administered by the local Building Official. The Building Permit will be paid and obtained for by the Owner. All other permits, local license fees, business fees, taxes, or similar assessments shall be obtained and paid for by the Contractor. See Section 25 of the General Conditions for utility connection fees and services. 17. MINORITY UTILIZATION: The County of Albemarle, Virginia, encourages the participation of minority businesses in public procurement activities. Towards that end, the Owner encourages firms to provide for the participation of minority owned businesses through partnerships, joint ventures, subcontracts, and other contractual opportunities. 18. BID DOCUMENTS: Bid Documents are the property of the Owner and are available electronically through the Purchasing Department’s file transfer protocol (FTP) site. Bidders are responsible to check the Purchasing FTP site and download any Addenda issued for the bid. A deposit is not required for downloading of electronic documents through the FTP site. The bidder is responsible for the cost of printing any contract documents necessary for bidding. If awarded a contract, the Owner will provide the contractor with two sets of contract documents (i.e. full sized drawings and specifications) for use in the field and the contractor will be responsible for the cost of printing any additional contract documents that may be needed. 19. GENERAL CONDITIONS: The County of Albemarle Construction Contract General Conditions are incorporated in the bid documents. The bidder may obtain a copy of the current edition of the ITB-7 County of Albemarle Instructions to Bidders (Rev. February 2013) Construction Contract General Conditions at no cost by request to the County of Albemarle, Office of Facilities Development, 401 McIntire Road, Room 228, Charlottesville, Virginia 22902 (434-8724501). 20. PREBID CONFERENCE: See the Invitation for Bids for requirements for a prebid conference and whether such conference is mandatory or optional. 21. INSPECTION OF BID DOCUMENTS: Copies of the Invitation for Bids documents including Plans and Specifications and the Construction Contract General Conditions will be available for inspection at the Albemarle County Purchasing Department, the A/E’s office, and at the locations listed in the Notice of the Invitation for Bids. 22. DRUG-FREE WORKPLACE REQUIRED: Bidders are reminded that §2.2-4312 of the Code of Virginia requires that during the performance of the contract resulting from this solicitation, the contractor agrees to (i) provide a drug-free workplace for the contractor’s employees; (ii) post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the contractor’s workplace and specifying the actions that will be taken against employees for violations of such prohibition; (iii) state in all solicitations or advertisements for employees placed by or on behalf of the contractor that the contractor maintains a drug-free workplace; and (iv) include the provisions of the foregoing clauses in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor. For the purposes of this section, "drug-free workplace" means a site for the performance of work done in connection with a specific contract awarded to a contractor in accordance with this solicitation, the employees of whom are prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession or use of any controlled substance or marijuana during the performance of the contract. 23. CERTIFICATION OF CRIMES AGAINST CHILDREN: Pursuant to Virginia Code §22.1296.1(C), as a condition of awarding a contract for the provision of services that require the contractor or his employees to have direct contact with students on school property during regular school hours or during school-sponsored activities, the School Board requires the contractor to provide certification that all persons who will provide such services have not been convicted of a felony or any offense involving the sexual molestation or physical or sexual abuse or rape of a child. Any person making a materially false statement regarding any such offense shall be guilty of a Class 1 misdemeanor and, upon conviction, the fact of such conviction shall be grounds for the revocation of the contract to provide such services and, when relevant, the revocation of any license required to provide such services. This requirement does not apply to a contractor or his employees providing services to the School Board in an emergency or exceptional situation, such as when student health or safety is endangered or when repairs are needed on an urgent basis to ensure that school facilities are safe and habitable, when it is reasonably anticipated that the contractor or his employees will have no direct contact with students. ITB-8 County of Albemarle Instructions to Bidders (Rev. February 2013) PREBID QUESTION FORM (Use separate form for each question submitted.) DATE: PROJECT: B.F. Yancey Elementary School Wastewater Treatment Improvements The following question concerns Drawing Sheet (number) ________________: The following question concerns Specifications Section (number) _______________ , page paragraph _______________ : All responses to questions will be made by Addendum. Questions submitted by: ______________________________ Name Organization Email Form To: County of Albemarle Purchasing Agent – [email protected] County of Albemarle Project Manager – [email protected]. WW Associates, Inc., Herbert F. White, P.E. – [email protected] Or Mail/Fax Form to: County of Albemarle Purchasing Department 401 McIntire Road, Room 248 Charlottesville, VA 22902-4596 FAX: (434) 972-4006 WW Associates, Inc. Attn: Herbert F. White, III, P.E. 3040 Avemore Square Place Charlottesville, VA 22911 [email protected] County of Albemarle Prebid Question Form (September 2013) , BID FORM DATE: May 15, 2014 PROJECT TITLE: B.F. Yancey Elementary School Wastewater Treatment Improvements IFB No. 2015-06113-06 TO: The County School Board of Albemarle County, Virginia Purchasing Office – Room 248 Albemarle County Office Building 401 McIntire Road Charlottesville, VA 22902 In compliance with and subject to your Invitation for Bids and the documents therein specified, all of which are incorporated herein by reference, the undersigned bidder proposes to furnish all labor, equipment, and materials and perform all work necessary for construction of this project, in accordance with the Plans and Specifications and the Addenda noted below, as prepared by WW Associates, Inc., 3040 Avemore Square Place, Charlottesville, Virgina 22911 for the consideration of the following amount: Base Bid Item No. 1 is defined as the Lump Sum price for construction of all improvements in accordance with plans and specifications: ___________________________________________ ______________________________________________________ Dollars ($ _______ ). (Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words shall govern.) Base Bid Item No. 2 is defined as the Owners Contingency: $15,000. Total Base Bid is defined as all work in Bid Item Nos. 1 and 2 for the sum of ______________ Dollars ($_______________). NOTES: 1. Owners contingency of $15,000 is an allowance in the Bid for potential change orders. Contractor shall include this in the Bid. Actual change order amounts will be negotiated using this contingency fund for that purpose. 2. B.F. Yancey Elementary School Wastewater Treatment Improvements consist of the following contract documents: . Project Manual entitled B.F. Yancey Elementary School Wastewater Treatment Improvements dated May 9, 2014 . Plans entitled B.F. Yancey Elementary School Wastewater Treatment Improvements dated March 21, 2014 . Plans entitled B.F. Yancey Elementary School Wastewater Treatment Improvements Erosion and Sediment Control Plan dated March 13, 2014 BF-1 Bid Form (Sept. 1998, Rev. Oct. 2001) Contract award will be based on the TOTAL LUMP SUM BID AMOUNT shown above (including any properly submitted bid modifications). The County reserves the right to reject any and all bids. The undersigned understands that time is of the essence and agrees that the time for Substantial Completion of the entire project shall be one hundred fifty (150) consecutive calendar days from the date of commencement of the Work as specified in the Notice to Proceed, and Final Completion shall be achieved within 30 consecutive calendar days after the date of Substantial Completion as determined by the A/E. All work on the existing school site, excluding the demolition of the existing septic tank, shall be completed by August 8, 2014. Acknowledgment is made of receipt of the following Addenda: ADDENDUM # DATE If notice of acceptance of this bid is given to the undersigned within 60 days after the date of opening of bids, or any time thereafter before this bid is withdrawn, the undersigned will execute and deliver a contract in the prescribed form (County of Albemarle Contract Between Owner and Contractor, Form AC-9) within 10 days after the contract has been presented to him for signature. The required payment and performance bonds, on the forms prescribed, shall be delivered to the owner along with the signed Contract. Immigration Reform and Control Act of 1986: The undersigned certifies that it does not and will not during the performance of the Contract for this project violate the provisions of the Federal Immigration Reform and Control Act of 1986, which prohibits employment of illegal aliens. DISQUALIFICATION OF CONTRACTORS: By signing this bid or proposal, the undersigned certifies that this Bidder or any officer, director, partner or owner is not currently barred from bidding on contracts by any Agency of the Commonwealth of Virginia, or any public body or agency of another state, or any agency of the federal government, nor is this Bidder a subsidiary or affiliate of any firm/corporation that is currently barred from bidding on contracts by any of the same. We have attached an explanation of any previous disbarment(s) and copies of notice(s) of reinstatement(s). CERTIFICATION OF NO COLLUSION: The undersigned does hereby certify in connection with the procurement and bid to which this Certification of No Collusion is incorporated that: This bid is not the result of, or affected by, any act of collusion with another person engaged in the same line of business or commerce; nor is this bid the result of, or affected by, any act of fraud punishable under Article 1.1 of Chapter 12 of Title 18.2 of the Code of Virginia, 1950, as amended (18.2-498.1 et seq.). BF-2 Bid Form (Sept. 1998, Rev. Oct. 2001) The undersigned declares that they are fully authorized to sign the proposal on behalf of the firm listed and to all conditions and provisions thereof. The firm name given below is the true and complete name of the bidder and the bidder is legally qualified and licensed by the Commonwealth of Virginia, Department of Commerce, State Board for Contractors, to perform all Work included in the scope of the Contract. Virginia License No. _______________________ Bidder _____________________________ (Name of Firm) Contractor Class __________________________ By _________________________ (Signature) Valid Until _______________________ (Typed Name) FEIN/SSN: _______________________________ Title: ______________________________ If Partnership (List Partner’s Names) If Corporation, affix Corporate Seal & list State of Incorporation State: ______________________________ (Affix Seal) Business Address: Telephone No.: Fax No.: Email: BF-3 Bid Form (Sept. 1998, Rev. Oct. 2001) CERTIFICATION OF CRIMES AGAINST CHILDREN Contractor acknowledges that the implementation of this contract requires Contractor, Contractor’s employees and subcontractors to have direct contact with Albemarle County Public Schools’ students. Therefore, Contractor hereby certifies that neither Contractor nor, to the best of Contractor’s knowledge, its employees and subcontractors have been convicted of a felony or any offense involving the sexual molestation or physical or sexual abuse or rape of a child. For the purposes of this certification, "direct contact with students" means being in the presence of students during regular school hours or during school sponsored activities. Contractor understands that, pursuant to Code of Virginia §22.1-296.1(C), making a materially false statement regarding offenses which are required to be included in the certification referenced above is a Class 1 misdemeanor and, upon conviction, the fact of such conviction shall be grounds for the revocation of the contract to provide such services and, when relevant, the revocation of any license required to provide such services. Albemarle County Public Schools shall not be liable for materially false statements regarding the certifications required under this Contract. Contractor By: Title: 5_Certification of Crimes Against Children - For School Projects.docx Date COUNTY OF ALBEMARLE CONSTRUCTION CONTRACT GENERAL CONDITIONS TABLE OF CONTENTS 1. DEFINITIONS ................................................................................................................................. 3 2. CONTRACT DOCUMENTS .......................................................................................................... 7 3. LAWS AND REGULATIONS ........................................................................................................ 8 4. NONDISCRIMINATION ................................................................................................................ 9 5. PROHIBITION OF ALCOHOL AND OTHER DRUGS .............................................................. 10 6. TIME FOR COMPLETION........................................................................................................... 10 7. CONDITIONS AT SITE ................................................................................................................ 12 8. CONTRACT SECURITY .............................................................................................................. 12 9. SUBCONTRACTS ........................................................................................................................ 13 10. SEPARATE CONTRACTS ........................................................................................................... 14 11. CONTRACTOR’S AND SUBCONTRACTOR’S INSURANCE ................................................ 14 12. “ALL RISK” BUILDER’S RISK INSURANCE ........................................................................... 15 13. TAXES, FEES AND ASSESSMENTS ......................................................................................... 16 14. PATENTS ...................................................................................................................................... 16 15. ARCHITECT/ENGINEER’S STATUS ......................................................................................... 17 16. INSPECTION................................................................................................................................. 18 17. SUPERINTENDENCE BY CONTRACTOR ............................................................................... 20 18. CONSTRUCTION SUPERVISION, METHODS AND PROCEDURES .................................... 21 19. SCHEDULE OF THE WORK ....................................................................................................... 21 20. SCHEDULE OF VALUES AND CERTIFICATE FOR PAYMENT ........................................... 25 21. ACCESS TO WORK ..................................................................................................................... 26 22. SURVEYS AND LAYOUT........................................................................................................... 26 -1County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) 23. PLANS AND SPECIFICATIONS ................................................................................................. 27 24. SUBMITTALS ............................................................................................................................... 28 25. FEES, SERVICES AND FACILITIES .......................................................................................... 30 26. EQUALS ........................................................................................................................................ 31 27. AVAILABILITY OF MATERIALS .............................................................................................. 32 28. CONTRACTOR’S TITLE TO MATERIALS ............................................................................... 32 29. STANDARDS FOR MATERIALS INSTALLATION & WORKMANSHIP .............................. 32 30. WARRANTY OF MATERIALS AND WORKMANSHIP .......................................................... 33 31. USE OF SITE AND REMOVAL OF DEBRIS ............................................................................. 34 32. TEMPORARY ROADS ................................................................................................................. 35 33. SIGNS ............................................................................................................................................ 35 34. PROTECTION OF PERSONS AND PROPERTY ....................................................................... 35 35. CLIMATIC CONDITIONS ........................................................................................................... 36 36. PAYMENTS TO CONTRACTOR ................................................................................................ 36 37. PAYMENTS BY CONTRACTOR (§2.2-4354, Code of Virginia) ............................................... 40 38. CHANGES IN THE WORK .......................................................................................................... 41 39. CONTRACTOR’S RIGHT TO STOP WORK OR TERMINATE THE CONTRACT ................ 46 40. OWNER’S RIGHT TO STOP WORK OR TERMINATE THE CONTRACT FOR CAUSE ..... 47 41. TERMINATION BY OWNER FOR CONVENIENCE ................................................................ 48 42. DAMAGES FOR DELAYS; EXTENSION OF TIME ................................................................. 48 43. INSPECTION FOR SUBSTANTIAL COMPLETION & FINAL COMPLETION ..................... 51 44. GUARANTEE OF WORK ............................................................................................................ 52 45. ASSIGNMENTS OF CONTRACTUAL OBLIGATIONS ........................................................... 54 46. CONTRACTUAL DISPUTES (§2.2-4363, Code of Virginia) ..................................................... 54 47. ASBESTOS .................................................................................................................................... 54 48. TRAINING, OPERATION AND MAINTENANCE OF EQUIPMENT ...................................... 55 49. PROJECT MEETINGS .................................................................................................................. 55 -2County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) 1. DE FI NI T IO NS Whenever used in these Construction Contract General Conditions (“General Conditions”) or in the Contract Documents, the following terms have the meanings indicated, which are applicable to both the singular and plural and the male and female gender thereof: Architect, Engineer, Architect/Engineer or A/E: The term used to designate the Architect and/or the Engineer that contracts with the Owner to provide the Architectural and Engineering services for the Project. The A/E is a separate contractor and not an agent of the Owner. The term includes any associates or consultants employed by the A/E to assist in providing the A/E services. Beneficial Occupancy: The condition after Substantial Completion but prior to Final Completion of the Project at which time the Project, or portion thereof, is sufficiently complete and systems operational such that the Owner could, after obtaining necessary approvals and certificates, occupy and utilize the space for its intended use. Guarantees and warranties applicable to that portion of the Work begin on the date the Owner accepts the Project, or a portion thereof, for such Beneficial Occupancy, unless otherwise specified in the Supplemental General Conditions or by separate agreement. Building Permit: The term building permit as used herein shall mean any and all permits required to comply with local and state building codes. Change Order: A document (Form AC-11) issued on or after the effective date of the Contract Between Owner and Contractor (Form AC-9) which is agreed to by the Contractor and approved by the Owner, and which authorizes an addition, deletion or revision in the Work, including any adjustment in the Contract Price and/or the Contract Completion Date. A Change Order once signed by all parties, with the exception of a Unilateral Change Order that is only signed by the Owner, is incorporated into and becomes a part of the Contract. Claim: A demand or assertion by one of the parties seeking, as a matter of right, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract. The term “claim” also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. Claims must be made by written notice. The responsibility to substantiate claims shall rest with the party making the claim. Code of Virginia: 1950 Code of Virginia as amended. Sections of the Code referred to herein are noted by (§xx-xx). Construction: The term used to include new construction, reconstruction, renovation, restoration, major repair, demolition and all similar work upon buildings and ancillary facilities, including any draining, dredging, excavation, grading or similar work upon real property. Contract: The Contract Between Owner and Contractor, Form AC-9, hereinafter referred to as the Contract. Contract Completion Date: The date by which the Work must be substantially complete. The Contract Completion Date is customarily established in the Notice To Proceed, based on the Time for -3County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) Completion. In some instances, however, the Contract contains a mandatory Contract Completion Date, which shall be stated in the Invitation for Bid. Contract Documents: The Contract Between Owner and Contractor (Form AC-9) signed by the Owner and the Contractor and any documents expressly incorporated therein. Such incorporated documents customarily include the bid submitted by the Contractor, these General Conditions, any Supplemental General Conditions, any Special Conditions, the plans and the specifications, and all modifications, including addenda and subsequent Change Orders. Contract Price: The total compensation payable to the Contractor for performing the Work, subject to modification by Change Order. Contractor: The person with whom the Owner has entered into a contractual agreement to do the Work. Day(s): Calendar day(s) unless otherwise noted. Defective: An adjective which, when modifying the word Work, refers to Work that is unsatisfactory, faulty, deficient, does not conform to the Contract Documents or does not meet the requirements of inspections, standards, tests or approvals required by the Contract Documents, or Work that has been damaged prior to the A/E’s recommendation of final payment (unless responsibility for the protection thereof has been assumed by Owner at Substantial Completion or Beneficial Occupancy). Drawing: A page or sheet of the Plans which presents a graphic representation, usually drawn to scale, showing the technical information, design, location, and dimensions of various elements of the Work. The graphic representations include, but are not limited to, plan views, elevations, transverse and longitudinal sections, large and small scale sections and details, isometrics, diagrams, schedules, tables and/or pictures. Emergency: Any unforeseen situation, combination of circumstances, or a resulting state that poses imminent danger to health, life or property. Final Completion Date: The date of the Owner’s acceptance of the Work from the Contractor upon confirmation from the Architect/Engineer and the Contractor that the Work is totally complete in accordance with Section 43(b). Field Order: A written order issued by the A/E which clarifies or explains the plans or specifications, or any portion or detail thereof, without changing the design, the Contract Price, the Time for Completion or the Contract Completion Date. Float: The excess time included in a construction schedule to accommodate such items as inclement weather and associated delays, equipment failures, and other such unscheduled events. It is the contingency time associated with a path or chain of activities and represents the amount of time by which the early finish date of an activity may be delayed without impacting the critical path and delaying the overall completion of the Project. Any difference in time between the Contractor’s approved early completion date and the Contract Completion Date shall be considered a part of the Project float. -4County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) Float, Free: The time (in days) by which an activity may be delayed or lengthened without impacting upon the start day of any activity following in the chain. Float, Total: The difference (in days) between the maximum time available within which to perform an activity and the duration of an activity. It represents the time by which an activity may be delayed or lengthened without impacting the Time for Completion or the Contract Completion Date. Notice: All written notices, including demands, instructions, claims, approvals and disapprovals, required or authorized under the Contract Documents. Any written notice by either party to the Contract shall be sufficiently given by any one or combination of the following, whichever shall first occur: (1) delivered by hand to the last known business address of the person to whom the notice is due; (2) delivered by hand to the person’s authorized agent, representative or officer wherever they may be found; or (3) enclosed in a postage prepaid envelope addressed to such last known business address and delivered to a United States Postal Service official or mailbox. Notice is effective upon such delivery. All notices to the Owner should be directed to the Project Manager. Notices transmitted by Facsimile (Fax) are acceptable for the Project. Notices shall be transmitted to the Fax number listed in the Contract and shall have a designated space for the Fax Notice recipient to acknowledge his receipt by authorized signature and date. The Fax Notice with authorized signature acknowledging receipt shall be Faxed back to the sender. The Faxed Notice shall be effective on the date it is acknowledged by authorized signature. All Faxed Notices shall also be sent by hard copy, which shall be effective upon delivery, as provided herein. Notice shall be effective upon the date of acknowledgment of the Faxed Notice or the date of delivery, whichever occurs first. Notice to Proceed: A written notice given by the Owner to the Contractor (with a copy to A/E) fixing the date on which the Contract time will commence for the Contractor to begin the prosecution of the Work in accordance with the requirements of the Contract Documents. The Notice to Proceed will customarily identify a Contract Completion Date. Owner: County of Albemarle, Virginia and/or The County School Board of Albemarle County, Virginia. Person: This term includes any individual, corporation, partnership, association, company, business, trust, joint venture, or other legal entity. Plans: The term used to describe the group or set of project-specific drawings which are included in the Contract Documents. Project: The term used instead of the specific or proper assigned title of the entire undertaking which includes, but is not limited to, the “Work” described by the Contract Documents. Project Inspector: One or more persons and/or firms employed by the Owner to inspect the Work for the Owner and/or to document and maintain records of activities at the Site to the extent required by the Owner. The scope of the Project Inspector’s authority with respect to the Contractor is limited to that indicated in Section 16(e) and (f). -5County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) Project Manager: The Project Manager as used herein shall be the Owner’s designated representative on the Project. The Project Manager shall be the person through whom the Owner generally conveys written decisions and notices. All notices due the Owner and all information required to be conveyed to the Owner shall be conveyed to the Project Manager. The Owner may change the Project Manager from time to time and may, in the event that the Project Manager is absent, disabled or otherwise temporarily unable to fulfill his duties, appoint an interim Project Manager. Provide: Shall mean furnish and install ready for its intended use. Site: Shall mean the location at which the Work is performed or is to be performed. Specifications: That part of the Contract Documents containing the written administrative requirements and the technical descriptions of materials, equipment, construction systems, standards, and workmanship which describe the proposed Work in sufficient detail and provide sufficient information for the Building Official to determine code compliance and for the Contractor to perform the Work. (The General Conditions, any Supplemental General Conditions, various bidding information and instructions, and blank copies of various forms to be used during the execution of the Work are usually bound with the Specifications.) Subcontractor: A person having a direct contract with Contractor or with any other Subcontractor for the performance of the Work. Subcontractor includes any person who provides on-site labor but does not include any person who only furnishes or supplies materials for the Project. Submittals: All shop, fabrication, setting and installation drawings, diagrams, illustrations, schedules, samples, and other data required by the Contract Documents which are specifically prepared by or for the Contractor to illustrate some portion of the Work and all illustrations, brochures, standard schedules, performance charts, instructions, diagrams and other information prepared by a Supplier and submitted by the Contractor to illustrate material or equipment conformance of some portion of the Work with the requirements of the Contract Documents. Substantial Completion: The condition when the Owner agrees that the Work, or a specific portion thereof, is sufficiently complete, in accordance with the Contract Documents, so that it can be utilized by the Owner for the purposes for which it was intended. The Owner at its sole discretion may, after obtaining the necessary approvals and certificates, take Beneficial Occupancy at this time or choose to wait to occupy until after Final Completion is achieved. Supplemental General Conditions: That part of the Contract Documents which amends or supplements the General Conditions. Supplier: A manufacturer, fabricator, distributor, materialman or vendor who provides material for the Project but does not provide on-site labor. Time for Completion: The number of consecutive calendar days following the issuance of the Notice to Proceed which the Contractor has to substantially complete all Work required by the Contract. When the Notice to Proceed is issued, it states a Contract Completion Date, which has been set by the Owner based on the Time for Completion. -6County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) Underground Facilities: All pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels or other such facilities or attachments, and any encasements containing such facilities which are or have been installed underground to furnish any of the following services or materials: electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, sewage and drainage removal, traffic or other control systems or water. Unilateral Change Order: A Change Order from the Owner directing the Contractor to proceed with work within the scope of the contract which may be undefined or for which there is no agreement on the cost or time associated with the work. Work: The services performed under this Contract including, but not limited to, furnishing labor, and furnishing and incorporating materials and equipment into the construction. The Work also includes the entire completed construction, or the various separately identifiable parts thereof, required to be furnished under the Contract Documents. 2. CONTRACT DOCUMENTS (a) The Contract Between Owner and Contractor (AC-9), the Standard Performance Bond (AC-10), the Standard Labor and Material Payment Bond (AC-10.1), the Schedule of Values and Certificate for Payment (AC-12), the Affidavit of Payments of Claims (AC-13), the Contractor’s Certificate of Substantial Completion (AC-13.2a), and the Contractor’s Certificate of Completion (AC-13.2) issued by the County of Albemarle are forms incorporated in these General Conditions by reference and are made a part hereof to the same extent as though fully set forth herein. They must be used by the Contractor for their respective purposes. (b) All time limits stated in the Contract Documents, including but not limited to the Time for Completion of the Work, are of the essence of the Contract. (c) The Contract Between Owner and Contractor shall be signed by the Owner and the Contractor in as many original counterparts as may be mutually agreed upon, each of which shall be considered an original. (d) Anything called for by one of the Contract Documents and not called for by the others shall be of like effect as if required or called for by all, except that a provision clearly designed to negate or alter a provision contained in one or more of the other Contract Documents shall have the intended effect. In the event of conflicts among the Contract Documents, the Contract Documents shall take precedence in the following order: the Contract Between Owner and Contractor; the Supplemental General Conditions; the General Conditions; the specifications with attachments; and the plans. (e) If any provision of this Contract shall be held invalid by any court of competent jurisdiction, such holding shall not invalidate any other provision. (f) All correspondence, invoices, memoranda, submittals and other documents related to this Project whether generated by the Owner, the A/E, the Contractor or others should be identified at the -7County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) beginning of the document with the Project Title shown in the Contract. Additional identification such as a job number, purchase order number or such may also be shown at the generator’s option. 3. LAWS AND REGULATIONS (a) The Contractor shall comply with all laws, ordinances, rules, regulations and lawful orders of any public authority bearing on the performance of the Work and shall give all notices required thereby. The Contractor shall assure that all Subcontractors and tradesmen who perform Work on the project are properly licensed by the Department of Professional and Occupational Regulation as required by Title 54.1, Chapter 11, Articles 1 and 3, Code of Virginia, and by applicable regulations. (b) This Contract and all other contracts and subcontracts are subject to the provisions of Articles 3 and 5, Chapter 4, Title 40.1, Code of Virginia, relating to labor unions and the “right to work.” The Contractor and its Subcontractors, whether residents or nonresidents of the Commonwealth, who perform any Work related to the Project shall comply with all of the said provisions. (c) IMMIGRATION REFORM AND CONTROL ACT OF 1986: By signing this Contract, the Contractor certifies that it does not and will not during the performance of this Contract violate the provisions of the Federal Immigration Reform and Control Act of 1986, which prohibits employment of illegal aliens. (d) The provisions of all rules and regulations governing safety as adopted by the Commission of the Commonwealth of Virginia and as issued by the Department Industry under Title 40.1 of the Code of Virginia shall apply to all Work under Inspectors from the Department of Labor and Industry shall be granted access to inspection without first obtaining a search or administrative warrant. Safety Codes of Labor and this Contract. the Work for (e) Building Permit: The Virginia Uniform Statewide Building Code applies to the Work and is administered by the local Building Official. The Building Permit will be obtained by the Contractor and paid for by the Owner. All other permits, local license fees, business fees, taxes, or similar assessments shall be obtained and paid for by the Contractor. See Section 25 for utility connection fees and services. (f) The Contractor shall include in each of its subcontracts a provision requiring each Subcontractor to include or otherwise be subject to the same payment and interest requirements in Subsections (a), (b), and (c) of Section 37 of these General Conditions with respect to each lower-tier Subcontractor and Supplier. (g) The Contractor, if not licensed as an asbestos abatement contractor in accordance with §54.1-514, Code of Virginia, shall have all asbestos-related Work performed by subcontractors who are duly licensed as asbestos contractors for the Work required. (h) Lead-Based Paint Activities: If the Contract Documents indicate that lead-based paint is present on existing materials, components, or surfaces, the Contractor shall conform to the following: -8County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (1) The requirements set forth in 59 Federal Register 45,872 (September 2, 1994) Proposed Rule Lead; Requirements for Lead-based Paint Activities (Proposed Rules) in selecting and performing the means, methods and procedures for performing the Work. This includes, but is not limited to, training of personnel, lead abatement, encapsulation of lead containing materials, removal and handling of lead containing materials, and methods of disposal. When the Final Rule, to be codified at 40 CFR 745, supersedes the Proposed Rule, the Contractor shall be responsible for conforming to the Final Rule, as of tile effective date set forth therein. (2) The requirements for employee protection contained in 29 CFR Part 1926, Subpart D, and the requirements for record-keeping contained in 29 CFR Part 1910. (3) The Virginia Department of Labor and Industry’s (DLI) Emergency Regulation published in the May 27, 1996 Virginia Register, requiring, among other things, that a permit be issued to the lead abatement contractor, or any subsequent regulation issued by DLI. (i) If the Contractor violates laws or regulations that govern the Project, the Contractor shall indemnify and hold the Owner harmless against any fines and/or penalties that result from such violation. To the extent that such violation is the result of negligence or other actionable conduct of the Contractor, the Contractor shall indemnify and hold the Owner harmless against any third party claims, suits, awards, actions, causes of action or judgments, including but not limited to attorney’s fees and costs incurred thereunder, that result from such violation. 4. NONDISCRIMINATION (a) §2.2-4311 of the Code of Virginia shall be applicable. It provides as follows: “1. During the performance of this Contract the Contractor agrees as follows: (a) The Contractor will not discriminate against any employee or applicant for employment because of race, religion, color, sex, national origin, age, disability, or other basis prohibited by state law relating to discrimination in employment, except where there is a bona fide occupational qualification reasonably necessary to the normal operation of the Contractor. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause. (b) The Contractor, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, will state that such Contractor is an equal opportunity employer. (c) Notices, advertisements and solicitations placed in accordance with federal law, rule or regulation shall be deemed sufficient for the purpose of meeting the requirements of this section. -9County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) 2. The Contractor will include the provisions of the foregoing paragraphs (a), (b) and c) in every subcontract or purchase order of over ten thousand dollars ($10,000), so that the provisions will be binding upon each Subcontractor or vendor.” (b) Where applicable, the Virginians with Disabilities Act and the federal Americans with Disabilities Act shall apply to the Contractor and all Subcontractors. 5. PROHIBITION OF ALCOHOL AND OTHER DRUGS (a) §2.2-4312 of the Code of Virginia shall be applicable. It provides as follows: “During the performance of this contract, the contractor agrees to (i) provide a drug-free workplace for the contractor’s employees; (ii) post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the contractor’s workplace and specifying the actions that will be taken against employees for violations of such prohibition; (iii) state in all solicitations or advertisements for employees placed by or on behalf of the contractor that the contractor maintains a drug-free workplace; and (iv) include the provisions of the foregoing clauses in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor. For the purposes of this section, “drug-free workplace” means a site for the performance of work done in connection with a specific contract awarded to a contractor in accordance with this chapter, the employees of whom are prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession or use of any controlled substance or marijuana during the performance of the contract.” (b) The Contractor shall also establish, maintain and enforce policies which prohibit the following acts by all Contractor, Subcontractor and Supplier personnel at the Site: (1) the manufacture, distribution, dispensation, possession, or use of alcohol or other drugs, except possession and medically prescribed use of prescription drugs; and (2) the impairment of judgment or physical abilities due to the use of alcohol or other drugs, including impairment from prescription drugs. 6. TIME FOR COMPLETION (a) The Time for Completion shall be designated by the Owner on the Invitation for Bids or other prebid documents. In some instances, the Time for Completion may be stated on the Invitation for Bids or other prebid document in the form of a Contract Completion Date. The Work must be substantially completed by the Time for Completion or the Contract Completion Date. Unless otherwise specified, the Contractor shall achieve Final Completion within thirty (30) days after the date of Substantial Completion. (b) The Time for Completion shall be stated in the Contract Between Owner and Contractor and shall become a binding part of the Contract upon which the Owner may rely in planning the use of -10County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) thefacilities to be constructed and for all other purposes. If the Contractor fails to substantially complete the Work within the Time for Completion or Contract Completion Date, as set forth in the Contract, he shall be subject to payment of actual damages incurred by the Owner or liquidated damages, if provided for in the Contract. (c) The Contractor, in submitting his bid, acknowledges that he has taken into consideration normal weather conditions. The listing below defines the monthly anticipated days of adverse weather for each month and is based upon NOAA climatological data for Charlottesville, Virginia, last revised January 1995. Adverse weather days shall be days of actual precipitation of 0.10 inch or greater. Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec 6 6 7 6 8 6 8 8 6 5 5 6 The anticipated days provided above will constitute the base line for adverse weather time evaluations. Throughout the portion of the contract from the date of Notice to Proceed until the building is “dried in”, actual adverse weather days are to be recorded by the Contractor and verified by the Architect each month. In addition to the anticipated days of adverse weather noted above, the Contractor must anticipate one day of adverse weather impact (snow, ice, mud) for each day of actual adverse weather during the months of January, February, March, and December. The building shall be considered “dried in” when the exterior block walls or stud and sheathing walls are in place, and a temporary (or permanent) roof is in place. The total anticipated adverse weather days for the project shall be the sum of all the monthly days for each month from the date of Notice to Proceed until the date the building is to be “dried in”, according to the Contractor’s schedule. If the total number of actual adverse weather days plus adverse weather impact days exceeds the anticipated adverse weather days determined above, the excess days may be used as a basis to determine whether a Contractor is entitled to a time extension. The adverse weather must have prevented work for 50 percent (50%) or more of the Contractor’s work day and delayed work critical to the timely completion of the project. The Contractor’s schedule must indicate the critical (path) work and must reflect the above anticipated adverse weather days for all weather dependent activities. (1) The extension requested must be supported by a delay in completion of the entire Project shown on the critical path of the accepted CPM Schedule or the approved bar graph schedule required for the Project. Extensions will be granted only for delays in completion of the Project, not for that portion of any delay which consumes only “float” time. (2) A request for extension of time based on abnormal weather must be made in writing within five (5) calendar days of the completion of the calendar month during which abnormal weather is claimed at the Site. (3) All of the evidence and data supporting the request (including both historical data and the recordings at the Site during the time of delay) must be furnished to the Owner before any -11County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) consideration will be given to the request. That supporting data shall be submitted by the end of the calendar month following the month for which the request is made. (d) The Contractor represents and agrees that he has taken into account in his bid the requirements of the bid documents, local conditions, availability of materials, equipment, and labor, and any other factors which may affect the performance of the Work. The Contractor agrees and warrants that he will achieve Substantial Completion of the Work to allow the Owner to have Beneficial Occupancy not later than the Time for Completion or Contract Completion Date. The Contractor agrees and warrants that he will achieve Final Completion of the Work (the entire completion of all Work, including “punch list” items), not later than thirty (30) days after achieving Substantial Completion. 7. CONDITIONS AT SITE (a) The Contractor is totally responsible for having ascertained pertinent local conditions such as location, accessibility and general character of the Site, and the character and extent of existing improvements and work within or adjacent to the Site. (b) If, in the performance of the Contract, hidden physical conditions of a building being modified are exposed revealing unusual or materially different conditions from those ordinarily encountered or inherent in work of this nature, or if subsurface or latent conditions at the Site are found which are materially different from those frequently present in the locality or from those indicated in the Contract Documents, the Contractor must report such conditions to the Owner and to the Architect/Engineer before the conditions are disturbed. Upon such notice, or upon his own observation of such conditions, the Architect/Engineer shall promptly propose such changes in the Contract Documents as he finds necessary to conform to the different conditions. Any change in the cost of the Work or additional time needed for completion must be requested pursuant to Sections 38 and/or 42 of these General Conditions. (c) If the Contractor, during the course of the Work, observes the existence of any material which he knows, should know, or has reason to believe is hazardous to human health, the Contractor shall promptly notify the Owner. The Owner will provide the Contractor with instructions regarding the disposition of the material. The Contractor shall not perform any Work involving the material or any Work causing the material to be less accessible prior to receipt of special instructions from the Owner. 8. CONTRACT SECURITY (a) For Contracts with a value exceeding one hundred thousand dollars ($100,000), the Contractor shall deliver to the Owner or its designated representative, a Standard Performance Bond and a Standard Labor and Material Payment Bond, each fully executed by the Contractor and one or more surety companies legally licensed to do business in Virginia and each in an amount equal to one hundred percent (100%) of the accepted bid. If more than one Surety executes a bond, each shall be jointly and severally liable to the Owner for the entire amount of the bond. Sureties shall -12County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) be selected by the Contractor, subject to approval by the Owner. No payment on the Contract shall be due and payable to the Contractor until the bonds have been approved by the Owner. (b) For the purposes of all Standard Labor and Material Payment Bonds entered into, the term “subcontractors” as used in §2.2-4337(A.2) of the Code of Virginia is interpreted to mean any contractors who participated in the prosecution of the Work undertaken by the Contractor (referred to in §2.2-4337(A.2) of the Code of Virginia as the “prime contractor”), whether such contractor had a direct contract with the Contractor (prime contractor) or whether there were one or more other intervening Subcontractors contractually positioned between it and the Contractor (prime contractor). (c) See §2.2-4338 of the Code of Virginia, for alternative forms of security for payment and/or performance bonds. (d) For contracts with a value of less than one hundred thousand dollars ($100,000), the Contractor will not be required to provide a Standard Performance Bond and a Standard Labor and Material Payment Bond as described above unless the Invitation for Bid states that such bonds will be required. 9. S UB CO NT RACTS (a) The Contractor shall, as soon as practicable after the signing of the Contract, notify the Owner and Architect/Engineer in writing of the names of all Subcontractors proposed for the principal parts of the Work and of such others as the Architect/Engineer may direct. Where the specifications establish qualifications or criteria for Subcontractors, manufacturers, or individuals performing Work on the Project, the Contractor shall be responsible for ascertaining that those proposed meet the criteria or qualifications. The Contractor shall not employ any Subcontractor that the Owner may, within a reasonable time, object to as unsuitable. Neither the Owner nor the Architect/Engineer shall direct the Contractor to contract with any particular Subcontractor unless provided in the specifications or Invitation for Bids. (b) The Owner may select a particular Subcontractor for a certain part of the Work and designate on the Invitation for Bids that the Subcontractor shall be used for the part of the Work indicated and that the Subcontractor has agreed to perform the Work for the subcontract amount stipulated on the bid form. The Contractor shall include the stipulated amount plus his Contractor markups in the bid. In such case, the Contractor shall be responsible for that Subcontractor and its work and the Subcontractor shall be responsible to the Contractor for its work just as if the Contractor had selected the Subcontractor. (c) The Owner shall, on request, furnish to any Subcontractor, if practicable, the amounts of payments made to the Contractor, the Schedule of Values and Requests for Payment submitted by the Contractor and any other documentation submitted by the Contractor which would tend to show what amounts are due and payable by the Contractor to the Subcontractor. -13County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (d) The Contractor shall be fully responsible to the Owner for all acts and omissions of his agents and employees and all succeeding tiers of Subcontractors and Suppliers performing or furnishing any of the Work. Nothing in the Contract Documents shall create any contractual relationship between Owner or Architect/Engineer and any such Subcontractor, Supplier or other person or organization, nor shall it create any obligation on the part of Owner or Architect/Engineer to pay for or to see to the payment of any moneys due any such Subcontractor, Supplier or other person or organization, except as may otherwise be required by law. (e) The Contractor shall be fully responsible for his invitees at the Site and for those of his Subcontractors, Suppliers, and their employees, including any acts or omissions of such invitee. (f) The Contractor agrees that he alone is responsible for all dealings with his Subcontractors and Suppliers, and their subcontractors, employees and invitee, including, but not limited to, the Subcontractors’ or Suppliers’ claims, demands, actions, disputes and similar matters unless specifically provided otherwise by the Contract or by statute. 10. SEPARATE CONTRACTS (a) The Owner reserves the right to let other contracts in connection with the Project, the Work under which may proceed simultaneously with the execution of this Contract. The Contractor shall afford other separate contractors reasonable opportunity for the introduction and storage of their materials and the execution of their work. The Contractor shall cooperate with them and shall take all reasonable action to coordinate his Work with theirs. If the Owner has listed other separate contracts in the Invitation for Bids which it expects to proceed simultaneously with the Work of the Contractor, and has included the estimated timing of such other Contracts in the Invitation for Bids, the Contractor shall integrate the schedule of those separate contracts into his scheduling. The Contractor shall make every reasonable effort to assist the Owner in maintaining the schedule for all separate contracts. If the work performed by the separate contractor is defective or performed so as to prevent or threaten to prevent the Contractor from carrying out his Work according to the Contract, the Contractor shall immediately notify the Owner and the Architect/Engineer upon discovering such conditions. (b) If a dispute arises between the Contractor and any separate contractor(s) as to their responsibility for cleaning up as required by Sections 31(c) and 31(d) of these General Conditions, the Owner may clean up and charge the cost thereof to the respective contractors in proportion to their responsibility. If a Contractor disputes the Owner’s apportionment of clean-up costs, it shall be that contractor’s burden to demonstrate and prove the correct apportionment. 11. CONTRACTOR’S AND SUBCONTRACTOR’S INSURANCE (a) Prior to execution of the Contract by the Owner, the Contractor shall provide written evidence (certificates of insurance) that he has obtained all the insurance required hereunder from an insurer authorized to do business in Virginia and such insurance has been approved by the Owner. Insurance providers must have an agent located in Virginia. The Contractor shall not allow any -14County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) Subcontractor to commence Work on his subcontract until the same types of insurance in an appropriate amount have been obtained by the Subcontractor and approved by the Contractor. Approval of insurance by the Owner shall not relieve or decrease the liability of the Contractor hereunder. In the event of cancellation of this insurance, not less than thirty (30) days prior written notice must be sent to the Owner. (b) The Contractor shall take out and shall maintain at all times during the performance of the Work Workers’ Compensation and Employers’ Liability Insurance for all of his employees engaged in the Work in an amount not less than the minimum required by §2.2-4332 and §65.2-100 et seq. of the Code of Virginia, and, in case any of the Work is sublet, the Contractor shall require each Subcontractor similarly to provide Workers’ Compensation and Employers’ Liability Insurance for all of the latter’s employees to be engaged in the Work. (c) During the performance of the Work under this Contract, the Contractor shall maintain commercial general liability insurance to include Premises / Operations Liability, Products and Completed Operations Coverage, Independent Contractor’s Liability, Owner’s and Contractor’s Protective Liability, and Personal Injury Liability, which shall insure him against claims of personal injury, including death, as well as against claims for property damage, which may arise from operations under this Contract whether such operations be by himself or by any Subcontractor, or by anyone directly or indirectly employed by either of them. The amounts of general liability insurance shall be not less than $1,000,000 per occurrence and $2,000,000 aggregate combined limit for projects with a construction cost of $200,000 or greater. The amounts of general liability insurance shall be not less than $250,000 per occurrence and $1,000,000 aggregate combined limit for projects with a construction cost of less than $200,000. The Owner, its officers, employees and agents, shall be named as an additional insured with respect to the Work being procured. The Supplemental General Conditions may require the Contractor to provide an Umbrella insurance policy in a specified amount for the Project. (d) During the performance of the Work under this Contract, the Contractor shall maintain automobile liability insurance which shall insure him against claims of personal injury, including death, as well as against claims for property damage, which may arise from operations under this Contract, whether such operations be by himself or by any Subcontractor, or by anyone directly or indirectly employed by either of them. The amounts of automobile insurance shall be not less than $1,000,000 combined limit for bodily injury and property damage per occurrence. (e) The Asbestos Contractor or Subcontractor, as the case may be, shall provide occurrence-based liability insurance with asbestos coverages in an amount not less than $1,000,000 and shall name the following as additional insured: The Owner, its officers, its employees and its agents; the Architect/Engineer (if not the Asbestos Project Designer); and the Contractor (where the asbestos work is being performed by the Asbestos Subcontractor). 12. “ALL RISK” BUILDER’S RISK INSURANCE (a) The Contractor, at his cost, shall obtain and maintain in the names of the Owner and the Contractor “all-risk” builder’s risk insurance (or fire, extended coverage, vandalism and malicious mischief -15County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) insurance, if approved by the Owner) upon the entire structure or structures on which the Work of this Contract is to be done, and upon all material in or adjacent thereto which is intended for use thereon, to one hundred percent (100%) of the insurable value thereof. Such insurance may include a deductible provision if the Owner so provides in the Supplemental General Conditions, in which case the Contractor will be liable for such deductions, whenever a claim arises. The loss, if any, is to be made adjustable with and payable to the Owner, in accordance with its interests, as they may appear. The Owner, its officers, employees and its agents, shall be named as an additional insured in any policy of insurance issued. Written evidence of the insurance shall be filed with the Owner prior to execution of the Contract by the Owner. Insurance providers must be authorized to do business in Virginia and have an agent located in Virginia. In the event of cancellation of this insurance, not less than thirty (30) days prior written notice must be sent to the Owner. A copy of the policy of insurance shall be given to the Owner upon demand. (b) The value of the builder’s risk insurance shall exclude the costs of excavations, backfills, foundations, underground utilities and Site work. (c) Certain projects, such as renovations and interior modifications of existing buildings, may be covered by the Owner’s insurance and may not require the “all risk” insurance required by this section. In those instances, the Supplemental General Conditions for the project shall expressly exclude the project from the requirements of Subsection 12(a). (d) Any insurance provided through the County of Albemarle, Virginia, for construction, additions or renovations will not extend to Contractor’s nor Subcontractors’ buildings, equipment, materials, tools or supplies unless these items are to become property of the Owner upon completion of the Project and the Owner has assumed responsibility for such items at the time of the loss. 13. TAXES, FEES AND ASSESSMENTS The Contractor shall, without additional expense to the Owner, pay all applicable federal, state, and local taxes, fees, and assessments except the taxes, fees and assessments on the real property comprising the Site of the project. The Owner shall pay inspection fees to the local building official except for reinspection fees resulting from incomplete or defective work. 14. PATENTS The Contractor shall obtain all licenses necessary to use any invention, article, appliance, process or technique of whatever kind and shall pay all royalties and license fees. The Contractor shall hold the Owner, its officers, agents and employees, harmless against any loss or liability for or on account of the infringement of any patent rights in connection with any invention, process, technique, article or appliance manufactured or used in the performance of the Contract, including its use by the Owner, unless such invention, process, technique, article or appliance is specifically named in the specifications or plans as acceptable for use in carrying out the Work. If, before using any invention, process, technique, article or appliance specifically named in the specifications or plans as acceptable for use in carrying out the Work, the Contractor has or acquires information that the same is covered by letters of -16County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) patent making it necessary to secure the permission of the patentee, or other, for the use of the same, he shall promptly advise the Owner and the Architect/Engineer. The Owner may direct that some other invention, process, technique, article or appliance be used. Should the Contractor have reason to believe that the invention, process, technique, article or appliance so specified is an infringement of a patent, and fail to inform the Owner and the Architect/Engineer, he shall be responsible for any loss or liability due to the infringement. 15. ARCHITECT/ENGINEER’S STATUS (a) The Architect/Engineer shall have authority to endeavor to secure the faithful performance by Owner and Contractor of the Work under the Contract. He shall review the Contractor’s Submittals for conformance to the requirements of the Contract Documents and return copies to the Contractor with appropriate notations. He shall interpret the requirements of the plans and specifications and issue Field Orders to the Contractor as may be required. He shall recommend to the Owner suspension of the Work (in whole or in part) whenever such suspension may be necessary to ensure the proper execution of the Contract. He shall have authority to reject, in writing, Work, including material, installation or workmanship, which does not conform to the requirements of the plans and specifications. He shall determine the progress and quality of the Work, subject to the right of the Owner to make an overriding decision to the contrary. Upon request by the Contractor, the Architect/Engineer shall confirm, in writing within ten (10) days, any oral order or determination made by him. (b) The Architect/Engineer shall have no authority to approve or order changes in the Work which alter the design concept or which call for an extension of time or a change in the Contract Price. (c) The Owner shall have the right, but not the duty, to countermand any decision of the Architect/Engineer and to follow or reject the advice of the Architect/Engineer, including but not limited to acceptance of the Work. (d) All orders from the Owner to the Contractor shall either be transmitted through the Architect/Engineer or communicated directly to the Contractor and the Architect/Engineer by the Owner. (e) Should the Owner choose to employ another or different Architect/Engineer, the status of the Architect/Engineer so employed shall be the same as that of the former Architect/Engineer. (f) The Architect/Engineer will provide to the Owner and the Contractor after each visit to the Site, a written report indicating the date, time of day, weather conditions and the names of the persons representing the Architect/Engineer who participated in the visit. The report will advise the Owner of any problems that were noted and shall compare the Architect/Engineer’s observations of the actual progress of the Work with that reported by the Contractor. On the basis of his on-Site observations as Architect/Engineer, he will make every reasonable effort to guard the Owner against defects and deficiencies in the Work of the Contractor. He shall have the authority to inspect the Work, to note and report Defective Work and deviations from the Contract Documents -17County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) to the Owner, to reject same, and to recommend to the Owner the suspension of the Work when necessary to prevent Defective Work from proceeding or being covered. (g) The Architect/Engineer shall not be responsible for construction means, methods, techniques, sequences or procedures (other than those expressly specified in Contract Documents), or for safety precautions and programs in connection with the Work, and he shall not be responsible for the Contractor’s failure to carry out the Contractor’s own responsibilities. (h) The provisions of this section are included as information only to describe the relationship between the Owner, A/E, and Contractor. No failure of the A/E to act in accordance with this section shall relieve the Contractor from his obligations under the Contract or create any rights in favor of the Contractor. 16. INS PECTIO N (a) All material and workmanship shall be subject to inspection, examination and testing by the Owner, the Architect/Engineer, the Project Inspector, authorized inspectors and authorized independent testing entities at any and all times during manufacture and/or construction. The Architect/Engineer and the Owner shall have authority to reject defective material and workmanship and require its correction. Rejected workmanship shall be satisfactorily corrected and rejected material shall be satisfactorily replaced with proper material without charge therefor, and the Contractor shall promptly segregate and remove the rejected material from the Site. If the Contractor fails to proceed at once with replacement of rejected material and/or the correction of defective workmanship, the Owner may, by contract or otherwise, replace such material and/or correct such workmanship and charge the cost to the Contractor, or may terminate the right of the Contractor to proceed as provided in Section 40 of these General Conditions, the Contractor and surety being liable for any damage to the same extent as provided in Section 40 for termination thereunder. (b) Site inspections, tests conducted on Site or tests of materials gathered on Site, which the Contract requires to be performed by independent testing entities, shall be contracted and paid for by the Owner. Examples of such tests are the testing of cast-in-place concrete, foundation materials, soil compaction, pile installations, caisson bearings and steel framing connections. The Contractor shall promptly furnish, without additional charge, all reasonable facilities, labor and materials necessary and convenient for making such tests. Except as provided in (d) below, whenever such examination and testing finds defective materials, equipment or workmanship, the Contractor shall reimburse the Owner for the cost of reexamination and retesting. Although conducted by independent testing entities, the Owner will not contract and pay for tests or certifications of materials, manufactured products or assemblies which the Contract, codes, standards, etc., require to be tested and/or certified for compliance with industry standards such as Underwriters Laboratories, Factory Mutual or ASTM. If fees are charged for such tests and certifications, they shall be paid by the Contractor. The Contractor shall also pay for all inspections, tests, and certifications which the Contract specifically requires him to perform or to pay, together with any inspections and tests which he chooses to perform for his own purposes, but are not required by the Contract. -18County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (c) Where Work is related to or dependent on the Defective Work, the Contractor shall stop such related or dependent Work until the Defective Work or deficiency is corrected or an alternative solution is presented that is satisfactory to the Owner. Where Work is rejected because of defective material or workmanship, the Contractor shall stop like Work in other areas or locations on the Project until the matter is resolved and the Owner has approved corrective measures. (d) Should it be considered necessary or advisable by Owner or the Architect/Engineer at any time before final acceptance of the entire Work to make an examination of any part of the Work already completed, by removing or tearing out portions of the Work, the Contractor shall on request promptly furnish all necessary facilities, labor and material to expose the Work to be tested to the extent required. If such Work is found to be defective in any respect, due to the fault of the Contractor or his Subcontractors, the Contractor shall defray all the expenses of uncovering the Work, of examination and testing, and of satisfactory reconstruction. If, however, such Work is found to meet the requirements of the Contract, the actual cost of the Contractor’s labor and material necessarily involved in uncovering the Work, the cost of examination and testing, and Contractor’s cost of material and labor necessary for replacement including a markup of fifteen percent (15%) for overhead and profit shall be paid to the Contractor and he shall, in addition, if completion of the Work has been delayed thereby, be granted a suitable extension of time. Notwithstanding the foregoing, the Contractor shall be responsible for all costs and expenses in removing and replacing the Work if the Contractor had covered the Work prior to any inspection or test contrary to the instructions of the A/E, Owner or Project Inspector. (e) The Project Inspector has the right and the authority to: (1) Inspect all construction materials, equipment, and supplies for quality and for compliance with the Contract Documents and/or approved shop drawings and Submittals; (2) Inspect workmanship for compliance with the standards described in the Contract Documents; (3) Observe and report on all tests and inspections performed by the Contractor; (4) Recommend rejection of Work which does not conform to requirements of the Contract Documents; (5) Keep a record of construction activities, tests, inspections, and reports; (6) Attend all joint Site construction meetings and inspections held by the Owner and/or the A/E with the Contractor; (7) Check materials and equipment, together with documentation related thereto, delivered for conformance with approved Submittals and the Contract; (8) Check installations for proper workmanship and conformance with shop drawing and installation instructions; -19County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (9) Assist in the review and verification of the Schedule of Values & Certificate for Payment, submitted by the Contractor each month; (10) Do all things for or on behalf of the Owner as the Owner may subsequently direct in writing. (f) The Project Inspector has no authority to: (1) Authorize deviations from the Contract Documents; (2) Enter into the area of responsibility of the Contractor’s superintendent; (3) Issue directions relative to any aspect of construction means, methods, techniques, sequences or procedures, or in regard to safety precautions and programs in connection with the Work; (4) Authorize or suggest that the Owner occupy the Project, in whole or in part; or (5) Issue a certificate for payment. (g) The duties of the Project Inspector are for the benefit of the Owner only and not for the Contractor. The Contractor may not rely upon any act, statement, or failure to act on the part of the Project Inspector, nor shall the failure of the Project Inspector to properly perform his duties in any way excuse Defective Work or otherwise improper performance of the Contract by the Contractor. 17. SUPERINTENDENCE BY CONTRACTOR (a) The Contractor shall have a competent foreman or superintendent, satisfactory to the Architect/Engineer and the Owner, on the Site at all times during the progress of the Work. The superintendent or foreman shall be familiar with and be able to read and understand the plans and specifications, and be capable of communicating orally and in writing with the Owner’s inspectors and the Contractor’s workers. The Contractor shall be responsible for all construction means, methods, techniques, sequences and procedures, for coordinating all portions of the Work under the Contract except where otherwise specified in the Contract Documents, and for all safety and worker health programs and practices. The Contractor shall notify the Owner, in writing, of any proposed change in superintendent, including the reason therefor, prior to making such change. (b) The Contractor shall, at all times, enforce strict discipline and good order among the workers on the Project, and shall not employ on the Work, or contract with, any unfit person, anyone not skilled in the Work assigned to him, or anyone who will not work in harmony with those employed by the Contractor, the Subcontractors, the Owner or the Owner’s separate contractors and their subcontractors. (c) The Owner may, in writing, require the Contractor to remove from the Site any employee or Subcontractor’s employee the Owner deems to be incompetent, careless, not working in harmony with others on the Site, or otherwise objectionable, but the Owner shall have no obligation to do so. -20County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) 18. CONSTRUCTION SUPERVISION, METHODS AND PROCEDURES (a) The Contractor shall be solely responsible for supervising and directing the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract. The Contractor shall be solely responsible for the means, methods, techniques, sequences and procedures of construction and for coordinating all portions of the Work under the Contract, except where otherwise specified in the Contract Documents. However, the Contractor shall not be responsible for the negligence of others in the design or selection of a specific means, method, technique, sequence or procedure of construction which is indicated in and required by the Contract. The Contractor is solely responsible to the Owner that the finished Work complies with the Contract Documents. The Contractor shall be solely responsible for health and safety precautions and programs for workers and others in connection with the Work. No inspection by, knowledge on the part of, or acquiescence by the Architect or Engineer, the Project Inspector, the Owner, the Owner’s employees and agents, or any other entity whatever shall relieve the Contractor from its sole responsibility for compliance with the requirements of the Contract or its sole responsibility for health and safety programs and precautions. (b) If a specific means, method, technique, sequence or procedure of construction is indicated in or required by the Contract Documents, the Contractor may furnish or utilize a substitute means, method, sequence, technique or procedure of construction acceptable to Architect/Engineer, subject to the Owner’s right to disapprove. The Contractor must submit its written request for the substitution to the Architect/Engineer with sufficient information to allow the Architect/Engineer to determine that the substitute proposed is equivalent to that indicated or required by the Contract. (c) The divisions and sections of the Specifications and the identification of any drawings shall not control the Contractor in dividing the Work among Subcontractors or Suppliers or delineating the Work to be performed by any specific trade. 19. SCHEDULE OF THE WORK (a) General: The Contractor is responsible for the scheduling and sequencing of the Work, for coordinating the Work, for monitoring the progress of the Work, and for taking appropriate action to keep the Work on schedule. The Contractor may attempt to achieve Substantial Completion on or before the Time for Completion or the Contract Completion Date established by the Contract and receive payment in accordance with Section 36 for the Work completed each period. However, the date established by the Contract Documents as the deadline for achieving Substantial Completion must be used in all schedules as the date on which Substantial Completion will be achieved. The time (in days) between the Contractor’s planned early completion and the contracted Time for Completion is part of the Project “Total Float” time and will be used as such. Extensions of time pursuant to Sections 38 and 42, damages for delay, and all other matters between the Owner and the Contractor will be determined using the contractually required Substantial Completion date, not an early Substantial Completion date planned by the Contractor. -21County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) Within two (2) weeks after the Contractor signs the Contract Between Owner and Contractor, unless otherwise extended by the Owner at the time of the signing, the Contractor shall prepare and submit to the Owner, with a copy to the Architect/Engineer, a preliminary bar graph schedule for accomplishing the Work based upon the Time for Completion stated in the Contract. The preliminary bar graph schedule shall be in sufficient detail to show the sequencing of the various trades for each floor level, wing or work area. The Owner will notify the Contractor of its acceptance of or objections to the preliminary schedule within fifteen (15) days of receipt by the Owner. A fully complete Project schedule for accomplishing the Work must be submitted in like manner no later than sixty (60) days after the Contract is signed by the Owner. The Owner’s failure to reject or its acceptance of any schedule, graph, chart, recovery schedule, updated schedule, plan of action, etc. shall not constitute a representation or warranty by the Owner, including but not limited to a representation or warranty that the schedule is feasible or practical nor shall any such acceptance or failure to reject relieve the Contractor from sole responsibility for completing the Work within the time allowed. No progress payments will be payable to the Contractor until after it has submitted a preliminary schedule which is acceptable to the Owner. Neither the second progress payment nor any subsequent payment shall be payable to the Contractor until it has submitted a fully complete Project schedule accepted by the Owner. Nor shall subsequent progress payments be payable to the Contractor unless and until he maintains the monthly bar graphs or status reports required by Section 19(d) herein or unless and until he provides any recovery schedule pursuant to Section 19(e) herein. Failure to provide a satisfactory preliminary or fully complete Project schedule within the time limits stated above shall be a breach of contract for which the Owner may terminate the Contract in the manner provided in Section 40 of these General Conditions. The fully complete Project schedule for accomplishing the Work shall be of the type set forth in subparagraph (1) or (2) below, as appropriate: (1) For Contracts with a price of $10,000,000 or less, a bar graph schedule will satisfy the above requirement. The schedule shall indicate the estimated starting and completion dates for each major element of the work. See (b) below. (2) For Contracts with a price over $10,000,000, a Critical Path Method (CPM) schedule shall be utilized to control the planning and scheduling of the Work. The CPM schedule shall be the responsibility of the Contractor and shall be paid for by the Contractor. See (c) below. (b) Bar Graph Schedule: Where a bar graph schedule is required, it shall be time-scaled in weekly increments, shall indicate the estimated starting and completion dates for each major element of the Work by trade and by area, level, or zone, and shall schedule dates for all salient features, including but not limited to the placing of orders for materials, submission of shop drawings and other Submittals for approval, approval of shop drawings by Architect/Engineer, the manufacture and delivery of material, the testing and the installation of materials, supplies and equipment, and all Work activities to be performed by the Contractor. -22County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) The Contractor shall allow sufficient time in his schedule for adverse weather anticipated in Section 6 and for the A/E to conduct whatever associated reviews or inspections as may be required under the A/E’s contract with the Owner. If the A/E and the Contractor are unable to agree as to what constitutes sufficient time, the Owner shall determine the appropriate duration for such Architect/Engineer activities. Each Work activity will be assigned a time estimate by the Contractor. One day shall be the smallest time unit used. It is the Contractor’s responsibility to submit a schedule that shows Substantial Completion of the Work by the Contract Time for Completion or the Contract Completion Date and any interim deadlines established by the Contract. (c) CPM Schedule: Where a CPM schedule is required, it shall be in the time-scaled precedence format using the Contractor’s logic and time estimates. The CPM schedule shall be drawn or plotted with activities grouped or zoned by Work area or subcontract as opposed to a random (or scattered) format. The CPM schedule shall be time-scaled on a weekly basis and shall be drawn or plotted at a level of detail and logic which will schedule all salient features of the Work, including not only the actual construction Work for each trade, but also the submission of shop drawings and other Submittals for approval, approval of shop drawings by Architect/Engineer, placing of orders for materials, the manufacture and delivery of materials, the testing and installation of materials and equipment, and all Work activities to be performed by the Contractor. Failure to include any element of Work required for the performance of this Contract shall not excuse the Contractor from completing all Work required within the Time for Completion, Contract Completion Date and any interim deadlines established by the Contract. The Contractor shall allow sufficient time in his schedule for adverse weather anticipated in Section 6 and for the A/E to conduct whatever associated reviews or inspections as may be required under the A/E’s contract with the Owner. If the A/E and the Contractor are unable to agree as to what constitutes sufficient time, the Owner shall determine the appropriate duration for such Architect/Engineer activities. Each Work activity will be assigned a time estimate by the Contractor. One day shall be the smallest time unit used. It is the Contractor’s responsibility to submit a schedule that shows Substantial Completion of the Work by the Contract Time for Completion or the Contract Completion Date and any interim deadlines established by the Contract. When completed, the CPM schedule shall be submitted to the Architect/Engineer and the Owner for review. The CPM schedule will identify and describe each activity, state the duration of each activity, the calendar dates for the early and late start and the early and late finish of each activity, and clearly highlight all activities on the critical path. “Total float” and “free float” shall be indicated for all activities. Float time, whether “free float” or “total float” as defined in Section 1, shall not be considered for the exclusive use or benefit of either the Owner or the Contractor, but must be allocated in the best interest of completing the Work within the Time for Completion or the Contract Completion Date. Extensions to the Time for Completion or the Contract Completion Date, when granted by Change Order, will be granted only when equitable time adjustment exceeds the Total Float in the activity or path of activities affected by the change. The CPM schedule shall -23County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) also show what part of the Contract Price (expressed in U.S. dollars) is attributable to each activity on the schedule, the sum of which for all activities shall equal the total Contract Price. The CPM schedule shall also show the planned workforce (crew size and number of crews) and the major pieces of equipment required for each activity on the schedule. When acceptable to the Owner and Architect/Engineer as to compliance with the requirements of this Section, but not as to logic, the schedule shall become the CPM schedule for the Project. Acceptance of the schedule by the Owner does not indicate agreement with nor responsibility for the proposed or actual duration of any activity shown on the accepted schedule. (d) Monthly Project Reports: The Contractor shall review progress not less than each month, but as often as necessary to properly manage the Project and stay on schedule. The Contractor shall collect and preserve information on Change Orders, including extensions of time. The Contractor shall evaluate this information and update the latest accepted schedule as often as necessary to finish within the Contract Time for Completion or before the Contract Completion Date. The Contractor shall submit to the A/E along with his monthly request for payment a copy of the bar graph schedule annotated to show the current progress. For projects requiring a CPM schedule, the Contractor shall submit a monthly report of the status of all activities. The bar graph schedule or monthly status report submitted with each periodic request for payment shall show the Work completed to date in comparison with the Work scheduled for completion, including but not limited to the dates for the beginning and completion of the placing of orders; the manufacture, testing and installation of materials, supplies and equipment. The form shall be approved by the A/E and the Owner; however, a bar graph or a CPM schedule marked, colored or annotated to reflect the above will usually satisfy this requirement. If any elements of the Work are behind schedule, regardless of whether they may prevent the Work from being completed on time, the Contractor must indicate in writing in the report what measures he is taking and plans to take to bring each such element back on schedule and to ensure that the Time for Completion or Contract Completion Date is not exceeded. (e) Progress Delay: Should any of the following conditions exist, the Owner may require the Contractor to prepare, at no extra cost to the Owner, a plan of action and a recovery schedule for completing the Work by the Contract Time for Completion or the Contract Completion Date: (1) The Contractor’ monthly progress report indicates delays that are, in the opinion of the A/E or the Owner, of sufficient magnitude that the Contractor’s ability to complete the Work by the scheduled Time for Completion or the Contract Completion Date is brought into question; (2) The CPM schedule sorted by early finish shows the Contractor to be thirty (30) or more days behind the critical path schedule at any time during construction up to thirty (30) days prior to scheduled Substantial Completion date; (3) The Contractor desires to make changes in the logic (sequencing of Work) or the planned duration of future activities of the CPM schedule which, in the opinion of the Architect/Engineer or the Owner, are of a major nature. -24County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) The plan of action and recovery schedule, when required, shall explain and display how the Contractor intends to regain compliance with the current accepted, fully completed, Project CPM schedule, as updated by approved change orders. The plan of action, when required, shall be submitted to the Owner for review within two (2) business days of the Contractor receiving the Owner’s written demand. The recovery schedule, when required, shall be submitted to the Owner within five (5) calendar days of the Contractor’s receiving the Owner’s written demand. (f) Early Completion of Project: The Contractor may attempt to achieve Substantial Completion on or before the Time for Completion or the Contract Completion Date. However, such planned early completion shall be for the Contractor’s convenience only and shall not create any additional rights of the Contractor or obligations of the Owner under this Contract, nor shall it change the Time for Completion or the Contract Completion Date. The Contractor shall not be required to pay damages to the Owner because of its failure to achieve Substantial Completion by its planned earlier date. Likewise, the Owner shall not pay the Contractor any additional compensation for achieving Substantial Completion early nor will the Owner owe the Contractor any compensation should the Owner, its officers, employees, or agents cause the Contractor not to achieve Substantial Completion earlier than the date required by the Contract Documents. If the Contractor seeks to change the Time for Completion or the Contract Completion Date to reflect an earlier completion date, he may request or propose such a change. The Owner may, but is not required to, accept such proposal. However, a change in the Time for Completion or the Contract Completion Date shall be accomplished only by Change Order. If the Contractor’s proposal to change the Time for Completion or the Contract Completion Date is accepted, a Change Order will be issued stating that all references in the Contract, including these General Conditions, to the Time for Completion or the Contract Completion Date shall thereafter refer to the date as modified, and all rights and obligations, including the Contractor’s liability for actual damages, delay damages and/or liquidated damages, shall be determined in relation to the date, as modified. 20. SCHEDULE OF VALUES AND CERTIFICATE FOR PAYMENT (a) Before submittal of the first partial payment request under the Contract, the Contractor shall prepare for review and approval of the Architect/Engineer and the Owner, a schedule of the estimated values listed by trades or by specification sections of the Work, totaling the Contract Price. Where the total project has multiple parts or phases, the Contractor shall prepare appropriate schedules of values to facilitate reviews and justifications for payments. All requests for payment shall be made on the Schedule of Values and Certificate for Payment (Form AC-12) pages 1 and 2. Succeeding pages may be on the Form AC-12 continuation sheets or a computerized spreadsheet which is in the same format and which contains the same information. Where a computerized spreadsheet is used, one copy of the entire Schedule of Values shall be provided to the Owner on diskette in a spreadsheet format (e.g. LOTUS, EXCEL, or QUATTRO PRO) with the initial request for payment if requested. -25County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (b) If the Contractor requests, or intends to request, payment for materials stored in an approved and secure manner, the Schedule of Values must indicate the amount for labor and the amount for materials, and in a supplement thereto must include an itemized list of materials for that trade or Work section. The material breakdown shall be in sufficient detail to allow verification of the quantities required for the Project, the quantities delivered, the Work completed, and the quantities stored on or off Site. (c) The “Value of Work Completed” portion of the Form AC-12 shall be completed, the Contractor’s certification completed and signed, and the appropriate substantiating material attached to each Certificate for Payment (AC-12). Such substantiating material includes, but is not limited to, invoices for materials, delivery tickets, time sheets, payroll records, daily job logs/records, and similar materials which, in the opinion of the Owner and the A/E, are necessary or sufficient to justify payment of the amount requested. (d) The labor progress for any task or activity shall be calculated based upon the percentage of Work complete up to fifty percent (50%) of the completion of the task or activity. Thereafter, the evaluation of labor progress will be based upon the effort required to complete that task or activity. The material progress shall be calculated as the invoiced dollar cost of materials used in relationship to the amount estimated as necessary to complete a particular element of Work. When calculating material progress, credit shall be given for installed material as well as that stored on the Site and any material stored off Site which has been certified by the Architect/Engineer in accordance with Section 36 of these General Conditions. (e) Should Work included in previous Form AC-12 submittals, and for which payment has been made, subsequently be identified, by tests, inspection, or other means, as not acceptable or not conforming to Contract requirements, the “Value of Work Completed” portion of the first Form AC-12 submitted after such identification shall be modified to reduce the “completed” value of that Work by deleting the value of that which has been identified as not acceptable or nonconforming. 21. ACCESS TO WORK The Architect/Engineer, the Owner, the Project Manager, the Owner’s inspectors and other testing personnel, inspectors from the Department of Labor and Industry, and others authorized by the Owner, shall have access to the Work at all times. The Contractor shall provide proper facilities for access and inspection. 22. SURVEYS AND LAYOUT (a) The Owner shall furnish the Contractor all necessary documents showing property lines and the location of existing buildings and improvements. The Contractor shall provide competent surveying and engineering services to execute the Work in accordance with the Contract and shall be responsible for the accuracy of these surveying and engineering services. -26County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (b) Such general reference points and benchmarks on the Site as will enable the Contractor to proceed with the Work will be established in the plans and specifications. If the Contractor finds that any previously established reference points have been lost or destroyed, he shall promptly notify the Architect/Engineer. (c) The Contractor shall protect and preserve the established benchmarks and monuments and shall make no changes in locations without written notice to the Architect/Engineer and the written approval from the Owner. Any of these which may be lost or destroyed or which require shifting because of necessary changes in grades or locations shall, subject to prior written approval of the Owner, be replaced and accurately located by the Contractor. 23. PLANS AND SPECIFICATIONS (a) The general character and scope of the Work are illustrated by the plans and the specifications. If the Contractor deems additional detail or information to be needed, he may request the same in writing from the Architect/Engineer. His request shall precisely state the detail or information needed and shall explain why it is needed. The Contractor shall also indicate a date when the requested information is required. The Architect/Engineer shall provide by Field Order such further detail and information as is necessary by the date required so long as the date indicated is reasonable. Any additional drawings and instructions supplied to the Contractor shall be consistent with the Contract Documents, shall be true developments thereof, and shall be so prepared that they can be reasonably interpreted as a part thereof. The Contractor shall carry out the Work in accordance with the additional detail drawings and instructions. (b) If the Contractor finds a contract error, or other discrepancy in the plans or specifications, he shall notify the Architect/Engineer in writing as soon as possible, but before proceeding with the affected Work. The Architect/Engineer shall issue a clarification by Field Order to the Contractor stating the correct requirements. If the Contractor deems the Field Order requires additional Work, he shall notify the A/E of such prior to proceeding with that Work and he shall submit a request for Change Order along with a detailed substantiating cost proposal thru the A/E to the Owner within ten (10) calendar days. (c) In case of differences between small and large scale drawings, the large scale drawings shall govern. Where on any of the drawings a portion of the Work is drawn out and the remainder is indicated in outline, the parts drawn out shall apply also to all other like portions of the Work. (d) Where the word “similar” appears on the drawings, it shall be interpreted in its general sense and not as meaning identical, and all details shall be worked out in relation to their location and their connection with other parts of the Work. (e) The specifications may be divided into several parts, or sections, for convenience only, since the entire specifications must be considered as a whole. The divisions of the specifications are not intended to control the Contractor in dividing the Work among Subcontractors or to limit the Work performed by any trade. The Contractor shall be solely responsible for the coordination of the trades, Subcontractors and vendors engaged in the Work. -27County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (f) Measurements or dimensions shown on the drawings for Site features, utilities and structures shall be verified at the Site by the Contractor. The Contractor shall not scale measurements or dimensions from the drawings. If there are discrepancies, the Architect/Engineer shall be consulted. If new Work is to connect to, match with or be provided in existing Work, the Contractor shall verify the actual existing conditions and necessary dimensions prior to ordering or fabrication. (g) As-Built Drawings: The Contractor shall maintain at the Site for the Owner one copy of all drawings, specifications, addenda, approved shop or setting drawings, Change Orders and other modifications (collectively referred to herein as “As-Built Drawings”) in good order and marked to record all changes as they occur during construction. These shall be available to the Architect/Engineer, the Owner, the Project Inspector, the Owner’s other inspectors and to the Owner’s testing personnel. The drawings shall be neatly and clearly marked in color during construction to record all variations made during construction. The representation of such variations shall include such supplementary notes, symbols, legends, and details as may be necessary to clearly show the as-built construction. (h) Record Drawings: Upon completion of the Work and prior to the final inspection, the Contractor shall deliver to the Architect/Engineer, for preparation of the Record Drawings, one complete set of “As-Built Drawings” referred to in the preceding subsection. 24. SUBMITT ALS (a) The Contractor shall submit a listing of all Submittals required by the Architect/Engineer or which the Contractor identifies as necessary, fixing the dates for the submission of shop or setting drawings, samples and product data. The listing shall be in a format acceptable to the Architect/Engineer. The Contractor shall identify all Submittals with the Owner’s Project Title as required by Section 2(f). (b) Submittals shall be forwarded to the Architect/Engineer for approval if required by the specifications or if requested by the Architect/Engineer or the Owner. No part of the Work dealt with by a Submittal shall be fabricated by the Contractor, save at his own risk, until such approval has been given. (c) The Contractor shall furnish to the Architect/Engineer for approval the name of the manufacturer, the model number, and other identifying data and information respecting the performance, capacity, nature and rating of the machinery and mechanical and other equipment which the Contractor contemplates incorporating in the Work. When Submittals are required by this Contract for materials, the Contractor shall furnish full information concerning the material or articles which he contemplates incorporating in the Work. When required, samples shall be submitted for approval at the Contractor’s expense, with all shipping charges prepaid. Machinery, equipment, material and articles installed or used without required approval shall be at the risk of subsequent rejection. -28County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (d) Unless otherwise indicated or required elsewhere in the specifications, shop drawings shall be submitted in the form of six (6) blue line or black line prints. Catalog cuts, product data and other non-reproducible literature, except certificates, shall be submitted in six (6) copies minimum, of which three (3) will be retained by the Architect/Engineer and the remainder will be returned to the Contractor. (e) Submittals shall be accompanied by a letter of transmittal which shall list the Project Title, the Submittals included, the specification section number applicable to each, and the date shown on each Submittal. Submittals shall be complete in every respect and bound in sets. Each Submittal shall be clearly marked to show each item, component and/or optional feature proposed to be incorporated into the Project. Cross reference to the plans or specifications as needed to identify the use for which the item or component is intended. (f) The Contractor shall check the Submittals for compliance with the requirements of the Contract Documents. The Contractor shall clearly note in writing any and all items which deviate from the requirements of the Contract Documents. Reasons for deviation shall be included with the Submittal. The Contractor shall be solely responsible for checking all dimensions and coordinating all materials and trades to ensure that the components or products proposed, individually or in combination, will fit in the space available and that they will be compatible with other components or products provided. (g) After checking each submittal, the Contractor shall stamp each sheet of the Submittal with the Contractor’s review stamp. Data submitted in a bound volume or on one sheet printed on two sides, may be stamped on the front of the first sheet only. The Contractor’s review stamp shall be worded as follows: The equipment and material shown and marked in this submittal is that proposed to be incorporated into this Project, is in compliance with the Contract drawings and specifications unless otherwise shown in bold face type or lettering and listed on a page or pages headed “DEPARTURES FROM DRAWINGS AND SPECIFICATIONS”, and can be installed in the allocated spaces. Reviewed by __________________ Date The person signing the review stamp shall be the person designated in writing by the Contractor as having that authority. (A copy of such designation shall be forwarded to the A/E prior to or with the first Submittal.) The signature on the stamped review statement shall be handwritten in ink. Stamped signatures are not acceptable. (h) The Contractor shall forward all Submittals sufficiently in advance of construction requirements to allow reasonable time for checking, correcting, resubmitting and rechecking. (i) If a Submittal indicates a departure from the Contract requirements, the Architect/Engineer may reject the Submittal or, if he deems it to have merit, may recommend it to the Owner, who shall approve or reject it as the Owner, in its sole discretion, sees fit. The departure from the Contract -29County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) requirements shall be further authorized by a Change Order, if a reduction or increase in the Contract Price is appropriate. (j) The Architect/Engineer is responsible to the Owner, but not to the Contractor, to verify that the Submittals conform to the design concept and functional requirements of the plans and specifications, that the detailed design portrayed in shop drawings and proposed equipment and materials shown in Submittals are of the quality specified and will function properly, and that the Submittals comply with the Contract Documents. (k) The Work shall be in accordance with approved Submittals. Approval of the Contractor’s Submittals by the A/E does not relieve the Contractor from responsibility of complying with the Contract and all drawings and specifications, except as changed by Change Order. (l) The plans and/or specifications may indicate that the Architect/Engineer designed or detailed a portion of the plans around a particular product (most commonly a piece of equipment). Should a different product be proposed by the Contractor and accepted, all modifications, rerouting, relocations and variations required for proper installation and coordination to comply with the design concept and requirements of the Contract Documents shall be the responsibility of the Contractor and shall be made at no extra cost to the Owner. If the plans were noted as designed or detailed around a particular product and/or if a product is named when a “brand name or equal” specification has been used, this is not intended to favor or preclude the use of other products pursuant to Section 26 of these General Conditions. Rather such design merely acknowledges the reality that in many instances the Architect/Engineer must have a basis to design and detail around for dimensions and characteristics of a product or system. (m) Additional Submittal requirements are shown in the specifications. 25. FEES, SERVICES AND FACILITIES (a) The Contractor shall obtain all permits and pay for all fees and charges necessary for temporary access and public right-of-way blockage or use, for temporary connections to utilities and for the use of property (other than the Site) for storage of materials and other purposes unless otherwise specifically stated in the Contract Documents. (b) Certain projects such as renovations and interior modifications of existing buildings will usually have water and electric service to the building. In those instances, water and electric power, if required for the Work under the Contract, will be furnished by the Owner subject to reasonable use by the Contractor, only to the extent and capacity of present services. The Contractor shall be responsible for providing required connections, temporary wiring, piping, etc. to these services in a safe manner and in accordance with applicable codes. All temporary wire, pipe, etc. shall be removed before the Substantial Completion inspection. Acceptance by the Contractor of the use of Owner’s water and electricity constitutes a release to the Owner of all claims and of all liability to the Contractor for whatever damages which may result from power and water outages or voltage variations. -30County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (c) The Owner shall pay any connection charges for permanent utility connections directly to the utility Supplier. The Contractor shall coordinate such connections with the utility Supplier. (d) It is understood that, except as otherwise specifically stated in the Contract Documents, the Contractor, either directly or through his Subcontractors, shall provide and pay for all material, labor, tools, equipment, water, light, power, telephone and other services or facilities of every nature whatsoever necessary to execute completely and deliver the Work within the Contract Time for Completion or before the Contract Completion Date. 26. EQUALS (a) Brand names: Unless otherwise stated in the specifications, the name of a certain brand, make or manufacturer denotes the characteristics, quality, workmanship, economy of operation and suitability for the intended purpose of the article desired, but does not restrict the Contractor to the specific brand, make, or manufacturer; it is set forth to convey to the Contractor the general style, type, character and quality of the article specified. (b) Equal materials, equipment or assemblies: Whenever in these Contract Documents, a particular brand, make of material, device or equipment is shown or specified, such brand, make of material, device or equipment shall be regarded merely as a standard. Any other brand, make or manufacturer of a product, assembly or equipment which in the opinion of the Architect/Engineer is the equal of that specified, considering quality, capabilities, workmanship, configuration, economy of operation, useful life, compatibility with design of the Work, and suitability for the intended purpose, will be accepted unless rejected by the Owner as not being equal. (c) Substitute materials, equipment or assemblies: The Contractor may propose to substitute a material, product, equipment, or assembly which deviates from the requirements of the Contract Documents but which the Contractor deems will perform the same function and have equal capabilities, service life, economy of operations, and suitability for the intended purpose. The proposal must include any cost differentials proposed. The Owner will have the A/E provide an initial evaluation of such proposed substitutes and provide a recommendation on acceptability and indicate the A/E’s redesign fee to incorporate the substitution in the design. If the proposed substitute is acceptable to the Owner, a Change Order will be proposed to the Contractor to accept the substitute and to deduct the cost of the A/E redesign fee and the proposed cost savings from the Contract Price. The Owner shall have the right to limit or reject substitutions at its sole discretion. (d) The Contractor shall be responsible for making all changes in the Work necessary to adapt and accommodate any equal or substitute product which it uses. The necessary changes shall be made at the Contractor’s expense. -31County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) 27. AVAILABILITY OF MATERIALS If a brand name, product, or model number included in the Contract Documents is not available on the present market, alternate equal products or model numbers may be proposed by the Contractor through the Architect/Engineer for approval by the Owner. 28. CONTRACTOR’S TITLE TO MATERIALS No materials or supplies for the Work shall be purchased by the Contractor, or by any Subcontractor or Supplier, subject to any security interest, installment or sales contract or any other agreement or lien by which an interest is retained by the seller or is given to a secured party. The Contractor warrants that he has clear and good title to all materials and supplies which he uses in the Work or for which be accepts payment in whole or in part. 29. STANDARDS FOR MATERIALS INSTALLATION & WORKMANSHIP (a) Unless otherwise specifically provided in the Contract, all equipment, material, and accessories incorporated in the Work are to be new and in first class condition. (b) Unless specifically approved by the Owner or required by the Contract, the Contractor shall not incorporate into the Work any materials known by the industry to be hazardous to the health of building construction workers, maintenance workers, or occupants (for example asbestos or lead paint). If the Contractor becomes aware that a material required by the Contract contains asbestos or other hazardous materials, he shall notify the Owner and the Architect/Engineer immediately and shall take no further steps to acquire or install any such material without first obtaining Owner approval. (c) All workmanship shall be of the highest quality found in the building industry in every respect. All items of Work shall be done by craftsmen or tradesmen skilled in the particular task or activity to which they are assigned. In the acceptance or rejection of Work, no allowance will be made for lack of skill on the part of workmen. Poor or inferior workmanship (as determined by the Architect/Engineer, the Owner or other inspecting authorities) shall be removed and replaced at Contractor’s expense such that the Work conforms to the highest quality standards of the trades concerned, or otherwise corrected to the satisfaction of the Architect/Engineer, the Owner, or other inspecting authority, as applicable. (d) Under the various sections of the plans or specifications, where specified items are supplied with the manufacturer’s printed instructions, recommendations, or directions for installation, or where such instructions, recommendations, or directions are available, installation of the specified items shall be in strict accordance with the manufacturer’s printed instructions unless those instructions contradict the plans or specifications, in which case the Architect/Engineer will be notified for an interpretation and decision. -32County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (e) Under the various sections of the plans or specifications, where reference is made to specific codes or standards governing the installation of specified items, installation shall in all cases be in strict accordance with the referenced codes and standards. Where no reference is made to specific codes or standards, installation shall conform to the generally recognized applicable standards for first-class installation of the specific item to be installed. Contractors are expected to be proficient and skilled in their respective trades and knowledgeable of the Codes and Standards of the National Fire Protection Association (NFiPA), National Electric Code (NEC), Occupational Safety and Health Act (OSHA) and other codes and standards applicable to installations and associated work by his trade. (f) Where the manufacturer’s printed instructions are not available for installation of specific items, where specific codes or standards are not referenced to govern the installation or specific items, or where there is uncertainty on the part of the Contractor concerning the installation procedures to be followed or the quality of workmanship to be maintained in the installation of specific items, the Contractor shall consult the Architect/Engineer for approval of the installation procedures or the specific standards governing the quality of workmanship the Contractor proposes to follow or maintain during the installation of the items in question. (g) During and/or at the completion of installation of any items, the tests designated in the plans or specifications necessary to assure proper and satisfactory functioning for its intended purpose shall be performed by the Contractor or by its Subcontractor responsible for the completed installation. All costs for such testing are to be included in the Contract Price. If required by the Contract Documents, the Contractor shall furnish prior to final inspection the manufacturers’ certificates evidencing that products meet or exceed applicable performance, warranty and other requirements, and certificates that products have been properly installed and tested. 30. WARRANTY OF MATERIALS AND WORKMANSHIP (a) The Contractor warrants that, unless otherwise specified, all materials and equipment incorporated in the Work under the Contract shall be new, in first class condition, and in accordance with the Contract Documents. The Contractor further warrants that all workmanship shall be of the highest quality and in accordance with the Contract Documents and shall be performed by persons qualified at their respective trades. (b) Work not conforming to these warranties shall be considered defective. (c) This warranty of materials and workmanship is separate and independent from and in addition to any of the Contractor’s other guarantees or obligations in the Contract or under Virginia law. -33County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) 31. USE OF SITE AND REMOVAL OF DEBRIS (a) The Contractor shall: (1) Perform the Work in such a manner as not to interrupt or interfere with the operation of any existing activity on, or in proximity to, the Site or with the Work of any other separate contractor; (2) Store his apparatus, materials, supplies and equipment in such orderly fashion at the Site of the Work as will not unduly interfere with the progress of his Work or the work of any other separate contractor; and (3) Place upon the Work or any part thereof only such loads as are consistent with the safety of that portion of the Work. (b) The Contractor expressly undertakes, either directly or through his Subcontractor(s), to effect all cutting, filling or patching of the Work required to make the same conform to the plans and specifications, and, except with the consent of the Architect/Engineer, not to cut or otherwise alter the Work of any other separate contractor. The Contractor shall not damage or endanger any portion of the Work or Site, including existing improvements, unless called for by the Contract. (c) The Contractor expressly undertakes, either directly or through his Subcontractor(s), to clean up frequently all refuse, rubbish, scrap materials and debris caused by his operations, to the end that at all times the Site shall present a neat, orderly and workmanlike appearance. No such refuse, rubbish, scrap material and debris shall be left within the completed Work nor buried on the building Site, but shall be removed from the Site and properly disposed of in a licensed landfill or otherwise as required by law. (d) The Contractor expressly undertakes, either directly or through his Subcontractor(s), before final payment or such prior time as the Owner may require, to remove all surplus material, false Work, temporary structures, including foundations thereof, plants of any description and debris of every nature resulting from his operations and to put the Site in a neat, orderly condition; to thoroughly clean and leave reasonably dust free all finished surfaces including all equipment, piping, etc., on the interior of all buildings included in the Contract; and to clean thoroughly all glass installed under the Contract, including the removal of all paint and mortar splatters and other defacements. If the Contractor fails to clean up at the time required herein, the Owner may do so and charge the costs incurred thereby to the Contractor in accordance with Section 10(b) of these General Conditions. (e) The Contractor shall prevent Site soil erosion, the runoff of silt and/or debris carrying water from the Site, and the blowing of debris off the Site in accordance with the applicable requirements and standards of the Contract and the County of Albemarle’s Water Protection Ordinance. -34County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) 32. TEMPORARY ROADS Temporary roads, if required, shall be established and maintained until permanent roads are accepted, then removed and the area restored to the conditions required by the Contract Documents. Crushed rock, paving and other road materials from temporary roads shall not be left on the Site unless permission is received from the Owner to bury the same at a location and depth approved by the Owner. 33. SIGNS The Contractor may, at his option and without cost to the Owner, erect signs acceptable to the Owner on the Site for the purpose of identifying and giving directions to the job. No signs shall be erected without prior approval of the Owner as to design and location. The Contractor shall pay all fees required by Albemarle County. 34. PROTECTION OF PERSONS AND PROPERTY (a) The Contractor expressly undertakes, both directly and through his Subcontractors, to take every reasonable precaution at all times for the protection of all persons and property which may come on the Site or be affected by the Contractor’s Work. (b) The Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. (c) The provisions of all rules and regulations governing health and safety as adopted by the Safety Codes Commission of the Commonwealth of Virginia, issued by the Department of Labor and Industry under Title 40.1 of the Code of Virginia, shall apply to all Work under this Contract. (d) The Contractor shall continuously maintain adequate protection of all his Work from damage and shall protect the Owner’s property from injury or loss arising in connection with this Contract. He shall make good any such damage, injury or loss, except as may be directly and solely due to errors in the Contract Documents or caused by agents or employees of the Owner. The Contractor shall adequately protect adjacent property to prevent any damage to it or loss of use and enjoyment by its owners. The Contractor shall provide and maintain all passageways, guard fences, lights and other facilities for protection as required by public authority, local conditions, or the Contract. (e) In an emergency affecting the health, safety or life of persons or of the Work, or of the adjoining property, the Contractor, without special instruction or authorization from the Architect/Engineer or the Owner, shall act, at his discretion, to prevent such threatened loss or injury. Also, should he, to prevent threatened loss or injury, be instructed or authorized to act by the Architect/Engineer or the Owner, he shall so act immediately, without appeal. Any additional compensation or extension of time claimed by the Contractor on account of any emergency work shall be determined as provided by Section 38 of these General Conditions. -35County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (f) When necessary for the proper protection of the Work, temporary heating of a type approved by the Architect/Engineer must be provided by the Contractor, at the Contractor’s expense, unless otherwise specified. 35. CLIMATIC CONDITIONS The Contractor shall suspend activity on and protect any portion of the Work that may be subject to damage by climatic conditions. 36. PAYMENTS TO CONTRACTOR (a) Unless otherwise provided in the Contract, the Owner will make partial payments to the Contractor on the basis of a duly certified and approved Schedule of Values and Certificate for Payment, Form AC-12, showing the estimate of the Work performed during the preceding calendar month or work period, as recommended by the Architect/Engineer. When evaluating the Contractor’s Form AC12, the Architect/Engineer will consider the value of the Work in place, the value of approved and properly stored materials, the status of the Work on the critical path with regard to the Time for Completion, and the estimated value of the Work necessary to achieve Final Completion. The Architect/Engineer will schedule a monthly pay meeting. The Contractor will submit his monthly estimate of Work completed on Form AC-12 so that it is received by the Architect/Engineer and the Owner’s Project Manager at least one work day prior to the date scheduled by the Architect/Engineer for the monthly pay meeting. The Owner will review the estimate with the Architect/Engineer and the Contractor at the monthly pay meeting, which shall be considered the receipt date, and may approve any or all of the estimate of Work for payment. In preparing estimates, the material delivered to the Site and preparatory Work done shall be taken into consideration, if properly documented as required by Section 20 of these General Conditions, or as may be required by the Architect/Engineer so that quantities may be verified. In addition to material delivered to the Site, material such as large pieces of equipment and items purchased specifically for the Project, but stored off the Site within the Commonwealth of Virginia, may be considered for payment, provided all of the following are accomplished prior to the submission of the monthly payment request in which payment for such materials is requested: (1) The Contractor must notify the Owner in writing, at least ten (10) days prior to the submission of the payment request, through the Architect/Engineer, that specific items will be stored off Site in a designated, secured place within the Commonwealth of Virginia. The Schedule of Values must be detailed to indicate separately both the value of the material and the labor/installation for trades requesting payment for stored materials. By giving such notification and by requesting payment for material stored off Site, the Contractor warrants that the storage location is safe and suitable for the type of material stored and that the materials are identified as being the property of the Contractor, and agrees that loss of materials stored off the Site shall not relieve the Contractor of the obligation to timely furnish these types and quantities of materials for the Project and meet the Time for Completion or Contract Completion Date, subject to Section 42(b) of these General Conditions. If the storage location is more than 20 miles from the Site, the Contractor may -36County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) be required to reimburse the Owner for the cost incurred for travel to the storage location to verify the Contractor’s request for payment for materials stored off Site. (2) Such notification, as well as the payment request, shall: (a) itemize the quantity of such materials and document with invoices showing the cost of said materials; (b) indicate the identification markings used on the materials, which shall clearly reference the materials to the particular project; (c) identify the specific location of the materials, which must be within reasonable proximity to the Site and within the Commonwealth of Virginia; (d) include a letter from the Contractor’s Surety which confirms that the Surety on the Performance Bond and the Labor and Material Payment Bond has been notified of the request for payment of materials stored off the Site and agrees that the materials are covered by the bond; and (e) include a certificate of all-risk builder’s risk insurance in an amount not less than the fair market value of the materials, which shall name the Owner and the Contractor as coinsured. (3) The Architect/Engineer shall indicate, in writing, to the Owner that Submittals for such materials have been reviewed and meet the requirements of the Contract Documents, that the stored materials meet the requirement of the plans and specifications, and that such materials conform to the approved Submittals. Should the A/E deem it necessary to visit the storage site to make such review, the Contractor shall bear the costs incurred therewith. (4) The Owner, through the Architect/Engineer, shall notify the Contractor in writing of its agreement to prepayment for materials. (5) The Contractor shall notify the Owner in writing, through the Architect/Engineer, when the materials are to be transferred to the Site and when the materials are received at the Site. (b) Payment will not be made for materials or equipment stored on or off the Site which are not scheduled for incorporation into the Work within the six months following submission of the request for payment, unless the Contractor has the prior consent of the Owner, which consent may be granted or withheld by the Owner in its discretion if, in the opinion of the Owner, it is not necessary to procure the materials more than six months in advance of use to assure their availability when needed. (c) In making such partial payments, five percent (5%) of each payment to the Contractor shall be retained until Final Completion and acceptance of all Work covered by the Contract, unless otherwise provided by any law, regulation or program of the federal government. Such retainage shall be held to assure faithful performance of the Contract and may also be used as a fund to deduct amounts due to or claimed by the Owner, including, but not limited to, payment to the -37County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) Owner of all monies due for deductive change orders, credits, uncorrected Defective Work, interest, damages, and the like. (§2.2-4333 of the Code of Virginia) (d) All material and Work for which partial payments are made shall thereupon become the sole property of the Owner, but this provision shall not relieve the Contractor from the sole responsibility for all materials and Work, including those for which payment has been made, or for the restoration of any damaged materials or Work. Nor shall this provision serve as a waiver of the right of the Owner to require the fulfillment of all of the terms and conditions of the Contract. (e) The final payment, which shall include the retainage, less any amounts due to or claimed by the Owner, shall not become due until the Architect/Engineer and the Owner agree that Final Completion has been achieved and until the Contractor shall deliver to the Owner through the Architect/Engineer a Certificate of Completion by the Contractor (Form AC-13.2) and an Affidavit of Payment of Claims (Form AC-13), stating that all Subcontractors and Suppliers of either labor or materials have been paid all sums claimed by them for Work performed or materials furnished in connection with this Project less retainage. Amounts due the Owner which may be withheld from the final payment may include, but are not limited to, amounts due pursuant to Section 3(i), Section 16(a)-(d), Section 31(d), costs incurred to repair or replace Defective Work, costs incurred as a result of the Contractor’s negligent acts or omissions or omissions of those for whom the Contractor is responsible, delay damages under Section 42(h), and any liquidated or actual damages. If all Subcontractors and Suppliers of labor and materials have not been paid the full amount claimed by them, the Contractor shall list each to which an agreed amount of money is due or which has a claim in dispute. With respect to all such Subcontractors and Suppliers, the Contractor shall provide to the Owner, along with the Affidavit of Payment of Claims (Form AC13), an affidavit from each such Subcontractor and Supplier stating the amount of their subcontract or supply contract, the percentage of completion, the amounts paid to them by the Contractor and the dates of payment, the amount of money still due if any, any interest due the Subcontractor or Supplier pursuant to Section 37(b) below, and whether satisfactory arrangements have been made for the payment of said amounts. If no agreement can be reached between the Contractor and one or more Subcontractors or Suppliers as to the amounts owed to the Subcontractors or Suppliers, the Owner may, in its discretion, pay such portion of the monies due to the Contractor which is claimed by the Subcontractor or Supplier into a Virginia Court or Federal Court sitting in Virginia, in the manner provided by law. Said payment into court shall be deemed a payment to the Contractor. Nothing in this Section shall be construed as creating any obligation or contractor relationship between the Owner and any Subcontractor or Supplier, and the Owner shall not be liable to any Subcontractor or Supplier on account of any failure or delay of the Owner in complying with the terms hereof. (f) Upon successful completion of the final inspection and all Work required by the Contract, including but not limited to the delivery of As-Built drawings, equipment manuals, written warranties, acceptance of the Work by the Owner and the delivery of the affidavits required in Section 36(e) of these General Conditions, the Architect/Engineer shall deliver the written Certificate of Completion by the Architect/Engineer (Form AC-13.1) to the Owner, with a copy to the Contractor, stating the entire amount of Work performed and compensation earned by the Contractor, including extra work and compensation therefor. The Owner may accept the Work for occupancy or use while asserting claims against the Contractor; disputing the amount of -38County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) compensation due to the Contractor; disputing the quality of the Work, its completion, or its compliance with the Contract Documents; or any other reason. (g) Unless there is a dispute about the compensation due to the Contractor, Defective Work, quality of the Work, compliance with the Contract Documents, completion itself, claims by the Owner, other matters in contention between the parties, or unless monies are withheld pursuant to Albemarle County’s Debt Setoff Program, within thirty (30) days after receipt and acceptance of the Schedule of Values and Certificate for Payment (Form AC-12) in proper form by the Architect/Engineer at the monthly pay meeting, which shall be considered the receipt date, the Owner shall pay to the Contractor the amount approved by the Architect/Engineer, less all prior payments and advances whatsoever to or for the account of the Contractor. In the case of final payment, the completed Affidavit of Payment of Claims (Form AC-13), the Certificate of Completion by the Contractor (Form AC-13.2) and the Certificate of Completion by the Architect/Engineer (Form AC-13.1) shall accompany the final Schedule of Values and Certificate for Payment (Form AC-12) which is forwarded to the Owner for payment. The date on which payment is due shall be referred to as the Payment Date. In the event of disputes, payment shall be mailed on or before the Payment Date for amounts and Work not in dispute, subject to any set offs claimed by the Owner, provided however, in instances where further appropriations are required by the County of Albemarle or where the issuance of further bonds is required, in which case, payment shall be made within thirty (30) days after the effective date of such appropriation or within thirty (30) days after the receipt of bond proceeds by the Owner. All prior estimates and payments including those relating to extra Work may be connected and adjusted in any payment and shall be corrected and adjusted in the final payment. In the event that any request for payment by the Contractor contains a defect or impropriety, the Owner shall notify the Contractor of any defect or impropriety which would prevent payment by the Payment Date, within five (5) days after receipt of the Schedule of Values and Certificate for Payment (Form AC-12) by the Owner from the Architect/Engineer. (h) Interest shall accrue on all amounts owed by the Owner to the Contractor which remain unpaid seven (7) days following the Payment Date. Said interest shall accrue at the discounted ninety-day U.S. Treasury bill rate as established by the Weekly Auction and as reported in the publication entitled The Wall Street Journal on the weekday following each such Weekly Auction. During the period of time when the amounts due to the Contractor remain unpaid following the seventh (7th) day after the Payment Date, the interest accruing shall fluctuate on a weekly basis and shall be that established by the immediately prior Weekly Auction. It shall be the responsibility of the Contractor to gather and substantiate the applicable weekly interest rates to the satisfaction of the Owner and to calculate to the satisfaction of the Owner the interest due. In no event shall the rate of interest charge exceed the rate of interest charged pursuant to §58.1-1812 of the Code of Virginia. No interest shall accrue on retainage or when payment is delayed because of disagreement between the Owner and the Contractor regarding the quantity, quality or timeliness of the Work, including, but not limited to, compliance with Contract Documents or the accuracy of any Request for Payment received. This exception to the accrual of interest stated in the preceding sentence shall apply only to that portion of a delayed payment which is actually the subject of such a disagreement and shall apply only for the duration of such disagreement. Nothing contained herein shall be interpreted, however, to prevent the withholding of retainage to assure faithful performance of the Contract. These same provisions relating to payment of interest to the Contractor shall apply also to the computation and accrual of interest on any amounts due from the Contractor to the Owner for deductive change orders and to amounts due on any claims by the -39County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) Owner. The date of mailing of any payment by the U.S. Mail is deemed to be the date of payment to the addressee. 37. (i) The acceptance by the Contractor of the final payment shall be and operate as a release to the Owner of all claims by the Contractor, its Subcontractors and Suppliers, and of all liability to the Contractor whatever, including liability for all things done or furnished in connection with this Work, except for things done or furnished which are the subject of unresolved claims for which the Contractor has filed a timely written notice of intent, provided a claim is submitted no later than sixty (60) days after final payment. Acceptance of any interest payment by the Contractor shall be a release of the Owner from claims by the Contractor for late payment. (j) No certificate for payment issued by the Architect/Engineer, and no payment, final or otherwise, no certificate of completion, nor partial or entire use or occupancy of the Work by the Owner, shall be an acceptance of any Work or materials not in accordance with the Contract, nor shall the same relieve the Contractor of responsibility for faulty materials or Defective Work or operate to release the Contractor or his Surety from any obligation under the Contract, the Standard Performance Bond and the Standard Labor and Material Payment Bond. PAYMENTS BY CONTRACTOR (§2.2-4354, Code of Virginia) Under §2.2-4354, Code of Virginia, the Contractor is obligated to: (a) Within seven (7) days after receipt of amounts paid to the Contractor by the Owner for Work performed by the Subcontractor or Supplier under this Contract, (1) Pay the Subcontractor or Supplier for the proportionate share of the total payment received from the Owner attributable to the Work performed by the Subcontractor or the materials furnished by the Supplier under this Contract; or (2) Notify the Subcontractor or Supplier, in writing, of his intention to withhold all or a part of the Subcontractor or Supplier’s payment with the reason for nonpayment; (b) Pay interest to the Subcontractor or Supplier on all amounts owed by the Contractor that remain unpaid after seven (7) days following receipt by the Contractor of payment from the Owner for Work performed by the Subcontractor or materials furnished by the Supplier under this contract, except for amounts withheld as allowed under subsection (a)(2) of this Section. (c) Include in each of his subcontracts a provision requiring each Subcontractor to include in each of its subcontracts a provision requiring each subcontractor to include or otherwise be subject to the same payment and interest requirements with respect to each lower tier subcontractor. Each Subcontractor shall include with its invoice to, or request for payment from, the Contractor, a certification that Subcontractor has paid each of its suppliers and lower tier subcontractors their proportionate share of previous payments received from the Contractor attributable to the Work performed or the materials furnished by it under this Contract. -40County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) The Contractor’s obligation to pay interest to the Subcontractor or Supplier pursuant to subsection (b) of this Section is not an obligation of the Owner. A modification to this Contract shall not be made for the purpose of providing reimbursement for such interest charge. A Contractor’s cost reimbursement claim shall not include any amount for reimbursement of such interest charge. 38. CHANGES IN THE WORK (a) The Owner may at any time, by written order utilizing the County of Albemarle Change Order Form AC-11 and without notice to the sureties, make changes in the Work which are within the general scope of the contract except that no change will be made which will increase the total Contract Price to an amount more than twenty-five percent (25%) in excess of the original Contract Price without notice to sureties. At the time of the Preconstruction Meeting described in Section 49(b), the Contractor and the Owner shall advise each other of their designees authorized to accept and/or approve changes to the Contract Price and of any limits to each designee’s authority. Should any designee or limits of authority change during the time this Contract is in effect, the Contractor or Owner shall give written notice to the other within seven (7) calendar days, utilizing the procedures set forth in these General Conditions. The Contractor agrees and understands that the authority of the Owner’s designee is limited by Virginia Code §2.2-4309 and any other applicable statute. If the Contractor claims that any instructions given to him by the Architect/Engineer or by the Owner, by drawings or otherwise, involve extra Work which increases the scope of the Contract, then, except in emergencies endangering life or property, he shall give the Architect/Engineer and the Owner written notice thereof before proceeding to execute the Work. Said notice shall be given promptly enough to avoid delaying the Work and in no instance later than fourteen (14) days after the receipt of such instructions. Should it not be immediately clear to the Contractor that the change involves extra Work outside the scope of the Contract, written notice shall be sufficient if given as soon as possible after such realization, but in no event later than fourteen (14) days after the start of such Work. If the Owner agrees, a Change Order shall be issued as provided herein, and any additional compensation shall be determined by one of the four (4) methods provided herein, as selected by the Owner. Except as otherwise specifically provided, no claims for extra Work shall be allowed unless timely notice, as required by this Section, is given by the Contractor and unless such Work is performed pursuant to written Change Order. The Change Order shall designate which of the four methods for computing charges and credits set forth herein shall be used. In making any change, the charge or credit for the change shall be determined by one of the following methods as selected by the Owner: (1) By a mutually agreed fixed amount change to the Contract Price and/or time allowed for completion of the Work. The Change Order shall be substantiated by documentation itemizing the estimated quantities and costs of all labor, materials and equipment required as well as any markup used. The price change shall include the Contractor’s overhead and profit. See Subsections (d) and (e) below. (2) By using unit prices and calculating the number of net units of Work in each part of the Work which is changed, either as the Work progresses or before Work on the change -41County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) commences, and by then multiplying the calculated number of units by the applicable unit price set forth in the Contract or multiplying by a mutually agreed unit price if none was provided in the Contract. No additional percentage markup for overhead or profit shall be added to the unit prices. (3) By ordering the Contractor, by Unilateral Change Order citing this subsection, to proceed with the change to the Work for the cost and completion schedule set forth by the Unilateral Change Order. The Contractor shall proceed with the work as directed, and shall notify the Owner when eighty-five percent (85%) of the amount obligated by this Unilateral Change Order has been expended. (4) By keeping in a form acceptable to the Owner, an accurate, itemized account of the cost of the change in the Work, including, but not limited to, the costs of labor, materials, equipment, and supplies; and to annotate a copy of the Project schedule to accurately show the status of the Work at the time this initial change order is issued, to show the start and finish of the changed Work, and the status of the Work when the changed Work is completed. A Change Order citing this subsection shall describe the parameters of the change in the Work, describe the cost items to be itemized and verified for payment, address the impact on the schedule for Substantial Completion, and state that a subsequent Change Order will be issued to incorporate the cost of the changed Work into the Contract Price and any change in the Contract Time for Completion or Contract Completion Date. The Contractor shall sign the Change Order acknowledging he has been directed to proceed with the changed Work. Except as otherwise may be agreed to in writing by the Owner, such costs shall not exceed those prevailing for the trades or crafts, materials, and equipment in the locality of the Project, may include only those items listed as allowable in Subsection 38(e), and shall not include any of the costs listed as not allowable in Subsection 38(f). The Owner shall be permitted, on a daily basis, to verify such records and may require such additional records as are necessary to determine the cost of the change to the Work. Within fourteen (14) days of the conclusion of such ordered Work, the Contractor and the Owner shall arrive at a cost for the Change Order, based on the records kept and the Contractor’s allowance for overhead and profit as set forth in Subsections (d), (e) and (f) below, and such costs shall be incorporated into a Change Order which references the Change Order ordering the Work. If agreement on the cost of the changed Work cannot be reached within the fourteen (14) days allotted, the Contractor may file a claim for the disputed amount as provided for in Section 46. (b) The Contractor shall review any Owner requested or directed change and shall respond in writing within fourteen (14) calendar days after receipt of the proposed change (or such other reasonable time as the Owner may direct), stating the effect of the proposed change upon his Work, including any increase or decrease in the Contract time and Price. The Contractor shall furnish to the Owner an itemized breakdown of the quantities and prices used in computing the proposed change in Contract Price. -42County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) The Owner shall review the Contractor’s proposal and respond to the Contractor within thirty (30) days of receipt. If a change to the Contract Price and time for performance are agreed upon, both parties shall sign the Change Order. If the price and time are not agreed upon, the Owner may direct the Contractor to proceed under Subsection 38(a)(3) or 38(a)(4). Changes to the Contract time and/or Price shall be effective when signed by both parties, with the exception of a Unilateral Change Order that is only signed by the Owner. (c) In figuring changes, any instructions for measurement of quantities set forth in the Contract shall be followed. (d) The percentage for overhead and profit to be used in calculating both additive and deductive changes in the Work (other than changes covered by unit prices) shall not exceed the percentages for each category listed below. Said percentages for overhead and profit shall he applied only on the cost of the changed Work (i.e. difference in cost between original and revised Work): (1) If a Subcontractor does all or part of the changed Work, the Subcontractor’s markup for overhead and profit on the Work it performs shall be a maximum of fifteen percent (15%). The Contractor’s markup on the subcontractor’s price shall be a maximum of ten percent (10%). (2) If the Contractor does all or part of the changed Work, its markup for overhead and profit on the changed Work it performs shall be a maximum of fifteen percent (15%). (3) If a Sub-subcontractor at any tier does all or part of the changed Work, the Subsubcontractor’s markup on that Work shall be a maximum of fifteen percent (15%). The markup of a sub-subcontractor’s Work by the Contractor and all intervening tiers of Subcontractors shall not exceed a total of ten percent (10%). (4) Where Work is deleted from the Contract prior to commencement of that Work without substitution of other similar Work, one hundred percent (100%) of the Contract Price attributable to that Work shall be deducted from the Contract Price including applicable overhead costs and profit. However, in the event that material Submittals have been approved and orders placed for said materials, a lesser amount, but in no case less than eighty percent (80%) of the Contract Price attributable to that Work, shall be deducted from the Contract Price. The credit to the Owner for reduced premiums on labor and material bonds and performance bonds shall in all cases be one hundred percent (100%). (e) Allowable costs for changes in the Work may include the following: (1) Labor costs for employees directly employed in the change in the Work, including salaries and wages plus the cost of payroll charges and fringe benefits and overtime premiums, if such premiums are explicitly authorized by the Owner. (2) Materials incorporated into the change to the Work, including costs of transportation and storage, if applicable. If applicable, all cash discounts shall accrue to the Contractor, unless the Owner deposits funds with the Contractor to make such payments, and all trade -43County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) discounts, rebates, refunds, and returns from the sale of surplus materials shall accrue to the Owner. (3) Equipment incorporated in the changed Work or equipment used directly in accomplishing the Work. If rented expressly for accomplishing the change in the Work, the cost shall be the rental rate according to the terms of the rental agreement, which the Owner shall have the right to approve. If owned by the Contractor, the costs shall be a reasonable price based upon the life expectancy of the equipment and the purchase price of the equipment. If applicable, transportation costs may be included. (4) Costs of increases in premiums for the Standard Labor and Material Payment Bond and the Standard Performance Bond, provided coverage for the cost of the change in the Work results in such increased costs. At the Owner’s request, the Contractor shall provide proof of his notification to the Surety of the change in the Work and of the Surety’s agreement to include such change in its coverage. The cost of the increase in premium shall be an allowable cost but shall not be marked up. (5) Contractor and Subcontractor overhead costs as set forth in Subsection (d) markups above. (6) If the change in the Work also changes the Time for Completion or Contract Completion Date by adding days to perform the Work, an itemized accounting of the following Site direct overhead expenses for the change to the time may be considered as allowable costs for compensation in addition to those shown above: The Site superintendent’s prorata salary, temporary Site office trailer expense, and temporary Site utilities including basic telephone service, electricity, heat, water, and sanitary/toilet facilities. All other direct and indirect overhead expenses are considered covered by and included in the Subsection (d) markups above. (7) Any other costs directly attributable to the change in the Work with the exception of those set forth below. (f) Allowable costs for changes in the Work shall not include the following: (1) Costs due to the negligence of the Contractor, any Subcontractor, Supplier, their employees or other persons for whom the Contractor is responsible, including, but not limited to, costs for the correction of Defective Work, for improper disposal of material, for equipment wrongly supplied, for delay in performing the Work, or for delay in obtaining materials or equipment. (2) Home office expenses including payroll costs for the Contractor’s officers, executives, administrators, project managers, accountants, counsel, engineers, timekeepers, estimators, clerks, and other similar administrative personnel employed by the Contractor, whether at the Site or in the Contractor’s principal or branch office for general administration of the Work. These costs are deemed overhead included in the percentage markups allowable in Subsection (d) above. -44County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (3) Home and field office expenses not itemized in Subsection 38(e)(6) above. Such items include, but are not limited to, expenses of Contractor’s home and branch offices, Contractor’s capital expenses, interest on Contractor’s capital used for the Work, charges for delinquent payments, small tools, incidental job costs, rent, utilities, telephone and office equipment, and other general overhead expenses. (g) All Change Orders, except the “initial” Change Orders authorizing work citing Subsection 38(a)(4) procedures, must state that the Contract Time for Completion or Contract Completion Date is not changed or is either increased or decreased by a specific number of days. The old Time for Completion and, if changed, the new Time for Completion must be stated. If the Contractor requests an extension to the Time for Completion or a later Contract Completion Date, he must provide written justification for the extension to the Architect/Engineer and to the Owner. The written justification must demonstrate an anticipated actual increase in the time required to complete the Work beyond that allowed by the Contract as adjusted by prior change orders or amendments to the Contract, not just an increase or decrease in the time needed to complete some portion of the total Work. When a CPM schedule is required by the Contract, no extension to the Time for Completion or Contract Completion Date shall be allowed unless, and then only to the extent that, the additional or changed Work increases the length of the critical path beyond the Time for Completion or Contract Completion Date. If approved, the increase in time required to complete the Work shall be added to the Time for Completion or Contract Completion Date. The Owner may decrease, by Change Order, the Time for Completion or Contract Completion Date when an Owner-requested deletion from the Work results in a decrease in the actual time required to complete the Work as demonstrable on the Bar Graph Schedule or on the CPM Schedule, whichever is appropriate. The Contractor may submit a request to decrease, by Change Order, the Time for Completion or Contract Completion Date under the procedures and subject to the considerations set forth in Section 19(f). No request for such decrease shall be considered for approval unless the proposed shorter schedule is otherwise acceptable under Sections 19(b) or (c), whichever is applicable. The Change Order decreasing the Time for Completion or changing the Contract Completion Date must be signed by both the Owner and the Contractor. With the exception of Change Orders under Subsection 38(a)(4), which shall arrive at a change to the Contract Price and any change to time using the procedures set forth therein, each Change Order shall include all time and monetary impacts of the change, whether the Change Order is considered alone or with all other changes during the course of the Project. Failure to include a change to time and Contract Price in Section 38(a)(1) or (2) Change Orders shall waive any change to the time and Contract Price unless the parties mutually agree in writing to postpone a determination of the change to time and price resulting from the Change Order. Such a determination may be postponed not more than forty-five (45) days to give the Contractor an opportunity to demonstrate a change in the time and price needed to complete the Work. During any such postponement, the Work shall proceed, unless the Owner agrees otherwise. If at any time there is a delay in the critical path of the Work due to postponement, due to the Contractor’s efforts to justify an extension of the time or an increase in the Contract Price, or due to the Contractor’s refusal to proceed with any of the Work, pending agreement on a change in time -45County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) or price, such delay and any Contractor costs resulting from it shall not serve as the basis for the extension of the Time for Completion or Contract Completion Date or for an increase in the Contract Price. (h) The acceptance by the Contractor of any payment made by the Owner under a Change Order shall be and operate as a release to the Owner of all claims by the Contractor and of all liability owing to the Contractor for all things done or furnished in connection with the Work described in the Change Order. The execution of any Change Order by the Owner shall not be an acceptance of any Work or materials not in accordance with the Contract Documents, nor shall it relieve the Contractor of responsibility for faulty materials or workmanship or operate to release the Contractor or his surety from any obligation arising under the Contract or the Standard Performance Bond or Standard Labor and Material Payment Bond. (i) Payments will not be made for any Work, labor or materials on a fixed price, unit price or Subsection 38(a)(4) basis until the Contractor has furnished the Owner documents, certified as true and correct by an authorized officer or agent of the Contractor, evidencing the cost of such Work, labor and materials. The Owner may require any or all of the following documentation to be provided by the Contractor: (1) certified payroll records showing the name, classification, date, daily hours, total hours, rate, and extension for each laborer, foreman, supervisor or other worker; (2) equipment type & model, dates, daily hours, total hours, rental rate or other specified rate, and extension for each unit of equipment; (3) invoices for materials showing quantities, prices, and extensions; (4) daily records of waste materials removed from the Site and/or fill materials imported to the Site; (5) certified measurements of over excavations, piling installed and similar work; and/or (6) transportation records for materials, including prices, loads, and extensions. Requests for payment shall be accompanied and supported by invoices for all materials used and for all transportation charges claimed. If materials come from the Contractor’s own stock, then an affidavit may be furnished, in lieu of invoices, certifying quantifies, prices, etc. to support the actual cost. 39. CONTRACTOR’S RIGHT TO STOP WORK OR TERMINATE THE CONTRACT If the Work should be stopped under an order of any court or other public authority for a period of ninety (90) days through no fault of the Contractor or anyone employed by him, or if the Owner should fail to pay to the Contractor within sixty (60) days any sum certified by the Architect/Engineer when no dispute exists as to the sum due or any provision of the Contract, then the Contractor may, upon ten (10) -46County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) calendar days written notice to the Owner and the Architect/Engineer, stop Work or terminate the contract and recover from the Owner payment for the cost of the Work actually performed, together with overhead and profit thereon, but profit on the Work performed shall be recovered only to the extent that the Contractor can demonstrate that he would have had profit on the entire Contract if he had completed the Work. The Contractor may not receive profit or any other type of compensation for parts of the Work not performed. The Contractor may recover the reasonable cost of physically closing down the Site, but no other costs of termination. The Owner may offset any claims it may have against the Contractor against the amounts due to the Contractor. In no event shall termination of the Contract by the Contractor terminate the obligations of the Contractor’s surety on its payment and performance bonds. 40. OWNER’S RIGHT TO STOP WORK OR TERMINATE THE CONTRACT FOR CAUSE (a) If the Contractor should be adjudged as bankrupt, or if he should make a general assignment for the benefit of his creditors, or if a receiver should be appointed on account of his insolvency, the Owner may stop work or terminate the Contract. If the Contractor should refuse or should repeatedly fail, except in cases for which extension of time is provided, to supply enough properly skilled workmen or proper materials and equipment, or if he should fail to make prompt payment to Subcontractors or Suppliers of material or labor, or if he should disregard laws, ordinances or the written instructions of the Architect/Engineer or the Owner, or otherwise be in substantial violation of any provision of the Contract, then the Owner may stop work or terminate the Contract. (b) Prior to termination of the Contract, the Owner shall give the Contractor and his surety ten (10) calendar days written notice pursuant to Section 1 (“Notice”) of these General Conditions, during which the Contractor and/or his surety may rectify the basis for the notice. If rectified to the satisfaction of the Owner within said ten (10) days, the Owner may rescind its notice of termination. If not, the termination for cause shall become effective at the end of the ten (10) day notice period. In the alternative, the Owner may, in writing, postpone the effective date of the termination for cause, at its sole discretion, if it should receive reassurances from the Contractor and/or its surety that the basis for the termination will be remedied in a time and manner which the Owner finds acceptable. If at any time after such postponement, the Owner determines that Contractor and/or its surety has not or is not likely to rectify the causes of termination in an acceptable manner or within the time allowed, then the Owner may immediately terminate the Contract for cause, without the necessity of further ten (10) day notice, by notifying the Contractor and his surety in writing of the termination. In no event shall termination for cause terminate the obligations of the Contractor’s surety on its payment and performance bonds. (c) Upon termination of the Contract, the Owner shall take possession of the Site and of all materials, tools and equipment thereon and finish the Work by whatever method he may deem expedient. In such case the Contractor shall not be entitled to receive any further payment. If the expense of finishing the Work, including compensation for additional managerial and administrative services, shall exceed the unpaid balance of the Contract Price, the Contractor shall pay the difference to the Owner, together with any other expenses of terminating the Contract and having it completed by others. -47County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) 41. (d) If it should be judicially determined that the Owner improperly terminated this Contract for cause, then the termination shall be deemed to be a termination for the convenience of the Owner. (e) Termination of the Contract under this Section is without prejudice to any other right or remedy of the Owner. TERMINATION BY OWNER FOR CONVENIENCE (a) Owner may terminate this Contract, in whole or in part, at any time without cause upon giving the Contractor written notice of such termination pursuant to Section 1 (“Notice”) of these General Conditions. Upon such termination, the Contractor shall immediately cease Work and remove from the Site all of its labor forces and such of its materials as Owner elects not to purchase or to assume in the manner hereinafter provided. Upon such termination, the Contractor shall take such steps as Owner may require to assign to the Owner the Contractor’s interest in all Subcontracts and purchase orders designated by Owner. After all such steps have been taken to Owner’s satisfaction, the Contractor shall receive as full compensation for termination and assignment the following: (1) All amounts then otherwise due under the terms of this Contract; (2) Amounts due for Work performed in accordance with the Contract subsequent to the latest approved Schedule of Values and Certificate for Payment (Form AC-12) through the date of termination; (3) Reasonable compensation for the actual cost of demobilization incurred by the Contractor as a direct result of such termination. The Contractor shall not be entitled to any compensation or damages for lost profits or for any other type of contractual compensation or damages other than those provided by the preceding sentence. Upon payment of the foregoing, Owner shall have no further obligations to Contractor of any nature. (b) In no event shall termination for the convenience of the Owner terminate the obligations of the Contractor’s surety on its payment and performance bonds. 42. DAMAGES FOR DELAYS; EXTENSION OF TIME (a) If the Contractor is delayed at any time in the progress of the Work by any act or omission of the Owner, its agents or employees or any separate independent contractor of the Owner, and the act or omission is the result of or is necessitated by causes outside the Owner’s control; or if the Contractor is delayed by strikes, fires, unusual delays in transportation or unavoidable casualties, or other causes outside the Owner’s or Contractor’s control, the Contractor shall give the Owner and Architect/Engineer written notice within ten (10) days of the inception of the delay. The Owner shall extend the time for Substantial Completion or Final Completion, as the case may be, for the length of time that the Substantial Completion or Final Completion of the Work was actually delayed thereby, and the Contractor shall not be charged with liquidated or actual damages for delay during the period of such extension nor shall the Contractor be due compensation or damages -48County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) of any kind, under any theory of law, as a result of such delay, the impact of such delay, or acceleration of Work as a result of such delay. In the event a CPM schedule is required by the Contract, no extension of the time allowed for Substantial Completion shall be granted unless the Contractor demonstrates a delay in the critical path of the approved CPM schedule or approved bar graph schedule. (b) If the Contractor is delayed at any time in the progress of the Work by any act or omission of the Owner, its agents or employees, due to causes within their control, or delayed by the Owner’s separate, independent contractors, when such delay results from causes within the Owner’s control, and the Contractor intends to seek additional compensation for damages, if any, caused by the delay, the Contractor shall inform the Owner and the Architect/Engineer immediately at the time of the occurrence giving rise to the delay by the fastest means available and shall give written notice no later than two (2) working days after inception of the delay. The Contractor’s notice to the Owner shall specify the nature of the delay claimed by the Contractor, the cause of the delay and the impact of the delay on the Contractor’s Work schedule. The Owner shall then have three (3) working days to respond to the Contractor’s notice with a resolution, remedy or direction to alleviate the delay or with a notice rejecting the claim for delay alleged to be caused by the Owner or parties for whom the Owner is responsible. If the issue is not then resolved, the Contractor may submit a request for Change Order in accordance with Section 38 or submit a claim as provided for in Section 46. The Contractor shall only be entitled to additional compensation if the delay was unreasonable and was caused solely by acts or omissions of the Owner, its agents or employees, due to causes within their control, or was caused by the Owner’s separate, independent contractor, when such delay resulted solely from causes within the Owner’s control. (c) The Contractor shall not be entitled to an extension of the Time for Completion or Contract Completion Date or to any additional compensation for delays caused by acts or omissions of the Contractor due to causes within his control, including, but not limited to, delays resulting from Defective Work including workmanship and/or materials, from rejected work which must be corrected before dependent work can proceed, from Defective Work or rejected work for which corrective action must be determined before like work can proceed, or from incomplete, incorrect or unacceptable submittals or samples. (d) No extension of time or additional compensation, if applicable, will be granted for any delay unless the claimed delay directly affects the critical path of the approved CPM schedule or the schedule shown on the approved bar graph schedule, whichever is applicable, and any float has been consumed. No extension of time or additional compensation shall be given for a delay if the Contractor failed to give notice in the manner and within the time prescribed in Subsections (a) or (b) above, whichever applies. Furthermore, no extension of time or additional compensation shall be given for any delay unless a claim therefor is made in writing to the Owner, with a copy to the Architect/Engineer, within twenty (20) days of the end of the delay. The claim shall state the cause of the delay, the number of days of extension requested and any compensation requested by the Contractor. The Contractor shall report the termination of the delay to the Owner and Architect/Engineer not less than ten (10) days after such termination. Failure to give notice of either the inception or the termination of the cause of delay or failure to present a claim for extension of time and/or monetary compensation within the times prescribed shall constitute a waiver of any claim for extension or additional compensation based upon that cause. -49County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (e) Requests for compensation for delays pursuant to Subsection (b) above must be substantiated by itemized data and records clearly showing that the Work delayed was on the critical path of the approved CPM schedule or on the sequence of Work on the approved bar graph schedule, as modified, and that the additional costs incurred by the Contractor are directly attributable to the delay in the Work claimed. Furthermore, compensation for delay shall be calculated from the contractual Time for Completion or Contract Completion Date, as adjusted by Change Order, and shall not be calculated based on any early completion planned or scheduled by the Contractor, unless a Change Order has been executed pursuant to Section 19(f) changing the Time for Completion or the Contract Completion Date to reflect such early completion. See Section 19 for procedures for the Contractor to follow if he plans early completion of the Work and wishes to request a Change Order reflecting the early completion date. If there is an extension in the Time for Completion or the Contract Completion Date and if the Contractor is entitled to compensation under Subsection 42(b), and where there is no change in the Work, an itemized accounting of the following direct Site overhead expenses will be considered as allowable costs to be used in determining the compensation due the Contractor: Site superintendent prorata salary, temporary Site office expense, temporary Site facilities, and temporary Site utilities including basic telephone service, electricity, heat, water, and sanitary/toilets. A fifteen percent (15%) markup of these expenses will be allowed to compensate the Contractor for home office and other direct or indirect overhead expenses. (f) If the Contractor submits a claim for delay damages pursuant to Subsection 42(b) above, the Contractor shall be liable to the Owner for a percentage of all costs incurred by the Owner in investigating, analyzing, negotiating and litigating the claim, which percentage shall be equal to the percentage of the Contractor’s total delay claim that is determined through litigation to be false or to have no basis in law or in fact. (§2.2-4335(C), Code of Virginia.) (g) Any change in the Contract Time for Completion or Contract Completion Date shall be accomplished only by issuance of a Change Order. (h) If the Contractor fails to complete the Work within the Time for Completion or the Contract Completion Date, the Contractor shall be liable to the Owner in the amounts set forth in the Supplemental General Conditions, if any, not as a penalty, but as fixed, agreed and liquidated damages for delay until the Work is substantially or finally completed as the case may be. If liquidated damages are not so fixed in the Supplemental General Conditions, the Contractor shall be liable for any and all actual damages sustained as a result of delay. In addition to damages for delay, whether liquidated or actual, the Contractor shall also be liable for any and all actual damages sustained by the Owner as a result of any other breach of the Contract, including, but not limited to, Defective Work and abandonment of the Contract. (i) If liquidated damages are provided by the Supplemental General Conditions, the following provisions apply: i. If the Work is not substantially complete by the Time for Completion or Contract Completion Date, the Contractor shall owe to the Owner, not as a penalty but as Step One -50County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) liquidated damages, the sum stated in the Supplemental General Conditions for Step One liquidated damages for each and every partial or total calendar day of delay in Substantial Completion. 43. ii. Once the Work is substantially complete, the accrual of Step One liquidated damages shall cease and the Contractor shall have thirty (30) calendar days in which to achieve Final Completion of the Work. iii. If Final Completion of the Work is not achieved on or before the thirtieth (30th) calendar day after Substantial Completion, and if the Owner has not granted any extension of time, the Contractor shall owe to the Owner, not as a penalty but as Step Two liquidated damages, the sum stated in the Supplemental General Conditions as Step Two liquidated damages for each and every partial or total calendar day of delay in Final Completion. INSPECTION FOR SUBSTANTIAL COMPLETION & FINAL COMPLETION (a) The Contractor shall notify the Owner, in writing on the Certificate of Partial or Substantial Completion by the Contractor (Form AC-13.2a), of the date when the Work or designated portion thereof, will be, in his opinion, substantially complete and ready for inspection and testing to determine if it has reached Substantial Completion. The notice shall be given at least ten (10) days in advance of said date and shall be forwarded through the Architect/Engineer, who will attach his written endorsement as to whether or not he concurs with the Contractor’s statement that the Work will be ready for inspection and testing on the date given. The Architect/Engineer’s endorsement is a convenience to the Owner only and shall not relieve the Contractor of his responsibility in the matter nor shall the Architect/Engineer’s endorsement be deemed to be evidence that the Work was substantially complete and ready for inspection and testing. Inspection and testing shall take place at a time(s) mutually agreeable to the Contractor, Owner and Architect/Engineer. The inspection shall include a demonstration by the Contractor that all equipment, systems and operable components of the project function properly and in accordance with the Contract Documents. The Contractor shall furnish access for the inspection and testing as provided in Section 21 of these General Conditions. The inspection and testing shall determine whether Substantial Completion has been accomplished and shall result in a written list of unfinished Work and Defective Work, commonly referred to as a “punch list”, which must be finished and corrected to obtain Final Completion. After successful completion of the testing and the Architect/Engineer determines that, in its opinion, the Work, either in whole or in part, is substantially complete, the Architect/Engineer shall notify the Owner, in writing on the Certificate of Partial or Substantial Completion by the Architect/Engineer (Form AC-13.1a), that the Work, or a specified portion thereof, is recommended to be declared substantially complete. The Owner shall notify the Contractor, in writing, of the date the Owner accepts the Work, or the specified portion thereof, as substantially complete or the Owner shall notify the Contractor of the deficiencies to be corrected or completed before such Work will be accepted as substantially complete. -51County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (b) The Contractor shall notify the Owner, in writing on the Certificate of Completion by the Contractor (Form AC-13.2), of the date when the Work has reached or will reach Final Completion and will be ready for final inspection and testing. The notice shall be given at least five (5) days in advance of said date and shall be forwarded through the Architect/Engineer, who will attach his endorsement as to whether or not he concurs in the Contractor’s statement that the Work will be ready for inspection and testing on the date given. That inspection and any necessary testing shall be conducted in the same manner as the inspection for Substantial Completion. When the Work is finally and totally complete, including the elimination of all defects, the Work shall be finally accepted by the Owner and final payment shall be made in accordance with Section 36 of these General Conditions. (c) The Architect/Engineer shall conduct the inspections. The Owner may elect to have other persons of its choosing also participate in the inspections. If one or more Substantial or Final Completion reinspections are required, the Contractor shall reimburse the Owner for all costs of reinspection or, at the Owner’s option, the costs may be deducted from payments due to the Contractor. (d) A representative of the local Building Official will either be present at the Substantial and Final Completion inspections or otherwise inspect the completed Work and advise the Owner whether the Work meets the requirements of the applicable building code(s). (e) Approval of Work at or as a result of any inspection required herein shall not release the Contractor or his surety from responsibility for complying with the Contract. 44. GUARANTEE OF WORK (a) Except as otherwise specified, all Work shall be, and is hereby, guaranteed by the Contractor against defects resulting from the use of materials, equipment or workmanship, which are defective, inferior, or not in accordance with the terms of the Contract, for one (1) year from the date of Final Completion of the entire Project by the Owner. Equipment and facilities which have seasonal limitations on their operation (e.g. heating or air conditioning units) shall be guaranteed for one (1) full year from the date of seasonally appropriate tests and acceptance, in writing, by the Owner. Where the Owner agrees to take Beneficial Occupancy of a portion or phase of the Work which has been determined to be substantially complete before the entire Work is finally completed, the guarantees for the materials, equipment and workmanship in that portion or phase shall begin on the date that the Owner takes Beneficial Occupancy, unless otherwise specified in the Supplemental General Conditions, Special Conditions, or by separate agreement. (b) If, within any guarantee period, Work which is not in accordance with the Contract, Defective Work, or inferior material, equipment or workmanship is noted by the Owner or Architect/Engineer which requires or renders necessary repairs or changes in connection with the guaranteed Work, the Contractor shall, promptly upon receipt of notice from the Owner, such notice being given not later than two weeks after the guarantee period expires, and without expense to the Owner: (1) Place in satisfactory condition in every particular all of such guaranteed Work and correct all defects, inferior materials, equipment or workmanship therein; -52County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (2) Make good all damage to the structure or Site or equipment or contents thereof, which, in the opinion of the Owner or the Architect/Engineer, is the result of the use of materials, equipment or workmanship which are inferior, defective or not in accordance with the terms of the Contract; and (3) Make good any Work or materials or the equipment and contents of structures and/or Site disturbance that results from fulfilling the provisions of this Section. (c) In any case, when in fulfilling the requirements of the Contract and this guarantee or any other guaranty or warranty, the Contractor disturbs any work performed by a separate contractor, he shall restore such work to a condition satisfactory to the Architect/Engineer and Owner and guarantee such restored work to the same extent as if it was guaranteed under this Contract. (d) If the Contractor, after notice, fails to proceed promptly to comply with the terms of the guarantee as set forth in this Section, the Owner may have the defects or inferior materials, equipment or workmanship corrected and the Contractor and his surety shall be liable for all expense incurred. (e) All special warranties and guarantees applicable to definite parts of the Work that may be stipulated in or required by the Contract Documents shall be subject to the terms of this Section during the first year of the life of such special warranty or guarantee. (f) The guarantee of this Section shall be in addition to and not in lieu of all other warranties, express or implied, applicable to or arising from this Contract or by law. (g) Nothing contained in this Section shall be construed to establish a period of limitation with respect to any other obligation which the Contractor might have under the Contract Documents, including liability for Detective Work under Section 30. This Section relates only to the specific obligation of the Contractor as set forth in this Section to correct the Work and does not limit the time within which his obligation to comply with the Contract Documents may be sought to be enforced, nor the time within which proceedings may be commenced to establish the Contractor’s liability with respect to his other obligations under the Contract Documents. (h) In the event the Work of the Contractor is to be modified by another contractor, either before or after the Final Inspection provided by Section 43 of the General Conditions, the first Contractor shall remain responsible in all respects under this Section’s Guarantee of Work and under any other warranties or guarantees, express or implied, applicable to or arising from this Contract or by law. However, the Contractor shall not be responsible for any defects in material or workmanship introduced by the contractor modifying his Work. The first Contractor and the contractor making the modifications shall each be solely responsible for his respective work. The contractor modifying the earlier Work shall be responsible for any damage to or defect introduced into the Work by his modification. If the first contractor claims that a subsequent contractor has introduced defects of materials and/or workmanship into his Work, it shall be the burden of the contractor making the claim to demonstrate clearly the nature and extent of such introduced defects and the other contractor’s responsibility for those defects. Any contractor modifying the work of another shall have the same burden if he asserts that defects in his work were caused by the contractor whose work he is modifying. -53County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) 45. ASSIGNMENTS OF CONTRACTUAL OBLIGATIONS Neither party to the Contract shall assign the Contract in whole or any part without the written consent of the other, nor shall the Contractor assign any monies due or to become due to him hereunder, without the prior written consent of the Owner. No assignment shall relieve any party from its obligations under the Contract. 46. CONTRACTUAL DISPUTES (§2.2-4363, Code of Virginia) Contractual claims, whether for money or for other relief, shall be submitted, in writing, no later than sixty (60) days after final payment; however, written notice of the Contractor’s intention to file such claim must be given at the time of the occurrence or beginning of the Work upon which the claim is based. The filing of a timely notice is a prerequisite to recovery under this Section. Although the Contractor may be required to submit certain classes of claims prior to final payment, and the Contractor is not prevented from filing claims during the pendency of the Work, the Owner shall not be obligated to render a final written decision on any claim until after final payment. All claims shall be submitted along with all practically available supporting evidence and documentation. No written decision denying a claim or addressing issues related to the claim, if rendered prior to final payment, shall be considered a denial pursuant to this Section unless the written decision makes express reference to this Section and is signed by the Owner or his designee. The Contractor may not institute legal action prior to receipt of the Owner’s final written decision on the claim unless the Owner fails to render such a decision within ninety (90) days of submission of the claim or within ninety (90) days of final payment, whichever is later. The decision of the Owner shall be final and conclusive unless the Contractor within six (6) months of the date of the final decision on a claim, initiates legal action as provided in §2.2-4364 of the Code of Virginia. Failure of the Owner to render a decision within 90 days shall not result in the Contractor being awarded the relief claimed nor shall it result in any other relief or penalty. The sole result of the Owner’s failure to render a decision within 90 days shall be the Contractor’s right to immediately institute legal action. No administrative appeals procedure pursuant to §2.2-4365 of the Code of Virginia has been established for contractual claims under this Contract. Venue for any litigation arising hereunder shall be in the Circuit Court for the County of Albemarle, Virginia. 47. ASBESTOS (a) This subsection applies to projects involving existing buildings where asbestos abatement is not a part of the Work, when the scope of the project has been reviewed and a comprehensive survey conducted by an individual licensed by the Virginia Department of Professional and Occupational Regulation to conduct building inspections for asbestos containing materials in buildings, and where the Owner has attempted to remove or encapsulate all asbestos containing material that may become friable or damaged during this Project. -54County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) Prior to commencement of Work, the results of the comprehensive survey or any other asbestos survey shall be made available to the Contractor, who shall be responsible for performing his Work so as not to disturb any remaining asbestos, encapsulated or otherwise, identified in such survey or surveys. If the Contractor discovers or inadvertently disturbs any material that he knows, should have known or has reason to believe, may contain asbestos that has not been previously identified, was overlooked during the removal, was deemed not to be friable or was encapsulated, the Contractor shall stop Work in the area containing or suspected to contain the asbestos, secure the area, and notify the Owner and the Architect/Engineer immediately by telephone or in person with written notice as soon as possible. The Owner will have the suspect material sampled. If the sample is positive and must be disturbed in the course of the Work, the Owner shall have the material repaired or removed and shall pay for the bulk sample analysis. Except as provided in §11-4.1 of the Code of Virginia, if the material disturbed is not within the Contractor’s authorized Work and/or Work area or under this Contract, the Contractor shall pay for all associated sampling and abatement Costs. (b) If asbestos abatement is included as a part of the Work, the Contractor shall assure that the asbestos abatement work is accomplished by those duly licensed as described in Section 3 of these General Conditions and in accordance with the specific requirements of the Contract and all applicable laws and regulations. (c) If asbestos abatement is included as part of the Work, the licensed asbestos Subcontractor shall obtain the insurance required under Section 11(e) of these General Conditions. 48. TRAINING, OPERATION AND MAINTENANCE OF EQUIPMENT (a) As a part of the Work, the Contractor in conjunction with his Subcontractors and Suppliers shall provide the Owner’s operations and maintenance personnel with adequate instruction and training in the proper operation and maintenance of any equipment, systems, and related controls provided or altered in the Work. The training requirements may be further defined in the specifications. (b) The Contractor shall provide the Owner with a minimum of two (2) copies of operating, maintenance and parts manuals for all equipment and systems provided in the Work. Further specific requirements may be indicated in the specifications. 49. PROJECT MEETINGS (a) The intention of this Section is that the Contractor, the Owner and the A/E have timely exchange of information and cooperate to accomplish the Work as required by the Contract Documents. The Contractor is responsible for managing the Work, obtaining approvals and requesting clarifications on a timely, reasonable basis. The Owner and its A/E are responsible for making a reasonable effort to provide timely responses to the Contractor. -55County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (b) Preconstruction Meeting: Prior to the start of construction and no later than 15 calendar days after the Notice to Proceed, a “Preconstruction” meeting shall be held with attendees to include the Owner’s Project Manager and Project Inspector, the Architect/Engineer’s project manager and representatives of each design discipline involved in the Project, the Contractor’s project manager and superintendent (and scheduler, if Contractor desires), and representatives of the Contractor’s major Subcontractors. The purpose of the meeting is to clarify and discuss the specifics related to, but not limited to, the following: (1) Persons involved from each entity and their chain of authority including the names of persons authorized to sign Change Orders and any limits to their authority. (2) Names, addresses, telephone numbers and FAX numbers to be used for Requests for Information (RFI), Requests for Clarification (RFC), Requests for Proposals (RFP), shop drawings, submittals, and notices. (3) Contractor’s proposed construction schedule and Owner’s sequencing requirements, if any. (4) Schedule of Values and Certificate for Payment (Form AC-12) requirements and procedures. (5) Procedures for shop drawings, product data and Submittals. (6) Procedures for handling Field Orders and Change Order Form AC-11. (7) Procedures for Contractor’s request for time extension, if any. (8) Construction Site requirements, procedures and clarifications to include: - Manner of conducting the Work - Site specialities such as dust and erosion control, stormwater management, project signs, clean up and housekeeping, temporary facilities, utilities, security, and traffic - Safety - Layout of the Work - Quality control, testing, inspections and notices required - Site visits by the A/E and others - Owner’s Project Inspector duties - Running Punch List - As-Built Drawings (9) Procedures and documentation of differing or unforeseen Site conditions (10) Monthly Pay Meeting. (11) Project Close-Out requirements and procedures. (12) Project records. -56County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) (d) Monthly Pay Meeting: Section 36 establishes the requirement for a monthly pay meeting which will usually be held at or near the Site. In addition to Owner, A/E and Contractor representatives, the following representatives, at a minimum, should be available to attend portions of the meeting, as applicable or necessary: - Owner’s Project Inspector. - Contractor’s project superintendent. - A/E representative of each discipline where Work was performed for the current pay request or where Work is projected to be performed in the coming month. - A representative of each subcontractor who performed work included in the current pay request. - A representative of each subcontractor who is projected to perform work in the coming month. The following topics should be included, as a minimum, in the monthly pay meeting: (1) Observations of status, quality and workmanship of Work in progress. (2) Validation of the Schedule of Values and Certificate for payment. (3) Conformance with proposed construction schedule. (4) Outstanding Requests for Information, Requests for Clarification and Requests for Proposal. (5) Submittals with action pending. (6) Status of pending Change Orders. (7) Status of Running Punch List items. (8) Work proposed for coming pay period. (9) Discussions of any problems or potential problems which need attention. (e) Other Meetings: Requirements for other meetings, such as progress meetings, coordination meetings, preinstallation meetings and/or partnering meetings, may be included in the Contract Documents. ***** END OF GENERAL CONDITIONS ***** -57County of Albemarle Construction Contract General Conditions (Feb. 1998, Rev. Oct. 2001) SUPPLEMENTAL GENERAL CONDITIONS THE COUNTY OF ALBEMARLE and/or THE COUNTY SCHOOL BOARD OF ALBEMARLE COUNTY, VIRGINIA CONSTRUCTION CONTRACT GENERAL CONDITIONS (February 1998, Revised October 2001) are modified and supplemented as hereinafter described. 1. Section 1 – DEFINITIONS, shall be supplemented by adding the following: Replace Notice with the following: Notice: All written notices, including demands, instructions, claims, approvals and disapprovals, required or authorized under the Contract Documents. Any written notice by either party to the Contract shall be sufficiently given by any one or combination of the following, whichever shall first occur: (1) delivered by hand to the last known business address of the person to whom the notice is due; (2) delivered by hand to the person’s authorized agent, representative or officer wherever they may be found; or (3) enclosed in a postage prepaid envelope addressed to such last known business address and delivered to a United States Postal Service official or mailbox. Notice is effective upon such delivery. All notices to the Owner should be directed to the Project Manager. Notices transmitted by Facsimile (Fax) or Email are acceptable for the Project. Notices may be transmitted to the Fax number listed in the Contract and shall have a designated space for the Fax Notice recipient to acknowledge his receipt by authorized signature and date. The Fax Notice with authorized signature acknowledging receipt shall be Faxed back to the sender. Notices may be sent to the Email address(es) as provided by the A/E and the Project Manager. The Email acknowledging receipt shall be emailed back to the sender. The Faxed Notice and/or Email shall be effective on the date it is acknowledged by authorized signature or Email acknowledgement. All Faxed and Emailed Notices shall also be delivered by hard copy, which shall be effective upon delivery, as provided herein. Notice shall be effective upon the date of acknowledgment of the Faxed or Emailed Notice or the date of delivery, whichever occurs first. 2. Section 2 – CONTRACT DOCUMENTS, shall be supplemented by adding the following: Replace Paragraph (f) with the following: (f) All correspondence, invoices, memoranda, submittals and other documents related to this Project whether generated by the Owner, the A/E, the Contractor or others should be identified at the beginning of the document with the Project Title shown in the Contract. Additional identification such as a job number, purchase order number or such may also be shown at the Owner’s option. Supplemental General Conditions Page 1 of 7 3. Section 6 – TIME FOR COMPLETION, shall be supplemented by adding the following: Replace Paragraph (3) with the following: (3) 4. All of the evidence and data supporting the request (including both historical data and the recordings at the Site during the time of delay) must be furnished to the Owner before any consideration will be given to the request. That supporting data shall be submitted by the end of the calendar month following the month for which the request is made. The submission must be made on the Cover Sheet of the Certificate of Payment Form AC12. A Change Order prepared in accordance with Change Order procedures specified in the Contract Documents must be submitted with a Weather Delay Rectification Form and supporting documentation as outlined in Section 6 – TIME FOR COMPLETION. Time extensions for adverse weather-related days granted by the Owner will extend the Contract Completion Date but will not include additional compensation to the Contractor. In no manner of interpretation will an adverse weatherrelated time extension be construed to be a compensable delay. Section 12 – “ALL RISK” BUILDER’S RISK INSURANCE Delete Paragraphs (a) and (b). (OR ) 5. Section 12 - “ALL RISK” BUILDER’S RISK INSURANCE Delete Paragraphs (a), (b) and (c) as written and in its place add the following: (a) The requirements of this section of the General Conditions for "all-risk" builders risk insurance on the full value of the entire building are waived for this project. The Owner maintains insurance on the existing building (including fire, vandalism and extended coverage). However, the Contractor shall provide “all risk” builders risk insurance for the Work in an amount equal to one hundred percent (100%) of the Contract Price for the Work. The loss, if any, is to be made adjustable with and payable to the Owner, in accordance with its interests, as they may appear. The Owner, its officers, employees and its agents, shall be named as an additional insured in any policy of insurance issued. Written evidence of the insurance shall be filed with the Owner no later than thirty (30) days following the award of the Contract. In the event of cancellation of this insurance, not less than thirty (30) days prior written notice must be sent to the Owner. A copy of the policy of insurance shall be given to the Owner upon demand. (b) Not used Supplemental General Conditions Page 2 of 7 (c) The Contractor is responsible for providing any desired coverage for Contractor's or Subcontractors' buildings, equipment, materials, tools or supplies that are on-site. [No change to paragraph (d) as written in the General Conditions.] 6. Section 16 - INSPECTION, shall be supplemented by adding the following: Replace Paragraph (b) with the following: (b) Site inspections, tests conducted on Site or tests of materials gathered on Site, which the Contract requires to be performed by independent testing entities, shall be contracted and paid for by the Owner. The Contractor shall schedule all required tests, approvals and inspections of the Work or other work related to the Project. The Contractor shall give proper notice to all required parties of such tests, approvals and inspections, if feasible, the Owner and Others may timely observe the tests at the normal place of testing. Unless otherwise required by the Contract Documents, required certificates of testing, approval or inspection shall be secured by the Contractor and promptly delivered to the Owner. Examples of such tests are the testing of cast-in-place concrete, foundation materials, soil compaction, pile installations, caisson bearings and steel framing connections. The Contractor shall promptly furnish, without additional charge, all reasonable facilities, labor and materials necessary and convenient for making such tests. Except as provided in (d) below, whenever such examination and testing finds defective materials, equipment or workmanship, the Contractor shall reimburse the Owner for the cost of reexamination and retesting. Although conducted by independent testing entities, the Owner will not contract and pay for tests or certifications of materials, manufactured products or assemblies which the Contract, codes, standards, etc., require to be tested and/or certified for compliance with industry standards such as Underwriters Laboratories, Factory Mutual or ASTM. If fees are charged for such tests and certifications, they shall be paid by the Contractor. The Contractor shall also pay for all inspections, tests, and certifications which the Contract specifically requires him to perform or to pay, together with any inspections and tests which he chooses to perform for his own purposes, but are not required by the Contract 7. Section 17 – SUPERINTENDENCE BY CONTRACTOR, shall be supplemented by adding the following: Replace Paragraph (a) with the following: (a) The Contractor shall have a competent foreman or superintendent, satisfactory to the Architect/Engineer and the Owner, on the Site at all times during the Time for Completion of the Work. The superintendent or foreman shall be familiar with and be able to read and understand the plans and specifications, and be capable of communicating orally and in writing with the Owner’s Project Manager and the Contractor’s workers. The Contractor shall Supplemental General Conditions Page 3 of 7 be responsible for all construction means, methods, techniques, sequences and procedures, for coordinating all portions of the Work under the Contract except where otherwise specified in the Contract Documents, and for all safety and worker health programs and practices. The Contractor shall notify the Owner, in writing, of any proposed change in superintendent, including the reason therefore, prior to making such change. 8. Section 19 – SCHEDULE OF THE WORK, shall be supplemented by adding the following: Replace Paragraph (a) (1) & (2) with the following: (1) For Contracts with a price of $250,000 or less, a bar graph schedule will satisfy the above requirement. The schedule shall indicate the estimated starting and completion dates for each major element of the work. See (b) below. (2) For Contracts with a price over $250,000, a Critical Path Method (CPM) schedule shall be utilized to control the planning and scheduling of the Work. The CPM schedule shall be the responsibility of the Contractor and shall be paid for by the Contractor. See (c) below. 9. Section 20 – SCHEDULE OF VALUES AND CERTIFICATE FOR PAYMENT, shall be supplemented by adding the following: Replace Paragraph (a) with the following: (a) Before submittal of the first partial payment request under the Contract, the Contractor shall prepare for review and approval of the Architect/Engineer and the Owner, a schedule of the estimated values using the Divisions of Construction as listed in the Project Manual Specifications. The Divisions will be further broken down into the following headings, which may result in divisions being used multiple times, as required in each heading: (1) SITEWORK a. b. c. d. e. f. g. h. i. Erosion and Sediment Control Demolition Earthwork Surfacing and Incidental Construction Water Distribution System Storm Sewer System Wastewater Piping Systems Chain Link Fence and Gates Seeding (2) DRIP IRRIGATION SYSTEM (3) PACKAGE WASTEWATER TREATMENT SYSTEM, including tanks. (4) CHEMICAL FEED SYSTEMS Supplemental General Conditions Page 4 of 7 (5) PRECAST CONCRETE BUILDING SYSTEM (6) CAST IN PLACE CONCRETE (7) ELECTRICAL (8) MOBILIZATION In addition to the divisions and headings in the abovementioned paragraph, the estimated values will be further broken down into Labor and Materials, so that the total of all the values equals the Contract Price. Where the total project has multiple parts or phases, the Contractor shall prepare appropriate schedules of values to facilitate reviews and justifications for payments. All requests for payment shall be made on the Schedule of Values and Certificate for Payment (Form AC-12). Succeeding pages may be on the Form AC-12 continuation sheets or a computerized spreadsheet which is in the same format and which contains the same information. 10. Section 23 – PLANS AND SPECIFICATIONS, shall be supplemented by adding the following paragraph: (i) Close-out and Operations and Maintenance Documents: Upon completion of the Work and prior to final payment, the Contractor shall deliver to the Architect/Engineer, two complete hard copy sets of the Close-out and Operations and Maintenance Documents as specified in the Project Manual Specifications. Additionally, the Contractor will provide two CDs or other acceptably formatted electronic copy of the abovementioned documents to accompany the hard copy versions. The electronic version will be organized with folders and appropriate hierarchy as to represent the hard copy versions. The documentation found on the electronic version will be in PDF format, or other acceptable format as directed by the Owner. 11. Section 38 – CHANGES IN THE WORK, shall be supplemented by adding the following paragraph: (4) By using Estimate for Change Order Forms GC-1, SC-1 and SS-1, respectively, the Contractor will present to the Owner, an accurate, itemized account of the cost of the change in the Work, including, but not limited to, the costs of labor, materials, equipment, and supplies; and to annotate a copy of the Project schedule to accurately show the status of the Work at the time this initial change order is issued, to show the start and finish of the changed Work, and the status of the Work when the changed Work is completed. A Change Order citing this subsection shall describe the parameters of the change in the Work, describe the cost items to be itemized and verified for payment, address the impact on the schedule for Substantial Completion, and state that a subsequent Change Order will be issued to incorporate the cost of the changed Work into the Contract Price and any change in the Contract Time for Completion or Supplemental General Conditions Page 5 of 7 Contract Completion Date. The Contractor shall sign the Change Order acknowledging he has been directed to proceed with the changed Work. Except as otherwise may be agreed to in writing by the Owner, such costs shall not exceed those prevailing for the trades or crafts, materials, and equipment in the locality of the Project, may include only those items listed as allowable in Subsection 38(e), and shall not include any of the costs listed as not allowable in Subsection 38(f). The Owner shall be permitted, on a daily basis, to verify such records and may require such additional records as are necessary to determine the cost of the change to the Work. Within fourteen (14) days of the conclusion of such ordered Work, the Contractor and the Owner shall arrive at a cost for the Change Order, based on the records kept and the Contractor’s allowance for overhead and profit as set forth in Subsections (d), (e) and (f) below, and such costs shall be incorporated into a Change Order which references the Change Order ordering the Work. If agreement on the cost of the changed Work cannot be reached within the fourteen (14) days allotted, the Contractor may file a claim for the disputed amount as provided for in Section 46. 12. Section 42 - DAMAGES FOR DELAY, EXTENSION OF TIME, shall be supplemented by adding the following paragraphs: (i) It is imperative that the Work in this contract be substantially completed not later than (date) to give time for the Owner to furnish and equip the facility and meet other contractual obligations. The Contractor represents and agrees that he has taken into account in his bid the requirements of the bid documents, the location, the time allowed for the Work, local conditions, availability of materials, equipment, and labor, and any other factors which may affect performance of the Work. The Contractor agrees and warrants that he will achieve substantial completion of the Work not later than (date) . (1) Assuming timely execution of the Contract with applicable Bonds, Notice to Proceed will be given to the Contractor no later than (date) . (j) Subject to the provisions of the General Conditions allowing for extension of time allowed for completion of the Work, if the work is not substantially completed by the specified date, the Contractor shall owe to the Owner, not as a penalty but as liquidated damages, the sum of One Thousand Dollars ($1,000.00) per day for each and every calendar day for delay in substantial completion of the Work beyond (date) . Likewise, if the Work is not finally completed by the specified date, the Contractor shall owe to the Owner, not as a penalty but as liquidated damages, the sum of hundred dollars ($ ) per day for each and every calendar day of delay in final completion of the Work. Supplemental General Conditions Page 6 of 7 (k) The Owner may withhold from the monthly Progress Payment, the current value of the liquidated damages. Failure of the Owner to withhold liquidated damages during ongoing operations that have exceeded the Contract Completion Date is not a waiver of the Owner’s entitlement to damages as set forth in the Contract Documents. (l) Final accounting of liquidated damages will be administered through a deduction in the final amount owed the Contractor, as reflected in the Cover Sheet of the Certificate of Payment Form AC-12. Supplemental General Conditions Page 7 of 7 SPECIAL CONDITIONS ALBEMARLE COUNTY PUBLIC SCHOOLS 1. Worker Standards of Conduct/Dress – Hard hats, safety shoes, appropriate shirts and pants are required at all times. Smoking is prohibited on school property. There is to be no contact or harassment of any kind between workers, teachers and students. Only the project superintendent may contact the school staff if necessary. Violence, Swearing, Drugs, Alcohol, Firearms and Weapons are prohibited on school property. Any workers violating these standards of conduct shall be ordered off the site and not allowed to return. 2. Workers shall wear identification indicating the company that employs them while working in an occupied school, even during summer months. 3. Drawings and/or Specifications – Any Additional Instructions by Architect/Owner to explain drawing and specifications shall be binding on Contractor. 4. The Contractor (or his designated sub-contractor) shall obtain and pay the fees for all permits necessary for the construction of the project, unless specifically stated otherwise. The Owner will pay for the County Building Permit fees, and the Contractor shall obtain the permits. The Owner will pay for water and sewer connection fees, and the contractor shall obtain the permit. The Contractor shall pay for the tapping fee whether done by himself or pay the Service Authority to make tap. Fees for all bonds (excluding erosion control bonds) will be the sole responsibility of the Contractor. It is the responsibility of the Contractor to determine which permits are necessary. The Owner will pay for the permanent connection to franchised utility companies, electric service, and gas service. The Contractor shall coordinate and schedule all permanent utility service work. Virginia Stormwater Management Program (VSMP) General Permit: Contractor to prepare stormwater pollution prevention plan, secure VSMP Phase 1 Land Clearing General Permit and Pay Permit Application Fee to Department of Environmental Quality (DEQ). Contact DEQ – Richmond for additional information. Telephone Number: (804) 698-4000. 5. Regarding asbestos work, the general contractor shall be responsible for submitting any required notices to all appropriate regulatory agencies, and shall do so within the required timeframe. 6. Contractor’s staging area, protective barriers and safety fencing, employee parking, loading access and stockpiling of soils shall be as shown on the plans or as approved by Owner. 7. Contractor’s staging area and general construction site shall be kept neat and clean so that grass is cut and debris and trash is removed on a weekly basis if not more frequently. School Special Conditions-June 2007 Page 1 of 3 8. Safe access to the designated areas adjacent to the construction area must be maintained at all times for pedestrians and maintenance vehicles. 9. Liquidated Damages: Shall be in accordance with the Supplementary General Conditions. 10. Section 01400 – General Requirements, Paragraph 1.8 Progress Meetings and County of Albemarle Construction Contract General Conditions, Section 24 Submittals are to include the following: 1) Bi-Monthly Job-Site meetings 2) The Contractor’s project superintendent shall provide the Architect and Owner with copies of his daily report on a weekly basis including manpower per trade, job progress, weather and activities. 11. Application for Payment and payments shall be delayed when project is not in compliance with Erosion Control Plan, permits, or any related instructions given by Owner. Lack of Project Cleanliness may also delay payment. Weekly broom cleaning required for interior renovations. 12. The Contractor shall coordinate all construction operations and deliveries with the school activity schedule. When school is in session, deliveries to the construction site shall not be allowed between the hours 8:00 a.m. and 4:00 p.m. 13. The Contractor shall allow for 5 days when work will be prohibited for student special testing in the school. These dates will be confirmed at the Pre-Construction meeting. 14. Contractors Work within the Existing and Functioning School Area shall be limited to when school is not in session (i.e. during summertime and/or after hours). Excessively noisy work or work producing noxious fumes adjacent to classrooms in session may also be subject to work after regular hours. 15. Hours of work will be limited for projects with exterior work areas, noisy loading or unloading, and work with close neighbors who could be adversely effected. 16. At the completion of the project and before the Final Application for Payment will be approved, Contractor shall provide the Owner written statement certifying that the work is asbestos free. 17. UL Labels are required on all electrical and mechanical equipment. If unlabeled equipment is delivered to the job site, Contractors shall remove and replace with properly labeled equipment or shall pay for UL field testing to properly label prior to payment being made such equipment. 18. Testing/Special Inspections - Owner shall obtain and pay for testing and special inspections services. The Contractor shall pay for any required re-testing due to School Special Conditions-June 2007 Page 2 of 3 failed initial tests. Special Inspectors instructions shall be binding on the Contractor. Contractor shall call the testing company designated by the Owner and coordinate any special inspections. Contractor shall provide the Special Inspector with any necessary equipment, such as ladders, scaffolding, etc. for inspection purposes. At the completion of the project and before the Final Application for Payment will be approved, all deficiencies on any special inspection reports, shall be remedied. 19. Building Inspections Department – The Contractor shall call for inspections in accordance with the local department’s procedures or by no later than 4 p.m. the day prior the inspection is requested. 20. Building security is the responsibility of the Contractor until final acceptance. 21. The Contractor shall provide approved, framed, operating and maintenance instruction, wiring diagrams and control diagrams as applicable: Drip Irrigation System Package Wastewater Treatment Plant Any other items or systems required but not specifically listed. 22. Constructor to provide comprehensive training and equipment demonstration for the Owner’s designated representatives and the Contractor shall schedule at least 2 weeks in advance for Owner’s coordination review and approval. 23. Cleaning during construction: Areas of work shall be cleaned broom clean at least weekly to minimize tracking dirt; Owners existing equipment and facility shall be protected from dust, splash or splatter and cleaned or replaced to return to preconstruction conditions. 24. Final Cleaning to be performed to the Owner’s satisfaction. If unsatisfactory cleaning is not remedied within 24 hour written notice to Contractor from Owner, Owner shall complete and deduct from Contractor’s final payment. *** END OF SPECIAL CONDITIONS *** School Special Conditions-June 2007 Page 3 of 3 CONTRACT BETWEEN OWNER AND CONTRACTOR This Contract dated this ____ day of ___________ , 20__, is between ______________ (“Owner”), and _______________________ (“Contractor”), and is binding among and between these parties as of the date of the Owner’s signature. RECITALS 1. The legal address for the Owner and for the Contractor and the addresses for delivery of Notices and other project documents are as follows: Owner: Attention: Address: City, State, Zip: Telephone: The County School Board of Albemarle County, Virginia Purchasing Office, Room 248 401 McIntire Road Charlottesville, Virginia 22902 (434) 296-5854 Contractor: Attention: Address: City, State, Zip: Telephone: FAX: Contractor’s Virginia License #: _______________ FEIN/SSN: __________ 2. The Project is identified as: Project Title: ___________________________________ IFB # General Project Description: The project is generally described as: The Project Title and Number indicated above are required to be shown for identification purposes on all project-related material and documents including, but not limited to, Notices, Change Orders, Submittals, Requests for Information, Requests for Quotes, Field Orders, minutes of meetings, correspondence, Schedule of Values and Certificate for Payment, test reports and related material. Form AC-9 (March 1998; Rev. Oct. 2001; Rev. Nov 2009) 3. After competitive sealed bidding pursuant to the Virginia Public Procurement Act, Contractor is awarded this Contract to perform the Work described by the Contract Documents for the above-described project (“the Project”). THEREFORE, in consideration of the Recitals set forth above, and good and valuable consideration as set forth below, the parties agree as follows: 1. STATEMENT OF WORK: The Contractor shall furnish all labor, equipment, and materials and perform all Work for the Project, including all work described in the Bid Form as Base Bid [and reference accepted alternates if applicable], in strict accordance with the Contract Documents. 2. CONTRACT DOCUMENTS: This Contract shall consist of the following: - this Contract Between Owner and Contractor; - the Bid Form submitted by the Contractor; - the County of Albemarle Construction Contract General Conditions, latest revision; - the Supplemental General Conditions, if any; - the Special Conditions attached to the Owner’s Invitation for Bids; - the Owner’s Project Plans and Specifications dated ________ ; and modifications shown as Addenda . All of these documents are incorporated herein by reference. 3. TIME FOR COMPLETION: The Work shall be commenced on a date to be specified in a written order of the Owner and shall be Substantially Completed within __ calendar days or not later than the Contract Completion Date which is ___________________ . The Work shall be finally completed within 30 days after the date of Substantial Completion of the Work. 4. COMPENSATION TO BE PAID TO THE CONTRACTOR: The Owner agrees to pay and the Contractor agrees to accept as just and adequate compensation for the performance of the Work in accordance with the Contract Documents the sum of _____ ($ ). This Contract is subject to annual funding by the Board of Supervisors of the County of Albemarle, Virginia, for services and work specified hereunder. In the event the Board of Supervisors fails to appropriate funds necessary to perform the services and work specified in this Contract and other contract documents, this Contract shall be deemed cancelled, with no penalty to the County, and of no effect, provided notice of such cancellation is given to the Contractor within thirty (30) days of the Board of Supervisors final approval of the annual County budget. In the event that this Contract is cancelled for the reasons set forth in this paragraph, the Contractor will be reimbursed for the value of all work performed or services rendered as of the date of cancellation in accordance with the General Conditions. Form AC-9 (March 1998; Rev. Oct. 2001; Rev. Nov 2009) 5. PAYMENTS: The procedures for establishing a Schedule of Values for the Work, for requesting monthly progress payments for Work in place, and for requesting payments for properly stored materials are stated in the General Conditions. Unless otherwise provided under the Contract Documents, interest on payments due the Contractor shall accrue at the rate of one percent per month. §2.2-4354(4) of the Code of Virginia. 6. CONTRACTUAL CLAIMS: Any contractual claims shall be submitted in accordance with the contractual dispute procedures set forth in Section 46 of the General Conditions and the supplemental instructions or procedures, if any, attached to this Contract. 7. NON-DISCRIMINATION: §2.2-4311 of the Code of Virginia applies to this contract (see Section 4 of the General Conditions). 8. IMMIGRATION REFORM AND CONTROL ACT OF 1986: §2.2-4311.1 of the Code of Virginia applies to this contract: Contractor does not, and shall not during the performance of the Contract for this project knowingly employ an unauthorized alien as defined in the federal Immigration Reform and Control Act of 1986. 9. PROHIBITION OF ALCOHOL AND OTHER DRUGS: §2.2-4312 of the Code of Virginia applies to this contract (see Section 5 of the General Conditions). IN WITNESS WHEREOF, the parties hereto on the day and year written below have executed this agreement in three (3) counterparts, each of which shall, without proof or accountancy for the other counterparts, be deemed an original thereof. CONTRACTOR OWNER By: By: (Signature in ink) (Date) (Signature in ink) (Date) Name: ____________________________________ Name: ___________________________ Title: Title: ATTEST __________________________________ ATTEST___________________________ (Signature) (Date) (Signature) (Date) Attachments: Bid Form submitted by Contractor Form AC-9 (March 1998; Rev. Oct. 2001; Rev. Nov 2009) POST BID MODIFICATION DATE: PROJECT TITLE: IFB NO.: OWNER: CONTRACTOR: As allowed by Section 12(c) of the Instructions to Bidders and by §2.2-4318, Code of Virginia, negotiations were conducted with the lowest responsive and responsible bidder, , hereinafter called the Contractor. The following clarifications, amendments, deletions, revisions, substitutions, and/or modifications to the Contract Documents were made along with corresponding adjustments in the Contractor’s bid amount for furnishing all labor and materials and performing all work necessary for construction of this project in accordance with the modified contract documents: Item Amount END OF POST BID MODIFICATION Form AC-9b (Aug. 1998, Rev. Oct. 2001) STANDARD PERFORMANCE BOND FOR CONSTRUCTION CONTRACTS KNOW ALL MEN BY THESE PRESENT: That __________________________________ , the Contractor (“Principal”) whose principal place of business is located at ___________________ ____________________________________and ________________________________(“Surety”) are held and firmly bound unto the County of Albemarle, Virginia, and/or The County School Board of Albemarle County, Virginia, the Owner (“Obligee”) in the amount of ____________________ ____________________________________Dollars ($ ), for the payment whereof Principal and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. WHEREAS, Principal has by written agreement dated _____________________ , _______, entered into a contract with Obligee for ________________________________________________________ which contract (the “Contract”) is by reference expressly made a part hereof; NOW THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if the Principal shall promptly and faithfully perform said Contract in strict conformity with the plans, specifications and conditions of the Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect. Provided, that any alterations which may be made in the terms of the Contract, or in the Work to be done under it, or the giving by the Obligee of any extension of the time for the performance of the Contract, or any other alterations, extensions or forbearance on the part of either or both of the Obligee or the Principal to the other shall not in any way release the Principal and the Surety, or either of them, their heirs, executors, administrators, successors or assigns from their liability hereunder, notice to the Surety of any such alterations, extension, or forbearance being hereby waived. No action shall be brought on this bond unless brought within one year after: (a) completion of the Contract and all Work thereunder, including expiration of all warranties and guarantees, or (b) discovery of the defect or breach of warranty or guarantee if the action be for such. The Surety represents to the Principal and to the Obligee that it is legally authorized to do business in the Commonwealth of Virginia. Signed and sealed this _________ day of Form AC-10 (February 1998) , . Page 1 of 2 PRINCIPAL BY: (Please sign above and print name below) TITLE: ADDRESS: PHONE: SURETY (Must be signed by a Virginia Resident Agent of Surety) BY: (Please sign above and print name below) ADDRESS: PHONE: BOND NO.: ADDRESS OF SURETY’S HOME OFFICE: Approved as to Form: County Attorney Form AC-10 (February 1998) Date Page 2 of 2 STANDARD LABOR AND MATERIAL PAYMENT BOND KNOW ALL MEN BY THESE PRESENT: That __________________________________ , the Contractor (“Principal”) whose principal place of business is located at ___________________ ____________________________________and ________________________________(“Surety”) are held and firmly bound unto the County of Albemarle, Virginia, and/or The County School Board of Albemarle County, Virginia, the Owner (“Obligee”) in the amount of ____________________ ____________________________________ Dollars ($ ), for the payment whereof Principal and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. WHEREAS, Principal has by written agreement dated _____________________ , _______ , entered into a contract with Obligee for ________________________________________________________ which contract (the “Contract”) is by reference expressly made a part hereof; NOW THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if the Principal shall promptly make payment to all claimants as hereinafter defined, for labor performed and material furnished in the prosecution of the Work provided for in the Contract, then this obligation shall be void; otherwise it shall remain in full force and effect, subject, however, to the following conditions. The Principal and Surety, jointly and severally, hereby agree with Obligee as follows: 1. A claimant is defined as one having a direct contract with the Principal or with a subcontractor of the Principal for labor, material, or both for use in the performance of the Contract. A “subcontractor” of the Principal, for the purposes of this bond only, includes not only those subcontractors having a direct contractual relationship with the Principal, but also any other contractor who undertakes to participate in the Work which the Principal is to perform under the aforesaid Contract, whether there are one or more intervening subcontractors contractually positioned between it and the Principal (for example, a subcontractor). “Labor” and “material” shall include, but not be limited to, public utility services and reasonable rentals of equipment, but only for periods when the equipment rented is actually used at the work site. 2. Subject to the provisions of paragraph 3, any claimant who has performed labor or furnished material in accordance with the Contract documents in the prosecution of the Work provided in the Contract, who has not been paid in full therefor before the expiration of ninety (90) days after the day on which such claimant performed the last of such labor or furnished the last of Form AC-10.1 (February 1998) Page 1 of 3 such materials for which he claims payment, may bring an action on this bond to recover any amount due him for such labor or material, and may prosecute such action to final judgment and have execution on the judgment. The Obligee need not be a party to such action and shall not be liable for the payment of any costs, fees or expenses of any such suit. 3. Any claimant who has a direct contractual relationship with any subcontractor of the Principal from whom the Principal has not required a subcontractor payment bond, but who has no contractual relationship, express or implied, with the Principal, may bring an action on this bond only if he has given written notice to the Principal within one hundred eighty (180) days from the day on which the claimant performed the last of the labor or furnished the last of the materials for which he claims payment, stating with substantial accuracy the amount claimed and the name of the person for whom the Work was performed or to whom the material was furnished. Notice to the Principal shall be served by registered or certified mail, postage prepaid, in an envelope addressed to the Principal at any place where his office is regularly maintained for the transaction of business. Claims for sums withheld as retainages with respect to labor performed or materials furnished shall not be subject to the time limitations stated in this paragraph 3. 4. No suit or action shall be commenced hereunder by any claimant; 5. a. Unless brought within one year after the day on which the person bringing such action last performed labor or last furnished or supplied materials, it being understood, however, that if any limitation embodied in this bond is prohibited by any law controlling the construction hereof, the limitation embodied within this bond shall be deemed to be amended so as to be equal to the minimum period of limitation permitted by such law. b. Other than in a Virginia court of competent jurisdiction, with venue as provided by statute, or in the United States District Court for the district in which the project, or any part thereof is situated. The amount of this bond shall be reduced by and to the extent of any payment or payments made in good faith hereunder. Signed and sealed this _________ day of Form AC-10.1 (February 1998) , . Page 2 of 3 PRINCIPAL BY: (Please sign above and print name below) TITLE: ADDRESS: PHONE: SURETY (Must be signed by a Virginia Resident Agent of Surety) BY: (Please sign above and print name below) ADDRESS: PHONE: BOND NO.: ADDRESS OF SURETY’S HOME OFFICE: Approved as to Form: County Attorney Form AC-10.1 (February 1998) Date Page 3 of 3 CONTRACT CHANGE ORDER Change Order Number: Date: PROJECT DESCRIPTION Project Title: 0 RFQ/Contract No.: 0 CHANG E DESCRI PTION TO: Gentlemen: Under your contract dated January 0, 1900 for work on the project shown above, you are hereby authorized to make the following changes: This Change Order will add to deduct from the Contract Price, in accordance with the Contract Documents, the sum of /100 dollars There will be an extension of days for contract completion. The contract completion date will now be January 0, 1900 . By signing this Change Order, the Contractor agrees to release and waive any and all claims related to this Change Order. (Failure to include a change for time shall waive any change to the time allowed by the Contract for completion of the Work unless the parties mutually agree in writing to postpone a determination of the change to time resulting from the Change Order. Such determination may not be postponed more than 45 days from the approval of this Change Order by the Owner.) CONTRACT COST SUMMARY (Show information on Contract Summary sheet) AMOUNT OF ORIGINAL CONTRACT $0.00 TOTAL ADDITIONS + $0.00 TOTAL DEDUCTIONS - $0.00 AMOUNT OF CONTRACT TO DATE = $0.00 CHANGE AUTHORIZATION Issued By: Architect/Engineer Approved By: Date Accepted By: Contractor Form AC-11 (May 2010) Date County of Albemarle, Virginia and/or The County School Board of Albemarle County, Virginia Date GENERAL CONTRACTOR ESTIMATE FOR CHANGE ORDER GC-1 DGS-30-200 (Rev. 09/04) Project Code: Agency: Project: General Contractor: Change Description: GENERAL CONTRACTOR DIRECT COSTS Scope Description Direct Labor Item No. Description Quantity Qty Units A B C D 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 Subtotal from Estimate Continuation Sheets 1.97 1.98 Subtotal (S/T) Direct Costs: Taxes/Insurance: 1.99 Total Direct Costs Direct Labor Hourly Wage Hours Total Direct Rate, Excl. Per Unit Labor Hours Taxes & Ins. E FICA, FUI, SUI, & Workmens' Comp. at SUBCONTRACT COSTS Item No. A Subcontractor Name (List totals from attached SC-1 forms) B Total Subcontract Costs G H=FxG $0.00 Material Cost Per Unit I Direct Equipment Total Material Cost Equipment Cost Per Unit J=CxI $0.00 K Total Cost C $0.00 Item No. Total Equipment Cost L=CxK $0.00 0.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subtotal Labor % of Item 1.97H = $0.00 Subtotal Mat'l $0.00 Sales Tax @ 5.3% $0.00 Subtotal Equip. $0.00 Sales Tax @ 5.3% $0.00 $0.00 Total Labor $0.00 Total Mat'l Total Equip. $0.00 $0.00 Submitted By SUMMARY 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.99 F=CxE 0.00 Direct Material Total Labor Cost 3.01 3.02 Description Total Direct Labor Cost Total Direct Material Cost Item 1.99H Item 1.99J Total Cost $0.00 3.03 3.04 3.05 3.06 3.07 3.08 3.09 3.10 Total Equipment Cost Item 1.99L Subtotal 3.01+3.02+3.03 Overhead and Profit 15% x Item 3.04 Subtotal 3.04+3.05 Subcontractor Cost Item 2.99 GC Markup on Subcontractor10% x Item 3.07 Subtotal 3.06+3.07+3.08 Additional Bond Cost $0.00 3.99 Total Change Order Cost $0.00 (3.09+3.10) $0.00 Name: Signature: $0.00 $0.00 T $0.00 $0.00 $0.00 $0.00 D i I have reviewed the costs proposed and find at them to be reasonable (as proposed) (as marked). $0.00 A/E Signature: tl ee SUPPLEMENTAL GENERAL CONDITIONS THE COUNTY OF ALBEMARLE and/or THE COUNTY SCHOOL BOARD OF ALBEMARLE COUNTY, VIRGINIA CONSTRUCTION CONTRACT GENERAL CONDITIONS (February 1998, Revised October 2001) are modified and supplemented as hereinafter described. 1. Section 1 – DEFINITIONS, shall be supplemented by adding the following: Replace Notice with the following: Notice: All written notices, including demands, instructions, claims, approvals and disapprovals, required or authorized under the Contract Documents. Any written notice by either party to the Contract shall be sufficiently given by any one or combination of the following, whichever shall first occur: (1) delivered by hand to the last known business address of the person to whom the notice is due; (2) delivered by hand to the person’s authorized agent, representative or officer wherever they may be found; or (3) enclosed in a postage prepaid envelope addressed to such last known business address and delivered to a United States Postal Service official or mailbox. Notice is effective upon such delivery. All notices to the Owner should be directed to the Project Manager. Notices transmitted by Facsimile (Fax) or Email are acceptable for the Project. Notices may be transmitted to the Fax number listed in the Contract and shall have a designated space for the Fax Notice recipient to acknowledge his receipt by authorized signature and date. The Fax Notice with authorized signature acknowledging receipt shall be Faxed back to the sender. Notices may be sent to the Email address(es) as provided by the A/E and the Project Manager. The Email acknowledging receipt shall be emailed back to the sender. The Faxed Notice and/or Email shall be effective on the date it is acknowledged by authorized signature or Email acknowledgement. All Faxed and Emailed Notices shall also be delivered by hard copy, which shall be effective upon delivery, as provided herein. Notice shall be effective upon the date of acknowledgment of the Faxed or Emailed Notice or the date of delivery, whichever occurs first. 2. Section 2 – CONTRACT DOCUMENTS, shall be supplemented by adding the following: Replace Paragraph (f) with the following: (f) 3. All correspondence, invoices, memoranda, submittals and other documents related to this Project whether generated by the Owner, the A/E, the Contractor or others should be identified at the beginning of the document with the Project Title shown in the Contract. Additional identification such as a job number, purchase order number or such may also be shown at the Owner’s option. Section 6 – TIME FOR COMPLETION, shall be supplemented by adding the Supplemental General Conditions Page 1 of 7 following: Replace Paragraph (3) with the following: (3) 4. All of the evidence and data supporting the request (including both historical data and the recordings at the Site during the time of delay) must be furnished to the Owner before any consideration will be given to the request. That supporting data shall be submitted by the end of the calendar month following the month for which the request is made. The submission must be made on the Cover Sheet of the Certificate of Payment Form AC12. A Change Order prepared in accordance with Change Order procedures specified in the Contract Documents must be submitted with a Weather Delay Rectification Form and supporting documentation as outlined in Section 6 – TIME FOR COMPLETION. Time extensions for adverse weather-related days granted by the Owner will extend the Contract Completion Date but will not include additional compensation to the Contractor. In no manner of interpretation will an adverse weatherrelated time extension be construed to be a compensable delay. Section 12 – “ALL RISK” BUILDER’S RISK INSURANCE Delete Paragraphs (a) and (b). (OR ) 5. Section 12 - “ALL RISK” BUILDER’S RISK INSURANCE Delete Paragraphs (a), (b) and (c) as written and in its place add the following: (a) The requirements of this section of the General Conditions for "all-risk" builders risk insurance on the full value of the entire building are waived for this project. The Owner maintains insurance on the existing building (including fire, vandalism and extended coverage). However, the Contractor shall provide “all risk” builders risk insurance for the Work in an amount equal to one hundred percent (100%) of the Contract Price for the Work. The loss, if any, is to be made adjustable with and payable to the Owner, in accordance with its interests, as they may appear. The Owner, its officers, employees and its agents, shall be named as an additional insured in any policy of insurance issued. Written evidence of the insurance shall be filed with the Owner no later than thirty (30) days following the award of the Contract. In the event of cancellation of this insurance, not less than thirty (30) days prior written notice must be sent to the Owner. A copy of the policy of insurance shall be given to the Owner upon demand. (b) Not used (c) The Contractor is responsible for providing any desired coverage for Contractor's or Subcontractors' buildings, equipment, materials, tools or supplies that are on-site. Supplemental General Conditions Page 2 of 7 [No change to paragraph (d) as written in the General Conditions.] 6. Section 16 - INSPECTION, shall be supplemented by adding the following: Replace Paragraph (b) with the following: (b) Site inspections, tests conducted on Site or tests of materials gathered on Site, which the Contract requires to be performed by independent testing entities, shall be contracted and paid for by the Owner. The Contractor shall schedule all required tests, approvals and inspections of the Work or other work related to the Project. The Contractor shall give proper notice to all required parties of such tests, approvals and inspections, if feasible, the Owner and Others may timely observe the tests at the normal place of testing. Unless otherwise required by the Contract Documents, required certificates of testing, approval or inspection shall be secured by the Contractor and promptly delivered to the Owner. Examples of such tests are the testing of cast-in-place concrete, foundation materials, soil compaction, pile installations, caisson bearings and steel framing connections. The Contractor shall promptly furnish, without additional charge, all reasonable facilities, labor and materials necessary and convenient for making such tests. Except as provided in (d) below, whenever such examination and testing finds defective materials, equipment or workmanship, the Contractor shall reimburse the Owner for the cost of reexamination and retesting. Although conducted by independent testing entities, the Owner will not contract and pay for tests or certifications of materials, manufactured products or assemblies which the Contract, codes, standards, etc., require to be tested and/or certified for compliance with industry standards such as Underwriters Laboratories, Factory Mutual or ASTM. If fees are charged for such tests and certifications, they shall be paid by the Contractor. The Contractor shall also pay for all inspections, tests, and certifications which the Contract specifically requires him to perform or to pay, together with any inspections and tests which he chooses to perform for his own purposes, but are not required by the Contract 7. Section 17 – SUPERINTENDENCE BY CONTRACTOR, shall be supplemented by adding the following: Replace Paragraph (a) with the following: (a) The Contractor shall have a competent foreman or superintendent, satisfactory to the Architect/Engineer and the Owner, on the Site at all times during the Time for Completion of the Work. The superintendent or foreman shall be familiar with and be able to read and understand the plans and specifications, and be capable of communicating orally and in writing with the Owner’s Project Manager and the Contractor’s workers. The Contractor shall be responsible for all construction means, methods, techniques, sequences and procedures, for coordinating all portions of the Work under the Contract except where otherwise specified in the Contract Documents, and for all safety and Supplemental General Conditions Page 3 of 7 worker health programs and practices. The Contractor shall notify the Owner, in writing, of any proposed change in superintendent, including the reason therefore, prior to making such change. 8. Section 19 – SCHEDULE OF THE WORK, shall be supplemented by adding the following: Replace Paragraph (a) (1) & (2) with the following: (1) For Contracts with a price of $250,000 or less, a bar graph schedule will satisfy the above requirement. The schedule shall indicate the estimated starting and completion dates for each major element of the work. See (b) below. (2) For Contracts with a price over $250,000, a Critical Path Method (CPM) schedule shall be utilized to control the planning and scheduling of the Work. The CPM schedule shall be the responsibility of the Contractor and shall be paid for by the Contractor. See (c) below. 9. Section 20 – SCHEDULE OF VALUES AND CERTIFICATE FOR PAYMENT, shall be supplemented by adding the following: Replace Paragraph (a) with the following: (a) Before submittal of the first partial payment request under the Contract, the Contractor shall prepare for review and approval of the Architect/Engineer and the Owner, a schedule of the estimated values using the Divisions of Construction as listed in the Project Manual Specifications. The Divisions will be further broken down into the following headings, which may result in divisions being used multiple times, as required in each heading: (1) SITEWORK a. b. c. d. e. f. g. h. i. Erosion and Sediment Control Demolition Earthwork Surfacing and Incidental Construction Water Distribution System Storm Sewer System Wastewater Piping Systems Chain Link Fence and Gates Seeding (2) DRIP IRRIGATION SYSTEM (3) PACKAGE WASTEWATER TREATMENT SYSTEM, including tanks. (4) CHEMICAL FEED SYSTEMS (5) PRECAST CONCRETE BUILDING SYSTEM (6) CAST IN PLACE CONCRETE Supplemental General Conditions Page 4 of 7 (7) ELECTRICAL (8) MOBILIZATION In addition to the divisions and headings in the abovementioned paragraph, the estimated values will be further broken down into Labor and Materials, so that the total of all the values equals the Contract Price. Where the total project has multiple parts or phases, the Contractor shall prepare appropriate schedules of values to facilitate reviews and justifications for payments. All requests for payment shall be made on the Schedule of Values and Certificate for Payment (Form AC-12). Succeeding pages may be on the Form AC-12 continuation sheets or a computerized spreadsheet which is in the same format and which contains the same information. 10. Section 23 – PLANS AND SPECIFICATIONS, shall be supplemented by adding the following paragraph: (i) Close-out and Operations and Maintenance Documents: Upon completion of the Work and prior to final payment, the Contractor shall deliver to the Architect/Engineer, two complete hard copy sets of the Close-out and Operations and Maintenance Documents as specified in the Project Manual Specifications. Additionally, the Contractor will provide two CDs or other acceptably formatted electronic copy of the abovementioned documents to accompany the hard copy versions. The electronic version will be organized with folders and appropriate hierarchy as to represent the hard copy versions. The documentation found on the electronic version will be in PDF format, or other acceptable format as directed by the Owner. 11. Section 38 – CHANGES IN THE WORK, shall be supplemented by adding the following paragraph: (4) By using Estimate for Change Order Forms GC-1, SC-1 and SS-1, respectively, the Contractor will present to the Owner, an accurate, itemized account of the cost of the change in the Work, including, but not limited to, the costs of labor, materials, equipment, and supplies; and to annotate a copy of the Project schedule to accurately show the status of the Work at the time this initial change order is issued, to show the start and finish of the changed Work, and the status of the Work when the changed Work is completed. A Change Order citing this subsection shall describe the parameters of the change in the Work, describe the cost items to be itemized and verified for payment, address the impact on the schedule for Substantial Completion, and state that a subsequent Change Order will be issued to incorporate the cost of the changed Work into the Contract Price and any change in the Contract Time for Completion or Contract Completion Date. The Contractor shall sign the Change Order acknowledging he has been directed to proceed with the changed Work. Supplemental General Conditions Page 5 of 7 Except as otherwise may be agreed to in writing by the Owner, such costs shall not exceed those prevailing for the trades or crafts, materials, and equipment in the locality of the Project, may include only those items listed as allowable in Subsection 38(e), and shall not include any of the costs listed as not allowable in Subsection 38(f). The Owner shall be permitted, on a daily basis, to verify such records and may require such additional records as are necessary to determine the cost of the change to the Work. Within fourteen (14) days of the conclusion of such ordered Work, the Contractor and the Owner shall arrive at a cost for the Change Order, based on the records kept and the Contractor’s allowance for overhead and profit as set forth in Subsections (d), (e) and (f) below, and such costs shall be incorporated into a Change Order which references the Change Order ordering the Work. If agreement on the cost of the changed Work cannot be reached within the fourteen (14) days allotted, the Contractor may file a claim for the disputed amount as provided for in Section 46. 12. Section 42 - DAMAGES FOR DELAY, EXTENSION OF TIME, shall be supplemented by adding the following paragraphs: (i) It is imperative that the Work in this contract be substantially completed not later than (date) to give time for the Owner to furnish and equip the facility and meet other contractual obligations. The Contractor represents and agrees that he has taken into account in his bid the requirements of the bid documents, the location, the time allowed for the Work, local conditions, availability of materials, equipment, and labor, and any other factors which may affect performance of the Work. The Contractor agrees and warrants that he will achieve substantial completion of the Work not later than (date) . (1) Assuming timely execution of the Contract with applicable Bonds, Notice to Proceed will be given to the Contractor no later than (date) . (j) Subject to the provisions of the General Conditions allowing for extension of time allowed for completion of the Work, if the work is not substantially completed by the specified date, the Contractor shall owe to the Owner, not as a penalty but as liquidated damages, the sum of One Thousand Dollars ($1,000.00) per day for each and every calendar day for delay in substantial completion of the Work beyond (date) . Likewise, if the Work is not finally completed by the specified date, the Contractor shall owe to the Owner, not as a penalty but as liquidated damages, the sum of hundred dollars ($ ) per day for each and every calendar day of delay in final completion of the Work. (k) The Owner may withhold from the monthly Progress Payment, the current value of the liquidated damages. Failure of the Owner to withhold liquidated damages during ongoing operations that have exceeded the Contract Supplemental General Conditions Page 6 of 7 Completion Date is not a waiver of the Owner’s entitlement to damages as set forth in the Contract Documents. (l) Final accounting of liquidated damages will be administered through a deduction in the final amount owed the Contractor, as reflected in the Cover Sheet of the Certificate of Payment Form AC-12. Supplemental General Conditions Page 7 of 7 SUB-SUBCONTRACTOR ESTIMATE FOR CHANGE ORDER SS-1 DGS-30-208 (Rev. 09/04) Project Code: Agency: Project: General Contractor: Subcontractor: Sub-Subcontractor: Sub-Subcontractor Trade: Change Description: SUB-SUBCONTRACTOR DIRECT COSTS Scope Description Item No. Description A B Direct Labor Quantity Qty Units Direct Labor Hours Per Unit C D E Total Hourly Wage Direct Labor Rate, Excl. Labor Hours Taxes & Ins. F=CxE G Direct Material Total Labor Cost H=FxG Material Cost Per Unit I Total Material Cost J=CxI Direct Equipment Equipment Cost Per Unit Total Equipment Cost K L=CxK 1.01 1.02 0.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 1.03 1.04 0.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 1.05 1.06 0.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 1.07 1.08 0.00 $0.00 $0.00 $0.00 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 1.09 Subtotal from Estimate Continuation Sheets 1.97 1.98 Subtotal (S/T) Direct Costs: Taxes/Insurance: 1.99 Total Direct Costs FICA, FUI, SUI, & Workmens' Comp. at Subtotal Labor % of Item 1.97H = $0.00 $0.00 Subtotal Mat'l $0.00 $0.00 Subtotal Equip. Sales Tax @ 5% Sales Tax @ 5% $0.00 $0.00 Total Labor $0.00 Total Mat'l $0.00 Total Equip. $0.00 Submitted By SUMMARY Item No. Description 3.01 3.02 3.03 Total Direct Labor Cost Total Direct Material Cost Total Equipment Cost 3.04 3.05 Subtotal Overhead and Profit 3.99 Total Sub-Subcontractor Total Cost Item 1.99H $0.00 Item 1.99J $0.00 Item 1.99L $0.00 3.01+3.02+3.03 $0.00 15% x Item 3.04 $0.00 $0.00 Name: Signature: Title: Date: SCHEDULE OF VALUES FORM AC-12 PART A SUMMARY AND CERTIFICATION PAYMENT REQUEST NO. and 1 PERIOD BEGINNING DATE: 01/00/1900 PERIOD ENDING DATE: 01/00/1900 CERTIFICATE FOR PAYMENT IFB NUMBER: 0 OWNER NAME: County of Albemarle, Virginia and/or The County School Board of Albemarle County, Virginia PROJECT TITLE: 0 VALUE OF WORK COMPLETED PREVIOUS VALUE TO DATE TOTAL VALUE A Original Contract Line Items (from AC-12, PART B) $ $ Approved Change Orders (from AC-12, PART C) $ ADJUSTED CONTRACT TOTAL Retainage Retainage Percentage: 5.0% VALUE THIS REPORT B - NET REQUISTION AMOUNT C CURRENT VALUE TO DATE PERCENT COMPLETE D=B+C E=D/A $ $ $ $ - $ $ $ $ - $ $ $ $ - $ - $ - $ - Amount Requested CONTRACTOR CERTIFICATION The undersigned Contractor requests of the foregoing Schedule of Values, and Schedule of Values is accurate and correct; accordance with the Contract Documents; under this Contract have been applied incurred in connection with Work covered (4) title to all materials and equipment in said Work, will pass to Owner at time encumbrances (except such materials payment of that portion of the contract represents and warrants to the (2) the Work covered by this (3) all previous progress payments to discharge in full (except for allowable by prior Certificates for Payment for which payment is requested in of payment free and clear of all and equipment which are covered price shown Owner that: (1) Certificate has received from retainage) ( N/A for Payment this Certificate, liens, claims, security by a Bond previously on the last line the data shown on the been completed in Owner on account of Work done all obligations of Contractor No. 1 ) ; whether or not incorporated interests and accepted by Owner). Contractor: 0 FEIN #: 0 By: Date: January 0, 1900 signature Typed Name: 0 ARCHITECT/ENGINEER CERTIFICATION This is to certify that, in accordance with the the terms of a contract for IFB/Contract Number executed day of , , by and between, , the Contractor, and the County of Albemarle, Virginia the and/or The County School Board of Albemarle County, Virginia, the Contractor the amount of Owner, for work at , there is due to No Dollars and No Cents $.00 Architect/Engineer: By: signature printed name date OWNER ACTION Recommended for Payment: Form AC-12 (May 2010) Project Manager Date 0% 0% 0% Original Contract Line Items Page 1 of 1 SCHEDULE OF VALUES AND CERTIFICATE FOR PAYMENT FORM AC-12 RFQ NUMBER: PART B ORIGINAL CONTRACT LINE ITEMS ITEM NO. Date Printed: 3/19/2014 PAYMENT REQUEST NO. 0 OWNER NAME: County of Albemarle, Virginia and/or The County School Board of Albemarle County, Virginia PROJECT TITLE: 0 ITEM DESCRIPTION VALUE OF WORK COMPLETED PREVIOUS VALUE CURRENT VALUE THIS VALUE TO DATE REPORT TO DATE TOTAL VALUE PERCENT COMPLETE $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% Do not insert rows below this point ! $ - $ - $ - $ - 0% TOTAL ORIGINAL CONTRACT $ - $ - $ - $ - 0% PERIOD BEGINNING DATE: PERIOD ENDING DATE: NOTES / COMMENTS 1 01/00/1900 01/00/1900 Approved Change Orders Page 1 of 1 SCHEDULE OF VALUES AND CERTIFICATE FOR PAYMENT FORM AC-12 PART C CONSTRUCTION CHANGE ORDERS CHNG ORD. NO. Date Printed: 3/19/2014 PROJECT CODE: 0 AGENCY NAME: County of Albemarle, Virginia and/or The County School Board of Albemarle County, Virginia PROJECT TITLE: 0 $ $ - VALUE OF WORK COMPLETED PREVIOUS VALUE CURRENT VALUE THIS VALUE TO DATE REPORT TO DATE $ $ $ $ $ $ - $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% $ - $ - $ - $ - 0% Do not insert rows below this point ! $ - $ - $ - $ - 0% ITEM DESCRIPTION TOTAL APPROVED CHANGE ORDERS TOTAL VALUE $ - $ - $ - $ - PERCENT COMPLETE 0% 0% 0% PAYMENT REQUEST NO. PERIOD BEGINNING DATE: PERIOD ENDING DATE: NOTES / COMMENTS 1 01/00/1900 01/00/1900 AFFIDAVIT OF PAYMENT OF CLAIMS By: This day _______________________________________________ personally appeared before me, ____________________________________________ , a Notary Public in and for the City/County of ___________________________ , ________________________ and, being by me first duly sworn, states that all subcontractors and suppliers of labor and materials have been paid all sums due them for work performed or materials furnished in the performance of the Contract between The County School Board of Albemarle County, Virginia, Owner and ____________________________ , Contractor, dated __________________ , 20____, for the construction of _______________________________________________________________ or arrangements have been made by the Contractor satisfactory to such subcontractors and suppliers with respect to payments of such sums as may be due them by the Contractor. (Contractor Name) By: ________________________________________ Print Name: ________________________________________ Title: ________________________________________ Subscribed and sworn to before me this __________ day of____________________ , 20 My commission expires on the day of _____________________, 20 ____ . Notary Registration #: ______________________ Notary Public Form AC-13 (May 2010) . ARCHITECT/ENGINEER’S CERTIFICATE OF SUBSTANTIAL COMPLETION Date: _______________________________ The County School Board of Albemarle County, Virginia c/o Building Services Department 2751 Hydraulic Road Charlottesville, Virginia 22901 Project Title: ____________________________________________________________ RFQ/Contract No.: __________________________ In accordance with the requirements of the Contract Between Owner and Architect/Engineer and based upon the knowledge gained in the performance of the architectural/engineering services provided in said Contract and the reports of the Owner’s Inspection and Testing entities, the undersigned Architect/Engineer states that the following portions of the project named above are substantially complete in accordance with the requirements of the Contract Documents and are recommended for use of their intended purpose (indicate portions which are ready for use and, if applicable, occupancy): All applicable tests, certificates and regulatory inspections required by the Contract Documents and any local, state or federal regulations have been performed with respect to the substantially completed portions of the project and the Owner has been provided with a copy of each report, except for the following: A tentative list of unfinished Work and defective Work, referred to as the “punch list,” is attached hereto. The list may not be all-inclusive, and the failure to include an item in it does not alter the responsibility of the Contractor to complete all the Work in accordance with the Contract Documents. The items in the tentative list shall be completed or corrected by the Contractor within ______ days of the above date of Substantial Completion. (A/E Firm Name) By: ____________________________________________ Print Name: _____________________________________________ Title: Attachment: Punch List Form AC-13.1a (June 2010) CERTIFICATE OF COMPLETION BY ARCHITECT/ENGINEER Date: The County School Board of Albemarle County, Virginia c/o Building Services Department 2751 Hydraulic Road Charlottesville, Virginia 22901 Project Title: _________________________________________________________________ RFQ/Contract No.: ________________________ In accordance with the requirements of the Contract Between the Owner and the Architect/Engineer for Professional Services and based upon the knowledge gained in the performance of the services required in said Agreement, the undersigned hereby states that the above named project was fully completed in accordance with the requirements of the Contract Documents on , . (Month) (Day) (Year) All applicable tests, certificates and regulatory inspections required by the Contract Documents and any local, state or federal regulations have been performed and the Owner has been provided with a copy of each report. Final as-built drawings have been prepared by the Architect/Engineer and submitted to the Owner in accordance with the requirements of the Contract Documents. The Owner has been provided with a copy of all warranties and guarantees, including the starting date(s) of all warranties and guarantees, written and unwritten, required by the Contract Documents. (A/E Firm Name) By: ________________________________________ Print Name: ________________________________________ Title: ________________________________________ Form AC-13.1 (June 2010) CERTIFICATE OF PARTIAL OR SUBSTANTIAL COMPLETION BY CONTRACTOR Date: The County School Board of Albemarle County, Virginia c/o Building Services Department 2751 Hydraulic Road Charlottesville, Virginia 22901 Project Title: ____________________________________________________________ RFQ/Contract No.: __________________________ In accordance with the requirements of the Agreement between the Owner and the Contractor, the undersigned Contractor hereby states that portions of the above named project are substantially completed in accordance with the requirements of the Contract Documents as modified by approved change orders. Those portions of the project now substantially complete are: All applicable tests, certificates and regulatory inspections required by the Contract Documents and any local, state or federal regulations have been performed with respect to the substantially completed portions of the project and the Owner has been provided with a copy of each report. As-built marked up prints of the substantially completed portions of the project have been provided to the Architect/Engineer as required by the Contract Documents. The Owner has been provided with a copy of all warranties and guarantees, including the starting date(s) of all warranties and guarantees, written and unwritten, required by the Contract Documents with respect to the completed portions of the project, except as follows: All training, operating instructions and maintenance manuals required by the Contract Documents have been provided to the Owner, except as follows: This certificate does not constitute an acceptance of Work not in accordance with the Contract Documents nor is it a release of CONTRACTOR’S obligation to complete the Work in accordance with the Contract Documents. (Contractor Name) By: ____________________________________________ Print Name: ____________________________________________ Title: Form AC-13.2a (June 2010) CERTIFICATE OF COMPLETION BY CONTRACTOR Date: The County School Board of Albemarle County, Virginia c/o Building Services Department 2751 Hydralic Road Charlottesville, Virginia 22901 Project Title: _________________________________________________________________ RFQ/Contract No.: _______________________ In accordance with the requirements of the Contract Between Owner and Contractor (Form AC9) the undersigned Contractor hereby states that the above named project has been fully completed in accordance with the requirements of the Contract Documents as modified by approved change orders. All applicable tests, certificates and regulatory inspections required by the Contract Documents and any local, state or federal regulations have been performed with respect to the completed project and the Owner has been provided with a copy of each report. As-built marked up prints of the completed project have been provided to the Architect/Engineer as required by the Contract Documents. The Owner has been provided with a copy of all warranties and guarantees, including the starting date(s) of all warranties and guarantees, written and unwritten, required by the Contract Documents. All training, operating instructions and maintenance manuals required by the Contract Documents have been provided to the Owner. (Contractor Name) B y: Print Name: Title: Copy: Architect/Engineer Form AC-13.2 (June 2010) ADVERSE WEATHER DAY RECTIFICATION FORM PROJECT TITLE ANTICIPATED w EA 7714R.:DAys: ADVERSE. January MFebrilafy, ay Jljne. March July A ugeA September October; November MpNTNLY WEATHER'DAYS. IMPACT •i ADVERSE.. Atf August 6: 14 - 12 Febriia'6i March A011' May 12: 14 6 8: 6 July September October November December; Jtirie 14 6 January .!7 May 12 6, 5 5 March CUMULATIVE ' .RECTIFICATION 6: January .D,OCe-ntOr: June MONTHLY 12 1: “ J ul y September October November 8 5 Decerriber 6 Page 1 of 2 8 0 6 12 Section 01400 General Requirements 1 General 1.1 Summary of Work 1.1.1 The work covered under this contract comprises the furnishing of all labor, materials, equipment, tools and services and the installation and construction of all items, and the performance of all work necessary to complete the work shown or called for on the drawings and/or this project manual. 1.1.2 All units under this Contract shall be operable, shall be installed as designed, and shall conform to the manufacturer’s specifications for the particular application. 1.2 Contractor Use of Premises 1.2.1 The Contractor shall assume full responsibility for protection and safekeeping of products stored on or off premises. 1.2.2 The Contractor shall coordinate use of premises with the Owner and Engineer, and remove stored products that interfere with the operations of the Owner or other contractors. 1.2.3 The Contractor shall obtain and pay for all additional storage or work areas needed for operations under this Contract. These areas shall be subject to the same conditions as described for the Owner’s property. 1.3 Permits – See Special Conditions 1.4 Construction and Scheduling Sequence 1.4.1 The existing wastewater treatment facilities shall remain in full operation during the construction period. The existing treatment facilities consist of a septic tank, dosing tank and subsurface soil absorption system. In addition, wastewater generated by Simpson Park discharges into the existing septic tank via a reported 1-1/2-inch PVC force main. Phases of the construction which involve the temporary interruption of essential services and demolition of existing items shall be scheduled in consultation with the Owner or his representative, shall not be of longer duration than essential to accomplish the purpose for such interruptions, and shall be coordinated to give the Owner the ability to maintain wastewater service. Liaison with the Owner in these matters is a salient feature of this contract. 1.4.2 Provide a written construction schedule and plan which describes in detail each major task and operation which will interfere with any existing system, equipment, or operation. The plan shall describe the sequence and proposed WW Associates Project No. 213003.05 01400/1 method of accomplishing each task and the proposed schedule for interruptions. 1.4.3 All construction activities shall be performed inside right of ways/limits of construction/limits of clearing and grading designated for this project. Laydown areas for this project shall be on-site and agreed upon by the Owner. Coordination and scheduling of construction activities with the Owner is a salient feature of this contract. 1.4.4 Provide temporary bypass pumping and piping, and temporary electrical service as required to maintain the existing wastewater treatment operations. 1.4.5 Additional contract requirements for the project are summarized as follows: 1.4.5.1 The Contractor shall construct new electrical supply from existing panel “G” inside existing school building and extend to new treatment building. A maximum outage of 4 hours will be allowed for this activity, if required. 1.4.5.2 Test and start up all structures, equipment, piping, and unit processes at the new WWTP as specified in this project manual. Perform leak testing for all wastewater-retention structures for new WWTP equipment with potable water. 1.4.5.3 Provide sufficient seed sludge from an existing WWTP with similar unit processes (activated sludge with nitrification and denitrification) to start biological processes at the new WWTP. Provide dry soda ash and MicroC1000 carbon for chemical feed system startup as specified in Section 11600 – Chemical Feed Equipment. 1.4.5.4 Once the new WWTP is fully functional and operable, divert wastewater to the new WWTP with a nighttime outage. Once wastewater is diverted to the new WWTP, the Contractor shall abandon the septic tank and dosing siphon. Remove wastewater and solids from septic tank and dosing siphon and dispose of these wastes at an approved facility. Tanks shall be abandoned in accordance with VDH Regulations. Fill tank and dosing siphon tank with sand or gravel. Disconnect and plug piping. 1.4.5.5 Comply with all rules and regulations required by the County of Albemarle School Board. The Contractor may be requested not to work during certain school activities and events. 1.4.5.6 All work associated with the existing school site, except for septic tank and dosing siphon demolition, shall be complete by August 8, 2014. This includes seeding the school site. WW Associates Project No. 213003.05 01400/2 1.4.5.7 5-day performance test shall be performed with wastewater. 1.5 Work Restrictions 1.5.1 Occupancy: If the Owner elects to operate any of the wastewater treatment plant improvements under partial utilization, prior to the project’s final acceptance, neither WW Associates nor the Contractor shall be held responsible for the safety or well being of those occupants beyond the normal care and practice of the construction industry. 1.5.2 Normal working hours for the Contractor shall be 8:00 A.M. to 5:00 P.M., Monday through Friday, excluding state and federal holidays, unless otherwise approved by the Owner and WW Associates. 1.6 Contract Modification Procedures 1.6.1 Change Orders: No amount, in part or in whole, of a change order shall be included in a requisition for payment by the Contractor until the change order has been executed and copies of the change order have been distributed to the Owner and Contractor. 1.6.2 Work Orders: A work order is a device which enables the Owner to promptly order changes in the work which may involve changes in cost or contract time, or both pending preparation and execution of a formal change order. 1.6.3 Request for Change Order Proposal: The Owner may request the Contractor to submit a change order proposal for changes in contract work. The Contractor shall submit the proposal in accordance with contract requirements within 3 days of a request by the Engineer or Owner. The Owner may issue to the Contractor a work order authorizing the required changes for an additional amount not to exceed, or a deduction of not less than the amount shown in the work order. If the Contractor is not in agreement with the amount stipulated in the work order, he shall, within a reasonable time after the issue date of the order, submit to WW Associates an equitable proposal and develop with the Owner a mutually acceptable price for the required change in work. 1.6.4 The Contractor may initiate changes by submitting a written notice to the Engineer containing: 1.6.4.1 Description of the proposed changes. 1.6.4.2 Statement of the reason for making the changes. 1.6.4.3 Statement of the effect on the Contract Sum and the Contract Time. 1.6.4.4 Statement of the effect on the Work of separate Contractors. WW Associates Project No. 213003.05 01400/3 1.6.4.5 Documentation supporting any change in Contract Sum or Contract Time, as appropriate. 1.7 Payment Procedures 1.7.1 Applications and Certificates for Payment: The form of each application for payment shall be AIA Document G702 entitled, “Application and Certificate for Payment” accompanied by “Continuation Sheet,” AIA Document G703. Each application for payment by the Contractor, excluding the first, shall be accompanied by a “Contractor’s Affidavit of Payment of Debts and Claims,” AIA Document G706, and “Contractor’s Affidavit of Release of Liens,” AIA Document G706A. Each application shall be submitted on forms, copies of which are included in this project manual. Payment for stored material delivered but not incorporated in the work will be the invoiced amount only. Submit application invoices with application for payment. 1.7.2 Upon recommendation by WW Associates of the Contractor’s request for partial payment, the Owner shall pay to the Contractor 95 percent of the total amount due and the Owner shall retain 5 percent of the amount due until final completion and acceptance of all work covered by the contract. 1.7.3 Schedule of Values: Submit complete schedule of values at least 10 days prior to first application for payment. 1.8 Project Meetings 1.8.1 Preconstruction conferences with the Contractor will be held after the effective date of the agreement. 1.8.2 Progress Meetings: Each month, the Contractor, Engineer, and the Owner shall hold a progress meeting to review progress to date and to resolve all questions for the upcoming month. 1.9 Progress Schedules: Submit a detailed construction schedule prior to the preconstruction conference. Revise the schedule prior to each progress meeting. Construction schedule shall be in a form that will clearly show the proposed degree of completeness of each aspect of the construction throughout the life of the contract. CPM schedule shall be provided in accord with the County of Albemarle Construction Contract General Conditions Paragraph 19(c). 1.10 Submittal Procedures 1.10.1 Shop Drawings, Product Data, and Samples: Prior to the preconstruction conference, prepare a submittal schedule satisfactory to WW Associates fixing the dates for submission of shop drawings, product data, samples, and the like and update this schedule at each progress meeting to reflect the status of each submittal item. WW Associates Project No. 213003.05 01400/4 1.10.1.1 Submit six copies of all shop drawings. 1.10.1.2 A maximum of two marked copies will be returned to the Contractor. 1.10.1.3 Submit shop drawings, product data, samples, and the like as required by applicable specification sections. 1.10.1.4 Identify each item submitted using applicable specification section number and paragraph reference or drawing reference. 1.10.1.5 Shop drawings shall be approved by the Contractor and those subcontractors whose work is associated with the subject equipment as being in accordance with the contract documents prior to submission. 1.10.1.6 Failure to comply with these requirements will result in the submittal being returned unprocessed. 1.10.2 The Engineer’s approval of Contractor’s shop drawings will be general and shall not relieve the Contractor from the responsibility for adherence to the Contract, nor shall it relieve him of the responsibility for any errors that may exist. Where such errors or omissions are discovered later, they shall be made good by the Contractor, irrespective of any approval by the Engineer. 1.11 Quality Control 1.11.1 Testing Laboratory Services: The Owner will employ and pay for the services of an independent testing laboratory to perform testing specified to be done by an independent testing laboratory, unless specifically stated otherwise in other sections of the specifications. Employment of the laboratory by the Owner shall in no way relieve the Contractor’s obligations to perform the work of the contract. 1.11 Temporary Utilities 1.11.1 Temporary Electricity: The Contractor shall make all necessary arrangements for obtaining temporary electric power for construction purposes. No separate payment for electric power for construction purposes or testing other than the payment included in the contract lump sum or unit prices will be allowed. Fees charged by the power company for permanent electrical service will be paid by the Owner. 1.11.2 Temporary Water shall be the responsibility of the Contractors. The school’s potable water supply is not to be used. WW Associates Project No. 213003.05 01400/5 1.11.3 Temporary Sanitary Facilities: The Contractor shall provide and maintain in a neat and sanitary condition such accommodations for the use of his employees as will comply with laws and regulations. 1.12 Temporary Controls 1.12.1 Construction Cleaning: The Contractor shall clean daily all areas under construction to ensure minimum interference with roads, streets, sidewalks, and access of School personnel. 1.12.2 Erosion and Sediment Control: These controls shall be in coordination with the appropriate drawings and any requirements of the local authority. 1.12.3 Dust Control: Contractor shall ensure that dust is held to a minimum throughout the length of the project through the application of moisture where applicable. 1.13 Vehicular Access and Parking 1.13.1 Parking and Laydown Areas: The location of Contractor parking and laydown areas shall be as agreed upon by the Owner and the Engineer. The Contractor shall obtain approval from the Owner in advance for proposed parking and laydown areas. Provide gravel in the laydown area and comply with the latest edition of Virginia Erosion and Sediment Control Handbook. 1.14 E-Mail Address: The Contractor shall provide an e-mail address to allow the Owner and the Engineer to correspond with the Contractor’s project manager during the construction period. 1.15 Product Requirements 1.15.1 Quality of Material and Equipment Incorporated into the Work: 1.15.1.1 Design, fabricate and assemble in accordance with the best engineering and shop practices. 1.15.1.2 Manufacture like parts of duplicate units to standard sizes and gauges, to be interchangeable. 1.15.1.3 Two or more items of the same kind shall be identical, by the same manufacturer. 1.15.1.4 Products shall be suitable for services conditions. 1.15.1.5 Equipment capacities, sizes, and dimensions shown or specified shall be adhered to unless variations are specifically approved in writing. WW Associates Project No. 213003.05 01400/6 1.15.2 Except as specifically indicated or specified, materials and equipment removed from the existing structure shall not be used in the completed work. 1.15.3 For material and equipment specifically indicated or specified to be reused in the work: 1.15.3.1 Use special care in removal, handling, storage, and reinstallation to assure proper function in the completed work. 1.15.3.2 Arrange for transportation, storage, and handling of products, which require off-site storage, restoration, or renovation. Pay all costs for such work. 1.15.4 Manufacturer’s Instructions 1.15.4.1 When contract documents require that installation of work shall comply with manufacturer’s printed instructions, obtain and distribute copies of such instructions to parties involved in the installation, including two copies to WW Associates. 1.15.4.2 Maintain one set of complete instructions at the job site during installation and until completion. 1.15.4.3 Handle, install, connect, clean, condition, and adjust products in accordance with such instructions and in conformity with specified requirements. 1.15.5 Transportation and Handling of Materials 1.15.5.1 Arrange deliveries of products in accordance with construction schedules. Coordinate to avoid conflict with work and conditions at the site. 1.15.5.2 Deliver products in undamaged condition, in manufacturer’s original containers or packaging, with identifying labels intact and legible. 1.15.5.3 Immediately on delivery, inspect shipments to assure compliance with requirements of contract documents and approved submittals, and that products are properly protected and undamaged. 1.15.6 Storage and Protection 1.15.6.1 Store products in accordance with manufacturer’s instructions, with seals and labels intact and legible. 1.15.6.2 Store products subject to damage by the elements in weathertight enclosures. WW Associates Project No. 213003.05 01400/7 1.15.6.3 Maintain temperature and humidity within the ranges required by manufacturer’s instructions. 1.15.6.4 Exterior Storage 1.15.6.4.1 Store fabricated products above the ground, on blocking or skids; prevent soiling or staining; cover products, which are subject to deterioration with impervious sheet coverings; and provide adequate ventilation to avoid condensation. 1.15.6.4.2 Store loose granular materials in a well-drained area on solid surfaces to prevent mixing with foreign matter. 1.15.6.4.3 Protection after Installation: Provide substantial coverings as necessary to protect installed products from damage from traffic and subsequent construction operations. Remove when no longer needed. 1.16 Lines and Grades 1.16.1 The Contractor shall include $7,000 in Base Bid to be provided as payment for the initial construction stakeout provided by WW Associates Certified Land Surveyor. Should the Contractor disturb the initial stakeout, restaking will be provided on an hourly rate to the Contractor by WW Associates. Stakeout services for the Base Bid will be as follows: Stake limits of clearing as required Stake sediment trap and stormwater management facilities Provide stakeout to rough grade site Stake storm structures and provide two point offsets Stake sanitary sewer and sanitary manholes and provide two point offsets Stake waterline and fittings and provide two point offsets Stake corners of treatment structures and new treatment building and provide offsets Stake Drip Dispersal Fields Stake limits of new gravel paving and access road Stake corners of fencing Stake TMP 128A2-18 and 22 property line (prior to construction) 1.17 Starting of Systems 1.17.1 The Contractor shall initially start up and place all piping systems installed by the Contractor into successful operation according to manufacturers’ written instructions and as instructed by manufacturers’ representatives. WW Associates Project No. 213003.05 01400/8 1.17.2 Provide all materials, labor, tools, equipment and expendables required. 1.17.3 Coordinate schedule for start-up of various piping systems. Notify the Engineer at least seven days prior to start-up of each piping system. The Owner’s operator and the Engineer will be present during start-up. 1.17.4 Execute start-up under supervision of responsible manufacturer’s representative in accordance with manufacturer’s instructions. 1.17.5 Submit a written report that piping systems have been properly installed and are functioning correctly. 1.17.6 General activities include the following: 1.17.6.1 Cleaning. 1.17.6.2 Removing temporary protective coverings. 1.17.6.3 Flushing and replacing greases and lubricants, where required by manufacturer. 1.17.6.4 Lubrication. 1.17.6.5 Check shaft and coupling alignments and reset where needed. 1.17.6.6 Check and set motor, pump and other equipment, rotation, safety interlocks, and belt tensions. 1.17.6.7 Check and correct, if necessary, leveling plates, grout, bearing plates, anchor bolts, fasteners, and alignment of piping which may put stress on equipment connected to it. 1.17.6.8 Test all equipment and systems at normal operating conditions and through the normal operating range. 1.17.6.9 Make all adjustments and balances required. 1.17.7 Minimum Start-Up Procedures. 1.17.7.1 Motors: Measure amperage of each motor and compare to nameplate valve. Correct conditions which produce excessive current flow, and which exist due to equipment malfunction. 1.17.7.2 Pumps: Check glands and seals for cleanliness and adjustment before operating pump. Inspect shaft sleeves for scoring. Inspect mechanical faces, chambers, and seal rings, and replace, if defective. Verify that piping system is free of debris before circulating liquid through pump. Pump startup shall be performed in accordance with the manufacturer’s written recommendations WW Associates Project No. 213003.05 01400/9 under the supervision of the manufacturer’s representatives, and as specified in the technical specifications of this document. 1.17.7.3 Valves: Inspect all valves, clean bonnets and stems. Inspect packing glands to assure no leakage, and tighten or replace as necessary. Verify that control valve seats are free from foreign material and are properly positioned for service. 1.17.7.4 Pipe Joints: Inspect all joints for leakage, and tighten, remake, or replace as necessary. 1.17.7.5 Pipe Supports: Inspect all piping supports to assure adequate restraint to prevent displacement, vibration, or failure of piping and fittings, while allowing for expansion and contraction. Modify and adjust as necessary. 1.17.7.6 Electrical Circuits: Check each electrical control circuit to assure operation complies with Specifications and requirements to provide desired performance. 1.17.7.7 Instruments: Test, adjust, and calibrate as required. 1.17.7.8 Wastewater Treatment Plant Equipment: Equipment startup shall be performed in accordance with the manufacturer’s written recommendations under the supervision of the manufacturer’s representatives, and as specified in the technical specifications of this document. 1.18 Demonstration and Instructions 1.18.1 Prior to final inspection, demonstrate operation of each system to the Engineer and the Owner. 1.18.2 Instruct the Owner’s personnel in operation, adjustment, and maintenance of systems. 1.19 Acceptance for Operation 1.19.1 As soon as the unit, equipment, or system has been properly prepared for operation and it is necessary to be placed into service, bring it on-line; then make an on-line performance test by operating it under approximately normal conditions using wastewater for a period of 5 consecutive days to demonstrate that all materials and components are in proper working order and free from defects. During this time, the Owner will receive specified instruction on the unit or system by qualified personnel, and be furnished all appropriate operation and maintenance manuals. In event of failure to demonstrate successful performance on the first or any subsequent attempt, make all alternations, adjustments, repairs, and replacements that may be WW Associates Project No. 213003.05 01400/10 needed; and, if it becomes necessary to shut down the unit or system, or any portion thereof before the on-line test is satisfactorily completed, provide all appropriate measures to resume wastewater treatment operations without the unit or system. When the unit or system is again ready for operation, bring it on-line and start a new on-line test. This procedure shall be repeated as often as necessary until the piping system shall have operated continuously to the satisfaction of the Owner, for a test period duration of 5 consecutive days. The Contractor will furnish all operating personnel (other than vendor’s or subcontractor’s service engineers) needed to operate equipment during the on-line test period; operating personnel will perform their duties under the Contractor’s direction and supervision. Until performance tests are completed and units and systems are accepted by the Owner for operation, the Contractor shall be fully responsible for supervising their operation. 1.19.2 When the on-line test has been completed, the Owner will notify the Contractor to this effect in writing and will then take over the unit or system for purpose of operation. Neither this notice nor the act of taking over any item for operation shall relieve the Contractor from his obligations to complete the facility or perform any other obligations or responsibilities, which extend beyond the completion of the on-line tests. 1.19.3 The Contractor shall maintain full responsibility for the maintenance of all units and systems placed on-line until they have been determined substantially complete. No warranties shall begin prior to the date of substantial completion. 1.19.4 Acceptance Requirements: All equipment shall pass the specified performance testing prior to substantial completion certifications. Partial acceptance of equipment will not be allowed. See additional performance test criteria requirements in Section 11400, Paragraph 3.3. 1.20 Cleaning 1.20.1 Periodically clean premises of accumulated construction debris. 1.20.2 Prior to final completion, thoroughly remove from premises any debris remaining from construction activities, and properly dispose. Leave premises in a clean, neat, orderly and safe condition. 1.21 Contract Closeout Procedures 1.21.1 Punch List: Correct All Punch List Items. 1.21.2 Operations and Maintenance Data: Obtain, assemble, and submit to WW Associates three manuals containing comprehensive operating and maintenance instructions and parts lists. Each manual shall be self-contained and include information for efficient servicing of equipment supplied and installed under the contract. WW Associates Project No. 213003.05 01400/11 1.21.2.1 Operating instructions shall explain maintenance procedures, methods of checking the systems for safe and normal operation, and recommended procedure for safely stopping and starting the equipment and systems. 1.21.2.2 These requirements shall be fulfilled before any guarantee periods become effective so as to limit the possibility of claims arising from the absence of pertinent information. 1.21.3 Guarantees, Warranties, and Bonds: Submit all required guarantees, warranties and bonds. 1.21.4 Project Record Documents 1.21.4.1 Provide one complete set of drawings and project manual recording all changes to work to indicate actual installation. Changes shall be noted in legible red letters at least 1/8-inch high. These changes shall include, but are not limited to, the following: 1.21.4.1.1 Size, depth or position of foundations 1.21.4.1.2 Exact location and elevation of all underground utility services 1.21.4.1.3 Changes in general construction, mechanical, or electrical work above or below ground. 1.21.4.2 These records are a specific contract requirement, and final payment will not be made until these drawings and project manual have been submitted in an acceptable form. 1.21.5 Spare parts and maintenance materials required by these contract documents shall be delivered to the Owner as directed by the Owner. 1.21.6 List of Manufacturers and Suppliers: At the conclusion of the project, the Contractor shall furnish WW Associates with a complete list of subcontractors, manufacturers, and suppliers who participated in the construction or who furnished materials or equipment. The address of each firm shall be included, together with types of materials or work performed. 1.21.7 Affidavit of Payment of Debts and Claims 1.21.8 Affidavit of Release of Liens End of Section WW Associates Project No. 213003.05 01400/12 Section 02010 Erosion & Sediment Control 1 GENERAL 1.1 Scope 1.1.1 The requirements of Division 0 - Bidding Information, General Conditions and Forms, Division 1 - General Requirements and Division 2 - Sitework, of this Project Manual apply to all work under this Section. 1.1.2 Perform all work required to control erosion and the sedimentation of downstream improvements and properties, indicated by the Contract Documents, and other related items necessary for the proper execution and completion of this Project. 1.2 References 1.2.1 The provisions of the current Virginia Erosion and Sediment Control Handbook, Albemarle County Code Chapter 17 Water Protection Ordinance, and related County of Albemarle policies apply to all work under this section. 2 PRODUCTS 2.1 All erosion and sediment control related materials shall conform to the current Virginia Erosion and Sediment Control Handbook. Where the Handbook specifications are lacking or less restrictive than the requirements of these plans and specifications, these plans and specifications will prevail. 3 EXECUTION Erosion and sediment control shall be implemented in accordance with the current Virginia Erosion and Sediment Control Handbook and as described in the Erosion and Sediment Control Narrative. 3.1 Erosion and Sediment Control Narrative, Control Measures and Strategies: See Contract Drawings. 3.2 Permanent Stabilization Permanent Stabilization will be in accordance with Section 02936 – Seeding. 3.3 Maintenance Inspect all erosion and sediment control measures at the close of each workday and after each significant rainstorm. Make necessary repairs or clean up immediately to maintain the effectiveness of the measures. The following items will be checked in particular: WW Associates Project No. 213003.05 002010/1 3.3.1 The silt fence barrier will be checked regularly for undermining or deterioration of the fabric. Sediment shall be removed when the level of sediment deposition reaches half way to the top of the barrier. 3.3.2 Inlet and outlet protection shall be checked regularly to ensure proper functioning. 3.3.3 The seeded areas will be checked regularly to ensure that a good stand is maintained. Areas shall be limed, fertilized, reseeded and mulched as needed. End of Section WW Associates Project No. 213003.05 002010/2 Section 02050 Demolition 1 GENERAL 1.1 Description: This section specifies demolition, removal and disposal, off site, of the following: 1.1.1 Existing improvements as indicated on the Drawings. 1.1.2 Incidental related work. 1.1.3 Rubbish and debris located on property identified at Tax Map 128A2-22 and within the limits of construction/limits of clearing and grading are to be removed. 1.2 Definitions 1.2.1 Remove: Remove and legally dispose of items except those indicated to be reinstalled, salvaged, or to remain on the Owner’s property. 1.2.2 Remove and Salvage: Items indicated to be removed and salvaged remain the Owner’s property. Remove, clean and pack or crate items to protect against damage. Identify contents of containers and deliver to the Owner’s designated storage area. 1.2.3 Remove and Reinstall: Remove items indicated; clean, service and otherwise prepare them for reuse; store and protect against damage. Reinstall items in locations indicated 1.2.4 Existing to Remain: Protect construction indicated to remain against damage and soiling during demolition. When permitted by WW Associates, items may be removed to a suitable, protected storage location during demolition and then cleaned and reinstalled in their original location. 1.3 Materials Ownership 1.3.1 Except for items or materials indicated to be reused, salvaged, or otherwise indicated to remain the Owner’s property, demolished materials shall become the Contractor’s property and shall be removed from the site and be disposed of by the Contractor. 1.3.2 Historical items, relics, and similar objects, which may be encountered during demolition, remain the Owner’s property. Carefully remove and salvage each item or object in a manner to prevent damage and deliver promptly to the Owner. WW Associates Project No. 213003.05 02050/1 1.4 Quality Assurance 1.4.1 Regulatory Requirements: Comply with governing Environmental Protection Agency (EPA) notification regulations before starting demolition. Comply with hauling and disposal regulations of authorities having jurisdiction. 1.5 Project Conditions 1.5.1 The Owner assumes no responsibility for actual condition of structures to be demolished. 1.5.2 Storage or sale of removed items or materials on-site will not be permitted. 1.5.3 Asbestos: It is not expected that asbestos will be encountered in the course of this contract. If any materials suspected of containing asbestos are encountered, do not disturb the materials. Immediately notify WW Associates and the Owner. 1.5.4 Remove rubbish, debris and trash from limits of construction at no additional cost to the Owner. 1.6 Prot ection 1.6.1 Protect all existing and newly constructed improvements and paved surfaces from damage due to project demolition and construction. Contractor shall repair or replace all damaged construction at no cost to Owner and to Owner’s satisfaction 1.6.2 Maintain and protect all trees along edge of ROW and limits of construction/limits of clearing and grading during construction. 1.6.2.1 Root prune trees per current arboriculture practices. 1.6.2.2 Repair, replace or regrade adjacent properties as necessary to maintain continuity between new and old conditions. 1.7 Scheduling 1.7.1 Arrange demolition schedule so as not to interfere with the access to adjacent properties. Work closely with the Owner to notify adjacent land owners and residents of construction activities affecting their access. Provide temporary access at all times as necessary. WW Associates Project No. 213003.05 02050/2 1.8 Submittals 1.8.1 Contractor shall provide sufficiently detailed photographs or videotape of existing conditions of adjoining construction and site improvements that could be misconstrued as damage caused by the contractor’s work. 1.8.2 Proposed dust control measures. 2 PRODUCTS: NOT USED. 3 EXECUTION 3.1 General 3.1.1 Existing asphalt surfaces and miscellaneous structures within the areas designated for new construction work shall be demolished to the extent necessary and all debris removed from the site. Asphalt surfaces to be demolished shall be smooth with saw cut. Existing rubbish/debris to be removed. Existing asphalt surfaces shall be restored in kind after construction of new improvements. 3.1.2 Work shall be performed in such manner as not to endanger the safety of the workmen or the public or cause damage to nearby structures. 3.1.3 Provide all barriers and precautionary measures in accordance with the Owner’s requirements and other authorities having jurisdiction. 3.1.4 Where parts of existing structures are to remain in service, demolish the portions to be removed, repair damage, and leave the structure in proper condition for the intended use. Remove concrete and masonry to the lines designated by drilling, chipping, saw cutting or other suitable methods. Leave the resulting surfaces reasonably true and even, with sharp straight corners that will result in neat joints with new construction and be satisfactory for the purpose intended. Where existing reinforcing rods are to extend into new construction, remove the concrete so that the reinforcing is clean and undamaged. Cut off other reinforcing 1/2 inch below the surface and fill with epoxy resin binder flush with the surface. 3.1.5 Prior to the execution of the work, the Contractor and Owner shall jointly survey the condition of the adjoining and/or nearby structures. Photographs and records shall be made of any prior settlement or cracking of structures, pavements, and the like, that may become the subject of possible damage claims. 3.1.6 Should previously unidentified archeological or cultural resources be encountered during construction, the contractor shall stop work in that area immediately and notify the Owner’s representative. The Owner will WW Associates Project No. 213003.05 02050/3 make every effort to allow the contractor to move to another location on the project and continue work until the issue is resolved. 3.2 Disposal of Material 3.2.1 All debris resulting from the demolition and removal work shall be disposed of by the Contractor as part of the work of this contract. All material shall be legally disposed of off site by the Contractor at his expense in accordance with all federal, state, and local regulations. 3.2.2 Burning of any debris resulting from demolition activities will not be permitted at the site. 3.3 Utility Services 3.3.1 Utility Requirements: Locate, identify, disconnect, and seal or cap off utility services to be removed or abandoned in place as indicated on the drawings. 3.3.2 Maintain existing utilities and protect them against damage during demolition operations. 3.3.2.1 Do not interrupt existing utilities serving occupied or operating facilities, except when authorized in writing by authorities having jurisdiction. Provide temporary services during interruptions to existing utilities, as acceptable to governing authorities. 3.4 Explosives: Explosives shall not be used for demolition activities. 3.5 Pollution Controls 3.5.1 Use water mist, temporary enclosures, and other suitable methods to limit the spread of dust and dirt. Comply with governing environmental protection regulations. 3.5.1.1 Do not use water when it may create hazardous or objectionable conditions, such as ice, flooding, or pollution. 3.5.2 Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas. Keep pavement and area adjacent to the site clean and free of mud, dirt, and debris at all times. 3.5.3 Clean adjacent buildings and improvements of dust, dirt, and debris caused by demolition operations. Return adjacent areas to the condition existing before the start of demolition activities. WW Associates Project No. 213003.05 02050/4 3.6 Filling Below Grade Areas: Completely fill below grade areas and voids resulting from demolition of structures and pavements with soil materials where applicable and in accordance with Section 02200 - Earthwork. Fill material shall be completely free of debris and rubbish. Seed disturbed areas are to be vegetated in accordance with Section 02936 – Seeding. 3.6.1 Prior to placement of fill materials, ensure that areas to be filled are free of standing water, frost, frozen material, trash, and debris. 3.6.2 After fill placement and compaction, grade surface to meet adjacent contours and to provide positive flow to surface drainage structures. 3.7 Asphalt Surface Removal: Saw cut and remove existing asphalt concrete pavement in accordance with Section 02500 –Surfacing and Incidental Construction. 3.8 Damages: Promptly repair damages to adjacent utilities, pavement or other existing improvements caused by demolition activities. Repair/replace in kind. 3.9 Cleanup 3.9.1 Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site. If the Contractor fails to remove excess debris promptly, the Owner reserves the right to remove it at the Contractor’s expense. 3.9.2 Remove promptly salvageable material that becomes property of the Contractor and is not to be reused in construction. Sale of material on the site will be prohibited. 3.9.3 Remove all tools, equipment, and materials from the demolition site, and all rubbish upon completion of the work. 3.9.4 Leave the site clean, neat, orderly, and in condition to begin new construction. End of Section WW Associates Project No. 213003.05 02050/5 Section 02200 Earthwork 1 GENERAL 1.1 References: The publication listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only. 1.1.1 American Society For Testing and Materials (ASTM) 1.1.1.1 ASTM C 136: Sieve analysis of fine and coarse aggregates 1.1.1.2 ASTM D 698: Laboratory compaction characteristics of soil using standard effort 1.1.1.3 ASTM D 1140: Amount of material in soils finer than the No. 200 (75-micrometer) sieve 1.1.1.4 ASTM D 1556: Density and unit weight of soil in place by the sandcone method 1.1.1.5 ASTM D 1557: Laboratory compaction characteristics of soil using modified effort 1.1.1.6 ASTM D 2487: Classification of soils for engineering purposes 1.1.1.7 ASTM D 6938: In-place density and water content of soil and soilaggregate by nuclear methods (shallow depth) 1.1.1.8 ASTM D 4318: Liquid limit, plastic limit, and plasticity index of soils 1.2 Definitions 1.2.1 Hard Materials: Weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of “rock” but which usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal. 1.2.2 Rock: Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1/2 cubic yard in WW Associates Project No. 213003.05 02200/1 volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production. 1.2.3 Cohesive Materials: Materials ASTM D 2487 classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesive only when the fines have a plasticity index greater than zero. 1.2.4 Cohesionless Materials: Materials ASTM D 2487 classified as GW, GP, SW, and SP. Materials classified as GM and SM will be identified as cohesionless only when the fines have plasticity index of zero. 1.3 Submittals: Provide the following in a timely manner in accordance with the approved submittals schedule as specified in Section 01400 – General Requirements. 1.3.1 Two copies of field test reports for fill and backfill tests, select materials tests, and density tests. 1.4 Delivery, Storage, and Handling: Perform in a manner to prevent contamination or segregation of materials. 1.5 Criteria for Bidding 1.5.1 Base bids on the elevations as indicated. 1.5.2 Rock excavation shall be unclassified. All earthwork excavation shall be performed to the indicated elevations. 1.5.3 Blasting will not be permitted on this project as specified herein. 1.5.4 Remove material in an approved manner, and provide excavation support structures as required in accordance with the U.S. Army Corps of Engineers “Safety and Health Requirements Manual,” EM-385-1-1, Section 25. Burning of trees and stumps is allowed if approved by the Albemarle County Fire Department. 1.6 Provide barricades, coverings, or other types of protection necessary to prevent damage to existing improvements not indicated to be removed, and improvements on adjoining properties. 1.6.1 Restore all improvements damaged by this work to their original condition, and acceptable to the Owner or other parties or authorities having jurisdiction, unless indicated otherwise. 1.7 Protect existing trees and other vegetation indicated to remain in place against cutting, breaking, or skinning of roots; skinning and bruising of bark; smothering of WW Associates Project No. 213003.05 02200/2 trees by stockpiling construction materials or excavated materials within drip line; excess foot or vehicular traffic; or parking of vehicles within drip line. Provide temporary fences, barricades, or guards as required to protect trees and vegetation to be left standing. 2 PRODUCTS 2.1 Soil Materials: Free of debris, roots, wood, scrap material, vegetation, refuse, soft unsound particles, and frozen deleterious or objectionable materials. The maximum particle diameter shall be one-half the lift thickness at the specified location. The maximum particle diameter for pipe backfill material located less than 1-foot above the pipe crown shall be 1-inch. 2.1.1 Common Fill: Approved, unclassified soil material with the characteristics required to compact to the soil density specified for the intended location. 2.1.2 Embankment and Cutoff Trench Fill: ASTM D 2487, Classification ML, CH with a minimum permeability of 10-5 centimeters/second. 2.1.3 Backfill and Fill Material: ASTM D 2487, Classification GW, GP, GM, GC, SW, SP, SM, SC with a maximum ASTM D 4318 liquid limit of 35, maximum ASTM D 4318 plasticity index of 12, and a maximum of 25 percent by weight passing ASTM D 1140, No. 200 sieve. 2.1.4 Topsoil: Provide as specified in Section 02936 – Seeding. 2.1.5 Select Material: ASTM D 2487, Classification GW, GP, SW, SP with a maximum of 10 percent by weight passing ASTM D 1140, No. 200 sieve. 2.1.6 Pipe Bedding Material: VDOT No. 57 coarse aggregate. 2.1.7 Aggregate Fill: VDOT No. 57 coarse aggregate. 2.1.8 Riprap: Class 1 dry riprap as defined in the Virginia Department of Transportation (VDOT) Road and Bridge Specifications, Section 414, “Riprap.” 2.2 Borrow: Obtain borrow materials required in excess of those furnished from excavations from sources off the Owner’s property. Provide and submit soil classification testing to ensure borrow materials meet the requirements of this specification. 2.3 Geotextile Fabric 2.3.1 Geotextile fabric shall be protected from mud, dirt, dust, sunlight, and debris during transport and storage. Material shall be inert to commonly encountered chemicals; resistant to mildew, rot, insects, and rodents; and WW Associates Project No. 213003.05 02200/3 biologically and thermally stable. Geotextile fabric for subsurface installation shall not be exposed to direct sunlight for more than 24 hours during installation. 2.3.2 Geotextile fabric for riprap bedding material shall be woven polypropylene and shall have the following properties as a minimum: Physical Property Apparent Opening Size Specification Equal to or greater than No. 50 sieve Test Method Grab Tensile Strength Warp/Fill 350 pounds/250 pounds ASTM D 4632 Puncture Strength 140 pounds minimum ASTM D 4833 ASTM D 4751 Acceptable products are Erosion 1 as manufactured by Synthetic Industries, 4019 Industry Drive, Chattanooga, Tennessee 37416, Telephone: (615) 8990444, and Amoco 1199 as manufactured by Amoco Fabrics and Fibers Company, 900 Circle 75 Parkway, Suite 300, Atlanta, Georgia 30339, Telephone: (404) 984-4444. 3 EXECUTION 3.1 Clearing 3.1.1 Remove from the site trees, stumps, roots, brush, shrubs, down timber, rotten wood, rubbish, other vegetation, as well as fences and incidental structures necessary to allow for new construction. 3.1.2 Clearing work shall be restricted to area within “Construction Limits” specified in this Section and as indicated on the drawings. 3.1.3 Remove all stumps and roots located within “Construction Limits” as specified herein and as indicated on the drawings. 3.2 Existing Trees and Shrubs 3.2.1 Trees and shrubs that are to remain shall be protected by the Contractor. 3.2.2 Ownership of Trees: Unless otherwise noted, trees removed to allow for new construction shall become the property of the Contractor and shall be removed from the site. 3.2.3 Provide protection for roots and branches over 11/2 inches in diameter that are cut during construction operations. Coat the cut faces with an emulsified WW Associates Project No. 213003.05 02200/4 asphalt or other coating especially formulated for horticultural use on cut or damaged plant tissues. Temporarily cover all exposed roots with wet burlap to prevent roots from drying out. Provide earth cover as soon as possible. 3.3 Clearing 3.3.1 Clear all areas located within “Limits of Construction” in preparation for drip field installation as follows: 3.3.1.1 Remove standing trees and downed trees. Trees shall be hand cut flush to grade. 3.3.1.2 Rake the site and remove all debris. 3.3.1.3 Grind large stumps to 8" below ground surface. Small stumps may be grubbed. 3.3.1.4 The soil scientist needs to approve moisture conditions before breaking ground, even for clearing. In tight clay soils moisture conditions will have to be correct and low. 3.3.2 Use only hand methods for grubbing inside the drip lines of trees that are to remain. 3.4 Land Disturbance and Limits of Construction Criteria for Utility Construction 3.4.1 General Requirements Applying to all Areas 3.4.1.1 Contractor shall plan construction to minimize disturbance to properties adjacent to the proposed utilities. Contractor shall flag the proposed limits of construction and mark all proposed trees to be cut for review and approval by the Engineer prior to any clearing being performed. 3.4.1.2 The Engineer reserves the right to limit the width of land to be disturbed and to designate on the drawings or in the field certain areas or items within this width to be protected from damage. 3.4.1.3 The Contractor shall be responsible for damages to area or items designated by the Engineer to be protected. Repairs to, replacement of, or reparations for areas or items damaged shall be made to the satisfaction of the Engineer before acceptance of the completed project. WW Associates Project No. 213003.05 02200/5 3.4.1.4 Unless otherwise noted on the contract drawings, all trees cut shall be removed from this project. Brush, laps, roots, and stumps from trees shall also be removed from the site. 3.4.1.5 All buildings or structures located along the line shall be protected by the Contractor. Hand trenching, shoring, or other methods may be required. 3.4.1.6 Any fences disturbed by the Contractor shall be repaired with new materials to a condition equal to or better than their original condition or to the satisfaction of the Engineer. Provide new fencing where indicated on the drawings 3.4.1.7 The Contractor shall obtain written permission from property owners for use of any access points other than ones located within right-ofways. Written permission shall contain conditions for use and restoration agreements between property owner and Contractor. 3.4.1.8 All areas disturbed shall be restored to a condition equal to or better than their original condition and shall be graded to drain. 3.4.1.9 The Contractor shall replace or repair all damaged or destroyed hedgerows or property corners. 3.4.1.10 Topsoil shall be removed from trench line to a depth of 18 inches and stockpiled for use in final restoration. Topsoil shall be replaced to the same depth. 3.4.1.11 Excavated rock shall be removed from the site unless otherwise ordered by the Engineer. 3.4.1.12 Restoration and fine grading shall follow within 1 week from the time an area is disturbed or within 500 feet from the immediate work site, whichever occurs first. Seeding shall follow as specified in Section 02936 – Seeding. 3.4.2 Limits of Construction 3.4.2.1 The Contractor shall not disturb any areas outside the construction limits indicated on the drawings without express written permission from the Engineer. Limits of Construction are defined as the limits of clearing and grading, existing public road right-of-way and new tree line. 3.4.2.2 No clear-cutting of timber shall be permitted within the limits of construction. The Contractor shall make select cutting of trees, WW Associates Project No. 213003.05 02200/6 taking the smallest trees first, that are mandatory for the construction of the utility line. The Engineer’s decision shall be final on determination of which trees are to be cut. 3.5 Clean up debris resulting from site clearing operations continuously with the progress of the work. 3.6 Remove debris from the site in such a manner as to prevent spillage. Keep pavement and areas adjacent to site clean and free from mud, dirt, and debris at all times. 3.7 Surface Preparation 3.7.1 Stripping: Strip existing topsoil, when present, to a depth of 6 inches without contamination by subsoil material. Stockpile topsoil separately from other excavated material and locate convenient to finish grading area. 3.7.2 Unsuitable Material: Remove unsuitable soil materials, waste material, vegetation, debris, decayed vegetable matter, sod, and mulch from the construction site. Dispose of the unsuitable material off the Owner’s property in accordance with all federal, state, and local regulations. 3.7.3 All subgrades shall be certified by a geotechnical engineer prior to construction. 3.8 Protections 3.8.1 Protection Systems: Provide shoring, bracing, and sheeting as required in accordance with the U.S. Army Corps of Engineers “Safety and Health Requirements Manual,” EM-385-1-1, Section 25. 3.8.2 Site Drainage: Provide for the collection and disposal of surface and subsurface water encountered during construction. 3.8.2.1 Surface Drainage: Completely drain the construction site during periods of construction to keep soil materials sufficiently dry. Provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified in this section at no additional cost to the Owner. 3.8.2.2 Subsurface Drainage: Consider site surface and subsurface conditions, available soil, and hydrological data. Remove water by benching, sump pumping, deep well pumping, or other methods to prevent softening of surfaces exposed by excavation. Use filters on dewatering devices to prevent removal of fines from soil. Provide WW Associates Project No. 213003.05 02200/7 erosion control at the outlet of piping to prevent erosion. Operate dewatering system continuously until construction work below existing water levels is complete. 3.8.3 Underground Utilities: Location of existing utilities indicated on the drawings is approximate. The Contractor shall physically verify the location and elevation of the existing utilities, whether indicated or not, prior to starting construction. The Contractor shall contact Miss Utility and respective utility owners for exact locations prior to any excavation near utilities. 3.8.4 Machinery and Equipment: Movement of construction machinery and equipment over pipes during construction shall be at the Contractor’s risk. Repair or remove and provide new pipe for existing or newly installed pipe that has been displaced or damaged at no additional cost to the Owner. 3.8.5 Flotation: The Contractor shall take all necessary precautions to prevent the flotation of new piping and structures during installation and the period before the new piping and associated structures are backfilled and placed in service. 3.9 Excavation 3.9.1 Excavate to the elevations and dimensions indicated and as specified in this section. Reuse excavated materials that meet the specified requirements for the material type required at the intended location. When soil not meeting the requirements specified in this section is encountered during excavation, remove the unsuitable soil material and replace with select material as specified in this section. Removal and disposal of unsuitable soil material and placement and compaction of select material shall be performed at no additional cost to the Owner. 3.9.2 Keep excavations free from water. Excavate soil disturbed or weakened by the Contractor’s operations, and soils softened or made unsuitable for subsequent construction due to exposure to weather. Refill with select material and compact to 95% of ASTM D 698 maximum density. Unless specified otherwise, refill excavations cut below indicated depth with select material and compact to 95% of ASTM D 698 maximum density. Side slopes when allowed shall be protected with 6-mil polyethylene sheeting. 3.9.3 Pipe Trenches: Excavate to the dimensions indicated and as specified herein. Trenches in public roadways shall be excavated in accordance with the latest edition of the VDOT Road and Bridge Specifications. Where rock is encountered, excavate and remove rock to a minimum depth of 6 inches below the pipe invert. Grade bottom of trenches to provide uniform support for each section of pipe after pipe bedding placement. WW Associates Project No. 213003.05 02200/8 3.9.4 Unsuitable Subgrade Soil Materials: Subgrades which are determined to be unsuitable for bearing new equipment, structures, pavements or piping, shall have the unsuitable subgrade soil materials removed and disposed of, and replaced with select material at no additional cost to the Owner. 3.9.5 Excavate embankment cutoff trench to the limits as shown on the drawings. 3.10 Filling and Backfilling: Fill and backfill to elevations and dimensions indicated. Compact each lift before placing overlaying lift. All backfill shall be placed at plus or minus three percent (3%) optimum moisture. 3.10.1 Common Fill Placement: Provide for general site. Place in 6-inch lifts. Compact areas not accessible to rollers or compactors with mechanical hand tampers. Aerate material excessively moistened by rain to satisfactory moisture content. Provide a smooth finish surface by blading, rolling with a smooth roller, or both. 3.10.2 Backfill and Fill Material Placement: Place in 6-inch lifts. Place backfill material adjacent to structures as the structural elements are completed and accepted. Backfill against concrete only when approved. Place and compact material to avoid loading upon or against structures. Place backfill and fill materials to 5 feet outside of structures. 3.10.3 Select Material Placement: Provide under all structures and concrete slabs. Select materials shall be provided from approved borrow areas. In addition, provide stone where indicated on the drawings. Place in 6-inch lifts. Backfill adjacent to structures shall be placed as structural elements are completed and accepted. Backfill against concrete only when approved. Place and compact material to avoid loading upon or against structures. 3.10.4 Trench Backfilling: Backfill as rapidly as construction, testing, and acceptance of work permits. Trenches shall be backfilled at the end of each working day except where otherwise permitted. Place and compact initial backfill and backfill materials in 6-inch lifts to the top of the trench. Trenches in public roadways shall be backfilled and compacted in accordance with the latest edition of the VDOT Road and Bridge Specifications. 3.10.5 Bedding Requirements: Bed all piping in accordance with bedding details of the pipe utility owner. 3.10.5.1 Where rock is encountered, provide a minimum bedding depth of 6 inches beneath the pipe invert. 3.10.6 Subgrade for piping placed under the embankment shall be certified by the geotechnical engineer prior to installation. WW Associates Project No. 213003.05 02200/9 3.10.7 Embankment and Cutoff Trench Requirements: Place in 6-inch lifts. 3.11 Compaction: Expressed as a percentage of maximum density. Determine in-place density of the existing subgrade; if required density exists, no compaction of the existing subgrade will be required. 3.11.1 General Site: Compact underneath areas designated for vegetation and areas outside the 10-foot line of structures to 90% of ASTM D 698. 3.11.2 Structures and Concrete Slabs: Compact 12 inches of subgrade, and all fill, backfill, and select materials to 98% of ASTM D 698. 3.11.3 Pipe Trenches: Compact fill, backfill, and select materials placed in pipe trenches to 95% of ASTM D 698. 3.11.4 Adjacent Areas: Compact areas within 10 feet of structures to 95% of ASTM D 698. 3.11.5 Paved Areas: Compact top 12 inches of subgrade, and all of fill, backfill, and select materials to 98% of ASTM D 698. In addition to the specified compaction requirements, fill and backfill materials shall be compacted to develop a California Bearing Ratio (CBR) of 10. 3.11.6 Embankment and Cutoff Trench: Compact to 98% of maximum dry weight density with a moisture content within + 3% of the optimum per ASTM D698. 3.12 Finish Operations 3.12.1 Grading: Finish grades as indicated within one-tenth of 1 foot. Grade areas to drain water away from structures. For existing grades that will remain but which were disturbed by the Contractor’s operations, grade as directed. 3.12.2 Seeding: Provide as specified in Section 02936 – Seeding. 3.12.3 Protection of Surfaces: Comply with all local requirements and the latest edition of the Virginia Erosion and Sediment Control Handbook to control erosion and sedimentation. Protect newly graded areas from traffic, erosion, and settlements that may occur. Repair or reestablish damaged grades, elevations, or slopes. 3.12.3.1 No more than 250 feet of trench shall be open at any one time. 3.12.3.2 During curb/curb and gutter construction activities, the Contractor shall provide seeding and mulch restoration to ensure no more than 10,000 square feet of disturbed area remains unrestored at any given time. WW Associates Project No. 213003.05 02200/10 3.12.3.3 Install silt fence on downhill side of construction activities and at other locations to prevent sediment from entering drainageways. 3.12.3.4 Apply permanent or temporary soil stabilization to denuded areas within 15 days after final grade is reached on any portion of the site. In addition, apply soil stabilization within 15 days to denuded areas which may not be at final grade but will remain dormant (undisturbed) for longer than 60 days. Soil stabilization practices include vegetative establishment, mulching, and the early application of gravel base on areas to be paved. 3.12.3.5 Install straw bale dam or silt fence around soil stockpiles and excavations. 3.12.3.6 Take all applicable erosion and siltation control measures prior to grading. 3.12.3.7 Protect and maintain storm sewer inlets with inlet protection. 3.12.3.8 Inspect all erosion and sediment control devices at the close of each work day and after each rainstorm. Make necessary repairs or clean up immediately to maintain effectiveness of the device. 3.12.3.9 Where consistent with job safety requirements, easement conditions, and construction methods, place all excavated material on the uphill side of the trench. When the soil is placed on the downhill side of the trench, divert maximum drainage toward the trench. 3.12.3.10 Repair after cleanup: Upon completion of construction work and after spoils and debris have been removed; regrade any areas disturbed by the operations. 3.12.3.11 Water discharged from dewatering activities shall not be discharged directly to any stream or body of water. Comply with Specification 3.26, “Dewatering Structure,” of the latest edition of the Virginia Erosion and Sediment Control Handbook. 3.13 Riprap: Riprap shall be installed in accordance with the latest edition of the VDOT Road and Bridge Specifications, Section 414, “Riprap.” Geotextile fabric shall be placed under all riprap. 3.14 Geotextile Fabric: Geotextile fabric shall be installed in accordance with the latest edition of the Virginia Erosion and Sediment Control Handbook and the manufacturer’s written recommendations. WW Associates Project No. 213003.05 02200/11 3.15 Disposition of Surplus Material: Waste unsuitable soil materials off the Owner’s property as directed by the Owner and WW Associates in accordance with federal, state, and local regulations. 3.16 Field Quality Control: The County shall employ an independent testing firm to provide all soil testing required for this project. The Contractor will schedule the tests as provided in Supplemental Contract General Conditions; Item 6. 3.16.1 Sampling: Take the number and size of samples required to perform the following tests. 3.16.2 Testing: Perform one of each of the required tests for each material used. Provide additional tests for each source change and as requested by WW Associates. 3.16.2.1 Fill, Backfill, Embankment and Cutoff Trench: Test fill, backfill and embankment/cutoff trench material in accordance with ASTM C 136 for conformance to ASTM D 2487 gradation limits; ASTM D 1140 for material finer than the No. 200 sieve; ASTM D 423 for liquid limit and ASTM D 424 for plastic limits; ASTM D 698 or ASTM D 1557 for moisture density relations, as applicable. 3.16.2.2 Select Material: Test select material in accordance with ASTM C 136 for conformance to ASTM D 2487 gradation limits; ASTM D 1140 for material finer than the No. 200 sieve; ASTM D 698 or ASTM D 1557 for moisture density relations, as applicable. 3.16.2.3 Density Tests: Test soil density in accordance with ASTM D 1556, or ASTM D 6938. When ASTM D 6938 density testing is used, verify density test results by performing an ASTM D 1556 density test at a location already ASTM D 6938 tested as specified herein. Perform an ASTM D 1556 density test at the start of the project, and for every ten (10) ASTM D 6938 density tests thereafter. Test each lift at randomly selected locations every 500 square feet of existing grade in fills for structures and concrete slabs, every 500 square feet for other fill areas, every 1,000 square feet of subgrade in cut, and every 250 linear feet for pipe line installation (minimum one test per pipe line), and additional tests as requested by WW Associates. End of Section WW Associates Project No. 213003.05 02200/12 Section 02500 Surfacing and Incidental Construction 1 GENERAL 1.1 Reference specifications where applicable to work under this section are referred to by abbreviation as follows: American Association of State Highway and Transportation Officials................................................................................ AASHTO American Society for Testing and Materials ..................................................... ASTM Virginia Department of Transportation ............................................................. VDOT 1.2 Submittals: Provide the following in a timely manner in accordance with the approved submittals schedule as specified in Section 01400 – General Requirements. 1.2.1 Materials certificates signed by material producer and Contractor. Certificates shall state that each material item meets specified requirements and is on the VDOT approved materials list. 1.3 Materials and work shall be performed in accordance with and shall meet the requirements of the referenced sections of the VDOT Road and Bridge Specifications (2007 Edition with latest VDOT revisions) and the VDOT Road and Bridge Standards (2008 Edition with latest VDOT revisions) unless noted otherwise. 2 PRODUCTS 2.1 ... Aggregate course for stone surface access road at the site shall be Size No. 25 or 26, graded aggregate material as defined in VDOT Road and Bridge Specifications, Section 203 “Coarse Aggregate” and Section 205, “Crusher Run Aggregate”, and cross-referenced sections. 3 E XE C U T IO N 3.1 Graded aggregate base course for stone surface construction methods and equipment shall conform to requirements of Section 309, “Aggregate Base Course,” of VDOT Road and Bridge Specifications. 3.2 ..... Subgrade Preparation: Subgrade preparation shall consist of the final machining of the subgrade immediately prior to placing the aggregate base course. The surface shall be true to line and grade. Construction methods and equipment shall conform to applicable portions of Section 305, “Subgrade and Shoulders,” of VDOT Road and Bridge Specifications. WW Associates Project No. 213003.05 02500/1 3.3 Pavement Repairs 3.3.1 Pavement repairs shall be performed at any point where excavations disturb existing asphalt. Repairs shall be included in the lump sum bid for this project. 3.3.2 Contractor shall match the existing subgrade, base, and overlay elevations when installing repairs. Repairs shall bring trench area to the same elevation as the surrounding area. 3.3.3 Asphalt surfaces that will be disturbed must be saw cut. No jagged edges will be allowed. Make the cut in a straight line, parallel to, and 6 inches wider than the trench, on each side, to provide an undisturbed shoulder under the new work. Provide heel cut where new asphalt concrete pavement connects to existing asphalt concrete pavement. 3.3.4 Where trenches cross a street, the Contractor shall disturb no more than one half of the street width at one time, and restore the firsts trench opening to satisfactory travelable condition before the second half is excavated. Avoid placement of excavated material on existing pavement wherever possible. Clean the pavement by an approved method. Do not use cleated equipment on pavements. Any pavements damaged by equipment or Contractor’s operation shall be repaired at the Owner’s discretion at no additional cost. Alter normal traffic flow only with permission from the Owner. 3.3.5 Replace aggregate base course in layers not to exceed 6 inches in thickness to a depth of 1 1/2 times the thickness of the original aggregate base. In no case shall the replaced base be less than 8 inches thick. 3.3.6 Replace asphalt concrete base course equal to the original pavement asphalt base. 3.3.7 Replace asphalt finish surface course equal to the original pavement surface course. 3.3.8 Restore private entrances to the original condition or provide no less than 6 inches of aggregate base course, whichever condition is better. 3.4 All finished pavement edges shall be clean and straight. The final paving quality control shall be the responsibility of the Contractor and shall be acceptable to the Owner based on surface thickness and smoothness. Adjacent earth surface shall match top of new gravel surface and ensure positive drainage. See Earthwork Section 02200 for material and compaction requirements. See Seeding Section 02936 for restoration. 3.5 Do not block private entrances except for short periods, and maintain ingress and egress to adjacent property at all times. WW Associates Project No. 213003.05 02500/2 3.6 Do not clog street drainage. Maintain shoulders, gutters, and ditches affected by trenching operations to carry drainage flows. New pavement overlays shall not block existing drainage flow conditions. 3.7 Upon completion of construction work and after spoils and debris have been removed; regrade any areas disturbed by the operations. 3.8 Upon completion of construction and upon approval of the Owner a two-inch thick top dressing of VDOT Size No. 25 or 26 grade aggregate material “Crusher Run Aggregate” shall be applied to the access road/parking lot/turnaround area. End of Section WW Associates Project No. 213003.05 02500/3 Section 02660 Water Distribution System 1 GENERAL 1.1 Description: This section specifies all potable water system work 5 feet or more outside of buildings. 1.2 Reference specifications are referred to by abbreviation as follows: 1.2.1 American Association of State Highway and Transportation Officials......................................................... AASHTO 1.2.2 American National Standards Institute .................................. ANSI 1.2.3 American Society of Sanitary Engineering ........................... ASSE 1.2.4 American Society for Testing and Materials ......................... ASTM 1.2.5 American Water Works Association ..................................... AWWA 1.2.6 Canadian Standards Association ........................................... CSA 1.2.7 Commercial Standard (National Bureau of Standards) ......... CS 1.2.8 Virginia Department of Health .............................................. VDH 1.3 Project Conditions: Separation of Water Lines and Sanitary Sewers. 1.3.1 Follow VDH standards for separation of water mains and sewer lines. 1.3.2 Parallel Installation 1.3.2.1 Normal Conditions: Water lines shall be constructed at least 10 feet horizontally from a sewer or sewer manhole whenever possible, the distance shall be measured edge-to-edge. 1.3.2.2 Unusual Conditions: When local conditions prevent a horizontal separation of at least 10 feet, the water line may be laid closer to a sewer or sewer manhole provided that: 1.3.2.3 The bottom of the water line is at least 18 inches above the top of the sewer. 1.3.2.3.1 Where this vertical separation cannot be obtained, the sewer shall be constructed of AWWA approved water pipe pressure-tested in place to 50 psi without leakage prior to backfilling. The sewer manhole shall be of watertight construction and tested in place. WW Associates Project No. 213003.05 02660/1 1.3.3 Crossing 1.3.3.1 Normal conditions: Water lines crossing over sewers shall be laid to provide a separation of at least 18 inches between the bottom of the water line and the top of the sewer whenever possible. 1.3.3.1.1 Unusual conditions: When local conditions prevent a vertical separation described in crossing, normal conditions, paragraph above, the following construction shall be used. 1.3.3.1.2 Sewers passing over or under water lines shall be constructed of the materials described in parallel installation, unusual conditions, as specified above. 1.3.3.1.3 Water lines passing under sewers shall, in addition, be protected by providing: 1.3.3.1.3.1 A vertical separation of at least 18 inches between the bottom of the sewer and the top of the water line. 1.3.3.1.3.2 Adequate structural support for the sewers to prevent excessive deflection of the joints and settling on and breaking water line. 1.3.3.1.3.3 That the length of the water line be centered at the point of the crossing so that joints shall be equidistant and as far as possible from the sewer. 1.3.4 Sanitary Sewers or Sewer Manholes: No water pipes shall pass through or come in contact with any part of a sewer or sewer manhole. 1.4 Submittals: Provide the following shop drawings in accordance with the approved submittals schedule as specified in Section 01400 – General Requirements. 1.4.1 Pipe and Fittings: Catalog cuts and certificates of compliance for pipe, fittings, linings, and materials for approval. Certificates shall state that materials furnished comply with the standards specified in this section. 1.4.2 Pipe Restraint Devices 1.4.3 Valves: Catalog cuts and certificates of compliance for valves. 1.4.4 Valve Boxes WW Associates Project No. 213003.05 02660/2 1.4.5 Tapping Sleeve and Valve 1.4.6 Water Piping Field Test Certification Reports 1.4.7 Bacteriological Test Reports (Submit to Owner) 2 PRODUCTS 2.1 Piping Application 2.1.1 The following piping systems, smaller than 2 inches in diameter, shall be constructed of ASTM B 88 Type K flexible copper pipe unless otherwise indicated: 2.1.1.1 Above grade water service piping 2.1.2 The following piping systems, smaller than 2 inches in diameter, shall be constructed of solvent welded Schedule 40 polyvinyl chloride (PVC) pipe unless otherwise indicated: 2.1.2.1 Below grade water service piping 2.1.3 Accessories: Provide flanges, joint restraints, connecting pieces, transition glands, transition sleeves, tapping saddles, and other adapters as required for complete and operable piping systems for the service indicated. Provide restrained joints where indicated on the drawings and as specified in this section. 2.2 Pipe 2.2.1 Polyvinyl Chloride (PVC) Piping 2.2.1.1 Pipe, couplings, and fittings shall be Schedule 40 meeting the requirements of ASTM D 1785, manufactured of material meeting the requirements of ASTM D 1784, Type 1120. Provide ASTM D 2467 Schedule 80 fittings, ASTM D 2564 solvent cement. Joints shall be solvent welded, meeting requirements of ASTM D 2855. 2.2.1.2 PVC pipe manufacturer shall be Charlotte Pipe and Foundry Company, P.O. Box 35430, Charlotte, North Carolina 28235 or approved equal. 2.2.1.3 Provide screwed joints and flanges as required to connect dissimilar pipe materials, valves, equipment, and appurtenances. 2.2.2 Copper Tubing 2.2.2.1 Copper tubing and associated fittings shall be ASTM B 88, Type K flexible. WW Associates Project No. 213003.05 02660/3 2.2.2.2 Brass fittings shall be compression joint by Ford Meter Box Company, Inc. or approved equal. 2.3 Pipe Labeling 2.3.1 Detectable tape shall be provided for all below grade piping systems and shall have a metallic core protected by a plastic jacket. The tape shall be continuously marked indicating that a water main is buried beneath the tape. In addition, a continuous No. 14 gauge copper wire with protective coating shall be provided for all below grade piping systems as indicated on the drawings. 2.4 Valves 2.4.1 Ball Valves: Ball valves shall be Class 150, meeting requirements of ANSI B16.34. Valves shall have ANSI carbon steel bodies and balls. Valves shall have stainless steel stems and trim, and Viton or Teflon seats, body seals, and stem seals. Valves shall be lever operated. Valves shall be manufactured by Velan Valve Corporation, ITT-Grinnell, Worchester, Inc., or approved equal. 2.5 Valve boxes shall be adjustable cast iron valve boxes of the two-piece screw-type. Base shall be proper type and size for the valve with which it is used. The word “WATER” shall be cast or embossed on the valve box lid in letters not less than 1inch high. Valve boxes shall be manufactured by Mueller Company, Dewey Brothers, Tyler, or Bingham-Taylor or approved equal. 2.6 Pipe to sleeve sealant shall be grouting compound. Grouting compound shall be as manufactured by 3M Company or be an equivalent product having tensile strength of 80 psi and elongation property of 700% in accordance with ASTM D 3574 Test E, and linear dimension change shall not exceed 18% when subject to wet and dry cycles in accordance with ASTM D 756, Procedure G and ASTM D 1042. 2.7 Mechanical Type Pipe to Wall Sleeve Seals: Mechanical type pipe to wall sleeve seals shall be “Link-Seal” pipe to wall closures manufactured by Thunderline Corporation, Wayne, Michigan or approved equal. Seals shall be modular mechanical type, consisting of interlocking synthetic rubber links shaped to fill annular space between pipe and wall opening and shall provide watertight seal between pipe and wall opening. 3 EXECUTION 3.1 Pipe Laying 3.1.1 Take all precautions necessary to insure that pipe, valves, fittings, and other accessories are not damaged in unloading, handling, and placing in trench. Examine each piece of material just prior to installation to determine that no WW Associates Project No. 213003.05 02660/4 damage has occurred. Remove any damaged material from the site and replace with undamaged material. 3.1.2 Exercise care to keep foreign material and dirt from entering pipe during storage, handling, and placing in trench. Close ends of in-place pipe at the end of any work period to preclude the entry of animals and foreign material. 3.1.3 Bedding of pipe shall be as specified in Section 02200 – Earthwork. 3.1.4 Do not lay pipe when trench bottom is muddy or frozen, or has standing water. 3.1.5 Use only those tools specifically intended for cutting the size and material and type pipe involved. Make cut to prevent damage to pipe or lining and to leave a smooth end at right angles to the axis of the pipe. 3.2 Lay water main piping with bell ends facing the direction of laying. Where grade is 10 percent or greater, pipe shall be laid uphill with bell ends upgrade. Lay water main piping with a minimum cover of 36 inches unless otherwise indicated. 3.3 Join and assemble solvent welded PVC pipe joints in accordance with requirements of ASTM D 2855. 3.4 Welded, soldered, or brazed joints between sections of copper pipe and between pipe and fittings shall be in compliance with ANSI B31.1. Make joints in piping system tight and leakproof against the design pressure. Peening of welded joints to correct leaks will not be permitted. Brazed or soldered joints that leak shall be disassembled, cleaned, and made again. 3.5 Install detectable tape in trench above all pipe per the manufacturer’s written recommendations. Install continuous copper wire in trench above all pipe as shown on the drawings. 3.6 Set Valves and Valve Boxes as follows: 3.6.1 Equip all underground valve operators with valve boxes. Set box in alignment with valve stem centered on valve nut. Set valve box to prevent transmitting shock or stress to the valve. Set box cover flush with the finished ground surface or pavement. 3.7 Installation of Tapping Saddles and Tapping Valves 3.7.1 All tapping saddles shall be set to avoid interference with existing pipe joints. 3.7.2 After all tapping saddles and valves have been set in place; a 150-psi pressure test shall be performed to insure that there are no leaks around the sleeve or through the valve prior to tapping. All leakage shall be corrected. WW Associates Project No. 213003.05 02660/5 3.7.3 Actual taps shall be made in the presence of the Owner’s representative. The Owner shall be given a minimum of 48 hours notice before tapping operations commence. 3.8 Construct concrete cap or cradle in accordance with the latest edition of the VDOT Road and Bridge Standards at locations where the vertical separation between the new water main piping and adjacent utilities is less than 6 inches. 3.9 Use sleeves where pipes, valves, stem extensions, or equipment parts pass through concrete or masonry walls or slabs. Sleeves shall be or sufficient size to allow sealing around pipes and clearance for valve stem or equipment. Extend vertical sleeves through slabs 1-inch above top surface. 3.9.1 Use cast iron or steel sleeves with intermediate collars to anchor and provide water stops on sleeves that pass through exterior walls below grade. Seal around pipes using grouting compound or “Link-Seal” pipe to wall closures manufactured by Thunderline Corporation, Wayne, Michigan. Seals shall be modular mechanical type, consisting of interlocking synthetic rubber links shaped to fill annular space between pipe and wall opening and shall provide watertight seal between pipe and wall opening. Grouting compound shall be mixed and placed in accordance with the recommendations of the manufacturer. Mechanical pipe to wall seal shall be installed in accordance with the written recommendations of the manufacturer. 3.10 Acceptance Tests 3.10.1 After the line has been backfilled, subject the line or any valved section of the line to a hydrostatic pressure test. Fill the system with water at velocity of approximately 1 foot per second while necessary measures are taken to eliminate all air. After the system has been filled, raise the pressure by pump to 1.5 times the working pressure. Measure pressure at the low point on the system compensating for gage elevation. Maintain this pressure for 2 hours. If pressure cannot be maintained, determine cause, repair, and repeat the test until successful. 3.10.2 A leakage test shall be conducted concurrently with the pressure test. Leakage shall be determined with a calibrated test meter furnished by the contractor. Leakage will be defined as the quantity of water required to maintain a pressure within 5 psi of the specified test pressure, after air has been expelled, and the pipe filled with water. Leakage shall not exceed that quantity obtained by the formula below. If leakage exceeds that determined by the formula, find and repair the leaks and repeat the test until successful. The leakage formula shall be as follows: L = SD (√P)/148,000 Where L = Allowable leakage in gallons/hour WW Associates Project No. 213003.05 02660/6 S = Length of pipeline tested in feet D = Nominal diameter of the piper in inches P = Average test pressure during leakage test in psig 3.10.3 All visible leaks shall be repaired regardless of the amount of leakage. 3.11 Disinfect and test water mains and accessories in accordance with AWWA standards and as specified herein. 3.11.1 Preliminary Flushing: The main shall be flushed prior to disinfection, except when the tablet method is used. Flushing shall be at a velocity of not less than 2.5 feet per second. Adequate provisions shall be made for drainage of flushing water. 3.11.2 Form of Chlorine for Disinfection 3.11.2.1 Liquid chlorine shall be used only when suitable equipment is available and only under the direct supervision of a person familiar with the physiological, chemical, and physical properties of this element and who is properly trained and equipped to handle any emergency that may arise. Introduction of chlorine-gas directly from the supply cylinder is unsafe and shall not be permitted. 3.11.2.2 Calcium hypochlorite contains 70% available chlorine by weight. It shall be either granular or tabular in form. The tablets, six to eight to the ounce, are designed to dissolve slowly in water. A chlorinewater solution shall be prepared by dissolving the granules or tablets in water in the proportion requisite for the desired concentration. 3.11.2.3 Sodium hypochlorite is supplied in strengths from 5.25% to 16% available chlorine. The chlorine-water solution shall be prepared by adding hypochlorite to water. 3.11.2.4 Application: The hypochlorite solutions shall be applied to the water main with a gasoline or electrically powered chemical feed pump designed for feeding chlorine solutions. For small applications, the solutions may be fed with a hand pump; for example, a hydraulic test pump. Feed lines shall be of such material and strength as to withstand safely the maximum pressures that may be created by the pumps. All connections shall be checked for tightness before the hypochlorite solution is applied to the main. 3.11.3 Methods of Chlorine Application 3.11.3.1 Continuous Feed Method: Water from the existing distribution system or other approved sources of supply shall be made to flow at a constant, measured rate into the newly laid pipeline. The water WW Associates Project No. 213003.05 02660/7 shall receive a dose of chlorine, also fed at a constant, measured rate. The two rates shall be proportioned so that the chlorine concentration in the water in the pipe is maintained at a minimum of 50 mg/L available chlorine. To assure that this concentration is maintained, the chlorine shall be measured at intervals not exceeding 2,000 feet in accordance with the procedures described in the current edition of “Standard Methods” and AWWA M12 – “Simplified Procedures for Water Examination.” In the absence of a meter, the rate may be determined either by placing a pitot gage at the discharge or by measuring the time to fill a container of known volume. During the application of the chlorine, valves shall be manipulated to prevent the treatment dosage from flowing back into the line supplying the water. Chlorine application shall not cease until the entire main is filled with the chlorine solution. The chlorinated water shall be retained in the main for at least 24 hours, during which time all valves and hydrants in the section treated shall be operated in order to disinfect the appurtenances. At the end of this 24-hour period, the treated water shall contain no less than 25 mg/L chlorine throughout the length of the main. 3.11.3.2 Tablet Method: Use only when allowed by the Engineer. Do not use this method if trench water or foreign material has entered the main or if the water is below 41°F (5°C). This method may be used for mains up to 12 inches in diameter, and where the total length of the main is less than 2,500 feet. Place tablets in each section of pipe and also in hydrants, hydrant branches, and other appurtenances. Enough tablets shall be used to ensure that a chlorine concentration of 25 mg/L is provided in the water. Attach tablets using Permatex No. 1 adhesive or other approved adhesive, except for the tablets placed in hydrants and in the joints between the pipe sections. Tablets shall be free of adhesive except on the one broad side to be attached. Place all tablets at the top of the main. If the tablets are attached before the pipe section is placed in the trench, mark the position of the tablet in the pipe and assure that the pipe is placed with the tablet at the top. When installation is completed, fill the main with water at a velocity of less than 1 foot per second. The water shall remain in the pipe for at least 24 hours. Operate valves so that the strong chlorine solution will not flow back into the line supplying the water. WW Associates Project No. 213003.05 02660/8 3.11.4 Final Flushing: After the applicable retention period, the heavily chlorinated water shall be flushed from the main until the chlorine concentration in the water leaving the main is no higher than that generally prevailing in the system, or less than 1 mg/L. Chlorine residual determination shall be made to ascertain that the heavily chlorinated water has been removed from the pipeline. Contractor shall provide dechlorination of all flushed water prior to discharge. 3.11.5 Bacteriologic Tests 3.11.5.1 After final flushing and before the water main is placed in service, samples shall be collected and tested for bacteriologic quality and shall show the absence of coliform organisms. At least two samples shall be collected at least 24 hours apart at intervals not exceeding 2,000 feet, and tested by a VDH-approved laboratory and results submitted to the Owner. 3.11.5.2 Samples for bacteriological analysis shall be collected in sterile bottles treated with sodium thiosulfate. If laboratory results indicate the presence of coliform bacteria, the samples are unsatisfactory, and disinfection shall be repeated until the samples are satisfactory. 3.11.5.3 A sampling tap consisting of a corporation cock with metal pipe shall be installed within 2 feet of valves. The corporation stop inlet shall be male, 1-inch in size, and the outlet shall have 1-inch I.P. threads and a cap. 3.11.6 Cleaning, disinfection, and testing will be the responsibility of the Contractor. The Contractor shall furnish the water required for these operations at his own cost and expense. No separate payment, other than that included in the contract lump sum, will be allowed. 3.11.7 Testing and disinfection of the completed sections shall not relieve the Contractor of his responsibility to repair or replace any cracked or defective pipe. All work necessary to secure a tight line shall be done at the Contractor’s expense. End of Section WW Associates Project No. 213003.05 02660/9 Section 02720 Storm Sewer System 1 GENERAL 1.1 System Description: Work in this section includes all storm drainage work on this project. 1.2 Reference specifications are referred to by abbreviation as follows: 1.2.1 American Association of State Highway and Transportation Officials ............................................................ AASHTO 1.3 1.2.2 American National Standards Institute .............................................. ANSI 1.2.3 American Society for Testing and Materials ................................... ASTM 1.2.4 Virginia Department of Transportation ........................................... VDOT Submittals: Provide the following in timely manner in accordance with the approved submittals schedule as specified in Section 01400 – General Requirements. 1.3.1 Shop Drawings of the following: 1.3.1.1 Pipe 1.3.1.2 End Sections/Endwalls 1.3.1.3 Storm Drainage Item Details 2 PRODUCTS: 2.1 Piping Application 2.1.1 HDPE storm sewer shall be constructed of high density polyethylene (HDPE) Type S corrugated pipe meeting AASHTO M294. 2.1.2 PVC storm sewer pipe and joints shall meet the requirements specified in Section 02660 Water Distribution System. 2.2 Drop inlets, curb drop inlets and manholes and other storm drainage items shall be in accordance with the latest edition of the VDOT Road and Bridge Standards (2008 edition with latest VDOT revisions). 2.3 Pipe to precast concrete storm drainage structure connections shall be installed in accordance with the latest edition of the VDOT Road and Bride Specifications. 3 EXECUTION 3.1 Maintain drainage on site to prevent erosion, damaging water, and standing water during all phases of construction. WW Associates Project No. 213003.05 02720/1 3.2 Keep excavations clear of water while work is being installed. Control subsurface water in accordance with Section 02200 - Earthwork. 3.3 Take all precautions necessary to insure that pipe, fittings, and related items are not damaged in unloading, handling, and placing in trench. Examine each piece of material just prior to installation to determine that no damage has occurred. Remove any damaged material from the site and replace with undamaged material. 3.4 Do not lay pipe when trench conditions or weather are unsuitable for such work. Keep pipe interior clean and free from dirt or waste materials. 3.5 Lay pipe so as to maintain a true alignment and grade as indicated on drawings. After completion, the pipe shall exhibit a full circle of light when lighted at one manhole and viewed from the next. 3.5.1 Commence laying piping at the lowest point on a section of line and lay pipe upgrade with bell or groove ends upstream. 3.5.2 Pipe Joint: Preparatory to making pipe joints, clean and dry all surfaces of joint pipe and jointing material. Use lubricants, primers, adhesives, and similar materials as recommended by the manufacturers. Place, fit, join, and adjust the jointing materials or factory fabricated joints as recommended by manufacturer to obtain the degree of water tightness required. As soon as possible after the joint is made, place sufficient backfill material, as specified in Section 02200 – Earthwork, along each side of pipe to resist forces that might tend to move pipe off line and grade. 3.5.3 Backfill as specified in Section 02200 – Earthwork. Place backfill over the pipe immediately after the pipe has been laid. 3.6 Construct end sections and other storm drainage items as detailed in the latest edition of the VDOT Road and Bridge Standards or on the drawings, as applicable. 3.7 Join pipe in accordance with manufacturer’s recommendations. 3.8 As each joint is laid, visually inspect to be certain that no jointing compound, gasket, or trash is protruding from the joint or lying inside the pipe. 3.9 At the completion of constructing the improvements associated with this contract, the contractor shall flush the entire closed conduit storm drain system with potable water under suitable pressure to remove any sediment deposits or other observed obstructions. End of Section WW Associates Project No. 213003.05 02720/2 Section 02730 Wastewater Piping Systems 1 GENERAL 1.1 Description: This section specifies all wastewater piping for the wastewater treatment plant. 1.2 Reference specifications are referred to by abbreviation as follows: 1.2.1 American National Standards Institute .............................. ANSI 1.2.2 American Society for Testing and Materials ..................... ASTM 1.2.3 American Water Works Association ................................. AWWA 1.2.4 Uni-Bell PVC Pipe Association ........................................ UNI-B 1.2.5 Virginia Department of Health .......................................... VDH 1.2.6 Virginia Department of Transportation ............................. VDOT 1.3 Project Conditions: Separation of Water Lines and Sanitary Sewers 1.3.1 Follow VDH standards for the separation of sanitary sewer and water distribution systems. 1.3.2 Parallel Installation 1.3.2.1 Normal Conditions: Sewer lines and manholes shall be constructed at least 10 feet horizontally from a water line whenever possible. The distance shall be measured edge-to-edge. 1.3.2.2 Unusual Conditions: When local conditions prevent a horizontal separation of at least 10 feet, then maximum horizontal separation shall be provided with vertical separation of bottom of water line at least 18 inches above top of sewer. Where this vertical separation cannot be obtained, the sewer shall be constructed of AWWA approved water pipe pressure-tested in place to 50 psi without leakage prior to backfilling. The sewer manhole shall be of watertight construction and tested in place. 1.3.3 Crossing 1.3.3.1 Normal Conditions: Sewers crossing under water lines shall be laid to provide a separation of at least 18 inches between the bottom of water line and the top of the sewer whenever possible. 1.3.3.2 Unusual Conditions: When local conditions prevent a vertical separation described in “Crossing, Normal Conditions,” paragraph above, the following construction shall be used. WW Associates Project No. 213003.05 02730/1 1.3.3.2.1 Sewers passing over water lines shall be laid to provide: 1.3.3.2.1.1 Vertical separation of at least 18 inches between bottom of sewer and top of water line, 1.3.3.2.1.2 Adequate structural support for the sewers to prevent excessive deflection of the joints and settling on and breaking the water line, 1.3.3.2.1.3 Maximum separation of water and sewer line joints. 1.3.3.2.1.4 Sewers passing over or under water lines shall be constructed of cast or ductile iron with mechanical joints as described in “Parallel Installation, Unusual Conditions,” paragraph above. 1.3.4 Sanitary Sewers or Sewer Manholes: No water pipes shall pass through or come in contact with any part of a sewer or sewer manhole. 1.4 Submittals: Provide the following in accordance with the approved submittals schedule as specified in Section 01400 – General Requirements. 1.4.1 Pipe and Fittings: Catalog cuts and certificates of compliance for pipe, fittings, linings, and materials for approval. Certificates shall state that materials furnished comply with the standards specified in this section. 1.4.2 Pipe Restraint Devices 1.4.3 Valves: Catalog cuts and certificates of compliance for valves. 1.4.4 Valve Boxes 1.4.5 Flexible Couplings 1.4.6 Precast Concrete Manhole and appurtenances 1.4.7 Manhole Frames and Covers 1.4.8 Manhole Steps 1.4.9 Pipe to Manhole Connection Details 1.4.10 Certification Reports for Manhole and Sanitary Sewer Testing WW Associates Project No. 213003.05 02730/2 2 PRODUCTS 2.1 Piping Application 2.1.1 All below grade sanitary sewer piping, 6 inches and larger in diameter, shall be constructed of push-on joint SDR 35 solid wall polyvinyl chloride (PVC) gravity sewer pipe. 2.1.2 All below grade wastewater treatment plant piping systems, smaller than 6 inches in diameter, shall be constructed of solvent welded Schedule 80 polyvinyl chloride (PVC) pipe unless otherwise indicated. 2.1.3 Accessories: Provide flanges, connecting pieces, transition glands, transition sleeves, and other adapters as required for complete and operable piping systems for service indicated. Provide restrained joints where indicated on the drawings and as specified in this section. 2.2 Valve Application 2.2.1 Wastewater plant valves shall be PVC ball valves. 2.2.2 Polyvinyl chloride (PVC) plastic gravity sewer piping (6 inches or larger) shall meet requirements of ASTM D 3034 and be integral bell, gasketed joint pipe with dimension ratio (DR) of 35 and minimum pipe stiffness (PS) of 46 psi. 2.2.2.1 Pipe joint shall meet requirement of ASTM D 3212. 2.2.2.2 Rubber gaskets shall meet physical requirements specified in ASTM F 477 in all respects. 2.2.2.3 PVC gravity sewer piping manufacturer shall be Charlotte Pipe and Foundry Company, P.O. Box 35430, Charlotte, North Carolina 28235 or approved equal. 2.2.3 Schedule 80 Polyvinyl Chloride (PVC) Piping 2.2.3.1 Pipe, couplings, and fittings shall be Schedule 80 meeting the requirements of ASTM D 1785, manufactured of material meeting the requirements of ASTM D 1784, Type 1120. Provide ASTM D 2467 Schedule 80 fittings, ASTM D 2564 solvent cement. Joints shall be solvent welded, meeting requirements of ASTM D 2855. 2.2.3.2 Provide screwed joints and flanges as required to connect dissimilar pipe materials, valves, equipment, and appurtenances. WW Associates Project No. 213003.05 02730/3 2.2.3.3 Schedule 80 PVC piping manufacturer shall be Charlotte Pipe and Foundry Company, P.O. Box 35430, Charlotte, North Carolina 28235 or approved equal. 2.3 Valves 2.3.1 Ball valves for service with polyvinyl chloride (PVC) piping shall be constructed of ASTM D 1784 PVC body, ball, carrier, and stem with reversible PTFE ball seat and FPM (Viton) “o” rings and gaskets. Socket welded construction shall be PVC full port, True Union (Double Union/Double Block through 3-inch diameter) design. Flanged construction shall be PVC flanges conforming to 150-pound drilling. Provide locking handle for ball valves at locations as indicated on the drawings. Valves shall be suitable for 150-psi nonshock cold water service at 70°F. Valves shall be Chemtrol or Hayward. No leakage shall be allowed. 2.4 Valve boxes shall be adjustable cast iron valve boxes of the three-piece type, consisting of lid, two-piece screw-type extension, and base. Base shall be proper type and size for the valve with which it is used. The word “SEWER” shall be cast or embossed on the valve box lid in letters not less than 1-inch high. Valve boxes shall be manufactured by Mueller Company, Dewey Brothers, Tyler, or BinghamTaylor. 2.5 Flexible couplings for connecting pipes of dissimilar materials shall be as manufactured by Fernco of Davison, Michigan or approved equal. 2.6 Flexible couplings for ductile iron piping shall be of a gasketed, sleeve type. Each coupling shall consist of a steel middle ring, two steel followers, two rubber compounded wedge section gaskets, and sufficient galvanized track head steel bolts to properly compress the gaskets. Couplings shall be of the type to match piping in which installed. Couplings shall be Style 38 manufactured by Dresser Manufacturing Division of Dresser Industries, Smith-Blair Products of Rockwell International, or approved equal. All couplings shall be provided with tie rod restraint. 2.7 Flange adapters for joining plain-end pipe to flanged items shall be Style 127 or 128 as manufactured by Dresser Manufacturing Division of Dresser Industries, SmithBlair Products of Rockwell International, or approved equal. 2.8 Pipe Labeling 2.8.1 Above grade piping 1-inch in diameter and larger shall be labeled. Provide labeling every 15 linear feet of pipe and spell out the pipe system. Labels shall be either black for light colored piping or white for dark colored piping. 2.8.2 Detectable tape shall be provided for all below grade piping systems and shall have a metallic core protected by a plastic jacket. The tape shall be continuously marked indicating that a sewer line is buried beneath the tape. WW Associates Project No. 213003.05 02730/4 In addition, a continuous No. 14 gauge copper wire with protective coating shall be provided for all below grade piping systems as indicated on the drawings. 2.9 Manholes 2.9.1 Precast Reinforced Concrete Manhole Section 2.9.1.1 Precast reinforced concrete manhole sections shall meet requirements of ASTM C 478. Section ends shall have o-ring gasket groove provided during manufacturing process. Gaskets for section joints shall meet requirements of ASTM C 443. Joints may also be sealed with flexible butyl resin sealant as manufactured by Concrete Sealants, Inc. or approved qual. Sealant shall be installed in accordance with the manufacturer’s written recommendations. Top sections for all manholes shall be designed to withstand HS-20 traffic loading. 2.9.1.2 Protective coating for concrete manhole section interior shall be two coats of coal tar solution such as International protective coat “Intertuf 100” or Pittsburgh Paint “Coal Cat 97-640/97-641” or manufactured with calcareous aggregate so that the finished product shall have an AZ factor equal to 90. 2.9.2 Manhole frames and covers shall be roadway type with deep socket covers. Machine frames and covers to prevent rattling. Frames shall be provided with holes for bolting it down to manhole riser section. Provide cover with two 3/4-inch diameter holes for ventilation. Castings shall be gray iron meeting requirements of ASTM A 48, Class 30, and have 24-inch diameter clear openings such as Neenah Foundry Company Type R-1642 with Type “C” cover by U.S. Foundry, East Jordan Iron Works, or approved equal. Each cover shall have cast or embossed on it in letters not less than 1-inch high “SANITARY SEWER” The frame and cover shall weigh at least 277 pounds. 2.9.3 Manhole frames shall be anchored to the top of the manhole riser sections with 3 /4-inch expansion bolts. Two passes of “ConSeal” bitumastic sealant or approved equal in 1-inch rope form shall be used to provide watertight seal between frame and manhole riser section. Clean manhole riser and frame thoroughly prior to installation. 2.9.4 Manhole steps shall be “Surefoot” step constructed of a No. 4 steel reinforcing rod encased in corrosion-resistant rubber by Oliver Tire & Rubber Company or approved equal. 2.9.5 Pipe to manhole connection shall be sealed with a flexible boot, gasket, sleeve, or as detailed on drawings and meet requirements of ASTM C 923. WW Associates Project No. 213003.05 02730/5 2.9.5.1 When the boot is used, the port shall be cored to the size, shape, surface finish, and location required and not cast in the manhole. Angular adjustments through 20º shall be allowed. The flexible boot shall be a 3/8-inch thick neoprene compound meeting ASTM C 443 specifications. The boot shall be secured to the port with an internal aluminum expanding band and to the pipe with a nonmagnetic corrosion resistant steel external band. Boot seal shall be “Kor-NSeal” as manufactured by National Pollution Control Systems, Inc. or approved equal. 2.9.5.2 When gasket is used, the gasket shall be a rubber pressed wedge gasket cast into the manhole with a maximum deflection of 15º as manufactured by Press-Seal Gasket Corporation or approved equal. 2.9.5.3 When sleeve is used, the sleeve shall be a flexible rubber sleeve cast into the manhole complete with stainless steel strap as manufactured by Interpace Corporation or approved equal. 2.10 Sleeves through concrete or masonry walls or slabs shall be cast iron or Schedule 40 steel. Provide sleeves through walls, floors, and ceilings for all pipe penetrations except where wall pipes are indicated. 2.11 Pipe to sleeve sealant shall be grouting compound. Grouting compound shall be as manufactured by 3M Company or be an equivalent product having tensile strength of 80 psi and elongation property of 700% in accordance with ASTM D 3574 Test E, and linear dimension change shall not exceed 18% when subject to wet and dry cycles in accordance with ASTM D 756, Procedure G and ASTM D 1042. 2.12 Mechanical Type Pipe to Wall Sleeve Seals: Mechanical type pipe to wall sleeve seals shall be “Link-Seal” pipe to wall closures manufactured by Thunderline Corporation, Wayne, Michigan or approved equal. Seals shall be modular mechanical type, consisting of interlocking synthetic rubber links shaped to fill annular space between pipe and wall opening and shall provide watertight seal between pipe and wall opening. 3 E XE C U T IO N 3.1 Inspection and Preparation: Prior to all piping work, carefully inspect the installed work or excavation by other trades and verify that all such work is complete to the point where the piping may installed in accordance with these documents. Follow the drawings in laying out work and check drawings of other trades to verify sufficient space to install piping. Undimensioned drawings are intended to indicate the general arrangement of piping systems and are not intended to convey precise locational information. Coordinate with other trades to permit all phases of the work to be installed. Offsets, fittings, and extra pipe, necessary to avoid interference or provide maximum headroom and space shall be furnished and installed without additional expense to the Owner. If the piping is installed without coordinating with WW Associates Project No. 213003.05 02730/6 other phases of the work and so as to cause interference, the necessary changes shall be made at no additional cost to the Owner. 3.2 Installation: Run piping concealed in finished areas unless otherwise indicated. Run piping exposed in equipment rooms, service areas, or areas with no means or need for concealment. Excessive cutting and similar operations likely to weaken a building structure to facilitate the piping installation will not be permitted. Implement suitable measures throughout the construction period to prevent trash and dirt from entering pipes, before, during, and after installation. Unless otherwise indicated, run piping parallel to the walls of the building. Erect vertical piping straight and plumb, with risers centered in pipe sleeves. Offsets shall conform to offsets in the building construction. Coordinate the work to insure that sleeves and inserts are positioned accurately along with other built-in items, before concrete pouring takes place, and before walls, partitions, and ceilings or roofs are erected so as to reduce to an absolute minimum the necessity for cutting or patching at a later stage. 3.3 Take all precautions necessary to insure that pipe, valves, fittings, and related items are not damaged in unloading, handling, and placing in trench. Examine each piece of material just prior to installation to determine that no damage has occurred. Remove any damaged material from the site and replace with undamaged material. 3.3.1 Keep pipe clean. Exercise care to keep foreign material and dirt form entering pipe during storage, handling, and placing. Close ends of in-place pipe at the end of any work period to prevent entry of animals and foreign material. 3.3.2 Bed pipe in accordance with Section 02200 – Earthwork and as detailed on the drawings. 3.3.3 Do not lay pipe when weather or trench conditions are unsuitable. 3.4 Lay gravity sewers so as to maintain a true alignment and grade as indicated on drawings. After completion, the pipe shall exhibit a full circle of light when lighted at one manhole and viewed from the next. 3.4.1 Commence laying gravity sewers at the lowest point on a section of line and lay pipe with the bell ends uphill. 3.4.2 Pipe Joint: Preparatory to making pipe joints on gravity sewer lines, clean and dry all surfaces of joint pipe and jointing material. Use lubricants, primers, adhesives, and similar materials as recommended by the manufacturers. Place, fit, join, and adjust the jointing materials or factory fabricated joints as recommended by manufacturer to obtain the degree of watertightness required. As soon as possible after the joint is made, place sufficient backfill material, as specified in Section 02200 – Earthwork, along each side of pipe to resist forces that might tend to move pipe off line and grade. WW Associates Project No. 213003.05 02730/7 3.4.3 Backfill as specified in Section 02200 - Earthwork. Place backfill over the pipe immediately after the pipe has been laid. 3.5 Join push-on joint pipe as follows: 3.5.1 Thoroughly clean inside of the bell and 8 inches of the outside of the spigot end of the joining pipe to remove oil, grit, excess coating, and other foreign matter. Flex rubber gasket and insert in the gasket recess of the bell socket. Apply a thin film of gasket lubricant supplied by pipe manufacturer to either the gasket or the spigot end of the joining pipe. 3.5.2 Start spigot end of pipe into socket with care. The joint shall then be completed by forcing the plain end to the bottom of the socket with a forked tool or jack type device. Field cut pipe shall have the end filed to match the manufactured spigot end. 3.5.3 Join restrained push-on joints as recommended in writing by the manufacturer. 3.5.4 Permissible deflection of push-on joint pipe shall not be greater than listed in AWWA C600. 3.5.5 Permissible deflection in restrained push-on joint pipe shall be as recommended in writing by the manufacturer. 3.6 Join restrained push-on joint ductile iron pipe as recommended in writing by the manufacturer. Permissible deflection in restrained joint pipe shall be as recommended in writing by the manufacturer. 3.7 Join polyvinyl chloride (PVC) pipe using rubber ring gaskets in bell joints as recommended in writing by the manufacturer. Join and assemble solvent welded PVC pipe joints in accordance with requirements of ASTM D 2855. 3.8 Join pipe of different materials by using Fernco couplings or approved equal in accordance with the manufacturer’s written recommendations. 3.9 Set Valves and Valve Boxes as follows: 3.9.1 Equip all underground valve operators with valve boxes. Set box in alignment with valve stem centered on valve nut. Set valve box to prevent transmitting shock or stress to the valve. Set box cover flush with the finished ground surface or pavement. 3.10 Construct manholes using precast reinforced concrete manhole sections except as otherwise noted. Install manhole frames and covers and manhole steps using materials specified under products. WW Associates Project No. 213003.05 02730/8 3.11 Construct manhole channel with smooth semicircular bottoms matching inside diameters of the connecting sewers. Change directions of flow with a smooth curve of as large a radius as the manhole size will permit. Change size and grade of channels gradually and evenly. Channels may be formed directly in the concrete manhole bottom, made of channel pipe, laid in concrete, or constructed by laying full section sewer pipe through the manhole and breaking out the top half when the surrounding concrete has hardened. Manhole floors outside the channels shall be smooth and shall have slope between 2 and 4 inches per foot toward the channels. 3.12 Install precast concrete valve structures in accordance with the manufacturer’s written recommendations. Provide clean coarse aggregate fill beneath each structure in accordance with Section 02200 – Earthwork and as indicated on the drawings. 3.13 Construct concrete cap or cradle in accordance with the latest edition of the VDOT Road and Bridge Standards at locations where the vertical separation between the new sanitary sewer and adjacent utilities is less than 6 inches. 3.14 Use wall pipes or sleeves where pipes, valves, stem extensions, or equipment parts pass through concrete or masonry walls or slabs. Sleeves shall be or sufficient size to allow sealing around pipes and clearance for valve stem or equipment. Extend vertical sleeves through slabs 1-inch above top surface. 3.14.1 Use cast iron or steel sleeves with intermediate collars to anchor and provide water stops on sleeves that pass through exterior walls below grade. Seal around pipes using grouting compound or “Link-Seal” pipe to wall closures manufactured by Thunderline Corporation, Wayne, Michigan. Seals shall be modular mechanical type, consisting of interlocking synthetic rubber links shaped to fill annular space between pipe and wall opening and shall provide watertight seal between pipe and wall opening. Grouting compound shall be mixed and placed in accordance with the recommendations of the manufacturer. Mechanical pipe to wall seal shall be installed in accordance with the written recommendations of the manufacturer. 3.15 For buried pressure piping, provide retainer gland type devices, restraining devices, or restrained joint type pipe at all changes in direction of pressure piping, at dead ends, and as shown on the drawings. 3.15.1 Restrain all joints with retainer glands/devices in accordance with the written recommendations of the retainer gland/device manufacturer. All pipe joints shall be restrained with retainer glands/devices a minimum of 60 feet each side of a fitting or valve. 3.15.2 Where retainer glands/devices are used, extreme care shall be taken so that each set screw is tightened as recommended by the manufacturer before the pipe is backfilled and tested. WW Associates Project No. 213003.05 02730/9 3.16 Install detectable tape in trench above all pipe per the manufacturer’s written recommendations. Install continuous copper wire in trench above all pipe as indicated on the drawings. 3.17 Pressure pipe tests shall be as follows: 3.17.1 Supply the pumps, potable water, calibrated gages and meters, and all the necessary apparatus. 3.17.2 Hydrostatic Pressure Test: After the line has been backfilled, a hydrostatic pressure test shall be performed using potable water. Carefully fill the system with potable water at a velocity of approximately 1 foot per second while necessary measures are taken to eliminate all air. After the system has been filled, raise the pressure by pump to 1.5 times the working pressure. Measure pressure at lowest point in the system with gauge compensated for elevation. Maintain this pressure for at least 2 hours. If pressure cannot be maintained, determine the cause, repair, and repeat the test until successful. 3.17.3 Following the hydrostatic pressure test, subject the system to a leakage test. Use calibrated meter to determine leakage. Leakage shall be defined as the quantity of potable water that must be supplied into the pipe to maintain working pressure, after all air in the pipe line has been expelled and the pipe has been filled with potable water. Duration of leakage test shall be 2 hours. Leakage shall not exceed the quantity determined by the formula, find and repair the leaks and repeat the test until successful. The formula is as follows. L = SD (√P)/148,000 Where: L = Allowable leakage in gallons/hour S = Lengths of pipeline tested in feet D = Nominal diameter of the pipe in inches P = Average test pressure during leakage test in psig 3.17.4 Repairs: If piping or valves fail to meet test requirements, or if any leaks, crooked pipe, or other defects are visible by inspection, the Contractor shall repair or rebuild at his expense those portions of pressure piping which are faulty. The tests and repairs shall be continued until the pressure piping is deemed acceptable. 3.18 Testing Gravity Sewer Lines 3.18.1 Low pressure air testing in accordance with UNI-B-6 may be used on polyvinyl chloride (PVC) sanitary sewer lines. Low pressure air testing in accordance with ASTM C 924 may be used on all other sanitary sewer lines 24 inches or less in diameter. All manholes shall be tested using the infiltration method, exfiltration method, or vacuum testing. Tests shall be WW Associates Project No. 213003.05 02730/10 conducted on short sections of sewer line; i.e., between manholes, or at the end of each day’s work. Installation of sewers will not be permitted at a point more than 2,000 feet ahead of any section of sewer or any manhole which has not been given the final test and accepted. The Contractor shall provide all labor, materials, tools, and equipment necessary to make the tests. All monitoring gauges shall be subject to calibration, if deemed necessary. All sewer lines, regardless of size, that cross above or below streams shall be tested for and exhibit zero infiltration or exfiltration. 3.18.2 Low Pressure Air Test 3.18.2.1 Summary of Method: After the backfill has been placed and compacted to a minimum depth of 1 foot over the pipe, plug the section of the sewer line to be tested. Introduce low-pressure air into the plugged line. 3.18.2.2 Preparation of the Sewer Line: Flush and clean the sewer line prior to testing, thus serving to wet the pipe surface as well as clean out any debris. A wetted interior pipe surface will produce more consistent results. Plug all pipe outlets using approved pneumatic plugs with a sealing length equal to or greater than the diameter of the line that is being tested. Give special attention to laterals. 3.18.2.3 Groundwater Determination: Install a 1/2-inch capped galvanized pipe nipple, approximately 12 inches long, through the manhole. Immediately prior to the line test, the groundwater elevation shall be determined by removing the pipe cap and blowing air through the pipe nipple into the ground so as to clear it, and then connecting a clear plastic hose to the pipe nipple. The hose shall be held vertically and a measurement of the height in feet of water over the invert of the pipe shall be taken after the water has stopped rising in the plastic hose. 3.18.2.4 Procedures 3.18.2.4.1 Determine the test duration for the section under test by computation from the applicable formulas shown in ASTM C 924, or from the following “Air Test Table.” The pressure-holding time is based on an average holding pressure of 3 psi (21 kPa) gauge or a drop from 3.5 psi (24 kPa) to 2.5 psi (17 kPa) gauge. The tests shall be conducted between two consecutive manholes or as directed. 3.18.2.4.2 The test section of the sewer line shall be plugged at each end. One of the plugs used at the manhole shall be WW Associates Project No. 213003.05 02730/11 tapped and equipped for the air inlet connection for filling the line from the air compressor. 3.18.2.4.3 All service laterals, stubs, and fittings into the sewer test section shall be properly plugged and carefully braced against the internal pressure to prevent air leakage by slippage and blowouts. 3.18.2.4.4 Connect air hose to tapped plug selected for the air inlet. Then connect the other end of the air hose to the portable air control equipment which consists of valves and pressure gages used to control the air entry rate to the sewer test section and the air pressure in the pipe line. 3.18.2.4.5 More specifically, the air control equipment shall include a shutoff valve, pressure regulating valve, pressure reduction valve, and a monitoring pressure gauge having a pressure range from 0 to 10 psi. The gauge shall have minimum divisions of 0.10 psi and an accuracy of plus or minus 0.04 psi. 3.18.2.4.6 Connect another air hose between the air compressor (or other source of compressed air) and the air control equipment. This completes the test equipment setup. Test operations may commence. 3.18.2.4.7 Supply air to the test section slowly, filling the pipe line until a constant pressure of 4.0 psig is maintained. The air pressure shall be regulated to prevent the pressure inside the pipe from exceeding 10.0 psig. 3.18.2.4.8 When constant pressure of 4.0 psig is reached, throttle the air supply to maintain the internal pressure above 3.5 psig for at least 5 minutes. This time permits the temperature of the entering air to equalize with the temperature of the pipe wall. During this stabilization period, check all plugged fittings with a soap solution to detect any leakage at these connections. If leakage is detected at any plug, release the pressure in the line and tighten all leaky plugs. Then start the test operation again by supplying air. When it is necessary to bleed off the air to tighten or repair a faulty plug, a new 5-minute interval shall be allowed after the pipe line has been refilled. WW Associates Project No. 213003.05 02730/12 3.18.2.4.9 After the stabilization period, shut off or disconnect the air supply. Before starting the test, the pressure may be allowed to drop to 3.5 psig. Record the drop in pressure for the test period. If the pressure has dropped more than 1.0 psi (7 kPa) gauge during the test period, the line shall be presumed to have failed. The test may be discontinued when the prescribed test time has been completed even though the 1.0 psig drop has not occurred. 3.18.2.4.10 If the pipe to be tested is submerged in groundwater, the test pressure shall be increased 1.0 psi for every 2.31 feet the groundwater level is above the invert of the sewer. 3.18.2.4.10.1 Example: If the vertical height of water from the sewer invert to the top of the water column measures 4.62 feet, the additional air pressure required would be 4.62 divided by 2.31 equals 2 psi. 3.18.2.4.10.2 Therefore, the starting pressure of the test would be 3.5 plus 2 or 5.5 psig, and the 1.0 psig drop would be to 4.5 psig. There is no change in the allowable drop (1.0 psig) or in the time requirements established for the basic air test. 3.18.2.5 Safety: The air test may be dangerous if, because of lack of understanding or carelessness, a line is improperly prepared. 3.18.2.5.1 It is extremely important that the various plugs be installed and braced in such a way as to prevent blowouts. A force of 250 pounds is exerted on an 8-inch (203 mm) plug by an internal pipe pressure of 5 psi (34 kPa), it should be realized that sudden expulsion of a poorly installed plug or of a plug that is partially deflated before the pipe pressure is released can be dangerous. 3.18.2.5.2 As a safety precaution, pressurizing equipment shall include a regulator or relief valve set at 10 psi (69 kPa) to avoid over-pressurizing and damaging an otherwise acceptable line. No one shall be allowed in the manholes during testing. WW Associates Project No. 213003.05 02730/13 3.18.2.6 Table: The air test table at the end of this section has been prepared utilizing applicable formulas from ASTM C 924. 3.19 Manhole Testing 3.19.1 All manholes shall be tested using the infiltration method, exfiltration method, or vacuum testing. 3.19.2 Infiltration or Exfiltration Method: All pipes leading to and from a manhole shall be plugged. Plugs shall be inserted into the pipes a distance greater than the length of the plugs used to test each respective section of sewer line to insure the manhole and sewer line tests overlap. Plugs shall be secured to the manhole structure. The manhole shall be filled with potable water to the top of frame and allowed to soak for a minimum of 2 hours and a maximum of 12 hours to permit the manhole to absorb water. The cover shall be on the manhole during the soaking period. At the end of the soaking period, potable water shall be added until the manhole overflows. After 30 minutes, check difference in level and convert to gallons. Manhole leakage shall not exceed 1 /4-gallon per hour. Upon completion of the test, the water shall be removed from the manhole. 3.19.3 Vacuum Testing: The vacuum test shall be made using an inflatable compression band, vacuum pump, and appurtenances specifically designed for vacuum testing manholes. Test procedures shall be in accordance with ASTM C 1244, except the more restrictive requirements specified herein. Equipment shall be manufactured by Peter A. Glazier, Inc., P.O. Box 1002, Worcester, Massachusetts 01613, Telephone: (508) 755-3849, Toll-Free: (800) 822-6488, or approved equal. 3.19.3.1 Manholes may be tested by vacuum test immediately after assembly of the manhole, frames, and connecting pipes and before any backfill is placed around the manholes. However, the final test and acceptance shall be based only upon a test after the manhole is backfilled and the cover frame castings are set in place. 3.19.3.2 All lift holes shall be plugged with nonshrink grout and all pipes shall be plugged, taking care to securely brace the plugs and pipe. 3.19.3.3 After the testing equipment is in place, a vacuum of 10 inches of mercury shall be drawn on the manhole. The manhole will be considered to have passed the test if the vacuum does not drop more than 1-inch of mercury within 60 seconds for manholes 7 feet in depth or less and 90 seconds for manholes over 7 feet deep. 3.19.3.4 If the manhole fails the initial test, the Contractor shall locate the leakage and make proper repairs, and retest until a satisfactory test result is obtained. WW Associates Project No. 213003.05 02730/14 3.19.3.5 After the manholes have been backfilled and the cover frame casting sealed in place, and prior to final acceptance of the project, any signs of leaks or weeping visible from the inside of the manhole shall be repaired, and the manhole made watertight and tested. 3.20 Test for leakage of gravity sewers including manholes, using either the infiltration or exfiltration method. Maximum allowable leakage shall be limited to 2,400 gallons per day per mile or 100 gallons per day per inch diameter per mile, whichever is less. 3.20.1 Use infiltration test when groundwater is at least 4 feet above top of the pipe for the entire length of line to be tested. Plug the pipe at the upper manhole. Install suitable measuring device at the next lowest manhole. Measure the amount of water flowing through the measuring device over a 30-minute period. Sewer lines crossing under streams shall exhibit zero infiltration. 3.20.2 Use exfiltration test when groundwater is less than 4 feet above top of pipe. Plug the pipe at the lower manhole. Fill the line and manhole with potable water to 4 feet above top of pipe, or top of manhole whichever is less. Let the water stand until pipe has reached maximum absorption and until all trapped air has escaped, 12-hour minimum. After maximum absorption is reached, refill manhole to original level. After 30 minutes, record difference in level and convert to gallons. 3.20.3 Groundwater Determination: Use same procedure as “Low Pressure Air Test” above. 3.21 Repairs: If sewer lines or manholes fail to meet test requirements or if any leaks, crooked pipe, or other defects are visible by inspection, the Contractor shall repair or rebuild at his expense those portions of sewer lines which are faulty. The tests and repairs shall be continued until the sewer line is deemed acceptable. Air Test Table Based on Formulas from ASTM C 924 Minimum Test Time in Minutes: Seconds For Pressure Drop From 3.5 to 2.5 psig Line Length in Feet 10 50 100 150 200 250 300 350 400 450 500 0:02 0:09 0:18 0:27 0:36 0:45 0:54 1:03 1:12 1:21 1:30 Pipe Size Inches 4 WW Associates Project No. 213003.05 02730/15 6 0:04 0:21 0:42 1:03 1:24 1:45 2:06 2:27 2:48 3:09 3:30 8 0:07 0:36 1:12 1:48 2:24 3:00 3:36 4:12 4:48 5:24 6:00 End of Section WW Associates Project No. 213003.05 02730/16 Section 02735 Pipe Supports and Anchors 1 GENERAL 1.1 Reference specifications are referred to by abbreviation as follows: 1.1.1 American National Standards Institute ......................................................ANSI 1.1.2 American Society for Testing and Materials ........................................... ASTM 1.1.3 Manufacturers Standardization Society of the Valve and Fittings Industry ..................................................................... MSS 1.2 Piping systems shall be supported in accordance with ANSI B31.1 “Power Piping” so as to maintain required pitch of lines, prevent vibration, and provide for expansion and contraction movement. Provide hangers in accordance with MSS SP-58 and MSS SP-69. Provide all supports required whether shown on the drawing or not. 1.3 Acceptable Manufacturer: Anvil, Elcen Metal Products, F&S Central, or Michigan Hanger Company. Anvil figure numbers establish the quality standard. 2 PRODUCTS 2.1 Hangers and Rigid Supports 2.1.1 Adjustable swivel split ring hanger shall be fabricated of black malleable iron and be approved by Factory Mutual and be UL listed. Hanger shall be Anvil Figure 104 or approved equal. 2.1.2 Adjustable clevis type hanger shall be black carbon steel and be approved by Factory Mutual and be UL listed. Hanger shall be Anvil Figure 260 or approved equal. 2.1.3 Pipe roll hangers shall consist of a cast iron roll and steel roll rod. Hanger shall be Anvil Figure 171 or approved equal. 2.1.4 Brackets shall be heavy welded carbon steel, of dimensions required to adequately support piping. Brackets shall be hot dipped galvanized after fabricated in accordance with ASTM A 123. Brackets shall be Anvil Figure 199 or approved equal. 2.1.5 U-bolts shall be standard weight, hot dipped galvanized carbon steel, furnished with four finished hex nuts. U-bolts shall be Anvil Figure 137 or approved equal. WW Associates Project No. 213003.05 02735/1 2.1.6 Short strap shall be carbon steel, Anvil Figure 262 or approved equal. One-hole clamp shall be black finished malleable iron, Anvil Figure 126 or approved equal. 2.1.7 Adjustable pipe saddle support shall be cast iron saddle, locknut nipple, and cast iron reducer, factory assembled. Stantion type support shall allow vertical adjustment by turning locknut nipple. Adjustable pipe saddle support shall be Anvil Figure 264 or approved equal. Adjustable pipe saddle support shall include pipe stand with base flange of suitable size to carry load. Provide expansion anchors for connecting base flange to finished floor, minimum four anchors required. 2.2 Hanger rods shall be ASTM A 575 or A 576 hot rolled carbon steel and meet mechanical property requirements of ASTM A 663. 2.3 Beam clamps shall be fabricated specifically for the structure to which the hanger rod is attached. 3 E X E C U T IO N 3.1 Install rigid pipe hangers as follows: 3.1.1 Uninsulated pipe 2 inches and smaller – Anvil Figure 104 or approved equal. 3.1.2 All piping 21/2 inches and larger – Anvil Figure 260 or approved equal. 3.2 Where necessary due to space limitations, provide pipe roll hanger equal to Anvil Figure 171 or approved equal for piping 21/2 inches and larger. 3.3 Space supports or hangers for horizontal piping as follows unless otherwise indicated on the drawings. Provide additional supports for concentrated loads at valves or specialties. Nominal Pipe Size, Inches Maximum Span in Feet Steel or Iron Pipe Plastic Pipe 1 /2-inch 4 2 3 /4-inch through 11/2-inch 6 3 2-inch and 21/2-inch 10 4 3-inch 12 5 4-inch and 5-inch 14 6 6-inch 16 6 8-inch and 10-inch 18 7 12-inch and 14-inch 22 8 16-inch and 18-inch 27 - WW Associates Project No. 213003.05 02735/2 20-inch 30 - 24-inch 32 - 3.3.1 Provide pipe hanger or support within 18 inches or every change in direction for piping 11/2 inches and below and within 3 feet of every change in direction for piping 2 inches and larger. Horizontal “No-Hub” piping shall be supported at each joint. 3.3.2 Vertical Piping: Support metal piping at each floor, but at not more than 10foot intervals. Support plastic at each floor and at midpoint between floors, but not at more than 5-foot intervals. 3.4 Support hangers for pipe by using malleable iron or galvanized steel concrete inserts, concrete anchor bolts, beam clamps with lock nuts or retaining straps, or other special fastening devices, as required, for the support of hangers. As an option where direct attachment to frame members is not possible, auxiliary frame members may be provided which shall span at least two structural frame members. 3.4.1 Where pipe cannot be suspended from overhead supports, use substantial cast iron or welded steel wall brackets to support the hangers, pipe seats, or roll stands, as conditions demand. 3.5 Use hot rolled steel hanger rods sized as follows: 3.5.1 For 2-inch pipe and smaller – 3/8-inch diameter 3.5.2 For 21/2-inch through 31/2-inch pipe – 1/2-inch diameter 3.5.3 For 4-inch and 5-inch pipe – 5/8-inch diameter 3.5.4 For 6-inch pipe – 3/4-inch diameter 3.5.5 For 8-inch and larger – 7/8-inch diameter End of Section WW Associates Project No. 213003.05 02735/3 Section 02831 Chain Link Fences and Gates 1 GENERAL 1.1 Scope: The work covered by this section consists of furnishing all labor, equipment, and materials necessary to install all required chain link fencing and gates for the work. The contract documents apply to this Section. 1.2 Reference specifications are referred to by abbreviation as follows: 1.2.1 American Society of Testing and Materials .............................................. ASTM 1.2.2 Chain Link Fence Manufacturer’s Institute ............................................. CLFMI 1.3 Submittals 1.3.1 Submit shop drawings showing all details of the chain link fence, gates, and lock. 2 MATERIALS 2.1 Fence 2.1.1 All tubular members shall meet the requirements of ASTM A 120 for weight and coating. 2.1.2 All structural shapes shall meet the requirements of ASTM A 123 for galvanized coatings. 2.1.3 End, corner, and pull posts shall be 2-7/8 inch O.D. pipe weighing 5.79 pounds per linear foot. 2.1.4 Line posts shall be 2-3/8 inch O.D. pipe weighing 3.65 pounds per linear foot. 2.1.5 Swing gate post shall be 4-inch O.D. pipe weighing 9.11 pounds per linear foot. 2.1.6 Fit top posts with galvanized malleable iron fittings designed to exclude water from the post interior. The top shall have provisions for accommodating a rail. 2.1.7 A No. 7 gauge coiled spring tension wire having a zinc coating of 1.6 ounces of zinc per square foot of surface shall be provided along the bottom of the fence. Top of the fence shall be finished with a pipe rail of 1-5/8 inch O.D. weighing 2.27 pounds per linear foot. WW Associates Project No. 213003.05 02831/1 2.2 Bracing and Tensioning 2.2.1 Bands shall be unclimbable, beveled edge type, secured with 3/8-inch diameter square shouldered aluminum carriage bolts, nonremovable from outside the fence enclosure. 2.2.2 All terminal posts shall have 1-5/8 inch O.D. horizontal compressive member braces, securely attached to terminal and first line posts with malleable iron fittings and bevel edge bands. Provide 3/8-inch diameter rod and turnbuckle truss braces from first line post to bottom of terminal post. 2.2.3 Tension bars for attaching fence fabric to terminal posts shall be 1/4-inch by 3/4inch high carbon steel, and shall be attached to terminal posts with of beveled edge bands. 2.3 Fabric 2.3.1 Fencing fabric shall consist of individual wire pickets, helically wound, and interwoven from 9 gauge copper bearing steel wire to form a continuous chain link fabric in 2-inch mesh. Top and bottom edges of the fabric shall have a twisted and barbed finish, and fabric shall be 6 feet in height between top and bottom edges. 2.3.2 Fence fabric edging shall be barbed top and bottom 2.3.3 The wire in the completed fabric shall have a tensile strength of not less 80,000 pounds per square inch. 2.4 Gates, Frames, and Hardware. 2.4.1 Swing gate frames shall be minimum 2 inches, O.D. standard weight steel pipe with interval bracing of 1-5/8 inch O.D. standard weight steel pipe. Frame members shall be welded at all joints to insure a watertight construction. 2.4.2 Fabric for gates shall be as specified for fence. 2.4.3 Hinges shall be standard offset type that will allow gates to swing back parallel with line fence. Hinge material shall be malleable iron or steel forgings. 2.4.4 Double latches shall be drop-bar type, securely bolted to the gate frames and designed to engage heavy malleable iron gate stops anchored in concrete footings. 2.4.5 Single latches for gate frames up to and including 8 feet wide shall be malleable iron, gravity type, designed to automatically engage a pin welded to the gate frame and to be secured with an approved type padlock. WW Associates Project No. 213003.05 02831/2 2.4.6 Gate shall be equipped with a gate keeper designed to engage with the gate when opened wide to secure it in this position. 2.4.7 Provide a padlock for the gate. Padlock key shall match “Best” keying system. 2.4.8 Provide diagonal cross-bracing consisting of a 3/8-inch diameter adjustable length truss rods on gates where necessary to provide frame rigidity without sag or twist. 2.5 All miscellaneous fence fittings shall be malleable iron, pressed steel, aluminum, or forgings. All miscellaneous ferrous metals shall be hot dipped galvanized. 2.6 Wire ties for tying fabric to post shall be minimum No. 9 gauge aluminum or steel for tubular posts. No. 9 gauge aluminum wire ties shall be used to tie fabric to rails and braces. No. 11 gauge pig rings shall be used to tie fabric to tension wire. Finish for coil wire, pig rings, and wire ties shall be the same as fencing fabric. 3 E X E C U T IO N 3.1 General 3.1.1 Space posts no more than 10 feet on center. 3.1.2 Encase post in concrete footings at least 3 feet in depth. There shall be a minimum of 6 inches of concrete below the post. Provide 10-inch diameter footings for line posts and 14-inch diameter footings for corner, end, and gate posts. Extend footings 2 inches above the ground line and slope to drain away from posts. 3.1.3 Where rock is encountered, drill holes 3 feet deep and 2 inches greater than the outside diameter of the post. Then fill hole around the post with grout. The post shall be 6 inches off the bottom the hole. 3.1.4 Where the fence is located on concrete structures, cast or grout a 18-inch section of steel pipe with an inside diameter at least 2 inches larger than the post into the structure. Grout the fence post into the steel pipe. 3.1.5 Brace terminal posts with horizontal compressive member and truss braces and fittings. 3.1.6 Brace corner posts in each direction with the bracing specified for terminal posts. 3.1.7 Brace line fence at not more than 500 foot intervals and each vertical angle point of 15 degrees or more with the bracing specified for terminal posts. 3.1.8 Install corner posts at each horizontal angle point. WW Associates Project No. 213003.05 02831/3 3.1.9 Install fence uniformly 2 inches above the ground. 3.1.10 Fasten fabric to top rail and bottom tension wire at intervals of 2 feet with pig rings. 3.1.11 Attach fabric to all posts at intervals of not more than 14 inches and on the outside of the post with relation to the enclosed area. 3.1.12 Bend ends of wire ties to minimize hazard to persons and clothing. 3.1.13 Attach stretcher bars to terminal posts with beveled edge band. 3.1.14 Install gates plumb, level and secure for full opening without interference. Install ground-set items in concrete as recommended by the manufacturer. Adjust and lubricate all hardware as required for smooth operation. 3.1.15 Install gate stops so that the plunger can be fully engaged. 3.1.16 Install nuts for tension band and hardware bolts on the inside of the fence. End of Section WW Associates Project No. 213003.05 02831/4 Section 02936 Seeding 1 GENERAL 1.1 Related Requirements: The following sections contain requirements that relate to this section. 1.1.1 Section 01400 – General Requirements 1.1.2 Section 02200 – Earthwork 1.2 Submittals: Provide the following items in accordance with the approved submittals schedule as specified in Section 01400 – General Requirements: 1.2.1 Seed Test Report 1.2.2 Fertilizer Analysis 1.3 Reference specifications are referred to by abbreviation as follows: 1.3.1 American Society of Testing and Materials .............................................. ASTM 1.3.2 Virginia Department of Transportation .................................................... VDOT 2 PRODUCTS 2.1 Topsoil: Topsoil shall be the top 6 inches of original soil from the site. Topsoil obtained off-site shall be fertile, friable loam, containing not less than 2% by weight of finely divided, decomposed vegetation. Topsoil shall be free of subsoil, clay lumps, brush, weeds, roots larger than 11/2-inch in diameter, stones larger than 11/2inch in diameter, and other material toxic or harmful to growth. 2.2 Fertilizer: Fertilizer shall meet requirements of Federal Specification O-F-241. Provide fertilizer that is complete, inorganic, uniform in composition, and suitable for application with approved equipment. Proportions of fertilizer nutrients shall be the following: 2.2.1 Permanent Seeding 2.2.1.1 5% total nitrogen 2.2.1.2 10% available phosphoric acid 2.2.1.3 5% soluble potash WW Associates Project No. 213003.05 02936/1 2.2.2 Temporary Seeding 2.2.2.1 10% total nitrogen 2.2.2.2 20% available phosphoric acid 2.2.2.3 10% soluble potash 2.3 Grass Seed: Grass seed, tested within 6 months of sowing, shall have the following characteristics: 2.3.1 Permanent Seeding Species Kentucky 31 tall fescue Merion Kentucky bluegrass Kenblue Kentucky bluegrass % Weight % Purity % Germination 90 98 90 5 90 75 5 85 75 2.3.2 Temporary Seeding Seeding Date Species % Wgt. % Purity % Germ. Feb 15-Apr 30 Oats 100 98 May 1-Aug 15 Millet 100 98 Aug 16-Nov 15 Rye 100 96 85 80 85 Speed Rate (lb/acre) 100 50 140 2.4 Lime: Lime shall be ground agriculture grade limestone containing not less than 85% calcium and magnesium carbonates. Fineness shall be such that 100% will pass a No. 20 sieve, and not less than 50% will pass a No. 100 sieve. Burnt lime or hydrated lime may be substituted in equivalent carbonates, if requested. 2.5 Mulch: Type II mulch composed of threshed straw of cereal grain, pine needles or wood fiber which shall be free of objectionable weed seeds or other harmful material. 2.6 Asphalt Adhesive: Asphalt adhesive for use with Type II mulch shall be emulsified asphalt meeting requirements of ASTM D 977, Grade SS-1. 2.7 Mulch Binder: Synthetic mulch binder for use with Type II mulch shall be Curasol, DCA-70 Petroset, or Terra Tack. 2.8 Jute Mesh: Jute mesh shall be as defined in the VDOT Road and Bridge Specifications, Section 244, “Roadside Development Materials.” WW Associates Project No. 213003.05 02936/2 3 EXECUTION 3.1 General 3.1.1 Before seeding, not less than 4 inches of topsoil shall be spread in areas to be seeded. In general, the topsoil shall come from the stockpiles created during the initial clearing of the site. If there is insufficient topsoil in the stockpiles, the Contractor shall provide topsoil from an offsite source at no additional cost to the Owner. 3.1.2 Material shall be delivered in unbroken containers, clearly marked by the manufacturer as to their contents. Seed, limestone, and fertilizer shall be labeled as to proportions, analysis, and quality. Store all materials in a manner affording protection from damage by weather or vandalism. 3.1.3 Seed only when the wind velocity is less than 15 miles per hour. 3.1.4 All areas disturbed by excavation, grading, or other construction operations, except areas to be paved or otherwise permanently stabilized, shall be seeded as specified for permanent seeding. Temporary seeding shall be provided when required at no additional cost to the Owner. 3.1.5 Remove all soiling or staining off finished structures or pavements resulting from seeding work. Maintain paved areas in clean condition. 3.2 Temporary Seeding 3.2.1 Use in areas when final grading has not been completed, when permanent seeding cannot be performed due to the specified permanent seeding dates, or when required for erosion control. 3.2.2 Apply fertilizer at a rate of 15 pounds per 1,000 square feet (600 pounds per acre) or equivalent. Apply lime at a rate of 50 pounds per 1,000 square feet. 3.2.3 For loose soil, work lime and fertilizer into soil and then seed. For packed or hard soil, loosen top layer while working lime and fertilizer into soil and then seed at the rate specified for the temporary seeding species. 3.2.4 Seed only between February 15 and November 15. Use mulch between November 15 and February 15. 3.3 Permanent Seeding 3.3.1 For all areas to receive permanent seeding, apply fertilizer at the rate of 25 pounds per 1,000 square feet and apply lime at the rate of 90 pounds per 1,000 square feet. WW Associates Project No. 213003.05 02936/3 3.3.2 Apply fertilizer and lime uniformly and mix well into the top 4 inches of the seedbed. 3.3.3 Prepare soil for permanent seeding by tillage of topsoil in place to loosen thoroughly and break up all clods to a depth of 6 inches. Remove all stumps and roots, coarse vegetation, stones larger than 11/2 inches, and all construction debris. Soil shall be worked by suitable agricultural equipment to a depth of not less than 4 inches. Surface shall be uniform, smooth, and drainable. A firm and compact seedbed is required. 3.3.4 Sow permanent grass seed between dates of March 1 and April 15 or September 1 and November 15. 3.3.5 Sow seed by mechanical seeder as follows: 3.3.5.1 Mix seed thoroughly with clean dry sawdust and broadcast at rate of 6 pounds of seed per 1,000 square feet for permanent seeding or as specified elsewhere for temporary seeding. 3.3.5.2 Apply Type II mulch uniformly to depth of approximately 1 1 / 4 inches. 3.3.5.3 Anchor Type II mulch by the following methods: 3.3.5.3.1 Apply light tack coat of asphalt emulsion or synthetic mulch binder. 3.3.5.3.2 On slopes steeper than 4 horizontal to 1 vertical, anchor with jute mesh fastened to wooden stakes. 3.3.6 Sow seed by hydraulic seeder as follows: 3.3.6.1 Prepare homogeneous slurry equal to the seed mixture used for mechanical seeding as specified in this section. 3.3.6.2 Distribute slurry uniformly at rate equal to the rate specified for mechanical seeding. 3.3.6.3 Apply mulch as specified for sowing by mechanical seeder. 3.4 Maintenance of Seeded Areas 3.4.1 Reseed and mulch spots larger than one square foot without uniform stand of grass. WW Associates Project No. 213003.05 02936/4 3.4.2 Maintain all seeded areas until uniform stand of grass is acceptable to the Engineer. 3.4.3 In the event that growth is not established by the final project inspection, continue the specified attention until the stand is accepted by the Engineer. 3.4.4 Correct or repair all undue settling for a period of one year after final inspection. 3.4.5 Water as necessary. 3.4.6 Mowing: Maintain grass height between 2 and 4 inches. End of Section WW Associates Project No. 213003.05 02936/5 Section 03300 Cast-In-Place Concrete 1 GENERAL 1.1 Reference publications are referred to by abbreviations as follows: 1.1.1 American Concrete Institute ACI 1.1.2 American Society for Testing and Materials ASTM 1.1.3 Concrete Reinforcing Steel Institute CRSI 1.1.4 National Institute of Standards and Technology 1.2 NIST Quality Assurance 1.2.1 Provide the services of an independent inspection agency to perform inspection as specified in this section. The inspection agency shall be approved by WW Associates. 1.2.2 The independent testing agency, including branch office used, referred to in this Section and Section 1 of ACI 301 shall meet the requirements of ASTM E 329 and shall have been inspected within the past 3 years by the cement and concrete reference laboratory of the NIST and shall have corrected any deficiencies noted. Project sponsor as defined in ASTM E 329 shall be the contractor. 1.3 Submittals: Provide the following in a timely manner. 1.3.1 Shop drawings of reinforcing steel in accordance with ACI 301. All construction joints shall be indicated on the shop drawings. 1.3.2 Complete concrete mix designs and documentation in accordance with ACI 301 Section 4.2.3 indicating compliance with one of the paths allowed in the flow chart. Include the following documentation: 1.3.2.1 Specific mix designs proposed. 1.3.2.2 Quantity and types of admixtures. 1.3.2.3 Strength test results used to establish standard deviation, and calculated standard deviation in accordance with ACI 301, Paragraph 4.2.3.2, if that procedure is followed. 1.3.2.4 Calculated required average compressive strength. 1.3.2.5 Strength test records used to verify that required average compressive strength is met in accordance with ACI 301, Paragraph 4.2.3.3, if that procedure if followed. WW Associates Project No. 213003.05 03300/1 1.3.2.6 Trial mixtures, strength test thereof, water-cement ratio curve, and selected water-cement ratio to meet the required average compressive strength in accordance with ACI 301, Paragraph 4.2.3.4.b, if that procedure is followed. 1.3.3 Manufacturer’s literature for the following: 1.3.3.1 Waterstops 1.3.3.2 Specific reference to ASTM D 471 for Rubber Properly-Effect of Liquite 1.3.3.3 List of materials and work requiring inspection; inspections to be performed; and a list of the individuals, approved agencies, and firms intended to be retained for conducting such inspections. These lists shall be submitted to WW Associates for approval and to the building official. 1.3.3.4 Inspection reports. 2 PRODUCTS 2.1 Concrete work shall meet the requirements set forth in ACI 350.2R-04 “Concrete Structures for Containment of Hazardous Materials.” 2.1.1 Compressure Strength – All concrete shall have a minimum compressure strength of 4,000 psi. 2.2 Concrete work shall meet applicable requirements of ACI 301-10 “Specifications for Structural Concrete,” except as modified by the supplemental requirements specified in this section. For numbers in parentheses, refer to ACI 301 paragraphs. 2.2.1 (1.6.4) All of the testing services of Sections 1.6.4.1, 1.6.4.2, and 1.6.4.3 shall be paid for by the Contractor. If the concrete is placed by pumping, the strength test shall be taken at the truck discharge and at the point of placement. 2.2.1.1 The testing representative shall sample concrete in accordance with the following schedule for each design mixture placed in any one day: Strength Tests 1 Set of 3 Cylinders per 50 CY or fraction thereof. Slump Test 1 Test per 50 CY or fraction thereof or if consistency varies WW Associates Project No. 213003.05 03300/2 Temperature 1 Test per 50 CY or fraction thereof Air Entrainment 1 Test per 50 CY or as necessary for control 2.2.2 (2.2.1.4) Except where otherwise noted, expansion joint material shall be self-expanding cork and shall meet the requirements of ASTM D1752. 2.2.3 (2.2.1.4) Except where otherwise noted, isolation joint material shall be the thickness shown and shall meet requirements of ASTM D 1751. 2.2.4 (2.2.1.5) Except where otherwise noted, waterstops shall be Volclay RX by Colloid Environmental Technology Company (CETCO), Synko-Flex by Synko-Flex Products, Inc., MC-2010M by Adeka Ultraseal, or Duroseal Type W by Absolute Waterproofing Systems, Inc. Install in accordance with manufacturer’s instructions. 2.2.5 (2.2.2.5) Unless otherwise indicated, locate construction joints so that the amount of concrete placed between forms does not exceed the following: 2.2.5.1 Walls and slabs of liquid retention structures: 35 feet in any horizontal direction. 2.2.5.2 Walls of other structures: 70 feet in any horizontal direction. 2.2.5.3 Slabs of other structures: 5,000 square feet. 2.2.6 (3.1) Reinforcement General 2.2.6.1 Details of reinforcing Verify the location of all sleeves, embedments, attachments, openings, and structural supports for the equipment provided. All reinforcing shall be as follows unless otherwise noted on the drawings: Reinforcing shall be detailed, fabricated, and placed in accordance with ACI 315-99, with the exception of development lengths and splice lengths. Splice lengths at locations not shown on the drawings shall be detailed on the shop drawings to conform to ACI 315-99. Use the splice category appropriate for the actual bar spacing and concrete cover. Pier ties shall be closed type (ACI Type T1). Unless otherwise detailed, dowels in walls and columns shall match size and spacing of main reinforcing bars. WW Associates Project No. 213003.05 03300/3 Unless otherwise detailed, provide corner bars at all locations where walls intersect in plan to make a corner as shown in Figure 11 of ACI 315. 2.2.7 (3.2.1.1) Reinforcing steel shall meet requirements of ASTM A 615 Grade 60 and shall be deformed. 2.2.8 (3.2.2.2) Welding of bar reinforcement will not be permitted. 2.2.9 (3.3.2.3) Cover requirements for concrete exposed to weather shall be used at all surfaces of liquid retention structures, except where concrete is deposited against earth. 2.2.10 (3.3.2.4) Where concrete will be exposed to view in the finished structure, the portions of all bar supports within 1/2 inch of the concrete surface shall be noncorrosive or protected against corrosion. 2.2.11 (4.2.1.1) Cement shall be as follows: 2.2.11.1 Portland cement for concrete for liquid retention structures shall be ASTM C150, Type II. Portland cement for concrete for all other structures shall be ASTM C150, Type I or II. 2.2.11.2 ASTM C989 Ground iron blast furnace slag may be mixed with ASTM C150 Portland cement to produce the equivalent of ASTM C595 Type IS (MS) blended cement, except that the blast furnace slag content shall not exceed 50 percent by weight of the total cementitious material. 2.2.11.3 ASTM C618 fly ash or pozzolan may be mixed with ASTM C150 Portland cement to produce the equivalent of ASTM C595 Type IP (MS) blended cement, except that the total fly ash and pozzolan content shall not exceed 25 percent by weight of the total cementitious material. Loss on ignition of fly ash or pozzolan shall not exceed 3 percent. 2.2.12 (4.2.1.2) Aggregates for slabs on grade shall conform to the following: 2.2.12.1 The nominal maximum size aggregate shall not be larger than the requirements of 4.2.2.3 – size of coarse aggregate. The combined aggregates shall be well graded from the coarsest to the finest with not more than 18 percent nor less than 8 percent, unless otherwise permitted, of the combined aggregate retained on any individual sieve with the exceptions that the No. 50 may have less than 8 percent retained, sieves finer than No. 50 shall have less than 9 percent retained, and the coarsest sieve may have less than 8 percent retained. WW Associates Project No. 213003.05 03300/4 2.2.12.2 Aggregates used in concrete shall have a combined aggregate distribution similar to the aggregates used in the concrete represented by field test data or used in trial mixtures. Reports of individual aggregates shall include sieve sizes 11/2-inches, 1inch, 3/4-inch, 1/2-inch, 3/8-inch, No. 4, No. 8, No. 16, No. 30, and No. 50 in accordance with ASTM E11. 2.2.13 (4.2.1.2) Coarse aggregate shall be a calcareous aggregate such as limestone or dolomite. 2.2.14 (4.2.2.4) Concrete shall be air entrained except for interior slabs, which shall be non-air entrained. 2.2.15 (4.2.2.5) Air entraining or water reducing admixtures or both will be permitted. Other admixtures shall be submitted for approval before submitting the mix designs and shall not be used without written approval. 2.2.16 (4.2.2.6) Calcium chloride shall not be used as an admixture, nor as an ingredient in any admixture. Chloride ions in admixtures shall not exceed 0.1 percent by weight of cement content. 2.2.17 (4.2.2.9) The 28-day compressive strength of all concrete shall be 4,000 pounds per square inch. 2.2.18 (4.2.2.9) Concrete for liquid retention structures shall have a watercementitious material ratio of not more than 0.45. The following structures are defined as liquid retention structures: building slab and walls. 2.2.19 (5.3.1) Foundation concrete shall not be placed until the soil subgrade for foundation bearing has been examined by the Geotechnical Engineer and found satisfactory for the design bearing capacity. 2.3 Moisture barrier beneath slabs on grade shall be minimum 6-mil polyethylene, with reinforced backing, with joints lapped not less than 6 inches. 2.4 Except as otherwise specified for secondary containment structures, nonshrink grout for setting base plates, leveling plates, and bearing plates for columns and machine bases shall be premixed and noncorrosive and shall meet the requirements of ASTM C1107. Water for mixing grout shall be potable. 2.5 Where joint sealants are used in non-secondary containment areas, joint sealant shall be Sikaflex 2C NS/SL by Sika Chemical Corporation, Eucolastic by Euclid Chemical Company or Stonflex MN6/MP6 by Stonhard, Inc. 2.6 Grout for shaped bottoms of liquid retention structures shall be a mix of three parts sand and one part ASTM C150 Type II cement. WW Associates Project No. 213003.05 03300/5 2.7 Provide anchor rods as required to suit the equipment provided. Anchor rods shall be ASTM A36 or ASTM F1554, Grade 36 unless otherwise noted. 2.8 Adhesive anchors shall be HVA Adhesive Anchors by Hilti Fastening Systems, Chem-stud by the Rawlplug Company, ET Epoxy-Tie Adhesive anchors by the Simpson Strong-Tie Co. The anchor shall consist of a polyester resin adhesive capsule and a chisel-pointed threaded steel rod. Steel shall be zinc plated ASTM A 307. This type of adhesive anchor shall not be used in masonry. Allowable working (service) loads shall be as follows for 4,000-psi concrete: Diameter Shear Tension (Inches) (Pounds) (Pounds) 2.9 1/2 1,800 2,850 5/8 2,750 4,550 3/4 3,850 6,100 7/8 4,925 7,700 1 6,725 8,750 Special inspection of materials 2.9.1 Provide the following special inspections: 2.9.1.1 Review documentation for materials furnished to verify conformance to quality standards for materials specified herein. 2.9.1.2 Review mix design for conformance to Chapter 4 of ACI 301. 2.9.1.3 Inspect concrete mixing techniques for compliance with Section 4.3 of ACI 301. 2.9.2 Special inspection of materials will not be required for the following elements: 2.9.2.1 Sidewalks 2.9.2.2 Other concrete items of a minor nature such as duct banks and thrust blocks. 3 EXECUTION 3.1 Refer to applicable sections of ACI 301-10, except as modified by the supplemental requirements specified in this section. For numbers in parentheses, refer to ACI 301 paragraphs. 3.1.1 (2.2.2.3) Earth cuts may be used as forms for foundations. 3.1.2 (5.3.2.1) Comply with ACI 306.1 for cold weather concreting and with the recommendations of ACI 305 R for hot weather concreting. WW Associates Project No. 213003.05 03300/6 3.1.3 (5.3.3) All formed concrete which will be exposed to public view shall receive a smooth form finish. 3.2 Backfilling adjacent to foundation walls shall not occur until structural elements designed to brace walls have been placed and such concrete has reached 70 percent of its 28-day design compressive strength. Backfilling adjacent to cantilever retaining walls shall not occur until wall concrete has reached its 28day design compressive strength. 3.3 Chamfer all exposed edges of concrete 1-inch. 3.4 Special Inspection of Field Work: 3.4.1 Provide the following special inspections: 3.4.1.1 Inspect installation of reinforcing steel to verify compliance with contract drawings and Sections 3.3 of ACI 301. 3.4.1.2 Inspect formwork for compliance with Section 2.3 of ACI 301. Inspect form removal for compliance with Section 2.3.2 of ACI 318. 3.4.1.3 Test concrete strength, air content, and slump in accordance with Section 1.6.4.2 of ACI 301. 3.4.1.4 Inspect concrete placement for compliance with Section 5.3.2 of ACI 301. 3.4.1.5 301. Inspect curing for compliance with Section 5.3.6.1 of ACI 3.4.2 Special inspection of field work will not be required for the following elements, except that concrete strength, air content, and slump shall be tested in accordance with Section 1.6.4.2 of ACI 301. 3.4.2.1 Sidewalks 3.4.2.2 Other concrete items of a minor nature such as duct banks and thrust blocks. End of Section WW Associates Project No. 213003.05 03300/7 Section 03450 Precast Concrete Tanks 1 GENERAL 1.1 General Requirements 1.1.1 Precast concrete tanks shall be those as manufactured by Concrete Pipe and Precast, LLC, GHP Systems, Inc., Hanover Precast, or approved equal and shall meet the dimensions and requirements of the package wastewater treatment plant and drip dispersal equipment providers. 1.2 Submittals 1.2.1 Preconstruction Submittals: 1.2.1.1 Submit quality control procedures established by the precast manufacturer in accordance with the NPCA Quality Control Manual for Precast Concrete Plants. 1.2.2 Shop Drawings: 1.2.2.1 Drawings for Precast Concrete Units 1.2.2.2 Submit shop drawings furnished by the manufacturer for approval by the Owner and WW Associates. Provide detailed layout for this project. These drawings shall demonstrate that the applicable industry design standards have been met. Installation and construction information shall be included on shop drawings upon request. Details of steel reinforcement size and placement as well as supporting design calculations, if appropriate, shall be included. The precast concrete units shall be produced in accordance with the contract drawings. Drawings shall indicate assumptions used in the design of standard units. Shop drawings shall be coordinated with the requirements of the package wastewater treatment plant and drip dispersal equipment providers. 1.2.2.3 Tank Access Ways 1.2.3 Precast Concrete Unit Data: 1.2.3.1 Standard Precast Concrete Units: 1.2.3.1.1. The manufacturer shall supply cut sheets showing conformance to project drawings and requirements and to applicable industry design standards listed in this specification. WW Associates Project No. 213003.05 03450/1 1.2.3.2 Anchorage, Lifting Inserts and Devices: For anchors, lifting inserts and other devices, the manufacturer shall provide product data sheets and proper installation instructions upon request. The Precast concrete unit dimensions and safe working load shall be clearly indicated. 1.2.3.3 Accessory Items: For items including, but not limited to sealants, gaskets, pipe entry connectors, steps, racks and other items installed before or after delivery, the manufacturer shall include proper installation instructions and relevant product data upon request. 1.2.4 Design Data: Upon request, the manufacturer shall supply precast concrete unit design calculations and concrete mix design proportions and appropriate mix design test data. Structural design calculations shall be signed by a licensed professional engineer. 1.2.5 Test Reports: Upon request, the manufacturer shall supply copies of material certifications and/or laboratory test reports, including mill tests and all other test data, for portland cement, blended cement, pozzolans, ground granulated blast-furnace slag, silica fume, aggregate, admixtures, and curing compound proposed for use on this project. Upon request, the manufacturer shall submit copies of test reports showing that the mix has been successfully tested to produce concrete with the properties specified and will be suitable for the project conditions. Such tests may include compressive strength, flexural strength, plastic or hardened air content, freeze-thaw durability, abrasion and absorption. Special tests for precast concrete items shall be clearly detailed in the specifications. Upon request, the manufacturer will supply copies of in-plant QA/QC inspection reports. 1.2.6 Certificates: Submit quality control procedures established in accordance with NPCA Quality Control Manual for Precast Concrete Plants or verification of current NPCA Plant Certification. 1.2.7 Delivery Time: Delivery time shall be 2 weeks from shop drawing approval. 1.3 Design 1.3.1 Precast Concrete Unit Design: Design standard precast concrete units to withstand indicated design load conditions in accordance with applicable industry design standards ACI 318, ACI 350, ASTM, ACPA Design Manual, PCI MNL-120, and AASHTO. Design must also consider WW Associates Project No. 213003.05 03450/2 stresses induced during handling, shipping and installation in order to avoid product cracking or other handling damage. Design loads for precast concrete units shall be indicated on the shop drawings. 1.3.2 Joints and Sealants: Precast removable top slab shall be equipped with a watertight seal. 1.3.3 Concrete Mix Design: 1.3.3.1 Concrete Proportions: Selection of proportions for concrete shall be based on the methodology presented in ACI 211.1 for normal weight concrete, ACI 211.2 for lightweight concrete and ACI 211.3 for no- slump concrete. The concrete proportions shall be developed using the same type and brand of cement, the same type and brand of pozzolan, the same type and gradation of aggregates, and the same type and brand of admixture that will be used in the manufacture of precast concrete units for the project. Accelerators containing calcium chloride shall not be used in precast concrete containing reinforcing steel or other embedded metal items. Upon request, the manufacturer shall submit a mix design for each strength and type of concrete that will be used. Submitted mix designs shall include the quantity, type, brand and applicable data sheets for all mix design constituents as well as documentation indicating conformance with applicable reference specifications. The use of self-consolidating concrete is permitted provided that mix design proportions and constituents meet the requirements of this specification. 1.3.3.2 Durability and performance requirements 1.3.3.2.1. Concrete Compressive Strength: Precast concrete units shall have a minimum 28-day compressive strength of 4000 psi. 1.3.3.2.2. Water-Cement Ratio: Concrete that will be exposed to freezing and thawing shall contain entrained air (see 1.4.5.2.3) and shall have water-cement ratios of 0.45 or less. Concrete which will not be exposed to freezing, but which is required to be watertight, shall have a water-cement ratio of 0.48 or less if the concrete is exposed to fresh water, or 0.45 or less if exposed to brackish water or sea water. For corrosion protection, reinforced concrete exposed to deicer salts, brackish WW Associates Project No. 213003.05 03450/3 water or seawater shall have a water-cement ratio of 0.40 or less. 1.3.3.2.3. Air Content: The air content of concrete that will be exposed to freezing conditions shall be within the limits given below. Air Content % Nominal Maximum Aggregate Size (in) Severe Exposure Moderate Exposure 3/8 6.0 to 9.0 4.5 to 7.5 1 /2 5.5 to 8.5 4.0 to 7.0 3 /4 4.5 to 7.5 3.5 to 6.5 1 4.5 to 7.5 3.0 to 6.0 1-1/2 4.5 to 7.0 3.0 to 6.0 * For specified compressive strengths greater then 5000 psi, air content may be reduced 1% 1.4 Quality Assurance: The manufacturer shall demonstrate adherence to the standards set forth in the NPCA Quality Control Manual for Precast Concrete Plants. The manufacturer shall meet requirements written in subparagraph 1.5.1 or 1.5.2. 1.4.1 NPCA Plant Certification: The manufacturer shall be certified by the NPCA Plant Certification Program prior to and during production of the products for this project. 1.4.2 Quality Control 1.4.2.1 Quality Control: The manufacturer shall show that the following quality control tests are performed as required and in accordance with the ASTM International standards indicated. a. Slump: A slump test shall be performed for each 150 cu yd of concrete produced per mix design, or once a day, whichever comes first. Slump tests shall be performed in accordance with ASTM C 143. Slump flow tests on selfconsolidating concrete mixes shall be performed in accordance with ASTM C 1611. b. Temperature: The temperature of fresh concrete shall be measured when slump or air content tests are made and when compressive test specimens are made in accordance with ASTM C 1064 c. Compressive Strength: At least four compressive strength specimens shall be made for each 150 cubic yards of concrete of each mix design in accordance with the following applicable ASTM standards; C 31, C 39, C 192, C 497 (no-slump concrete). WW Associates Project No. 213003.05 03450/4 d. Air Content: Tests for air content shall be made on airentrained, wet-cast concrete for each 150 cu yd of concrete, per mix design, but not less often than once each day when air-entrained concrete is used. The air content shall be determined in accordance with either ASTM C 231 or ASTM C 173 for normal weight aggregates and ASTM C 173 for lightweight aggregates. e. Density (Unit Weight): Tests for density shall be performed a minimum of once per week to verify the yield of batch mixes. Density tests shall be performed for each 100 cu yd of lightweight concrete in accordance with ASTM C 138. Density tests shall be performed for each 100 cu yd of concrete per mix design, but not less often than once per day when volumetric batch equipment is used. The manufacturer shall submit documentation demonstrating compliance with the above subparagraphs. 1.5 Handling, Storage and Delivery 1.5.1 Handling: Precast concrete units shall be handled and transported in a manner to minimize damage. Lifting devices or holes shall be consistent with industry standards. Lifting shall be accomplished with methods or devices intended for this purpose as indicated on shop drawings. Upon request, the manufacturer shall provide documentation on acceptable handling methods for the product. 1.5.2 Storage: Precast concrete units shall be stored in a manner that will minimize potential damage. 1.5.3 Delivery: Precast concrete units shall be delivered to the site in accordance with the delivery schedule to avoid excessive build-up of units in storage at the site. Upon delivery to the jobsite all precast concrete units shall be inspected by the Owner or WW Associates for quality and final acceptance. 2 PRODUCTS 2.1 All precast tanks shall meet the requirements of the Package Wastewater Treatment Plant and drip irrigation system providers and these specifications. 3 PRECAST CONCRETE UNITS 3.1 Manufacturers: The precast concrete manufacturer must meet the requirements established in section 1.5 Quality Assurance. WW Associates Project No. 213003.05 03450/5 3.2 Materials: Except as otherwise specified, material shall conform to the following section. 3.2.1 Cement ASTM C 150 (Type I, II, III or V) ASTM C 595 (for Blended Cements) 3.2.2 Silica Fume ASTM C 1240 3.2.3 Fly Ash and Pozzolans ASTM C 618 3.2.4 Ground Granulated Blast-Furnace Slag ASTM C 989 3.2.5 Water ASTM C1602 The use of reclaimed/recycled process water shall be permitted. 3.2.6 Aggregates 3.2.6.1 Aggregate Selection: The nominal maximum aggregate size should not exceed one-fifth the narrowest dimension between sides of forms, nor three-quarters the minimum clear spacing between individual reinforcing bars or wires. Aggregates shall conform to ASTM C 33. Aggregates shall not contain any substance which may be deleteriously reactive with the alkalies in the cement. Upon request, the manufacturer shall provide documentation indicating the aggregates are not susceptible to alkali-aggregate reaction. 3.2.6.2 Aggregates for Lightweight Concrete ASTM C 330 3.2.7 Admixtures 3.2.7.1 Air-Entraining ASTM C 260 WW Associates Project No. 213003.05 03450/6 3.2.7.2 Accelerating, Retarding, Water Reducing [Moderate to High] ASTM C 494 3.2.7.3 Corrosion Inhibitors ASTM C 1582 3.2.8 Reinforcement 3.2.8.1 Reinforcing Bars NOTE: Specify ASTM A 706 reinforcing steel when welding or bending of reinforcement bars is critical. In addition, ASTM A 775 epoxy-coated reinforcing may be specified where extra reinforcement corrosion protection is required. 3.2.8.1.1. Deformed Billet-Steel ASTM A 615 3.2.8.1.2. Deformed Low-Alloy Steel ASTM A 706 3.2.8.2 Reinforcing Wire 3.2.8.2.1. Plain Wire ASTM A 185 3.2.8.2.2. Deformed Wire ASTM A 496 3.2.8.3 Welded Wire Reinforcement 3.2.8.3.1. Plain Wire ASTM A 185 3.2.8.3.2. Deformed Wire ASTM A 497 3.2.8.4 Epoxy Coated Reinforcement 3.2.8.4.1. Reinforcing Bars ASTM A 775 WW Associates Project No. 213003.05 03450/7 3.2.8.4.2. Wires and Welded Wire Reinforcement ASTM A 884 3.2.8.5 Galvanized Reinforcement ASTM A 767 3.2.9 Inserts and Embedded Metal: All items embedded in concrete shall be of the type required for the intended for the intended use and meet the following standards. 3.2.9.1 Structural Steel Plates, Angles, etc. ASTM A 36 3.2.9.2 Hot-Dipped Galvanized ASTM A 152 3.3 Manufacture: Manufacture shall conform to the NPCA Quality Control Manual for Precast Concrete Plants unless specified otherwise. 3.3.1 Forms: Forms for manufacturing precast concrete units shall be of the type and design consistent with industry standards and practices. They should be capable of consistently providing uniform products and dimensions. Forms shall be constructed so that the forces and vibrations to which the forms will be subjected cause no damage to the precast concrete unit. Forms shall be cleaned of concrete build-up after each use. Form release agents shall be applied according to the manufacturer’s recommendations and shall not be allowed to build up on the form casting surfaces. 3.3.2 Reinforcement: Applicable ASTM International and/or ACI 318 standards for placement and splicing Cages of reinforcement shall be fabricated either by tying the bars, wires or welded wire reinforcement into rigid assemblies or by welding, where permissible, in accordance with AWS D1.4. Reinforcing shall be positioned as specified by the design and so that the concrete cover conforms to requirements. The tolerance on concrete cover shall be one-third of that specified but not more than 1/2 in. Concrete cover shall not be less than 1/2 in., unless otherwise specified. Positive means shall be taken to assure that the reinforcement does not move during the casting operations. WW Associates Project No. 213003.05 03450/8 3.3.3 Embedded Items: Embedded items shall be positioned at locations specified in the design documents. Welding shall be performed in accordance with AWS D1.1 when necessary. Inserts, plates, weldments, lifting devices and other items to be embedded in precast concrete units shall be held rigidly in place so that they do not move during casting operations. 3.3.4 Concrete 3.3.4.1 Concrete Mixing: Mixing operations shall produce batch-to-batch uniformity of strength, consistency, and appearance. 3.3.4.2 Concrete Placing: Conventional concrete shall be deposited into forms as near to its final location as practical. Self-consolidating concrete shall be placed in a manner in which it flows and consolidates without segregation or air entrapment. The free fall of the concrete shall be kept to a minimum. Concrete shall be consolidated in such a manner that segregation of the concrete is minimized and honeycombed areas are kept to a minimum. Consolidation efforts are often not required when using selfconsolidating concrete. Vibrators used to consolidate concrete shall have frequencies and amplitudes sufficient to produce wellconsolidated concrete. 3.3.4.2.1. Cold Weather Concreting: Recommendations for cold weather concreting are given in detail ACI 306 R. Adequate equipment shall be provided for heating concrete materials and protecting concrete during freezing or near-freezing weather. All concrete materials and all reinforcement, forms, fillers, and ground with which concrete is to come in contact shall be free from frost. Frozen materials or materials containing ice shall not be used. In cold weather the temperature of concrete at the time of placing shall not be below 45° F. Concrete that freezes before its compressive strength reaches 500 psi shall be discarded. 3.3.4.2.2. Hot Weather Concreting: Recommendations for hot weather concreting are given in ACI 305 R. During hot weather, proper attention shall be given to constituents, production methods, handling, placing, protection, and curing to prevent excessive concrete temperatures or water evaporation that could impair required strength or serviceability of the member or structure. The temperature of concrete at the time of placing shall not exceed 90° F. WW Associates Project No. 213003.05 03450/9 3.3.4.3 Concrete Curing: Commence curing operations immediately following the initial set of the concrete and completion of surface finishing. 3.3.4.3.1. Curing by Moisture Retention: Moisture shall be prevented from evaporating from exposed surfaces until adequate strength for stripping the precast concrete unit from the forms is reached by one of the following methods: Cover with polyethylene sheets a minimum of 6 mils thick (ASTM C 171) Cover with burlap or other absorptive material and keep continually moist Use of a membrane-curing compound applied at a rate not to exceed 200 sq. ft. per gallon, or per manufacturers’ recommendations (ASTM C 309) Surfaces that will be exposed to weather during service shall be cured as above a minimum of 7 days. Forms shall be considered effective in preventing evaporation from the contact surfaces. If air temperature is below 50° F the curing period shall be extended. 3.3.4.3.2. Curing with Heat and Moisture: Concrete shall not be subjected to steam or hot air until after the concrete has attained its initial set. Steam, if used, shall be applied within a suitable enclosure, which permits free circulation of the steam in accordance with ACI 517.2R. If hot air is used for curing, precautions shall be taken to prevent moisture loss from the concrete. The temperature of the concrete shall not be permitted to exceed 150° F. These requirements do not apply to products cured with steam under pressure in an autoclave. 3.3.4.4 Surface Finish: Unformed surfaces of wet-cast precast concrete products shall be finished as specified. Surfaces shall be finished using a strike-off to level the concrete with the top of the form. 3.3.4.4.1. Formed Non-Architectural Surfaces: Surfaces shall be cast against approved forms in accordance with standard industry practices in cleaning forms, designing concrete mixes, placing and curing concrete. Normal color variations, form joint marks, WW Associates Project No. 213003.05 03450/10 small surface holes caused by air bubbles, and minor chips and spalls will be accepted. Major imperfections, excessive honeycombing or other major defects shall not be permitted. 3.3.4.4.2. Unformed Surfaces: Surfaces shall be finished with a vibrating screed, or by hand with a float. Normal color variations, minor indentations, minor chips and spalls will be accepted. Major imperfections, excessive honeycombing or other major defects shall not be permitted. 3.3.4.5 Stripping Precast Concrete Units From Forms: Precast concrete units shall not be removed from the forms until the concrete reaches the compressive strength for stripping required by the design. Stripping strengths shall be routinely measured to ensure product has attained sufficient strength for safe handling. 3.3.4.6 Patching and Repair 3.3.4.6.1. Repairing Minor Defects: Defects that will not impair the functional use or expected life of a precast concrete unit may be repaired by any method that does not impair the product. 3.3.4.6.2. Repairing Honeycombed Areas: When honeycombed areas are to be repaired, all loose material shall be removed and the areas cut back into essentially horizontal or vertical planes to a depth at which coarse aggregate particles break under chipping rather than being dislodged. Proprietary repair materials shall be used in accordance with the manufacturer’s instructions. If a proprietary repair material is not used, the area shall be saturated with water. Immediately prior to repair, the area should be damp, but free of excess water. A cement-sand grout or an approved bonding agent shall be applied to the chipped surfaces, followed immediately by consolidating an appropriate repair material into the cavity. 3.3.4.6.3. Repairing Major Defects: Defects in precast concrete products which impair the functional use or the expected life of products shall be evaluated by qualified personnel to determine if repairs are feasible and, if so, to establish the repair procedure. WW Associates Project No. 213003.05 03450/11 3.3.4.7 Shipping Precast Concrete Units: Precast concrete units shall not be shipped until they are at least 7 days old, unless it can be shown that the concrete strength has reached at least 75% of the specified 28-day strength, or that damage will not result, impairing the performance of the product. 3.3.4.8 Lift Eyes: Provide lifting eyes for each 5 foot section of lids. 4 EXECUTION 4.1 Installation 4.1.1 Site Access: The contractor shall be responsible for coordinating access to the site with the Owner to facilitate hauling, storage and proper handling of the precast concrete units. 4.1.2 Installation Precast concrete tanks/vault shall be installed to the lines and grades shown in the contract documents. Precast concrete tanks/vault shall be lifted by suitable lifting devices at points provided by the manufacturer. Precast concrete tanks/vault shall be installed in accordance with applicable industry standards. Upon request, the manufacturer shall provide installation instructions. 4.1.3 Watertightness: Watertight joints, pipe-entry connectors and inserts should be used to ensure the integrity of the entire system. End of Section WW Associates Project No. 213003.05 03450/12 Section 11400 Package Wastewater Treatment Plant 1 GENERAL 1.1 System Description 1.1.1 This work consists of furnishing and installing one complete wastewater treatment facility with all necessary parts and equipment as described in the following specifications. The wastewater treatment facility shall provide treatment of the wastewater flow in accordance with the performance and sizing requirements stated herein and the process flow diagram shown on the drawings. The wastewater treatment facility shall consist of the following unit processes: 1) Septic Tank 2) Equalization Tank & Effluent Pump 3) First Stage Aeration 4) Second Stage Aeration 5) Denitrification Filter 6) Re-aeration 7) Pump Station & Recycle Pump 8) Hydraulic Unit 9) Backwash Tank 1.1.2 Principal items of equipment supplied with the system, to achieve one completely functional and operational wastewater treatment plant as described herein, shall include, but not be limited to, the following: 1.1.2.1 Tankage with volumes and capacity as defined in these specifications, pumps, air supply distribution system, air diffuser systems, blowers, blower motors, complete control systems for equipment, weirs, and all necessary piping and plumbing. 1.1.2.2 All equipment shall be retrievable from the top of the plant. 1.1.2.3 Hydraulic unit specification is in Section 11700 – Drip Irrigation System. 1.1.3 Principal tankage for the wastewater treatment plant shall be used for the following functions: 1.1.3.1 Septic Tank: 5,000 gallons of storage capacity 1.1.3.2 Equalization: 5,000 gallons of storage capacity WW Associates Project No. 213003.05 11400/1 1.1.3.3 Stage 1 Aeration for Carbon Reduction: 5,000 gallons of storage capacity 1.1.3.4 Stage 2 Aeration for Nitrification: 5,000 gallons of storage capacity 1.1.3.5 Denitrification Filter: 3,000 gallons of storage capacity 1.1.3.6 Re-aeration: 1,250 gallons of storage capacity 1.1.3.7 Pump Station: 5,000 gallons of storage capacity 1.1.3.8 Hydraulic Unit 1.1.3.9 Backwash Tank: 5,000 gallons of storage capacity 1.2 Related Requirements: The following sections contain requirements that relate to this section. 1.2.1 Section 02200 – Earthwork 1.2.2 Section 02730 – Wastewater Piping System 1.2.3 Section 03450 – Precast Concrete Tanks/Vaults 1.2.4 Section 11600 – Chemical Feed Systems 1.2.5 Section 11700 – Drip Irrigation System 1.2.6 Section 16010 – Electrical General Provisions 1.3 Reference Specifications where applicable to work under this section are referred to by abbreviation as follows: 1.3.1 American National Standards Institute .................................. ANSI 1.3.2 American Society for Testing and Materials ......................... ASTM 1.3.3 National Electrical Code ........................................................ NEC 1.3.4 National Electrical Manufacturers Association ..................... NEMA 1.3.5 Occupational Safety and Health Administration ................... OSHA 1.3.6 Precast Concrete Institute ...................................................... PCI 1.3.7 Virginia Department of Health .............................................. VDH WW Associates Project No. 213003.05 11400/2 1.4 Quality Assurance 1.4.1 The wastewater treatment facility shall be provided as a package system as specified, as indicated on the drawings, and as required to provide a complete installation ready for operation. 1.4.2 The package system shall be provided by a single source supplier regularly engaged in providing wastewater treatment facilities as specified in this section. 1.4.3 The equipment manufacturer/supplier shall have unit responsibility for equipment startup. Provide the services of an experienced, manufacturertrained technician for one site visit consisting of a total of five 8-hour working days on the site, to demonstrate satisfactory operation and to provide training and instruction of the Owner’s personnel for equipment operation. 1.4.4 Experience: The wastewater treatment plant manufacturer shall certify to not less than 15 years of experience in the design and fabrication of wastewater treatment plants. The manufacturer shall submit a list of not less than ten operating wastewater treatment plants installed in the last five years as evidence of meeting the experience requirement. 1.4.5 The drawing and design of the wastewater treatment plant is based on the BioMicrobics, Inc. “FAST” systems as represented by Nature Works, Inc. [Address: P.O. Box 639, Burgess, Virginia 22432; Telephone: (804) 4537946; Email: [email protected]; Point of Contact: Michael I. Burch] as the design standard. Approved alternate is the Advantex System as manufactured by Orenco [Address: 814 Airway Ave., Sutherlin Oregon 97479; Telephone: (800) 348-9843 x 358; Email: [email protected]; Point of Contact: Jesten Brenner]. Other manufacturers substitution will not be permitted. 1.4.6 If the alternate system is used, the Contractor shall provide a similar arrangement, and revise the dimensional layout as necessary. The design of the alternate wastewater treatment plant must be certified by a licensed professional engineer and approved by WW Associates in the shop drawing phase of construction. 1.5 Submittals: Provide the following in a timely manner in accordance with the approved submittals schedule as specified in Section 01400 – General Requirements. 1.5.1 Detailed shop drawings of the wastewater treatment plant, including plan view, hydraulic profile, individual tank details, pump and blower capacities, pipe penetrations, manways and mechanical and electrical details. 1.5.2 Detailed design calculations, showing all design equations for all aspects of the treatment plant. WW Associates Project No. 213003.05 11400/3 1.5.3 Product data, catalog cut sheets, certified pump curves, and diffuser oxygen transfer efficiency and pressure drop curves for associated equipment and accessories. 1.5.4 Electrical power supply equipment and instrumentation and controls data, including equipment, point-to-point wiring diagrams, point-to-point instrumentations, control panels, and sequence of operation. 1.5.5 Plant performance certification. 1.5.6 All tankage shall be non-buoyant when empty with groundwater to top of the tank. Shop drawings and design calculations for systems to prevent flotation of the wastewater treatment plant tankage. All drawings and structural calculations shall be stamped by a licensed professional engineer. 1.5.7 Operation and maintenance manuals, including approved shop drawings, recommended spare parts, instructions on lubrication and adjustment requirements, recommended schedule of maintenance tasks, startup and operating instructions, troubleshooting instructions, and addresses and telephone numbers for equipment manufacturers of all major components. 1.6 Project Conditions 1.6.1 Equipment furnished in accordance with this section shall be installed at the location and in general the space allocated on the contract drawings. 1.6.2 Material used in the manufacturing of the tankage and equipment shall be of excellent quality used for the purpose in commercial practice. Material shall be free from all defects and imperfections that might affect the serviceability of the finished product. 1.6.3 The equipment supplied under this specification shall be the standard product of the specified manufacturer so that prompt and continuous service and delivery of spare parts may be secured. The component parts of the unit shall be supplied by one manufacturer. 1.6.4 Pump and blower motors shall be sized such that the motor does not overload at any point on the operating curve. Pumps, blowers, and motors shall be designed to perform with a reasonable service life when operated continuously or intermittently. Motors shall be designed with a minimum service factor of 1.15. Other motor requirements shall be as specified in this section and as specified in Division 16 – Electrical. 1.6.5 Electrical Motors, Controllers, Starters, and Disconnects: Furnish motors, controllers, starters, and disconnects with their respective pieces of equipment. Motors, controllers, starters, and disconnects shall conform to and shall have electrical connections in accordance with the National Electrical Code. Controllers and starters shall have a maximum of 120-volt control circuits, and auxiliary contacts for use with the controls furnished. WW Associates Project No. 213003.05 11400/4 1.6.6 Any structural, piping, electrical requirements, wiring, instrumentation and controls, drawings, or other modifications required to accommodate equipment offered shall be done at no additional cost to the Owner. 1.7 Warranty 1.7.1 The equipment manufacturer/supplier shall guarantee for 12 months from date of start-up that the structure and all work and equipment will be free from all defects in design, material, and workmanship. Warranties and guarantees by the suppliers of various components in lieu of single source responsibility by the manufacturer will not be accepted. 1.7.2 In the event one or more components fail to perform as specified or is proven defective in service during the guarantee period, the equipment manufacturer/supplier shall provide replacement parts without cost to the Owner. 2 PRODUCTS 2.1 Design Criteria: The wastewater treatment plant system shall be designed in accordance with the following design criteria: 2.1.1 Average daily design flow: 2400 gpd 2.1.2 Peak daily design flow: 4800 gpd 2.1.3 Design Loadings Average Constituent BOD5 TSS NH3-N TN Alkalinity Influent 400 mg/L 300 mg/L 85 mg/L 90 mg/L 200 mg/L Effluent (from Re-aeration Tank) 15 mg/L 15 mg/L 5 mg/L 2.1.4 Wastewater Temperature: 50°F to 68°F 2.1.5 Approximate Job Site Elevation: 490 feet MSL 2.1.6 Ambient Air Temperature: 0°F to 100°F 2.1.7 All applicable regulatory requirements of the Commonwealth of Virginia Departments of Health and Environmental Quality and the U.S. EPA (Environmental Protection Agency) with regard to the minimum dimensions, capacities, and performance of the proposed wastewater treatment plant shall be satisfied. WW Associates Project No. 213003.05 11400/5 2.2 Polyvinyl chloride (PVC) plant flow piping used as part of the package wastewater treatment plant facility shall be as specified in Section 02730 – Wastewater Piping Systems. 2.3 (1) Septic Tank 2.3.1 Septic tanks shall be precast concrete with an effective storage volume of 5,000 gallons. 2.3.2 Septic tank shall be buried and equipped with manway risers to above grade. 2.3.3 Septic tank influent tee, baffle and outlet structure shall be in accord with applicable sections of the VDH On-Site Water and Sewage Regulation. Provide 30-inch cast iron frames and covers. 2.4 (2) Equalization Tank 2.4.1 Equalization tank shall be precast concrete with an effective storage volume of 5,000 gallons. 2.4.2 Equalization tank to be equipped with float controls, duplex submersible pumping units with guiderail retrieval system and flow control to ensure constant flow is delivered to the Stage 1 Aeration for Carbon Reduction Tank. Submersible pumps shall be non-clog cast iron sewage pumps capable of passing 3-inch solids. Pumps shall be Zoeller, Goulds, or approved equal. Pumps shall be rated for a minimum flow rate of 15 gpm at a TDH of 11 feet. Pumps shall be capable of passing a 3/8” diameter solid. Each pump section shall be equipped with a screen which will pass solids no greater than 1/4” diameter. Provide a recycle loop to allow the discharge rate leaving the equalization tank to be adjustable. The recycle loop shall be designed with a “head box.” The head box shall consist of 2 adjustable weirs. One weir shall discharge to the first stage aeration tank; the second weir shall discharge back to the equalization tank. The head box shall be constructed of aluminum plate. Submit the head box design for review and approval. Design feed rate to the Stage 1 Aeration unit shall be 4500 gpd. The pump recycle loop shall also be utilized to completely mix the contents of the equalization tank. The equalization pumps shall be provided with variable frequency drive units (2 each) to allow for finite flow control adjustment. The VFD’s shall be mounted in the new treatment building and will allow for manual adjustment of the pump flow rates. The VFD shall be Square D or approved equivalent. 2.4.3 Pumps shall be UL listed. 2.4.4 Pumps shall be hardwired in a watertight junction box per local code. 2.4.5 Each pump shall have individual breaker contactor and capacitor. WW Associates Project No. 213003.05 11400/6 2.4.6 Pumps shall have check valve, disconnect and shut-off valve on discharge side and shall be equipped with stainless steel lifting cable. 2.5 (3) Stage 1 Aeration for Carbon Reduction 2.5.1 Stage 1 Aeration for Carbon Reduction Unit shall be housed in a precast concrete tank with an effective volume of 5,000 gallons. 2.5.2 Unit shall be equipped with aeration and fixed media to facilitate reduction of BOD. Fixed media shall be constructed of polypropylene, supported by a polyethylene insert. The media shall be fixed in position and contain no moving or wearing parts and shall not corrode. The media shall be designed and installed to ensure that sloughed solids descend through the media to the bottom of the tank. Tanks shall be vented with a vent grate and at least 19.3 square inches of open surface area. Secure with Stainless steel screws. Vent piping must not allow condensate build up or create back pressure. Vent shall be above finished grade. Tanks shall be designed to prevent air passage between the settling zone/tank and the treatment zone and preventing an air lock. Provide pump out access to clean out all zones. Provide concrete pad for aeration blower unit. 2.5.3 See paragraph 2.12 for blower requirements. 2.5.4 Bio-Microbics, Inc. MicroFAST 4.5 FAST Unit is the design standard. 2.6 (4) Stage 2 Aeration for Nitrification 2.6.1 Stage 2 Aeration for Nitrification unit shall be housed in a precast concrete tank with an effective volume of 5,000 gallons. 2.6.2 Unit shall be equipped with aeration and fixed media to facilitate nitrification. Fixed media shall be constructed of polypropylene, supported by a PE insert. The media shall be fixed in position and contain no moving or wearing parts and shall not corrode. The media shall be designed and installed to ensure that sloughed solids descend through the media to the bottom of the tank. Tanks shall be vented with a vent grate and at least 7 square inches of open surface area. Secure with Stainless steel screws. Vent piping must not allow condensate build up or create back pressure. Vent shall be above finished grade. Tanks shall be designed to prevent air passage between the settling zone/tank and the treatment zone and preventing an air lock. Provide pump out access to clean out all zones. Provide concrete pad for aeration blower unit. 2.6.3 A complete Soda Ash feed system for pH/alkalinity adjustment shall be as specified in Specification Section 11600 – Chemical Feed Equipment. 2.6.4 Blower for aeration shall be capable of delivering 140 SCFM. See paragraph 2.12 for further requirements. WW Associates Project No. 213003.05 11400/7 2.6.5 Bio-Microbics, Inc. NitriFAST 4.5 FAST Unit is the design standard. 2.7 (5) Denitrification Filter 2.7.1 Denitrification Filter unit shall be housed in a precast tank with an effective volume of 3,000 gallons. 2.7.2 Unit shall be equipped with fixed media and recirculation pump which discharges to the equalization tank. Recirculation pump shall be equipped with stainless steel cable. Recirculation pump shall be 5 gpm minimum, nonclog, cast iron, sewage pump, capable of passing a 3-inch solid with adjustable recycle rate from 50% to 150% of plant rate flow of 4500 gpd. Unit shall be vented and provided with a pump out access as specified in paragraph 2.6.2. 2.7.3 A complete chemical feed system to feed supplemental carbon (MicroC1000) is specified in Specification Section 11600 – Chemical Feed Equipment. 2.7.4 Bio-Microbics, Inc. ABC-N 3.0 is the design standard. The treatment system shall be complete with all needed equipment as specified herein. Provide tank venting and pump out access. The unit shall include ABC-N system insert, leg extensions, and pump. Media shall be rigid PVC, Polyethylene, or polypropylene and shall be supported by the PE insert. The media shall be fixed in position and contain no moving or wearing parts and shall not corrode. The media shall be designed and installed to ensure that sloughed solids through the media to the bottom the tank. The unit shall be equipped with a continuous duty recirculation pump and recirculation assembly. Recirculation pump shall be a cast iron, non-clog submersible wastewater pump as manufactured by Zoeller, Gould, or approved equivalent. 2.8 (6) Re-aeration 2.8.1 The re-aeration unit shall be housed in a precast concrete tank with an effective volume of 1,250 gallons. 2.8.2 Unit shall be equipped with aeration and fixed media to facilitate reduction of BOD from the denitrification filter. See paragraph 2.12 for blower requirements. 2.8.3 Bio-Microbics, Inc. MicroFAST 0.9 FAST Unit is the design standard. 2.9 (7) Pump Station 2.9.1 The pump station unit shall be housed in a precast concrete tank with an effective volume of 5,000 gallons. WW Associates Project No. 213003.05 11400/8 2.9.2 The pump station pump equipment to hydraulic unit is specified in Specification Section 11700 – Drip Irrigation System. 2.9.3 The pump station unit will be equipped with a second set of duplex submersible type pumps each rated at 15 gpm at a TDH of 7.8 feet. These pumps will discharge to the equalization tank. Pumps shall be Zoeller, Goulds or approved equal. The recycle pumps shall be provided with variable frequency drive units (2 each) to allow for finite flow adjustment. The VFD’s shall be mounted in the new treatment building and will allow for manual adjustment of the pump flow rates. The VFD shall be Square D or approved equal. 2.9.4 Pumps shall be UL listed. 2.9.5 Pumps shall be hardwired in a watertight junction box per local code. 2.9.6 Each pump shall have individual breaker contactor and capacitor. 2.9.7 Pumps shall have check valve, disconnect and shut-off valve on discharge side and shall be equipped with stainless steel lifting cable. 2.10 (8) Hydraulic Unit 2.10.1 The hydraulic unit shall be housed in a manufactured housing unit with heating unit as provided by the manufacturer. 2.10.2 The hydraulic unit is specified in Specification Section 11700 – Drip Irrigation System. 2.11 (9) Backwash Tank 2.11.1 The backwash tank unit shall be housed in a precast concrete tank with an effective volume of 5,000 gallons. 2.11.2 The backwash tank will be equipped with duplex submersible type pumps each rated at 15 gpm at a TDH of 8 feet. Backwash pumps will discharge to the equalization tank. Pumps shall be Zoeller, Goulds or approved equal. 2.11.3 Pumps shall be UL listed. 2.11.4 Pumps shall be hardwired in a watertight junction box per local code. 2.11.5 Each pump shall have individual breaker contactor and capacitor. 2.11.6 Pumps shall have check valve, float controls, disconnect and shut-off valve on discharge side and shall be equipped with stainless steel lifting cable. Pump shall pass a minimum 3/8” diameter solid. WW Associates Project No. 213003.05 11400/9 2.12 Air Blower Systems and Appurtenances 2.12.1 The stage 1, stage 2 and re-aeration tanks shall be aerated. Each tank is to be individually equipped with dedicated blowers. Blowers are to be in continuous operation. Blower manufacturer to be FUJI Electric or approved equal. 2.12.2 Blowers shall be of a single stage ring compressor type with single shaft direct drive TEFC electric motor. Each blower shall be equipped with a removable all steel air intake filter. Filter shall be capable of being removed to be cleaned with compressed air or tap water. Each blower is to be equipped in a two-piece rectangular housing with tamper-proof screws. 2.12.3 The blowers which serve the stage 1 or stage 2 aeration tanks shall meet the following: 2.12.3.1 Motor 2.5 horsepower 220 VAC, 60 Hz with NEMA Class B insulation and pilot duty type thermal protector. 2.12.3.2 Each blower shall supply a minimum of 130 SCFM to the aeration tanks. 2.12.3.3 Blower to be FUJI Model VFC 50 or approved equal. 2.12.4 The blower which serves the re-aeration tank shall meet the following: 2.12.4.1 Motor 1/3 horsepower 110 VAC, 60 Hz with NEMA Class B insulation and pilot duty type thermal protector. 2.12.4.2 Blowers hall supply a minimum of 10 SCFM to the re-aeration tank. 2.12.4.3 Blower to be FUJI Model VFC20 or approved equal. 2.12.5 Blower units shall be mounted on a precast concrete pad located at the finished ground surface and adjacent to the treatment unit served. Precast concrete shall be 4000 psi. 2.12.5.1 Stage 1 and stage 2 aeration tank concrete blowers pads minimum 57” x 36” x 2.5” thick. 2.12.5.2 Re-aeration tank concrete blower pad minimum 26” x 20” x 2.5” thick. 2.12.5.3 Mount blowers recommendations. to concrete pad per manufacturer’s 2.12.6 Each motor/blower assembly shall be enclosed with a weatherproof, one-piece molded fiberglass reinforced plastic (FRP) acoustical enclosure to help WW Associates Project No. 213003.05 11400/10 reduce the resultant noise level. Each enclosure shall be constructed of a fiberglass composite laminate of 3/16-inch minimum thickness with 1-inch thick layer of polyurethane foam insulation sprayed on the inside surface. Each enclosure shall include one pair of stainless steel hinges, aluminum lifting handle with spring latch, a locking hasp, and vents. 2.13 Blower/Pump Motor Control Panel: Electrical controls for the blowers and equalization pump motors shall be provided within a NEMA 4X control panel to be wall-mounted in the building. Controls shall include motor circuit breakers, acrossthe-line magnetic type motor starters, motor thermal overload protection, indicating lights, and elapsed time meters. The panel shall control the operation of all motors. 2.13.1 The control panel shall include a 15-minute, multiple 24-hour time clock to permit automatic operation of the treatment facility throughout the day. A second time clock shall be provided for blower operation during low flow conditions (i.e., weekends, vacation periods, etc.) to allow operational flexibility. A three-position “hand-off-auto” (H-O-A) selector switch shall be installed for each motor, to allow the treatment plant aeration unit to operate either on a continuous run basis or according to the cycle established on the time clock. The control panel shall be provided by the treatment plant equipment supplier. 2.14 Air Distribution Piping 2.14.1 The air distribution piping shall be Schedule 40 galvanized steel piping, and Schedule 40 galvanized malleable iron pipe fittings shall be used throughout the air distribution system. Individual galvanized pipe unions and flexible couplings with stainless steel clamps shall be provided as necessary in the air distribution system. Individual air control valves shall be installed in the air distribution piping as required to allow individual adjustment of each separate element within the system. 2.14.2 Air distribution shall be provided through Schedule 40 galvanized steel air header piping and fittings. The air header shall have individual drop pipes connected to the header assembly for air supply to each individual diffuser header and air lift assembly. Each drop pipe shall be equipped with an air adjustment ball valve to control air flow to each individual diffuser header and air lift assembly. In addition, a quick release union shall be provided for each drop pipe downstream from the air adjustment ball valve. 2.15 Air Diffuser System 2.15.1 Each diffuser assembly shall be installed not more than 12 inches away from the chamber sidewall. Diffuser headers shall be constructed of 1 1/4inch diameter Schedule 40 galvanized steel and shall be designed to insure uniform mixing within the chambers. Each diffuser header shall be equipped with 3/4-inch Model D-24 coarse bubble air diffusers as manufactured by Sanitaire Corporation, 9333 North 49th Street, Brown WW Associates Project No. 213003.05 11400/11 Deer, Wisconsin 53223, Telephone: (414) 365-2200, Fax: (414) 365-2210, or approved equal. 2.15.2 Coarse Bubble Air Diffuser Performance (Minimum Requirements) 2.15.2.1 Oxygen transfer efficiency shall be defined as follows: 10% at 13 feet submergence 6% at 8 feet submergence 3% at 6 feet submergence 2.15.2.2 Pressure drop: 0.10 psig 2.15.2.3 Diffuser headers shall be located 8 inches above the tank floor. Air bubble distribution effected by the diffusers shall be adequate to provide all oxygen necessary for nitrification/aerobic digestion/aeration processes, while maintaining a minimum dissolved oxygen residual concentration of 3 mg/L in the respective tanks. A minimum dissolved oxygen residual concentration of 8 mg/L shall be maintained in the re-aeration tank. 3 E XE C U T IO N 3.1 Excavation and Backfill 3.1.1 The Contractor shall provide a coarse aggregate base with a geotextile fabric underliner beneath the reinforced concrete tanks. Aggregate fill material shall be used between and around the tankage. Aggregate fill shall satisfy the requirements specified in Section 02200 – Earthwork. Absolutely no saturated soils, rocky material, or other questionable materials shall be used for backfill activities. The voids between the tanks shall be filled before backfilling around the outer perimeter of the plant. In addition, the Contractor shall backfill evenly around the outer perimeter of the plant and the remaining portions between the tankage in order to minimize unbalanced external loading. Provide factory trained personnel for five (5) working days for plant start-up. 3.1.2 Aggregate fill material used as backfill around the tankage shall not be compacted to prevent damage to the precast concrete tankage from compaction equipment. 3.1.3 The site shall be graded in such a way that all stormwater runoff drains away from the site. Stormwater runoff shall not be permitted to enter the excavation at any time. The Contractor shall backfill between and around all tankage as soon as possible to prevent potential flotation. WW Associates Project No. 213003.05 11400/12 3.2 Manufacturer’s Instructions 3.2.1 Install the wastewater treatment plant system in accordance with the written instructions of the equipment manufacturer as indicated and as specified in this section. Provide all necessary interconnections, services, and adjustments for a complete operating system. 3.3 Performance Tests 3.3.1 Provide the services of the equipment manufacturer’s experienced engineers to perform testing of the system installed. During the tests, all manufacturers integrated equipment shall be tested under every condition of operation, and controls shall be tested to demonstrate performance of function. All adjusting and balancing shall be completed to the satisfaction of the Engineer. Warranty on adjustment of controls and extend one year after the system is put into operation. The equipment manufacturer/supplier shall correct all defects to the work at no expense to the Owner and the test repeated until satisfactory. 3.3.2 Five days of training shall be provided by a factory trained representative supplying the package wastewater treatment plant equipment. Provide plant startup and performance testing specified in Section 01400 – General Requirements. Manufacturer shall return to site, test and balance system, and verify treatment parameters three (3) additional times in the first six (6) months of operation. Provide 12 month warranty for all equipment. Provide Operation and Maintenance Manual for all equipment in one concise manual. Provide Operation and Maintenance Manual in PDF form with two (2) compact discs. 3.3.3 Effluent Parameters: The plant shall be designed based on the design criteria set forth in Section 2.1 to ensure the plant can treat a wide variety of influent and effluent conditions. The following effluent standards apply for the purposes of permitting and the performance test: Constituent BODS TSS TN Performance Standards 30 mg/l 30 mg/l 20 mg/l The plant must consistently meet this performance standard criteria prior to successfully passing the performance testing and substantial completion. 3.4 Leakage Tests: All precast concrete structures shall be tested for leakage using potable water. Measure the amount of leakage occurring over a 24-hour period. Zero leakage from a structure shall demonstrate successful test completion. If leakage is observed, find and repair the leaks, and repeat the test until successful. WW Associates Project No. 213003.05 11400/13 3.5 Piping Systems 3.5.1 Piping shall be hydrostatically tested at not less than 1.5 times the working pressure, but not less than 50 psig and shall show no leakage or reduction of gauge pressure after 4 hours. End of Section WW Associates Project No. 213003.05 11400/14 Section 11600 Chemical Feed Equipment 1 GENERAL 1.1 Description 1.1.1 Chemical feed equipment shall consist of, but not be limited to, all piping, valves, and other appurtenances required for complete and operable feed systems for the following chemical services: 1.1.1.1 Soda Ash Solution 1.1.1.2 MicroC1000 Carbon 1.1.2 The Contractor shall provide all labor, materials, equipment, and incidentals required to install, test, and place in satisfactory services all chemical feed systems and equipment as indicated on the drawings and as specified herein. 1.1.3 Provide PVC conduit below grade to convey tubing to point of application. 1.2 Submittals: Provide the following in a timely manner in accordance with Section 01400 – General Requirements. 1.2.1 Catalog cuts, performance data, shop drawings, replaceable parts lists, and certificates of compatibility with intended chemical service for the following: 1.2.1.1 Piping, Fittings, and Pipe Appurtenances 1.2.1.2 Valves 1.2.1.3 Chemical Feed Pump Wall Mounted Shelves 1.2.1.4 Eye/Face Wash Station 1.2.1.5 Soda Ash Feed System and Appurtenances 1.2.1.6 MicroC1000 Feed System and Appurtenances 1.2.1.7 Miscellaneous Treatment Building Equipment 1.2.2 Provide piping schematics, wiring schematics with interconnection diagrams, instrumentation diagrams, and a complete written sequence of operation for each chemical feed equipment item. Provide plumbing riser for soda ash make up water. 1.2.3 Operation and Maintenance Manuals: Bound in loose-leaf binders for review by WW Associates. 1.2.3.1 The manual’s identification shall be inscribed on the cover. WW Associates Project No. 213003.05 11600/1 1.2.3.2 Each manual shall include the names, addresses, and telephone numbers of the local representatives for each item of equipment and each system. 1.2.3.3 Each manual shall have a table of contents and be assembled to conform to the project manual table of contents with the tab sheets placed before instructions covering the subject. Additionally, each manual shall contain a comprehensive index of all manuals submitted in accordance with this paragraph. 1.2.3.4 Manuals and specifications shall be furnished which provide full and complete coverage of the following subjects: 1.2.3.4.1 Operational Requirement: This document shall describe, in concise terms, all the functional and operational requirements for the system. 1.2.3.4.2 Maintenance: Documentation of all user-performed maintenance on all system components including inspection, periodic preventative maintenance, fault diagnosis, and repair or replacement of defective units. This shall include calibration, maintenance, and repair of all equipment, instrumentation, and controls, plus diagnosis and repair or replacement of all system hardware. 1.2.4 Spare Parts: Each equipment manufacturer shall submit a recommended list of spare parts for the equipment supplied. 1.3 Quality Assurance 1.3.1 The manufacturers shall provide all piping, valves, equipment, and appurtenances required for complete and operable chemical feed systems. 1.3.2 Each equipment manufacturer shall have unit responsibility to the Contractor for the installation of all equipment, instrumentation, and controls specified in this section. 1.3.3 Each equipment supplier shall have unit responsibility for its equipment startup. Provide services of experienced, manufacturer-trained technicians for two separate site visits consisting of a minimum one 8-hour working day on the site to demonstrate satisfactory operation and another minimum of one 8-hour working day to provide training and instruction of owner’s personnel for equipment operation. Site visits shall be coordinated with the engineer. 1.4 Project Conditions 1.4.1 Equipment furnished in accordance with this section shall be installed at the location and in the space allocated on the contract drawings. The Contractor WW Associates Project No. 213003.05 11600/2 shall provide all labor, materials, equipment, and incidentals required to install, test, and place in satisfactory service all chemical feed equipment as indicated on the drawings and as specified herein. 1.4.2 Any structural, piping, electrical requirements, wiring, instrumentation and controls, drawings, or other modifications required to accommodate equipment offered other than that specified as the design standard and as shown on the drawings shall be done at no additional cost to the Owner. 1.5 Warranty 1.5.1 In addition to the manufacturer’s standards guarantee, the contractor shall include the services of a factory-trained serviceman to provide repair services for the equipment for the period of 1 year commencing with the time the equipment is placed in continuous permanent operation. This service shall include the cost of all replacement parts required during the interval. 1.6 Below grade chemical tubing shall be routed through PVC conduit. 2 PRODUCTS 2.1 Materials 2.1.1 All chemical feed equipment shall have manufacturer’s name, model number, working pressure if pertinent and other technical information as required cast in raised letters on body of equipment. 2.1.2 All bolts, nuts, studs, etc. on or required to connect chemical feed equipment to bases, supports, walls, and other surfaces shall be of fiberglass reinforced plastic (FRP). 2.1.3 Bolts and nuts shall have hexagon heads and nuts. 2.1.4 Gasket materials and installation shall conform to manufacturer’s recommendations. 2.2 Piping Application 2.2.1 Chemical Solution Piping 2.2.1.1 MicroC1000 Carbon: Tygon Chemfluor FEP tubing 200 psi rating 2.2.1.2 Soda Ash Solution: Tygon Chemfluor FEP tubing, 200 psi rating 2.2.2 Water supply piping for soda ash make up water, PVC 200 psi rating. 2.2.3 Below grade chemical feed conduit: Solvent welded Schedule 80 PVC. WW Associates Project No. 213003.05 11600/3 2.2.4 Accessories: Provide chemically resistant flanges, quick disconnects, connecting pieces, transition glands, transition sleeves, injectors , shut off ball type valves, and other adapters and appurtenances as required for complete and operable piping systems for service indicated. 2.3 Pipe 2.3.1 Chemical Tubing 2.3.1.1 Tubing for Soda Ash feed solution and MicroC1000 product shall be Tygon Chemfluor FEP tubing, as manufactured by Norton Performance Plastics Corporation, 150 Dey Road, Wayne, New Jersey 07470, United States Plastics Corporation, Saint-Gobain Performance Plastics, 2664 Gilchrist Road, Akron, Ohio 44305, or approved equal. Inside diameter shall be 1/4-inch; minimum wall thickness shall be 3/8-inch. Tubing shall be rated for a maximum working pressure of 200 psig in accordance with ASTM D1599. Fittings shall be molded Chemfluor PFA Teflon, “Gorilla-Grip” compression type. 2.3.2 Polyvinyl Chloride (PVC) Piping 2.1.3.1 Pipe, couplings, and fittings shall be Schedule 80 meeting the requirements of ASTM D1785, manufactured of material meeting the requirements of ASTM D1784, Type 1120. Provide ASTM D2467 Schedule 80 fittings and ASTM D2564 solvent cement. 2.1.3.2 Provide screwed joints and flanges, couplings, nipples, sleeves, as required to connect dissimilar pipe materials, valves, equipment and appurtenances. 2.3.3 Tubing pipe supports shall be provided in accordance with Section 02735 – Pipe Supports and Anchors. 2.4 Eyewash Station 2.4.1 Eyewash Station shall be a wall mounted using gravity to supply a continuous flow of clear water for a full 15 minutes at a rate of 0.42 gpm. Unit shall be FDA approved and meet the requirements of ANSI Z358.1. 2.4.2 Acceptable Manufacturer: Haws, Model 7500 Speakman or approved equal. 2.4.3 Preservative/Bacteriostatic Additive – provide supply for treating 100 gallons. 2.5 Soda Ash Feed System 2.5.1 General: The soda ash feed system shall consist of one chemical metering pumps, one mechanical agitator, one wall shelf and one soda ash solution storage tank. Mount pump on wall shelf and place pump in operation. WW Associates Project No. 213003.05 11600/4 2.5.2 Chemical Metering Pump: Pump shall be an LMI-Milton Roy Model Roytronic Excel AD, or approved equal. Pump shall be positive displacement diaphragmtype, pump capable of pumping liquid soda ash at a rate of 0-0.20 GPH against a backpressure of 100 psi. Pump shall be provided with a 4-function valve assembly to aid in priming, prevent backflow, prevent loss of suction and allow off-gassing/bleed-off. Pump shall be equipped with dual manual controls, allowing adjustment of both stroke length and speed. Suction and discharge 1/4” diameter tubing of sufficient length for the application as intended and as shown on the drawings is to be provided. The suction tubing shall be equipped with “tubing straightner” device to preclude entanglement with the tank agitator. The suction tubing will be equipped with a foot valve to facilitate maintenance of pump suction prime. Connectors shall be provided at the pump head and ball cut-off valve to facilitate maintenance. Two spare connectors shall be provided. 2.5.3 Storage Tank: The tank shall be constructed of polyethylene with 50-gallon storage capacity (10-gallon gradations boldly marked). The tank shall have a cover with a factory-drilled openings for the mechanical agitator, tubing and appurtenances. 2.5.4 Mechanical Agitator: The agitator shall be an LMI Model No. 10590. Shaft length shall be approximately 34 inches. Impeller construction shall be Type 303 stainless steel with epoxy chemical resistant coating. Agitator motor shall be 1/20 HP, 1,600 RPM, with an electrical plug connection. 2.5.5 Electrical service for the soda ash feed system shall be wall receptacle. 2.6 MicroC1000 Feed Pumps 2.6.1 General: The MicroC1000 feed system shall consist of one chemical metering pumps on one wall shelf. 2.6.2 Chemical Metering Pump: Pump shall be an LMI – Milton Roy Model Roytronic Excel AD, or approved equal. Pump shall be positive displacement diaphragmtype, capable of pumping liquid sodium hypochlorite solution at a rate of 0-0.21 GPH against a back pressure of 100 psi. Pump shall be provided with a 4function valve assembly to aid in priming, prevent backflow, loss of suction and allow off-gassing/bleedoff. Pump shall be equipped with dual manual controls, allowing adjustment of both stroke and speed. Suction and discharge 1/4” diameter tubing of sufficient length for the application as intended and as shown on the drawings is to be provided. The suction tubing will be equipped with “tubing straightener” device to keep tubing straight and foot valve to facilitate maintenance of suction prime. Connectors shall be provided at the pump head and ball cut-off valve to facilitate maintenance. Two spare connectors shall be provided. 2.6.3 Furnish and install complete LMI Metering Pump Wall Shelf 34643 with poly propylene wall bracket assembly with mounting hardware to support two LMI WW Associates Project No. 213003.05 11600/5 chemical metering pump. Mount pump on wall shelf and place pump in operation. 2.6.4 Provide drum cover with openings for tubing and appurtenances. 2.6.5 Electrical service is a wall receptacle. 2.7 Chemical Supply: The Contractor shall provide the following chemicals: 2.7.1 MicroC1000 Carbon Product: (1) 55-gallon drum with 55 gallon Polyethylene tank cover. Cover shall have appropriate penetrations to facilitate suction and blow-off of product from the chemical metering pump and tubing straightener. 2.7.2 Soda ash: (5) 50 pound bags of soda ash. 2.8 Chemical Feed Pump Wall Mounted Shelves 2.8.1 Each chemical feed shelf shall be constructed of vinylester fiberglass shapes and suitable for resistance to the chemicals that it may come in contact with. 2.8.2 Each shelf shall be sized to adequately accommodate the chemical feed pumps, piping and all other appurtenances supported by the shelf. 2.8.3 Each shelf shall be provided by the chemical feed pump manufacturer and shall be suitable for withstanding all static and dynamic loads imparted by the chemical feed pumps and their appurtenances without vibration. 2.8.4 Quantity: Two (2). 2.9 Spill Containment Deck and Ramp 2.9.1 Furnish and install low profile type spill containment deck for each the soda ash feed storage tank and the MicroC1000 feed drum and as shown on the drawings. 2.9.2 Provide and install one containment deck ramp. 2.9.3 Containment deck and ramp shall be from the same manufacturer and are to be compatible. 2.9.4 Containment deck shall be a polypropylene sump with deck, minimum volume 11 gallons and integral ramp. 2.9.5 Containment deck as manufactured by UltraTech International, Inc. or approved equal. WW Associates Project No. 213003.05 11600/6 3 E XE C U T IO N 3.1 Installation: Install equipment as shown on the drawings and according to the written instructions of the manufacturer. Provide all necessary interconnections, services, and adjustments required for complete operating chemical feed systems. 3.2 Provide wall sleeves with mechanical link-seals for pipe penetrations. 3.3 Rough-in piping for make up water prior to pouring treatment building floor slab. 3.4 Performance Tests: Provide the services of the manufacturer’s experienced engineers to perform testing of the chemical feed equipment as installed. During the tests, all manufacturer’s integrated design equipment shall be tested under every condition of operation, and all controls shall be tested to demonstrate performance of the required function. All adjusting and balancing shall be completed to the satisfaction of WW Associates. Warranty on adjustment of controls shall extend 1 year after the system is put into operation. All defects in the work and equipment shall be corrected by the Contractor at his own expense and the test repeated until proven satisfactory. 3.5 Startup: Follow the manufacturer’s recommended startup procedures and demonstrate to the Owner that the equipment is performing as specified in this section. End of Section WW Associates Project No. 213003.05 11600/7 Section 11700 Drip Irrigation System 1 GENERAL 1.1 System Description 1.1.1 This work consists of furnishing and installing one compete wastewater drip irrigation system with all necessary parts and equipment as described in the following specifications and as shown on the drawings. Drip irrigation system source of supply shall be effluent from the re-aeration unit from the package wastewater treatment plant. 1.1.2 Principal items of equipment include all valves, piping, filters, hydraulic units, meters, solenoid valves, controls, electrical supply and components, header piping, pressure compensating drip tubing, air release/vacuum breaker valves fittings, pumps, pump hoists, float switches supports and appurtenances described, shown on the drawings and as needed to place the irrigation system into operation. 1.2 Related Requirements: The following sections contain requirements that relate to this section. 1.2.1 Section 02200 – Earthwork 1.2.2 Section 02500 – Surfacing and Incidental Construction 1.2.3 Section 02730 – Wastewater Piping Systems 1.2.4 Section 03450 – Precast Concrete Tanks 1.2.5 Section 11400 – Package Wastewater Treatment Plant 1.2.6 Section 16010 – Electrical General Provision 1.3 Quality Assurance 1.3.1 The drip irrigation system shall be provided as a package system as specified, as indicated on the drawings, and as required to provide a complete installation ready for and placed into operation. 1.3.2 The package system shall be provided by a single source supplier regularly engaged in providing drip irrigation for wastewater as specified in this section. 1.3.3 The drip irrigation system equipment manufacturer/supplier shall have unit responsibility for equipment startup. Provide the services of an experienced, WW Associates Project No. 213003.05 11700/1 manufacturer-trained technician for one site visit consisting of a total of five 8-hour working days on the site, to demonstrate satisfactory operation and to provide training and instruction of the Owner’s personnel for equipment operation. 1.3.4 Experience: The wastewater drip irrigation system equipment manufacturer shall certify to not less than 5 years of experience in the design and fabrication of wastewater drip irrigation system equipment. The manufacturer shall submit a list of not less than ten operating wastewater drip irrigation system facilities installed in the last five years as evidence of meeting the experience requirement. 1.3.5 The drawings and design of the wastewater drip irrigation system is based on “Perc-Rite System Manufactured by American Manufacturing Company, Inc. [Address: P.O. Box 97, Elkwood, Virginia 22718; Telephone: 1-8003453132; Email: [email protected]; Point of Contact: Bryan Allen] as the design standard. Approved alternate is Geoflow, Inc. [Address: 506 Tamal Plaza, Corte Madera, California 94925; Telephone: 1-800-8243388]. Other manufacturer substitutions will not be permitted. 1.3.6 If the alternate system is used, the Contractor shall provide a similar arrangement and revise the dimensional layout as necessary. The design of the alternate wastewater drip irrigation system must be certified by a licensed professional engineer and approved by WW Associates in the shop drawing review phase of construction. 1.4 Submittals: Provide the following in a timely manner in accordance with the approved submittals schedule as specified in Section 01400 – General Requirements. 1.4.1 Detail shop drawings for mechanical and electrical equipment including pumps, piping, float switches, controllers, valves, valve boxes, hydraulic units, flow meters, filters, and appurtenances of the wastewater drip irrigation system. 1.4.2 Product data, catalogue cut-sheets, certified pump curves for associated equipment and accessories/appurtenances. 1.4.3 Electrical power supply equipment and instrumentation and controls data, including equipment, point-to-point wiring diagrams, point-to-point instrumentations, control panels, and sequence of operation. 1.5 Project Conditions 1.5.1 Equipment furnished in accordance with this section shall be installed at the location and in the space allocated on the contract drawings. WW Associates Project No. 213003.05 11700/2 1.5.2 Material used in the manufacturing of the tankage and equipment shall be of excellent quality used for the purpose in commercial practice. Material shall be free from all defects and imperfections that might affect the serviceability of the finished product. 1.5.3 The equipment supplied under this specification shall be the standard product of the specified manufacturer so that prompt and continuous service and delivery of spare parts may be secured. The component parts of the unit shall be supplied by one manufacturer. 1.5.4 Pump and motors shall be sized such that the motor does not overload at any point on the operating curve. Pumps and motors shall be designed to perform with a reasonable service life when operated continuously or intermittently. Motors shall be designed with a minimum service factor of 1.15. Other motor requirements shall be as specified in this section and as specified in Division 16 – Electrical. 1.5.5 Electrical Motors, Controllers, Starters, and Disconnects: Furnish motors, controllers, starters, and disconnects with their respective pieces of equipment. Motors, controllers, starters, and disconnects shall conform to and shall have electrical connections in accordance with the National Electrical Code. Controllers and starters shall have a maximum of 120-volt control circuits, and auxiliary contacts for use with the controls furnished. 1.5.6 Any structural, piping, electrical requirements, wiring, instrumentation and controls, drawings, or other modifications required to accommodate equipment offered shall be done at no additional cost to the Owner. 2 PRODUCTS 2.1 Hydraulic Unit Effluent Pump and Filtration Controls 2.1.1 Provide complete pump and filter control system consisting of the pump control panel, processor/controller panel, programmable logic controller and applicable software, flow meter and field control devices such as differential pressure switches, solenoid valves, float switches and American Mfg. Company, Inc. Model ASD 15 - (15 gpm) hydraulic unit mounted on a 22” x 28” aluminum skid. 2.1.2 Control panel shall be located in the building. The system control panel(s) shall be in a NEMA-4X enclosure. For those panels where “Hand-Off-Auto” (HOA) switches for zones, pumps and master valve are not mounted on backplate, those panels shall be provided with a hinged door. Duplex alternating pumps are required. The panel(s) shall house the following: 2.1.2.1 Circuit breaker for each pump motor starter. WW Associates Project No. 213003.05 11700/3 2.1.2.2 Magnetic starter, sized for pump motor HP, with overload protection in each phase. 2.1.2.3 “Hand-Off-Auto” selector switches, run indicating lights and running time meter and cycle counters for each pump. 2.1.2.4 Provide an “Emergency Stop” quick pump shut-off switch on outside of panel if requested. 2.1.2.5 Terminal blocks for field wiring. 2.1.2.6 Auxiliary contacts of starters for remote “run” indication. 2.1.2.7 Components shall be UL Listed. 2.1.2.8 Wires shall be color and number coded. 2.1.2.9 Schematic shall be provided with control. 2.1.2.10 Provide optional remote alarm. 2.1.2.11 Installation shall be in accordance with National Electrical Code. 2.1.3 The programmable logic controller shall be as manufactured by Allen Bradley or Siemens. The PLC shall be housed inside of the NEMA-4X enclosure. All input/output (I/O) cards and electrical control components shall be located in the NEMA-4X enclosure. The controller shall include logic to do the following: 2.1.3.1 Alternate pumps following each dose. 2.1.3.2 Dose drip zones either individually or two at a time. 2.1.3.3 Provide for automatic filter backflushes at the beginning of each cycle. 2.1.3.4 Provide for automatic Forward Field Flushing based on a total cycle. 2.1.3.5 Provide threshold monitoring for flow variances. 2.1.3.6 Dosing shall be controlled by a float switch enable time dosed system. WW Associates Project No. 213003.05 11700/4 2.1.3.7 The system controller shall provide for a zone to be “rested” or taken “out of service”. The controller shall have the capability to bypass the zone(s) that have been taken out of service and dose the next available zone with normal sequence continuation. 2.2 Flow Meter 2.2.1 The effluent flow meter shall be 1.0 inch diameter Multi-Jet Model # ACS100-R/1G AWWA Standard C with thread connections manufactured by Accent Control Systems or approved equivalent. 2.2.2 Meter must be velocity-type meter with water evenly distributed by multiple jet-nozzles. The meter’s register shall integrate velocity into totalized flow. 2.2.3 Meter shall have a magnetic drive with 1 contact closure per gallon. 2.2.4 Transmitter shall be two wire with pulse output proportional to flow. 2.3 Hydraulic Unit Effluent Pumps 2.3.1 Submersible Turbine Goulds Blaster Model 20EB05, 3.75”, 1/2HP, 4 stage, 11/4” NPT Discharge, 230V, 1 phase, rated for 15 gpm at 125’ TDH or approved equal. 2.3.2 Pumps must be able to satisfy the three operating conditions: multiple zone dose, individual zone forward flush, and filter backwash. 2.3.3 Pumps shall be UL Listed. 2.3.4 Pumps shall be hardwired in a watertight junction box per local code. 2.3.5 Each pump shall have individual breaker, contactor and capacitor. 2.3.6 Pumps shall have check valve, disconnect and shut-off valve on supply pipe prior to hydraulic unit. 2.3.7 Pumps and motors shall be supplied as part of the Drip Irrigation System package. 2.4 Float Switches 2.4.1 The drip system shall contain four (4) float switches (Off Level, Dose Enable, Level Indicator, and High Level). WW Associates Project No. 213003.05 11700/5 2.4.1.1 All floats to have two-conductor cords and be hardwired in a watertight junction box. 2.4.1.2 All floats to be UL Listed. 2.4.1.3 All floats to have normally open contacts. 2.4.1.4 All floats to send signal to PLC when activated. 2.4.1.5 All float switches to be installed per local code. 2.4.2 The bottom two floats (Off Level & Dose Enable) shall be: 2.4.2.1 115 volt 2.4.2.2 Narrow angle pilot duty switch. 2.4.3 The top two floats (Level Indicator, High Level) shall be: 2.4.3.1 115 volt 2.4.3.2 Wide angle encapsulated differential switches. 2.5 Hydraulic Unit Filtration Rack 2.5.1 Automatic Filter Assembly 2.5.1.1 The automatic filter shall be a package assembly filter battery consisting of two – 3/4 inch single filters. 2.5.1.2 Filters shall be controlled from the PLC controller by electrically activated valves. 2.5.1.3 Filter battery shall have the following: 2.5.1.3.1 Inlet/outlet diameter: 3/4 inch MIP 2.5.1.3.2 Minimum backflush pressure: 5 0 psi 2.5.1.3.3 Maximum working pressure: 140 psi 2.5.1.3.4 Maximum recommended flow rate: 15 gpm 2.5.1.3.5 Filter surface area: 25 sq. in. per filter 2.5.1.3.6 Filtering volume: 5.8 cu. in. WW Associates Project No. 213003.05 11700/6 2.5.1.3.7 Length of flushing period: 10-15 seconds/filter 2.5.1.3.8 Amount of water used for flushing: 10 gallons 2.5.1.3.9 Filter rings: 140 mesh - 115 micron 2.5.1.3.10 Head loss: 5.0 psi at 15 gpm 2.5.1.4 Backflush procedure to operate as follows 2.5.1.4.1 Control calls for backflush to start. 2.5.1.4.2 Backflush initiated at beginning of each cycle. 2.5.1.4.3 Filtration rings separate on filter element 2.5.1.4.4 Hydraulic valves close discharge and open backflush outlet on one bank at a time which takes that filter out of service. 2.5.1.4.5 Water supply for backflush is provided through the filters in service. 2.5.1.4.6 Backflushing takes place for 10-15 seconds per filter; discharge of flush water is to wet well. 2.5.1.4.7 Remaining filters are sequentially backflushed until entire battery has been cleaned. 2.5.1.5 Automatic Filter battery shall be by American Manufacturing Co., Inc. Model ASD-15 or approved equivalent. 2.6 Precast Reinforced Concrete Tanks – See Section 03450 – Precast Concrete Tanks 2.7 Valves 2.7.1 Pump Master Control Valve 2.7.1.1 Shall be hydraulic valve with integral diaphragm operated by hydraulic pressure to control the irrigation pump discharge. 2.7.1.2 Valve body and cover shall be 1-1/2 inch diameter reinforced nylon. 2.7.1.3 Springs shall be stainless steel. 2.7.1.4 Valve shall have threaded end connections. WW Associates Project No. 213003.05 11700/7 2.7.1.5 Inlet pressure range shall be 15-140 psi. 2.7.1.6 Valve shall have slow drip-tight closure to prevent water hammer. 2.7.1.7 Valve control shall be electrically from the computer controller. 2.7.1.8 Valve shall be DOROT “Gal” valve 1-1/2 inch diameter plastic valve. 2.7.2 Field Control Valves 2.7.2.1 Shall be hydraulic valve with integral diaphragm operated by water pressure to operate the drip system discharge in both the irrigation mode and forward field flush mode. 2.7.2.2 Valve body shall be 1.0 inch diameter plastic. 2.7.2.3 Springs shall be stainless steel. 2.7.2.4 Valve shall have threaded end connections. 2.7.2.5 Inlet pressure range shall be 15-140 psi. 2.7.2.6 Valve shall have slow drip-tight closure to prevent water hammer. 2.7.2.7 Valve control shall be electrically from the computer controller. 2.7.2.8 Valve shall be Dorot “Gal” valve 1.0 inch diameter plastic valve or equal. 2.7.3 Check Valves 2.7.3.1 Check valves smaller than 3 inches shall be iron body, bronze trim, swing check valves, meeting requirements of MSS-SP-71. Flanged valves shall conform to ANSI B 16.10 and B16.1 for Class 125. 2.7.3.2 Check valves shall be iron body, bronze mounted, swing check valves, meeting requirements of AWWA C508. Check valves 3 through 12 inches shall be for 175-psi nonshock cold water working pressure. Valves shall have outside weight and lever. Manufacturer shall be American Darling Valve and Manufacturing Company, Clow Valve, Kennedy Valve Manufacturing Company, M&H Division of Dresser Industries, G-A Industries, Inc., or approved equal. WW Associates Project No. 213003.05 11700/8 2.7.4 Gate Valves 2.7.4.1 Nonrising stem gate valves 3 inches and larger shall meet requirements of AWWA C500 “AWWA Standard for Gate Valves for Water and Sewerage Systems, or valves 3 inches through 12 inches shall meet requirements of AWWA C509 “AWWA Standard for Resilient Seated Gate Valves for Water and Sewerage Services.” Working pressure shall be at least 200 psi for valve sizes 3 though 12 inches or at the pressure rating specified for adjacent piping, whichever is greater. Valve ends shall be compatible with piping systems in which valves are installed. Valve shall be cast iron body, bronze mounted. Valves shall have 0-ring seals and shall open counterclockwise. Asbestos packing will not be acceptable. 2.7.4.2 Exterior valves shall be suitable for underground service and have a standard 2-inch square operating nut that extends within 12 inches of the prevailing ground surface. 2.7.4.3 All gate valves shall be manufactured by Mueller Company, American Darling, or Clow Valve. 2.7.5 Air Release Valves 2.7.5.1 Shall be placed on high point of each sub-zone supply and return manifolds and at high point on common supply and return manifolds as per design. 2.7.5.2 Shall be 1 inch diameter (or greater where required) combined air release and vacuum breaker valve. 2.7.5.3 Shall operate to release or admit air from or into the line. 2.7.5.4 Shall be suitable for the designed working pressures in the line. 2.7.5.5 Valve body shall be high strength fiberglass reinforced plastic with operating parts of non-corrosive materials. 2.7.5.6 Valves shall be API Air Released Vacuum Release Model VBK-1. 2.8 Effluent Piping/Wiring 2.8.1 Gravity Piping WW Associates Project No. 213003.05 11700/9 2.8.1.1 Shall be Schedule 40 PVC DWV as a minimum. 2.8.1.2 Fittings shall be Schedule 40 PVC suitable for underground installation, and meeting the requirements of ASTM D 1784, Type 1120, ASTM D 1785, and ASTM D 2467. 2.8.1.3 All joints shall be solvent welded in accordance with ASTM D 2855 with the use of purple primer and ASTM D 2564 PVC glue. 2.8.2 Non-Dripper Pressure Pipe, Including Supply and Return Piping 2.8.2.1 All non-dripper pressure pipe shall be Schedule 40 PVC pressure rated. 2.8.2.2 Rigid piping shall be ASTM D 1784, Type 1120 for use with solvent welded ASTM D2467 Schedule 40 fittings, and meeting the requirements of ASTM D 1785. 2.8.2.3 All joints shall be solvent welded in accordance with ASTM D 2855 with the use of purple primer and ASTM D 2564 PVC glue. 2.8.2.4 All flexible PVC shall be Schedule 40 PVC and shall be readily assembled using Schedule 40 PVC fittings and flexible PVC to rigid PVC adhesive. The flexible PVC shall be solvent welded in accordance with ASTM D 2855 with the use of purple primer and ASTM D2564 PVC glue. 2.8.2.5 Top feed Supply and Return Manifolds shall be used on sites with drainfield slopes of greater than 10% or as required by manufacturer. Top Feed manifolds shall be constructed of Schedule 40 PVC pipe and fittings. 2.8.3 Drip Tubing 2.8.3.1 All dripper tubing shall have the following characteristics: 2.8.3.1.1 Dripperline shall be 1/2 inch diameter nominal O.D. Polyethylene tubing with a pressure compensating mechanism allowing a constant discharge rate from each dripper opening. Inside diameter shall not be less than 0.57 inch. 2.8.3.1.2 Dripperline discharge rate per orifice shall be 0.61 gallons per hour. Orifice spacing shall be 2 foot on center. WW Associates Project No. 213003.05 11700/10 2.8.3.1.3 Dripper pressure compensating mechanism shall maintain a uniform dripper flow rate over a pressure range of 5-60 psi. Dripper mechanism shall be activated at 5 psi. 2.8.3.1.4 Dripper diaphragm shall be constructed of synthetic elastomer to withstand effects of chemicals, fertilizers and acids (to a pH of 2) 2.8.3.1.5 Diaphragm shall have a continuous self-cleaning feature which continuously measures the actual flow rate. Particle that could clog the dripper create back pressure and push back the diaphragm to continuously clean and flush particles from the regulating chamber of the diaphragm. 2.8.3.1.6 Irrigation dripperline shall be equal to Netafim Irrigation, Inc. BIOLINE pressure compensating dripperline for wastewater as distributed by American Manufacturing Company, Inc. 2.8.3.1.7 Drip tubing shall be installed where indicated on design drawings. 2.8.3.2 The dripper lines are to be automatically scoured (forward flushed) at a minimum of one time per month or once every prescribed number of cycles with a minimum scouring velocity of 2 feet per second at the distal end of each lateral. 2.8.3.3 The drip tubing manufacturer shall provide a head loss chart for various drip tubing lateral lengths to provide for a minimum scouring velocity of 2 feet per second at the distal end of each lateral. 2.8.3.4 Dripperline shall be installed along contour and in accordance to manufacture’s requirements. 2.8.3.5 Drip tubing shall be connected to header lines with special connectors provided by manufacturer to provided water tight connection. 2.8.3.6 Drip tubing is NOT to be glued but rather connected to PVC with the barbed-typed fittings approved by the manufacturer. WW Associates Project No. 213003.05 11700/11 2.8.4 Field Wiring 2.8.4.1 All electrical wiring from the computer/controller to the field control valves shall be furnished and installed by system installer. 2.8.4.2 All field wiring shall be appropriately sized by an electrician according to local code. 2.8.4.3 All electrical cables shall be U.L. Listed suitable for direct burial. 2.8.4.4 Field wire splices shall be installed in suitable wire splice pull boxes with waterproof connections for access to splice connections. The boxes shall be well marked (not with metal posts or rods) and have structural capacity for in-ground installation and light vehicular yard care traffic. At-grade access is preferred. 2.8.5 Lightning Protection: Provide lightning protection for field wiring, hydraulic unit building and control panel in accordance with the Nation Electric Code and as approved by WW Associates. 2.9 System Operation 2.9.1 Time Dosing 2.9.1.1 The drip dispersal system shall utilize a time dosing technique via the automatic controller specified herein. 2.9.1.2 System shall utilize level sensing devices (standard mechanical differential float switches) located in a dosing tank downstream from the pretreatment process. 2.9.1.3 When activated by the rising level of effluent in the dosing tank, the controller shall enable the disposal cycle, and as dictated by the controller, pump the effluent through 115 micron disc filters and then to final drip dispersal. 2.9.1.4 The pump control panel shall be equipped with four float switches to control the timed doses to be discharged. 2.9.1.5 The four float switches, "Redundant Off", "Standard Dose Enable", “Peak/Level Indicator” and "High Level" shall function as follows: 2.9.1.5.1 Redundant Off - The water level must be high enough to overcome the "Redundant Off" (first and bottom) WW Associates Project No. 213003.05 11700/12 float in order for the pump to be permitted to run in automatic mode. 2.9.1.5.2 Standard Dose Enable - When the water level rises high enough to overcome the "Standard Dose Enable" (second) float and the time clock has timed out the preset time delay (rest time between dosing cycles), the pump will activate and the lead zone(s) is dosed. The pump will continue to run for the length of time required to disperse of the specified dose volume and then shut off. The pump will remain off until the internal time clock again times out the preset time delay which the pump will activate (as long as the "Standard Dose Enable" float is still up) and will run again until the specified volume is pumped. This process will repeat until the water level drops below the "Standard Dose Enable" float and the pump run timer has timed out. 2.9.1.5.3 Peak / Level Indicator - Used to indicate level of effluent in final pump tank. 2.9.1.5.4 High Level - If the water level rises enough to overcome the "High Level" (fourth) float, the audiovisual alarm will activate (if applicable). The audio portion of the alarm may be silenced by pressing the Test-NormalSilence switch to the silence position. 2.9.2 Automatic Disc Filtration and Backflush 2.9.2.1 Submersible pumps (duplex) shall deliver unfiltered effluent to each of the disc filters during the normal forward filtration process. 2.9.2.2 Each filter shall automatically go through a backflush cycle to clean all of the disc filters at the beginning of the cycle. 2.9.2.3 Backflushing shall proceed as follows: 2.9.2.3.1 One filter valve shall close, thus blocking the flow of unfiltered effluent to that filter. 2.9.2.3.2 After a short delay, the other flushing valves shall open. 2.9.2.3.3 The clean effluent from the forward filtration filters shall be directed to the outlet manifold. WW Associates Project No. 213003.05 11700/13 2.9.2.3.4 Filtered effluent from the outlet manifold shall then flow in reverse direction (in through the spine) of the filter to be backflushed and into the backflush nozzles, spinning the loosened discs and flushing the captured debris out the drain manifold. 2.9.2.3.5 The accumulated impurities shall discharge back into the backwash unit. 2.9.2.3.6 The backflush procedure shall last approximately fifteen to thirty seconds (or longer if necessary) then the back flushing valve shall close. 2.9.2.3.7 Only after the first filter has completed its backflushing cycle, will the next filter begin its cycle of backflushing in the same manner as the first until all the filters have been backflushed. 2.9.2.3.8 Effluent shall then be pumped through clean disc filters, then through the flow meter and finally through the outlet manifold to the drip field supply line. 2.9.3 Forward Field Flush 2.9.3.1 Each drip zone shall automatically undergo a periodic “Forward Field Flush” every fifty cycles or 15 days (whichever occurs first) to scour the inside of the dripper tubing. 2.9.3.2 Forward Field Flush to be accomplished by automatically opening a Zone Return valve to allow effluent to return to the head of the system after passing through the drip field. 2.9.3.3 1.6 gpm per distal lateral connection shall be provided to maintain minimum scouring velocity of 2 feet per second at the distal end of each lateral. 2.9.3.4 Zones shall Forward Field Flush individually. 2.9.3.5 Flushing volume to be a minimum of three times the volume of the drip tubing. 3 E XE C U T IO N 3.1 Installation and Construction WW Associates Project No. 213003.05 11700/14 3.1.1 System Installation 3.1.1.1 Pumps, filtration rack, hydraulic unit enclosure with heating element, controls, floats and valves shall be installed according to plans and in accordance with appropriate regulations. 3.1.1.2 Non-dripper piping and electrical connections shall be made in accordance with all appropriate codes and regulations. 3.1.1.3 Hydraulic unit enclosure shall be heated with thermostatically controlled heater, 225 watt, 120 volt powered through the controller to include wiring and conduit. 3.1.1.4 Drip Tubing Installation (See “Construction Notes” specified herein): 3.1.1.4.1 No wet weather installation. 3.1.1.4.2 Prepare field location for installation. 3.1.1.4.3 Dig header ditch for field manifold. 3.1.1.4.4 Install dripper tubing. 3.1.1.4.4.1 Install all drip tubing along contour. 3.1.1.4.4.2 Install at depth specified on plans. 3.1.1.4.4.3 Install drip tubing with either standard trencher (i.e., Ditch Witch) or by hand. 3.1.1.4.4.4 See construction notes for addition installation techniques. 3.1.1.4.5 Install loops (flex tubing). 3.1.1.4.6 Dig ditches for conveyance lines. 3.1.1.4.7 Dry fit pressure lines and field manifolds. 3.1.1.4.8 Glue all fittings and place valve boxes. 3.1.1.4.9 Install electrical and phone line. 3.1.1.4.10 Check power supply and power up unit. WW Associates Project No. 213003.05 11700/15 3.1.1.4.11 Provide one day volume of clean water for startup. 3.1.1.4.12 Pressure check all fittings and lines 3.1.1.4.13 Inspection of field and loops. 3.1.1.4.14 Flush all fields through the air release valves. 3.1.1.4.15 Set run time for Central Unit. 3.1.1.4.16 Check setup values against calculated values. 3.1.1.4.17 Find leaks and repair. 3.1.1.4.18 Backfill once lines and fields are determined to have no leaks. Back filling is to be controlled to prevent the damaging of pipes or fittings 3.1.1.4.19 Grade and seed site. 3.1.2 Supervisory and Technical Support 3.1.2.1 Drip irrigation manufacturer shall provide supervisory services and technical support during installation of the drip effluent disposal system. 3.1.2.2 Services to be provided are as follows: 3.1.2.2.1 Supervise/inspect installation of filtration system, float switches and pumping systems. 3.1.2.2.2 Technical support for installation of the control panels. 3.1.2.2.3 Supervise/inspect installation of subsurface pressure compensating drip irrigation tubing. 3.1.2.2.4 Supervise/inspect installations and hookups of automatic valves. 3.1.2.2.5 Supervise/inspect installation of connections of drip tubing to supply and return manifolds. WW Associates Project No. 213003.05 11700/16 3.1.3 Drip Dispersal Field Construction Notes 3.1.3.1 All installation and construction techniques shall conform to state and county codes pertaining to on-site sewage systems and the permit for this site. 3.1.3.2 The installation of this system shall be in accordance with specifications and procedures as supplied by the Manufacturer of the equipment. 3.1.3.3 The drip tubing shall be installed using a trencher or by hand. 3.1.3.4 All PVC pipe and fittings shall be Schedule 40 Type 1 rated for pressure applications. All glued joints shall be cleaned and primed with purple (dyed) PVC primer prior to being glued. 3.1.3.5 All cutting of PVC pipe, flexible PVC and dripper tubing of size 1 1/2” or smaller shall be accomplished with pipe cutters approved by American Manufacturing Company, Inc. No sawing of PVC, flexible PVC or dripper tubing of size 1 1/2” or smaller allowed. 3.1.3.6 All PVC pipe, flexible PVC and dripper tubing in the work area shall have the ends covered with duct tape to prevent construction debris from entering the pipe. Prior to gluing, all joints shall be inspected for and cleared of any construction debris. 3.1.3.7 All automatic valves (zone valves & field flush return valves) shall be installed with isolation valves, bypass valves, and disconnects (i.e. unions, flanges) for manual field operation during field maintenance events. All valves must be provided with at-grade access. 3.1.3.8 Drainfield supply and return lines and manifolds to be installed at adequate depth to prevent freezing. Horizontal spacing between the dripper lines and the installation depth to be as specified. 3.1.3.9 No activity on drainfield area other than minimum required to install system. Do not park equipment, drive large equipment over or store materials on drainfield area. 3.1.3.10 No wet weather installation is permitted. 3.1.3.11 The contractor shall be certified by the drip irrigation manufacturer to install this type of system and shall hold a pre-construction meeting with the individuals responsible for soil evaluation, WW Associates Project No. 213003.05 11700/17 permitting and inspections prior to site work beginning to insure protection of the site conditions and to ensure the system is installed according to design. 3.1.3.12 If site conditions are determined to require the installation of the system to deviate from these plans, all work shall stop immediately and WW Associates shall be notified. Any ongoing work shall be at the sole responsibility of the contractor. 3.1.3.13 All force mains shall be tested for leaks prior to drip tubing installation and prior to system startup. Uncovered force mains shall be visibly inspected for leaks. If a leak is suspected in covered force mains then the force main shall be re-tested at a minimum pressure of at least percent above the design operating pressure, for at least 30 minutes. There shall be no discernible leakage. 3.1.4 System Startup 3.1.4.1 A representative from the manufacturer shall be on hand for system startup. 3.1.4.2 Three (3) days of training shall be provided by the factory trained representative supplying the drip irrigation system equipment. 3.2 Drip System Warranty 3.2.1 For one year (12 months) after the date of purchase, drip system manufacturer will repair or replace any product or portion thereof which proves to be defective due to materials or workmanship. 3.3 Service and Maintenance 3.3.1 Contractor shall provide a one year maintenance warranty beginning at the expiration manufacturer's original one year warranty (see above “Drip System Warranty”). End of Section WW Associates Project No. 213003.05 11700/18 Section 13100 Precast Concrete Building System 1 GENERAL 1.1 Description: The Contractor shall furnish precast concrete building system for chemical feed equipment. The building shall be delivered and field erected by the manufacturer on the Contractor’s poured-in-place floor slab as indicated on the contract drawings. The precast concrete building shall be EASI-SET brand Model 1012 as manufactured by Smith-Midland Corporation, or equal by the Clear Flow Company, Rotondo Precast, or other manufacturer as approved by WW Associates. The manufacturer shall provide the building with all necessary openings as indicated on the drawings in conformance with the manufacturer’s structural requirements. 1.2 References: The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only. 1.2.1 ACI-318-93, “Building Code Requirements for Reinforced Concrete.” 1.2.2 Concrete Reinforcing Institute, “Manual of Standard Practice.” 1.2.3 ANSI/ASCE 7-93 “Building Code Requirements for Minimum Design Loads in Buildings and Other Structures.” 1.2.4 American Society for Testing and Materials (ASTM). 1.2.5 1996 BOCA. 1.2.6 UL-752 Test Method Level 4 for bullet resistance certified by an independent structural engineer. 1.2.7 Building fabricator must be producer member of National Precast Concrete Association (NPCA) and participate in its plant certification program. In addition, building fabricator must have a minimum of 5 years experience manufacturing and setting transportable precast concrete buildings. 1.3 Quality Assurance 1.3.1 Installer Qualifications: Engage an experienced installer to erect the pre-engineered precast concrete building who has specialized in the erection and installation of types of precast concrete building systems similar to that required for this project and who is certified in writing by the precast concrete building system manufacturer as qualified for erection of the manufacturer’s products. 1.3.2 Single-Source Responsibility: Obtain the precast concrete building system components, including precast concrete wall and gabled roof panels, and accessory components, from one source from a single manufacturer. WW Associates Project No. 213003.05 13100/1 1.4 Design Criteria 1.4.1 Dimensions 1.4.1.1 Exterior: 10’ wide x 12’ long x 10’ – 7 1/2” high. 1.4.1.2 Interior: 9’-6” wide x 11’-6” long x 7’ – 6” high. 1.4.2 Design Loads 1.4.2.1 Seismic Load Performance Category “C,” Exposure Group III. 1.4.2.2 Standard Live Roof Load: 60 psf. 1.4.2.3 Standard Floor Load: 250 psf. 1.4.2.4 Standard Wind Loading: 130 mph. 1.4.2.5 Allowable Soil Bearing Capacity: 2,500 psf (assumed). 1.4.3 Roof 1.4.3.1 Gabled roof panel shall have a peak in center of 10-foot direction and shall slope 12 horizontal and 3.713 vertical to each side. The roof shall extend a minimum of 6 inches beyond the wall panel on each side. 1.4.4 Gabled roof and wall panels must each be produced as single component monolithic panels. No roof or vertical wall joints will be allowed, except at corners. Wall panels shall be set on top of the cast-in-place concrete floor slab. 1.5 Submittals: Provide the following submittals to WW Associates in a timely manner for approval: 1.5.1 Shop drawings and product data consisting of precast concrete building system manufacturer’s product information for building components and accessories. 1.5.2 Shop drawings for precast concrete roof and wall panels, and other precast concrete building system components and accessories that are not fully detailed or dimensioned in manufacturer’s product data. 1.5.3 Shop drawings and product data for mechanical heating and ventilation equipment. 1.5.4 Building engineering calculations prepared by or under supervision of a professional engineer legally authorized to practice in the jurisdiction where the project is located. WW Associates Project No. 213003.05 13100/2 1.5.5 Manufacturer’s color charts showing full range of colors, textures, and patterns available for precast wall panels with factory-applied finishes. 1.5.6 Professional engineer’s certificate prepared and signed by a professional engineer, legally authorized to practice in the jurisdiction where the project is located, verifying that the precast concrete building system meets indicated loading requirements and codes of authorities having jurisdictions. 1.6 Delivery, Storage, and Handling 1.6.1 Deliver prefabricated components, panels, and other manufactured items so they will not be damaged or deformed. Package wall and roof panels for protection against transportation damage. 1.6.2 Handling: Exercise care in unloading, storing, and erecting wall, roof, and floor panels to prevent bending, warping, twisting, and surface damage. 1.6.3 Stack materials on platforms or pallets, covered with tarpaulins or other suitable weathertight ventilated covering. Store precast concrete wall and roof panels so that water accumulations will drain freely. Do not store panels in contact with other materials that might cause staining, denting, or other surface damage. 2 PRODUCTS 2.1 Materials 2.1.1 Concrete: ASTM C 260, steel-reinforced, 5,000-psi minimum 28-day compressive strength, air entrained for precast concrete panels. Reinforced concrete for the floor slab shall be as specified in Section 03300 – Cast-inPlace Concrete. Precast concrete roof panels shall be 4-inch minimum thickness. Precast concrete wall panels shall be 3-inch minimum thickness. 2.1.2 Reinforcing Steel: ASTM A 615, Grade 60. 2.1.3 Post-tensioning Strand: Post-tensioning cable shall be 41K Polystrand CP50, 1/2inch, 270 ksi, 7-wire strand, ASTM A 416, greased plastic sheath. The roof and floor slab shall each be post-tensioned by a single, continuous tendon. The tendon shall form a substantially rectangular configuration having gently curving corners and a corner where the tendon members are anchored. Tendons shall be greased and enclosed within a sheath. 2.1.4 Caulking: All joints between panels shall be caulked on the exterior and interior surface of the joints. Caulking shall be Sikaflex-1A elastic sealant. Exterior caulk joint shall be 3/8-inch square so that sides of joint are parallel for correct caulk adhesion. Back of joint shall be taped with bond breaking tape to ensure adhesion of caulk to parallel sides of joint and not the back. WW Associates Project No. 213003.05 13100/3 2.1.5 Openings: 13” x 13” for exhaust fan as shown on drawings. 2.1.6 Panel Connections: All panels shall be securely fastened together with 1/4-inch thick steel brackets. Steel shall be structural quality, hot-rolled carbon complying with ASTM A 283, Grade C, and hot-dipped galvanized after fabrication. All fasteners shall be 1/2-inch diameter bolts complying with ASTM A 307 for low carbon steel bolts. Cast-in anchors used for panel connections shall be Dayton-Superior No. F-63. All inserts for corner connections must be bolted directly to form before casting panels. No floating-in of connection inserts shall be allowed. The manufacturer shall connect wall panels to floor slab with 4-inch expansion anchors. 2.2 Accessories 2.2.1 Doors and Frames: Doors and frames shall comply with Steel Door Institute “Recommended Specifications for Standard Steel Doors and Frames” (SDI100), and as herein specified. The buildings shall be equipped with double 3’0” x 6’-8” x 13/4”, 18-gauge galvanized/insulated CECO Imperial right hand reverse metal doors with 16-gauge galvanized frames. Doors and frames shall be bonderized and painted with one coat of rust inhibitive primer and one finish coat of enamel paint selected by the Owner from the manufacturer’s color charts. 2.2.2 Door Hardware 2.2.2.1 Handle: Lindstrom stainless steel, 81/2 inches x 2 inches. 2.2.2.2 Hinges: Hager 920P (primed with non-removable hinge pins), three hinges per door. 2.2.2.3 Lock Set: Easy-Set 200KD (Bigon No. 26 finish). 2.2.2.4 Surface Bolt, Upper: CECO 4031-US2C (Cadmium plated finish). 2.2.2.5 Surface Bolt, Lower: CECO 4032-US2C (Cadmium plated finish). 2.2.2.6 Astragal: A4441/68R. 2.2.2.7 Threshold: CECO No. 897 V-raised interior, extruded aluminum threshold with neoprene seal and shall be ADA compliant. 2.2.2.8 Door Holder: Yale H940V26D, overhead slide type surface mounted door holder with safety release. 2.2.2.9 Drip Cap: National Guard 15D72. 2.2.2.10 Door Stop: Ives 445B26D. WW Associates Project No. 213003.05 13100/4 2.2.3 Mechanical Heating and Ventilation Equipment/Accessories: Provide unit heater, intake louvers, and exhaust fan as indicated on the drawings. 2.3 Finishes 2.3.1 Interior of Building: Smooth steel form finish on all interior panel surfaces. 2.3.2 Exterior of Building: Exterior finish shall be EASI-Brick. 2.3.3 Doors shall be finished as selected by the owner. 3 E XE C U T IO N 3.1 Site Preparation 3.1.1 Provide cast-in-place reinforced concrete floor slab as indicated on the drawings. The slab shall be sloped in both directions as indicated on the drawings and capable of supporting loads imposed by the structure. 3.1.2 The floor slab for the building shall bear fully on a crushed stone base that is at least 1 foot larger than the length and width of the building. 3.1.3 Stone layer beneath the building floor slab shall be a minimum of 6 inches thick. The vertical soil capacity under stone shall be compacted to have a minimum bearing capacity of 1,500 psf. Stone shall be VDOT No. 57 coarse aggregate fill. Stone shall be placed within a perimeter form to 1-inch above highest point of area where the building will be placed. 3.1.4 The crushed stone base shall be kept within the confines of the soil or perimeter form. Do not allow the stone base to become unconfined so that it may wash, erode, or otherwise be undermined. 3.1.5 Provide positive drainage for the concrete floor slab as indicated on the drawings. 3.2 Site Access 3.2.1 The Contractor must provide a level, unobstructed area large enough for a crane and tractor-trailer to park adjacent to the floor slab. Crane must be able to place outriggers within 5 feet of edge of the slab, and truck and crane must be able to get side-by-side under their own power. No overhead lines may be within 75-foot radius of center of the slab. 3.3 Install mechanical heating and ventilation equipment in accordance with the manufacturer’s written recommendations. End of Section WW Associates Project No. 213003.05 13100/5 Section 15000 Floor Drain Equipment, Piping and Fittings 1 GENERAL 1.1 Description: 1.1.1 Floor drain system shall consist of, but not be limited to all piping, fittings, fixtures associated with the treatment building floor drain, outfall floor drain pipe. 1.1.2 The Contractor shall provide all labor, materials, fittings, appurtenances, trenching, backfilling and compaction for the installation of the floor drain system as shown on the drawings. 1.2 Reference Specifications: 1.2.1 Sections 02200 Earthwork. 2 PRODUCTS 2.1 PVC pipe and fittings Schedule 40, Grade PVC 2116: ASTM D 1785 and ASTM D 2241 outside building footprint. 2.2 Piping under building shall be cast iron soil pipe. 2.3 Floor drains shall be coated cast iron with double drainage flange, weep holes, bottom outlet and round strainer in an adjustable clamping collar. 2.3.1 Drains shall be as manufactured by Josam, Model 30900-9AD Series or approved equal. 3 E XE C U T IO N 3.1 Inspection and Preparation 3.1.1 Prior to all piping work, carefully inspect the installed work or excavation by other trades and verify that all such work is complete to the point where the piping may be installed in accordance with these documents. 3.1.2 Follow the drawings in laying out work and check drawings of other trades to verify sufficient space to install piping. 3.1.3 Coordinate with other trades to permit the work of all trades to be installed. 3.1.4 Offsets, fittings, and extra pipe necessary to avoid interference shall be furnished and installed without additional expense to the Owner. WW Associates Project No. 213003.05 15000/1 3.1.5 If the piping is installed without coordinating with other trades and so as to cause interference with work of other trades, the necessary changes shall be made at no extra charge. 3.2 Installation 3.2.1 Rough in piping below treatment building floor slab and install floor drain in treatment building concrete floor slab in accordance with manufacturers requirements. 3.2.2 Provide water seal trap. (“p” trap). 3.2.3 Make up pipe joints and install pipe to lines and grades as shown on the drawings to include outfall structure. 3.2.4 Test pipe/system to insure no leakage prior to backfilling trench or pouring treatment building concrete flooring. 3.2.5 Backfill and compact trench per Section 02200 – Earthwork of these specifications. 3.2.6 Clean floor drain system and flush piping. Piping and floor drain to be smooth and entirely free from obstructions to flow. 3.2.7 Protect system from entrance of foreign matter during construction. End of Section WW Associates Project No. 213003.05 15000/2 Section 16010 Electrical General Provisions 1 GENERAL 1.1 The contract documents apply to this section. 1.2 Provide necessary items for a complete installation of electrically operated equipment specified in specifications and as shown on Contract Drawings. 1.3 Arrange equipment substantially as shown on the drawings. Make deviations only where necessary to avoid interference. Check equipment size against available space prior to shipment to avoid interference. 1.4 Material, equipment and installation shall meet requirements of applicable codes and standards listed below. Electrical material and equipment shall bear the UL label except where UL does not label such types of material and equipment. 1.4.1 Reference standards are referred to by abbreviation: International Building Code ....................................................................... IBC Certified Ballast ........................................................................................CMB Electrical Testing Lab ................................................................................ ETL National Fire Protection Association...................................................... NFPA National Electrical Code ........................................................................... NEC Underwriter’s Laboratories, Inc. ................................................................ UL National Electrical Manufacturers Association. .................................... NEMA Institute of Electrical and Electronic Engineering. ................................... IEEE Insulated Power Cable Engineers Association ...................................... IPCEA National Electrical Safety Code ............................................................. NESC Illuminating Engineering Society ............................................................... IES Edison Electric Institute.............................................................................. EEI Electronic Industries Association ............................................................... EIA American National Standards Institute .................................................... ANSI American Society for Testing and Materials ......................................... ASTM 1.5 Submit shop drawings for the following: 1.5.1 Panelboards 1.5.2 Molded Case Circuit Breakers 1.5.3 Fused Disconnect Switches WW Associates Project No. 213003.05 16010/1 1.5.4 Lighting Fixtures 1.5.5 Devices 2 PRODUCTS 2.1 Nameplates 2.2 General - Furnish and mount on each new and modified panelboard, starter, safety switch, and all similar controls, a nameplate descriptive of the equipment or equipment controlled and circuit or device controlled from. 2.3 Provide black and white nameplates constructed from laminated phonemic with a white center core. Letters shall be engraved in the phonemic to form white letters 3/8inch high. Fasten nameplates with screws or a non-adhesive type fastener. 2.4 Supporting material shall be complete with hangers, connectors, bolts, clamps, and necessary accessories to make a complete installation. Products by Binkley, Steel City, Kindorf, Raco, Unistrut, or Erico will be acceptable. 2.5 Stainless steel enclosures for electrical equipment shall be Type 304 stainless steel. 3 E XE C U T IO N 3.1 Provide equipment connections complete with motor controls, switches, wiring devices, control devices, protective devices, wiring, conduit and other accessories. All equipment and connections shall be as recommended by the manufacturer and as indicated on drawings and specified in specifications. 3.2 Install control and alarm wiring for all equipment in accordance with Division 16 Specification Sections. Before installing control circuits, ensure that controls and wiring diagrams are in accordance with those furnished with the equipment. Make any changes required due to different equipment, more up-to-date controls or safety devices, so that the equipment operates as required. Control voltage shall not exceed 120 volts unless indicated otherwise on the drawings. 3.3 When equipment is supplied with electrical requirements other than those specified or shown on the drawings, associated electrical devices and circuitry of the current sizes and ratings shall be provided. End of Section WW Associates Project No. 213003.05 16010/2 Section 16040 Testing and Placing in Service 1 GENERAL 1.1 Description: Provide all material, equipment, labor, and supervision to perform electrical tests in accordance with the requirements of this specification. Notify the Owner at least 3 working days in advance of tests. 1.2 Quality Assurance: Final acceptance will depend upon meeting requirements of specified tests. 1.2.1 Perform all tests in accordance with manufacturer's recommendations. Should manufacturer's recommendations conflict with these specifications, contact the owner for instructions. 1.2.2 Material or equipment failing tests shall be repaired or replaced at the Contractor's expense. 1.2.3 Record all test results and incorporate into a legible report. Four bound copies of all test reports shall be delivered to the owner at the end of test period. 2 P R O D UC T S 2.1 The contractor shall employ appropriate testing devices and personnel trained in their use. 3 EXEC UT ION 3.1 System Tests 3.1.1 Perform equipment tests as required in equipment sections of this specification. 3.1.2 Upon completion of equipment tests, function test each Division 16 electrical system specified to verify total system operation. 3.1.3 Test all interlocks, safety devices, and fail safe functions in addition to design function. 3.1.4 Tests shall include the following in addition to test requirements of individual sections of Division 16 3.1.4.1 Measure the load on each phase of the service panel. 3.1.4.2 Measure the no load and full load voltages (phase to phase and phase to ground for each phase) of each service. WW Associates Project No. 213003.05 16040/1 3.1.4.3 Measure the ground resistance of the main service grounding electrode. 3.1.4.4 Make insulation resistance tests on all power circuitry and motors. 3.2 Instruct Owner personnel in proper operation and maintenance of equipment. End of Section WW Associates Project No. 213003.05 16040/2 Section 16110 Raceways 1 GENERAL 1.1 The contract documents apply to this section. 2 PRODUCTS 2.1 Rigid Steel Conduit: Low carbon, hot-dipped galvanized inside and outside, with threaded ends, minimum size 3/4-inch. Fittings: Cast iron or alloy steel, galvanized. 2.2 Liquid tight flexible metal conduit - Sealtite Type U.A. by Anaconda, Type U.L. and CSA by International Metal Hose Co., Sealflex-U by Universal Metal Hose Co., or approved equal. 2.3 Polyvinyl chloride conduit: Schedule 80, with threaded ends, minimum size 3/4-inch. Fittings shall be threaded. 2.4 Schedule 40 electrical plastic conduit: Designed for underground installation without concrete encasement and normal duty application above ground and made of polyvinyl chloride (EPC-40-PVC for type II and III applications.) 2.5 Sealing fittings or bushings - Crouse-Hines Series EYS, EZD or EZS or equal by Pyle National, Appleton, or approved equal. 2.6 Insulated Bushings - Type B or SBT, as applicable, by O-Z or Series B1900 or Series TC700, as applicable, by Steel City. 3 E XE C U T IO N 3.1 Install Galvanized Rigid Steel conduit for all above grade, exposed interior and exterior conduit. 3.2 Install non-metallic schedule 40 conduit for all below grade conduit unless indicated otherwise. 3.3 Space groups of conduit uniformly. 3.4 For bends and offsets, use an approved Hickey or Bending machine. 3.5 Cut all conduits with hacksaw or approved cutting machine and ream after threading to remove all burrs. 3.6 Fasten conduit securely to outlets, junctions and pull boxes to ensure firm electrical contact. Join conduit with approved couplings. No running threads will be allowed. 3.7 Provide insulated bushings and double locknuts on conduits entering or leaving outlet, junction, or pull boxes, and cabinets. WW Associates Project No. 213003.05 16110/1 3.8 Avoid condensation pockets in installations. Keep conduit, fittings and boxes free from foreign matter, before, during and after installation. 3.9 All buried conduits outside of buildings shall have a minimum of thirty (30) inches of cover. End of Section WW Associates Project No. 213003.05 16110/2 Section 16120 Wire, Cable and Wiring (600 Volt Max.) 1 GENERAL 1.1 The contract documents apply to this section. 1.2 Standards - NEMA Publications WC3, WCS, and WCZ, as applicable. 1.3 Conductor Coding 1.3.1 Color code insulated grounding conductors in accordance with NEC. 1.3.2 Color code current carrying conductors, except control and instrumentation conductors, as scheduled on the drawings. 1.3.3 No. 12 and No. 10 conductors shall have continuous insulation color. 1.3.3.1 Color code conductors larger than no. 10 which do not have continuous insulation, color by application of at least two laps of colored tape on each conductor at all points of access. 1.3.3.2 Number code all control and instrumentation wiring at all points of access. 1.4 Conductor sizes are based on copper unless otherwise indicated on drawings. 2 PRODUCTS 2.1 Conductors 2.1.1 Conductors shall have moisture resistant, flame retarding, thermoplastic insulation, type "THHN/THWN", rated for 600 volts unless. 2.1.2 Conductors shall be stranded, soft annealed copper. 2.1.3 Underground outdoor conductors shall be alloy coated, type “Use” insulated and rated for 600 volts. 2.1.4 Provide No. 12 conductors, unless otherwise indicated. 2.1.5 Control conductors shall be No. 14 minimum for NEC Class I and No. 16 for NEC Class II. 3 E X E C U T IO N 3.1 Install wiring in conduit. 3.2 Install splice-free conductors within ducts, conduits or earth. WW Associates Project No. 213003.05 16120/1 3.3 Connect No. 10 and smaller wires with constant pressure expandable spring type connectors, "Scotchlok" by 3M, or approved equal. 3.4 Connect No. 8 and larger wires with compression connectors or splices as manufactured by Burndy, T & B, or approved equal. 3.5 Insulate mechanical splicing connectors to at least 200 PCT. of wire insulation using pre-stretched tubing connector insulators, 3/M PST for No. 2 and larger conductors. 3.6 Use terminal strips to interconnect and splice control cables. 3.7 Pull conductors using recognized methods and equipment leaving ample lengths of wire at junctions for connections. 3.7.1 Use soapstone or UL approved compound as required to facilitate pulling. 3.7.2 Complete and cleanout conduit system before pulling wire. 3.8 Form and tie all wiring in panelboards and control panels. End of Section WW Associates Project No. 213003.05 16120/2 Section 16130 Switch and Outlet Boxes 1 GENERAL 1.1 The contract documents apply to this section. 1.2 Provide boxes, complete with cover or device plate for switches, receptacles, or other similar devices, or where required for pulling or joining branch circuit wiring. 1.3 Conduit bodies may be used on exposed conduit work instead of outlet boxes. 2 PRODUCTS 2.1 Cast boxes, zinc-cadmium finish malleable iron. Cast boxes shall be series FD by Crouse-Hinds, Appleton, or approved equal. 2.2 Box sizes (minimum) shall be four (4) inches wide, four (4) inches long and 2-1/2 inches deep. 2.3 Cover plates for exterior areas - Corrosion resistant cast aluminum, gasketed, weatherproof, Crouse-Hinds = DS701G for duplex receptacles and - DS185 for switches, or approved equal. 2.4 Provide covers and gaskets with conduit bodies, of a design suitable for the application. Provide watertight conduit bodies in damp and wet locations. Conduit bodies will be cast ferrous alloy, galvanized, as manufactured by Crouse-Hinds, Appleton, or approved equal. 3 E XE C U T IO N 3.1 Support all boxes to maintain alignment and rigidity. 3.2 All interior and exterior device boxes shall be cast type. 3.3 Clean boxes of all foreign matter prior to installation or wiring or devices. End of Section WW Associates Project No. 213003.05 16130/1 Section 16140 Wiring Devices 1 GENERAL 1.1 The contract documents apply to this section. 1.2 Standards, NEMA Publications No. WD-1, No. WD-2, No. WD-3, No. WD-5. 1.3 Wiring device color shall be gray except where otherwise indicated. 2 PRODUCTS 2.1 A.C. General-Use snap switches 2.1.1 Provide totally enclosed, 20 ampere, 120/277 volt, quiet A.C. General-Use snap switches. 2.1.2 Switches shall be single pole. 2.1.3 Switches shall be specification grade. Bryant 4900 series, Hubbell 1220 series, P&S 20AC series, G.E. 5950 series. 2.2 Duplex convenience receptacles 2.2.1 Provide NEMA configuration 5-20R duplex 125 volt grounding type receptacles rated for 20 amperes unless otherwise indicated on the drawings. 2.2.2 Receptacles shall be specification grade. Bryant 5362, Hubbell 5362, P&S 6300, G.E. 4108. 3 E X E C U T IO N 3.1 Install A.C. General-Use snap switches for switching lighting or other branch circuit loads as indicated on the drawings. 3.1.1 Locate approximately 4 foot, 6 inches above finished grade unless other indicated. 3.2 Install receptacles as indicated on drawings. 3.2.1 Locate approximately where indicated on drawings. 3.3 All wiring devices indoors and exterior shall have a weatherproof ‘in-use” cover. End of Section WW Associates Project No. 213003.05 16140/1 Section 16150 Motors 1 GENERAL 1.1 The contract documents apply to this section. 1.2 Standards, NEMA Publications MG-1, MG-2, MG-13. 1.3 Motors shall be furnished as part of the equipment which they drive. Their characteristics shall be such as to provide proper operation of the driven equipment without exceeding motor ratings. Motor enclosures shall be appropriate for the location and provide physical protection from external sources of motor damage. 2 PRODUCTS 2.1 Unless otherwise specified or indicated on the drawings, the following features and ratings apply. 2.1.1 Motor winding insulation shall be Class "B". 2.1.2 Motor frequency shall be 60 HZ. 2.1.3 Motors shall be designed to operate on either 200 or 110 Volt. 2.2 Motor enclosures, types, and features specifically indicated on drawings or in other portions of specifications shall be provided. 2.3 Motor shall be suitable for starting by type of starters indicated. 2.4 Phase and voltage ratings shall be NEMA standard ratings indicated on electrical drawings. 2.5 All 3-phase motors shall have low voltage protection and be protected from short circuits and overloads on all three phases. 3 E XE C U T IO N 3.1 Not applicable. End of Section WW Associates Project No. 213003.05 16150/1 Section 16190 Supporting Devices 1 GENERAL 1.1 The contract documents apply to this section. 1.2 References: Reference standards are referred to by abbreviation as follows: ASTM A47 Malleable Iron Castings ASTM A48 Gray Iron Castings ASTM A108 Steel Bard, Carbon, Cold-Finished, standard quality ASTM A123 Zinc (hot galvanized) coatings on products fabricated from rolled, pressed, and forged steel shapes, plates, bars, and strip ASTM A153 zinc coating (hot dip) on iron and steel hardware ASTM A164 Electrodeposited coatings of zinc on steel (type RS) for zinc ASTM A165 Electrodeposited coatings of cadmium on steel (type TS) for cadmium ASTM A167 stainless and heat-resisting chromium-nickel steel plate, sheet and strip ASTM A307 carbon steel externally and internally threaded standard fasteners ASTM A525 steel sheet, zinc coated (galvanized) by the hot-dip process, general requirements ASTM A366 steel, carbon, cold-rolled sheet, commercial quality ASTM A386 zinc coating (hot dip) on assembled steel products ASTM A526 steel sheet, zinc coated (galvanized) by the hot-dip process, commercial quality ASTM A569 steel, carbon (0.15 maximum percent), hot rolled sheet and strip, commercial quality ASTM A570 hot-rolled carbon steel sheet and strip, structural quality ASTM A575 merchant quality hot-rolled carbon steel bars ASTM A576 steel bars, carbon, hot-rolled, specialty quality ASTM A611 steel, cold-rolled sheet, carbon, structural ASTM A635 hot-rolled carbon sheet and strip, commercial quality, heavythickness coils (formerly plate) ASTM B26 aluminum alloy sand castings ASTM B85 aluminum alloy die castings WW Associates Project No. 213003.05 16190/1 ASTM B209 aluminum alloy die castings ASTM B221 aluminum alloy extruded bars, rods, wires, shapes, and tubes ASTM B316 aluminum-alloy extruded bar, rod, pipe, and structural shapes for electrical purposes (bus conductors) ASTM B633 electrodeposited coatings of zinc on iron and steel 1.3 Materials shall conform to the following standards. 1.4 Channel Steel for hot-dip galvanizing; grade 33 12 gage & 14 gage ..........................A570 Steel for hot-dip galvanizing, Grace C 14 gage & 18 gage ...........................A611 Aluminum, alloy 6061 or 6063 ..................................................................... B308 Stainless steel, Type 304 ...............................................................................A167 1.5 Nuts S Steel, electroplated or A108 .......................................................................A567 Aluminum or 6061 ....................................................................................... Alloy Stainless steel, Type 304 ...............................................................................A167 1.6 Threaded Fasteners Steel bolts, nuts, washers ...............................................................................A307 Aluminum or B316 ........................................................................................ B221 Stainless Steel, type 304 ................................................................................A157 1.7 General Fittings Steel, plated; made from 1-5/8 bar 1/4” and thicker .......................................A576 Steel, plated; made from 1-5/8 bar 1/4” and thicker .......................................A569 Steel, plated; made from flat plates 1/4” and thicker....................... A569 or A635 Iron Castings............................................................................. A47-68 and 48-74 Aluminum castings ................................................................. B26-74 and B85-73 Aluminum............................................................................................ Alloy 3003 Stainless Steel .............................................................................. A167, Type 304 1.8 Pipe Clamps and Straps Steel .................................... A570 Grade 33, A575, A611 Grade C as Applicable Aluminum............................................................................................ Alloy 3003 Stainless Steel .............................................................................. A167, Type 304 WW Associates Project No. 213003.05 16190/2 1.9 Plates (4”x4”x1/4” thick and larger) Galvanized ..........................................................................................A525, A123 Aluminum ..................................................................................B209, Alloy 3003 Stainless Steel .............................................................................. A167, Type 304 1.10 Finishes Hot-Dip Galvanized (Iron & Steel Hardware) ............................................. A153 Hot-Dip Galvanized (Assembled Steel Prod.).............................................. A386 Mill Galvanized (Sheet Steel & Coils) ..................................................A525 G90 Electrodeposited Zinc ................................................................... A164 and B633 Electrodeposited Cadmium ............................................................. 165, Type TS 1.11 Supporting Material shall be complete with hangers, connectors, bolts, clamps, and necessary accessories to make a complete installation. 2 PRODUCTS 2.1 Outdoors: Threaded materials shall be stainless steel. All other materials shall be aluminum, stainless steel, or both. 2.2 Acceptable factory fabricated channel support system manufacturers: B-Line Systems, Inc. Midland-Rose Corporation, Electrical Products Division (Kindorf) Unistrut 3 E XE C U T IO N 3.1 Support all equipment which is not inherently self-supporting in such a manner as to effect a rigid and permanent installation. Use factory-fabricated channel, support systems, and as appropriate, other structural shapes such as angles, “C” Channels, pipe, and the like. End of Section WW Associates Project No. 213003.05 16190/3 Section 16420 Electric Service 1 GENERAL 1.1 The contract documents apply to this section. 1.2 Electrical characteristics of service will be: 1.3 208/120 Volts, 3 phase, 4 wire. 2 PRODUCTS 2.1 Specified in other Sections. 3 E XE C U T IO N 3.1 Contractor is responsible for contacting Appalachian Electric Power Company and satisfying all requirements for the new electric service connection. 3.2 Metering provisions shall meet requirements of the power company. 3.3 Install meter bases furnished by the power company. 3.4 Provide overhead electric service conduit, weather head, drip loop and point of attachment. Coordinate installation with the power company to make the project a complete and useable facility. End of Section WW Associates Project No. 213003.05 16420/1 Section 16450 Grounding 1 GENERAL 1.1 The contract documents apply to this section. 1.2 Provide grounding in accordance with NEC as a minimum. Additional grounding requirements shall be as specified or indicated on drawings. 2 PRODUCTS 2.1 Ground rods shall be copper clad steel, 10 feet in length and 3/4-inch in diameter. 2.2 Grounding electrode conductors shall be bare copper sized in accordance with NEC Table 250-94, or as shown on the contract drawings. 2.3 Equipment grounding conductors in raceways shall be copper with green insulation, sized in accordance with NEC 250-95. Bare copper grounding conductors will be acceptable in underground outside raceways. 2.4 Ground connections shall be exothermic type Cadweld or Thermoweld, when direct buried. 3 E XE C U T IO N 3.1 Install equipment grounding conductors in all raceways containing conductors having 100 volts or more to ground. 3.2 If earth resistance of the service grounding electrode is more than required, install one additional ground rod a minimum of sixteen (16) feet from other electrodes. End of Section WW Associates Project No. 213003.05 16450/1 Section 16470 Panelboards 1 GENERAL 1.1 The contract documents apply to this section. 1.2 Standards - NEMA Publication No. P8-1. 2 PRODUCTS 2.1 Panelboards shall be enclosed dead-front safety type with features and ratings as scheduled on the drawings. 2.2 Panelboards shall be as manufactured by Square D, General Electric, Siemens, or approved equal. Other manufacturer substitutions will not be allowed. 2.2.1 Panels known as “Load Centers” are unacceptable. 2.2.2 208 volt panels shall be “NQOB” type. 2.3 Molded case circuit breakers shall be as required for intended use and specified in this Division. 2.4 Bus Bars shall be rectangular solid copper. 2.5 Panelboard enclosures shall be NEMA 1 rated. Provide locks with four (4) master keys to fit all panels, plastic covered directory holders and cards. 2.6 Space where shown in panel schedules designates space for future protective devices and shall include bus and support components. 3 E XE C U T IO N 3.1 Bolt all connections to bus bars through highly conductive metal. 3.2 Install cabinets so that center of top breaker or switch does not exceed six (6) feet, six (6) inches above finished floor. 3.3 Circuits shall be arranged and numbered so as to provide balance of all phases and/or legs. 3.4 Provide stainless steel 1/4-inch spacers between all panel enclosures and masonry walls. End of Section WW Associates Project No. 213003.05 16470/1 Section 16475 Molded Case Circuit Breakers (MCCB) 1 GENERAL 1.1 References: NEMA Publication AB 1 molded case circuit breakers. 1.2 This section applies to all MCCB whether individually enclosed, group mounted, or part of other equipment. 2 PRODUCTS 2.1 General 2.1.1 MCCB shall be bolt-on type with ratings and special features as scheduled. 2.1.2 Trips Trips shall be thermal magnetic with inverse time delay and instantaneous time-current characteristics. Motor Circuit Protectors (MCP) having magnetic only trips shall be provided where indicated. MCP’s used with high efficiency motors shall be capable of carrying the transient inrush current without having to be set at more than 13 times full load current. 2.2 208/120 volt MCCB shall be commercial grade NQOB. 2.3 Manufacturer shall be Square D, General Electric, Siemens, or approved equal. 3 E X E C U T IO N 3.1 Not used. End of Section WW Associates Project No. 213003.05 16475/1 Section 16510 Lighting 1 GENERAL 1.1 Related Documents: Documents affecting work of this section include, but are not necessarily limited to, General Conditions, and Sections of Division 1 of these Specifications. 1.2 Work Included 1.2.1 Furnish, assemble, hang, and connect all lighting fixtures for fixture outlets shown by symbols on the drawings. 1.2.2 All fixtures shall be furnished complete with sockets, internal wiring, leads, trim, plaster rings and frames, hangers, supports, ballasts, etc., as applicable and required for a complete and workmanlike installation. 2 PRODUCTS 2.1 Acceptable Manufacturers 2.1.1 Products of certain manufacturers are specified, equal and similar products of other manufacturers will be acceptable. 2.2 Light Fixtures 2.2.1 Lighting fixtures shall be as indicated on the contract drawings with applicable design features specified in this section. 3 E X E C U T IO N 3.1 Supports 3.1.1 Support light fixtures directly from the building structure. 3.2 Alignment: Align all fixtures and fixture rows and clean all fixtures and diffusers prior to final acceptance. End of Section WW Associates Project No. 213003.05 16510/1
© Copyright 2024