SubSea Modeling Example

SubSea Modeling Example
by Gerrit Muller
HBV-NISE
e-mail: [email protected]
www.gaudisite.nl
Abstract
This presentation provides an example of modeling in the subsea domain.
assembly,
functional test
perform
workover
operations
run
EDP/LRP
retrieve coil
tubing and
wireline BOP
1
2
run risers
unhook coil
tubing and
wireline BOP
hook up SFT
and TF
ROV assisted
disconnect
move above well
move away from
well
ROV assisted
connect
retrieve SFT and
TF
3
Distribution
This article or presentation is written as part of the Gaudí project. The Gaudí project
philosophy is to improve by obtaining frequent feedback. Frequent feedback is pursued by an
open creation process. This document is published as intermediate or nearly mature version
to get feedback. Further distribution is allowed as long as the document remains complete
and unchanged.
November 13, 2014
status:
preliminary
draft
version: 0.4
7
rig
TF
wireline
coil tubing BOP
SFT
8
vessel or
platform
4
5
6
7
9
riser
10
hook up coil
tubing and
wireline BOP
retrieve risers
system function
and connection
seal test
retrieve
EDP/LRP
run coil tubing
and wireline
disassembly
EDP
11
12
LRP
XT
well
head
well
WOCS
Colophon
The examples in this presentation are based on the work of
SEMA participants: Martin Moberga, Tormod Stranda, Vazgen
Karlsenf, and Damien Weef, and the master project paper by
Dag Jostein Kleverf. Sensitive and confidential information is
removed or obfuscated.
All mistakes are to be blamed to the author.
Gunnar Berge stimulated the creation of a subsea example.
a
Aker Solutions
f
FMC Technologies
SubSea Modeling Example
2
Gerrit Muller
version: 0.4
November 13, 2014
SSMEcolophon
Story: Workover Anno 2015
well 1
harbor
On September 4, Captain Frode Johansen was discussing the plans for the
upcoming workover of South Gulfaks (see http://www.npd.no/en/Publications/
Facts/Facts-2011/Chapter-10/Gullfaks-Sor-/) with his crew. Their vessel had been
out of operation for recertification of the equipment much longer than anticipated,
so there was a lot of pressure from Statoil on their schedule. Statoil sees
diminishing production in several of the wells, so workover operations are urgent.
With the upcoming fall and winter storms, Frode hopes to finish the next three
workover operations in a new record time. The equipment supplier had not only
recertified all equipment, but also renovated parts of the riser system allowing for
faster deployment and retrieval. The supplier tested and installed equipment in
Horten. Tomorrow they will arrive in Sotra, their company support station. Here
they will stock their fuel, food, coiled tubing, and other material.
The weather forecast shows a depression close to Iceland that moves slowly in
Norway’s direction. If they can start deployment of the riser on September 7, then
they probably finish the workover before the storm associated with the depression
is too severe.
Since the schedule is so tight, the captain proposes to preassemble the riser
system as far as possible while traveling. In addition, the accumulators can already
be charged. The captain asks the foreman to make a schedule and to allocate
tasks to the crew. Safety will be a key attention point, since working with such
equipment with sea state 3 provides risks.
SubSea Modeling Example
3
Gerrit Muller
version: 0.4
November 13, 2014
SSMEstory
Annotated Physical Diagram of WorkOver System
rig
tension frame connects
riser to rig tension system
surface flow tree
provides well control
TF
SFT
vessel or
platform
wireline
coil tubing BOP
provides well control
WOCS work over control system
monitoring and control
of subsea installation
riser
conduit for running
tools to well
ROV
emergency disconnect package
provides disconnect function
Xmas tree
provides well control
EDP
ROV
remotely operated vehicle
one for observation
one for operation
LRP
lower riser package
provides well control function
XT
well
head
structural and pressurecontaining interface
well
SubSea Modeling Example
4
Gerrit Muller
version: 0.4
November 13, 2014
SSMEworkoverPhysicalAnnotated
Typical Workover Operation
assembly,
functional test
perform
workover
operations
run
EDP/LRP
retrieve coil
tubing and
wireline BOP
run risers
unhook coil
tubing and
wireline BOP
1
2
3
hook up SFT
and TF
ROV assisted
disconnect
move above well
move away from
well
7
rig
TF
wireline
coil tubing BOP
SFT
8
vessel or
platform
4
5
ROV assisted
connect
6
riser
9
retrieve SFT and
TF
10
hook up coil
tubing and
wireline BOP
retrieve risers
system function
and connection
seal test
retrieve
EDP/LRP
run coil tubing
and wireline
disassembly
EDP
11
LRP
XT
well
head
12
well
7
SubSea Modeling Example
5
Gerrit Muller
version: 0.4
November 13, 2014
SSMEtypicalWorkoverOperation
WOCS
Typical Workover Operation as Cartoon
rig
1
rig
2
TF
3
TF
rig
4
TF
rig
5
TF
EDP
SFT
LRP
WOCS
SFT
rig
6
TF
TF
SFT
WOCS
vessel or
platform
rig
WOCS
vessel or
platform
SFT
vessel or
platform
WOCS
SFT
vessel or
platform
WOCS
vessel or
platform
SFT
WOCS
vessel or
platform
EDP
LRP
riser
EDP
EDP
LRP
LRP
EDP
LRP
7
rig
vessel or
platform
EDP
ROV
LRP
ROV
XT
well
head
XT
well
head
XT
well
head
XT
well
head
XT
well
head
XT
well
head
well
well
well
well
well
well
8
TF
SFT
riser
9
rig
TF
WOCS
SFT
rig
10
rig
11
TF
rig
12
TF
rig
TF
TF
WOCS
vessel or
platform
SFT
WOCS
vessel or
platform
SFT
SFT
EDP
SFT
WOCS
WOCS
LRP
WOCS
vessel or
platform
vessel or
platform
vessel or
platform
EDP
LRP
riser
riser
EDP
EDP
LRP
LRP
EDP
EDP
LRP
LRP
XT
well
head
XT
well
head
XT
well
head
XT
well
head
XT
well
head
XT
well
head
well
well
well
well
well
well
SubSea Modeling Example
6
Gerrit Muller
ROV
version: 0.4
November 13, 2014
SSMEtypicalWorkoverOperationCartoon
Typical Workover Operation on Timeline
assumptions:
running and retrieving risers: 50m/hr
running and retrieving coiled tubing/wireline: 100m/hr
preparation 36 hrs
stop production
24
72
96
hours
SubSea Modeling Example
7
Gerrit Muller
version: 0.4
November 13, 2014
SSMEtypicalWorkoverOperationTimeline
retrieve EDP/LRP
disassembly
retrieve risers
retrieve SFT and TF
finishing 27 hrs
resume
production
deferred operation 62 hrs
48
move away from well
actual workover operation
48 hrs
retrieve coiled tubing/wireline
run coiled tubing/wireline
move above well
ROV assisted connect
hook up coiled tubing/wireline
function and seal test
hook up SFT and TF
run risers
run EDP/LRP
assembly and test
depth: 300m
Typical Workover Operation Context
zero order model
tworkover =
ttransportation + tpreparation+ tworkover+
tfinishing
well 3
well 2
first order model
well 1
tworkover =
ttransportation + tpreparation+ tworkover+
tdisruption + tfinishing
harbor
disruption
5
10
days
SubSea Modeling Example
8
Gerrit Muller
version: 0.4
November 13, 2014
SSMEtypicalWorkoverOperationContext
finishing 24 hrs
continued
workover
reconnect
storm
workover
preparation
32 hrs
transportation
24 hrs
actual
workover
operation
48 hrs
workover well 2
finishing 24 hrs
preparation
32 hrs
transportation
24 hrs
workover well 1
0-order Cost Model Workover Operation
workover cost per day
platform, rig
equipment
crew
total
assumed cost (MNoK)
2
0.2
0.1
2.3 MNoK/day
deferred operation per day
production delay
ongoing cost operation
total
assumed cost (MNoK)
0.1
0.2
0.3 MNoK/day
workover duration
transportation
preparation
workover
finishing
total
estimated duration (hours)
production loss
24
6
36
48
48
8
27
135 (5.6 days) 62 (2.6 days)
cost = costworkover/day * tworkover + costdeferred op./day * tdeferred op.
~= 2.3 * 5.6 + 0.3 * 2.6 ~= 14 MNoK / workover
SubSea Modeling Example
9
Gerrit Muller
version: 0.4
November 13, 2014
SSMEcostModelWorkoverOperation
Disruption Workover Operation
7a
rig
7
disruption,
e.g. storm
SFT
shut down valves
SFT
WOCS
vessel or
platform
vessel or
platform
retract wireline
7b
TF
TF
7
rig
7c
TF
WOCS
rig
TF
SFT
WOCS
SFT
vessel or
platform
riser
riser
rig
WOCS
vessel or
platform
riser
riser
control t&p well
7a
EDP
EDP
LRP
LRP
LRP
LRP
move away
XT
well
head
XT
well
head
XT
well
head
XT
well
head
well
well
well
well
open valves
7c
run wireline
move away
control t&p well
workover
disruption
reconnect EDP
EDP
continue workover
move above well
reconnect
wait
EDP
move above well
7b
wait for resolution
of disruption
perform
workover
operations
disconnect EDP
7
24
SubSea Modeling Example
10
Gerrit Muller
version: 0.4
November 13, 2014
SSMEdisruptionWorkoverOperation
48
hours
ROV
1st order Cost Model Workover Operation
workover cost per day
platform, rig
equipment
crew
total
assumed cost (MNoK)
2
0.2
0.1
2.3 MNoK/day
deferred operation per day
production delay
ongoing cost operation
total
assumed cost (MNoK)
0.1
0.2
0.3 MNoK/day
1st order cost
workover duration
workover 0-order
average disruption
duration
overhead
disruption frequency
1st order disruption
correction
total
estimated duration (hours)
production loss
135 (5.6 days) 62 (2.6 days)
72
11
0.3
83*0.3=
27
27
162 (6.7 days) 89 (3.7 days)
= costworkover/day * tworkover + costdeferred op./day * tdeferred op.
~= 2.3 * 6.7 + 0.3 * 3.7 ~= 16.5 MNoK / workover
0-order
cost ~= 14 MNoK ; disruption cost ~= 2.5 MNoK
SubSea Modeling Example
11
Gerrit Muller
version: 0.4
November 13, 2014
SSMEcostModelWorkoverOperation1stOrder
A3 Architecture Overview
This A3 based on the work of SEMA participants: Martin Moberga, Tormod Stranda, Vazgen Karlsenf, and Damien Weef,
and the master project paper by Dag Jostein Kleverf. aAker Solutions, f FMC Technologies
Workover operation; architecture overview
workover
workflow
assembly,
functional test
workover workflow
rig
1
EDP
LRP
vessel or
platform
2
TF
rig
SFT
WOCS
vessel or
platform
4
TF
SFT
vessel or
platform
EDP
LRP
WOCS
SFT
WOCS
SFT
XT
well
head
XT
well
head
XT
well
head
XT
well
head
well
well
well
well
well
ROV
ROV
TF
WOCS
vessel or
platform
SFT
rig
10
WOCS
SFT
7a
rig
WOCS
vessel or
platform
EDP
LRP
XT
well
head
EDP
LRP
XT
well
head
well
well
well
ROV
vessel or
platform
EDP
LRP
TF
retract wireline
vessel or
platform
5
SFT
shut down valves
7b
rig
WOCS
SFT
7c
rig
WOCS
SFT
TF
WOCS
SFT
vessel or
platform
XT
well
head
XT
well
head
XT
well
head
well
well
well
well
disconnect EDP
move away
ROV
Xmas tree
provides well control
run wireline
24
48
hours
actual workover operation
48 hrs
retrieve risers
depth: 300m
11
retrieve EDP/LRP
disassembly
running and retrieving coiled tubing/wireline: 100m/hr
retrieve SFT and TF
running and retrieving risers: 50m/hr
retrieve
EDP/LRP
preparation 36 hrs
stop production
finishing 27 hrs
resume
production
deferred operation 62 hrs
disassembly
24
SubSea Modeling Example
12
Gerrit Muller
48
72
remotely operated vehicle
one for observation
one for operation
lower riser package
provides well control function
XT
well
head
structural and pressurecontaining interface
0-order workover cost estimate
workover cost per day
96
hours
assumed cost (MNoK)
workover duration
estimated duration (hours)
production loss
platform, rig
2
transportation
24
equipment
0.2
preparation
36
6
crew
0.1
workover
48
48
total
2.3 MNoK/day
finishing
27
8
deferred operation per day
12
work over control system
monitoring and control
of subsea installation
well
move away from well
assumptions:
retrieve coiled tubing/wireline
workover timeline
run coiled tubing/wireline
move above well
ROV assisted connect
hook up coiled tubing/wireline
function and seal test
retrieve risers
hook up SFT and TF
10
run risers
retrieve SFT and
TF
assembly and test
move away from
well
run EDP/LRP
ROV assisted
disconnect
ROV
EDP
LRP
open valves
8
9
WOCS
ROV
emergency disconnect package
provides disconnect function
7c
unhook coil tubing
and wireline BOP
SFT
riser
conduit for running
tools to well
continue
workover
reconnect
move above
well
workover
disruption
reconnect EDP
move away
retrieve coil tubing
and wireline BOP
well
wireline
coil tubing BOP
provides well control
vessel or
platform
disruption timeline
move above well
control t&p well
7
well
TF
disruption workflow
7
perform workover
operations
LRP
XT
well
head
EDP
LRP
XT
well
head
well
well
7b
wait
run coil tubing and
wireline
EDP
rig
surface flow tree
provides well control
riser
EDP
LRP
XT
well
head
EDP
LRP
XT
well
head
wait for
resolution of
disruption
system function
and connection
seal test
7a
EDP
LRP
XT
well
head
tension frame connects
riser to rig tension system
WOCS
vessel or
platform
riser
riser
TF
SFT
WOCS
EDP
LRP
control t&p well
6
vessel or
platform
rig
EDP
LRP
vessel or
platform
rig
TF
vessel or
platform
12
TF
SFT
WOCS
riser
EDP
LRP
XT
well
head
TF
rig
11
TF
SFT
WOCS
physical model
7
move above well
hook up coil tubing
and wireline BOP
rig
TF
vessel or
platform
riser
riser
9
rig
8
SFT
WOCS
vessel or
platform
EDP
LRP
XT
well
head
rig
TF
TF
vessel or
platform
EDP
LRP
disruption
workflow
7
rig
6
TF
vessel or
platform
EDP
LRP
3
ROV assisted
connect
rig
5
riser
2
run risers
rig
TF
SFT
WOCS
run
EDP/LRP
4
rig
3
TF
SFT
WOCS
1
hook up SFT and
TF
version 2.2 Gerrit Muller
assumed cost (MNoK)
production delay
0.1
ongoing cost operation
0.2
total
0.3 MNoK/day
total
135 (5.6 days) 62 (2.6 days)
cost = costworkover/day * tworkover + costdeferred op./day * tdeferred op.
~= 2.3 * 5.6 + 0.3 * 2.6 ~= 14 MNoK / workover
version: 0.4
November 13, 2014
SSMEoverviewA3