Delay Claims from the Owner and Contractor’s Perspectives Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11, 2010 – Los Angeles Delay Claims from the Owner and Contractor’s Perspectives Claims Avoidance and Resolution Committee Understanding Claims Subcommittee • Dennis M. Mac Bride, Chair - SEPTA • Craig Lindquist – CCS Group, Inc. • Patrick Watz – AECOM • John (Jack) Chiaverini – Retired, Perini Corporation AGENDA • What is a Delay Claim? • Contract Language Related to Delay • Types of Delays • Types of Damages • Requirements for a Successful Claim AGENDA • Contractor’s Delay Claim Submission • Owner’s Defense • Owner’s Damages / Counterclaim • Contractor’s Defense • Case Study What is a Delay Claim? In simple terms: Contractor: A request for compensation and/or time due to owner-caused delays Owner: An assessment of liquidated damages or a claim for actual damages due to contractor-caused delays Contract Language • “Time is of the essence” • Contract time of completion • Contract milestones / Phasing • Scheduling specifications (CPM or bar chart) • Notice provisions Contract Language • Time extension requests (time impact analysis) • Time extensions / change orders • Liquidated damages • “No damage for delay” clause • Delays by other contractors clause • Disputes clause Types of Delays Examples of Owner-Caused Delays • • • • • • • Site access Differing site conditions Shop drawing approval Design errors and omissions Extra work / change orders Failure by owner to timely provide materials Changed conditions, e.g., working hour restrictions • Work suspension Types of Delays Examples of Contractor-Caused Delays • Procurement/Submittal problems (material & equipment) • Subcontractor delays • Lack of adequate resources (labor, material, equipment) • Poor work sequencing • Lack of productivity • Rework • Financial difficulties Types of Delays Third-Party Delays • Permit acquisition • Utility relocations • Adjacent contractors • Government Actions/Inactions Types of Delays - Analysis • Excusable / Non-excusable delays • Compensable / Non-compensable delays • Force majeur (Beyond either party’s control) • Concurrent delays Examples of Contractor Delay Damages Recoverable • Field office overhead (General conditions) – Trailers, utilities, on-site supervision, etc. • Added cost of work, e.g., winter work protection • Subcontractor pass through • Labor and material escalation • Acceleration – Directed and constructive acceleration • Idle labor and equipment • Lost productivity (inefficiencies) • Insurance and bonding costs Examples of Contractor Delay Damages Not Recoverable (Depends on contract language) • Home office overhead (G & A) – Delay vs. total suspension of work • Lost opportunities – Lost business revenue, loss of bonding capacity • Legal and consultant fees Owner Damages Liquidated Damages • Described in contract • $ per day for each day substantial completion is beyond the current contract completion date • Must be a reasonable estimate of damages and not a penalty Examples of Owner’s Actual Damages • Owner costs – Lost revenue, interest on financing, project management, inspection, etc. • Architect/Engineer costs/fees – Additional shop drawing reviews, rate escalation, etc. • Construction Manager costs/fees Requirements for a Successful Claim The burden of proof is on the contractor Requirements for a Successful Claim Three elements needed: • Liability (Entitlement) • Causation • Damages (Quantification) Requirements for a Successful Claim Liability • Contractual duties and obligations – Notice provisions – Site access, accurate plans and specs – Adequate resources, workmanship Causation • “Cause and effect” • Link between delay and damages Damages • Substantiating documentation for extended costs • Actual costs or daily rates Contractor’s Delay Claim Submission • Why the owner is responsible for delays and associated costs • Schedule analysis • Damages • Substantiating documentation • Transparency Owner’s Defense Determine Type of Delay: Excusable Non-excusable Owner-caused Force majeur Contractor-caused Compensable Noncompensable Non-compensable Owner’s Defense Identify Concurrent Delays: Excusable Caused by Owner and Contractor Non-compensable Owner’s Defense • Liability Review - Contract terms • Causation Review - Schedules, daily reports, shop drawing logs, meeting minutes, etc. • Damage Review – Receipts, invoices, cost reports, etc. – Reasonable estimates ___________________________________________ Owner Costs that Offset Contractor Damages: • Overhead paid as part of change orders during the extended period • Liquidated or actual damages Owner’s Damages / Counterclaim • Why the contractor is responsible for delays and liquidated or actual damages • Schedule analysis • Damage calculations • Substantiating documentation Contractor’s Defense • Contract Terms / Plans & Specs – Ambiguities, conflicts, errors & omissions • Change orders, RFI’s, etc. – Effect on schedule and costs • Schedule Analysis – Owner-caused delays – Concurrent delays Delay Claim Case Study Case Study This is the story of a construction project that was planned to be completed in 24 months. Unfortunately, stuff happened and it was completed much later. Because of this, the contractor incurred extra costs and requested additional compensation from the owner. The following describes the process that was used to resolve this delay claim. The As-Planned Schedule (What was supposed to happen) Case Study: Subway Station Expansion Project 1 A 2 M 3 J 4 J 5 A 6 S 7 O 8 N 9 D Months 10 11 12 13 14 J F M A M Winter 1 Mobilize 2 15 J 16 J 17 A 18 S 19 O 20 N 21 D 22 J 23 24 F M Winter As-Planned Excavate & sheeting 3 Erect structural steel & pour mezzanine 4 Backfill & paving 5 Mechanical equipment 6 Elevators & escalators Power & lighting Gates & cashier booths 7 8 Finishes 9 Demobilize 10 The As-Built Schedule (What actually happened) Case Study: Subway Station Expansion Project 1 A 2 M 3 J 4 J 5 A 6 S 7 O 8 N 9 D 10 11 12 13 14 15 J F M A M J Original Contract Period Winter Access Delay (1 month) 1 Months 16 17 J A 18 S 19 O 20 N 21 D 22 J 23 F 24 M 25 A 26 M 27 J 28 J 29 A 30 S 31 O 32 N Extended Period = 8 months Winter Delays Mobilize As-Built Differing Site Conditions (2 months) 2 Excavate & sheeting Re-design Delay (2 months) 3 Erect structural steel & pour mezzanine 4 Backfill & paving 5 Mechanical equipment 6 Gates & cashier booths Strike (1 month) 7 Elevators & escalators Power & lighting Lack of Progress (1 month longer than planned) 8 Rework Finishes (1 month) 9 Demobilize 10 The As-built Schedule shows that there were six delays that resulted in an eight month delay to the project. Case Study: Subway Station Expansion Project 1 2 A M P 3 J 4 J 5 A 6 S 7 O Months 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 D J F M A M J J A S O N D J F M A M J J A S O N Original Contract Period Extended Period Winter Winter 8 N A Mobilize P A As-Planned vs. As-Built Excavate P A P Erect structural steel & pour mezzanine A Backfill & paving New Labor Agreement P A Mechanical equipment P A Gates & cashier booths P A P Elevators & A Power & lighting P Finishes A P = Planned P Demobilize A A = Actual <--- 8 month delay ---> Because the project finished eight months late, the contractor submitted the following claim to the owner: Case Study: Subway Station Expansion Project Contractor's Claim Claim Item Cause for Added Costs Field Office Overhead (trailer, supervision, Total delay of eight months etc.) Labor Escalation after May 1st Labor 2 Delays to finish trades Agreement 1 Months 8 Monthly Cost $ 8 2 50,000 $ 400,000 $ 5,000 10,000 $ 20,000 3 Idle Equipment Re-design delay 4 Winter Work Winter concrete (blankets, heaters, etc.) $ 10,000 5 Constructive Acceleration No time extension issued / threat of LD's $ 10,000 6 Lost Productivity Adverse weather, out-of-sequence work, etc. $ 10,000 7 Home Office Overhead Total delay of eight months 20,000 $ 160,000 8 Consultant Fees Claim preparation $ 50,000 9 Interest @ 5% on Delayed Payments Job financing $ 33,250 10 Bond at 1.5% Eight month delay $ 10,474 TOTAL CLAIM $ 708,724 8 $ Damages Claimed $ Before analyzing the contractor’s costs, the owner performed a Delay Responsibility Analysis as follows: Case Study: Subway Station Expansion Project 1 A 2 M 3 J 4 J 5 A 6 S 7 O 8 N 9 D 10 11 12 13 14 15 J F M A M J Original Contract Period Winter Access Delay (1 month) 1 Months 16 17 J A 18 S 19 O 20 N 21 D 22 J 23 F 24 M 25 A 26 M 27 J 28 J 29 A 30 S 31 O 32 N Extended Period = 8 months Winter Delays Mobilize As-Built Differing Site Conditions (2 months) 2 Excavate & sheeting Re-design Delay (2 months) 3 Erect structural steel & pour platforms & mezzanine 4 Backfill & paving 5 Mechanical equipment 6 Gates & cashier booths Strike (1 month) Elevators & escalators Power & lighting Lack of Progress (1 month longer than planned) 7 8 Rework Finishes (1 month) 9 Demobilize 10 Delay Responsibility Analysis Delay Type Access Delay Differing Site Conditions Re-design Strike Lack of Progress Re-work Responsibility Owner Owner Owner Neither Contractor Contractor Case Study: Subway Station Expansion Project 1 A 2 M 3 J 4 J 5 A 6 S 7 O 8 N 9 D 10 11 12 13 14 15 J F M A M J Original Contract Period Winter Months 16 17 J A 18 S 19 O 20 N 21 D 22 J 23 F 24 M 25 A 26 M 27 J 28 J 29 A 30 S 31 O 32 N Extended Period = 8 months Winter Access Delay 1 Delay Responsibility Analysis Mobilize Differing Site Conditions 2 Excavate & sheeting Re-design Delay 3 Erect structural steel & pour platforms & mezzanine 4 Delay Responsibility Months Owner 5 New Labor Agreement Backfill & paving 5 Mechanical equipment 6 Gates & cashier booths Strike Contractor 2 Elevators & escalators Neither 1 8 Power & lighting Lack of Progress 7 8 Rework Finishes 9 Demobilize 10 Based on its Delay Responsibility Analysis, the owner apportioned the contractor’s claimed costs and estimated the contractor’s entitlement to additional compensation as follows: Case Study: Subway Station Expansion Project Contractor's Claim Owner's Estimate of Entitlement Monthly Damages Monthly Claim Item Months Months Estimate Reason Cost Claimed Cost Field Office Overhead (trailer, supervision, 1 8 $ 50,000 $ 400,000 5 $ 50,000 $ 250,000 Owner delay = 5 months etc.) Labor Escalation after May 1st Labor Apportioned owner delay 2 8 $ 5,000 5 $ 3,125 Agreement = 5/8 3 Idle Equipment $ 10,000 $ 20,000 $ 10,000 $ 20,000 All costs substantiated 4 Winter Work $ 10,000 $ 10,000 All costs substantiated 5 Constructive Acceleration $ 10,000 $ 6 Lost Productivity $ 10,000 $ - Causation not shown $ 20,000 $ 160,000 $ - Delay, not a work suspension 8 Consultant Fees $ 50,000 $ - Not part of the Work 9 Interest @ 5% on Delayed Payments $ 33,250 $ - Not substantiated 10 Bond at 1.5% $ 10,474 $ 7 Home Office Overhead 2 8 2 Subtotal $ TOTAL CLAIM $ Liquidated Damages $ @ $500 per day x 61 TOTAL 708,724 $ ENTITLEMENT 7,500 Some costs substantiated 4,359 Cost substantiated 294,984 (30,500) 264,484 Contractor delay = 2 months The contractor requested more than $700,000 in additional compensation due to project delays. The owner estimated that the contractor was entitled to approximately $260,000. They negotiated a settlement somewhere in between . . . . . . and everyone lived happily ever after. THE END Delay Claims from the Owner and Contractor’s Perspectives Questions? Delay Claims from the Owner and Contractor’s Perspectives Additional Information Construction Delay Claims, Third Edition, Barry B. Bramble & Michael T. Callahan, 1999 Construction Delays: Documenting Causes, Winning Claims, Recovering Costs, Theodore J. Trauner, 1990 Construction Scheduling: Preparation, Liability, and Claims, John M. Wickshire, Thomas J. Driscoll, Stephen B. Hurlbut, 2008 CPM in Construction Management, Seventh Edition, Fredric Plotnick & James O’Brien, 2009 Proving and Pricing Construction Claims, Robert F. Cushman, 2000 Recommended Practice No. 29R-03, Forensic Schedule Analysis, AACE International, 2007
© Copyright 2024