OPMA 5364 Project Management Part 5 Project Scheduling Topic Outline: Project Scheduling • • • • • • • • • Identifying relationships among activities Project network diagrams Identifying critical paths and critical activities Determining activity slack times Gantt charts Project scheduling exercise Microsoft Project example Other precedence relationships Management of project schedules Part 5 - Project Scheduling 2 Identifying Activity Relationships In addition to estimating activity time duration and cost, relationships among activities must also be identified Relationships: • What task immediately precedes this task? • What task immediately follows this task? • What tasks can be done concurrently? These are referred to as precedence relationships The main relationship for scheduling is ‘what task immediately precedes the current task,’ which is referred to as the immediate predecessor task Part 5 - Project Scheduling 3 Project Network Diagrams • Network diagrams show the precedence relationships among activities • It’s easier to understand these relationships graphically • Network diagrams help to understand the flow of work in a project • Network diagrams are a useful tool for project planning and control, as well as for scheduling • One (perhaps exaggerated) claim is that the network represents ¾ of the planning process Part 5 - Project Scheduling 4 2 Versions of Network Diagrams Activity-on-Arrow (AOA) networks – – – – also called Arrow Diagramming Method (ADM) simpler for projects with many dependencies emphasizes events; milestones can be easily flagged sometimes requires dummy activities Activity-on-Node (AON) networks – – – – also called Precedence Diagramming Method (PDM) easier to draw for simple projects emphasizes activities no dummy activities Part 5 - Project Scheduling 5 Activities vs. Events • Activity – a chunk of work that is part of the project; an activity may be broken down into multiple subactivities • Event – a significant point in time during the project, such as a milestone event; an event could be the time at which an activity is completed or the time at which related concurrent activities have all completed • Dummy Activity – an artificial activity with zero time duration that only shows a precedence relationship among activities Part 5 - Project Scheduling 6 Activity-on-Arrow (AOA) Networks c e b g d f k k k or j j j Dashed lines are called dummy activities Activity m n r s Predecessor _ _ m, n n m r n s Part 5 - Project Scheduling 7 Install rough electrical & plumbing 6 Pour basement floor Install finished plumbing Install drywall Install cooling & heating 7 11 8 Install drains 10 9 Erect frame & roof 1 Excavate & pour footings 2 Pour foundation 3 Lay flooring 12 Install kitchen equipment Paint 4 Lay brickwork Finish carpeting 5 16 Finish electrical work Finish roof Project Network for House Construction Lay storm drains 13 14 Finish floors Install roof drainage (AOA network) 15 Part 5 - Project Scheduling Finish grading 18 Pour walks; Landscape 17 8 Project Network Example Task Pred. Dur. Task Pred. Dur. a -4 g c,d 1 b -3 h e 4 c a 3 i f 5 d a 2 j e,g 6 e b 6 k h,i 1 f b 4 Draw AOA and AON networks Part 5 - Project Scheduling 9 Activity-on-Arrow (AOA or ADM) Network (Initial Network) Part 5 - Project Scheduling 10 Activity-on-Arrow (AOA or ADM) Network (Final Network) c a d g j b e h f i k Part 5 - Project Scheduling 11 Activity-on-Node (AON or PDM) Network Part 5 - Project Scheduling 12 Project Network Example A project has the following activities and precedence relationships: Predecessor Predecessor Activity Activities Activity Activities a -f c,e b a g b c a h b,d d a i b,d e b j f,g,h Draw AOA and AON networks Part 5 - Project Scheduling 13 Activity on Arrow (Initial Network) Part 5 - Project Scheduling 14 Activity on Arrow (Final Network) g b a e c d j f h i Part 5 - Project Scheduling 15 Activity on Node Part 5 - Project Scheduling 16 Critical Path path – any route along the network from start to finish Critical Path – path with the longest total duration This is the shortest time in which the project can be completed. Critical Activity – an activity on the critical path *If a critical activity is delayed, the entire project will be delayed. Close attention must be given to critical activities to prevent project delay. There may be more than one critical path. Part 5 - Project Scheduling 17 Critical Path Brute force approach to finding critical path: 1. identify all possible paths from start to finish 2. sum up durations for each path 3. largest total indicates critical path (This approach is inefficient, but is instructive) Part 5 - Project Scheduling 18 2 1 b=2 d=4 4 3 6 g=9 7 5 h=9 Part 5 - Project Scheduling 19 Slack Times • EST—Earliest Start Time – Largest EFT of all predecessors • EFT—Earliest Finish Time – EST + duration for this task • LFT—Latest Finish Time – Smallest LST of following tasks • LST—Latest Start Time – LFT – duration for this task • Slack—LFT – EFT or LST – EST Part 5 - Project Scheduling 20 Computing Slack Times EST EFT Task = duration slack = xxxx LST LFT Part 5 - Project Scheduling 21 Slack Times Example Task Pred. Dur. Task Pred. Dur. a -4 g c,d 1 b -3 h e 4 c a 3 i f 5 d a 2 j e,g 6 e b 6 k h,i 1 f b 4 For each task, compute ES, EF, LF, LS, Slack Part 5 - Project Scheduling 22 c=3 slack= EST Task=dur slack=xxx LST g=1 slack= a=4 slack= EFT LFT j=6 slack= d=2 slack= Finish Start e=6 slack= h=4 slack= b=3 slack= k=1 slack= f=4 slack= i=5 slack= Part 5 - Project Scheduling 23 Gantt Charts • The main purpose of a Gantt chart is to display the schedule of activities • They are easy to understand • They are flexible in that you can also show other information on the chart, such as resources required, who is responsible, critical activities, percent complete, etc. • All project management software packages will create Gantt charts Part 5 - Project Scheduling 24 Gantt Chart Activity a b c d e f g h i Time (weeks) Part 5 - Project Scheduling 25 Project Scheduling Exercise DynaTech Equipment Corp. case • Divide into small groups • Read case (5 minutes) • Assignment: (40 minutes) – List the immediate predecessors and WBS number for each activity – Draw project network diagram (lowest level) – Draw Gantt chart – Determine project completion time Part 5 - Project Scheduling 26 Microsoft Project Example Part 5 - Project Scheduling 27 Microsoft Project Example Part 5 - Project Scheduling 28 Microsoft Project Example Part 5 - Project Scheduling 29 Other Precedence Relationships • The typical precedence relationship between two activities is that when the first activity has finished, then the second activity can start. In this case the first activity is called the immediate predecessor of the second activity. • This is referred to as a Finish-to-Start linkage. • Other precedence relationships, or linkages, are also possible. • Lead and lag times are also possible. Part 5 - Project Scheduling 30 Other Precedence Relationships Finish-to-Start Linkage (FS) Start-to-Start Linkage (SS) Finish-to-Finish Linkage (FF) Activity 1 Lead and Lag Times Activity 2 Activity 1 Activity 2 Activity 1 Activity 2 Activity 1 Start-to-Finish Linkage (SF) Lead (-) and Lag (+) times are expressed as part of the immediate predecessor notation. So 1FS+3 listed for the immediate predecessor of Activity 2 means that Activity 1 is the predecessor with a Finishto-Start linkage and a 3-day lag time after Activity 1 finishes before Activity 2 can start. 1FS-3 means that Activity 2 can start 3 days before Activity 1 finishes. 1FF+3; 1SF-5; 1SS+4 Activity 2 Part 5 - Project Scheduling 31 Management of Project Schedules • Meeting project deadlines is often the most important goal in project management • Careful scheduling of project activities is critical to meeting the project due date • Effective project managers should have a good understanding of the issues involved in activity scheduling Part 5 - Project Scheduling 32 Ineffective Scheduling Notice: As of tomorrow, employees will only be able to access the building using individual security cards. Pictures will be taken next Wednesday, and employees will receive their cards in two weeks. Part 5 - Project Scheduling 33
© Copyright 2024