MANUAL DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE Title: Distribution Task Manual – Part 11 CIRCUIT BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM:BLR, BLRM & BLRME COMPILED BY APPROVED BY Unique Identifier: Document Type: Revision: Published date: Total pages: Review date: FUNCTIONAL RESP 34-960 DMN 0 FEBRUARY 2009 26 FEBRUARY 2014 AUTHORISED BY _ _ _ _ _ _ _ SJ FABER/ DM NTOMBELA _ _ _ _ _ _ _ A PERSADH _ _ _ _ _ _ _ CD SMITH _ _ _ _ _ _ _ MN BAILEY Compiler Switchgear Care Chairperson for TESCOD DTM for MD (D Div) DATE: 09 Dec 2008 DATE: 09 Dec 2008 DATE: 27 Jan 2009 DATE: 28 Jan 2009 WG Content Page Foreword...................................................................................................................................................... 2 Introduction .................................................................................................................................................. 3 1 Scope .................................................................................................................................................. 4 1.1 Purpose.................................................................................................................................... 4 1.2 Applicability .............................................................................................................................. 4 1.3 Roles and Responsibilities....................................................................................................... 4 2 Normative/Informative References...................................................................................................... 5 2.1 Normative................................................................................................................................. 5 2.2 Informative. .............................................................................................................................. 5 3 Definitions And Abbreviations ............................................................................................................. 5 3.1 Definitions ................................................................................................................................ 5 3.2 Abbreviations ........................................................................................................................... 5 4 Requirements ...................................................................................................................................... 5 4.1 First and Second Line Maintenance ........................................................................................ 5 4.2 Specialist Maintenance ............................................................................................................ 6 4.3 Modifications ............................................................................................................................ 20 5 Testing................................................................................................................................................. 20 6 Related/Supporting Documents .......................................................................................................... 20 6.1 Related Documents.................................................................................................................. 20 6.2 Forms and Records.................................................................................................................. 20 7 Spares ................................................................................................................................................. 20 Annex A-Circuit-breaker report.................................................................................................................... 21 Annex B - Impact assessment..................................................................................................................... 23 JF Scholtz / Feb 2009 Rev 0 DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 2 of 26 Foreword This Task manual was compiled to document the tasks procedure of maintaining DELLE / ALSTOM’S CIRCUIT BREAKERS of types HG 710 and HG 720, rated at 33KV and 1250A with BLR, BLRM or BLRME MECHANISMS to ensure that maintenance tasks are carried out in a safe manner. This Task manual supersedes all previous work instructions / maintenance procedures on HG 710 and HG 720 with BLR series mechanisms. DELLE / ALSTOM HG 710 AND HG 720 BREAKERS Revision history This document cancels document SCSINAAV0. Date SEPTEMBER 2005 JANUARY 2007 Rev. no. 0 Clause Remarks - Compiled By: DM Ntombela Original issues as SCSINAAV0 0 - Compiled By: SJ Faber /DM Ntombela The template / format and ref. number changed Revision date. 2 3 - Normative references updated; Definitions and abbreviation updated; Re-numbered all the titles and added more information Included Revision History information; - Included impact assessment form; and When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Date FEBRUARY 2009 Rev. no. Clause 0 Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 3 of 26 Remarks - Reference number changed to DMN_34-960 - Work instruction naming changed to Task manual - Document approved as DMN_34-960 Authorisation This document has been seen and accepted by: Name Designation MN Bailey Corporate Manager Divisional Technology C Smith TESCOD A Persadh Switchgear Care WG Chairperson SJ Faber / DM Ntombela Compiler Development team This Task manual was previously prepared by: J.H. Coetzer A.M. Jacobs E. Mutloane D. Ntombela J. Richter C.D. Smith T. Stoffberg H.Z. Strzalkowski C. Troskie K. van Coller H. van der Westhuizen And was revised by: DM Ntombela J Wilson S Bouwer J Ramoroka E Mandavha SJ Faber Introduction The Task Manual has replaced the Work Instructions within the Distribution Division. This has been done to assist the end users of these documents and the following is important to note: • The contents of a Task Manual are always linked to the requirements of one or more Job Plans. In many instances only selected paragraphs / sections of the Task Manual will apply to a specific Job Plan. • Task Manuals also form the main content of the training module for the task and therefore only people who have attended the training and assessed as competent should be assigned the task as described in the Task Manual. This Task manual is the revision of the document that was initially compiled and titled CIRCUITBREAKERS: DELLE / ALSTOM, TYPE: HG 710 & HG 720, MECHANISM: BLR, BLRM & BLRME, RATINGS: 33kV; 1250A to formalize the procedures of performing tasks when carrying maintenance tasks out. The document includes the latest updates in information, format, diagrams to make the document more user-friendly and safety precautions. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 4 of 26 Key words Specialist Maintenance, Tools, Equipment, Personal Protective, circuit-breaker, Fixed contact, HG 720, HG 710, Arc control device, Moving contact, Transfer contact, Re-assembly, External mechanism, Testing Bibliography Manufacturer’s manual. 1 Scope 1.1 Purpose The purpose of this Task manual is to standardise maintenance instructions on DELLE / ALSTOM CIRCUIT-BREAKERS, TYPE HG 710 and HG 720 with BLR series MECHANISM and rated 33kV; 1250A. 1.2 Applicability This document is applicable to Eskom Distribution Division and all contractors working for distribution division. 1.3 Roles and Responsibilities 1.3.1 Plant Managers shall be responsible for: a) Ensuring that equipment job plans are available and issued for specific maintenance. b) Ensuring that the maintenance feedback information that is available in the maintenance management system is analysed. 1.3.2 Each Field Services Manager shall be responsible for: a) Ensuring that staff carrying out maintenance tasks is trained, competent and authorized to perform maintenance on the specific equipment; b) Ensuring that instructions are implemented and adhered to and equipment is maintained in accordance to relevant Task manuals. c) Ensuring that the maintenance feedback information / data is captured and recorded into the system for future maintenance planning. 1.3.3 Electricity Delivery Manager shall be responsible for: a) Ensuring that trained, competent and authorized staff is available to perform maintenance / tests on equipment out on maintenance when scheduled; b) Ensure that the relevant EDM section is available on site to isolate the equipment AC / DC supply. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME 2 Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 5 of 26 Normative/Informative References Parties using this document shall apply the most recent edition of the documents listed below: 2.1 Normative Occupational Health and Safety Act and Regulations (OHSAct). NRS079-1: Mineral Insulating Oils. ESKASABT0 (EST_32-332): Rev. 0, Oil spill clean-up and rehabilitation. ESKPVAEY6: Rev. 0, Operating Regulations for High Voltage Systems. DISASAAT8 (DST_34-1710): Rev. 4, Provision and use of Personal protective equipment. SCSPBAAY2 (DPL_34-1005): Rev. 0, Environmental management policy. SCSASAAX4 (DST_34-1451): Rev. 2, Standard for the maintenance of circuit-breakers and oil immersed isolators. DPC_34-444: Rev. 0, Procedure for the application and maintenance of portable earth’s. SCSPVABF4 (DPC_34-908): Rev. 0, Procedure for Barricading. DPC_34-227: Rev. 0, Pre-Task Planning and feedback process. Manufacturers manual. 2.2 Informative. DST_34-04: TESCOD framework 3 Definitions And Abbreviations 3.1 Definitions All definitions in ESKPVAEY6 and OHSAct 85 of 1993 are applicable. 3.2 Abbreviations PCB: Polychlorinated Biphenyls. CDP: Career Development Programme; PTO: Principal Technical Officer; STO: Senior Technical Officer; TO: Technical Officer; and CCC: Change Control Committee. 4 Requirements 4.1 First and Second Line Maintenance a) Insulators shall be inspected for cracks or burn marks. b) Pollution levels on fibre insulators shall be monitored. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 6 of 26 c) There shall be no oil leaks - if any leaks are found these shall only be repaired by authorised personnel. d) All gauge glasses shall be clear and legible. e) All oil levels shall be at the level mark - there shall be maximum and minimum level marks on all oil gauge glasses f) Mechanism boxes shall be clean and dust free - checks shall be made for any general or obvious defects. g) Mechanism box door and cover seals shall be intact. h) Mechanism heaters shall be operational - if a thermostat is fitted the cut out shall be set at approximately 250C. i) The operating label shall be securely mounted and shall be legible from the operating position. j) All metal work shall be checked for corrosion or rust. k) The earth straps shall be in a good condition and effectively connected. l) All feeder advances shall be recorded as fault trips or operations. NOTE: All defects found are to be reported to the Work Management Centre with the work order feedback. 4.2 Specialist Maintenance 4.2.1 Pre-Planning 4.2.1.1 Spares and Materials a) Approved lubricant; b) Approved electrical cleaner; c) Lint free cloth; d) Upper insulating cylinder "O"ring gaskets; e) Oil filling plug gasket; f) Upper case gasket; g) Sheath for upper contact fingers; h) Oil level indicator gaskets; i) Contact fingers; j) Contact tip and contact rod; k) Arcing ring; l) Pole cover gasket; m) Lower insulating cylinder gaskets; n) Tripping damper gasket; o) Drain cock gasket; p) Bearing covers gaskets; q) Mechanism shaft gasket; r) Shaft gasket and. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME s) Split pins: 4.2.1.2 Tools and Equipment a) Micro ohmmeter; b) Standard set of tools; c) Mechanism operating lever/tool ; d) Scaffolding/Ladder; e) a 5 kV insulation tester; f) 1 x empty drum; g) Cleaning tray; h) Portable oil pump and hose with fittings; i) Grease gun; and j) Speed tester. 4.2.1.3 Personal Protective Equipment Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 7 of 26 All personal protective equipment shall be in accordance with DISASAAT8 and shall include those identified during risk assessment (DPC_34-227). a) Overall; b) Hard hat; c) Safety boots; d) Fall Arrest System (where necessary); e) Gloves. 4.2.2 Safety and Preparation a) Isolate and earth panel in accordance with ESKPVAEY6. b) Erect barricading in accordance with SCSPVABF4. c) Erect scaffolding/ladder (where required). d) Ensure all tools, equipment and materials are placed inside the barricaded area and where they will not hinder or obstruct any worker or the entrance. e) Manually close and open the circuit-breaker from the mechanism box to discharge springs. f) Environmental hazards shall be removed in accordance with SCSPBAAY2 and ESKASABT0 g) Isolate the D.C. supply to the panel to prevent accidental closing or tripping of the circuitbreaker. h) Ensure that circuit-breaker is isolated in terms of ESKPVAEY6 and any LV supply is switched OFF before commencing with the next steps. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME 4.2.3 Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 8 of 26 Maintenance Risk assessment and critical task analysis shall be done in accordance to DPC_34-227 and approved safe work procedures before the commencement of work. 4.2.3.1 Opening the circuit-breaker a) Ensure that the correct circuit-breaker has been OPENED, ISOLATED and EARTHED as per ESKPVAEY6 and check the status indicator on the mechanism door to be indicating OFF. b) Where the moving contact is to be replaced, close the circuit-breaker and remove fuses or switch the D.C. supply to the panel OFF. c) Ensure that under no circumstances will any person start to work on the mechanism while the trip spring is still charged and proceed to step f). d) Where the moving contact is not going to be replaced, close the circuit-breaker, remove or switch the D.C. supply to the panel OFF to prevent accidental closing or tripping of the circuitbreaker. e) Before draining the oil, manually perform an open – close - open operation to discharge the closing springs in the operating mechanism (refer to step b) and see figure 1). f) Ensure that the circuit-breaker is in an open position before commencing with maintenance (refer to step b) and see figure 1). Figure 1 g) Loosen and remove the drain plug, attach the draining hose onto the draining valve and the oil pump. h) Loosen and remove the explosion chamber securing screws and remove it from the pole head. i) Open the oil drain valve (where applicable), start the oil pump and drain the dirty oil into the empty drum (see figure 2). When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 9 of 26 Figure 2 j) Inspect the gas exhaust opening grate and the vent to be clean and free from blockages. k) Also inspect the safety valve and oil return valve to be free from blockages, clean with electrical cleaner and rinse with oil. l) Check the explosion chamber gasket for cracks and any physical damage, replace it with a new one during re-assembly. m) Loosen and remove the jumper connection bolts for the upper terminal and lower terminal and secure the jumper at a safe position (see figure 3). n) Loosen and remove the upper case securing bolts and remove the upper case (see figure 3). Figure 3 o) Loosen and remove the gauge glass securing bolts, remove the gauge glass and the gaskets (see figure 4). p) If the gauge glass housing is dirty, it must be cleaned with approved electrical / hand cleaner and painted with white paint where necessary. q) Inspect the gauge glass and the securing gauge glass holder for cracks and any physical damages and replace them with new ones if necessary (see figure 4). When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 10 of 26 Figure 4 r) Re-fit the gauge glass gaskets (new one), gauge glass and the gauge glass securing holder/flange and tighten the securing screws. s) Check the upper case gasket for cracks and any physical damages. 4.2.3.2 Fixed contact NOTE: In case of type HG 720 the fixed contacts-assembly and explosion pot are attached to expansion chamber and the fixed contact will only be exposed after removing the explosion pot. a) b) c) For HG 720 • Loosen and remove the expansion chamber securing screws, remove the expansion assembly and place it on the cleaning tray. • Loosen and remove explosion chamber / arc control device securing screws and remove it from the expansion chamber / fixed contact assembly. • Loosen and remove the fixed contacts-assembly holding screws and remove the assembly from the expansion chamber for inspection and maintenance. For HG 710 • Loosen and remove the expansion chamber securing screws, remove the expansion assembly and place it on the cleaning tray. • Loosen and remove the fixed contacts-assembly securing screws and remove the assembly from the expansion chamber for inspection and maintenance. Inspect the fixed contacts and the arcing rings for pitting, burn marks, carbon deposits and any physical damages (see figure 5). Figure 5 When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME d) Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 11 of 26 Should the fixed contact fingers and the arcing rings be damaged the following steps shall be followed to dismantle the fixed contact assembly: • Remove the arcing ring by inserting a rod (20mm for HG 710 and 22mm for HG 720) in the fixed contact. • Loosen and remove the arcing ring from the finger contacts protecting sheath. • Unscrew and remove the protecting sheath, remove the fixed contact fingers and extract the rod. e) Clean the contact-fingers and the arcing ring with electrical cleaner and scourer, and examine their condition. f) Measure the diameter of the arcing ring bore and it must not exceed 28mm for HG720 and 26mm for HG710 and replace the damaged ring with the new one (see figure 6). Figure 6 g) Measure the remaining contact surface of the finger contacts, the remaining contact surface must not be less than 15mm for HG720 and HG710 and replace the damaged contacts with the new one (see figure 7). h) In reverse order assemble the new finger contacts onto the contact holder. Figure 7 When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 12 of 26 i) Re-fit the protective sheath over the finger contacts and screw it onto the contact holder, insert the appropriate rod into the fixed contact and screw the arcing ring onto the sheath. j) Assemble the fixed contact assembly onto the upper case. 4.2.3.3 Arc control device (Turbulator/Explosion pot) a) When type HG 720 is being maintained: b) • And the explosion pot / arc control device has been remove from the expansion chamber, proceed with / to step c). • But if it has not been removed from the expansion chamber or the circuit-breaker head, loosen and remove expansion chamber securing bolts and lift the assembly from the pole and place on the cleaning tray. • Loosen and remove the explosion chamber securing screws and remove it from the uppercase and proceed to step c). When type HG 710 is being maintained: • Loosen and remove the upper insulating cylinder holding bolts and remove the cylinder (refer to figure 6). • Loosen and remove the explosion pot holding screws and remove the explosion pot. c) Place the explosion pot in a cleaning tray and clean or wash it with insulating oil. d) Inspect the explosion pot for burn marks, cracks, carbon deposits and any physical damages (see figure 8). Figure 8 e) If the explosion pot is badly damaged replace it with a new one. 4.2.3.4 Moving contact a) With the explosion pot removed the moving contact will be exposed (see figure 9 (6)). When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 13 of 26 Figure 9 List of Parts on the figure 9 above: 1. Gasket for filling plug. 20. Arcing ring of upper fixed contact 2. Gas expansion chamber. 21. Explosion pot. 3. Upper case. 38. Gasket for lower insulating cylinder (27) (2 gaskets). 39. Clamping bolts of lower insulating cylinder (27) (2 SCREWS +6 BOLTS). 4. Safety valve. 22. Moving contact rod (conducting portion). 5. Upper terminal: – pad for HG 710. pad for HG 720 23. Lower sliding contact finger (8 finger for HG 710 and 10 for HG 720). 6. Arcing tip of moving contact rod (22). 7. Un-used number. 24. Set screws of upper and lower insulating cylinders (8 and 27) (8 screws). 8. Upper insulating cylinder (extinguishing chamber). 25. Centring elastic pin (HG 710) (2 pins). 9. Explosion pot support (for HG 710). 26. Insulating extension of moving contact rod (22). 44. Gasket for tripping damper (32). 27. Lower insulating cylinder. 46. Gasket for drain cock (33). 28. Tie rod (2 tie rods) 47. Gasket for bearing cover (50). 29. Mechanism case. 48. Mechanism shaft 30. Centring elastic pin (4 pins for HG 710). 49. Gasket for mechanism shaft (48). 31. Set screw of upper case (3) (8 screws). 51. Gasket for bearing cover (52). 10. Lower sliding contact – lower terminal. 11. Guide for moving contact rod (22) (2guides). 12. Filling plug. 13. Set screw of expansion chamber (2) (6 screws). 14. Gasket between expansion chamber (2) and upper case. 15. Oil return valve. 16. Gasket for oil level indicator. 17. Oil level indicator. 18. Finger protective sheath. 19. Upper contact finger (8 fingers for HG 710 and 10 for HG 720). 32. Tripping damper. 33. Pole drain cock. 34. Gas exhaust and vent opening. 35. Gas exhaust jet. 36. Gasket for upper insulating cylinder (8) (2 gasket). 37. Upper fixed contact holder. 40. Un-used number. 41. Stop screw to secure guide (11) (2 screws). 42. Damper guide of moving contact rod (22). 43. Base plate of guides (11). 45. Mechanism arm 50. Bearing cover (shaft exit side). 52. Bearing cover (opposite to shaft exit side). 53. Finger protective sheath (lower sliding contact (23)) (HG 720). 54. Tie-rod connecting pin (with damper guide portion of contact rod (42)). NOTE: Gasket 36 and 38 are identical in breakers HG 710. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 14 of 26 b) Clean the moving contacts arcing tip and the rod with electrical cleaner and scourer. c) Inspect the contact arcing tip for burn marks, carbon deposits and any physical damages (refer to figure 9 (6)). d) Should the contact arcing tip be heavily damaged replace it with the new one. e) To remove the contact arcing tip, use the square wrench to unscrew it (excessive force should not be applied without supporting or holding the contact rod with pliers). f) Ensure that the insulating extension part of the rod is free from cracks and any physical damages (refer to figure 9 (26)). g) Replace the contact arcing tip with the new one and tighten it. 4.2.3.5 Transfer contact a) To inspect the transfer contact: b) • Remove the lower insulating cylinder by loosening and removing holding screws; and • Remove the lower insulating cylinder (see figure10). Inspect the transferring contact fingers for burn marks, carbon deposits and any physical damages (in case of HG 720 a protective sheath has to be removed first and explosion port support has to be removed on type HG 710) (see figure 10 & refer to figure 9 (23)). Figure 10 c) Should the transferring contact fingers be badly damaged, replace them with the new ones. d) To replace the contact fingers on HG 720 follow the next steps: e) • Loosen and remove the transfer contact assembly securing screws and remove the assembly from the flange. • Remove the protective sheath from the contact assembly. • Disassemble the finger contact cluster assembly and replace the finger contact with new ones. To replace the contact fingers on HG 710 follow the next steps: • Loosen and remove the explosion support securing bolts / screws and remove the explosion pot / arc control device. • Loosen and remove the transfer contact securing screws / bolts and remove the transfer contact assembly. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME • Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 15 of 26 Disassemble the finger contact cluster assembly and replace the finger contact with new ones. f) Inspect the tie rod and the levers in the crank casing for any wear and cracks, and replace the damaged parts with ones. g) Assemble the transferring contact fingers cluster onto the flange and tighten the securing screws. 4.2.3.6 Re-assembly a) Re-fit the explosion pot assembly for type HG 710 and tighten the support holding screws and in case of type HG 720 re-fit the protective sheath and tighten the securing screws. b) Re-fit the lower insulating cylinder into position, insert the holding bolts and tighten the bolts. c) Refit the upper cylinder onto the lower cylinder and tighten the securing screws / bolts. d) For type HG 710 assemble the fixed contact assembly onto upper case, tighten the contact assembly holding screws. e) For type HG 720 assemble the fixed contact assembly, the explosion pot and the upper casing and tighten the securing screws / bolts. f) Re-fit the upper casing assembly onto the upper cylinder and tighten the securing bolts. g) Flush all poles with approved insulating oil, allow oil to drain and close the drain valve (where applicable). h) Remove the drain hose and the oil pump and re-fit the draining plug. i) Fill all poles with approved insulating oil, re-fit the expansion chamber and tighten the securing screws. j) Clean the external surface of the circuit-breaker with electrical cleaner and wipe it clean with lint free cloth. 4.2.3.7 External mechanism a) Ensure that all springs are still discharged before commencing with any work. b) Clean the pivots and the linkages with electrical cleaner and a paint-brush. c) Inspect the pivots and the linkages for wear, rust and any mechanical damages (see figure 11). Figure 11 d) Should any of the parts be worn or damaged it must be replaced with a new one. e) Lubricate all pivots with approved lubricant and spray the linkages with approve lubricant. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME 4.2.3.8 Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 16 of 26 Mechanism NOTE: The mechanism shall not be operated when it is not linked to circuit-breaker as this could lead to rupture or complete destruction of some parts of the mechanism. NOTE: When cleaning parts composing of sealed bearings (unless the bearings are to be replaced) with electrical cleaner ensure that the solvent does not penetrate the bearing as it will dissolve and remove the bearing grease. a) Ensure that the circuit breaker is switched off and the mechanism is discharged (closing spring is indicated as free) by manually OPENING, CLOSING and OPENING the circuit-breaker. b) If the circuit-breaker is closed "open-close-open" the circuit-breaker to discharge the springs and if the circuit-breaker is open "close-open" to ensure that the springs are discharged. c) Loosen and remove the operating mechanism cover securing screws and remove the mechanism cover (see figure 12). Figure 12 d) Clean dust and excessive grease deposits from the mechanism. e) Check and ensure that the trip and close plungers are free to move and are not bent. f) Inspect the operating mechanism parts (chains, cams, sprockets, lever, links etc.) for wear and rust, and check the springs for rust and tension loss (deformation) (see figure 13). g) Replace the damaged parts with new ones, and lightly lubricate drive levers, sprockets, rollers, drive chains etc with Vactra no 3 oil from Mobile (see figure 13). Figure 13 When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 17 of 26 h) Also apply a thin layer of grease over the closing and opening springs (see figure 14). i) Lubricate all the cams with Vélocité oil no.10 from Mobile or Vaseline from Mauny (see figure 14). j) Use S A E 90 to lubricate sprockets and chains and use silicone oil to lubricate pins, rollers, lever hinges, tie-rods and springs (see figure 14). Figure 14 NOTE: While cleaning and lubricating ensure that the cleaning materials and lubricants is prevented from going into the auxiliary switches. k) Clean the terminal blocks and auxiliary contacts, check that all electrical connections are tight, clean any oil drops on them and spray them with moisture repellent spray (see figure 15). Figure 15 l) To check the spring rewind motor brushes loosen and remove the brushes securing cap (on old equipment), unclip the plastic stopper (new equipment), remove the brushes, check the length of the brushes and inspect the commutator segments for excessive wear, short circuits and carbon build-up in between. m) Where the commutator segments are damaged, replace the motor (replace the commutator/rotor if available) with new one and where only brushes need to be replaced, clean carbon off the commutator with approved electrical cleaner, scourer and a brush and re-fit the brushes into position (see figure 16). When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 18 of 26 Figure 16 n) To replace the motor label motor-supply wires (where necessary) and disconnect the motor supply wires. o) Support the motor, loosen and remove the motor fixing screws, unhook the rubber drive belt and remove the motor (see figure 17). p) Loosen and remove cap screw (Allen screw) securing the pulley onto the shaft and remove the pulley form the shaft. q) Examine the drive belt for cracks and replace it with a new one where necessary, check the cam belt for wear, cracks or excessive slack and replace if it is necessary (see figure 17). Pulley Rubber Drive Belt and the drive pulley Figure 17 r) Check the anti-condensate heater to be in working order, if not repair or replace it with a new one (see figure 8. Figure 18 When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 19 of 26 s) Check the resistance of the closing, tripping and backup tripping coils, record the reading for future references and inspect the coils for any physical damages i.e. insulation breakdown, sticking plungers. t) Should any of the coils or part of the solenoid assemblies are damaged replace it with a new one by label the supply wires, disconnecting it and replacing it. u) Measure the core travel (must be 11mm wide), loosen and remove securing screws and remove the coil from the support plate / bracket. v) Clean the solenoids assemblies mounting place with electrical cleaner and the scourer, mount the new solenoid onto support plate / bracket and loosely tighten the securing screws (see figure 19). w) Check the travel core gap to be 11mm, adjust the gap when it is necessary, tighten the solenoid assembly securing screws and apply a little bit of locktite adhesive on the securing nuts. x) Ensure that the plunger rod clears the tripping lever by 2mm if not, loosen the assembly securing screws (8mm screws), adjust the gap and tighten the screws and nuts and apply the locktite again. y) Where it is necessary to replace the stop screw, ensure that ONLY ALUMINIUM SCREW is used and NO STEEL SCREWS shall be used as a stop screw. z) The steps p) to s) must be followed in replacing tripping and backup coils and it shall be ensured that the upper solenoid’s core is directly against the lower solenoid’s push rod (see figure 19). Figure 19 aa) To replace under voltage coil and micro switches (where applicable) mark the supply wires and disconnect them. bb) Loosen and remove the securing screws and remove the coil or the micro switch and replace them with new ones. cc) To replace the anti-pumping relay mark the wires, remove the wires, unclip the relay from the tray and remove it. dd) Refit and re-connect the anti-pumping relay in reverse order. ee) Check the door and side cover seals to be in place and in good order, replace the seals if damaged or perished and re-fit all the covers. ff) Re-fit the mechanism cover, insert the holding screws and tighten them. 4.2.3.9 Adjustments Not applicable. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME 4.3 Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 20 of 26 Modifications Not applicable. 5 Testing a) Test contact resistance across main and transfer contacts: Maximum 60μΩ per phase. b) Test minimum release voltage of main and back-up trip coils is 70% of nominal voltage. c) Measure trip and close coil current. d) Check closing and opening times with a speed recorder: - Opening time 40ms ±10ms. Closing time 140ms-145ms ±10ms. Make/Trip time 40ms ±10ms. Make/Break time 30ms ±10ms. e) Note spring rewind time of the motor - <10 seconds, 3 crank revolutions when manually charged. f) Note resistivity values of the coils for future references. g) Note maximum allowable time discrepancies between phases. - Close maximum 5 ms. Open maximum 5 ms. h) Carry out insulation test if leakage to earth is suspected due to damaged bushings, contaminated oil or excessive moisture found inside breaker pole. 6 Related/Supporting Documents 6.1 Related Documents a) Critical task analysis: 1. 2. 3. Work in Live Chambers and Prohibited areas; High Voltage Operating; and Work with/on Extension/Single Ladders. b) Training module; c) Manufacturers manual. 6.2 Forms and Records The attached report shall form the record of work done. The completed report must be returned to the Work Co-ordinator together with the work order and a copy to the Technical Services Group. 7 Spares Refer to 4.2.1.1Spares and Materials When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 21 of 26 Annex A-Circuit-breaker report Circuit-breaker report SUBSTATION PANEL / FEEDER Circuit-breaker TYPE MAKE kV AMPS POLE NUMBER SERIAL NUMBER R Ph: W Ph: B Ph: kA Mechanism DRIVE TYPE HEATER Before: SUPPLY VOLTAGE: (tick which is applicable) Contact resistance (micro-ohm) R Phase W Phase SERIAL NUMBER R Ph: W Ph: B Ph: 220V D.C. 220V A.C. COUNTER After: 110 V D.C. Tests B Phase R Phase Contact penetration (mm) W Phase B Phase TEST 1 TEST 2 TEST 3 COILS Minimum trip release voltage Main R Ph: Back-up R Ph: Minimum close release voltage Coil amperage Main trip: Coil resistance Main trip: W Ph: W Ph: Back-up: Back-up: Speed recording test Trip Phase Close Red A Red B White A White B Blue A Blue B Motor rewind time to recharge spring: Time discrepancies between phases Insulation test R Phase W Phase S to E L to E S to L Trip: B Phase B Ph: B Ph: Close: Close: Trip/close Close/trip Close: SF6 gas alarm test o Nominal at 20 C Alarms Lock-out at When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 22 of 26 Annex A (Concluded) Good Replaced Fixed contacts Arcing ring Moving contacts Transfer contacts Arc control device Inspect Close latch Trip latch Needle bearings Interlocks Checklist Good Oil/SF6/Vacuum Gauge glasses Seals Valves Door seals Lubricate Free Replaced Good Coils Motors Pumps Contactor Counters Inspect Lubricate Replaced No leaks Drives Damper Springs Shafts When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 23 of 26 Annex B - Impact assessment 1. Guidelines o o o o All comments must be completed. Motivate why items are N/A (not applicable) Indicate actions to be taken, persons or organisations responsible for actions and deadline for action. Change control committees to discuss the impact assessment, and if necessary give feedback to the compiler of any omissions or errors. 2. Critical points 2.1 Importance of this document. E.g. is implementation required due to safety deficiencies, statutory requirements, technology changes, document revisions, improved service quality, improved service performance, optimized costs. Comment: Statutory requirements and or document revisions 2.2 If the document to be released impacts on statutory or legal compliance - this need to be very clearly stated and so highlighted. Comment: No impact on statutory or legal compliance and mainly document revisions 2.3 Impact on stock holding and depletion of existing stock prior to switch over. Comment: N/A - No new equipment or item need to be acquired for implementation of this document. 2.4 When will new stock be available? Comment: N/A –see 10.2.3 above. 2.5 Has the interchange ability of the product or item been verified - i.e. when it fails is a straight swap possible with a competitor's product? Comment: N/A – It is a maintenance document and also see 10.2.3 above. 2.6 Identify and provide details of other critical (items required for the successful implementation of this document) points to be considered in the implementation of this document. Comment: Consult / Refer to SCSASABA8 for revised earth application when implementing the document. 2.7 Provide details of any comments made by the Regions regarding the implementation of this document. Comment: None. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 24 of 26 Annex B (continued) 3. Implementation timeframe 3.1 Time period for implementation of requirements. Comment: N/A – No technical changes were made to this document. 3.2 Deadline for changeover to new item and personnel to be informed of DX wide change-over. Comment: None. 4. Buyers Guide and Power Office 4.1 Does the Buyers Guide or Buyers List need updating? Comment: NO. 4.2 What Buyer’s Guides or items have been created? Comment: NONE. 4.3 List all assembly drawing changes that have been revised in conjunction with this document. Comment: NONE – The configuration hasn’t changed. 4.4 If the implementation of this document requires assessment by CAP, provide details under 10.5 Comment: N/A – The revision requires no new equipment / assessment. 4.5 Which Power Office packages have been created, modified or removed? Comment: NONE: 5. CAP / LAP Pre-Qualification Process related impacts 5.1 Is an ad-hoc re-evaluation of all currently accepted suppliers required as a result of implementation of this document? Comment: NO 5.2 If NO, provide motivation for issuing this specification before Acceptance Cycle Expiry date. Comment: N/A – The document doesn’t specify but stipulated the maintenance procedures on the existing equipment. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 25 of 26 Annex B (continued) 5.3 Are ALL suppliers (currently accepted per LAP), aware of the nature of changes contained in this document? Comment: N/A – The specification is supplied to the suppliers not this document. 5.4 Is implementation of the provisions of this document required during the current supplier qualification period? Comment: Yes – This is the revision of document that is presently being implemented and requires no change to the supplier’s qualification period. 5.5 If Yes to 10.4, what date has been set for all currently accepted suppliers to comply fully? Comment: N/A – see 10.5.4 above. 5.6 If Yes to 10.4, have all currently accepted suppliers been sent a prior formal notification informing them of Eskom’s expectations, including the implementation date deadline? Comment: N/A – see 10.5.4 above. 5.7 Can the changes made, potentially impact upon the purchase price of the material/equipment? Comment: N/A – No new material is required. 5.7.1 Material group(s) affected by specification: (Refer to Pre-Qualification invitation schedule for list of material groups) Comment: N/A – No new material is required. 6. Training or communication 6.1 State the level of training or communication required to implement this document. (E.g. none, communiqués, awareness training, practical / on job, module, etc.) Comment: Practical / On job and training module. 6.2 State designations of personnel that will require training. Comment: TSO, PTO & STO. 6.3 Is the training material available? Identify person responsible for the development of training material. Comment: Yes – DT- Training is revising earthing related training manual which will address the changes in this document. 6.4 If applicable, provide details of training that will take place. (E.G. sponsor, costs, trainer, schedule of training, course material availability, training in erection / use of new equipment, maintenance training, etc). Comment: Safety and Maintenance training. When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB. DOCUMENT CLASSIFICATION: CONTROLLED DISCLOSURE CIRCUIT-BREAKER: DELLE / ALSTOM TYPE: HG 710 & HG 720 RATINGS: 33kV; 1250A MECHANISM: BLR, BLRM & BLRME Unique Identifier: 34-960 Type: DMN Revision: 0 Page: 26 of 26 Annex B (concluded) 6.5 Was Training & Development Section consulted w.r.t training requirements? Comment: Yes. 7. Special tools, equipment, software 7.1 What special tools, equipment, software, etc will need to be purchased by the Region to effectively implement? Comment: NONE. 7.2 Are there stock numbers available for the new equipment? Comment: N/A – No new equipment is required. 7.3 What will be the costs of these special tools, equipment, software? Comment: N/A – No new equipment is required. 8. Finances 8.1 What total costs would the Regions be required to incur in implementing this document? Identify all cost activities associated with implementation, e.g. labour, training, tooling, stock, obsolescence Comment: No costs other than the training will be incurred by the regions and this will depend on the arrangements made for training ie Training is held regionally or nationally. Impact assessment completed by: Name: David M. Ntombela Designation: Consultant When downloaded from the DT WEB, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the WEB.
© Copyright 2024