Design and Construction of Civil Works and Services for the City East 132kV Cable Tunnel FORMAL INSTRUMENT OF AGREEMENT EA 0933/09 213212412_14 FORMAL INSTRUMENT OF AGREEMENT DATE OF THE DEED: day of December 2011 PARTIES Ausgrid (ABN 67 505 337 385) (Principal) Thiess Pty Ltd (ABN 87 010 221 486) (Contractor) RECITAL A. The parties wish to enter into the Deed to record their agreement for the design, procurement and construction of the Work under the Deed. OPERATIVE PROVISIONS 1. The Contractor must design (other than the design for which the Principal is responsible), procure and construct the Work under the Deed in accordance with the Deed. 2. The Principal must pay the Contractor the Contract Price in accordance with the Deed. 3. The Principal and the Contractor agree that the following documents form the Deed between them: (a) this Formal Instrument of Agreement; and (b) the other documents referred to in the definition of "Deed" in clause 1.1 of the attached General Conditions of Deed. 4. The law of the Deed is the law in force in New South Wales. The Princpal and the Contractor submit to the jurisdiction of the courts of New Souith Wales. 5. Each person who executes the Deed on behalf of a party under a power of attorney declares that he or she is not aware of any fact or circumstance that might affect his or her authority to do so under that power of attorney. EXECUTED as a deed. SIGNED for and on behalf of Ausgrid in the presence of: Signature of witness Signature of person signing for Ausgrid Name of witness Name of person signing for Ausgrid SIGNED for Thiess Pty Ltd under power of attorney in the presence of: Signature of attorney Signature of witness Name of attorney Name of witness Date of power of attorney Design and Construction of Civil Works and Services for the City East 132kV Cable Tunnel GENERAL CONDITIONS OF DEED EA 0933/09 GENERAL CONDITIONS OF DEED Table of Contents Clause Number Heading 1 Definitions 2 Contract Documents 21 3 Interpretation 22 4 Scope of the Work under the Deed 25 5 Time for Commencement 30 6 Contractor‟s Obligations 30 7 Terms of Payment 35 8 Security 42 9 Taxes 44 10 Security of Payment Act 45 11 Intellectual Property Rights 46 12 Confidential Information 47 13 Representatives 48 14 Contractor‟s Organisation 50 15 Contract Programme 50 16 Subcontracts 54 17 Design 55 18 Procurement 57 19 Construction 59 20 Testing and Inspection 63 20A NGER Reporting Obligations 64 21 Substantial and Practical Completion 67 22 Completion and Close Out Workshop 70 23 Representations and Warranties 71 24 Warranties 72 25 Delay to Completion 73 26 Defect Correction 74 27 Care of the Work under the Deed 76 28 Indemnities 77 29 Insurance 78 30 Site Conditions, GBR administration and Selection of Equipment 81 31 Re-Instatement 85 213212412_14 Page 7 32 Force Majeure 85 33 Change in the Work under the Deed 86 34 Extension of Time 89 35 Acceleration 94 36 Suspension 95 37 Termination 95 38 Notices 99 39 Assignment and change 100 40 Claims and Dispute Resolution 102 41 Liability 110 Schedule 1 Contract Information 112 Schedule 2 Separable Portions 115 Schedule 3 Commercial Schedules 117 Schedule 4 GBR Administration 139 Schedule 5 Provisional Sums 159 Schedule 6 Key Personnel 160 Schedule 7 Insurances 161 Schedule 8 Approved Subcontractors 163 Schedule 9 Form of Security 165 Schedule 10 Contract Programme 166 Schedule 11 Pre-Contract Information 167 Schedule 12 DRB Appointment and Operating Procedures 168 Schedule 13 DRB Appointment Agreement 174 Schedule 14 Subcontractors Statement and Statutory Declaration 188 Schedule 15 Guarantee and Indemnity 193 Schedule 16 CECT Development Approval 202 Schedule 16A Schedule of CECT Development Approval Responsibilities 219 Schedule 17 Schedule of Interface Agreement Responsibilities 227 Exhibit A Specification Exhibit A1 Alternate specification Exhibit B Environmental Assessment Exhibit C Geotechnical Baseline Report Exhibit D Interface Agreements and Draft Interface Agreements 1 Definitions 1.1 The following words and expressions where used in the Deed have these meanings unless the contrary intention appears: Acceleration Direction has the meaning given to it by clause 35.2. Acceleration Direction Information Request has the meaning given to it by clause 35.3. Adverse Condition has the meaning given to it in Schedule 4 - GBR Administration. Affiliate means a person who is a related body corporate within the meaning of “related body corporate” in Section 9 of the Corporations Act. Approved Off-Site Materials means the items so nominated in Schedule 1 Contract Information. Authorised Representative means: (a) in respect of the Principal, the person so specified in Schedule 1 - Contract Information or such other person as may be nominated for the role of Authorised Representative by the Principal by written notice to the Contractor from time to time; and (b) in respect of the Contractor, the person so specified in Schedule 1 - Contract Information or such other person of at least equivalent experience and seniority: (i) nominated for the role of Authorised Representative by the Contractor by written notice to the Principal; and (ii) approved in writing by the Principal (acting reasonably), from time to time. Best Industry Practices means the practices, methods, standards of safety, design and performance and acts which are generally engaged in or observed by international design, construction and maintenance industries with respect to the design, construction and maintenance of works similar to the Work under the Deed and which, with respect to any objective, may be expected, in the exercise of reasonable judgment, to accomplish the same in a manner consistent with requirements of Government Authorities, reliability, safety, economy, expediency and environmental protection. Bligh St Development Approval means the planning approval granted to the Principal under Part 3A of the Environmental Planning and Assessment Act 1979 (NSW) for the construction of that part of the Project not included in the CECT Development Approval, as may be modified or replaced from time to time. BOOS means the Bondi Ocean Outfall Sewer. business day means any day other than a Saturday, Sunday, public holiday in New South Wales or 27, 28, 29, 30 or 31 December. 7 Cable Installation Contractor means the Separate Contractor to be engaged by the Principal for the installation of 33kV and 132kV cables in the Tunnel. Cable Installation Works means all work to be performed by the Cable Installation Contractor under its contract with the Principal. CCM means CrossCity Motorway Pty Ltd (ABN 45 098 445 839) and CrossCity Motorway Nominees No.2 Pty Ltd (ABN 53 098 445 811). CCM Tunnels means the tunnel components of the CrossCity Motorway. CECT Development Approval means the planning approval granted to the Principal under Part 3A of the Environmental Planning and Assessment Act 1979 (NSW) dated 18 July 2011 (a copy of which is set out in Schedule 16 – CECT Development Approval), as may be modified or replaced from time to time. CES Site has the meaning given to it in the Specification. CES Shaft has the meaning given to it in the Specification. Change means any modification, addition to or omission from or other variation of the Work under the Deed directed or approved by the Principal in writing in accordance with clause 33. Change Order has the meaning given to it in clause 33.5. City East Substation Stub Tunnel or CES Stub Tunnel has the meaning given to "City East Substation Stub Tunnel" in the Specification. Claim has the meaning given to it in clause 40.1(a)(i). Close Out Workshop means the close out workshop described clause 22.3. Commencement Date means the later of the date on which the parties execute the Deed or the date on which the Contractor provides to the Principal evidence of all insurances required to be taken out by the Contractor, or such other date as the parties may agree for the purpose of the Deed. Completion means the stage in the execution of the Work under the Deed when the Contractor has: (a) fully completed all of the Work under the Deed including rectification of all Defects remaining at Practical Completion (including any which only became patent subsequent to Practical Completion); (b) provided to the Principal electronic and hard copies of „as-built‟ survey and drawings, and a geotechnical as-built report for the Works, in accordance with the requirements of the Specification; (c) provided to the Principal all operational and maintenance manuals for the Work under the Deed required to be provided under the Deed in a form reasonably acceptable to the Principal; (d) provided to the Principal all geographical information systems for the Work under the Deed required to be provided under the Deed in a form reasonably acceptable to the Principal; 8 (e) provided to the Principal copies of all Government Approvals and other approvals (including any necessary approvals from land owners and tenants) relating to the Work under the Deed which the Contractor must obtain under the Deed; (f) provided to the Principal all manufacturers‟, suppliers‟ and subcontractors‟ warranties in respect of the Work under the Deed specified in the Deed in a form reasonably acceptable to the Principal, for the period specified in the Deed (or, where no warranty period is specified in the Deed, for the period normally provided by manufacturers, suppliers or subcontractors for work similar to the part of the Work under the Deed subcontracted), and each duly executed by the manufacturer, supplier or subcontractor, as applicable; (g) provided to the Principal all information necessary for the Principal to acquire a stratum easement for the Works via the Land Titles Office; (h) provided to the Principal all information required under the Interface Agreements in respect of the Work under the Deed which the Principal is required to provide to each Interface Party; (i) delivered to the Principal all spare parts and other materials in respect of the Works required to be supplied under the Deed; (j) completed all necessary cleaning up of the Works and that part of the Site on which the Works are constructed, all site restoration works in respect of the Work under the Deed required under the Deed and has removed all debris and surplus materials, temporary works and Construction Plant from that part of the Site on which the Works are constructed and from the Works; and (k) complied with all of the other obligations in respect of the Work under the Deed required under the Deed to be performed prior to Completion. Completion Certificate means a certificate issued by the Principal‟s Representative in accordance with clause 22.2 stating the date upon which Completion is achieved. Completion Payment means the outstanding balance of the Contract Price at Completion, as assessed by the Principal‟s Representative following receipt of the Contractor‟s statement under clause 7.4. Confidential Information means all information disclosed to the Contractor by, or on behalf of, the Principal, the Principal‟s Representative or any related entity of the Principal, including: (a) information, which, either orally or in writing, is designated or indicated as being the proprietary or confidential information of the Principal; (b) trade secrets or information, which is capable of protection at law or equity as confidential information; (c) information from a third party, where the Contractor is advised by the Principal, the Principal‟s Representative or any related entity of the Principal that such information is confidential; and 9 (d) information derived or produced, partly or wholly, from the information referred to above, including any calculation, conclusion, summary or computer modelling, whether the information was disclosed: (e) orally, in writing or in electronic or machine readable form; (f) before, on or after the date of the Deed; (g) as a result of discussions between the parties; or (h) by the Principal, any of its related entities or third parties, which is not in the public domain. Construction Plant means plant and equipment used to do the Work under the Deed, which do not form part of the Works. Contract Price means the aggregate of: (a) where the Principal has accepted lump sum prices, the lump sum prices stated in Schedule 3 - Commercial Schedules; (b) where the Principal has accepted rates, the sum of the products of the actual quantities and the relevant rate for each item in Schedule 3 - Commercial Schedules; and (c) amounts payable in respect of Provisional Sums, as calculated in accordance with clause 4.2, subject to such additions and adjustments or deductions as may be made pursuant to the Deed. Contract Programme means Schedule 10 - Contract Programme, as revised by the Contractor pursuant to clause 15.1. Contractor means the person specified in Schedule 1 - Contract Information. Contractor’s Cost Report means any report prepared or otherwise maintained by or for the Contractor, which constitutes or evidences a record of all: (a) costs, expenses and losses; and (b) progress payments and income receipts, that have been incurred in relation to the Project or otherwise charged to or recorded against the Project by the Contractor to date. Contractor’s Documents means drawings, specifications, calculations and other documents and information, meeting the requirements of clause 17, which the Contractor must produce to design and construct the Work under the Deed in accordance with the Deed. 10 Contractor’s Margin means the margin for profit and additional overhead costs (including administration, supervision, establishment and attendance costs) specified in Schedule 1 - Contract Information. Contractor’s Representative means the Contractor‟s Representative appointed at the date of the Deed specified in Schedule 1 – Contract Information or replaced in the manner provided in clause 13.2. Controller has the meaning given to it in the Corporations Act. Corporations Act means the Corporations Act 2001 (Cth). CSCT Extension means the Roadheader section of the Tunnel to be constructed between the Riley Street Shaft and the CSCT. CSCT means the existing City South Cable Tunnel. Date for Completion means the date 30 days after the Date for Practical Completion, being the date by which Completion is to be achieved, as may be extended in accordance with clause 34. Date for Practical Completion means the relevant date stated in Schedule 2 Separable Portions being the date by which the Contractor is to bring the Work under the Deed to Practical Completion, as may be extended in accordance with clause 34 or adjusted in accordance with clause 19.7(a). Date for Substantial Completion means the date stated in Schedule 2 - Separable Portions being the date by which the Contractor is to bring the Work under the Deed for Separable Portion 1 to Substantial Completion, as may be extended in accordance with clause 34. Date of Completion means the date stated in the relevant Completion Certificate issued by the Principal‟s Representative under clause 22.2 as the date upon which Completion was achieved. Date of Practical Completion means the date stated in the relevant Practical Completion Certificate issued by the Principal‟s Representative under clause 21.2(c) or clause 21.2(e) (as applicable) as the date upon which Practical Completion was achieved. Date of Substantial Completion means the date stated in the relevant Substantial Completion Certificate issued by the Principal‟s Representative under clause 21.1(d) or clause 21.1(f) (as applicable) as the date upon which Substantial Completion of Separable Portion 1 or Substantial Completion of Separable Portion 2 (as the case may be) was achieved. day means a calendar day. Deed means the engineering, design and construction deed entered into between the Principal and the Contractor in respect of the Project, comprising: (a) the Formal Instrument of Agreement; (b) the General Conditions of Deed; (c) Schedules 1 to 17 (inclusive); 11 (d) the Specification including its appendicies; and (e) the Exhibits A to D (inclusive). Defect includes any omission from or defect in the Work under the Deed which: (a) does not conform to the requirements of the Deed (including the Specification and the performance requirements for the Work under the Deed stated in the Deed); (b) is improper or inferior; or (c) may adversely affect the reliable installation and/or operation of the Works or the performance of any part of the Works, other than any deficiency falling within (a) or (b) above which is due to: (i) improper use of the Works by the Principal (including operation outside any specifications provided in the Deed); or (ii) normal wear and tear. Defects Correction Period has the meaning given to it in clause 26.3. Development Approvals means: (a) if the Bligh St Development Approval is granted, the Bligh St Development Approval; and (b) the CECT Development Approval. direction includes agreement, approval, assessment, authorisation, certificate, decision, demand, determination, explanation, instruction, notice, order, permission, rejection, request or requirement. Dispute Resolution Board or DRB means the board constituted by the three neutral individuals mutually selected by the Principal and the Contractor in accordance with clause 40.2 to consider and recommend resolution of disputes referred to it. Draft Interface Agreements means the agreements so described in Schedule 17 Schedule of Interface Agreement Responsibilities, forming part of Exhibit D, which have been initialled by the Principal and the Contractor for identification purposes. Drawings means: (a) the drawings which form appendices to the Specification; and (b) any modification of the drawings referred to in paragraph (a) above notified in writing by the Principal‟s Representative to the Contractor. DRB Appointment Agreement means the agreement so entitled between the Principal, the Contractor and the DRB members appointed pursuant to the Deed, in the form of Schedule 13 - DRB Appointment Agreement. Environment means all aspects of the surroundings of human beings including: 12 (a) the physical factors of those surroundings including the atmosphere, soil, subsoil, waters and seabed; (b) the biological factors of those surroundings including human, other animal, plant and other forms of life; and (c) the aesthetic factors of those surroundings including appearance, sounds, smells, tastes and textures. Environmental Assessment means the document so entitled, forming Exhibit B, which has been initialled by the Principal and the Contractor for identification purposes. Event of Force Majeure means any of the following listed events or circumstances or a combination of those events and circumstances: (a) war, hostilities or warlike operations (whether a state of war be declared or not), invasion, act of foreign enemy or civil war; or (b) rebellion, revolution, insurrection, mutiny, usurpation of civil or military government, riot, civil commotion or terrorist acts; or (c) confiscation, nationalisation, mobilisation, commandeering or requisition by or under the order of any government or de jure or de facto authority or ruler or any other act or failure to act of any local, state or national government authority; or (d) sabotage, lock-out, embargo, import restriction, shipwreck, epidemics, quarantine or plague; or (e) earthquake, landslide, volcanic activity, fire, flood or inundation, tidal wave, typhoon or cyclone, hurricane, lightning, nuclear and pressure waves, or other natural or physical disaster; or (f) shortage of labour, materials or utilities where caused by circumstances that are themselves Events of Force Majeure, which: (g) is beyond the reasonable control of the party affected by that event or circumstance; (h) causes or results in delay in, or prevention of, the performance by the affected party of any of its obligations under the Deed; and (i) cannot be prevented, overcome or remedied by the exercise by the affected party of a standard of care and diligence consistent with that of a prudent and competent utilities owner or contractor (as the case may be). Final Payment means the payment to be made by the Principal or the Contractor under clause 7.5(g). Final Payment Certificate means the Principal‟s Representative‟s certificate under clause 7.5, which states the final balance due to the Contractor or the Principal, as the case may be. 13 Formal Instrument of Agreement means the deed signed between the Principal and the Contractor attached to these General Conditions of Deed. Geotechnical Baseline Report or GBR means the document entitled “Energy Australia - City East Cable Tunnel Geotechnical Baseline Report PSM1055-008R Rev 3, dated18 April 2011, forming Exhibit C, which has been initialled by the Principal and the Contractor for identification purposes. General Conditions of Deed means clauses 1 to 41 (inclusive) of this document. Government Approval means any authorisation, consent, approval, licence, lease, ruling, permit, exemption, variance, order, judgment, decree, publication, notice, declaration or regulation made, issued or given by any Federal, State, or Local Government, or any Government Authority, relating to the occupation, design, construction, start-up, testing, operation or maintenance of the Works or to the execution, delivery or performance of any document relating to the Project including the Deed. Government Authority means any national, state, local, regional, territorial or municipal government, ministry, governmental department, commission, board, bureau, agency, instrumentality, executive, legislative, judicial or administrative body, or government corporation having jurisdiction over the Work under the Deed, the Principal or the Contractor, or anything in connection with any of them. GST means a goods and services tax, as governed by the GST Act. GST Act is A New Tax System (Goods and Services Tax) Act 1999 (Cth). Hold Point means a position in the progress of the Work under the Deed beyond which work must not proceed without mandatory verification and acceptance by the Principal‟s Representative. Insolvency Event means, with respect to a party, that: (a) it is, or states that it is, insolvent, as defined in the Corporations Act; (b) it has a Controller appointed to any part of its property; (c) it is in receivership, in receivership and management, in liquidation, in provisional liquidation, under administration or wound up or has had a Receiver appointed to any part of its property; (d) it is subject to any arrangement, assignment, moratorium or composition, protected from creditors under any statute or dissolved, other than to carry out a reconstruction or amalgamation while solvent on terms approved by the other party; (e) an application or order has been made (and, in the case of an application, it is not stayed, withdrawn or dismissed within 20 business days), a resolution passed, a proposal put forward or any other action taken, in each case in connection with that party, which is preparatory to, or could result in, any of the circumstances set out in paragraphs (a), (b), (c) or (d) above; (f) it is taken, under section 459(F)(1) of the Corporations Act, to have failed to comply with a statutory demand; 14 (g) it is the subject of an event described in section 459(C)(2)(b) or section 585 of the Corporations Act or it makes a statement from which the other party reasonably deduces it is so subject; (h) it is otherwise unable to pay its debts when they fall due; or (i) something having a substantially similar effect to the circumstances set out in paragraphs (a) to (h) above happens in connection with that party under the law of any jurisdiction. Intellectual Property Rights means copyright, all rights conferred under statute, common law or equity in relation to inventions (including patents), registered and unregistered trademarks, registered and unregistered designs, circuit layouts and confidential information, and all other rights resulting from intellectual activity in the industrial, scientific, literary or artistic fields. Interface Agreements means the agreements so described in Schedule 17 - Schedule of Interface Agreement Responsibilities, forming part of Exhibit D, which have been initialled by the Principal and the Contractor for identification purposes, and will include the executed versions of any Draft Interface Agreements. Interface Party means: (a) Rail Corporation New South Wales (ABN 59 325 778 353) (“RailCorp”); (b) Roads and Traffic Authority NSW (ABN 64 480 155 255) (“RTA”); (c) Sydney Water Corporation (ABN 49 776 225 038) (“Sydney Water”); (d) State Library of New South Wales (ABN 19 665 924 697) (“State Library”); (e) The Domain Trust (ABN 97 270 414 025) (“Domain Trust”); and (f) CCM. Key Personnel means the personnel specified in Schedule 6 - Key Personnel as the Contractor‟s key personnel, including any replacement personnel engaged pursuant to clause 14.2. Law means: (a) Commonwealth and State legislation, including regulations, by-laws and other subordinate legislation; (b) common law and equity; (c) Government Authority requirements; and (d) guidelines of Government Authorities with which the Contractor is legally required to comply. Materially Adverse Conditions has the meaning given to it in Schedule 4 - GBR Administration. Materials means materials, articles and things of all kinds to be utilised in the execution of the Work under the Deed by the Contractor (including drafting, drawing, 15 computer hardware, software, accessories, spare parts and consumables to be supplied by the Contractor under the Deed, but excluding any Construction Plant). Moral Rights means any of the rights described in Article 6bis of the Berne Convention for the Protection of Literary and Artistic Works 1886 (as amended and revised from time to time), being “droit moral” or other analogous rights arising under any statute (including the Copyright Act 1968 (Cth)) or any other law (including any law outside Australia), that exist, or that may come to exist, anywhere in the world. OH&S Plan is the occupational health and safety management plan to be submitted by the Contractor prior to commencement of any Work under the Deed on the Site, as updated under clause 19.6. OH&S Regulation is the Occupational Health and Safety Regulation 2001 (NSW). Other Claims has the meaning given to it in clause 40.1(a)(ii). Parameters has the meaning given to it in Schedule 4 - GBR Administration. Payment Withholding Request means a request which is, or purports to be, a payment withholding request made under the Building and Construction Industry Security of Payment Act 1999 (NSW). Practical Completion means the stage in the execution of the Work under the Deed when: (a) the Work under the Deed has been completed in accordance with the Deed and is free from Defects, except for minor defects or omissions as referred to in clause 21.2(b); (b) the Contractor has completed all Tests in respect of the Works and has provided evidence to the reasonable satisfaction of the Principal that all such Tests have been passed in accordance with the Deed; (c) the Contractor has provided to the Principal all necessary surveys, certifications and draft operations and maintenance manuals in respect of the Work under the Deed; (d) the Contractor has provided to the Principal the up to date property information log in respect of the Work under the Deed; (e) the Principal is able to install and commission its infrastructure components and interconnect such infrastructure components with the Works; (f) the Contractor has provided to the Principal‟s personnel and such other persons as nominated by the Principal such training as specified in the documents comprising the Deed; and (g) the Contractor has complied with all of the other obligations in respect of the Work under the Deed required under the Deed to be performed prior to Practical Completion. Practical Completion Certificate means the certificate issued by the Principal‟s Representative in accordance with clause 21.2(c) or 21.2(e) (as applicable) stating the date upon which Practical Completion is achieved. 16 Pre-Contract Information comprises the documents listed in Schedule 11 - PreContract Information, which have been initialled by the Principal and the Contractor for identification purposes. Principal means the person so specified in Schedule 1 - Contract Information. Principal’s Representative means any person appointed by the Principal in the manner provided in clause 13.1 to perform the duties delegated by the Principal. Progress Claim means each fully supported invoice delivered to the Principal‟s Representative by the Contractor at the time set out in Schedule 1 - Contract Information containing all of the requirements set out or contemplated in clause 7.3 and in a form approved by the Principal‟s Representative. Project means Energy Australia‟s City East 132kV Cable Tunnel Project, as more precisely described in the Deed. Project Construction Manager means the person appointed by the Contractor under clause 19.1. Project Control Group means the project control group referred to in clause 15.2(a). Project Plans means: (a) (b) each of the following plans so described in the Deed, and particularly in the Specification, to be prepared by the Contractor: (i) Quality Plan; (ii) Construction Environmental Management Plan (CEMP) (iii) OH&S Plan; (iv) Drainage and Water Quality Plan; (v) Waste Management Plan; (vi) Community Involvement Plan (CIP); (vii) Risk Management Plan; (viii) Contingency Management Plan; (ix) Traffic Control Plan; (x) Commissioning Plan; and (xi) Asset Management Plan; and any other plans referred to in the Development Approvals and either: (i) specified in Schedule 16A - Schedule of CECT Development Approval Responsibilities as the Contractor‟s responsibility; or (ii) notified by the Principal to the Contractor under clause 6.3(a)(i) as the Contractor's responsibility, 17 each as is updated from time to time under clause 6.4. Provisional Sums are the allowances included in the Contract Price which are provisional monetary, prime cost, contingency or other such sums or allowances for the work specified in Schedule 5 - Provisional Sums. Receiver has the meaning given to it in the Corporations Act. Riley Street Shaft has the meaning given to it in the Specification. Roadheader means the machinery / equipment used to excavate the City East Substation Stub Tunnel, the TBM Backshunt Tunnel and the CSCT Extension. Roadheader Section of Tunnel has the meaning given to it in the Specification. Schedule 1 - Contract Information means schedule 1 to the General Conditions of Deed. Schedule 2 - Separable Portions means schedule 2 to the General Conditions of Deed. Schedule 3 - Commercial Schedules means schedule 3 to the General Conditions of Deed. Schedule 4 - GBR Administration means schedule 4 to the General Conditions of Deed. Schedule 5 - Provisional Sums means schedule 5 to the General Conditions of Deed. Schedule 6 - Key Personnel means schedule 6 to the General Conditions of Deed. Schedule 7 - Insurances means schedule 7 to the General Conditions of Deed. Schedule 8 - Approved Subcontractors means schedule 8 to the General Conditions of Deed. Schedule 9 - Form of Unconditional Undertaking means schedule 9 to the General Conditions of Deed. Schedule 10 - Contract Programme means schedule 10 to the General Conditions of Deed. Schedule 11 - Pre-Contract Information means schedule 11 to the General Conditions of Deed. Schedule 12 - DRB Appointment and Operating Procedures means schedule 12 to the General Conditions of Deed. Schedule 13 - DRB Appointment Agreement means schedule 13 to the General Conditions of Deed. Schedule 14 - Subcontractors Statement and Statutory Declaration means schedule 14 to the General Conditions of Deed. Schedule 15 - Guarantee and Indemnity means schedule 15 to the General Conditions of Deed. 18 Schedule 16 – CECT Development Approval means schedule 16 to the General Conditions of Deed. Schedule 16A –Schedule of CECT Development Approval Responsibilities means schedule 16A to the General Conditions of Deed. Schedule 17 - Schedule of Interface Agreement Responsibilities means schedule 17 to the General Conditions of Deed. Security Interest means any bill of sale, as defined in any Law, mortgage, charge, lien, pledge, hypothecation, title retention arrangement, trust or power, as, or having effect as, a security for the payment of any monetary obligation or the observance of any other obligation. Security of Payment Act means the Building and Construction Industry Security of Payment Act 1999 (NSW). Separable Portion means each of the discrete parts of the Work under the Deed so identified in Schedule 2 - Separable Portions or created pursuant to clause 3.9. Separate Contractors means contractors (other than the Contractor) engaged by the Principal or third parties to carry out works or services of whatever nature at or in the vicinity of the Site, including: (a) the Principal‟s cable supply and installation contractors; (b) the Riley Street STSS Building Contractor; (c) the City East Substation Building Contractor; and (d) other separate contractors as may be advised to the Contractor by the Principal during the course of the Work under the Deed. Shafts has the meaning given to it in the Specification. Site means the land and other places upon which, or within which, the Works are to be constructed and the Work under the Deed is to be performed, as shown in the Drawings and the Specification, and any other lands and places made available to the Contractor by the Principal for the purpose of the Deed. Site Conditions means any physical conditions of the Site and its surroundings (including hydrological, surface and sub-surface conditions and characteristics, but excluding weather conditions or physical conditions which are a consequence of weather conditions) encountered in the execution of the Work under the Deed. Site Representative means each such person appointed by the Contractor under clause 13.2. Specification means the document titled “Design and Construction of Civil Works and Services for the City East 132kV Cable Tunnel - Specification EA 0933/09", including its Appendices A to R, forming Exhibit A to the Deed, as initialled by the parties for identification purposes and as may be amended in accordance with clause 4.1A and otherwise in accordance with the Deed. Subcontractor means any person to whom execution of any part of the Work under the Deed, including preparation of any design for which the Contractor is responsible 19 under the Deed, is subcontracted directly or indirectly by the Contractor and includes its legal successors or permitted assigns. Substantial Completion means: (a) (b) in respect of Separable Portion 1, the stage in the execution of the Work under the Deed relating to Separable Portion 1 when: (i) the tunnel excavation is complete; (ii) all tunnel interface excavation works are complete; (iii) the structural lining, including walls, roof and invert slabs, is complete; (iv) all physical permanent services fixtures (excluding permanent lighting, cabling or hydraulic equipment) are installed in situ suitable for clear unimpeded access for the Cable Installation Contractor; (v) the tunnel walls, ceiling and floor and the interfaces are ready for installation of the 33kV and 132kV cables by the Cable Installation Contractor; and (vi) the cable support bracket system is supplied and fixed to the tunnel wall; and in respect of Separable Portion 2, the stage in the execution of the Work under the Deed relating to Separable Portion 2 when: (i) the tunnel excavation is complete; (ii) all tunnel interface excavation works are complete; and (iii) the Contractor has demobilised the Roadheader and all temporary construction facilities installed by the Contractor or its Subcontractors from the Site. Substantial Completion Certificate means the certificate issued by the Principal‟s Representative in accordance with clause 21.1(d) or clause 21.1(f) (as applicable) stating the date upon which Substantial Completion of Separable Portion 1 or Substantial Completion of Separable Portion 2 (as the case may be) is achieved. Tax means any tax, levy, impost, deduction, charge, duty or withholding which is levied or imposed by a Government Authority, including any income, capital gains, or value added tax, goods and services tax, withholding, stamp and transaction tax, duty or charge, sales tax or any similar tax pursuant to any Law together with interest, penalties, charges, fees or other amounts (if any) imposed or made on or in respect of the above. TBM has the meaning given to it in the Specification. TBM Backshunt Tunnel has the meaning given to it in the Specification. TBM Section of the Tunnel has the meaning given to it in the Specification. 20 Tests includes examinations, measurements, trials and tests of all or any part of the Work under the Deed, including all examinations, measurements, trials and tests which are described in the Deed and particularly in the Specification. Tunnel means Tunnel as defined in the Specification. Tunnel Site means that part of the Site comprising the Tunnel. Typical Condition has the meaning given to it in Schedule 4 - GBR Administration. Unit has the meaning given to it in Schedule 4 - GBR Administration. Valid Tax Invoice means an invoice which complies with the GST Act relating to the production and form of tax invoices for GST purposes. Work under the Deed means the whole of the work to be supplied and carried out by the Contractor in accordance with the Deed and as further described in the Specification and includes all Changes and all work and activities necessary for completion of the work to be carried out by the Contractor, whether described in the Deed or not. Works means that part of the Work under the Deed (including Changes) which is required by the Deed to be handed over to the Principal. 1.2 2 Where a word or expression is not defined in clause 1.1, reference should be made to the Specification unless the contrary intention appears. Contract Documents 2.1 All documents forming part of the Deed are intended to be correlative, complementary and mutually explanatory of one another. The Deed must be read as a whole, and anything required by one document forming part of the Deed is deemed to form part of the relevant party‟s obligations, whether or not required by any other such document. 2.2 If: (a) the Principal or the Contractor notifies the Principal‟s Representative in writing of; or (b) the Principal‟s Representative otherwise discovers, an ambiguity, error, omission, discrepancy, inconsistency or other fault in, from or between any of the terms of the Deed, the Principal‟s Representative must issue such direction as may be necessary to resolve or correct that ambiguity, error, omission, discrepancy, inconsistency or other fault. 2.3 The Contractor is not entitled to any compensation or extension of time arising out of a direction from the Principal‟s Representative under clause 2.2, except as set out in clause 2.5. 2.4 The parties acknowledge and agree that the Contractor is not responsible for any ambiguity, error, omission, discrepancy, inconsistency or other fault in, from or between any documentation in relation to the design of such parts of the Work under the Deed for which the Principal has design responsibility under the Deed. 21 2.5 If the Principal‟s Representative is notified of, or otherwise discovers, an ambiguity, error, omission, discrepancy, inconsistency or other fault in, from or between any documentation in relation to the design of such parts of the Work under the Deed: (a) for which the Principal has design responsibility under the Deed; and (b) which would not have been reasonably discoverable by the Contractor in discharging its obligations under clause 17.1, the Principal‟s Representative must direct a Change under clause 33. 3 Interpretation 3.1 General In the Deed unless a contrary intention is stated: (a) a reference to the Deed or another instrument includes any variation or replacement of the Deed or that instrument; (b) a reference to the Deed includes all schedules, exhibits and annexures to the Deed; (c) a reference to a statute, ordinance, code or other Law includes consolidations, amendments, re-enactments or replacements of any of them; (d) a reference to a court is to an Australian court; (e) a reference to a party is to a party to the Deed; (f) the singular includes the plural and vice versa; (g) person includes an individual, corporation, partnership, joint venture, association, trust, unincorporated association, Government Authority or any other entity; (h) a reference to a person includes a reference to the person‟s legal personal representatives, executors, administrators, successors in title, substitutes and assigns; (i) a reference to $, AUD or dollar is to the lawful currency of the Commonwealth of Australia; (j) a reference to a subcontractor includes a consultant or supplier; (k) if an act must be done on a specified day which is not a business day, it must be done instead on the next business day; (l) if a period of time is specified and dates from a given day or the day of an actual event, it is to be calculated exclusive of that day; (m) a reference to a month means a calendar month; (n) where an expression is defined, another part of speech or grammatical form of that expression has a corresponding meaning; 22 3.2 (o) headings are for reference only and do not form part of the Deed; (p) references to “includes”, “including” and “include” are to be read as if followed by the words “without limitation”; (q) a reference to a clause, schedule, exhibit, annexure or appendix is a reference to a clause of or schedule, exhibit, annexure or appendix to these General Conditions of Deed; and (r) (in the Specification) wherever the imperative form of a verb is used alone without it being prefaced by the words “The Contractor must”, those words must be read to be included as prefacing that verb. Amendment No amendment or other variation of the Deed will be effective unless it is in writing, is dated, expressly refers to the Deed, and is signed by the Authorised Representative of each party. 3.3 3.4 3.5 Independent Contractor (a) The Contractor is an independent contractor performing the Work under the Deed and its other obligations under the Deed. The Deed does not, in any way, create any agency, partnership, joint venture or other joint relationship between the parties. (b) Subject to the provisions of the Deed, the Contractor is solely responsible for the manner in which the Work under the Deed is performed. All employees, representatives or Subcontractors engaged by the Contractor in connection with the performance of the Deed will be under the complete control of the Contractor and will not be deemed to be employees of the Principal. Nothing contained in the Deed or in any subcontract awarded by the Contractor will be construed to create any contractual relationship between any of the Contractor‟s employees, representatives or Subcontractors and the Principal. Non-waiver (a) Subject to clause 3.4(b), no relaxation, forbearance, delay or indulgence by either party in enforcing any of the terms and conditions of the Deed or the granting of time by either party to the other will prejudice, affect or restrict the rights of that party under the Deed, nor will any waiver by either party of any breach of the Deed operate as a waiver of any subsequent or continuing breach of the Deed. (b) Any waiver of a party‟s rights, powers or remedies under the Deed must be in writing, dated and signed by the Authorised Representative of the party granting such waiver, and must specify the right and the extent to which it is being waived. Severability If any provision or condition of the Deed is prohibited or rendered invalid or unenforceable, such prohibition, invalidity or unenforceability does not affect the validity or enforceability of any other terms and conditions of the Deed. 23 3.6 Contra proferentem In the interpretation of the Deed, no rule of construction applies to the disadvantage of one party on the basis that it put forward the Deed or any part of it. 3.7 Joint and several If the Contractor is comprised of more than one person: 3.8 (a) the obligations of those persons as the Contractor under the Deed are joint and several; and (b) the Principal may proceed against any or all of them in respect of the Contractor‟s obligations under the Deed. Comments, review, representation or approval by the Principal or the Principal’s Representative The Contractor acknowledges that no comment, review, representation, vetting, inspection, examination, testing or approval by the Principal or the Principal‟s Representative in respect of the Contractor‟s performance of its obligations under the Deed will lessen or otherwise affect the Contractor‟s obligations under the Deed. 3.9 Separable Portions and use of partly completed Works (a) The interpretations of: (i) Date for Substantial Completion; (ii) Date of Substantial Completion; and (iii) Substantial Completion, and clauses 4.1A(f), 4.1B(c)(iii), 15.1(b), 15.4, 21.1, 25.1(a), 25.2(a), 25.2(c), 25.2(e), 25.2(f), 30.3(a), 30.3(e), 30.3(f), 32.2, 33.3, 33.5, 33.8, 34, 35 and 36.2 apply separately to each of Separable Portion 1 and Separable Portion 2 and references in those definitions and clauses to the Works and the Work under the Deed means those parts of the Works and the Work under the Deed comprised in the relevant Separable Portion. (b) In addition to the Separable Portions described in the Contract, the Principal‟s Representative may by notice in writing to the Contractor, determine: (i) that any part of the Work under the Deed or of a Separable Portion will be a Separable Portion; (ii) the respective dates for Substantial Completion and/or Practical Completion for the new Separable Portion and the resultant Separable Portion (as applicable), which should be made reasonably and in consultation with the Contractor; and (iii) the liquidated damages applicable to each such Separable Portion on the basis of the proportion that the value of each new Separable Portion bears to the value of the prior Separable Portion of which it forms part, or, if appropriate, to the whole of the Work under the 24 Deed, applied to the liquidated damages for the previous Separable Portion, or the Work under the Deed, as the case requires, and, if Substantial Completion is applicable to the new Separable Portion, clause 3.9(a) will be interpreted and separately apply to that new Separable Portion in addition to Separable Portion 1 and Separable Portion 2. (c) 3.10 Without limiting paragraph (b), if part of the Works has reached a stage equivalent to that of Practical Completion but another part of the Works has not reached such a stage, the Principal's Representative may determine: (i) that the respective parts shall be Separable Portions; and (ii) the liquidated damages applicable to each such Separable Portion on the basis of the proportion that the value of each new Separable Portion bears to the value of the prior Separable Portion of which it forms part, or, if appropriate, to the whole of the Work under the Deed, applied to the liquidated damages for the previous Separable Portion, or the Work under the Deed, as the case requires. Application of Deed The Deed applies to the performance of the Work under the Deed before, on or after the date of the Deed. 3.11 Entire agreement Except to the extent set out in clause 47 of the agreement titled "EnergyAustralia City East 132kV Cable Tunnel Project – Early Contractor Involvement Agreement" between the Principal and the Contractor, the Deed constitutes the entire agreement between the parties in respect of its subject matter and supersedes all prior agreements, representations, warranties, promises, statements, negotiations and letters in respect of its subject matter. 3.12 Counterparts The Deed may consist of a number of copies each signed by one or more parties to the Deed. If so, the signed copies are treated as making up the one document. 4 Scope of the Work under the Deed 4.1 Scope of work (a) The scope of the Work under the Deed is described in the Specification, but that description does not limit the Contractor‟s obligation to undertake all activities, subject to the terms of the Deed, necessary for performance of the Work under the Deed. (b) The Contractor warrants that: (i) it has examined the Site and its surroundings; (ii) it has examined all other information relevant to the risks, contingencies and other circumstances having an effect on its 25 obligations under the Deed which is obtainable by making reasonable enquiries; (c) 4.1A (iii) it has examined the Deed; (iv) it has satisfied itself as to the extent and nature of work including: (A) Materials and Construction Plant necessary for the execution and completion of the Work under the Deed; and (B) any works of environmental remediation which are required to be carried out as a result of activities or works undertaken by the Contractor or its Subcontractors provided that the Contract Price will be adjusted for any works of environmental remediation for any existing contaminates found or uncovered on the Site during the execution and completion of the Work under the Deed as if those works were directed as a Change under the Deed; (v) it has satisfied itself as to the means of access to the Site and the accommodation it may require; (vi) it has satisfied itself as to the correctness and sufficiency of the Deed and that the Contract Price covers the costs of complying with all the Contractor‟s obligations under the Deed and of all matters and things necessary for the due and proper completion of the Work under the Deed; and (vii) it is practicable to execute and complete the Work under the Deed in accordance with the Deed without any need for Changes. Subject to the terms of the Deed, the Contractor is not relieved of any of its obligations under the Deed, and it does not have any remedy against the Principal, by reason of the existence or occurrence of any matter or thing not anticipated by the Contractor as at the date of the Deed and which may not be contemplated by the Deed. Alternate scope of work due to progress (a) The parties acknowledge and agree the following: (i) as at the date of the Deed, the parties expect that the applicable Work under the Deed will be carried out as contemplated by clause 4.1A(a)(ii); (ii) the: (A) Specification forming Exhibit A to the Deed; and (B) Contract Programme, have been compiled on the basis that the excavation of the City East Substation Stub Tunnel will be complete before the TBM arrives at the point where the TBM Section of the Tunnel intersects with the City East Substation Stub Tunnel (Intersection Point); 26 (iii) depending on the progress (as against the Contract Programme) of: (A) the excavation of the TBM Section of the Tunnel; relative to (B) the excavation of the City East Substation Stub Tunnel, it may be necessary, after the date of the Deed, for the Contractor to change the way in which the City East Substation Stub Tunnel is constructed. The extent of this potential change in construction methodology is described further in Section 4.3 of Schedule 4 – GBR Administration; and (iv) (b) accordingly, the parties have included the flexibility in clause 4.1A(b) to replace the drawings numbered 208450, 208451, 208457, 208458, 208465, 208466 and 208467 in the Specification with the alternative drawing in Exhibit A1. If the Contractor considers (acting reasonably) that the Work under the Deed will not be completed in the order contemplated by clause 4.1A(a)(ii), the Contractor must, not later than 60 days prior to the date on which the TBM is expected to arrive at the Intersection Point, provide written notice to the Principal setting out: (i) the progress of the excavation of the TBM Section of the Tunnel as against the Construction Programme; (ii) the progress of the excavation of the City East Substation Stub Tunnel as against the Construction Programme; and (iii) the reasons why the Contractor considers that: (A) the excavation of the TBM Section of the Tunnel and/or the excavation of the City East Substation Stub Tunnel (as the case may be) is progressing otherwise than in accordance with the Contract Programme; and (B) the excavation of the City East Substation Stub Tunnel will not be complete before the TBM arrives at the Intersection Point, together with all relevant supporting documentation as reasonably required by the Principal. (c) Unless the parties otherwise agree in writing, if: (i) the Contractor provides a written notice under clause 4.1A(b) and the Principal has provided a notice under clause 4.1A(e)(i), the drawings numbered 208450, 208451, 208457, 208458, 208465, 208466 and 208467 in the Specification will be deleted and replaced with the alternative drawing in Exhibit A1 with effect from the date which is 30 days after the Principal receives the Contractor's notice under clause 4.1A(b); or (ii) the Principal has provided a notice under clause 4.1A(e)(ii), the drawings numbered 208450, 208451, 208457, 208458, 208465, 208466 and 208467 in the Specification will be deleted and replaced 27 with the alternative drawing in Exhibit A1 with effect from the date of the Principal's notice under clause 4.1A(e)(ii). (d) Subject to clause 4.1A(f), the Contractor is not entitled to any adjustment to the Contract Price, any extensions of time or delay costs, or any other compensation, arising out of or in connection with the giving of the written notice under clause 4.1A(b) or clause 4.1A(e) or the replacement of the drawings numbered 208450, 208451, 208457, 208458, 208465, 208466 and 208467 in the Specification with the alternative drawing in Exhibit A1 under this clause 4.1A. (e) If: (i) both of the following have occurred: (A) the Contractor has provided a written notice and all relevant supporting documentation in accordance with clause 4.1A(b); and (B) the Principal considers (acting reasonably) that the Work under the Deed will not be completed in the order contemplated by clause 4.1A(a)(ii) soley: (aa) due to an act or omission of the Principal (including a failure to provide access to the Site in accordance with clause 19.3 but excluding the exercise of the Principal's express rights or powers under the Deed); or (ab) because: (I) the proportion of Adverse Ground Conditions encountered in the City East Substation Stub Tunnel is greater than the expected proportions included in Table 5.5.3 of the GBR; or (II) Materially Adverse Conditions were encountered in the City East Substation Stub Tunnel, the Principal must, within 30 days of receipt by the Principal of the Contractor's written notice and all relevant supporting documentation under clause 4.1A(b), provide a written notice to the Contractor to that effect; or (ii) (f) the Work under the Deed has not been completed in the order contemplated by clause 4.1A(a)(ii), the Principal may provide a written notice to the Contractor to that effect. If the Principal provides a written notice to the Contractor under clause 4.1A(e): (i) the Contract Price will be adjusted by the relevant amount; and 28 (ii) the Date for Substantial Completion and the Date for Practical Completion will be adjusted by the relevant period, set out in Schedule 1 – Contract Information. 4.1B Masked for Confidentiality 4.2 Provisional Sums A Provisional Sum is not itself payable by the Principal but where the work or item to which the Provisional Sum relates is performed or supplied by the Contractor, unless otherwise provided or agreed, the reasonable cost to perform the work or supply the item (exclusive of GST) must be determined by the Principal‟s Representative, and: (a) any difference between such cost and the particular Provisional Sum; and (b) the amount calculated by applying the rate specified in Schedule 1 - Contract Information to such cost, must be added to or deducted from the Contract Price, as the case may require. 29 5 Time for Commencement 5.1 6 Subject to clause 19.3, the Contractor must commence the Work under the Deed on the Commencement Date. Contractor’s Obligations 6.1 Compliance with the Deed, Law and Government Approvals (a) The Contractor must perform the Work under the Deed in a professional manner and in accordance with the Specification and all other terms and conditions of the Deed. (b) The Contractor must acquire all Government Approvals, which are necessary for the performance of the Work under the Deed, except for the Development Approvals. (c) Unless otherwise specified in the Deed, the Contractor must comply with all Laws affecting the performance of the Work under the Deed and its other obligations under the Deed and binding upon the Contractor. (d) The Contractor must, when performing its obligations under the Deed, comply with all NSW Government policies, codes and guidelines relevant to the Project and its execution of the Work under the Deed including the following: (e) 6.2 (i) NSW Government‟s Occupational Health, Safety and Rehabilitation Management System Guidelines; (ii) NSW Government‟s Industrial Relations Management Guidelines; (iii) NSW Government‟s Environmental Management System; and (iv) the NSW Government Code of Practice for Procurement. The Contractor must, to the extent practical, conduct all work for the design and construction of the Work under the Deed in a manner which will ensure that it has minimum impact on and disruption to the Environment or the community at or in the vicinity of the Site. Compliance with Interface Agreements (a) The Contractor: (i) acknowledges that the Principal has entered or will enter into the Interface Agreements described in Schedule 17 - Schedule of Interface Agreement Responsibilities; (ii) must, during the performance of its obligations under the Deed, not cause the Principal to be in breach of its obligations under those Interface Agreements; 30 (b) (iii) must not transfer, grant or create, or purport to grant or create or permit the creation of any right of way, easement, licence or security interest in or over those agreements referred to in clause 6.2(a)(i); (iv) must comply with all of the Principal‟s obligations under each Interface Agreement other than those identified in Schedule 17 Schedule of Interface Agreement Responsibilities as the Principal‟s responsibility; (v) must assist the Principal in any way that the Principal reasonably requires to enable the Principal to perform the obligations identified as the Principal‟s responsibility in Schedule 17 - Schedule of Interface Agreement Responsibilities; and (vi) must comply with any reasonable directions of the Principal‟s Representative (who will have regard to any reasonable submissions made by the Contractor to the Principal‟s Representative) in relation to compliance with the relevant conditions and requirements of each Interface Agreement. The parties acknowledge that: (i) as at the date of the Deed, the terms and conditions of the Draft Interface Agreements have not been finalised between the Principal and the relevant Interface Party; (ii) subject to clause 6.2A, the Contractor has reviewed the Interface Agreements executed at the date of the Deed (if any) and the Draft Interface Agreements and has included in the Contract Price: (A) all of its costs (including the cost of all physical works) in complying with the Principal‟s obligations under the Interface Agreements executed at the date of the Deed (if any) and the Draft Interface Agreements other than those identified in Schedule 17 - Schedule of Interface Agreement Responsibilities as the Principal‟s responsibility; and (B) a Provisional Sum amount of one hundred and eighty thousand dollars ($180,000) for the activities described in item 13.1 of the pricing schedule included in Schedule 3 – Commercial Schedules and item 5.1 of Schedule 5 – Provisional Sums; (iii) following execution of any Interface Agreement after the date of the Deed, the Principal must promptly give the Contractor a copy of that Interface Agreement; (iv) within 14 days of receipt of an executed Interface Agreement, the Contractor must inform the Principal‟s Representative in writing of any terms and conditions of the executed Interface Agreement which the Contractor reasonably considers are substantially more onerous than those contained in the relevant Draft Interface Agreement and provide details of: 31 (A) the additional administration costs to be incurred by the Contractor in complying with such terms and conditions; and (B) the cost of carrying out any additional physical works not forming part of the Work under the Deed; (v) if the Principal does not receive a notice from the Contractor under clause 6.2(b)(iv) within the 14 day period, it is deemed that the Contractor can carry out its obligations under the executed Interface Agreement without any adjustment to the Contract Price; (vi) if the Principal‟s Representative receives a notice from the Contractor under clause 6.2(b)(iv) within the 14 day period, then the Principal‟s Representative must: (A) give the Contractor a notice setting out the Principal‟s Representative‟s determination of the reasonable, additional administration costs incurred by the Contractor in complying with the executed Interface Agreement (as determined by the Principal‟s Representative in accordance with clause 4.2); and (B) if the terms of any Interface Agreements executed after the date of the Deed require the Contractor to carry out any physical work which: (aa) does not form part of the Work under the Deed; and (ab) is additional to any physical works contemplated by the Interface Agreements executed at the date of the Deed and the Draft Interface Agreements, the Principal must direct a Change under clause 33; and (vii) 6.2A notwithstanding the provisions of this clause 6.2(b), the amount of any additional costs incurred by the Contractor as a result of the circumstances referred to in clause 6.2(b)(iv) will not be added to the Contract Price unless the Contractor has taken all proper and reasonable measures to avoid or minimise the extra costs resulting from such circumstances. Interface Agreement between the Principal and RailCorp The Principal and the Contractor acknowledge and agree that any changes required to the Design Documents by RailCorp under the RailCorp Interface Agreement may impact on the Work under the Deed. If the Contractor is delayed or incurs more or less cost as a result of RailCorp's rights to require changes to the Design Documents, this will be deemed to be a Change and clause 33 (including clauses 33.3 and 33.8) applies. 6.3 Development Approvals (a) The Contractor must comply with: (i) if the Bligh St Development Approval is granted, the conditions of the Bligh St Development Approval which are notified by the 32 Principal to the Contractor as the Contractor's responsibility on the following basis: (A) the notice is taken to be a direction for a Change for the purposes of clause 33; and (B) the Change is to be valued in accordance with clause 33.8, except to the extent that the responsibilities were already included in the scope of the Work under the Deed; and (ii) (b) 6.4 the conditions of the CECT Development Approval which are identified in Schedule 16A –Schedule of CECT Development Approval Responsibilities as the Contractor's responsibility. If the Contractor does not comply with any condition of the Development Approvals for which it is responsible, the Principal may: (i) comply with that condition; and (ii) recover from the Contractor all costs and expenses incurred as a debt. Project Plans (a) (b) The Contractor acknowledges and agrees that the intended purposes of the Project Plans include: (i) demonstrating to the Principal and relevant Government Authorities that the Contractor has the understanding, capacity and capability at all times to carry out the Work under the Deed in accordance with the requirements of the Deed; (ii) ensuring that the Work under the Deed complies with the requirements of the Deed, including the Development Approvals; and (iii) allowing the Principal to understand how the Contractor will achieve the performance outcomes specified in the Deed and otherwise fulfil its obligations under the Deed. The Contractor must: (i) develop, continually review and, if necessary, update the Project Plans: (A) to take into account events or circumstances which will, or may reasonably be expected to, affect the manner in which the Contractor carries out the Work under the Deed, including: (aa) Changes; (ab) changes in Law; (ac) Government Approvals; 33 (B) (ii) (c) (ad) the commencement of new phases or stages of design or construction as shown in the Contract Programme; and (ae) those events or circumstances identified in the Specification in respect of each Project Plan; and as otherwise specified in the Deed or directed by the Principal‟s Representative; and promptly submit each updated Project Plan to the Principal‟s Representative. The Principal and the Principal‟s Representative may: (i) review any Project Plan submitted under this clause 6.4; and (ii) if the Project Plan does not comply with the requirements of the Deed, notify the Contractor of that non-compliance within 20 Business Days of the submission of the Project Plan. If the Contractor receives a notice under this clause 6.4(c), the Contractor must promptly submit an amended Project Plan to the Principal‟s Representative. (d) The Principal and the Principal‟s Representative owe no duty of care to the Contractor to review any Project Plan submitted by the Contractor for errors, omissions or compliance with the Deed. No review of, comments upon, or notice in respect of, or any failure to review, comment upon or give notice in respect of, any Project Plan submitted by the Contractor, or any other direction, act or omission of the Principal or the Principal‟s Representative, will in any way: (i) relieve the Contractor from, or alter or affect, the Contractor‟s liabilities, obligations or responsibilities whether under the Deed or otherwise according to Law; or (ii) prejudice the Principal‟s rights against the Contractor whether under the Deed or otherwise according to Law. (e) The Contractor must comply with each Project Plan which has been submitted to the Principal‟s Representative and in respect of which the Contractor has not been given a notice under clause 6.4(c). (f) The Contractor will not be relieved from compliance with any of its obligations under the Deed or from any of its liabilities under the Deed or otherwise according to Law as a result of: (i) compliance by the Contractor with its obligations under this clause 6.4, including compliance with any Project Plan; or (ii) any failure by the Principal, or anyone acting on behalf of the Principal, to detect any non-compliance, including where any failure arises from any negligence on the part of the Principal, the Principal‟s Representative or any other person. 34 7 Terms of Payment 7.1 7.2 Payments (a) The Principal must pay to the Contractor the Contract Price in accordance with the procedures set out in this clause 7, Schedule 3 - Commercial Schedules and Schedule 4 - GBR Administration. (b) Work performed pursuant to a Change must be paid for in accordance with the applicable Change and must be invoiced and documented under clause 7.3 as part of the Work under the Deed. Detailed Statement The Contractor must submit to the Principal a cash flow indicating the anticipated value of work to be executed during each month from commencement of any part of the Work under the Deed until Completion at the following times: 7.3 (a) not later than one week after the Commencement Date; and (b) each month following the Commencement Date. Progress Claims (a) At each time identified for a progress claim in Schedule 1 - Contract Information, the Contractor must submit to the Principal‟s Representative a Progress Claim signed by the Contractor‟s Representative which must set out: (i) the value of Work under the Deed completed by the Contractor (subject to the limitations (if any) for the particular work set out in the pricing schedule included in Schedule 3 - Commercial Schedules), to the date of the Progress Claim, detailed against the applicable categories of costs in Schedule 3 - Commercial Schedules; and (ii) the sum of all prior payments made to that date, and be accompanied by the statements, declarations and other documents: (b) (iii) described in clause 7.3(e); and (iv) described in the pricing preamble to the pricing schedule included in Schedule 3 - Commercial Schedules. The Contractor may not include in a Progress Claim under clause 7.3(a) any amount for Materials which have been fabricated or manufactured off-site but which have not been incorporated into the Works, except for Approved Off-Site Materials. The Principal‟s Representative may give written approval for payment to the Contractor for Approved Off-Site Materials, provided the Contractor: (i) ensures that the Approved Off-Site Materials are: 35 (c) (A) in a secured location; (B) properly stored, marked with the names of the Contractor and the Principal, protected and insured; and (C) free from defects, which are discoverable by inspection; (ii) ensures that clear title to the materials, goods or equipment will pass to the Principal upon payment; (iii) indemnifies the Principal against loss of, or damage to, the Approved Off-Site Materials and against any claims by third parties to title in the Approved Off-Site Materials, until they are incorporated into the Works; and (iv) provides the Principal with: (A) an unconditional undertaking in the form of Schedule 9 Form of Unconditional Undertaking, and from a financial institution acceptable to the Principal, equal to the total value of the Approved Off-Site Materials, and (B) evidence reasonably satisfactory to the Principal‟s Representative that the Approved Off-Site Materials have been insured. Within 10 business days of receiving a Progress Claim and the Contractor‟s progress report under clause 15.3 for the relevant month, the Principal‟s Representative must determine the amount payable in respect of the Progress Claim and issue a certificate to the Principal and the Contractor identifying the Progress Claim to which it relates and setting out that determination showing: (i) the Principal‟s Representative‟s assessment of the value of the Work under the Deed completed by the Contractor, after allowing for the cost of rectifying any Defect; (ii) the value of the Work under the Deed completed by the Contractor assessed by the Principal‟s Representative and taken into account in determining the amount certified for payment to the Contractor by the Principal, or to the Principal by the Contractor, in the last certificate issued under this clause 7.3(c); (iii) any moneys which have been set-off or deducted under clause 7.6; (iv) any moneys which are due or which may become due from the Contractor to the Principal in respect of the Deed or the Work under the Deed; and (v) the amount (if any) certified as then being due for payment to the Contractor by the Principal or to the Principal by the Contractor, as the case may be. The Principal‟s Representative must include in or with the certificate, details of the reason for any difference between the amount certified as payable and 36 the amount claimed by the Contractor, including (if applicable) the reason why any payment is being withheld. (d) The Contractor must give the Principal a Valid Tax Invoice in respect of the amount certified as then being due for payment to the Contractor by the Principal plus any amount in respect of GST to which the Contractor is entitled under clause 9.2 within seven business days of receipt of that certificate. (e) The Contractor must give the Principal‟s Representative as part of each Progress Claim under clause 7.3(a), statement under clause 7.4(a) and statement under clause 7.5(a): (f) (g) (i) a duly signed written statement which complies with the Contractor‟s obligations under section 127 of the Industrial Relations Act 1996 (NSW), Schedule 2 Part 5 of the Pay-roll Tax Act 2007 (NSW) and section 175B of the Workers Compensation Act 1987 (NSW) to provide a statement to the “principal contractor” as contemplated by those Acts. At the date of the Deed, a duly completed signed written statement in the approved form set out in Part 1 of Schedule 14 Subcontractors Statement and Statutory Declaration, accompanied by the required certificate of currency, will comply with the requirements of this clause 7.3(e)(i); and (ii) a statutory declaration in the approved form set out in Part 2 of Schedule 14 - Subcontractors Statement and Statutory Declaration that all its Subcontractors have been paid all amounts due and payable to them for work performed by them in respect of the Work under the Deed. Subject to clause 7.9, where an amount is due from the Principal to the Contractor in respect of a certificate issued pursuant to clause 7.3(c), the Principal must pay the Contractor the amount certified as payable by the Principal‟s Representative under clause 7.3(c) by the latest of: (i) the 25th day of the following month after receipt by the Principal‟s Representative of the Progress Claim provided in accordance with clause 7.3(a); (ii) the receipt by the Principal‟s Representative of the Contractor‟s progress report under clause 15.3 for the month the subject of the Progress Claim; (iii) the receipt by the Principal of the evidence required under clause 7.3(b) (where the certificate from the Principal‟s Representative includes payment for Approved Off-Site Materials); (iv) the receipt by the Principal of security under clause 8; and (v) the receipt by the Principal of the evidence of insurance referred to in clause 29. Where an amount is due from the Contractor to the Principal in respect of a certificate issued pursuant to clause 7.3(c), the Contractor must, within 30 37 days after receipt of that certificate, pay the Principal the amount stated in that certificate as due from the Contractor to the Principal. 7.4 Completion Payment (a) Within one month after receipt of the last Completion Certificate under clause 22.2, the Contractor must submit to the Principal‟s Representative a statement for the Contract Price, summarising and reconciling all previous payments made by the Principal and all adjustments in the Contract Price pursuant to the terms of the Deed together with the statements, declarations and other documents described in clause 7.3(e). (b) Within 10 business days of receiving a statement under clause 7.4(a), the Principal‟s Representative must determine the amount payable in respect of the Contractor‟s statement and issue a certificate to the Principal and the Contractor identifying the statement to which it relates and setting out that determination showing: (i) the Principal‟s Representative‟s assessment of the value of the Work under the Deed completed by the Contractor, after allowing for the cost of rectifying any Defect; (ii) the value of the Work under the Deed completed by the Contractor assessed by the Principal‟s Representative and taken into account in determining the amount certified for payment to the Contractor by the Principal, or to the Principal by the Contractor, in the last certificate issued under clause 7.3(c); (iii) any moneys which have been previously set-off or deducted under clause 7.6; (iv) any moneys which are due or which may become due from the Contractor to the Principal in respect of the Deed or the Work under the Deed; and (v) the amount (if any) certified as then being due for payment to the Contractor by the Principal or to the Principal by the Contractor, as the case may be. The Principal‟s Representative must include in or with the certificate, details of the reason for any difference between the amount certified as payable and the amount claimed by the Contractor, including (if applicable) the reason why any payment is being withheld. (c) The Contractor must give the Principal a Valid Tax Invoice in respect of the amount certified as then being due for payment to the Contractor by the Principal plus any amount in respect of GST to which the Contractor is entitled under clause 9.2 within seven business days of receipt of that certificate. (d) Subject to clause 7.9, where an amount is due from the Principal to the Contractor in respect of a certificate issued pursuant to clause 7.4(b), the Principal must pay the Contractor the amount certified as payable by the Principal‟s Representative under clause 7.4(b) by the latest of: 38 (e) 7.5 (i) the 25th day of the following month after receipt by the Principal‟s Representative of the Contractor‟s statement under clause 7.4(a); (ii) the receipt by the Principal‟s Representative of the written statement and statutory declaration referred to in clause 7.3(e); (iii) the receipt by the Principal‟s Representative of the Contractor‟s progress report under clause 15.3 for the month the subject of the Contractor‟s statement under clause 7.4(a); (iv) the receipt by the Principal of security under clause 8; and (v) the receipt by the Principal of the evidence of insurance referred to in clause 29. Where an amount is due from the Contractor to the Principal in respect of a certificate issued pursuant to clause 7.4(b), the Contractor must, within 30 days after receipt of that certificate, pay the Principal the amount stated in that certificate as due from the Contractor to the Principal. Final Payment (a) Within one month of the expiry of the last Defects Correction Period under the Deed to expire, the Contractor must submit to the Principal‟s Representative a statement endorsed as its “Final Statement” setting out any amounts claimed by the Contractor under the Deed or otherwise arising out of or in connection with the Work under the Deed together with the statements, declarations and other documents described in clause 7.3(e). (b) Any claims or actions whatsoever which the Contractor may have which are not included in the Final Statement under clause 7.5(a), whether in contract, tort, equity, under statute or otherwise, under or arising out of or in connection with the Deed, will be released and forever discharged upon the expiry of the time stipulated in clause 7.5(a) for the Contractor to lodge its Final Statement. (c) The Principal‟s Representative may, within five business days of receipt of the Final Statement, request further substantiating information of any claim in the Final Statement and the Contractor must provide such information within three business days of the Principal‟s Representative‟s request. (d) The Principal‟s Representative may issue a Final Payment Certificate at any time after the time for the Contractor to submit the Final Statement (whether or not the Contractor has submitted a Final Statement). If the Contractor has submitted the Final Statement, the Principal‟s Representative must issue the Final Payment Certificate within the later of: (i) 10 business days after the Contractor has submitted the Final Statement; and (ii) receipt by the Principal of a duly executed deed of release (in a form acceptable to the Principal) from the Contractor stating that it releases the Principal from and against any and all claims under or arising out of or in connection with the Deed which may be brought 39 by the Contractor against the Principal or any of its employees, agents, consultants, successors or assignees. (e) The Final Payment Certificate must state: (i) the Contract Price adjusted according to the provisions of the Deed; (ii) any moneys which have been previously set-off or deducted under clause 7.6; (iii) any moneys which are due or which may become due to the Principal in respect of the Deed or the Work under the Deed; and (iv) the amount certified as then being due for payment to the Contractor by the Principal or to the Principal by the Contractor, as the case may be. The Principal‟s Representative must include in or with the certificate, details of the reason for any difference between the amount certified as payable and the amount claimed by the Contractor in its Final Statement, including (if applicable) the reason why any payment is being withheld. (f) The Contractor must give the Principal a Valid Tax Invoice in respect of the amount certified as then being due for payment to the Contractor by the Principal plus any amount in respect of GST to which the Contractor is entitled under clause 9.2 within seven business days of receipt of that certificate. (g) Subject to clause 7.9, where an amount is due from the Principal to the Contractor in respect of the Final Payment Certificate, the Principal must pay the Contractor the amount stated in the Final Payment Certificate as due from the Principal to the Contractor on the later of: (h) 7.6 (i) the 25th day of the following month after the issue of the Final Payment Certificate; or (ii) the receipt by the Principal‟s Representative of the written statement and statutory declaration referred to in clause 7.3(e). Where an amount is due from the Contractor to the Principal in respect of the Final Payment Certificate, the Contractor must, within one month after the issue of the Final Payment Certificate, pay the Principal the amount stated in the Final Payment Certificate as due from the Contractor to the Principal. Set Off The Principal may deduct or set off from: (a) any payments due to the Contractor under the Deed (including any amounts certified by the Principal‟s Representative); and (b) the amount available to the Principal if it exercises its rights under the security (whether in the form of unconditional undertakings or retention moneys) referred to in clause 8, 40 any moneys due or which may become due from the Contractor to the Principal, whether under the Deed or otherwise (unless they have already been included in a Principal‟s Representative‟s determination under clauses 7.3(b), 7.4(b) or 7.5(d)) including the liquidated damages referred to in clause 25 and, where the Contractor has failed to rectify any Defect of which the Principal has given reasonable notice to the Contractor, the reasonable costs of rectifying that Defect. Such amount of reasonable costs (less any amounts actually expended by the Principal) must be paid to the Contractor in future progress payments if the Contractor rectifies the Defect. 7.7 Nature of Payments No payment by the Principal to the Contractor will be taken to be acceptance of any work undertaken by the Contractor or evidence of the value of work or an admission of liability on the part of the Principal, and all payments other than the Final Payment will be payment on account only. 7.8 No adjustment to Contract Price for rise and fall The Contract Price, and the rates and lump sums it includes, are not subject to change for rise and fall including: (a) for exchange rates; (b) in the cost of labour or materials provided by the Contractor; or (c) for new, changed or increased taxes or duties, unless expressly stated in the Deed. 7.9 Payment Withholding Request Without limiting clause 7.6, the Principal and the Contractor acknowledge and agree that where: (a) the Principal receives a Payment Withholding Request from a Subcontractor; and (b) the Principal withholds, from any one or more payments of the Contract Price and/or any other payments under the Deed, the amount set out in the Payment Withholding Request, then: (c) the Principal's withholding of any payment or amount referred to in clause 7.9(b) shall not be a breach of the Deed; (d) subject to clause 7.9(e), the Principal will not be liable in respect of any claim or action whatsoever by the Contractor arising out of or in connection with the Principal's withholding of any payment or amount referred to in clause 7.9(b), including any claim or action for interest on such payment or amount; and (e) clause 7.9(d) does not apply to any right, claim or action by the Contractor arising under the Building and Construction Industry Security of Payment Act 1999 (NSW). 41 8 Security 8.1 If it has not done so before the date of the Deed, on the date of the Deed the Contractor must provide to the Principal five unconditional undertakings for the amounts specified in Schedule 1 - Contract Information in the form in Schedule 9 Form of Unconditional Undertaking and from a financial institution acceptable to the Principal, as security for the performance of its obligations under the Deed. 8.2 Before the Contractor is entitled to make a claim for payment in respect of any portion of Items 2.3 – 2.6 (inclusive) of the Pricing Schedule included in Schedule 3 - Commercial Schedules, the Contractor must provide to the Principal an unconditional undertaking for the amount specified in Schedule 1 - Contract Information and in the form in Schedule 9 - Form of Unconditional Undertaking and from a financial institution acceptable to the Principal, as security for the performance of the Contractor‟s obligations under the Deed in respect of the procurement and installation of the TBM. 8.3 The Contractor may by written notice to the Principal request permission to substitute any form of security required under this clause 8. The Principal may, in its absolute discretion, accept or reject the request. If permission is granted, to the extent another form of security is provided by the Contractor, the Principal must promptly release and return the original security. 8.4 Subject to clause 8.5, the Principal must: (a) (b) in respect of the security referred to in clause 8.1: (i) release one of the unconditional undertakings for the value of 0.5% of the Contract Price within 10 days after the Date of Substantial Completion of Separable Portion 1; (ii) release one of the unconditional undertakings for the value of 0.5% of the Contract Price within 10 days after the Date of Substantial Completion of Separable Portion 2; (iii) release the unconditional undertaking for the value of 3% of the Contract Price within 10 days after the Date of Practical Completion of Separable Portion 3; (iv) release one of the unconditional undertakings for the value of 0.5% of the Contract Price within one month after the expiry of the last Defects Correction Period; and (v) release one of the unconditional undertakings for the value of 0.5% of the Contract Price within one month after the issue of the Final Payment Certificate; in respect of the security referred to in clause 8.2, release the unconditional undertaking within 10 days after the TBM has been installed on the Site and the Contractor has provided the Principal with evidence reasonably satisfactory to the Principal‟s Representative that: (i) the TBM has passed all acceptance testing required under the Deed; 42 (c) 8.5 (ii) title to the TBM has passed to the Contractor; and (iii) the TBM has been insured by the Contractor for the full reinstatement value of the TBM; and in respect of any security provided by the Contractor pursuant to clause 7.3(b)(iv)(A), release the unconditional undertaking within 10 days after all of the relevant materials have been incorporated into the Works. The Principal may have recourse to the security: (a) (b) referred to in clause 8.1: (i) at any time where it reasonably believes that the Contractor has not duly and properly performed any of its obligations under the Deed; or (ii) to recover any moneys which become payable from the Contractor to the Principal, under or in connection with the Deed including any liability of the Contractor for liquidated damages, pursuant to the indemnities given under clause 28.1 or pursuant to any cause of action which the Principal may have against the Contractor whether for breach of contract, in tort, under statute or otherwise. The Principal will have no obligation to release any security for so long as the Contractor has any liability to the Principal (whether actual or contingent) of which the Principal has given notice to the Contractor and which equals or exceeds the value of the security; referred to in clause 8.2, at any time where it reasonably believes the Contractor: (i) has not duly and properly performed any of its obligations as contemplated by clause 8.4(b); or (ii) is unable to demonstrate to the Principal‟s Representative‟s reasonable satisfaction that it is able to install the TBM on the Site within a reasonable time after the date identified in the Contract Programme for the installation and commissioning of the TBM on the Site; and (c) referred to in clause 7.3(b)(iv)(A), at any time where it reasonably believes the Contractor has not duly and properly performed any of its obligations as contemplated by clause 7.3(b). (a) The Contractor must not take any steps whatever to: 8.6 (i) injunct the issuer of the unconditional undertakings referred to in clauses 8.1, 8.2 and 7.3(b)(iv)(A) or the Principal in respect of dealing with those unconditional undertakings; or (ii) restrain the Principal from exercising its rights under the unconditional undertakings referred to in clause 8.1, 8.2 and 7.3(b)(iv)(A). 43 (b) (c) 8.7 9 The Principal: (i) is not obliged to pay the Contractor interest on the proceeds of the unconditional undertakings referred to in clauses 8.1, 8.2 and 7.3(b)(iv)(A) if any of them is converted into cash; and (ii) does not hold the proceeds of any unconditional undertakings on trust for the Contractor. The Contractor is responsible for all stamp duty (including penalties, if applicable) payable in connection with: (i) the unconditional undertakings provided by the Contractor under clauses 8.1, 8.2 and 7.3(b)(iv)(A); and (ii) any demands made on those unconditional undertakings. If the Contractor is a subsidiary (as defined in the Corporations Act), and it has not done so prior to the date of the Deed, on the date of the Deed the Contractor must provide to the Principal a parent company guarantee and indemnity in the form set out in Schedule 15 - Guarantee and Indemnity, duly executed by the Contractor‟s parent company (the “Guarantor”) for the performance of the obligations and the discharge of the liabilities of the Contractor under the Deed. Taxes 9.1 Except as otherwise specifically provided in the Deed, the Contractor must bear and pay all present Taxes (other than GST) in connection with the Deed and the execution of the Work under the Deed. 9.2 If any supply made under the Deed is, or becomes, subject to GST, the party to whom the supply is made (“Recipient”) must pay to the party making the supply (“Supplier”), as consideration, in addition to any consideration payable or to be provided elsewhere in the Deed, subject to issuing a Valid Tax Invoice, an additional amount on account of GST, such amount to be calculated by multiplying the consideration by the applicable rate of GST. 9.3 Any amount in respect of GST payable under clause 9.2 must be paid to the Supplier by the 21st day of the month following the month in which the Recipient receives the Valid Tax Invoice. 9.4 If any party is required to reimburse or indemnify the other party for a cost or expense (“Cost”) incurred by the other party, the amount of that Cost for the purpose of the Deed is the amount of the Cost incurred, less the amount of any input tax credit or refund of GST, which the party incurring the Cost is entitled to claim in respect of the Cost. 9.5 If GST is linked with the abolition or reduction of other taxes and charges, all amounts payable by the Recipient to the Supplier under the Deed (excluding GST) must be reduced by the same proportion as the actual total costs of the Supplier (excluding GST) are reduced either directly as a result of the abolition or reduction of other taxes and charges payable by the Supplier or indirectly by way of any reduction in prices (excluding GST) charged to the Supplier. 44 9.6 10 Unless otherwise expressly stated, all prices or other sums payable or consideration to be provided under the Deed are exclusive of GST. Security of Payment Act 10.1 The Contractor must: (a) (b) promptly give the Principal and the Principal‟s Representative a copy of any notice the Contractor: (i) receives from a Subcontractor under section 15, 16 or 24 of the Security of Payment Act; or (ii) has been required to supply to a Subcontractor under section 15(1) of the Contractors Debts Act 1997 (NSW) setting out the Principal‟s name; and promptly notify the Principal and the Principal‟s Representative if it becomes aware that a Subcontractor intends to exercise a statutory lien, under section 11(3) of the Security of Payment Act, over unfixed Materials or Construction Plant supplied by the Subcontractor for use in carrying out work forming part of the Work under the Deed. 10.2 If the Principal becomes aware that a Subcontractor is entitled to suspend work under section 27 of the Security of Payment Act, the Principal may pay the Subcontractor such money that is, or may be, owing to the Subcontractor for work forming part of the Work under the Deed and the Principal may recover any amount so paid for the Contractor as a debt. 10.3 The Contractor must indemnify the Principal against any loss, expense or damage of any nature, including financial loss and lawyers‟ fees and expenses on an indemnity basis, suffered or incurred by the Principal arising out of: 10.4 (a) a suspension by a Subcontractor of work, which forms part of the Work under the Deed, under section 27 of the Security of Payment Act; (b) a notice of claim being served on the Principal under Part 2 of the Contractors Debts Act 1997 (NSW); (c) a Subcontractor exercising a statutory lien, under section 11(3) of the Security of Payment Act, over unfixed Materials or Construction Plant supplied by the Subcontractor for use in carrying out work forming part of the Work under the Deed; and (d) a failure by the Contractor to comply with clause 10.1(a). Any payment claim under section 13 of the Security of Payment Act the Contractor serves on the Principal, and any notice required to be served on, or copy of an adjudication application required to be copied to, the Principal by the Contractor under any provision of the Security of Payment Act, must be addressed to the address and to the attention of the Authorised Representative of the Principal. 45 10.5 11 For the purposes of this clause 10, work refers to work which the Contractor is, or may be, required to do under the Deed and includes Materials, design and other services and temporary works. Intellectual Property Rights 11.1 11.2 Vesting of Intellectual Property Rights (a) All Intellectual Property Rights created, discovered, or coming into existence as a result of, for the purposes of, or in connection with the performance of the Work under the Deed in accordance with the Deed will be vested in and owned by the Principal upon their creation, discovery or coming into existence and the Contractor must do all things necessary to ensure that the Principal has the benefit of and unencumbered title to such Intellectual Property Rights. (b) If anything referred to in clause 11.1(a) cannot be immediately transferred to or vested in the Principal, the Contractor must ensure that the Principal is provided with an unrestricted, non-exclusive, irrevocable (in whole or in part) and royalty-free licence (whether by sub-licence from the Contractor or direct licence from the owner of those Intellectual Property Rights) to use, and to grant rights to third parties to use, those Intellectual Property Rights. Non-exclusive licence The Contractor grants to the Principal an unrestricted, non-exclusive, irrevocable (in whole or in part) and royalty-free licence to use the Intellectual Property Rights in anything owned or developed by the Contractor prior to the date of the Deed for the purposes of executing, using, operating or maintaining the Works. 11.3 Infringement of Intellectual Property Rights Each party must inform the other immediately upon becoming aware of any infringement or threatened infringement of any Intellectual Property Rights. The parties agree to co-operate with each other by doing all acts and things which the party owning such Intellectual Property Rights may reasonably require in respect of any infringement or threatened infringement. 11.4 Moral Rights The Contractor must procure from any person (including each of its relevant employees and relevant employees of its Subcontractors) who is an author (in this clause called “author”) of any copyright work forming part of the documentation produced by or on behalf of the Contractor as part of the Work under the Deed (in this clause called “material”) which is assigned or licensed to the Principal under the Deed, and (to the extent the Contractor itself has any Moral Rights as an author of such material) hereby itself grants: (a) to the extent permitted by law, an unconditional and irrevocable waiver of all Moral Rights in respect of such material to which the author may be or become entitled, whether in Australia or overseas; and (b) consent in writing authorising: 46 (i) the Principal; (ii) the Principal‟s licensees and successors in title; and (iii) any other person authorised by the Principal or by such a licensee or successor in title, to exercise in accordance with the Deed all acts comprised in the copyright in the material including the use, dealing, reproduction, modification, distortion, abridgement, revision, retitling, transmission, publication, exhibition, adaptation or translation into other dimensions, format or media of that material: (iv) without attribution of authorship to the author; (v) bearing the name of the Project, the Contractor, the Principal, the Principal‟s Representative, or any other person associated with the Project; (vi) even if it results in “derogatory treatment” which may be prejudicial to the author‟s honour or reputation; and (vii) by changing, relocating, demolishing or destroying any three dimensional reproduction of that material without notice to or consultation with the author, and the Contractor must ensure that the consent and waiver is genuinely given and not obtained by duress or by the making of any false or misleading statement. The Contractor must produce all consents and waivers to the Principal‟s Representative upon receipt of a direction to do so. 11.5 Survival of Obligations The obligations in this clause 11 will continue notwithstanding completion, termination or any other discharge of the Deed. 12 Confidential Information 12.1 The Contractor must ensure that all Confidential Information is kept confidential and must not disclose directly or indirectly any Confidential Information to a third party without the prior approval of the Principal, provided that the foregoing provisions will not apply to Confidential Information which: (a) was in the Contractor‟s possession prior to the date of the Deed except where the Confidential Information was provided directly or indirectly by the Principal or which is the subject of a confidential obligation between the parties; or (b) becomes generally available to the public or is in the public domain; or (c) is required to be produced by order of the Court or under the requirements of any applicable Law; or (d) is obtained from a third party without an obligation of confidentiality. 47 13 12.2 The Contractor must not use any Confidential Information received from the Principal for any purpose other than the performance of the Work under the Deed and its obligations under the Deed. 12.3 The Contractor may disclose Confidential Information: (a) as required or authorised by any Law; and (b) as required by the listing rules of any stock exchange where the Contractor‟s securities are listed or quoted. 12.4 The obligation imposed upon the Contractor not to disclose Confidential Information will not cease on the completion, expiry, or termination of the Deed or any other discharge of the Deed. 12.5 Except as contemplated by clause 12.7, the Contractor must not, and must ensure its Subcontractors and other parties employed directly or indirectly by the Contractor do not, release or disclose to the media any information relating to the Work under the Deed. 12.6 All media requests received by the Contractor must be directed to the Principal for consideration. 12.7 Where the Contractor considers a media release is required, the Contractor must submit the details and a draft to the Principal for consideration and/or approval. Details to be included in such a submission are the media name, contact name, telephone number, facsimile number and electronic address, as applicable. Representatives 13.1 Principal’s Representative (a) Within seven days of the date of the Deed, the Principal must appoint and notify the Contractor of the name of the Principal‟s Representative. The Principal may from time to time appoint some other person as the Principal‟s Representative in place of the person previously so appointed and must give a notice of the name of such other person to the Contractor without delay. Such appointment will only take effect upon receipt of such notice by the Contractor. The Principal‟s Representative must represent and act for the Principal at all times during the currency of the Deed. All notices, instructions, information and other communications to be given by the Contractor to the Principal under the Deed must be given to the Principal‟s Representative, except as otherwise provided. (b) The Principal‟s Representative may at any time delegate to any person any of the powers and duties vested in him or her. Any such delegation may be revoked at any time. Any such delegation or revocation will be subject to a prior notice signed by the Principal‟s Representative and any notice of delegation or revocation must specify the powers and duties thereby delegated or revoked. Such delegation or revocation will become valid upon receipt of such notice by the Contractor. 48 Any act or exercise by any person of powers and duties delegated to him or her in accordance with this clause 13.1(b) will be deemed to be an act or exercise by the Principal‟s Representative. 13.2 (c) The Principal‟s Representative will carry out his or her functions under the Deed as the agent of the Principal (and not as an independent certifier, assessor or valuer). (d) If pursuant to a provision of the Deed enabling the Principal‟s Representative to give directions, the Principal‟s Representative gives a direction, the Contractor must comply with that direction. (e) Except where the Deed otherwise provides, the Principal‟s Representative may give a direction orally but must as soon as practicable confirm it in writing. If the Contractor in writing requests the Principal‟s Representative to confirm an oral direction, the Contractor will not be bound to comply with the direction until it is confirmed in writing by the Principal‟s Representative. Contractor’s Representative and Site Representative (a) The Contractor has appointed the person so specified in Schedule 1 Contract Information as the Contractor‟s Representative who at all times during the currency of the Deed has authority to act on behalf of the Contractor in respect of the Deed. (b) All notices, instructions, information and all other communications by the Principal to the Contractor under the Deed must be given to the Contractor‟s Representative, except as otherwise provided in the Deed. (c) The Contractor‟s Representative may at any time delegate to any person any of the powers, functions and authorities vested in him or her. Any such delegation may be revoked at any time. Any such delegation or revocation will be subject to a prior notice signed by the Contractor‟s Representative and any notice of delegation or revocation must specify the powers, functions and authorities delegated or revoked. No such delegation or revocation will take effect unless and until the Principal has received such notice. Any act or exercise by any person of powers, functions and authorities so delegated to him or her in accordance with this clause 13.2(c) will be deemed to be an act or exercise by the Contractor‟s Representative. The Contractor must ensure that any delegate notified to the Principal under this clause 13.2(c) is not replaced without the prior approval of the Principal. (d) From the commencement of the Work under the Deed at the Site until Completion, the Contractor‟s Representative must appoint suitable persons as the Site Representatives. The Site Representatives must supervise all work done at the Site by the Contractor and must be present at the Site throughout working hours except when on leave, sick or absent for reasons connected with the proper performance of the Work under the Deed. Whenever a Site Representative is absent from the Site, a suitable person must be appointed to act as his or her deputy. 49 The Principal or the Principal‟s Representative must give all notices, instructions, information and other communications pertaining to the execution of the Work under the Deed at the Site to the relevant Site Representative or, in his or her absence, his or her deputy. A notice given by the Principal or the Principal‟s Representative under this clause 13.2(d) will be deemed to be a notice to the Contractor‟s Representative for the purposes of clause 13.2(b). 14 15 Contractor’s Organisation 14.1 On or before the Commencement Date, the Contractor must supply to the Principal an organisation chart showing the proposed organisation to be established by the Contractor for carrying out the Work under the Deed, including the Contractor‟s Key Personnel specified in Schedule 6 - Key Personnel. 14.2 The Contractor must not remove or replace any members of the Key Personnel without the prior approval of the Principal‟s Representative, which approval must not be unreasonably withheld. Any substitute personnel proposed by the Contractor must at least be equally qualified for the duties of the position as the persons for whom they are substituted. 14.3 The Contractor must promptly give to the Principal‟s Representative notice of any replacement personnel for persons identified by name in the Contractor‟s organisation chart. The Principal may make reasonable objection to any proposed replacement personnel, in which case the Contractor must substitute a person to whom the Principal has no objection. 14.4 The Principal‟s Representative may direct the Contractor to remove from the Site, or from any activity connected with the Deed or the Work under the Deed, any person who, in the opinion of the Principal‟s Representative, is guilty of misconduct or is incompetent or negligent or is otherwise interfering with the orderly progress of the Work under the Deed or any other work on, or in the vicinity of, the Site or in connection with the Deed. Any person so removed may not be subsequently engaged in any activity concerned with the Deed or the Work under the Deed without the prior written approval of the Principal‟s Representative. Contract Programme 15.1 Contract Programme (a) The Contractor must: (i) carry out the Work under the Deed in accordance with; and (ii) comply with the requirements of clause 1.2.6 of the Specification in respect of, the Contract Programme. (b) The Contractor must revise the Contract Programme in accordance with the requirements of the Deed, including the Specification, and must submit all such revisions to the Principal‟s Representative. No revision of the Contract 50 Programme will amend any dates specified in the Deed (including the Date for Substantial Completion, the Date for Practical Completion and the Date for Completion) except to take account of approved extensions of time. 15.2 Project Control Group (a) The Project Control Group comprises the representatives of the Principal and the Contractor referred to in clause 1.2.3 of the Specification. (b) The Contractor, when the Principal‟s Representative requires, must ensure that representatives of Subcontractors attend Project Control Group meetings. (c) The Project Control Group must meet: (i) fortnightly for the first three months during the currency of the Deed; and (ii) monthly thereafter until Practical Completion; and (iii) at other times as agreed between the parties, at times and at a place to be nominated by the Principal‟s Representative. (d) 15.3 The Principal‟s Representative must: (i) convene and chair all meetings of the Project Control Group; (ii) take minutes of all meetings held by the Project Control Group; (iii) not later than four days after a meeting held by the Project Control Group, provide a copy of those minutes to the Contractor‟s Representative who must, if he or she accepts them as accurate, notify the Principal‟s Representative as soon as practicable of their acceptance (upon which notification such minutes become the official record of the relevant meeting, or if the Contractor‟s Representative fails to notify the Principal‟s Representative within 10 days of receipt of such minutes whether he or she accepts them as accurate, those minutes will be deemed to be the official record of the relevant meeting); (iv) if the Contractor‟s Representative disagrees with those minutes, discuss and amend the minutes to reflect the agreed position (upon which amendment such minutes become the official record of the relevant meeting); and (v) give to the Project Control Group members a copy of those minutes if the minutes are accepted by the Contractor‟s Representative or deemed to be the official record of the relevant meeting under clause 15.2(d)(iii), or are agreed by the Principal‟s Representative and the Contractor‟s Representative under clause 15.2(d)(iv). Reporting On the first Tuesday of each month, for the period from the date of the Deed and until Practical Completion, the Contractor must submit to the Principal‟s 51 Representative a progress report prepared by a suitably qualified person acceptable to the Principal‟s Representative in a form agreed between the Contractor and the Principal‟s Representative or otherwise as reasonably required by the Principal‟s Representative. The progress report must indicate and include: (a) percentage completion achieved compared with the planned percentage completion for each activity on the Contract Programme; (b) actual and planned progress shown against the Contract Programme; (c) where any activity is behind the Contract Programme, the likely consequences and stating the corrective action being taken; (d) a general report on the status of the Work under the Deed; (e) information of all critical aspects influencing the progress of the Work under the Deed; (f) any foreseen delays to future activities on the Contract Programme; (g) the likely effect on the Contract Programme of any actual or foreseen delays; (h) current claims for extensions of time, including details of dates submitted, dates determined and any other details the Principal‟s Representative requires; (i) the forecast Date of Substantial Completion of Separable Portions 1 and Separable Portion 2 and the forecast Date of Practical Completion of Separable Portion 3; (j) a summary of all Changes including approved Changes and proposed Changes (separately and individually identified); (k) a forecast completion cost of the Works; (l) key actions to be undertaken by the Principal or others under the Deed; (m) details of all Subcontractors currently engaged or proposed to be engaged by the Contractor; (n) details of daily staff levels of the Contractor and all Subcontractors on the Site including all activities, locations and hours of work of those staff; (o) details of Construction Plant used in connection with the carrying out of Work under the Deed, including whether in use, on standby, or under or awaiting maintenance; (p) details of safety-related issues including all lost-time injuries records; (q) evidence of compliance with the quality management requirements of the Deed; (r) evidence of compliance with the environmental management requirements of the Deed; 52 (s) a summary of community consultation issues including details of public complaints and corrective actions; (t) expenditure against predicted cash flow and budget; (u) revised cashflow based on the Contract Programme; (v) industrial relations issues affecting or which may affect the Work under the Deed; (w) any other matters required by the Principal‟s Representative. Within 2 business days after the end of each week for the period from the date of the Deed and until Practical Completion, the Contractor must submit to the Principal‟s Representative a report prepared by a suitably qualified person acceptable to the Principal‟s Representative, in a form agreed between the Contractor and the Principal‟s Representative or otherwise as reasonably required by the Principal‟s Representative. This report must include details of: (x) each Unit of ground conditions the Contractor has encountered working at the tunnel face; (y) the actual length of ground conditions encountered in each category of Typical Conditions, Adverse Conditions and Materially Adverse Conditions; (z) water inflow into the Tunnel, including adjustments for spoil moisture; and (aa) any other matters relevant to the procedures included in the Deed (including in Schedule 4 - GBR Administration and the Specification) for the classification and measurement of ground conditions encountered by the Contractor. The Contractor must advise the Principal‟s Representative (in writing if the Principal‟s Representative requires and within the time specified by the Principal‟s Representative) of suitable courses of action in relation to matters raised in Project Control Group meetings. The Contractor must establish and maintain any records and registers which the Principal‟s Representative reasonably requires. 15.4 Progress of Work under the Deed If at any time in the opinion of the Principal the Contractor‟s actual progress falls behind the Contract Programme, or it becomes apparent that it will fall behind, and the Contractor is not entitled to an extension of time under clause 34, the Contractor must: (a) take all necessary steps (at its own cost) to mitigate the effects of any delay; and (b) notify the Principal of the steps being taken to expedite progress, so as to achieve Substantial Completion by the Date for Substantial Completion, Practical Completion by the Date for Practical Completion and Completion by the Date for Completion. 53 16 Subcontracts 16.1 Subcontracting (a) Except for subcontracting the works specified in Schedule 8 - Approved Subcontractors to the Subcontractors specified in Schedule 8 - Approved Subcontractors, the Contractor must not subcontract any part of the Work under the Deed which has a value of greater than $100,000 without the written approval of the Principal‟s Representative. (b) With a request for approval, the Contractor must provide to the Principal‟s Representative full particulars in writing of the part of the Work under the Deed to be subcontracted and the name and address of the proposed Subcontractor. The Contractor must promptly give the Principal‟s Representative any information requested by the Principal‟s Representative (including an unpriced copy of the relevant subcontract) to enable it to consider any request for approval from the Contractor to appoint a Subcontractor. (c) The Contractor must ensure that all subcontracts for the Work under the Deed adequately address all industrial relations, safety, environmental and programming issues relevant to the Work under the Deed. (d) The Contractor must manage the performance of each Subcontractor to ensure the quality and timeliness of its performance meet the requirements of the Deed for the Work under the Deed. (e) The Contractor must ensure that each subcontract entered into by the Contractor contains: (f) (i) a covenant (in a form acceptable to the Principal) which will entitle the Contractor to novate the subcontract to the Principal, at no cost to the Principal; (ii) a covenant (in a form acceptable to the Principal) which will entitle the Guarantor (as that term is defined in clause 8.7) to novate the subcontract in its favour, at no cost to the Guarantor, for the purpose referred to in clause 5(b) of the form of guarantee and indemnity in Schedule 15 - Guarantee and Indemnity; and (iii) a term which: (A) requires the Subcontractor to provide to the Principal any warranties specified in the Deed and other types of warranties normally provided by subcontractors for work similar to the part of the Work under the Deed subcontracted; and (B) ensures that the Principal obtains the benefit of the warranties referred to in clause 16.1(e)(iii)(A). The Contractor: 54 (g) 16.2 (i) irrevocably and severally appoints (for valuable consideration) the Principal and the Authorised Representative of the Principal to be the Contractor‟s attorney to execute, sign, seal and deliver all notices, deeds and documents for the purpose referred to in clause 16.1(e); and (ii) ratifies anything done by an attorney or its delegate in accordance with this clause 16.1(f). The Contractor must ensure that the Principal obtains the benefit of the warranties referred to in clause 16.1(e)(iii)(A) on or before the Date of Completion. Responsibility The Contractor‟s obligations under the Deed are not lessened or otherwise affected by subcontracting the performance of those obligations. The Contractor will be liable to the Principal for the acts and omissions of Subcontractors and employees and agents of Subcontractors, as if they were acts or omissions of the Contractor. 17 Design 17.1 Documents comprising the Deed (a) (b) 17.2 Without limiting clause 2, the Contractor warrants that, prior to entering into the Deed: (i) it checked the documents comprising the Deed; and (ii) subject to clauses 4.1A and 17.1(b), there are no ambiguities, inconsistencies or discrepancies in any documents comprising the Deed which would be reasonably discoverable by an appropriately qualified and experienced professional designer, engineer and constructor with experience in designing, engineering and constructing facilities of a similar size, type, nature and complexity of the Work under the Deed. The parties acknowledge and agree that the Contractor is not responsible for detailed design review and verification of the design of those parts of the Work under the Deed for which the Principal has design responsibility under the Deed. Contractor’s Documents (a) The Contractor must carry out all necessary design to complete the design of those parts of the Work under the Deed for the design of which it is responsible under the Deed and produce Contractor‟s Documents which meet the requirements of all of the following: (i) the Deed; (ii) Principal‟s instructions; (iii) Law (including Government Approvals); 55 17.3 (iv) the Building Code of Australia and relevant international and Australian Standards described in the Specification; and (v) if no other standard is specified in the Deed, then Best Industry Practices. (b) The Contractor must not change the Principal‟s design in the Deed without the Principal‟s prior written approval. Whenever requested by the Principal, the Contractor must promptly confirm in writing that the Contractor‟s Documents are consistent with and comply with the Deed. If the Principal‟s design is required to be changed (with the Principal‟s prior written approval), the Change must be dealt with under the procedures in clause 33. (c) The Contractor must produce the Contractor‟s Documents to ensure that the design of those parts of the Work under the Deed for the design of which it is responsible under the Deed fulfils the requirements of the Deed and is suitable for its intended purpose. Submitting Contractor’s Documents (a) The Contractor must submit Contractor‟s Documents (as developed progressively and in stages, but so that each part is complete and in sufficient detail to explain what is proposed) to the Principal at least 21 days before the date the Contractor proposes to use them for construction (including procurement, manufacture or fabrication) of any part of the Work under the Deed. (b) The Contractor must, in respect of all Contractor‟s Documents: (i) develop and complete the Contractor‟s Documents to the standards required by the Deed for the proper completion of the Work under the Deed; (ii) ensure that all Contractor‟s Documents are prepared by employees or Subcontractors with appropriate professional qualifications; and (iii) ensure that it obtains all relevant Government Approvals in respect of Contractor‟s Documents. (c) The Contractor is responsible for and must bear the cost of any expenses arising out of any discrepancies, errors or omissions in the specifications, drawings and other technical documents prepared by it. (d) The Principal‟s Representative may (but is not obliged to) comment on any Contractor‟s Documents. Review of any Contractor‟s Documents by the Principal‟s Representative in accordance with the Deed is solely to monitor the performance of the Contractor. The Contractor is solely responsible for carrying out all design to complete the design of those parts of the Work under the Deed for the design of which it is responsible under the Deed and to produce the Contractor‟s Documents in accordance with the Deed and (unless a Change is directed under clause 33) is not entitled to any extensions of time or delay costs arising out of such comments. (e) The Principal‟s Representative may give a written notice to the Contractor stating that the Contractor‟s Documents submitted for its review do not meet 56 the requirements of the Deed and must where practicable give notice of any objections prior to the Contractor‟s Documents being used for construction. 17.4 (f) If the Principal‟s Representative notifies the Contractor in accordance with clause 17.3(e), the Contractor must revise the Contractor‟s Documents so as to comply with the requirements of the Deed and resubmit the document to the Principal‟s Representative and clauses 17.3(d) to 17.3(f) apply again. (g) The Principal is not liable for the costs of orders placed or work commenced by the Contractor before the review of the Contractor‟s Documents by the Principal‟s Representative is complete and nothing the Principal does, or omits to do, in connection with clause 17 makes the Principal liable for Contractor‟s Documents, or prevents the Principal from relying on or enforcing a right, under the Deed or otherwise. Codes and standards Wherever references are made in the Deed to codes and standards in accordance with which the Work under the Deed must be executed, the Contractor must comply with the latest edition or the latest revised version of such codes and standards unless otherwise specified in the Deed. 18 Procurement 18.1 Materials and Construction Plant The Contractor must procure and transport to the Site all the Materials and Construction Plant in an expeditious and orderly manner in accordance with the Contract Programme. 18.2 Title to Materials Except where expressly provided to the contrary in the Deed, title to all Materials and other items and assets intended to form, or forming, part of the Work under the Deed, will pass to the Principal upon the earlier of: 18.3 (a) the delivery of such Materials or other items or assets to the Site; and (b) payment by the Principal (either in part or in full) for such Materials or other items or assets. Removal of Materials, Construction Plant and temporary works (a) Subject to clause 18.3(b), all Materials, Construction Plant and temporary works provided by the Contractor will, when brought onto the Site, be deemed to be exclusively intended for the execution of the Work under the Deed and the Contractor must not remove the same or any part of them, except for the purpose of moving it from one part of the Site to another, without the written consent of the Principal‟s Representative. (b) The written consent of the Principal‟s Representative is not required for vehicles engaged in transporting any staff, labour, Materials, Construction Plant and temporary works to and from the Site. 57 (c) The Principal will not at any time be liable for the loss of or damage to any of the said Materials, Construction Plant or temporary works. (d) The Principal must use reasonable endeavours in assisting the Contractor, where required, in obtaining clearance through Customs of Materials, Construction Plant and other things required for the Work under the Deed. (e) If the Deed is terminated under clause 37.1 or clause 37.2 prior to Completion, then the Principal may require the Contractor to give, and require its Subcontractors to give, to the Principal (or its nominee) possession of any Materials, Construction Plant and temporary works being used in the performance of the Work under the Deed which are reasonably required to facilitate Completion. (f) If the Principal (or its nominee) takes possession of Materials, Construction Plant or temporary works in accordance with clause 18.3(e), then the Principal must use its reasonable endeavours to procure: (i) the proper use and maintenance; and (ii) when they are no longer required in the performance of the Work under the Deed, the handover to the Contractor, of such Materials, Construction Plant and temporary work which have not been consumed or incorporated in the Work under the Deed. (g) 18.4 The Principal will pay the Contractor its reasonable direct costs in respect of clause 18.3(f) if the Deed is terminated under clause 37.2. Restrictions on sale, lease and parting with possession (a) The Contractor must not: (i) create or allow to exist any security interest over; or (ii) lease, license, transfer, sell, dispose of, part with possession of, or otherwise deal with, the whole or any part of the Construction Plant identified in Schedule 1 Contract Information, except as approved in writing by the Principal. (b) 18.5 The Contractor warrants that clear title to the TBM will pass to the Contractor upon delivery of the TBM to the Site. Samples (a) Where works or items are referred to as requiring samples in the Deed or the Contractor is directed to provide samples by the Principal‟s Representative, the Contractor must provide to the Principal‟s Representative samples in accordance with the Deed and the requirements of the Principal‟s Representative. (b) Where samples have been provided to and approved by the Principal‟s Representative, the Contractor must label the approved samples and keep them on the Site for reference unless otherwise directed by the Principal‟s Representative. 58 19 (c) The samples provided by the Contractor and approved by the Principal‟s Representative may be used in the Work under the Deed with the Principal‟s Representative‟s prior written consent, such consent to be in the Principal‟s Representative‟s absolute discretion. (d) All relevant Work under the Deed must conform to the samples as approved by the Principal‟s Representative. Construction 19.1 Contractor’s Supervision The Contractor must give or provide all necessary superintendence during the execution of the Work under the Deed, and the Project Construction Manager or a deputy must be constantly on the Site to provide full-time superintendence of the Work under the Deed. The Contractor must provide and employ only such technical personnel as are approved by the Principal and skilled and experienced in their respective callings and such supervisory staff as are competent to give adequate supervision to the work they are required to supervise. 19.2 Labour The Contractor must provide and employ on Site in the execution of the Work under the Deed such skilled, semi-skilled and unskilled labour as is necessary for the proper and timely execution of the Work under the Deed. 19.3 Access to Site (a) The Principal must make the Site available to the Contractor in accordance with, and subject to the conditions in, clause 3.3 of the Specification and the other requirements of the Deed, sufficient for the Contractor to carry out its obligations under the Deed in accordance with the requirements of the Deed. (b) Access to or possession of the Site will confer on the Contractor a right only to such use and control as is necessary to enable the Contractor to execute the work under the Deed. (c) Failure by the Principal to make the Site available to the Contractor as contemplated by clause 19.3(a) is not a breach of contract by the Principal, but will entitle the Contractor to claim an extension of time and delay costs in accordance with clause 34. (d) The Contractor: (i) is not entitled to, and must not, access or carry out any Work under the Deed on any part of the Site which has not been made available by the Principal under clause 19.3(a); (ii) acknowledges that failure by the Principal to make the Site available to the Contractor as contemplated by clause 19.3(a) may result in (among other things) the Contractor being required to slow or stop the progress of the Work under the Deed; and 59 (iii) 19.4 19.5 is not entitled to any adjustment to the Contract Price or any other compensation arising out of or in connection with any failure by the Principal to make the Site available to the Contractor as contemplated by clause 19.3(a) other than as contemplated by clause 19.3(c). Principal’s Access to the Site and the Work under the Deed (a) The Principal or any personnel or officers of the Principal or related corporations, contractors, agents and consultants of the Principal authorised by the Principal may enter the Site provided that no person who enters the Site upon the authority of the Principal interferes with or impedes the progress of the Work under the Deed (subject to the right of the Principal‟s Representative to give directions with respect to work which in its opinion is not in accordance with the Deed). (b) The Principal must give to the Contractor reasonable (and in any event not less than 24 hours‟) notice of all persons other than personnel or officers of the Principal or related corporations of the Principal whom the Principal proposes to authorise to enter the Site or inspect the Work under the Deed. (c) Without limiting clause 19.4(b), the Principal must, where practicable, give the Contractor reasonable notice of any personnel or officers of the Principal or its related corporations it authorises to enter the Site but will not be obliged to give such notice with respect to the Principal‟s Representative. (d) The Principal must use reasonable endeavours to procure that any person authorised by the Principal to enter the Site complies with the Contractor‟s site regulations and safety procedures. Separate Contractors (a) The Contractor acknowledges that Separate Contractors will be present on the Site during the execution of the Work under the Deed by the Contractor. (b) The Contractor must: (c) (i) coordinate the execution of the Work under the Deed with the work of Separate Contractors as notified to the Contractor by the Principal; (ii) co-operate with Separate Contractors; (iii) not obstruct, delay or interfere with the work of Separate Contractors; (iv) not damage the work of Separate Contractors; and (v) comply with all written directions from the Principal‟s Representative regarding Separate Contractors and their work. Without limiting any other provision of the Deed, if a Separate Contractor checks tolerances of any part of the Work under the Deed and determines that they are not strictly within tolerances stated in the Specification, the Principal‟s Representative may direct the Contractor to make good the relevant part or parts of the Work under the Deed so as to be strictly within 60 tolerances stated in the Specification and the Contractor must comply with such a direction without delay and at its own cost. (d) 19.6 Any action of the Contractor under clause 19.5(b) does not lessen or otherwise affect the Contractor‟s other obligations under the Deed. Neither the Principal nor the Principal‟s Representative assumes any responsibility or duty of care to the Contractor in respect of its actions under clause 19.5. Occupational Health and Safety (a) In accordance with clause 210 of the OH&S Regulation, the Principal: (i) appoints the Contractor as the principal contractor for the construction work forming part of the Work under the Deed; and (ii) authorises the Contractor to exercise such authority of the Principal as is necessary to enable the Contractor to discharge the responsibilities imposed on a principal contractor under Part 8 of the OH&S Regulation, except as otherwise provided in clauses 19.6(b) and 19.6(h). (b) The Contractor acknowledges and agrees that the Principal will appoint the Cable Installation Contractor as the principal contractor for the construction work forming part of the Cable Installation Works from the date the Contractor hands over the CSCT Extension to the Cable Installation Contractor (as directed by the Principal‟s Representative under clause 19.7) until the time the CSCT Extension is handed back to the Contractor. (c) From the Date of Substantial Completion of Separable Portion 1 until the time the CSCT Extension is handed back to the Contractor under the Deed, the Contractor: (d) (i) is only permitted access to the CSCT Extension with the prior approval, and in accordance with the directions, of the Principal and the Cable Installation Contractor; and (ii) must comply with, and ensure that its Subcontractors and employees engaged in executing the Work under the Deed in the CSCT Extension, comply with: (A) the Cable Installation Contractor‟s occupational health and safety management plan in respect of the CSCT Extension; and (B) any reasonable direction of the Cable Installation Contractor or the Principal in respect of occupational health and safety in the CSCT Extension. The Principal agrees to use all reasonable endeavours to procure that any Separate Contractor present on the Site during the execution of the Work under the Deed by the Contractor will comply with the Contractor‟s reasonable directions with respect to occupational health and safety while the Contractor is appointed the principal contractor under the Deed. 61 19.7 (e) The Contractor must comply with the requirements of the Specification in respect of occupational health and safety requirements. (f) If the Contractor fails to comply with any of its obligations under the Deed in respect of occupational health and safety, the Principal may perform, or have performed, the obligation on the Contractor‟s behalf and recover from the Contractor as a debt all costs and expenses incurred. (g) If and to the extent the Principal or the Principal‟s Representative considers it necessary to undertake any activity, give any direction or otherwise perform any of the works or services for which the Contractor is responsible under the Deed, the parties acknowledge and agree that in doing so the Principal is not acting as a principal contractor, nor is the Principal to be taken, for any purpose, to be the principal contractor. In these circumstances, the Contractor must indemnify the Principal against any loss, expense or damage of any nature, including financial loss and lawyers‟ fees and expenses on an indemnity basis, suffered or incurred by the Principal arising out of the performance or authorisation of the performance of any of the works or services referred to in this clause 19.6. (h) The Contractor acknowledges and agrees that: (i) part of the Work under the Deed will be carried out on land which is owned by an Interface Party; (ii) clause 210 of the OH&S Regulation requires the owner of the land on which any construction work is carried out to appoint a principal contractor for that work; and (iii) the Contractor must execute any reasonable agreement required by the Principal or an Interface Party which gives effect to the appointment of the Contractor as the principal contractor for Work under the Deed to be carried out on land which is owned by an Interface Party. (i) For the purpose of this clause 19.6, the term construction work has the meaning given to it in the OH&S Regulation. (j) If there is any change to the OH&S Regulation following the execution of the Deed: (i) the Principal and the Contractor agree that any principal contractor appointment made under this clause 19.6 continues to be effective as an appointment under any new or amended regulation or law; and (ii) by this clause, the Principal authorises the Contractor to have management and control of the workplaces at which the Contractor is performing the Work under the Deed to the extent necessary to discharge its obligations as principal contractor. Handover to Cable Installation Contractor (a) The parties acknowledge and agree that: 62 19.8 20 (i) in respect of Separable Portion 1, the Contract Programme has allowed 10 months following Substantial Completion of Separable Portion 1 for the CSCT Extension to be handed over to the Principal for the purposes of the Cable Installation Contractor carrying out the Cable Installation Works; and (ii) if the period referred to in clause 19.7(a)(i) exceeds 10 months, the Contractor may claim an extension of time and delay costs in accordance with clause 34 but is not entitled to any other compensation. (b) Following Substantial Completion of Separable Portion 1, the Principal‟s Representative will give the Contractor written notice of the date the Contractor must hand over the CSCT Extension to the Principal for the purposes contemplated by clause 19.7(a)(i). (c) The Contractor must hand over the CSCT Extension to the Principal on the date directed by the Principal‟s Representative under clause 19.7(b). (d) The Principal will, as soon as reasonably practicable, notify the Contractor in writing of the time when the CSCT Extension will be handed back to the Contractor to complete the remaining Work under the Deed. Industrial relations (a) The Contractor must, and must ensure that its Subcontractors, comply with all applicable Commonwealth and state industrial instruments. (b) The Contractor must regularly consult with the Principal‟s Representative, throughout the performance of the Work under the Deed, concerning any industrial relations issues which may arise and, in particular, its negotiation of any industrial instruments with its employees. Testing and Inspection 20.1 Tests and inspections must be conducted as provided in the Deed and by the relevant person specified in Schedule 6 - Key Personnel. 20.2 Subject to clause 20.5, the Principal‟s Representative (or its delegate) will be entitled to attend any Tests. 20.3 Whenever the Contractor is ready to carry out a Test: (a) which is nominated by the Principal as a Hold Point, the Contractor must give the Principal five business days‟ advance notice of such Test and of the place and time; or (b) which is required by an Interface Party under an Interface Agreement, the Contractor must give the Principal not less than 2 business days‟ advance notice of such Test prior to the time the Principal is required to give such notice to the relevant Interface Party and any other information required by the Interface Agreement in respect of such Test. 63 The Principal‟s Representative may agree to a shorter period of notice in any particular instance. 20.4 20.5 The Contractor must provide the Principal‟s Representative with a report of the results of any such Test: (a) in both hard copy and electronic format; and (b) which is certified as contemplated by the Specification. If the Principal‟s Representative (or its delegate) fails to attend a Test, or it is agreed between the parties that the Principal‟s Representative must not do so, the Contractor may proceed with the Test in the absence of the Principal‟s Representative and provide the Principal with a report of the results of any such Test: (a) in both hard copy and electronic format; and (b) which is certified as contemplated by the Specification. 20.6 The Contractor must pay the costs of all Tests. 20.7 The Contractor must submit its testing procedures and methodologies and the proposed form of the test report to the Principal‟s Representative for approval prior to commencing any testing, in accordance with the requirements of the Specification. The Principal‟s Representative must review and comment on the documents submitted to it within 10 days of such submission and the Contractor must revise any such documents as reasonably required by the Principal‟s Representative. 20.8 The Principal‟s Representative must not unreasonably withhold its approval to any procedures, methodologies or reports in connection with testing provided that the documents are in accordance with the requirements of the Deed (including the Specification). 20.9 Neither the Principal nor the Principal‟s Representative is under any obligation to the Contractor to enter, inspect or Test under clause 20 and owes no duty of care or otherwise to the Contractor in doing so (other than to the extent expressly stated in clause 19.4) and no entry, inspection or Test by the Principal, the Principal‟s Representative or any person authorised by the Principal or the Principal‟s Representative will affect the Contractor‟s obligations under the Deed. 20A NGER Reporting Obligations 20A.1 - Definitions In clauses 20A and 34.4: (a) 'GHG Legislation' means any Law which has as one of its purposes the reduction, offset or management of GHG emissions and includes a law in connection with: (i) any GHG emissions trading scheme (howsoever named); (ii) a tax, levy, impost, deduction, charge, withholding or duty, together with a related interest, penalty, fine or other statutory charge, relating to GHG emissions, fuel or energy use; or 64 (iii) a requirement to undertake action to reduce, minimise or offset GHG emissions, fuel or energy use. (b) 'GHG' means one or more of the gases listed in Annex A to the Protocol of the United Nations Framework Convention on Climate Change adopted at the meeting of the parties in Kyoto, Japan on 10 December 1997 as amended or implemented by the conference of the parties to the Protocol. (c) 'NGER Act' means the National Greenhouse and Energy Reporting Act 2007 (Cth). 20A.2 - Reporting Obligation The parties acknowledge and agree, to the extent permitted by Law, that: (a) either of the parties could satisfy section 11(1)(a) of the NGER Act in respect of the Work under the Deed; (b) the Contractor has the greatest authority to introduce and implement the policies mentioned in section 11(1)(a)(i) and 11(1)(a)(iii) of the NGER Act in respect of the Work under the Deed; and (c) the Contractor has operational control in respect of the Work under the Deed for the purposes of the NGER Act until Practical Completion and accordingly, without limiting clause 6.1, the Contractor shall comply with the NGER Act in relation to the Work under the Deed. 20A.3 - Amendments to Reporting Obligation (a) This clause 20A.3 applies if the NGER Act, the GHG Legislation or other Law enables the parties to nominate the person with the reporting obligation under the NGER Act. (b) The parties acknowledge and agree, to the extent permitted by Law, that: (c) (i) either of the parties could satisfy section 11(1)(a) of the NGER Act in respect of the Work under the Deed; and (ii) despite clause 20A.2, a court or Government Authority may determine that neither of the parties has the greatest authority to introduce and implement the policies mentioned in section 11(1)(a)(i) and 11(1)(a)(iii) of the NGER Act in respect of the Work under the Deed. The parties jointly nominate the Contractor as the nominated person under the NGER Act and acknowledge and agree that the Contractor is taken to have operational control in respect of the Work under the Deed for the purposes of the NGER Act until Completion. 20A.4 - Provision of Information (a) The Principal agrees to provide all reasonable assistance to the Contractor to enable the Contractor to comply with the NGER Act in relation to the Work under the Deed. 65 (b) The Principal warrants that all information and data provided to the Contractor under this clause 20A.4 is, to the knowledge of the Principal, not false or misleading. (c) Without limiting clause 12, the Contractor agrees to keep any information or data provided to it by the Principal confidential except to the extent that: (d) (i) the Contractor is required to disclose the information to comply with a Law; or (ii) the information is otherwise in the public domain. The Contractor agrees to provide data requested by the Principal relating to GHG emissions, energy consumption and energy production arising from, or in connection with, the Work under the Deed. The Contractor warrants that all information and data provided to the Principal under this clause is, to the knowledge of the Contractor, not false or misleading. 20A.5 - No Liability from Determination If, despite clauses 20A.2, 20A.3 and 20A.4, a court or Government Authority determines that the Principal has the reporting obligation under the NGER Act in respect of the Work under the Deed, the Principal has no liability to the Contractor for any loss, claim, cost, damage or expense arising from, or in connection with, that determination. 20A.6 - Principal has Reporting Obligation (a) This clause applies if, despite clauses 20A.2, 20A.3 and 20A.4, a court or Government Authority determines that the Principal has the reporting obligation under the NGER Act in respect of the Work under the Deed. (b) If the NGER Act, the GHG Legislation or other Law enables the Principal to transfer the reporting obligation to the Contractor: (c) (i) the parties acknowledge and agree that the reporting obligation is to be transferred from the Principal to the Contractor; and (ii) the parties acknowledge and agree that they will take all reasonable steps to transfer the reporting obligation from the Principal to the Contractor. If the NGER Act, the GHG Legislation or other Law does not enable the Principal to transfer the reporting obligation to the Contractor, the Contractor agrees to provide all necessary assistance to the Principal to enable it to comply with the NGER Act and the GHG Legislation in relation to the Work under the Deed including: (i) providing all data relating to GHG emissions, energy consumption and energy production arising from, or in connection with, the Work under the Deed in a form reasonably requested by the Principal; and (ii) providing all reasonable assistance to an auditor appointed by the Contractor under the NGER Act or the GHG Legislation. 66 (d) The Contractor warrants that all information and data provided to the Principal under this clause is, to the knowledge of the Contractor, not false or misleading. (e) The Contractor indemnifies, and will keep indemnified, the Principal for any loss, claim, cost, damage, expense or other liability which may be suffered or incurred in connection with the failure of the Contractor to provide the data requested under this clause or if the data provided by the Contractor is incorrect or otherwise false or misleading. 20A.7 Changes to NGER Act of GHG Legislation which impacts on Reporting Obligations (a) Subject to clause 20A.7(b), if there is: (i) a change in the NGER Act after the date of the Deed; or (ii) a change in the GHG Legislation after the date of the Deed, that will increase the Contractor's reporting obligations under this clause 20A, the Contractor is entitled to claim an adjustment to the Contract Price as if those increased reporting obligations were directed as a Change under the Deed. (b) 21 The Contractor is not entitled to be paid for the same amount under both this clause 20A.7 and any delay costs in respect of the cause of delay contemplated in clause 34.4(d)(xi). Substantial and Practical Completion 21.1 Substantial Completion (a) This clause 21.1 only applies in respect of Separable Portion 1 and Separable Portion 2. (b) The Contractor must give the Principal‟s Representative: (i) at least 25 business days‟ notice; and (ii) at least five business days‟ notice, of the date upon which the Contractor anticipates the Contractor will achieve Substantial Completion. (c) As soon as the Contractor has, in the opinion of the Contractor, satisfied all of the requirements for Substantial Completion, the Contractor must notify the Principal‟s Representative. (d) The Principal‟s Representative must, within 10 days after receipt of the Contractor‟s first notice under clause 21.1(c), either issue a Substantial Completion Certificate stating that the Work under the Deed has reached Substantial Completion as at the date of the Contractor‟s notice under clause 21.1(c) (or such other date specified by the Principal's Representative), or notify the Contractor of any matters listed in the 67 definition of Substantial Completion to be attended to before Substantial Completion will be achieved. (e) If the Principal‟s Representative notifies the Contractor under clause 21.1(d) or clause 21.1(g) of any matters to be attended to, the Contractor must attend to such matters and must repeat the procedure described in clause 21.1(c). (f) If the Work under the Deed has reached Substantial Completion, the Principal‟s Representative must, within five days after receipt of the Contractor‟s repeated notice contemplated in clause 21.1(e), issue a Substantial Completion Certificate stating that the Work under the Deed has reached Substantial Completion as at the date of the Contractor‟s repeated notice (or such other date specified by the Principal's Representative). (g) If the Principal‟s Representative determines that Substantial Completion has still not been achieved, the Principal‟s Representative must within five days after receipt of the Contractor‟s repeated notice contemplated in clause 21.1(e) notify the Contractor of any remaining matters listed in the definition of Substantial Completion to be attended to. The Contractor must then repeat the procedure described in clause 21.1(e) and clause 21.1(f) and 21.1(g) shall apply accordingly. (h) While the Contractor may achieve Substantial Completion before the Date for Substantial Completion, the Principal and the Principal‟s Representative have no responsibility or duty of care to do, or refrain from doing, anything to enable the Contractor to achieve those results. (i) The Contractor acknowledges and agrees that for the purposes of this clause 21.1: (j) 21.2 (i) the Principal‟s Representative may inspect the Work under the Deed; (ii) the Principal‟s Representative may request the Contractor to inspect the Work under the Deed jointly with the Principal‟s Representative and the Contractor must attend such inspections; and (iii) the Principal‟s Representative may request (and the Contractor must allow) other consultants, the Cable Installation Contractor and other persons to attend any inspection where the Principal‟s Representative considers it appropriate. The Contractor acknowledges that the inspections referred to in clause 21.1(i) will not relieve the Contractor of any obligations under the Deed, including the obligation to bring the Work under the Deed to Substantial Completion by the Date for Substantial Completion. Practical Completion (a) The Contractor must give the Principal‟s Representative at least 20 days‟ notice of the date upon which the Contractor anticipates the Work under the Deed will be brought to Practical Completion. (b) As soon as the Work under the Deed has, in the opinion of the Contractor, been completed in accordance with the Deed, excluding minor defects or omissions not materially affecting the design, procurement and construction 68 or safety of the Work under the Deed, and the Contractor has satisfied all of the other requirements for Practical Completion, the Contractor must notify the Principal‟s Representative. (c) The Principal‟s Representative must, within 10 days after receipt of the Contractor‟s first notice under clause 21.2(b), either issue a Practical Completion Certificate stating that the Work under the Deed has reached Practical Completion as at the date of the Contractor‟s notice under clause 21.2(b) (or such other date specified by the Principal's Representative), or notify the Contractor of any Defects in the Work under the Deed or other matters listed in the definition of Practical Completion to be attended to before Practical Completion will be achieved. (d) If the Principal‟s Representative notifies the Contractor under clause 21.2(c) or clause 21.2(f) of any Defects and/or other matters to be attended to, the Contractor must correct such Defects or attend to such matters, as applicable, and must repeat the procedure described in clause 21.2(b). (e) If the Work under the Deed has reached Practical Completion, the Principal‟s Representative must, within five days after receipt of the Contractor‟s repeated notice contemplated in clause 21.2(d), issue a Practical Completion Certificate stating that the Work under the Deed has reached Practical Completion as at the date of the Contractor‟s repeated notice (or such other date specified by the Principal's Representative). (f) If the Principal determines that Practical Completion has not been achieved, the Principal‟s Representative must within five days after receipt of the Contractor‟s repeated notice contemplated in clause 21.2(d) notify the Contractor of any remaining Defects or matters listed in the definition of Practical Completion to be attended to. The Contractor must then repeat the procedure described in clause 21.2(d) and clause 21.2(e) and 21.2(f) shall apply accordingly. (g) With a Practical Completion Certificate in respect of the Work under the Deed, the Principal‟s Representative must issue a certificate setting out the minor items referred to in clause 21.2(b) which are to be attended to by the Contractor prior to Completion. As soon as possible, but in any case no later than 4 weeks after Practical Completion, the Contractor must complete the minor items set out in such certificate. All such work must be completed as a condition of Completion. (h) While the Contractor may achieve Practical Completion before the Date for Practical Completion, the Principal and the Principal‟s Representative have no responsibility or duty of care to do, or refrain from doing, anything to enable the Contractor to achieve those results. (i) The Contractor acknowledges and agrees that for the purposes of this clause 21.2: (i) the Principal‟s Representative may inspect the Work under the Deed; (ii) the Principal‟s Representative may request the Contractor to inspect the Work under the Deed jointly with the Principal‟s Representative and the Contractor must attend such inspections; and 69 (iii) (j) 22 the Principal‟s Representative may request (and the Contractor must allow) other consultants, the Cable Installation Contractor and other persons to attend any inspection where the Principal‟s Representative considers it appropriate. The Contractor acknowledges that the inspections referred to in clause 21.2(i) will not relieve the Contractor of any obligations under the Deed, including the obligation to bring the Work under the Deed to Practical Completion by the Date for Practical Completion. Completion and Close Out Workshop 22.1 Notice of Completion When the Contractor is of the opinion that it has satisfied all of the requirements for Completion, it must give notice to that effect to the Principal‟s Representative requesting the issue of a Completion Certificate. 22.2 Completion Certificate (a) (b) 22.3 Within 15 days of the Contractor‟s notice under clause 22.1, the Principal‟s Representative must either: (i) issue the Completion Certificate; or (ii) notify the Contractor of its reasons for not issuing the Completion Certificate. If the Principal‟s Representative gives notice under clause 22.2(a)(ii), the Contractor must attend to the matters in the notice and the provisions of clause 22.1 and 22.2(a) re-apply. Close Out Workshop (a) The Principal may, in its absolute discretion, convene a close-out workshop within 21 days after achieving Completion to evaluate the performance of the parties in connection with the Deed. (b) If directed by the Principal, the Contractor must attend the Close Out Workshop and must, in conjunction with the Principal, decide who else will attend (which may include Subcontractors and Interface Parties and, if appropriate, representatives of Government Authorities, persons to be involved in using or occupying any part of the Works, and local community representatives). (c) Each party and any others who participate in the workshop must meet their own costs for attendance at the Close Out Workshop, and the parties will share equally any other costs. 70 23 Representations and Warranties 23.1 Representations and warranties of the Principal The Principal warrants that it has the power to execute, deliver and perform its obligations under the Deed and all necessary corporate and other action has been taken to authorise that execution, delivery and performance. 23.2 Representations and warranties of the Contractor The Contractor makes the following representations and warranties to the Principal each of which is true and correct on the date of execution of the Deed: (a) the Contractor has been incorporated in accordance with the laws of its place of incorporation, is validly existing under those laws, and has the power and authority to carry on its business as it is now being conducted; (b) the Contractor has the power to enter into and deliver the Deed and comply with its obligations under the Deed; (c) the Deed and the transactions under it which involve the Contractor do not contravene its constituent documents (if any) or any law or obligation by which it is bound or to which any of its assets are subject or cause a limitation on its powers or the powers of its directors to be exceeded; (d) to the best of the Contractor‟s knowledge, no suit, claim, action, arbitration, or legal, administrative or other proceedings is pending or threatened against the Contractor that would affect the validity or enforceability of the Deed or the ability of the Contractor to fulfil its commitments hereunder in any material respect, or that could result in any material adverse change in the business or financial condition of the Contractor; (e) the Contractor is a solvent legal entity and is under no form of insolvency, administration or legal disability to contract of any kind; (f) the Contractor has no conflict of interest or anticipated conflict of interest in entering into the Deed and doing all things required of it under the Deed which has not otherwise been disclosed in writing to the Principal prior to or at the time of entering into the Deed; (g) the Contractor has after diligent inquiry and investigation fully disclosed to the Principal all information (within its knowledge or which ought to have been within its knowledge) which could reasonably be regarded as affecting in any way the decision of the Principal to enter into the Deed with the Contractor; (h) all authorisations, registrations, consents, approvals, licences or permits required by any Government Authority or under any Law which are or will be required in connection with the execution and delivery of, performance of obligations under or validity or enforceability of, the Deed have been or will be obtained or effected and are or will be in force and effect; and (i) the Contractor will immediately notify the Principal of the occurrence of any event which may constitute a breach of any of the representations, warranties 71 or covenants made in connection with the Deed, including any event which may result in material adverse change in the business of the Contractor. 24 Warranties 24.1 24.2 24.3 The Contractor warrants to the Principal that: (a) the Work under the Deed will be designed, engineered, constructed and maintained with all the skill and care to be expected of appropriately qualified and experienced professional designers and engineers with experience in designing, engineering, constructing and maintaining facilities of a similar size, type, nature and complexity of the Work under the Deed; (b) the Work under the Deed will be designed, engineered, constructed and maintained in a manner commensurate with Best Industry Practices; (c) the Works will comprise Materials which will be of good quality and free from any encumbrance or lien and will conform to the requirements of the Deed, including the Specification; and (d) the Work under the Deed will be designed, engineered, constructed, maintained, completed, tested and delivered in accordance with the Deed. The Contractor further warrants that: (a) the Work under the Deed will be designed, engineered, constructed and maintained in accordance with all Government Approvals, all Laws, the requirements of all Government Authorities and to the applicable Australian Standards and industry standards; (b) all Materials specified by the Contractor or used in the construction of the Works will be suitable new materials, will meet the requirements of the Deed and will be fit for their intended purpose; (c) all Construction Plant used in the construction of the Work under the Deed will meet the requirements of the Deed and will be fit for their intended purpose; (d) all the Work under the Deed will be carried out in a professional manner and to the standards otherwise required by the Deed; (e) the Works upon Completion will: (i) be suitable in all respects for their purpose stated in the Deed; (ii) without limiting clause 24.2(e)(i), meet all performance requirements stated in the Deed; and (iii) without limiting clauses 24.2(e)(i) and 24.2(e)(ii), strictly comply with every aspect of the Deed and any variations in size, configuration or performance will be strictly within tolerances stated in the Specification. The Contractor‟s warranties given in clause 24.1 and 24.2 will not be affected or limited by: 72 24.4 25 (a) any Change directed or approved by the Principal; or (b) any review of, comment (or failure to comment) on or concurrence with or approval by the Principal or the Principal‟s Representative of any Contractor‟s Documents prepared by the Contractor or samples submitted by the Contractor. The warranties given by the Contractor under this clause 24, to the extent that they relate to design, are only given in relation to such parts of the Works and the other Work under the Deed for which the Contractor has design responsibility under the Deed. Delay to Completion 25.1 25.2 Time for Completion (a) The Contractor must achieve Substantial Completion by the Date for Substantial Completion. (b) The Contractor must achieve Practical Completion by the Date for Practical Completion. (c) The Contractor must achieve Completion by the Date for Completion. Liquidated damages (a) In the event of the Contractor‟s failure to achieve Substantial Completion by the Date for Substantial Completion, the Contractor must pay to the Principal liquidated damages at the rate specified in Schedule 2 - Separable Portions for each day from that date until the earlier of the Date of Substantial Completion or the date the Deed is terminated. (b) In addition to the liquidated damages payable under clause 25.2(a), in the event of the Contractor‟s failure to achieve Practical Completion by the Date for Practical Completion, the Contractor must pay to the Principal liquidated damages at the rate specified in Schedule 2 - Separable Portions for each day from that date until the earlier of the Date of Practical Completion or the date the Deed is terminated. (c) The parties agree that the liquidated damages specified in Schedule 2 Separable Portions are a fair and reasonable pre-estimate of the damages likely to be sustained by the Principal as a result of the Contractor‟s failure to achieve Substantial Completion by the Date for Substantial Completion and/or the Contractor‟s failure to achieve Practical Completion by the Date for Practical Completion, as the case may be. (d) The aggregate liability of the Contractor for liquidated damages under clauses 25.2(a) and 25.2(b) will not exceed the amount specified in Schedule 1 - Contract Information. (e) The liability of the Contractor to pay liquidated damages under clauses 25.2(a) and 25.2(b) is, subject to clause 25.2(f), in substitution of the Principal‟s right to recover damages at general law due to a delay to the Date of Substantial Completion and/or the Date of Practical Completion, as the 73 case may be, but does not otherwise limit any right or entitlement of the Principal in respect of any breach of the Deed by the Contractor. (f) 26 If clauses 25.2(a) or 25.2(b) are found for any reason to be void, invalid or otherwise inoperative, so as to disentitle the Principal from recovering liquidated damages for the Contractor‟s failure to achieve Substantial Completion by the Date for Substantial Completion and/or Practical Completion by the Date for Practical Completion (as the case may be), the Principal is entitled to recover damages from the Contractor for such failure under general law, which damages will not be limited to the liquidated damages that the Principal would otherwise have been entitled to recover from the Contractor. Defect Correction 26.1 Defective materials or work (a) If the Principal‟s Representative discovers material or work provided by the Contractor, which is not in accordance with the Deed, the Principal may, at any time before the expiry of the last Defects Correction Period, direct the Contractor at its own cost to do any or all of the following: (i) remove the material from the Site; (ii) demolish the work; (iii) reconstruct, replace or correct the material or work; or (iv) not deliver the material or work to the Site. (b) The Principal may direct the times within which the Contractor must commence and complete the removal, demolition, replacement or correction. (c) If: (i) the Contractor fails to comply with a direction issued by the Principal‟s Representative pursuant to this clause 26.1 within the time frame specified by the Principal‟s Representative in the direction; and (ii) that failure has not been made good within seven days after the Contractor receives written notice from the Principal‟s Representative that the Principal intends to have the subject work rectified by others, the Principal may have the work of removal, demolition, replacement or correction carried out by others and the cost incurred by the Principal in having the work so carried out will be a debt due from the Contractor to the Principal. 74 26.2 26.3 Acceptance of defective materials or work (a) The Principal‟s Representative may, instead of a giving a direction under clause 26.1(a), notify the Contractor that the Principal elects to accept material or work notwithstanding that it is not in accordance with the Deed. (b) If the Principal‟s Representative gives a notice under clause 26.2(a), the Principal‟s Representative must give the Principal and the Contractor‟s Representative its determination of the cost incurred by the Principal in accepting the defective work or materials, such cost to be valued based on the cost of rectifying the defective work or based on diminution of value of the Works (or relevant part of the Works) or a combination of the costs of partial rectification and the remaining diminution of value (as the case may be), and that amount will be a debt due from the Contractor to the Principal. Defects Correction Period (a) The Contractor warrants that the Works will be free from Defects in design (in relation to those parts of the Works, for the design of which the Contractor is responsible), engineering and construction. (b) If during the Defects Correction Period, any Defect should be found in the design, engineering, construction or other work executed by the Contractor, the Contractor must promptly and at its cost repair, replace or otherwise make good (as the Principal‟s Representative may at its discretion direct) such Defect as well as damage to the Works caused by such Defect. (c) The Defects Correction Period shall commence on the Date of Practical Completion and end when the period specified in Schedule 1 - Contract Information expires after the Date of Practical Completion. (d) The Principal must give the Contractor a notice stating the nature of any Defect and a reasonable date or time by which the Contractor must complete the repair, replacement or other making good (as the case may be) having regard to the nature of the Defect. (e) Subject to clause 26.4, the Principal must afford the Contractor all necessary access to the Works and the Site to enable the Contractor to perform its obligations under this clause 26 and must where necessary authorise the Contractor to enter land on behalf of the Principal. (f) If the Contractor fails to commence the work necessary to remedy any Defect or any damage to the Works caused by such Defect within the time stated in a notice from the Principal‟s Representative, the Principal may (or may engage others to) proceed to do such work and the reasonable costs incurred by the Principal will be a debt due from the Contractor to the Principal. (g) If it becomes necessary under clause 26 for the Contractor to carry out any repair, replacement or other making good: (i) the provisions of the Deed relating to the Works apply to the repair, replacement or other making good as if it were the Works; and (ii) the Defects Correction Period for such repair, replacement or other making good: 75 26.4 (A) commences on the day on which the repair, replacement or other making good is completed to the Principal‟s Representative‟s reasonable satisfaction; and (B) ends 12 months thereafter or 12 months after the Date of Completion to reach Completion, whichever is the later. Operation of Works during Defects Correction Period The Contractor acknowledges and agrees that, during the Defects Correction Period: 27 (a) live 132kV cables will be operational within, or in the vicinity of, the Works; and (b) the Contractor must: (i) access the Site only with the prior approval, and in accordance with the directions, of the Principal‟s Representative; (ii) perform any repair or replacement work in such a manner as to interfere to the least extent possible with the conduct of the business of the Principal on the Site; (iii) only access the Site during the hours and on the days directed in writing by the Principal‟s Representative; (iv) take all steps necessary to protect all people from risks to safety caused by the performance of the repair or replacement work; (v) complete such safety or other training or induction as the Principal‟s Representative from time to time directs; (vi) comply with all procedures, policies and rules adopted from time to time by the Principal in connection with the Site; and (vii) keep itself informed as to the requirements of, comply with and not do anything which may place the Principal in breach of Law. Care of the Work under the Deed 27.1 27.2 (a) Subject to clause 27.3, the Contractor is responsible for the care and custody of the Work under the Deed until the Date of Completion and must make good at its own cost any loss or damage that may occur to the Work under the Deed from any cause whatsoever during such period. (b) The Contractor is also responsible for any loss or damage to the Work under the Deed caused by the Contractor or its Subcontractors in the course of the work carried out pursuant to clause 26. The Contractor is liable for any loss of or damage to any construction equipment or any other property of the Contractor used or intended to be used for the purposes of the Work under the Deed, save where such loss or damage arises by reason of the use or occupation by the Principal or any third party (other than a Subcontractor) authorised by the Principal of any part of the Work under the Deed. 76 27.3 28 The Contractor‟s obligations under clause 27.1(a) do not apply in respect of the CSCT and CSCT Extension from the date the CSCT and CSCT Extension is handed over to the Principal until the date the CSCT and CSCT Extension is handed back to the Contractor as contemplated by clause 19.7 or any loss or damage to the Work under the Deed arising from: (a) any negligent act or omission of the Principal‟s Representative, the Principal or its consultants, agents, employees, Interface Parties, Separate Contractors or other contractors (not being employed by the Contractor); (b) any risk specifically excepted elsewhere in the Contract; (c) war, invasion, acts of foreign enemies, hostilities (whether war be declared or not), civil war, rebellion, revolution, insurrection or military or usurped power, martial law or confiscation by order of any government or public authority; (d) ionising radiations or contamination by radioactivity from any nuclear fuel or from any nuclear waste from the combustion of nuclear fuel not caused by the Contractor or its subcontractors or either‟s employees or agents; (e) use or occupation of any part of the Works by the Principal‟s Representative, the Principal or its consultants, agents, Interface Parties, Separate Contractors or other contractors (not being employed by the Contractor); and (f) defects in the design of the Works, other than design provided by the Contractor or design for which the Contractor is responsible. Indemnities Masked for Confidentiality 28.2 The Contractor‟s obligation to indemnify the Principal under clause 28.1 will be reduced only to the extent that the same was caused by or contributed to by any negligent act or omission of the Principal or an Interface Party. 28.3 Each indemnity in the Deed is a continuing obligation, separate and independent from the other obligations of the party giving that indemnity, and remains in full force and effect following completion or termination of the Deed. 77 29 Insurance 29.1 The Contractor must at its expense take out and maintain, or cause to be taken out and maintained, the insurances at the times, in the manner, on the terms and in the form specified in Schedule 7 - Insurances and this clause 29. 29.2 The Contractor must: (a) ensure that the insurance policies effected under clause 29.1 and Schedule 7 Insurances (with the exception of statutory insurances) are effected with reputable insurers with a financial security rating of "A-" or better by Standard & Poors or the equivalent rating with another recognised rating agency, or another reputable insurer approved in writing by the Principal‟s Representative, which approval must not be unreasonably withheld; Masked for Confidentiality 78 Masked for Confidentiality 29.3 The Contractor must, on or prior to the Commencement Date and thereafter upon request by the Principal‟s Representative, provide evidence of compliance with clause 29.1 to the Principal‟s Representative. Where the Contractor employs Subcontractors, the Contractor must also provide evidence of compliance by the Subcontractors with clause 29.1 to the satisfaction of the Principal‟s Representative. For the purposes of this clause 29.3, the Contractor must give the Principal‟s Representative certificates from the relevant insurer or broker specifying for each insurance policy: 29.4 (a) the cover; (b) any significant exclusions, limitations or conditions; (c) the policy number; (d) the expiry date; and (e) sufficient information to enable the Principal‟s Representative to confirm proof of currency and coverage of each insurance policy The Contractor must: (a) give (or make available for inspection by) the Principal‟s insurance brokers the insurance policies effected by the Contractor under clause 29.1; (b) immediately notify the Principal and the Principal‟s Representative if an insurer gives notice of cancellation or other notice in respect of any insurance policy, including notice of any proposed variation, amendment or endorsement which materially adversely affects the amount, scope or terms of any policy; (c) ensure that premiums are paid on time and the conditions of insurance are otherwise complied with; (d) promptly pay the deductible in connection with any claim made in respect of any loss or risk covered by an insurance policy effected under clause 29.1. In circumstances where the claim is as a result of the Principal‟s or Principal‟s Representative‟s act, error or omission or the matters described in clauses 27.3(a) to 27.3(f) (inclusive) the Principal will reimburse the Contractor a 79 proportion of the deductible paid by the Contractor which reflects the extent to which the claim was as a result of the Principal‟s or Principal‟s Representative‟s act, error or omission or the matters described in clauses 27.3(a) to 27.3(f) (inclusive); 29.5 (e) not do or omit to do anything which might vitiate, impair or derogate from the cover under any insurance policy or which might prejudice any claim under any policy; (f) immediately notify the Principal‟s Representative of an event which may result in any insurance policy lapsing or being cancelled or avoided; and (g) as soon as practicable notify the Principal‟s Representative of any occurrence that may give rise to a claim under any insurance policy and thereafter keep the Principal‟s Representative informed of developments concerning the claim. If any insurance the Contractor is required to maintain under clause 29 is effected with an insurer in Australia: (a) (b) 29.6 where the insurance policy was effected before the date of the Deed, the Contractor: (i) warrants that it informed the insurer of the extent of its entitlement to an input tax credit for the last premium it paid at or before the time of first making any subsequent claim under the insurance policy; and (ii) must provide written proof of this to the Principal‟s Representative within five business days of the date of the Deed; and with respect to every insurance policy referred to in clause 29, whether effected before, on or after the date of the Deed, the Contractor must: (i) immediately inform the insurer of any change in the extent of its entitlement to an input tax credit for the last premium paid; (ii) inform the insurer of the extent of its entitlement to an input tax credit for any future premium it pays immediately after paying that premium; and (iii) provide written proof to the Principal‟s Representative that it has complied with clauses 29.5(b)(i) and 29.5(b)(ii) within five business days of informing the insurer. If the Contractor fails to take out or maintain, or to cause to be taken out or maintained, any specified insurance as required by Schedule 7- Insurances and this clause 29, or to provide satisfactory evidence of such insurance in accordance with clause 29.3, the Principal may (but is not obliged to) take out the insurance and the costs of doing so will be a debt due and payable from the Contractor to the Principal. The Contractor is not relieved of any liability under the Deed due to, or as a result of, the Principal taking out or maintaining any insurance policy referred to in Schedule 7 - Insurances. 80 30 Site Conditions, GBR administration and Selection of Equipment 30.1 Site Conditions Subject to clause 4.1A(e), clause 4.1(b)(iv)(B) and clause 30.3, the Contractor bears the risk of all Site Conditions encountered during the execution of the Work under the Deed and is not entitled to any additional payment or adjustment to the Contract Price, or any extension of time, arising out of the actual conditions encountered. 30.2 Site Information (a) Neither the Principal nor the Principal‟s Representative: (i) is responsible for the accuracy or the contents of; or (ii) makes any representation or assumes any duty of care in respect of, the following information: (b) (iii) the Pre-Contract Information; and (iv) any other reports, data, test results, samples or geotechnical investigations or information provided to the Contractor prior to the date of the Deed that have not been expressly included in the Deed. The Contractor acknowledges that: (i) the information referred to in clause 30.2(a) does not form part of the Deed and the Contractor has not relied on that information in choosing to enter into the Deed; (ii) the Principal is not responsible for the accuracy of the information referred to in clause 30.2(a) or for any negligence in the preparation of that information; (iii) the Contractor has: (iv) (A) been allowed adequate access to the Site; (B) been allowed to consult with the authors of the information referred to in clause 30.2(a); (C) had sufficient time to review thoroughly the information referred to in clause 30.2(a); (D) carried out its own investigations of the Site and its surroundings, before the date of the Deed, to reach its own conclusions as to the Site Conditions; and to the extent the Principal is not the author of the information referred to in clause 30.2(a), the Principal is not adopting or endorsing, but is merely passing on that information to the Contractor. 81 (c) (d) 30.3 Neither the Principal nor the Principal‟s Representative is liable in contract, tort or otherwise for any damage, expense, loss or liability suffered or incurred by the Contractor (whether arising by the negligence of the Principal or the Principal‟s Representative or their employees, consultants or agents or otherwise) however caused in respect of: (i) the provision of the information referred to in clause 30.2(a); or (ii) a failure to provide any information to the Contractor. The Contractor acknowledges that the Principal has entered into the Deed in reliance on the acknowledgments made by the Contractor in this clause 30.2. GBR administration and adjustments to time and costs for actual ground conditions encountered (a) The parties acknowledge and agree that: (i) the GBR contains descriptions of Typical Conditions and Adverse Conditions agreed by the parties prior to the date of the Deed for the sole purpose of determining the Contractor‟s entitlement under the Deed to: (A) payment; and (B) any adjustment to the Date for Substantial Completion, the Date for Practical Completion and the Date for Completion (as the case may be), arising out of the actual ground conditions encountered by the Contractor; (ii) they have not relied, and will not rely, on the GBR for any reason other than for the purpose stated in clause 30.3(a)(i); and (iii) in respect of the TBM Section of the Tunnel: (A) the "relative production factor" and "relative wear factor" included in item 6.5 of the pricing schedule in Schedule 3 Commercial Schedules for Typical Conditions is 1.00; (B) the "relative production factor" and "relative wear factor" included in item 6.5 of the pricing schedule in Schedule 3 Commercial Schedules for Adverse Conditions is also 1.00; and (C) accordingly, whether or not the actual ground conditions encountered by the Contractor in the TBM Section of the Tunnel are Typical Conditions or Adverse Conditions, the application of the regime in this clause 30.3 will result in Typical Conditions and Adverse Conditions being treated the same. 82 (b) (c) The Contractor: (i) must sample, test and measure the characteristics of ground conditions encountered during the execution of the Work under the Deed in accordance with the procedures set out in Schedule 4 - GBR Administration (or such additional or alternative procedures agreed in writing by the parties); and (ii) acknowledges and agrees that ground conditions encountered will be deemed to be Typical Conditions for the purposes of the Deed unless the Contractor demonstrates, to the Principal‟s Representative‟s reasonable satisfaction, by agreed testing procedures, that the ground conditions encountered are: (A) outside the limits of one or more of the Parameters for Typical Conditions; and (B) within, or in the case of Materially Adverse Conditions beyond, the limits of one or more of the Parameters for Adverse Conditions (where applicable). If the Contractor encounters, in the execution of the Work under the Deed, the types of Site Conditions referred to below, the Contractor must promptly notify the Principal in writing (and in any event within seven days of encountering the relevant Site Conditions and prior to making any Claim): (i) (ii) in respect of any Adverse Conditions or Materially Adverse Conditions, giving full details of: (A) the relevant Site Conditions encountered; and (B) the manner in which they are said to be different from those defined to be Typical Conditions by the GBR, together with information, including records of samples, supporting this contention; and in respect of Materially Adverse Conditions, giving full details of: (A) the effect on the Work under the Deed; (B) the delay (if any) to progress of the Work under the Deed; and (C) any other relevant matters, and the Principal may request the Contractor to provide any further information relating to the circumstances of the relevant Site Conditions encountered and the Contractor must provide such further information within the time reasonably required by the Principal. (d) Subject to the other provisions of the Deed, the Contractor is entitled to payment in connection with actual ground conditions encountered in the Roadheader Section of the Tunnel and TBM Section of the Tunnel and the Shafts as calculated in accordance with the procedures described in Schedule 4 - GBR Administration. 83 (e) Subject to the other provisions of the Deed, the Contractor is entitled to an adjustment to the Date for Substantial Completion and the Date for Practical Completion in connection with actual ground conditions encountered as calculated in accordance with the procedures described in Schedule 4 - GBR Administration. (f) The Contractor acknowledges and agrees that: (g) (h) 30.4 (i) it is solely responsible for dealing with the Site Conditions encountered in a manner so as to minimise any extra costs and in a manner to which the Principal has no objection; and (ii) the Contractor is not entitled to any compensation or adjustment to either the Date for Substantial Completion or the Date for Practical Completion as a result of delay or disruption arising out or in connection with actual ground conditions encountered by the Contractor other than as set out in Schedule 4 - GBR Administration. No claim by the Contractor for an adjustment under this clause 30.3 will be allowed unless: (i) the Contractor has given the written notices (as applicable) under clause 30.3(c)(i) above; and (ii) the Contractor has promptly allowed the Principal‟s Representative to have access to such parts of the Site as are required by the Principal‟s Representative to investigate the Site Conditions the subject of the Contractor‟s notice in clause 30.3(c)(i). No claim by the Contractor for an adjustment under this clause 30.3 will be allowed if it is made after the Principal has issued the Final Payment Certificate. Selection of equipment The Contractor acknowledges that by providing geotechnical information in the Deed (including in the GBR) and otherwise, the Principal is deemed not to have attempted to determine, or assist in, the selection of the size, excavation cutters, consumable parts and other characteristics of the Contractor‟s Construction Plant, including the type of Roadheader equipment, type of TBM or any other equipment necessary to perform the Work under the Deed. The selection of Construction Plant, including type of Roadheader and type of TBM capable of performing the relevant parts of the Work under the Deed, is solely the responsibility of the Contractor. Any errors in selecting any aspect of the Contractor‟s Construction Plant, and any consequences flowing from such selection, will be the Contractor‟s responsibility. Subject to the Contractor‟s express entitlements under Schedule 4 - GBR Administration, the Principal will not accept or consider, and the Contractor will not be entitled to, any Change, extension of time or relief from liquidated damages in respect of the suitability of the type of Roadheader equipment or type of TBM selected or any other Construction Plant necessary to perform the Work under the Deed. 30.5 Dilapidation surveys The Contractor must: 84 (a) have a property condition assessment undertaken in accordance with the requirements of the Specification; and (b) lodge with the Principal‟s Representative a copy of the property condition assessment showing the date of the property condition assessment and signed on behalf of the Contractor by way of acknowledgment that the property condition assessment is true and correct. The Contractor is responsible for any discrepancy between the conditions described in the property condition assessment referred to in this clause 30.5 and the actual condition of any property adjoining or in the vicinity of the Site, to the extent the discrepancy can be attributed to the execution of the Work under the Deed. As soon as practicable, but no later than the Date of Practical Completion, the Contractor must promptly reinstate each such affected property to the condition in which it existed prior to the commencement of the Work under the Deed. 31 Re-Instatement 31.1 32 The parties acknowledge that re-instatement of disturbed artificial surfaces (paving, asphalt, concrete etc) to equivalent conditions as existed prior to the Work under the Deed and in accordance with local council specifications, to the extent the disturbance can be attributed to the execution of the Work under the Deed, forms part of the Work under the Deed and must be undertaken by the Contractor at its cost under arrangements between local councils and the Contractor. Force Majeure 32.1 If either party is prevented, hindered or delayed from or in performing any of its obligations under the Deed by an Event of Force Majeure, it must promptly notify the other party in writing of the occurrence of the Event of Force Majeure and the circumstances as soon as practicable after becoming aware of the Event of Force Majeure and in any case within five days after the occurrence of the Event of Force Majeure. 32.2 The party who has given such notice will be excused from the performance or punctual performance of its obligations under the Deed for so long as the Event of Force Majeure continues and to the extent that such party‟s performance is prevented, hindered or delayed. If applicable, the Date for Substantial Completion, the Date for Practical Completion and the Date for Completion must be extended in accordance with (and subject to) clause 34. 32.3 The party or parties affected by the Event of Force Majeure must use reasonable efforts to mitigate the effect upon its or their performance of the Deed and to fulfil its or their obligations under the Deed, but without prejudice to the Principal‟s right to terminate the Deed under clause 32.6. 32.4 On the cessation of the Event of Force Majeure which is the subject of a written notice given under clause 32.1, the party affected by the Event of Force Majeure must: (a) immediately give written notice to the other party of the cessation of the Event of Force Majeure; and 85 (b) 32.5 33 resume performance of the obligations suspended as a result of the Event of Force Majeure. The Contractor will have no entitlement, and the Principal will have no liability for: (a) any costs, losses, expenses, damages or the payment of any part of the Contract Price relating to work affected by the Event of Force Majeure during any period of Event of Force Majeure (but will, subject to clause 7, be obliged to pay to the Contractor any payments which fall due during such period in respect of work undertaken by the Contractor and included in a Progress Claim prior to the relevant Event of Force Majeure); or (b) any delay costs in any way incurred by the Contractor due to an Event of Force Majeure. 32.6 If the performance of the Work under the Deed is substantially prevented, hindered or delayed for an aggregate period of more than 60 days on account of one or more Events of Force Majeure during the currency of the Deed, the Principal may terminate the Deed by giving a written notice to the Contractor. 32.7 In the event of termination pursuant to clause 32.6, the rights and obligations of the Principal and the Contractor will be as specified in clause 37.2, except that the amount specified in Schedule 1 - Contract Information referred to in clause 37.2(d)(iii) will be nil. Change in the Work under the Deed 33.1 33.2 General (a) The Principal has the right to direct by written notice to the Contractor any Change. (b) The Principal may, prior to giving any such direction, give written notice to the Contractor of its proposal to direct a Change but shall not be obliged to give such notice. (c) Upon receipt of a direction or proposal under this clause 33.1, the Contractor must promptly notify the Principal in writing if it considers that the Change is not technically practicable, taking into account the state of advancement of the Work under the Deed or the technical compatibility of the Change envisaged with the nature of the Work under the Deed as specified in the Deed. (d) The Contractor acknowledges and agrees that directions given to the Contractor by the Principal or the Principal‟s Representative in connection with the Deed will not constitute a Change unless the direction is the subject of a Change Order given pursuant to clauses 33.5 or 33.6 or an Urgent Change Direction under clause 33.7. Proposal by Contractor (a) The Contractor may from time to time during its performance of the Deed propose to the Principal any Change which the Contractor considers 86 necessary or desirable to improve the quality, efficiency or safety of the Work under the Deed. (b) The Principal may, in its absolute discretion and without in any way being obliged to do so, approve any Change proposed by the Contractor by written notice to the Contractor. Any such approval may be given on such conditions as the Principal considers appropriate. (c) The Contractor acknowledges and agrees that if: (i) the Principal approves a Change proposed by the Contractor under this clause 33.2; and (ii) such Change requires amendment to any aspect of the design of the Works which is the Principal‟s responsibility under the Deed so as to enable the Change proposed by the Contractor to be implemented, the amount of any costs (including any consultant‟s costs) incurred by the Principal in amending such design will be a debt due and payable by the Contractor to the Principal. 33.3 Detailed particulars If either party proposes a Change, the Contractor must promptly prepare and furnish to the Principal a written statement setting out detailed particulars of any such Change (and if the Change is proposed by the Contractor, the reasons for the Change), the work and/or Materials and Construction Plant required or no longer required, the increase or decrease in the Contract Price calculated on the basis of the rates in the Contractor's statement under clause 7.2 and Schedule 3.3 - Cost Reimbursable Schedules, any requisite adjustment to the Date for Substantial Completion, the Date for Practical Completion or the Date for Completion and any effect such Change would have on the Work under the Deed or the performance of any of the Contractor‟s other obligations under the Deed. Subject to clause 33.7, the Contractor must not commence any Change without the written approval of the Principal. 33.4 Deductions In determining the deduction to be made for work or services which is taken out of the Deed, or for a Change which results in a saving to the Contractor, the deduction must include an amount for the Contractor‟s Margin. 33.5 Change Order After Proposal If, in the case of a Change proposed by either the Principal or the Contractor, the Principal and the Contractor reach agreement on all matters identified in the written statement furnished by the Contractor pursuant to clause 33.3, the Principal may, if it wishes to proceed with the Change, issue a written Change Order giving effect to the Change. Such Change Order must contain full particulars of the Change, any adjustment of the Contract Price, the Date for Completion and/or the Date for Practical Completion and/or the Date for Substantial Completion and must be signed by the Principal. Such Change will thereupon be deemed to form part of the Work under the Deed. 87 33.6 Change Otherwise Whether or not a Change has been proposed and whether or not the Contractor has furnished a statement under clause 33.3, the Principal may at any time (subject to clause 34.1) give the Contractor a written Change Order directing the Contractor to implement a Change specified in such direction, and the Contractor must comply with any such direction. 33.7 Urgent Change Notwithstanding any other provision of the Deed, the Principal‟s Representative may, by a written form expressly identified as an “Urgent Change Direction,” direct the Contractor to carry out the work described in the Urgent Change Direction and the Contractor must immediately proceed to carry out that work. 33.8 Valuation by Principal’s Representative (a) If a Change is directed by the Principal: (i) pursuant to clause 33.6 or 33.7; or (ii) without agreement having been reached on the valuation of the Change or any other matter relevant to the Change (including any applicable extension or reduction of time), the Principal‟s Representative must value the Change and those other matters and, subject to the parties‟ rights to refer any aspect of such valuation to dispute resolution under clause 40, the Contract Price and the Date for Substantial Completion, the Date for Practical Completion and the Date for Completion must be adjusted accordingly. (b) For the purpose of this clause 33.8: (i) the Principal‟s Representative must value any Change in accordance with the rates and prices set out in: (A) the detailed statement provided by the Contractor under clause 7.2; and (B) Schedule 3 - Commercial Schedules, to the extent that the Principal‟s Representative determines that those rates and prices are applicable to the Change; (ii) (iii) where the Principal‟s Representative determines that the rates and prices do not apply to a Change: (A) the Principal‟s Representative and the Contractor must attempt to agree on the value of the Change; or (B) failing agreement, the Principal‟s Representative must use reasonable rates (exclusive of GST); the allowance for overhead and profit applying to any Change will be calculated by multiplying the Contractor‟s Margin to the sum of the rates and prices determined in accordance with clause 33.8(b)(i) or 88 clause 33.8(b)(ii) to the extent those rates and prices do not include provision for the Contractor‟s overhead and profit; and (iv) 34 the Contractor is not entitled to any extension of time unless: (A) in the case of a Change proposed by the Principal in respect of which the Contractor is obliged to prepare a statement under clause 33.3, details of the need for an adjustment to the Date for Substantial Completion, the Date for Practical Completion and/or the Date for Completion are set out in such statement; and (B) in the case of any other Change directed by the Principal, the Contractor has given notice under clause 34 of the likely delay to the progress of the Work under the Deed prior to commencing to comply with the direction. Extension of Time 34.1 Application of clause 34 (a) 34.2 The Contractor acknowledges and agrees that: (i) it has no entitlement under this clause 34 to an extension of time for delay arising out of or in connection with Site Conditions; and (ii) clause 30.3 and Schedule 4 - GBR Administration regulate the Contractor‟s sole entitlement to any adjustment to the Date for Substantial Completion, Date for Practical Completion and Date for Completion (as the case may be) arising out of or in connection with actual ground conditions encountered during the execution of Work under the Deed comprising Separable Portion 1. Notice of Delay (a) The Contractor must immediately notify the Principal‟s Representative of all incidents and/or events of whatsoever nature affecting or likely to affect the progress of the Work under the Deed, including delays in obtaining data and information necessary for the performance of the Work under the Deed, the supply or transportation of Materials or Construction Plant, strikes or disruption of the Work under the Deed involving employees and/or agents of the Contractor and Subcontractors engaged in the performance of the Work under the Deed and hidden obstacles or obstructions on Site. Notice under this clause 34.2(a) will not entitle the Contractor to any extension of time and any such entitlement must be determined strictly in accordance with the following provisions of this clause 34. (b) The Contractor must at all times keep the Principal‟s Representative informed of any actual delay to the progress of the Work under the Deed and the effect on the Work under the Deed of any event which has been the subject of a notice under clause 34.2(a). (c) Without limiting clause 34.2(b), within 10 days after any event referred to in a notice under clause 34.2(a) which has affected the progress of the Work 89 under the Deed has ceased to have effect, the Contractor must give a further notice to the Principal‟s Representative: 34.3 (i) setting out the material circumstances including the cause or causes and the nature and extent of the delay to the progress of the Work under the Deed and detailing the corrective action already undertaken or to be undertaken by the Contractor; and (ii) if the event is one listed in clause 34.4 as a cause entitling the Contractor to an extension of time (but not otherwise), stating the period by which in its opinion the Date for Substantial Completion, the Date for Practical Completion and the Date for Completion should be extended. Determination of Extension of Time (a) The Principal‟s Representative must, within 30 business days of receipt of notice under clause 34.2(c) pursuant to which a claim is made for an extension of time: (i) request the Contractor to provide further details relating to the claim; or (ii) notify the Contractor‟s Representative whether an extension of time is to be granted or not and, if so, its determination as to the period, if any, by which the Date for Substantial Completion, the Date for Practical Completion and the Date for Completion are to be extended. (b) If a request is made under clause 34.3(a)(i), the Contractor must provide such details within five business days, and the Principal must thereafter determine the Contractor‟s claim and give notice under clause 34.3(a)(ii) to the Contractor as soon as practicable and in any event within 10 business days. Nothing in this clause 34.3 will oblige the Principal‟s Representative to request further information from the Contractor and the onus will at all times remain with the Contractor to establish all elements necessary to establish its entitlement to an extension of time. (c) If the Principal‟s Representative: (i) does not make a request or give a notice within the period referred to in clause 34.3(a); or (ii) if applicable, does not give a notice within the period referred to in clause 34.3(b), the Contractor must within seven days of the expiry of that period give written notice to the Principal and the Principal‟s Representative requesting the Principal‟s Representative to make such a request or give such a notice. (d) Subject to clause 34.3(e), if the Principal‟s Representative does not make a request or give a notice within seven days of receipt of a written notice from the Contractor under clause 34.3(c) the Date for Substantial Completion, the Date for Practical Completion and the Date for Completion are extended by the period stated in the Contractor‟s notice given under clause 34.2(b). 90 (e) 34.4 If the Date for Substantial Completion, the Date for Practical Completion and the Date for Completion are extended in accordance with clause 34.3(d), the Principal may, if it does not agree with that extension, refer the matter for dispute resolution in accordance with clause 40. Causes of delay Subject to clause 35 and without limiting the separate operation of clause 4.1A(f)(ii), the Contractor will be entitled to a reasonable extension of time to any or all of the Date for Substantial Completion, the Date for Practical Completion or the Date for Completion, subject to the other provisions of this clause 34, only where the Contractor reasonably satisfies the Principal‟s Representative that: (a) Substantial Completion, Practical Completion or Completion (as applicable) have actually been delayed; (b) the delay is demonstrable on an assessment of the critical path of the network of the revision of the Contract Programme last submitted under clause 15.1(b) when the delay first arose; (c) the cause of the delay is not in any way connected with an act of, or omission by, the Contractor or its Subcontractors; and (d) the delay is caused by any of the following events: (i) any breach by the Principal or the Principal‟s Representative of its obligations under the Deed; (ii) an act or omission of the Principal or the Principal‟s Representative (excluding an act or omission which relates to the exercise of the Principal's or the Principal's Representative's express rights or powers under the Deed); (iii) an act or omission of a Separate Contractor; (iv) a Change (other than as contemplated in clause 33.8(b)(iv)); (v) an order to suspend the execution of the Work under the Deed pursuant to clause 36, except where such order is caused by an act or omission of the Contractor; (vi) an Event of Force Majeure; (vii) suspension by the Contractor of the performance of the Work under the Deed where entitled to do so under section 27 of the Security of Payment Act; (viii) the cause of delay contemplated by clause 19.7(a)(ii); (ix) an event which entitles an adjustment to the Date for Substantial Completion and the Date for Practical Completion in accordance with clause 30.3; (x) delays as a result of state or industry wide Industrial Relations disputes; 91 34.5 (xi) changes to the GHG Legislation or the NGER Act after the date of the Deed; (xii) changes in law after the date of the Deed other than those described in clause 34.4(d)(xi); (xiii) the cause of delay contemplated by clause 19.3(c). Extension of Time without claim Notwithstanding any other provisions of this clause 34, if there is a delay to any Work under the Deed for which the Contractor is not entitled to an extension of the Date for Substantial Completion, the Date for Practical Completion or the Date for Completion, the Principal or the Principal‟s Representative may grant, but has no obligation to grant, nor to consider whether it should grant, an extension to the Date for Substantial Completion, the Date for Practical Completion and the Date for Completion (as the case may be). 34.6 Best endeavours The Contractor must constantly use its best endeavours to avoid delay in the progress of the Work under the Deed. 34.7 Concurrent delays If there are two or more concurrent causes of delay and at least one of those concurrent causes is not a cause of delay which would entitle the Contractor to an extension of time under clause 34.4, the Contractor is not entitled to an extension of time to the extent that the causes are concurrent. 34.8 Conditions Precedent to extension of time It is a condition precedent to any entitlement of the Contractor to an extension of time that: 34.9 (a) the Contractor has given notice under clause 34.2(c) claiming an extension of time within the period stated in that clause; (b) if the cause is one described in clause 34.4(d)(i), the Contractor has given notice under clause 34.2(a) either before the event has caused delay to the Work under the Deed or within 24 hours of reasonably becoming aware that the relevant event was likely to delay the progress of the Work under the Deed, whichever is the later; and (c) the Contractor has taken all reasonable measures both to preclude the occurrence of the cause of delay and to avoid or minimise its consequences and, in respect of Separable Portion 3, to reprogram the sequence of activities with a view to minimising the delay to the Work under the Deed (including carrying out any activities in parallel with the Work under the Deed for Separable Portions 1 and 2 without incurring demonstrated additional costs to the Contractor). Delay Costs (a) Subject to clauses 30.3(e) and 34.9(b) and Part 5 of Schedule 4 - GBR Administration, the Contractor accepts the risk of all increased costs 92 resulting from delay in the execution of the Work under the Deed and the performance of its other obligations under the Deed with the exception of a delay directly caused by: (i) a breach by the Principal or the Principal‟s Representative of its obligations under the Deed; (ii) the suspension of the execution of the Work under the Deed (or any part of the Work under the Deed) pursuant to a written order issued under clause 36 except where such order was issued as a result of a breach by an act or omission of the Contractor; (iii) a Change; (iv) a suspension by the Contractor of the performance of the Work under the Deed where entitled to do so under section 27 of the Security of Payment Act; (v) the cause of delay contemplated by clause 19.3(c); (vi) subject to clause 34.9(d), the cause of delay contemplated by clause 19.7(a)(ii); and (vii) the causes of delay contemplated by clause 34.4(d)(iii) or clause 34.4(d)(xi), in respect of which the Contractor has been granted an extension of time under the Deed. (b) Subject to clauses 30.3(d) and Part 4 of Schedule 4 - GBR Administration, the Principal and the Contractor acknowledge and agree that the Contractor‟s sole entitlement to recover from the Principal any compensation incurred as a result of delay or disruption to the execution of the Work under the Deed is limited to the amount determined in accordance with Schedule 1 - Contract Information and the Contractor has such entitlement only if: (i) there is a delay in achieving Substantial Completion or Practical Completion or Completion for which the Contractor has been granted an extension of time under clause 34.3; and (ii) the Contractor has used reasonable endeavours to mitigate the delay costs. (c) The Principal‟s Representative must give a written notice to the Contractor adjusting the Contract Price to reflect the amount of delay costs referred to in clause 34.9(b). (d) The Contractor accepts the risk of all increased costs resulting from delay in the execution of the Work under the Deed and the performance of its other obligations under the Deed for the first 8 weeks of any extension of time granted for the cause of delay referred to in clause 34.4(d)(viii). 93 35 Acceleration 35.1 The Principal‟s Representative may direct the Contractor to do any or all of the following: (a) alter the sequence of activities comprised in the Work under the Deed from that shown in the Contract Programme; (b) accelerate the progress of any one or more of such activities so as to complete such activities in advance of the dates for completion of those activities shown on the Contract Programme; and (c) overcome or minimise the extent and effects of some or all of a delay, including to achieve Substantial Completion by the Date for Substantial Completion and Practical Completion by the Date for Practical Completion, if the Contractor submits a notice under clause 34.1 or clause 34.2. 35.2 A direction given under clause 35.1 may only be effected by a written form expressly identified as “Acceleration Direction” signed by the Principal‟s Representative and given to the Contractor. 35.3 Before issuing an Acceleration Direction, the Principal‟s Representative may issue a written form, expressly identified as an “Acceleration Direction Information Request”, advising the Contractor of the proposed actions and requiring the Contractor, within the time specified, to: (a) advise whether it is practicable to accelerate the Work under the Deed, and (b) if it is practicable to accelerate the Work under the Deed: (i) provide an estimate of the valuation of the proposed acceleration and any adjustment to the Contract Price; and (ii) provide an estimate of the effect the proposed acceleration will have on the time for achieving Substantial Completion and Practical Completion (as applicable), including the earlier date. 35.4 Within the time specified in the Acceleration Direction Information Request, the Contractor must provide the required information to the Principal‟s Representative in writing. 35.5 The Contractor must (where practicable) execute the Work under the Deed in accordance with an Acceleration Direction. 35.6 The Contractor is entitled to payment of the additional direct and reasonable costs incurred as a result of complying with an Acceleration Direction, except to the extent the Acceleration Direction is given as a result of, or in connection with, an act or omission of the Contractor. 35.7 The Principal‟s Representative and the Contractor‟s Representative must attempt to agree on the payment to which the Contractor will be entitled under clause 35.6 as a result of complying with an Acceleration Direction under clause 35.1. If the Principal‟s Representative and the Contractor‟s Representative agree on that payment, the Principal‟s Representative must give a written notice to the Contractor 94 setting out the adjustment to the Contract Price. If the Principal‟s Representative and the Contractor‟s Representative fail to reach agreement within seven days of the issue of the Acceleration Direction, the Principal‟s Representative may determine the amount payable and give a written notice to the Contractor setting out the adjustment to the Contract Price. 35.8 36 37 The Principal and the Contractor acknowledge and agree that the Principal‟s Representative may issue an Acceleration Direction in accordance with this clause 35 in lieu of the Contractor‟s entitlement to an extension of time under clause 34. Suspension 36.1 The Principal may by written notice to the Contractor order the Contractor to suspend performance of all or any of its obligations under the Deed. Such notice must specify the obligation the performance of which is to be suspended, the effective date of the suspension and the reasons for the suspension. The Contractor must thereupon suspend performance of such obligation (except those obligations which are necessary for the care, safety or preservation of the Works) until ordered in writing to resume such performance by the Principal. 36.2 If the Contractor‟s performance of its obligations is suspended pursuant to this clause 36, the Date for Substantial Completion, the Date for Practical Completion and the Date for Completion may, subject to the provisions of clause 34, be extended in accordance with clause 34. 36.3 The Contractor may suspend the performance of any part of the Work under the Deed only where it is ordered to do so under clause 36.1 or it has a statutory entitlement to do so. Termination 37.1 Termination for the Contractor’s Default (a) (b) The Principal, without prejudice to any other rights or remedies it may possess, may immediately either terminate the Deed or determine the Contractor‟s engagement under the Deed and take over the whole of the work remaining to be completed in the following circumstances by giving a written notice to the Contractor referring to this clause 37.1(a) and its reasons for giving the notice: (i) if an Insolvency Event occurs with respect to the Contractor; (ii) if the Contractor assigns any right or interest under the Deed in breach of clause 39.1; or (iii) if the Contractor has abandoned the Work under the Deed or repudiated the Deed. Without limiting or otherwise affecting the Principal‟s rights at general law, if the Contractor: 95 (i) has without valid reason failed to commence the Work under the Deed promptly or has suspended any part of the Work under the Deed in breach of clause 36.3; (ii) defaults in the performance of any provision of the Deed; or (iii) without limiting clause 37.1(b)(ii), fails to comply with any of its safety obligations under the Deed, the Principal may, without prejudice to any other rights or remedies it may possess, give a written notice to the Contractor stating the nature of the default and requiring the Contractor to remedy the same. (c) (d) If the Contractor fails to remedy a default of which it has been given notice under clause 37.1(b), or show cause why the Principal should not terminate the Deed or take the Work under the Deed (or any part of the Work under the Deed) out of the Contractor‟s hands within 10 days of its receipt of such notice, the Principal may immediately: (i) terminate the Deed by giving a written notice of termination to the Contractor referring to this clause 37.1(c); or (ii) by written notice to the Contractor take out of the hands of the Contractor either the whole of the Work under the Deed remaining to be completed or such works as are specified in the notice. Upon receipt of notice of termination (whether under the above provisions or otherwise) or notice of taking over the Work under the Deed under clause 37.1(a) or clause 37.2(a), the Contractor must either immediately or upon such date as is specified in the relevant notice: (i) cease all further work, except for: (A) such work as the Principal may specify in a notice of termination for the sole purpose of protecting that part of the Work under the Deed already executed; or (B) any work required to leave the Site in a clean and safe condition; or (C) where the Principal takes over part only of the Work under the Deed, any remaining work which is not within the scope of the Principal‟s notice; (ii) terminate all subcontracts, except those to be assigned to the Principal pursuant to paragraph (iv) below or those necessary to perform any work referred to in paragraph (i) above; (iii) deliver to the Principal the parts of the Work under the Deed executed by the Contractor up to the date of the Principal‟s notice; (iv) to the extent legally possible, assign or transfer to the Principal all right, title and benefit of the Contractor to the Work under the Deed and in the Materials and Construction Plant as at the date of the Principal‟s notice and, as may be required by the Principal, in any subcontracts concluded between the Contractor and its 96 Subcontractors or other agreements entered into for the purpose of the Work under the Deed, including the benefit of all warranties obtained by the Contractor; (v) where anything referred to in paragraph (iv) above cannot be assigned or transferred to the Principal: (A) hold the right, title and interest of the Contractor in the agreement or warranty for the benefit of the Principal, and do any act or thing reasonably requested by the Principal in respect of the agreement or warranty; and (B) where any Construction Plant is leased to the Contractor, sub-lease such Construction Plant to the Principal at no cost to the Principal; (vi) deliver to the Principal all drawings, specifications and other documents prepared by the Contractor or its Subcontractors in connection with the Work under the Deed as at the date of the Principal‟s notice and all Government Approvals held by the Contractor; and (vii) if required by the Principal, novate to the Principal any subcontracts or other agreements in relation to the Work under the Deed. (e) The Contractor hereby irrevocably (for valuable consideration) appoints the Principal as its lawful attorney for the purpose of executing any documents on behalf of the Contractor necessary to give effect to clause 37.1(d). (f) Upon termination or taking over the Work under the Deed or part of the Work under the Deed under clause 37.1(a) or 37.1(c), the Principal is not obliged to make any further payment to the Contractor until the whole of the Work under the Deed is completed. (g) When the Principal completes the Work under the Deed, the cost of completing the Work under the Deed by the Principal must be determined by the Principal‟s Representative. (h) If the sum which the Contractor has been paid up to the date of the Principal‟s notice under clause 37.1(a) or 37.1(c), plus the reasonable costs incurred by the Principal, in completing the Work under the Deed exceeds the Contract Price, the Contractor is liable to the Principal for such excess which will be a debt due and payable within 30 days of the Principal‟s Representative‟s determination under clause 37.1(g). The Contractor is liable to the Principal for any costs, losses, expenses or damages incurred by the Principal arising out of the Contractor‟s breach or the termination of the Deed (if applicable). (i) If clause 37.1(h) does not apply, subject to clause 7.9, the Contractor is entitled to be paid the portion of the Contract Price attributable to the Work under the Deed executed as at the date of termination and the value of any unused or partially used Materials on the Site. Any sums due to the Principal from the Contractor accruing prior to the date of the Principal‟s notice under 97 clause 37.1(a)) or 37.1(c) must be deducted from the amount to be paid to the Contractor under this clause 37.1(i). (j) 37.2 Notwithstanding any termination of the Deed under this clause 37.1, any dispute concerning the amount payable by the Principal or the Contractor under clause 37.1(h) or 37.1(i) must be referred to dispute resolution under clause 40. Termination by the Principal for convenience (a) Notwithstanding any other provision of the Deed: (i) the Principal may at its sole discretion terminate the Deed by giving 28 days‟ written notice to the Contractor; and (ii) the Contractor must: (A) cease the execution of the Work under the Deed within the time specified in the written notice; and (B) ensure that the Site is left in a clean and safe condition and the Work under the Deed is properly secured. (b) If for any reason a purported termination under clause 37.1 by the Principal is held to be ineffective, the purported termination is not a breach or repudiation of the Deed and must be treated to have been effected under clause 37.2(a). (c) If the Deed is terminated pursuant to clause 37.2(a), the Contractor may, after demobilisation from the Site, submit a statement in a form approved by the Principal‟s Representative showing: (i) the value of Work under the Deed completed by the Contractor to the date of termination; and (ii) except to the extent already covered under clause 37.2(c)(i), the cost of materials ordered for the Work under the Deed to the extent the Contractor cannot cancel such orders provided that: (iii) (d) (A) upon payment by the Principal, the unencumbered title to the materials passes to the Principal; and (B) the materials have not been prematurely ordered; and reasonable demobilisation costs incurred by the Contractor. Following receipt of a statement provided in accordance with clause 37.2(c), the Principal‟s Representative must, within 14 days, determine the amount payable in respect of that statement and issue a certificate to the Principal and the Contractor setting out that determination showing: (i) the Principal‟s Representative‟s assessment of the value of the items stated in the statement provided in accordance with clause 37.2(c); (ii) the value of the Work under the Deed completed by the Contractor, assessed by the Principal‟s Representative and taken into account in 98 determining the amount certified for payment to the Contractor by the Principal or to the Principal by the Contractor, as the case may be, in the last certificate issued pursuant to clause 7.3(c) or 7.4(b); (e) (f) 38 (iii) the amount specified in Schedule 1 - Contract Information; (iv) any moneys which have been previously set-off or deducted under clause 7.6; (v) any moneys which are due or which may become due from the Contractor to the Principal in respect of the Deed or the Work under the Deed; and (vi) the amount certified as then being due for payment to the Contractor by the Principal or to the Principal by the Contractor, as the case may be. The Contractor must give the Principal: (i) a Valid Tax Invoice in respect of the amount certified as then being due for payment to the Contractor by the Principal plus any amount in respect of GST to which the Contractor is entitled under clause 9.2 within two days of receipt of that certificate; and (ii) before it receives a payment under clause 37.2(f), the written statement and statutory declaration referred to in clause 7.3(e). Subject to clause 7.9, where an amount is due from the Principal to the Contractor in respect of a certificate issued pursuant to clause 37.2(d), the Principal must pay the Contractor the amount certified as payable by the Principal‟s Representative under clause 37.2(d) by the later of: (i) 30 days after receipt by the Principal‟s Representative of the statement provided in accordance with clause 37.2(c); and (ii) the receipt by the Principal‟s Representative of the Valid Tax Invoice, statement and statutory declaration referred to in clause 37.2(e)(ii). (g) Where an amount is due from the Contractor to the Principal in respect of a certificate issued pursuant to clause 37.2(d), the Contractor must, within 30 days after receipt of that certificate, pay the Principal the amount stated in that certificate as due from the Contractor to the Principal. (h) The Contractor is not entitled to any other compensation, including any consequential costs, losses or damages. Notices 38.1 Unless otherwise stated in the Deed, all notices to be given under the Deed must be in writing, and sent by personal delivery, post, courier or facsimile to the address of the relevant party provided that: 99 39 (a) any notice sent by facsimile must be confirmed within two days after dispatch by notice sent by post or courier; (b) any notice sent by post or special courier will be deemed (in the absence of evidence of earlier receipt) to have been delivered three days after dispatch and in proving the fact of dispatch it will be sufficient to show that the envelope containing such notice was properly addressed, stamped and conveyed to the postal authorities or courier service for transmission by post or special courier; and (c) any notice delivered personally or sent by facsimile will be deemed to have been delivered on the date of its dispatch if a business day, otherwise on the next business day. 38.2 Either party may, by notice to the other party, change its postal or facsimile address or addressee for the receipt of notices to be given under the Deed. If a party changes its address it must give prompt notice of the change to the other party. 38.3 In the Deed, notices include any approvals, consents, instructions, orders, requests, certificates or other communication to be given under the Deed. Assignment and change 39.1 Subject to clause 39.2, neither party may assign any interest or right arising under the Deed without the consent of the other party. 39.2 The Principal may: (a) assign the benefit of the Deed to an Affiliate of the Principal without the consent of the Contractor; or (b) with the consent of the Contractor (such consent not to be unreasonably withheld or delayed), assign, novate, transfer, mortgage, charge, encumber or otherwise deal with the Deed, any security or any of its interests, rights or obligations under or in connection with the Deed at any time to: (i) any government owned entity or entities that the New South Wales Government nominates to assume any part or all; or (ii) any other party that the New South Wales Government nominates to assume a substantial part or all, of the Principal's functions, rights or obligations (including as set out in clause 39.6) (a Purchaser) and the Contractor must, if requested by the Principal, execute a deed on terms reasonably required by the Principal giving effect to the assignment, novation, transfer, charge, mortgage, encumbrance or other dealing. 39.3 The Contractor must not create any Security Interest, or allow any Security Interest to subsist, over the Deed, without the Principal‟s written approval. 39.4 Without limiting clause 39.2, if requested by the Principal, the Contractor must, subject to the Principal not being in material breach of any provision of the Deed, enter into an agreement pursuant to which the Deed is novated by the Principal to a 100 person of equivalent financial standing to the Principal, and reasonably acceptable to the Contractor, acting reasonably. 39.5 39.6 39.7 If the Principal assigns or novates the Deed in accordance with this clause 39, the Contractor agrees that it will: (a) provide substitute unconditional undertakings in favour of the person to whom the Deed is assigned or novated for those held by the Principal in accordance with clause 8. The form and issuer of the substitute unconditional undertakings must satisfy the requirements of clause 8; and (b) extend all relevant insurance policies effected under the Deed to name the party to which the Deed is novated under clause 39.4 as a named insured. The Contractor acknowledges that: (a) the Principal may be reconstituted, renamed, dissolved, replaced or restructured and that some or all of the powers, functions, assets, liabilities or responsibilities of the Principal (the Principal's Assets) may be transferred to or vested in another entity (an Entity); (b) the Principal may, or may be required to (including as a result of changes to New South Wales Government policy or directions) add to, or dispose of, any property or assets forming part of the Principal's Assets; (c) any such change to the Principal's Assets may involve amendment to the Contractor's rights and obligations under the Deed (where any such amendment will be deemed to be a Change and clause 33 (including clauses 33.3 and 33.8) applies); and (d) other than as contemplated in clause 39.6(c), the Contractor shall not have, and the Principal shall not be liable for, any claim or action whatsoever as a result of the changes to the Principal's Assets referred to in this clause 39.6. The Contractor acknowledges that: (a) the Principal may, or may be required to, provide the benefit of any or all of its rights under or in connection with the Deed to: (i) TRUenergy Pty Ltd as purchaser of the Principal's retail business; (ii) any Purchaser or Purchasers referred to in clause 39.2; or (iii) any Entity or Entities referred to in clause 39.6(a), for the purpose of any current or future arrangements between the Principal and any or all of the parties referred to in clauses 39.7(a)(i), 39.7(a)(ii) or 39.7(a)(iii) for the provision of transitional services by the Principal to any or all of those parties. If, by Ausgrid providing the benefit of any or all of its rights under or in connection with the Deed as contemplated by this clause 39.7(a), there is any change in the Contractor's obligations under the Deed, then any such change will be deemed to be a Change and clause 33 (including clauses 33.3 and 33.8) applies; and 101 (b) 40 other than as contemplated in clause 39.7(a), the Contractor shall not have, and the Principal shall not be liable for, any claim or action whatsoever as a result of any of the matters referred to in clause 39.7(a). Claims and Dispute Resolution 40.1 Claims, Other Claims and time bars Definitions (a) For the purposes of this clause 40: (i) a “Claim” means any claim for money or time in connection with the Deed or a Change directed under clause 33, other than Other Claims; and (ii) “Other Claims” means claims for payment made pursuant to clause 7 or claims for extensions of time made pursuant to clause 34. Notification of Claims (b) All Claims must initially be made to and considered by the Principal‟s Representative in accordance with the Deed. (c) The Contractor must ensure that all Claims are delivered to the Principal‟s Representative in the form and containing such details as stipulated in the Deed. If the Deed does not specifically stipulate the form or detail required for a Claim, the Claim must be in writing and clearly identify the factual and legal bases for the Claim, the quantification of the Claim (or if the Contractor is unable to quantify the Claim, the Contractor‟s best estimate of the value of the Claim) and the calculations and methodology used in arriving at the quantification (or estimate). Time bars (d) Time bars will apply at two stages: (i) the initial occurrence of the facts or events giving rise to a Claim (as set out in clauses 40.1(e) and 40.1(f)); and (ii) the time at or within which a dispute must be referred to the dispute resolution process after the Claim or the Other Claim has been rejected by the Principal‟s Representative (as set out in clause 40.1(i)). (e) A notice of Claim in accordance with clause 40.1(c) must be given to the Principal‟s Representative within 10 business days of the occurrence of the facts and circumstances on which the Claim is based. (f) The 10 day time bar referred to in clause 40.1(e) will commence to run in the manner set out below. If the basis of the Claim can be construed as being more than one of the bases set out below, the time bar will commence to run from the first of the bases to occur: 102 (g) (i) if the Claim is based on a direction from the Principal or the Principal‟s Representative, then from the date of the Contractor‟s receipt of the direction; (ii) if the Claim is based on a breach of the Deed, then from the date on which the breach is alleged to have occurred; (iii) if the Claim is based on tort, then from the date on which the tortious act or breach of duty is alleged to have occurred; (iv) if the Claim is based on a breach of statute, then from the date on which the statute is alleged to have been breached; or (v) if the Claim is based on an equitable or restitutionary principle, then from the date on which the last of the facts alleged to give rise to the Claim occurred. The Principal‟s Representative must: (i) notify both parties in writing of its determination in respect of a Claim within a reasonable time (not exceeding 20 business days from receipt of the Claim), providing reasons for the determination; and (ii) deal with Other Claims in accordance with the relevant provisions of the Deed. Notification of disputes (h) If the Principal‟s Representative rejects a Claim or an Other Claim (as the case may be), in whole or part, the rejected portion of the Claim or the Other Claim may become the subject of a dispute. (i) If the Contractor or the Principal wishes to dispute the Principal‟s Representative‟s determination of a Claim or an Other Claim, that party must deliver to the Principal‟s Representative and the other party a notice setting out the legal and factual bases of the dispute and the portion of the Principal‟s Representative‟s determination that it wishes to refer to dispute within 15 business days of the issue of the Principal‟s Representative‟s determination. Bar on Claims and Other Claims (j) If a party fails to comply with the time bars set out in this clause, all Claims and, in the case of clause 40.1(h), Other Claims arising out of the facts and circumstances which gave rise to the Claim or the Other Claim will be barred and extinguished. (k) The time bars set out in this clause 40.1 are in addition to and will not derogate from any specific time bars or timing requirements set out in the Deed. 103 40.2 Dispute Resolution Board (DRB) Appointment (a) A DRB will be jointly established by the parties to assist in the resolution of disputes. (b) The DRB will comprise three suitably qualified persons (“the members”). Each party must nominate one member for approval by the other party. The parties must consult both these members and agree upon the third member, who will be appointed to act as chairman. The parties must have regard to the selection criteria and procedures set out in Schedule 12 - DRB Appointment and Operating Procedures. (c) The parties acknowledge and agree that: (d) (i) the Principal, the Contractor and the three DRB members must enter into the DRB Appointment Agreement in the form of Schedule 13 DRB Appointment Agreement, with such amendments as are agreed between them, within two weeks after the selection and approval of the third DRB member; (ii) the DRB Appointment Agreement will formalise the creation of the DRB and establish the scope of its service, and the related rights and responsibilities of the parties; (iii) the DRB Appointment Agreement and clauses 40.1 to 40.3 are not an arbitration agreement within the meaning of section 4 of the Commercial Arbitration Act 2010 (NSW); and (iv) the Commercial Arbitration Act 2010 (NSW) does not apply to any determination made by the DRB under the Deed. The DRB will be dissolved as of the date of final payment to the Contractor under clause 7.5(g) or to the Principal under clause 7.5(h) (as the case may be), unless the DRB is earlier terminated or dissolved by mutual agreement of the Principal and the Contractor. Purpose (e) The DRB, as an independent third party, will assist in and facilitate the timely resolution of disputes between the Principal and the Contractor that are referred to the DRB under clause 40.3(c), in an effort to achieve a just and speedy resolution of the real issues in dispute between the parties and minimise delay to the Project. (f) The primary functions of the DRB are: (i) to impartially consider the dispute referred to it; and (ii) to provide a written recommendation for resolution of the dispute to the Principal and the Contractor. 104 Operation (g) The DRB must agree and provide the Principal and the Contractor with a written copy of the DRB operating procedures consistent with the rules and procedures contained in clauses 40.2 and 40.3 and Schedule 12 - DRB Appointment and Operating Procedures. (h) The parties must use all reasonable endeavours to keep the DRB informed of construction activity and other developments by means of timely transmittal of relevant information prepared by the Principal and the Contractor in the normal course of construction, including progress reports, minutes of Project Control Group meetings, updates to the Contract Programme, Other Claims and Claims submitted by the Contractor. (i) The DRB must visit the Site and meet with representatives of the Principal and the Contractor no less frequently than three monthly intervals or otherwise as requested by both the Principal and Contractor, and at times of significant construction milestones nominated in the Contract Programme. The frequency and scheduling of these visits will be as agreed among the Principal, the Contractor and the DRB, depending on the progress of the Work under the Deed. In case of failure to agree, the DRB will schedule the visits. (j) Each meeting of the DRB will consist of an informal round table discussion followed by field observation of the Work under the Deed. The round table discussion may be attended by no more than two representatives each of the Principal and the Contractor, unless otherwise agreed by the DRB. The agenda will generally include the following: (i) opening remarks by the chairman; (ii) Contractor discussion items: (iii) (iv) (A) work accomplished since the last meeting; (B) current status of the Contract Programme and schedule for future work; (C) anticipated or potential disputes and proposed solutions; and (D) status of current and potential disputes, Claims and other controversies; Principal discussion items: (A) the Contract Programme; (B) perspectives on potential disputes, Claims and other controversies; and (C) status of current and past disputes, Claims and other controversies; such other items as the parties may wish to discuss with the DRB; and 105 (v) 40.3 tentative date for next meeting(s). (k) The Principal‟s Representative must prepare minutes of all meetings and circulate them for comment, revisions and/or approval of the parties and the DRB. (l) The field observations of the DRB will cover all active segments of the Work under the Deed. The DRB must be accompanied by representatives of both the Principal and Contractor. (m) The Principal, at its own expense, will provide the DRB with administrative services, such as conference facilities and secretarial support, as specified in the DRB Appointment Agreement. Review of disputes by Dispute Resolution Board (a) The Principal and the Contractor must co-operate to ensure that the DRB considers disputes promptly, taking into consideration the particular circumstances and the time required to prepare appropriate documentation. (b) Procedures and time periods referred to in this clause 40.3 may be modified by mutual agreement in writing of the parties and the DRB. Requesting Review (c) Either party may refer a dispute to the DRB by notice in writing to the chairman of the DRB, provided that, prior to referring the dispute to the DRB: (i) the parties have followed the express provisions of the Deed in relation to Other Claims and the Principal‟s Representative has made a determination in respect of such claims; or (ii) if the dispute relates to a Claim made under clause 40.1, the Principal‟s Representative has given its determination of the Claim in accordance with the procedures in clause 40.1. The request for review must state clearly and in full detail: (iii) the specific details of the dispute to be considered by the DRB; and (iv) a recommendation as to whether it should be heard at the next regular DRB meeting or at a special meeting. A copy of the request for review must be simultaneously provided to the other party. (d) Upon receipt of a request for review, the DRB chairman will confer with both parties and: (i) establish a submissions schedule so that adequate time is allowed for the other party to respond to the requesting party's statement and for the DRB members to review both statements and the supporting documentation before the next meeting of the DRB; and (ii) schedule a meeting date. 106 Suspension of Review (e) If a party becomes aware that the whole or part of a dispute referred to the DRB under clause 40.3(c): (i) has not been referred to the Principal‟s Representative for prior determination as required under the Deed; or (ii) is the subject of an adjudication application under the Security of Payment Act, that party must immediately give notice of that fact to the other party and the DRB (f) Within two business days of receipt of a notice under clause 40.3(e), the parties must meet to determine whether, and to what extent, the DRB will continue its review of a dispute the subject of a notice under clause 40.3(e). (g) Unless the parties mutually agree to suspend the DRB process (in which case the parties must notify the DRB in writing of their election to suspend the DRB process in respect of a dispute the subject of a notice under clause 40.3(e)), the DRB will continue to review that dispute unless and until such time as it receives a written notice from both parties requesting the DRB to cease it review of the dispute. Pre-meeting Requirements (h) Concise written position statements must be prepared by both parties, with page number references to any supporting documentation, and submitted by each party to each DRB member and to the other party in accordance with the schedule established under clause 40.3(d)(i). (i) A single and complete compilation of supporting documentation, with pages consecutively numbered for ease of reference, must be used. The parties must cooperate in compiling and submitting this documentation to each DRB member for review before the next DRB meeting. (j) For the purpose of position statements and supporting documentation under clauses 40.3(h) and 40.3(i): (k) (i) a copy of any prior determination by the Principal‟s Representative in respect of the subject matter of the dispute (including all supporting documentation considered by the Principal‟s Representative in reaching its determination) must be provided to the DRB; and (ii) the Contractor acknowledges and agrees to provide the Principal with the Contractor‟s Cost Report (in both electronic and hard copy format) upon request by the Principal. Subject to clause 40.3(s)(i), the parties acknowledge and agree that, if the whole or any part of a dispute has previously been the subject of an adjudicator‟s determination under the Security of Payment Act, the parties must not provide the DRB with a copy of the adjudicator‟s determination, including reasons. 107 Meeting (l) The parties acknowledge and agree that: (i) typically, meetings of the DRB will be conducted at the Site office of the Principal‟s Representative; (ii) a location away from the Site office of the Principal‟s Representative is satisfactory for meetings of the DRB if it is more convenient to all concerned and that location still provides all required facilities and access to necessary documentation; and (iii) private sessions of the DRB may be held at any convenient location. (m) The Principal and the Contractor may have no more than two representatives at all meetings (unless otherwise agreed by the DRB), other than private sessions of the DRB. (n) The DRB members and the parties may ask questions, request clarification, or ask for additional data. In difficult or complex cases, additional meetings may be necessary with the agreement of the parties and the DRB, in order to facilitate full consideration and understanding of all the evidence presented by both parties. Deliberations (o) After the meeting is concluded, the DRB will confer to formulate its recommendations. All DRB deliberations will be conducted in private. (p) The DRB must endeavour to reach a unanimous decision. If this proves impossible, the applicable decision will be made by a majority of the members, who may require the minority member to prepare a written report for submission to the Principal and the Contractor. Recommendations (q) The DRB's recommendations for resolution of the dispute will be provided in writing to both the Principal and the Contractor within two weeks of the completion of the meetings. The DRB‟s recommendations must include reasons for the decisions made by the DRB. (r) If necessary due to either or both of the nature and complexity of the dispute and the DRB's schedule, the period referred to in clause 40.3(q) may be extended by mutual agreement of the parties and the DRB members. (s) If the DRB‟s recommendation involves a Progress Claim that has been the subject of an adjudicator‟s determination under the Security of Payment Act, then: (i) within two business days from the date of receipt by the parties of the DRB‟s recommendation, the Contractor must notify the DRB of the adjudicated amount only as set out in the adjudicator‟s determination; and (ii) the DRB must allow for any amount paid to either party under or for the purposes of Part 3 of the Security of Payment Act and issue to 108 both parties its revised recommendation (which will supersede the recommendation issued under clause 40.3(r)). (t) (u) If the DRB‟s recommendation (either under clause 40.3(q) or 40.3(s)(ii)) is for a payment by one party to the other of an amount: (i) equal to or less than $1 million, then that recommendation will be binding on both parties; or (ii) greater than $1 million, then that recommendation will be binding on both parties unless and until it is revised in an amicable settlement or in legal proceedings. The parties agree that a binding recommendation of the DRB will be a decision of a tribunal for the purposes of section 32(3) of the Security of Payment Act. Acceptance or Rejection (v) Subject to clause 40.3(t), within ten weeks of receiving the DRB's recommendations or such longer time as the parties may agree, each of the Principal and the Contractor must provide written notice to the other and to the DRB of its acceptance or rejection of the DRB's recommendation. (w) The failure of either party to respond within the period specified in clause 40.3(v) will be deemed an acceptance of the DRB's recommendation. Admissibility (x) 40.4 If the DRB's recommendation does not resolve the dispute, the written recommendation, including any minority report, and the disclosure statements referred to in clause 1.5 of Schedule 12 - DRB Appointment and Operating Procedures, will be admissible as evidence to the extent permitted by law in any subsequent dispute resolution proceeding or forum to establish: (i) that a DRB considered the dispute; (ii) the qualifications of the DRB members; and (iii) the DRB recommendation that resulted from the issue resolution process contemplated by clauses 40.2 to 40.4. Payment and expenses (a) The Principal will pay all fees and expenses of the three DRB members for attendance at site visits and periodic meetings of the DRB and for review of regular reports and other relevant information provided to the DRB. (b) The fees and expenses of all three members of the DRB for additional meetings and for the review of referred disputes in accordance with the Deed, where additional costs are incurred including a requirement for meetings additional to the periodic DRB meetings, will be shared equally by the Principal and the Contractor. (c) The Contractor must pay the invoices of the DRB members after approval by both parties. The Contractor will then invoice the Principal for 100% of such 109 invoices for the site visits and periodic meetings and 50% of such invoices for additional costs of additional meetings required and for the review of disputes. 40.5 (d) If the DRB wishes to obtain special services such as legal or other consultation, accounting, data research and the like, both parties must first agree in writing, and the costs will be shared by them equally. (e) Each party will be responsible for its own costs during the DRB process. including staff time for preparatory work and attendance at meetings, consultants and legal fees and any other costs. Contractor to perform the Work under the Deed Notwithstanding the other provisions of this clause 40, the Contractor must: 40.6 (a) continue to execute the Work under the Deed; (b) perform its other obligations under the Deed; and (c) comply with all directions of the Principal or the Principal‟s Representative including any direction in respect of a dispute or difference being dealt with in accordance with this clause 40. Legal proceedings Nothing in this clause 40 will prevent: 41 (a) either party commencing any legal proceedings for urgent or interlocutory relief; or (b) the Contractor from applying for adjudication of a Progress Claim or from taking any other action under the Security of Payment Act. Liability 41.1 Civil Liability Act 2002 (NSW) The parties agree that it is their intention that all rights, obligations and liabilities under or in connection with the Deed are to apply, even where the relevant circumstances involve a failure to take reasonable care and the existence of concurrent wrongdoers (as that term is defined in section 34(2) of the Civil Liability Act 2002 (NSW)), unlimited and otherwise unaffected by anything that, but for this clause 41.1, may by virtue of the provisions of the Civil Liability Act 2002 (NSW) have limited or otherwise affected those rights, obligations and liabilities. 41.2 Limitation on and exclusions from the Contractor’s Liability (a) Except as specified in clause 41.2(b), the Contractor‟s liability to the Principal: (i) under or in connection with the Deed or the Contractor‟s performance of the Work under the Deed and its other obligations under the Deed; or 110 (ii) in tort (including negligence) or under any statute or otherwise at law, notwithstanding any other provision of the Deed (including indemnities): Masked for Confidentiality (iv) (b) is limited in the aggregate to the amount stated in Schedule 1 Contract Information. The limitations on and exclusions from the Contractor‟s liability contained in clause 41.2(a) do not apply to or limit or restrict in any way: Masked for Confidentiality 111 Schedule 1 Contract Information Description Clause Reference Details Authorised Representative of the Contractor Clause 1.1 Glen Ashton Authorised Representative of the Principal Clause 1.1 Trevor Armstrong Contractor Clause 1.1 Thiess Pty Ltd (ABN 87 010 221 486) Contractor‟s Margin Clause 1.1 Principal Clause 1.1 Ausgrid (ABN 67 505 337 385) of 570 George Street, Sydney NSW 2000 Time for Progress Claims Clause 1.1 Last day of the month Masked for Confidentiality Clause 7.3(a) Adjustment to Contract Price, Date for Substantial Completion and Date for Practical Completion for the purposes of clause 4.1A(f) Clause 4.1A(f) Adjustment to Contract Price: the Contract Price will, with effect from the date of the notice from the Principal under clause 4.1A(e), be increased by an amount of (more particularly described in the preabmble to the pricing schedule in Schedule 3 – Commercial Schedules). Masked for Confidentiality Adjustment to Date for Substantial Completion for Separable Portion 1: there will be no adjustment to the Date for Substantial Completion for Separable Portion 1. Adjustment to Date for Substantial Completion for Separable Portion 2: the Date for Substantial Completion of Separable 112 Description Clause Reference Details Portion 2 will, with effect from the date of the notice from the Principal under clause 4.1A(e), be extended by a period of 10 days. Adjustment to Date for Practical Completion of Separable Portion 3: the Date for Practical Completion of Separable Portion 3 will, with effect from the date of the notice from the Principal under clause 4.1A(e), be extended by a period of 25 days. Rate to be applied to the cost to perform the work or supply the item to which a Provisional Sum relates (exclusive of GST) Clause 4.2(b) Approved Off-Site Materials Clause 7.3(b) Precast concrete segments Amount of unconditional undertaking Clause 8.1 Four unconditional undertakings each for of the Contract Price. Masked for Confidentiality Masked for Confidentiality One unconditional undertaking for of the Contract Price. Masked for Confidentiality Amount of unconditional undertaking Clause 8.2 Contractor‟s Representative Clause 13.2(a) Christian D'Hondt Construction Plant over which the Contractor must not create any security interest Clause 18.4(a) TBM and Roadheader Limit of the Contractor‟s aggregate liability for liquidated damages Clause 25.2(d) Defects Correction Period Clause 26.3(c) Masked for Confidentiality of the Contract Price Masked for Confidentiality In respect of all civil works forming part of the Work under the Deed - 12 months In respect of all other Work under the Deed (excluding civil works) - 24 months 113 Description Clause Reference Details Delay costs Clause 34.9(b) The costs per day which the Contractor demonstrates (to the reasonable satisfaction of the Principal‟s Representative) that it has incurred as a result of the delay commencing from the date Substantial Completion, Practical Completion or Completion (as applicable) was or were first actually delayed Amount payable on termination for convenience Clause 37.2(d)(iii) Masked for Confidentiality Limitation on the Contractor‟s liability Clause 41.2(a)(iv) Masked for Confidentiality 114 of the value of the remaining Work under the Deed, as assessed by the Principal‟s Representative of the Contract Price Schedule 2 Separable Portions Work under the Deed Date for Substantial Completion Date for Practical Completion Liquidated damages Not Applicable Masked for Confidentiality SEPARABLE PORTION 1 Consisting of the construction of the CSCT Extension, the Surry Hills Annex Joint Bay, the Little The date which is 561 business days Riley Street 33kV Cable Shaft, and the Rose Bay Feeder Shaft and Vault, including: from the date of the Completion of the permanent tunnel and shaft linings and all other permanent structural Deed elements; Installation of all cable support members and tunnel and shaft fixtures excluding permanent lighting, cabling or hydraulic equipment (eg. rising mains); Construction of a partition between the CSCT Extension and the Riley Street Shaft and provision of a temporary ventilation outlet for the CSCT Extension; Completion of all structural modifications required to the Surry Hills shaft. Upon Substantial Completion of Separable Portion 1, ventilation of the CSCT Extension will be via the permanent CSCT fan system however a temporary ventilation outlet for the tunnel will be required to be installed by the Contractor. It is envisaged that this outlet will be via the Riley Street Shaft. The Contractor must make available temporary lighting in the CSCT Extension to facilitate Cable Installation works. This temporary lighting must be maintained until commissioning of the permanent Tunnel lighting system. Following Substantial Completion of Separable Portion 1, the CSCT Extension will be considered as a live electrical facility, with access by the Contractor to be controlled in accordance with Clause 3.11.2 of the Specification. 115 Work under the Deed Date for Substantial Completion Date for Practical Completion Liquidated damages SEPARABLE PORTION 2 Consisting of all work associated with the excavation and temporary support of the City East Shaft and the City East Stub Tunnel, including the sump and cavern at the interface with the main TBM alignment (at Chainage 2148m), the removal of the Roadheader and the demobilisation of all temporary construction facilities installed by the Contractor at the CES Site and anything else necessary to allow handover of the CES Site to the City East Substation Building Contractor in accordance with Clause 3.3.4 of the Specification. The date which is Not 633 business days Applicable from the date of the Deed Masked for Confidentiality Not applicable Masked for Confidentiality SEPARABLE PORTION 3 Consisting of all Work under the Deed not covered by Separable Portions 1 and 2 or otherwise associated with the finalisation of the Work under the Deed. 116 The date which is 1270 business days from the date of the Deed Schedule 3 Commercial Schedules General Measurement and Pricing Principles 1. The Contract Price has the meaning defined in clause 1.1. The Contract Price is made up of a mixture of lump sum prices, the sum of the products of the actual quantities and the relevant rate for each item and amounts payable in respect of Provisional Sums as described in the Pricing Schedule. 2. When carrying out Work under the Deed, payment will be made for the actual quantities measured on Site in respect of the schedule of rate items, unless noted otherwise in the Pricing Schedule. 3. When carrying out the Work under the Deed and in the event that Materially Adverse Conditions (as defined in Schedule 4 – GBR Administration) are encountered the Contractor will be reimbursed at the rates and margin allowances in the Cost Reimbursable Schedules. 4. This Schedule 3 - Commercial Schedules comprises: (a) Pricing Schedule (a mixture of lump sums, Provisional Sums and schedule of rates); (b) Dayworks Rates Schedule (including schedules for Labour, Construction Plant and Equipment and margin for subcontract works); and (c) Cost Reimbursable Schedule (as described in clause 3 above). 117 1. Pricing Schedule Preamble 1. The Contract Price is broken down in the Pricing Schedule. The Pricing Schedule includes a lump sum for each lump sum item of Work under the Deed and a rate and sum for each schedule of rates item of Work under the Deed. For the purposes of clause 7.3 of the General Conditions of Deed and without limiting item 11(b) below, for each lump sum item of Work under the Deed, the Contracor is not entitled to, and must not, claim (in aggregate) more than the total lump sum amount specified in the Pricing Schedule (as adjusted in accordance with the Deed) in respect of that particular item of work. 2. Quantities identified to be measured in-situ in the Pricing Schedule shall be measured in accordance with the measurement instructions and assumptions noted in the Pricing Preamble for those items. 3. Unit rates are fixed and shall not be varied, re-valued or adjusted in any way, even in the event of a significant increase or decrease in quantities as compared to the quantities shown in the Pricing Schedule. 5. The quantities shown in the Pricing Schedule are by way of example only, and are not warranted in any way by the Principal. 6. The rates included in the Pricing Schedule are deemed to include margins for head office overheads and profit, all direct costs for labour, plant and materials, and all recurring time dependent costs not otherwise included in other items including, inter alia, supervisory and site office costs, surface and underground direct and support labour, plant, services and materials. 7. Nothing in this Schedule 3 describes, limits or otherwise affects the Work under the Deed to be carried out by the Contractor under the Deed and the Contract Price is deemed to cover all of the Work under the Deed to be carried out under the Deed, regardless of whether or not it is listed in this Schedule 3. 8. Only one of the rates set out in items 3.7.1, 3.7.2, 3.7.3 or 3.7.4 of the Pricing Schedule can apply in respect of a particular unit of measure of Work under the Deed at any one time. 9. Only one of the rates set out in items 4.7.1, 4.7.2, 4.7.3 or 4.7.4 of the Pricing Schedule can apply in respect of a particular unit of measure of Work under the Deed at any one time. 10. If the Contract Price is to be adjusted under clause 4.1A(f)(i) of the General Conditions of Deed, the adjustment to the Contract Price will be applied to item 4.9 of the Pricing Schedule. 11. If the Contract Price is to be reduced under clause 4.1B(c)(ii) of the General Conditions of Deed, the reduction in the Contract Price will be applied: (a) firstly to items 4.1 to 4.8 (inclusive) of the Pricing Schedule, then to items 4.10 to 4.11 (inclusive) of the Pricing Schedule and then to item 4.9 of the Pricing Schedule; and 118 (b) if the amounts in items 4.1 to 4.11 (inclusive) of the Pricing Schedule are insufficient to satisfy the reduction, to the next Progress Claim(s) made by the Contractor under the Deed as if the remainder of the reduction were moneys which are due from the Contractor to the Principal in respect of the Deed. 12. All rates and prices included in the Pricing Schedule exclude GST. 13. For the purposes of the Pricing Schedule, a reference to the AECOM Geotechnical Engineer means the person(s) nominated in writing by the Principal to the Contractor from time to time as being the AECOM Geotechnical Engineer for the purposes of the Deed. 119 Pricing Schedule: Item 1 Item Description Unit of Measure Qty Rate Amount Lump Sum N/A N/A N/A Schedule of Rates 1.1 Preliminary Items Design 1.2 Condition Surveys Lump Sum N/A N/A N/A 1.3 Insurances Lump Sum N/A N/A N/A 1.4 General Site Establishment (Offices etc) Lump Sum N/A N/A N/A 1.5 Site Labour N/A N/A N/A 1.6 Survey N/A N/A N/A 1.7 Security - unconditional undertakings Lump Sum Lump Sum Lump Sum N/A N/A N/A 1.8 Fees Lump Sum N/A N/A N/A Pricing Preamble Lump Sum Masked for Confidentiality 120 A Progress Claim which relates to this item must be accompanied by itemised design activities and “For Construction” drawings verified by Aecom Australia Pty Ltd on behalf of the Principal and certified by the Contractor‟s designer(s). The condition surveys are to be done both pre and post construction activities. A Progress Claim which relates to this item must be accompanied by a copy of the completed survey with documentary evidence satisfactory to the Principal A Progress Claim which relates to this item must be accompanied by documentary evidence that all required policies are in place for the term required under the Deed. In the event that policies are renewable annually, payment made will be pro-rata the existing policy validity period compared to the contract period For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted upon completion of the facilities in accordance with the “For Construction” Temporary Works drawings and occupation and/or commissioning of services. A Progress Claim which relates to this item must be accompanied by documentary evidence that all required unconditional undertakings are in place for the term required under the Deed. Item Item Description Unit of Measure Qty Rate Amount Schedule of Rates Pricing Preamble Lump Sum Procurement, Mobilisation and Commissioning of Tunnelling Equipment and associated Facilities 2 Masked for Confidentiality 2.1 Procurement of Plant & Equipment for RHOperation Lump Sum N/A N/A N/A For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted: Masked for Confidentiality when roadheader is ordered, in which case the Progress Claim for this 50% amount must be accompanied by a copy of the relevant purchase order issued by the Contractor; and in respect of the remaining Masked for Confidentiality upon delivery of the roadheader to the Site. 2.2 Procurement of Plant & Equipment for TBMTunnel excluding TBM Lump Sum N/A N/A N/A 2.3 Procurement of TBM - 1st instalment Place Order Lump Sum N/A N/A N/A 2.4 Procurement of TBM - 2nd instalment Lump Sum N/A N/A N/A 2.5 Procurement of TBM - 3rd instalment Workshop Acceptance Lump Sum N/A N/A N/A For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted: Masked for Confidentiality when all nessecary TBM plant and equipment is ordered, in which case the Masked for Confidentiality Progress amount must be accompanied by a copy of all relevant purchase order(s) issued by the Contractor; and in respect of the remaining 50% of the lump sum, upon delivery of all nessecary TBM plant and equipment to the Site. For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted on order of TBM. The Progress Claim for this amount must be accompanied by a copy of the relevant purchase order issued by the Contractor. For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted after 90 calendar days from the order date. For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted when Factory Acceptance Testing is complete and approved by the Contractor's Representative. The Progress Claim for this amount must be accompanied by evidence of the relevant testing and approval. 121 Item Item Description Unit of Measure Qty Rate Amount Schedule of Rates 2.6 Procurement of TBM - final instalment Site Assembly Complete Lump Sum N/A N/A N/A 2.7 Procurement of Lining Works Lump Sum N/A N/A N/A Riley St Substation Site - RSS General Tunnelling Worksite Establishment Riley Street Site - RSS Lump Sum N/A N/A N/A 3.2 Services Establishment for Operations (RH & TBM) - RSS Lump Sum N/A N/A N/A 3.3 Excavate and Support Shaft - RSS-S N/A N/A N/A 3.4 Concrete lining to Shaft - RSS-S N/A N/A N/A N/A N/A N/A N/A N/A N/A 3 3.1 Plant & Equipment for Tunnelling 3.5.1 TBM Launch Chamber Class-RH-6-T and Class-RH-6-A Lump Sum Lump Sum Lump Sum 3.5.2 TBM Backshunt Class-RH-6-T and ClassRH-6-A Lump Sum 122 Pricing Preamble Lump Sum Masked for Confidentiality For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted, when the TBM is fully commissioned on Site and approved by the Contractors Representative as „Ready to Bore‟. The Progress Claim for this amount must be accompanied by evidence of the relevant commissioning and approval. For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted: Masked for Confidentiality when lining works plant and equipment is ordered, in which case the Progress Claim for this 50% amount must be accompanied by a copy of all relevant purchase order(s) issued by the Contractor; and Masked for Confidentiality upon delivery of the applicable plant and equipment to the Site. For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submittedafter completion of the facilities in accordance with the “For Construction” Temporary Works drawings and occupation and/or commissioning of services. For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted after completion of the facilities in accordance with the “For Construction” Temporary Works drawings and occupation and/or commissioning of services. Payment will be valued based upon actual quantity determined by the AECOM Geotechnical Engineer, also be used for time adjustments. Payment will be valued based upon actual quantity determined by the AECOM Geotechnical Engineer, also be used for time adjustments. encountered as the quantity will encountered as the quantity will Item 3.6 Item Description Unit of Measure Qty Rate Amount Schedule of Rates Pricing Preamble Lump Sum Excavate and Support CSCT Extension Tunnel Excavate and Support CSCT Extension Tunnel in Class-RH-6-T Lineal metre 37.6 N/A 3.6.2 Excavate and Support CSCT Extension Tunnel in Class-RH-6-A Lineal metre 9.4 N/A 3.6.3 Excavate and Support CSCT Extension Tunnel in Class-RH-8a-T Lineal metre 33.0 N/A 3.6.4 Excavate and Support CSCT Extension Tunnel in Class-RH-8b-T Lineal metre 32.0 N/A 3.6.5 Excavate and Support CSCT Extension Tunnel in Class-RH-8b-A Lineal metre 8.0 N/A 3.6.6 Excavate and Support CSCT Extension Tunnel in Class-RH-2-T Lineal metre 25.0 N/A Extra over for excavation in „adverse‟ Lineal metre Lineal metre 3.6.1 3.7 3.7.1 Extra over for excavation in the single „adverse‟ criteria for UCS Masked for Confidentiality Masked for Confidentiality 1.00 Rate only Rate Only Payment will be valued based upon actual quantity determined by the AECOM Geotechnical Engineer, also be used for time adjustments. Payment will be valued based upon actual quantity determined by the AECOM Geotechnical Engineer, also be used for time adjustments. Payment will be valued based upon actual quantity determined by the AECOM Geotechnical Engineer, also be used for time adjustments. Payment will be valued based upon actual quantity determined by the AECOM Geotechnical Engineer, also be used for time adjustments. Payment will be valued based upon actual quantity determined by the AECOM Geotechnical Engineer, also be used for time adjustments. Payment will be valued based upon actual quantity determined by the AECOM Geotechnical Engineer, also be used for time adjustments. encountered as the quantity will encountered as the quantity will encountered as the quantity will encountered as the quantity will encountered as the quantity will encountered as the quantity will For the purposes of Schedule 4 – GBR Adminiatration, where conditions are classified as „adverse‟ for the criteria of UCS only an extra over payment will be made and a time adjustment made of Masked for Confidentiality 3.7.2 Extra over for excavation in the single „adverse‟ criteria for Defects Lineal metre 1.00 Rate only Rate Only 3.7.3 Extra over for excavation in the single „adverse‟ criteria for Groundwater inflow Lineal metre 1.00 Rate only Rate Only 3.7.4 Extra over for „adverse‟ criteria Lineal metre 1.00 Rate only Rate Only excavation in multiple 123 For the purposes of Schedule 4 – GBR Adminiatration, where conditions are classified as „adverse‟ for the criteria of Defects only an extra over payment will be made and a time adjustment made of 3hrs per M For the purposes of Schedule 4 – GBR Adminiatration, where conditions are classified as „adverse‟ for the criteria of Groundwater inflow only an extra over payment will be made and a time adjustment made of Masked for Confidentiality For the purposes of Schedule 4 – GBR Adminiatration, where conditions are classified as „adverse‟ for more than one criteria simultaneously an extra over payment will be made and a time adjustment made of Masked for Confidentiality Item Item Description Unit of Measure Qty Rate Amount Schedule of Rates 3.8 Concrete lining to CSCT Extension Tunnel RSS-T Lineal metre 3.9 N/A N/A N/A N/A N/A N/A N/A N/A 3.12 U/G Excavation and Lining Costs - RSS Lump Sum Lump Sum Lump Sum Lump Sum N/A 3.11 Interface Works at Surry Hills Substation RSS Rose Bay Feeder Cable Jointing Bay RSS-S Control Room Structure - RSS-S N/A N/A N/A 3.13 Spoil Disposal - RSS N/A N/A N/A 3.14 Demobilisation of Worksite - RSS Lump Sum Lump Sum N/A N/A N/A City East Substation Site - CES General Tunnelling Worksite Establishment - CES Lump Sum N/A N/A N/A 4.2 Worksite and Services Establishment for RH Operation - CES Lump Sum N/A N/A N/A 4.3 Excavate and Support Shaft - CES-S N/A N/A N/A 4.4 Concrete lining to Shaft - CES-S N/A N/A N/A 4.5 Excavate and Support Stub Tunnel and Cavern in Class RH-6-T and RH-6-A Lump Sum Lump Sum Lineal metre 145.0 Pricing Preamble Lump Sum N/A Masked for Confidentiality Masked for Confidentiality Masked for Confidentiality 3.10 4 4.1 165.64 Masked for Confidentiality Masked for Confidentiality 124 The value of work completed for this item will be determined by reference to the estimated % complete of all work described in this item 3 (Riley St Substation Site – RSS) at the time of the relevant Payment Claim For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted upon completion of the facilities in accordance with the “For Construction” Temporary Works drawings and occupation and/or commissioning of services. For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted upon completion of the facilities in accordance with the “For Construction” Temporary Works drawings and occupation and/or commissioning of services. N/A Payment will be valued based upon actual quantity encountered as determined by the AECOM Geotechnical Engineer, the quantity will also be used for time adjustments. Item Item Description Unit of Measure 4.6 Extra over for additional 3.7m CT rock bolts 4.7 Extra over for excavation in „adverse‟ Qty Rate Amount Schedule of Rates Ea 1.00 Masked for Confidentiality Pricing Preamble Lump Sum Rate Only Rate Only For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted for the each CT bolt which has been installed as at the time of the relevant Payment Claim For the purposes of Schedule 4 – GBR Adminiatration, where conditions are classified as „adverse‟ for the criteria of UCS only an extra over payment will be made and a time adjustment made of 4.7.1 Extra over for excavation in the single „adverse‟ criteria for UCS Lineal metre 1.00 Rate only Rate Only 4.7.2 Extra over for excavation in the single „adverse‟ criteria for Defects Lineal metre 1.00 Rate only Rate Only 4.7.3 Extra over for excavation in the single „adverse‟ criteria for Groundwater inflow Lineal metre 1.00 Rate only Rate Only 4.7.4 Extra over for „adverse‟ criteria multiple Lineal metre 1.00 Rate only Rate Only 4.8 Concrete lining to Tunnel & Cavern - CES-T N/A N/A N/A 4.9 U/G Excavation and Lining Costs - CES Lump Sum Lump Sum N/A N/A N/A 4.10 Spoil Disposal - CES N/A N/A N/A 4.11 Demobilisation and Re-instatement of Worksite - CESS Not used TBM Tunnel from RSS to CNS - CECT Mobilisation, Assembly, Test & Commission TBM Plant & Equipment Lump Sum Lump Sum N/A N/A N/A Lump Sum N/A N/A N/A Masked for Confidentiality For the purposes of Schedule 4 – GBR Adminiatration, where conditions are classified as „adverse‟ for the criteria of Defects only an extra over payment will be made and a time adjustment made of Masked for Confidentiality excavation in For the purposes of Schedule 4 – GBR Adminiatration, where conditions are classified as „adverse‟ for the criteria of Groundwater inflow only an extra over payment will be made and a time adjustment made of Masked for Confidentiality For the purposes of Schedule 4 – GBR Adminiatration, where conditions are classified as „adverse‟ for more than one criteria simultaneously an extra over payment will be made and a time adjustment made of Masked for Confidentiality Masked for Confidentiality 5 6 6.1 125 The vaue of work completed for this item will be determined by reference to the estimated % complete of all work described in this section 4 (City East Substation Site - CES) at the time of the relevant Payment Claim This lump sum amount includes the fixed cost of mobilising, installing and commissioning all required tunnel equipment along this section of tunnel, including fixed components of all man and materials transport arrangements. Item Item Description Unit of Measure Qty N/A Rate Amount Schedule of Rates Pricing Preamble Lump Sum 6.2 Supply of Tunnel Lining Segments - CECT Lump Sum 6.3 Excavate and Line TBM Tunnel in GBR ground conditions - CECT Lineal metre 3,193.68 N/A 6.4 Wear allowance per m of TBM excavated tunnel Lineal metre 3,193.68 N/A N/A N/A Masked for Confidentiality 126 For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted upon: acceptance by the Principal of documentary evidence of manufacture to the standard defined in the Specification; and delivery of units into secure storage area with guaranteed ownership of units passing to the Principal in accordance with the General Conditions of Deed. The value of work completed for this item will be determined by reference to the average rate per m of tunnel excavated through a mix of rock types not worse than identified in the GBR and summarised in 6.5 Masked for Confidentiality The rate includes any necessary forward probe drilling The value of work completed for this item will be determined by reference to each m of tunnel excavated. The rate includes wear costs for all equipment associated with the excavation of undisturbed rock at tunnel face and spoil removal from the tunnel face into the ultimate transport system for removal off Site. Item 6.5 Item Description Ground Grouping Dyke Zones Typical Adverse Type Expected % total length Unit of Measure of Qty Rate Amount Schedule of Rates Relative product ion factor (applies to 6.3)** Relative wear factor (applies to item 6.4)** Pricing Preamble Lump Sum The summation of (% length x Relative production or wear factor) must equal 100% in each case. Progressive payment will be made at the average rates in item 6.4 and 6.5 Adjustments to the total payment will be made following Substantial Completion where, for the actual conditions encountered, the summation of (relative production or wear factor x % type) exceeds the value for the original material type assumptions. Rock will be classified as „Typical‟ or „Adverse‟ in accordance with the definitions contained in the GBR, Exhibit C of the Deed and the regular sampling and testing undertaken in accordance with Section 6.2 of Part 6 of Schedule 4 GBR Administration of the Deed Masked for Confidentiality Adverse conditions may include different combinations of the factors identified in the GBR (Exhibit C to the Deed) and administered in accordance with Schedule 4 to the Deed. The Contractor may subdivide the relative production and relative wear factors if it so chooses. However, the summation of (% length x relative production or wear factor) for Typical and any Adverse combinations must remain equal to 100%. Payment will not be adjusted for better than expected conditions. Time will be adjusted by pro-rating time using the actual weighted relative production factor. The average programmed drive time calculated from completion of the first 200 rings, excluding Dyke zones and Materially Adverse Conditions, until completion of the first Masked forofConfidentiality excavation of the TBM section of the tunnel, will be used as the average production rate for all excavation of the TBM section of the tunnel for the purposes of calculating any time adjustments. No negative time adjustments will apply. The comparative relative wear factor will be applied to the amount included for item 6.4 only Masked for Confidentiality 6.6 6.7 Remove TBM lining Segments at LPS and CNSS Tunnel Invert Slab - CECT Lump Sum Lump Sum N/A N/A N/A N/A N/A N/A 127 Item Item Description Unit of Measure Qty Rate Amount Schedule of Rates 6.8 Dismantle TBM, bury remainders, tunnel cleanup - CECT Lump Sum N/A N/A N/A 6.9 Construction of Sump at Ch 640 Lump Sum Lump Sum N/A N/A N/A N/A N/A N/A Lump Sum N/A N/A N/A Lump Sum Lump Sum Lump Sum Lump Sum Lump Sum Lump Sum N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Lump Sum N/A N/A N/A 6.10 U/G Excavation and Lining Costs - CECT 6.11 Spoil Disposal - CECT 7 7.1 7.2 City North Substation Site - CNS General Worksite Establishment - CNS 7.3 Worksite and Services Establishment for U/G Operations - CNS Excavate and Support Cavern - CNS 7.4 Concrete lining to Cavern - CNS 7.5 7.6 Interface Works at City North Substation CNS U/G Excavation and Lining Costs - CNS 7.7 Spoil Disposal - CNS 128 Pricing Preamble Lump Sum Masked for Confidentiality For the purposes of clause 7.3(a)(i) of the General Conditions of Deed, a Progress Claim which relates to this item can only be submitted: Masked for Confidentiality of the lump sum for this item, after completion of removal from the shaft of all TBM components and backup; and Masked for Confidentiality of the lump sum for this item, after removal of all TBM components from the Site. The value of work completed for this item will be determined by reference to the estimated % complete of all work described in this section 6 (TBM Tunnel from RSS to CNS – CECT) at the time of the relevant Payment Claim The vaue of work completed for this item will be determined by reference to the estimated % complete of all work described in this section 7 (City North Substation Site – CNS) at time of the relevant Payment Claim. Item Unit of Measure Qty Feeder Shaft Construction Construction of Little Riley St 33 kV Feeder Connection, Cable Shaft Lump Sum N/A N/A N/A This lump sum amount includes all costs associated with boring the shaft, supply and installation of steel liner, backfill grouting of liner as may be required, and provision of any necessary sealing arrangements between liner and base intersection chamber. 8.2 Construction of Rose Bay Feeder Cable Shaft Lump Sum N/A N/A N/A This lump sum amount includes all costs associated with boring the shaft, supply and installation of steel liner, backfill grouting of liner as may be required, and provision of any necessary sealing arrangements between liner and base intersection chamber. 8.3 Construction of Domain 33 kV Cable Shaft Lump Sum N/A N/A N/A This lump sum amount includes all costs associated with boring the shaft, supply and installation of steel liner, backfill grouting of liner as may be required, and provision of any necessary sealing arrangements between liner and base intersection chamber. 8.4 Re-instate Cable Shaft Worksites Lump Sum N/A N/A N/A 9.1 General Tunnel and Shaft Fitout Supply and Install Cable Support Structures Lump Sum Lump Sum N/A N/A N/A N/A N/A N/A Lump Sum Lump Sum Lump Sum Lump Sum Lump Sum Lump Sum N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 8 8.1 9 9.2 Item Description 10.1 Structural Steelwork, Grated Floors, Fire Doors & Seals Mechanical & Electrical Tunnel Fitout Cable Support Structures 10.2 Ventilation 10.3 Drainage System 10.4 Electrical Services 10.5 Radio Comms 10.6 Monitoring & Control System 10 Rate Amount Schedule of Rates Pricing Preamble Lump Sum Masked for Confidentiality 129 Item 10.7 Fire Detection & Alarm System 10.8 Ancillary Services 10.9 Fire Rating 10.10 Signage 10.11 Telephones 10.12 Commissioning Training Documentation 10.13 Maintenance Provision 12 Mths 11 11.1 12 Item Description Post Construction Works Maintenance of permanent Works and temporary services upon Practical Completion (for 12 months) ESTIMATED SCHEDULE SUB-TOTALS Unit of Measure Qty Rate Amount Lump Sum Lump Sum Lump Sum Lump Sum Lump Sum Lump Sum Lump Sum N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Lump Sum N/A N/A N/A Schedule of Rates Lump Sum Masked for Confidentiality Masked for Confidentiality Masked for ConfidentialityMasked for Confidentiality 130 Pricing Preamble Item 13 13.1 13.2 Item Description Provisional Sums Provisional Sum for: the additional administration costs of complying with the terms and conditions of any Interface Agreement executed after the date of the Deed which the Contractor reasonably considers are substantially more onerous than those contained in the relevant Draft Interface Agreement (refer clause 6.2(b)(ii)(B) of the General Conditions of Deed); and all monitoring required to be undertaken by the Contractor as part of the Work under the Deed including: monitoring of CCM Tunnels and adjustments to construction methodologies in the vicinity of CCM Tunnels as a result of restrictions on excavation imposed by CCM or otherwise associated with the actual crossing of the CCM Tunnels; monitoring of BOOS in accordance with Sydney Water requirements; and monitoring of RailCorp assets in accordance with RailCorp requirements. Provisional Sum for disposing of water from CES (Refer Part 4.5 of Schedule 4) Unit of Measure Qty Rate Amount Lump Sum N/A N/A N/A N/A N/A N/A Schedule of Rates Lump Sum Masked for Confidentiality (Provisional) Lump Sum (Provisional) 13.3 Provisional Sum for maintaining site infrastructure at CES during excavation of CES 14 TOTAL PROVISIONAL SUMS 15 ESTIMATED CONTRACT PRICE Lump Sum N/A N/A N/A (Provisional) 141,543,241 131 Pricing Preamble 2 Daywork Rates Schedule The Daywork rates, overheads and margins are deemed to include all costs of design, construction works, maintaining and operating site facilities and services, including tunnel services. Any other cost not noted in this Daywork Rates Schedule is deemed to be included in the daywork rates, overheads and margins listed in this Daywork Rates Schedule. TABLE 2.1 LABOUR DAYWORK RATES This Table 2.1 contains a comprehensive list covering all classifications of trade labour expected to be employed on the Work under the Deed. An overhead and margin allowance of 43% is included in the rates detailed below. Ref Staff and Labour Hourly rate Classification List by trade or award classification. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 Average hourly shift pattern Rate Underground Labour - single shift Tunnel Worker Class 1 Tunnel Worker Class 2 Tunnel Worker Class 3 Tunnel Worker Class 4 Tunnel Worker Class 5 Underground Labour - double shift Tunnel Worker Class 1 Tunnel Worker Class 2 Tunnel Worker Class 3 Tunnel Worker Class 4 Tunnel Worker Class 5 Surface Labour - single shift |Surface Worker Class 2 |Surface Worker Class 3 |Surface Worker Class 4 |Surface Worker Class 5 |Surface Worker Class 6 Time & Double time 1/2 Masked for Confidentiality Notes Rates included cover all direct and indirect employee costs including loadings for holidays and sick pay, superannuation, bonus provisions, statutory on-costs, vehicle and accommodation allowances where applicable and any other costs associated with employment of labour under the terms of the industrial instrument applicable to the Project. Rates included cover all costs associated with employment of subcontract workers under the terms of the industrial instrument applicable to the Project. Rates included cover all costs associated with direct supervision of daywork labour during the performance of the work; kitting out of staff, including but not limited to small tools with a capital value lessMasked for Confidentialityand clothing; non-project dedicated company costs relating to fleet vehicles, IT, communications and depreciation of equipment, allocated divisional infrastructure costs including general management, business development, safety, accredited systems, finance and costing, billing and debt recovery, human resources and administration; staff training time and training costs; Workers Compensation costs 132 TABLE 2.2 CONSTRUCTION PLANT DAYWORKS RATES This Table 2.2 contains a comprehensive list of all Construction Plant required for the Project in excess Masked for Confidentiality capital value expected to be provided by the Contractor. For avoidance of doubt, the rates included in this Table 2.2 are to reimburse the Contractor for the operating costs only. Masked for Confidentiality Any items not listed but found to be required during the progress of the Work under the Deed will be valued using the same principles applied by the Contractor to arrive at the rates included in this Table 2.2. Ref 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 1 Item Description Operating costs, (excluding operators) Hourly Rate |TBM - 3.9M Dia open SS - Operate incl cutter consumption TBM Grout Plant - Operate TBM Grout Plant - Cement & Bentonite Silos Roadheader S200m, 200 Kw, Hire and operating costs |Roadheader, 200Kw, Auto Profile System, Hire Locomotive Tunnel Car Vent Fan - TBM Tunnel - Operate (excl power costs) Gantry Crane - Operate (no power costs) |Water Treatment Plant, 16 L/Sec - Operate, Maintain incl chemicals Telehandler - Operate Shotcrete Pump & Boom - Operate Rockbolter - Operate Fel CAT 972 - Operate - in Tunnel Elevated Work Platform - Hire & Operate Compressor, 1000 Cfm & Receiver - Operate Bunded Fuel Installation - Operate Bobcat - Operate Hiab Truck - Operate Grout Pump for Rockbolts Site Vehicle Alimak |Electrical Reticulation - Maintain Dewatering Pump 20KW Power Reticulation Hire for RH TBM Power Reticulation, Hire for Job Duration Masked for Confidentiality Notes Operating costs include all fuels, oils and greases, power, spares and any other direct operating expenses. TABLE 2.3 OVERHEAD AND MARGIN ON MATERIAL AND SUBCONTRACT DAYWORK (OTHER THAN SUBCONTRACT LABOUR): Masked for Confidentiality 133 3 Cost Reimbursable Schedule TABLE 3.1 CONSTRUCTION PLANT DIRECT COSTS This Table 3.1 contains a comprehensive list of Construction Plant required for the Project to be provided by the Contractor. Masked for Confidentiality This Table 3.1 includes all surface and underground Construction Masked for Confidentiality which is expected to be required and is included in the Contract Price. Masked for Confidentiality Masked for Confidentiality Masked for Confidentiality Any items not listed but found to be required during the progress of the Work under the Deed will be valued using the same principles applied by the Contractor to arrive at the rates included in this Table 3.1. Ref 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Item Description Owned or Operating costs, External excluding Hire operators Daily cost Note 2 standby on Per hour of Ownership, Other Note 1 operation incl insurance (list) Masked for Confidentiality TBM - 3.9M Dia open SS - Operate incl cutter consumption TBM Grout Plant Operate TBM Grout Plant Cement & Bentonite Silos Roadheader S200m, 200 Kw, Hire and operating costs Roadheader, 200Kw, Auto Profile System, Hire Locomotive Tunnel Car Vent Fan - TBM Tunnel Operate (excl power costs) Gantry Crane - Operate (no power costs) |Water Treatment Plant, 16 L/Sec - Operate, Maintain incl chemicals Telehandler - Operate Shotcrete Pump & Boom - Operate Rockbolter - Operate Fel CAT 972 - Operate in Tunnel Elevated Work Platform - Hire & Operate Compressor, 1000 Cfm & Receiver - Operate Bunded Fuel Installation 134 TABLE 3.1 CONSTRUCTION PLANT DIRECT COSTS - Operate Masked for Confidentiality 18 Bobcat - Operate 19 Hiab Truck - Operate 20 Grout Pump for Rockbolts 21 Site Vehicle 22 Alimak 23 |Electrical Reticulation Maintain 24 Dewatering Pump 20KW 25 Power Reticulation Hire for RH 26 TBM Power Reticulation, Hire for Job Duration Notes Operating time measured by recorded time on equipment hour meter or other agreed method of recording. Operating costs to include all fuels, oils and greases, power, spares and any other direct operating expenses. 1 2 Items required as spares or backup and available for use will be classed as on standby. Items part used on any day will be considered as on standby for the balance of the day (pro rata) assuming a 20 hour maximum day for underground works and a 12 hour maximum day for surface works. 3 Items no longer in use or awaiting or undergoing repair will be classed as unavailable and not included for payment. Rates do not include costs of power (to be supplied by the Principal free of charge) 135 TABLE 3.2 LABOUR AND SUPERVISION DIRECT COSTS The Table 3.2 contains a comprehensive list covering all classifications of staff and trade labour expected to be employed on the Work under the Deed. Masked for Confidentiality Any classifications not listed but found to be required during the progress of the Work under the Deed will be valued using the same principles applied by the Contractor to arrive at the rates included in this Table 3.2. Ref Labour Classification Daily rate Note Hourly rate Note 2 1 Average hourly shift pattern Rate Staff classifications: List by category. Daily or hourly rate according to employment terms. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Masked for Confidentiality Project Manager Project Superintendent Project Engineer Snr Tunnel Project Engineer Jnr Tunnel Safety Officer/Coord Shift Boss - Tunnel Foreman - Senior Foreman - Mid level Site Engineer - Senior Site Engineer - Tunnel Project Engineer M&E Foreman M&E Office Mngr/Administrator Admin Clerk Direct employed worker classifications List by trade or award classification. 15 16 17 18 19 20 21 22 23 24 Underground Labour single shift Tunnel Worker Class 1 Tunnel Worker Class 2 Tunnel Worker Class 3 Tunnel Worker Class 4 Tunnel Worker Class 5 - Underground Labour double shift Tunnel Worker Class 1 Tunnel Worker Class 2 Tunnel Worker Class 3 Tunnel Worker Class 4 Tunnel Worker Class 5 - Masked for Confidentiality 136 Time & Double time 1/ 2 TABLE 3.2 LABOUR AND SUPERVISION DIRECT COSTS 25 26 27 28 29 Surface Labour - single shift |Surface Worker Class 2 |Surface Worker Class 3 |Surface Worker Class 4 |Surface Worker Class 5 |Surface Worker Class 6 Masked for Confidentiality Subcontract worker classifications Note 3 List by trade or award classification. 1 2 3 Notes Rates included cover all direct and indirect employee costs including loadings for holidays and sick pay, superannuation, bonus provisions, statutory on-costs, vehicle & accommodation allowances where applicable, company supplied vehicles to be included in plant & equipment, and any other costs associated with staff employment. Rates included cover all direct and indirect employee costs including loadings for holidays and sick pay, superannuation, bonus provisions, statutory on-costs, and any other costs associated with employment of labour under the terms of the industrial instrument applicable to the Project. Rates included cover all costs associated with employment of subcontract workers under the terms of the industrial instrument applicable to the Project. 137 TABLE 3.3 DAILY DIRECT COSTS OF MAINTAINING AND OPERATING SITE FACILITIES AND SERVICES, INCLUDING TUNNEL SERVICES NOT OTHERWISE INCLUDED IN TABLE 3.1. Masked for Confidentiality Ref Item Description 1 Operate miscellaneous tunnel and shaft services not otherwise included in Table 3.1 Maintain site offices and facilities, including ownership and operating costs of all miscellaneous office and communication costs and equipment during periods of cost reimbursable working 2 Rate per 24 hr day when working in tunnel Rate per 24 hr day when not working in the tunnel Rate per 12 hr working day when working in the tunnel Rate per day when no work is proceeding on site Masked for Confidentiality TABLE 3.4 OVERHEAD AND MARGIN ON MATERIAL AND SUBCONTRACT COSTS (OTHER THAN SUBCONTRACT LABOUR): Masked for Confidentiality 138 Schedule 4 GBR Administration Masked for Confidentiality 139 Masked for Confidentiality 140 Masked for Confidentiality 141 Masked for Confidentiality 142 Masked for Confidentiality 143 Masked for Confidentiality 144 Masked for Confidentiality 145 Masked for Confidentiality 146 Masked for Confidentiality 147 Masked for Confidentiality 148 Masked for Confidentiality 149 Masked for Confidentiality 150 Masked for Confidentiality 151 Masked for Confidentiality 152 Masked for Confidentiality 153 Masked for Confidentiality 154 Masked for Confidentiality Masked for Confidentiality 155 Masked for Confidentiality 156 Masked for Confidentiality 157 Masked for Confidentiality 158 Schedule 5 Provisional Sums Item No. 5.1 Description Provisional Sum for: the additional administration costs of complying with the terms and conditions of any Interface Agreement executed after the date of the Deed which the Contractor reasonably considers are substantially more onerous than those contained in the relevant Draft Interface Agreement (refer clause 6.2(b)(ii)(B) of the General Conditions of Deed); and all monitoring required to be undertaken by the Contractor as part of the Work under the Deed including: monitoring of CCM Tunnels and adjustments to construction methodologies in the vicinity of CCM Tunnels as a result of restrictions on excavation imposed by CCM or otherwise associated with the actual crossing of the CCM Tunnels; monitoring of BOOS in accordance with Sydney Water requirements; and monitoring of RailCorp assets in accordance with RailCorp requirements. 5.2 5.3 159 Provisional Sum for disposing of water from CES (Refer Part 4.5 of Schedule 4). Provisional Sum for maintaining site infrastructure at CES during excavation of CES. Provisional Sum Masked for Confidentiality Schedule 6 Key Personnel Name Christian D‟Hondt Nominated Position Project Manager John Milner Construction Manager Dougal Guthrie Senior Project Engineer Claire Driver Project Engineer Todd Ferguson Site Engineer Charles Scarf Occupational Health, Safety, Environment & Community Manager Glenn Day Tunnel Superintendent Darren Campbell Mechanical & Electrical Superintendent 160 Schedule 7 Insurances The Contractor agrees to take out and maintain, or cause to be taken out and maintained, the following insurance coverage in accordance with clause 29 of the General Conditions of Deed. (a) Public and Products Liability Insurance covering bodily injury or death suffered by third parties and loss of or damage to property, including the property of the Principal, occurring in connection with the execution by the Contractor of the Work under the Deed and its other obligations under the Deed or arising out of the use, manufacture, supply or installation of any item or thing by the Contractor, in an amount not less than per Masked for Confidentiality for Products and Completed Operations liability to be in the joint names of each Interface Party or note each Interface Party‟s interests. Masked for Confidentiality This insurance must be in force on the Commencement Date and be maintained until the issue of the Final Payment Certificate or the early termination of the Deed. (b) Worker’s Compensation in accordance with the statutory requirements applicable in any jurisdiction where the Work under the Deed or any part is executed. This insurance must be in force on the Commencement Date and be maintained until the issue of the Final Payment Certificate or the early termination of the Deed. (c) Contract Works Insurance covering the Work under the Deed for the full reinstatement value plus the costs of demolition and removal and reasonable allowances for escalation and consultants‟ fees. Masked for Confidentiality Masked for Confidentiality This insurance must be in force before the Work under the Deed commences and be maintained until the expiry of the Defects Correction Period in relation to the Work under the Deed to which the insurance relates. (d) Professional Indemnity Insurance covering liability or damage arising from professional duties undertaken by the Contractor in an amount of not less than Masked for Confidentiality Masked for Confidentiality This insurance must be in force on the Commencement Date and be maintained until the expiration of the period of 161 seven years from the issue of the Final Payment Certificate or early termination of the Deed. (e) Transit Insurance covering the TBM and any Materials to be employed about or used in performing the Work under the Deed, for loss or damage, from the time such insured property leaves the premises of the manufacturer or any other place where the insured property is procured until delivery at the Site, for an insured sum of not less than the full replacement value of the insured property shipped or transported, including freight and insurance. This insurance must be in force at the start of each conveyance and be maintained until the end of each conveyance by delivery at the Site. Masked for Confidentiality (f) Motor Vehicle Insurance covering all motor vehicles owned, leased or hired by the Contractor used in the connection with the Work under the Deed, including the use of unregistered motor vehicles and plant in an amount not less than Masked for Confidentiality This insurance must be in force on or by the date any plant, equipment or motor vehicles are used in connection with the Work under the Deed or used on or around the Site and be maintained until the plant, equipment or motor vehicles cease to be used in connection with the Work under the Deed or on or around the Site. (g) All other insurances which: (i) a prudent contractor would provide or take out in respect of work of the nature of the Work under the Deed or any equipment utilised by the Contractor in undertaking the Work under the Deed; or (ii) are required by Law to be taken out or maintained by the Contractor. 162 Schedule 8 Approved Subcontractors Subcontracting The following parts of the Work under the Deed may be subcontracted to the following Subcontractors without the approval of the Principal‟s Representative under clause 16.1 of the General Conditions of Deed: Project Element Proposed Subcontractor/Supplier Precast Concrete Segment Manufacturer Structural Concrete Industries (Aust) Pty Limited (ABN: 62 003 872 259) or Wilson Tunnelling Pty Ltd (NZ Company) Gasket Manufacturers Phoenix GmbH (germany) Concrete Supplier Boral Construction Material Group Ltd (ABN 15 000 028 080) / Holcim (Australia) Pty Ltd (ABN 87 099 732 297) / Hanson Construction Materials Pty Ltd (ABN 90 009 679 734) Formwork / Concrete Placement P&T Formworking & Welding Pty Limited (ABN 72 003 994 625), Lis-con Services Pty Ltd (ABN 55 130 866 474) Traffic Management Australian Retro Pty Ltd (ABN 60 003 387 497) Temporary Water Treatment Plant OVIVO Australia Pty Ltd (ABN 11 089 029 809) Radio Communication Star Electrical Co Pty Ltd (ABN 65 000 218 708) Mechanical Contractor Star Electrical Co Pty Ltd (ABN 65 000 218 708) Electrical Contractor Star Electrical Co Pty Ltd (ABN 65 000 218 708) Cable Support Manufacturer Ancon Building Products Pty Ltd (ABN 41 000 496 079), Korvest Ltd (ABN 20 007 698 106) trading as EzyStrut or Ogis Engineering Pty Ltd (ABN 15 000 425 865) 163 Project Element Proposed Subcontractor/Supplier Piling Contractor Avopiling (NSW) Pty Ltd (ABN 58 142 840 275)or Advance Foundation Solutions (Aust) Pty Ltd (ABN 80 099 819 762) Steel Shaft Lining Manufacturer Rollpress Proplate Group Pty Ltd (ABN 92 011 070 394) Reinforcing Steel Bluescope Distribution Pty Ltd (ABN 88 096 380 068) trading as Smorgon Steel Sheet Metal Supplies, The Australian Steel Company (Operations) Pty Ltd (ABN 89 069 426 955), Onesteel Trading Pty Ltd (ABN 50 007 519 646) Structural Steel S&L Steel Fabrications Pty Ltd (ABN 54 121 540 038) or F.&D. Normoyle Engineering Pty Ltd (ABN 12 003 635 461) Systems Contractor (PLC programming etc) Star Electrical Co Pty Ltd (ABN 65 000 218 708) Fire System Contractor Star Electrical Co Pty Ltd (ABN 65 000 218 708) Spoil Removal Earth Exchange Pty Limited (ABN 58 124 884 206), Lion Earthworks Pty Ltd (ABN 72 106 908 365) or Kingsfeld Contracting (ABN 55 106 123 755) Waterproofing Bluey Technologies Pty Ltd (ABN 36 115 613 646) or Eptec Pty Ltd (ABN 48 080 052 259) Acoustic Shed Protector Building Systems Pty Limited (81 003 633 314), IDEC Solutions Pty Ltd (ABN 15 082 559 920) or Advance Steel Design Pty Ltd (ABN 46 121 192 523) Condition Surveys Opus International Consultants (NSW) Pty Limited (ABN 69 001 184 694) or Dilapidation Surveys Pty Limited (ABN 19 074 423 466) Survey Lynton Surveys Pty Ltd (ABN 27 084 774 514), Surex Pty Ltd (ABN 64 107 423 414) or VMT GmbH (Germany) 164 Schedule 9 Form of Security UNCONDITIONAL UNDERTAKING Bond No: 2010XX-XXXX At the request of Thiess Pty Ltd ABN 87 010 221 486 (“the Contractor”) and in consideration of Ausgrid ABN 67 505 337 385 of 570 George Street, Sydney NSW 2000 (“the Principal”) accepting this undertaking in respect of the contract for Design and Construction of Civil Works and Services for the City East 132kV Cable Tunnel (“the Contract”), Swiss Re International SE ARBN 138 873 211 (“the Financial Institution”) C/- Assetinsure Pty Limited ACN 066 463 803 of Level 3, 44 Pitt Street, Sydney NSW 2000 unconditionally undertakes to pay on demand any sum or sums which may from time to time be demanded by the Principal to a maximum aggregate sum of [Bond Amount in Words and Figures] (“the Sum”). This undertaking is to continue until: written notification has been received by the Financial Institution from the Principal that the Sum is no longer required by the Principal; or this undertaking is returned to the Financial Institution; or payment to the Principal by the Financial Institution of the whole of the Sum or such part as the Principal may require. Should the Financial Institution be notified in writing to its address set out above, purporting to be signed by the person holding the position of Executive Manager, Projects (or equivalent) for and on behalf of the Principal that the Principal desires payment to be made of the whole or any part or parts of the Sum, it is unconditionally agreed that the Financial Institution will make the payment or payments to the Principal forthwith without reference to the Contractor and notwithstanding any notice given by the Contractor not to pay same and without regard to the performance or non-performance by the Contractor or the Principal of the Contract. Provided always that the Financial Institution may at any time without being required so to do pay to the Principal: the Sum less any amount or amounts it may previously have paid under this undertaking or such lesser sum as may be specified by the Principal in writing to the Financial Institution to it‟s address set out above, and thereupon the liability of the Financial Institution hereunder shall immediately cease. This undertaking is governed by the laws of New South Wales, Australia. Each person who executes this undertaking on behalf of the Financial Institution under a power of attorney declares that he or she is not aware of any fact or circumstance that might affect his or her authority to execute under the power of attorney. Signed by the attorney of Swiss Re International SE under Power of Attorney dated this ______________ Day of _____________ 2011 Signature of Witness: ___________________________ Signature of Attorney: ___________________________ Name of Witness: ___________________________ Name of Attorney: ___________________________ 165 Schedule 10 Contract Programme 166 Schedule 11 Pre-Contract Information 1 DESIGN REPORT The document titled "Design of Civil Works and Services for the City East 132kV Cable Tunnel Project, Detailed Design Report (Rev B)" dated 9 September 2011, Document No. 60102986-RP-020 167 Schedule 12 DRB Appointment and Operating Procedures 1 DRB Appointment Selection criteria (a) (b) The parties agree that the following criteria apply in the selection and approval of DRB members: (i) It is desirable that all DRB members be experienced in the type of construction required in connection with the Contract, interpretation of contract documents and resolution of construction disputes. (ii) It is imperative that the DRB members be neutral, act impartially and be free of any conflict of interest. (iii) The goal in selecting the third member is to appoint a legal practitioner experienced in construction and engineering law who will complement the experience of the first two members and provide leadership of the operation of the DRB. (iv) If a list of potential members is included in the Contract, the members will be selected from those on the list, other than anyone who is unable or unwilling to accept appointment to the DRB. The parties agree the following circumstances (unless otherwise agreed in writing by the party giving its approval) constitute prohibitions and disqualifying relationships for prospective members: (i) a direct ownership interest in any entity or its related bodies corporate involved in the Project except for disclosed shareholdings approved by the parties, or a financial interest in the Project except for payment for services on the DRB; (ii) previous employment by, or financial ties to, any party involved in the Project within a period of twelve months prior to award of the Contract, except for fee-based consulting services on other projects and disclosed shareholdings approved by the parties; (iii) a close professional or personal relationship with any key member of any entity involved in the Project which, in the 168 reasonable judgment of either party, could suggest partiality or a conflict of interest; or (iv) (c) (d) prior involvement in the Project of a nature which could compromise that member's ability to participate impartially in the operations of the DRB. The parties agree the following circumstances constitute prohibitions and disqualifying relationships for members of the DRB following appointment: (i) employment, including fee-based consulting services, by any entity involved in the Project except with the express approval of both parties; or (ii) discussion concerning or the making of an agreement with any entity involved in the Project regarding employment after the Project is completed. For the purpose of clauses 1(a) to (d) of this Schedule 12 - DRB Appointment and Operating Procedures: (i) the term “member" also includes the member's current primary or full time employer; and (ii) the term “involved” means having a contractual relationship with either party to the Contract, or any other entity, such as a Subcontractor, Supplier, Consultant or other design professional, having a role in the Project. Disclosure statement (e) As a part of the selection process, the first two prospective members will be required to submit complete disclosure statements for the approval of both the Principal and the Contractor. Each statement must include: (i) a resumé of experience; and (ii) a declaration describing all past, present, anticipated and planned future relationships, including indirect relationships through the prospective member‟s primary or full-time employer: (A) to the Project; and (B) with all parties involved in the Contract, including Subcontractors, Suppliers and Consultants. Disclosure of close professional or personal relationships with all key members of all parties involved in the Project must be included, as well as current shareholdings in any entity involved in the Project. 169 (f) The third DRB member will be required to submit a statement that complies with clause 1(e) of this Schedule to the first two DRB members and to the Principal and Contractor as a part of the selection and evaluation process. Nomination and approval of first two members (g) The Principal and the Contractor must each nominate a proposed DRB member and convey the nominee's name and disclosure statement to the other party within three weeks after the Date of Contract. (h) If a nominee is not rejected within one week after receipt of the name and disclosure statement, that nominee will be deemed approved. (i) No reasons for rejection need be stated. In the event of rejection, the nominating party will submit another nomination within two weeks of receipt of the notice of rejection. This process will be repeated until two mutually acceptable members are named or clause 1(m) of this Schedule applies. Nomination and approval of third member (j) Upon approval of both of the first two members, the Principal and Contractor will instruct them to begin the selection process for the third member. The first two members will endeavour to nominate a third member who meets all the criteria listed in this Schedule. (k) The third member must be nominated within two weeks after the first two members are instructed to proceed with this selection. The nominee‟s name and disclosure statement will be conveyed to the Principal and the Contractor, who will either accept or reject the nominee within one week. In the event of rejection, the first two members will be requested to submit another nomination within one week of receipt of the notice of rejection. Replacement of members (l) If at any time the parties so agree, they may appoint a suitably qualified person or persons to replace any one or more members of the DRB. Unless the parties otherwise agree, the appointment will come into effect if a member declines to act or is unable to act as a result of death, disability, resignation or termination of appointment. The replacement will be appointed in the same manner as the replaced person was nominated and agreed upon under clause 1 of this Schedule. Failure to agree DRB (m) If any of the following conditions apply: (i) either party fails to nominate a member (for approval by the other party) within the time stated in clause 1(g) of this Schedule; 170 (ii) the parties fail to agree upon the appointment of the first two members within eight weeks after the Date of Contract; (iii) the parties fail to agree upon the appointment of the third member (to act as chairman) of the DRB within six weeks after the appointment of the first two members; or (iv) the parties fail to agree upon the appointment of a replacement person within six weeks after the date on which the original member declines to act or is unable to act as contemplated by clause 1(l) of this Schedule, then, at the request of either or both of the parties and after due consultation with both parties, the Institution of Engineers Australia (in the case of either of the first two members) or the NSW Law Society (in the case of the chairman) will appoint this member of the DRB. (n) An appointment pursuant to clause 1(m) of this Schedule will be final and conclusive. (o) Each party will be responsible for paying one-half of the remuneration of the appointing entity or official. 2 DRB Operating Procedures (a) The Principal and the Contractor must provide the DRB with one copy of all documents which the DRB may request, including the Deed, progress reports, variation instructions, certificates, determinations by the Principal‟s Representative and other documents pertinent to the dispute. All communications between the DRB and the Principal or the Contractor must be copied to the other party. The Principal and the Contractor must send copies of these requested documents and these communications to each member of the DRB. (b) The DRB must proceed in accordance with clauses 40.2 and 40.3 and this Schedule. Subject to the time allowed to give notice of a recommendation and other relevant factors, the DRB must: (i) act fairly and impartially as between the Principal and the Contractor, giving each of them a reasonable opportunity of putting its case and responding to the other's case; and (ii) adopt procedures suitable to the dispute, avoiding unnecessary delay or expense. (c) The DRB may conduct a hearing on the dispute, in which event it will decide on the date and place for the hearing and may request that written documentation and arguments from the Principal and the Contractor be presented to it prior to or at the hearing. (d) Except as otherwise agreed in writing by the Principal and the Contractor, the DRB has power to adopt an inquisitorial procedure, to 171 refuse admission to hearings or audience at hearings to any persons other than representatives of the Principal and the Contractor, and to proceed in the absence of any party who the DRB is satisfied received notice of the hearing; but has discretion to decide whether and to what extent this power may be exercised. (e) (f) The Principal and the Contractor empower the DRB, among other things, to: (i) establish the procedure to be applied in formulating its recommendation concerning a dispute; (ii) decide upon the DRB's own jurisdiction, and as to the scope of any dispute referred to it; (iii) conduct any hearing as it thinks fit, not being bound by any rules or procedures other than those contained in the Deed; (iv) take the initiative in ascertaining the facts and matters required for a recommendation; (v) make use of its own specialist knowledge, if any; (vi) decide upon the payment of financing charges in accordance with the Deed; (vii) decide upon any provisional relief such as interim or conservatory measures; and (viii) open up, review and revise any certificate, decision, determination, instruction, opinion or valuation of the Principal‟s Representative, relevant to the dispute. The DRB: (i) may convene in private after a hearing, if any, in order to have discussions and prepare its recommendation; (ii) must endeavour to reach a unanimous decision concerning its recommendation: if this proves impossible, the applicable recommendation will be made by a majority of the members, who may require the minority member to prepare a written report for submission to the Principal and the Contractor; and (iii) if a member fails to attend a meeting or hearing, or to fulfil any required function, the other two members may nevertheless proceed to make a recommendation, after first informing the parties, unless: (A) either the Principal or the Contractor does not agree that they do so; or 172 (B) the absent member is the Chairman and he/she instructs the other members not to make a recommendation. 173 Schedule 13 DRB Appointment Agreement DRB Appointment Agreement Dated Ausgrid ABN 67 505 337 385 (“Principal”) Thiess Pty Ltd ABN 87 010 221 486 (“Contractor”) [#] (“Member”) 174 Details Parties Principal, Contractor and Member Principal Name Ausgrid ABN 67 505 337 385 Address 570 George Street Sydney NSW 2000 Telephone [#] Fax [#] Attention [#] Name Thiess Pty Ltd ABN 87 010 221 486 Address [#] Telephone [#] Fax [#] Attention [#] Name [Name of Member] Address [Address of Member] Telephone [#] Fax [#] Attention [#] Contractor Member Recitals A The Principal and the Contractor have entered into a contract for the construction of the City East 132kV cable tunnel and services, including design of the TBM lining (“CECT Contract”). B Clause 40 of the CECT Contract provides for a dispute resolution process through the establishment and the operation of a Dispute Resolution Board (“DRB”) to assist in resolving disputes under the CECT Contract. The DRB will comprise of the Member and two other members. 175 C Governing law Together with clause 40 of the CECT Contract, this Agreement sets out the rights, obligations and duties of the Member, the Principal and the Contractor. New South Wales Date of agreement 176 General terms 1 Definitions and interpretation 1.1 Definitions In this Agreement: Agreement means this Agreement. Change means any modification, addition to or omission from or other variation of the Work under the Deed directed or approved by the Principal in writing in accordance with clause 33 of the CECT Contract. Confidential Information means all information disclosed to the Member by, or on behalf of, the Principal, the Contractor or any related entity of the Principal or the Contractor, including: (a) information, which, either orally or in writing, is designated or indicated as being the proprietary or confidential information of the Principal or the Contractor; (b) trade secrets or information, which is capable of protection at law or equity as confidential information; (c) information from a third party, where the Member is advised by the Principal, the Contractor or any related entity of the Principal or the Contractor that such information is confidential; and (d) information derived or produced, partly or wholly, from the information referred to above, including any calculation, conclusion, summary or computer modelling, whether the information was disclosed: (e) orally, in writing or in electronic or machine readable form; (f) before, on or after the date of this Agreement; (g) as a result of discussions between the Parties; or (h) by the Principal, the Contractor, any of the Principal‟s or the Contractor‟s related entities or third parties, which is not in the public domain. Details is the section of this Agreement headed “Details”. Dispute Resolution Board or DRB means the board constituted by the Member and two other members mutually selected by the Principal and the Contractor in accordance with clause 40.2 of the CECT Contract to consider and recommend resolution of disputes referred to it. 177 GST means a goods and services tax, as governed by the GST Act. GST Act is A New Tax System (Goods and Services Tax) Act 1999 (Cth). Parties means the Principal, the Contractor and the Member. Project means Energy Australia‟s City East 132kV Cable Tunnel Project, as more precisely described in the CECT Contract. Schedule of Rates means Schedule 1 to this Agreement. Site means Site as defined in the CECT Contract. Valid Tax Invoice means an invoice which complies with the provisions of the GST Act relating to the production and form of tax invoices for GST purposes. Work under the Deed means the whole of the work to be supplied and carried out by the Contractor in accordance with the CECT Contract and includes all Changes and all work and activities necessary for completion of the work to be carried out by the Contractor, whether described in the CECT Contract or not. Works means that part of the Work under the Deed (including Changes) which is required by the CECT Contract to be handed over to the Principal. 1.2 Interpretation In this Agreement unless a contrary intention is stated: 2 (a) the singular includes the plural and vice versa; (b) a reference to a clause is a reference to a clause of this Agreement; and (c) headings are for reference only and do not form part of this Agreement. Formation of the DRB The Parties acknowledge that the DRB has been formed. 3 Relationship between Agreement and CECT Contract 3.1 Application of CECT Contract Clauses 40.2 and 40.3 of, and Schedule 12 to, the CECT Contract apply to this Agreement as if they were set out in full in this Agreement. 3.2 Agreement to prevail Each Party agrees that if there is any inconsistency between the terms of this Agreement and the CECT Contract, the terms of this Agreement prevail. 178 4 Agreement effective This Agreement is effective as of the date all Parties have signed this document and continues until: (a) the DRB is dissolved in accordance with clause 40.2(d) of the CECT Contract; or (b) this Agreement is terminated under clause 12. 5 Member warranties and obligations 5.1 Member warranties The Member warrants that he or she (as the case may be): (a) does not have a direct ownership interest in any entity or its related bodies corporate involved in the Project; (b) does not have a financial interest in the Project except for payment for services under this Agreement; (c) has not been previously employed by, and does not have and has not had, within a period of 12 months prior to execution of the CECT Contract, any financial ties to any party involved in the Project except for fee-based consulting services on other projects and shareholdings disclosed before the date of this Agreement to, and approved by, the Principal and the Contractor; (d) does not have a close professional or personal relationship with any key person associated with any entity involved in the Project which, in the reasonable judgment of the Principal or the Contractor, could suggest partiality or a conflict of interest; and (e) has no prior involvement in the Project of a nature which could compromise the Member's ability to participate impartially in the operations of the DRB, except as disclosed to the Principal and the Contractor in accordance with the process set out in clauses 1(e) and (f) of Schedule 12 to the CECT Contract. 5.2 Member obligations The Member must: (a) consider fairly and impartially each dispute referred to the DRB; (b) act independently in the consideration of facts and conditions relating to each dispute referred to the DRB; (c) perform honestly the duties and functions set out in clauses 40.2 and 40.3 of, and Schedule 12 to, the CECT Contract: (i) with due care and diligence; and 179 (ii) in compliance with all applicable laws, regulations and other statutory requirements; (d) be available for any Site visit and hearings described in clause 40.2 of and clause 2 of Schedule 12 to the CECT Contract; (e) not give advice to the Principal, the Contractor, the Principal‟s directors, officers or employees or the Contractor‟s directors, officers or employees concerning the conduct of the CECT Contract, other than in accordance with the operating procedures set out in clause 2 of Schedule 12 to the CECT Contract; (f) not, for the duration of this Agreement, be employed, including as a fee-based consultant, by any entity involved with the Project, except as may be agreed in writing by the Principal and the Contractor; and (g) not enter into discussions or make any agreement with any entity involved in the Project regarding employment after the Project is finished. 6 Principal’s commitments and responsibilities 6.1 Principal’s obligations The Principal must: 6.2 (a) not solicit advice or consultation from the DRB or the Member on matters dealing with the resolution of disputes which may compromise the DRB‟s integrity; (b) act in good faith towards the Member and the DRB; and (c) comply with reasonable requests of the DRB. Principal’s provision of services The Principal must, at its own expense, provide the DRB with the following administrative services: 7 (a) a meeting room; (b) clerical support; and (c) [Note: To be agreed between the parties prior to the execution of this Agreement]. Contractor’s commitments and responsibilities The Contractor must: (a) not solicit advice or consultation from the DRB (including the Member) on matters dealing with the resolution of disputes which may compromise the DRB‟s integrity; (b) act in good faith towards the Member and the DRB; and 180 (c) 8 comply with reasonable requests of the DRB. Confidentiality In relation to all Confidential Information disclosed to the DRB during the resolution of a dispute, the Member: 9 (a) must keep that information confidential; (b) must not disclose that information except to a Party or a representative of that Party participating in the resolution of the dispute or if compelled by law to do so; (c) must not use that information for a purpose other than the resolution of the dispute; and (d) is bound by this obligation of confidentiality whether or not such Confidential Information is or later becomes available in the public domain. Conflict of interest If the Member, during the term of appointment as a member of the DRB, becomes aware of any circumstance that might reasonably be considered to affect the Member‟s capacity to act impartially, or which is inconsistent with a warranty that the Member has given under clause 5.1, the Member must inform the Principal and the Contractor and the other two members of the DRB as soon as practicable after becoming aware of the circumstance. 10 Liability 10.1 Liability The Member is not liable to either the Principal or the Contractor for any act done or omission made in good faith and with due care and diligence in the performance or non-performance of his or her (as the case may be) obligations under this Agreement. 10.2 Due care and diligence For the purpose of clauses 10.1, the Member‟s act is deemed to have been done in good faith and with due care and diligence unless no reasonable person in the position of the Member would have so acted or made such an omission. 11 Payment 11.1 Payment for services and expenses (a) The Contractor must pay the Member for the services performed by the Member at the rates set out in the Schedule of Rates. (b) Any direct expenses not included in the rates set out in the Schedule of Rates and incurred by the Member in the course of carrying out the Member‟s functions and obligations under this Agreement must be reimbursed at the actual cost to the Member in accordance with this Agreement. Such expenses include, but are not limited to, parking, 181 travel expenses, food and accommodation, telephone and postage. Billing for such expenses must include an itemised listing supported by copies of the original bills, invoices, expense accounts and miscellaneous supporting data. 11.2 Invoices The Member must submit a Valid Tax Invoice to the Contractor for payment for services provided not more often than once per month during the progress of Work under the Deed. Such invoices must be in a format approved by the Contractor, and accompanied by a general description of activities performed during that period. 11.3 11.4 Taxes (a) If any supply made by the Member under this Agreement is, or becomes, subject to GST, the Member is, subject to his or her (as the case may be) compliance with clause 11.2, entitled to receive the amount equal to any GST owed or owing in addition to the amount forming the payment under this Agreement for the services supplied by the Member. (b) If any Party is required to reimburse or indemnify another Party for a cost, expense or liability (“Cost”) incurred by that other Party, the amount of that Cost for the purpose of this Agreement is the amount of the Cost incurred less the amount of any credit or refund of GST to which the Party incurring the Cost is entitled to claim in respect of the Cost. (c) In this clause 11.3 the expressions “supply”, “recipient” and “taxable supply” have the meaning given to those expressions in the GST Act. (d) Unless otherwise expressly stated, all prices or other sums payable or consideration to be provided under this Agreement are exclusive of GST. (e) If the amount of GST paid or payable by the supplier on any supply made under this Agreement differs from the amount of GST paid by the recipient, because the Commissioner of Taxation lawfully adjusts the value of the taxable supply for the purpose of calculating GST, then the amount of GST paid by the recipient will be adjusted accordingly by a further payment by the recipient to the supplier or the supplier to the recipient, as the case may be. Audit The Member must keep available for inspection by the Principal or the Contractor for a period of three years after final payment, the cost records and accounts pertaining to this Agreement. 12 Termination of Agreement (a) Subject to clauses 12(b) and 13.3, this Agreement may be terminated by mutual written agreement of the Principal and the Contractor. (b) This Agreement remains in force until: 182 (i) (ii) a replacement Agreement is entered into by: (A) the Principal; (B) the Contractor; and (C) the replacement member of the DRB; or the DRB is dissolved in accordance with clause 40.2(d) of the CECT Contract. 13 Termination of Member 13.1 Resignation The Member may resign from the DRB by providing four weeks‟ written notice to the two other members of the DRB, the Principal and the Contractor. 13.2 Termination The Principal and the Contractor may, by mutual written agreement, terminate the Member‟s appointment by providing ten business days‟ written notice to the Member. 13.3 Re-Appointment If the Member resigns under clause 13.1 or has his or her membership terminated under clause 13.2, then, unless the circumstances referred to in clause 12(a) and 12(b)(ii) pertain, a replacement member of the DRB must promptly be appointed using the procedures set out in clause 1(l) of Schedule 12 to the CECT Contract. The Principal and the Contractor acknowledge that they must enter into a replacement agreement in the same form as this Agreement with the replacement member. 14 15 16 Law of this Agreement (a) The law of this Agreement is the law in force in New South Wales. (b) The Parties submit to the non exclusive jurisdiction of the courts of New South Wales. Nature of the relationship (a) Nothing in this Agreement constitutes a joint venture, agency, partnership or other fiduciary relationship between any two or more of the Parties. (b) No Party has authority to bind another Party. (c) At all times during the performance of services pursuant to this Agreement, the Member is an independent consultant and is not an employee or agent of the Principal or Contractor. Notices Unless otherwise specifically provided, any notice, consent, approval or other communication under this Agreement must be: 183 17 (a) in writing; and (b) delivered by hand or by mail to the address, or sent to the facsimile number or email address, shown in the Details, or such other postal address, facsimile number or email address as a Party may notify to the other Parties from time to time in writing. Assignment The Member may not assign any right under this Agreement without the prior written approval of the Principal and the Contractor. EXECUTED as an agreement 184 Schedule 1 - Schedule of Rates [Note: Rates for payment of the Member’s services to be inserted.] 185 Signing page DATED:______________________ SIGNED by #NAME OF AUTHORISED REPRESENTATIVE # as authorised representative for AUSGRID in the presence of: ) ) ) ) ............................................................ ) Signature of witness ) ) ............................................................ ) Name of witness (block letters) ) ............................................................ ) By executing this agreement the signatory warrants that the signatory is duly authorised to execute this agreement on behalf of AUSGRID ) 186 SIGNED by #NAME OF ) AUTHORISED ) REPRESENTATIVE # as authorised representative for THIESS ) PTY LTD in the presence of: ) ............................................................ ) Signature of witness ) ) ............................................................ ) Name of witness (block letters) ) ............................................................ ) By executing this agreement the signatory warrants that the signatory is duly authorised to execute this agreement on behalf of THIESS PTY LTD ) ) SIGNED by [#NAME OF MEMBER#] in the presence of: ) ) ) ) ............................................................ ) Signature of witness ) ) ............................................................ ) ............................................................ ) Signature of [#NAME OF MEMBER#] Name of witness (block letters) ) 187 Schedule 14 Subcontractors Statement and Statutory Declaration 188 189 190 Part 2 Statutory Declaration [Name of Contractor] [#] STATUTORY DECLARATION Statutory declaration in the matter of building contract dated [#] (“Contract”) between [#] (the “Principal”) and [#] (ABN [#]) (“Contractor”) I, [#] of [#] in the state of New South Wales, [occupation], do solemnly and sincerely declare that, after having made enquiries: 1 I have knowledge of the relevant facts and am authorised by the Contractor to make this statutory declaration on its behalf; 2 this statutory declaration is made under clause 7.3(e)(ii) of the Contract in relation to the payment of a progress certificate in respect of the progress claim no. [#] submitted by the Contractor on [#]; [Note : in the case of payment of the final payment certificate issued by the Principal’s Representative under clause 7.5(a) of the Contract, replace the above paragraph with the following paragraph: this statutory declaration is made under clause 7.5(g) of the Contract in relation to the payment of the final payment certificate issued by the Principal’s Representative under clause 7.5(d) of the Contract] [Note : in the case of payment of the certificate issued by the Principal’s Representative under clause 37.2(d) of the Contract, replace the above paragraph with the following paragraph: this statutory declaration is made under clause 37.2(f)(ii) of the Contract in relation to the payment of the certificate issued by the Principal’s Representative under clause 37.2(d) of the Contract] 3 all amounts properly payable by the Contractor to consultants, suppliers and subcontractors in respect of the Work under the Contract have been paid; 4 there are no outstanding amounts due and payable by the Contractor or any security held by any person in relation to the Works. AND I MAKE this solemn declaration conscientiously believing the same to be true and by virtue of the provisions of the Oaths Act 1900 (NSW). 191 DECLARED at this [#] day of [#] before me: ) ) ) _______________________________ ) Signature of authorised witness ) ) _______________________________ ) Name of authorised witness ) (block letters) ) ) ) _______________________________ ) Address of authorised witness ) ) Capacity in which authorised witness ) takes the statutory declaration ) Justice of the Peace */ Solicitor of the ) Supreme Court of New South Wales ) holding a current practising certificate ) under the Legal Profession Act 1987 ) (NSW)* ) *Delete whichever is not applicable ) ) _______________________________ Signature of declarant 192 Schedule 15 Guarantee and Indemnity Guarantee and Indemnity Masked for Confidentiality 193 Guarantee and Indemnity Masked for Confidentiality 194 Masked for Confidentiality 195 Masked for Confidentiality 196 Masked for Confidentiality 197 Masked for Confidentiality 198 Masked for Confidentiality 199 Guarantee and Indemnity Masked for Confidentiality 200 Masked for Confidentiality 201 Schedule 16 CECT Development Approval 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 Schedule 16A Schedule of CECT Development Approval Responsibilities DA Ref Subject matter Contractor’s Responsibility Principal’s Responsibility Minister for Planning and Infrastructure, Project Approval 18th July 2011, Application #: MP 10_0141 A1 Compliance with planning approval documents The Contractor must comply with the requirements of the documents listed in A1 to the extent they relate to Work under the Deed and, in respect of condition A1(e), to the extent allocated under this Schedule 16A – Schedule of CECT Development Approval Responsiblities. The Principal must comply with condition A1(e) to the extent allocated under this Schedule 16A – Schedule of CECT Development Approval Responsiblities. A2 Inconsistency between documents Interpretation condition only. Interpretation condition only. A3 Compliance with reasonable requirements of the Director General The Contractor must comply with any reasonable requirements of the Director General to the extent they relate to Work under the Deed. The Principal must comply with all other reasonable requirements of the Director General. A4 Limits of approval Interpretation condition only. Interpretation condition only. A5 Statutory requirements Without limiting any of the Contractor's obligations under clause 6.1 of the General Conditions of Deed, the Contractor must obtain and maintain all approvals, licences and permits which relate to Work under the Deed other than the CECT Development Approval and Bligh Street Development Approval. The Contractor must ensure that a copy of the CECT Development Approval and all relevant environmental approvals are available on the Site at all times during the 219 DA Ref Subject matter Contractor’s Responsibility Principal’s Responsibility Minister for Planning and Infrastructure, Project Approval 18th July 2011, Application #: MP 10_0141 Project. A6 Compliance by employees, The Contractor must ensure contractors and sub-contractors that all of its employees, contractors and sub-contractors are aware of, and comply with, the conditions of the CECT Development Approval in relation to the Work under the Deed. A7 Environmental impacts resulting from actions of invitees The Contractor shall be responsible for environmental impacts resulting from the actions of all persons that it invites onto the Site. B1 Pollution of waters The Contractor must comply with (and not comit an offence under) section 120 of the Protection of the Environment Operations Act 1997 (NSW) and prevent the pollution of any waters in relation to the Work under the Deed. B2 Waste generated outside the Site The Contractor must not cause, permit or allow waste generated off Site to be received at the Site for storage, treatment, processing, reprocessing or disposal on the Site (except as expressly permitted by a licence under the Protection of the Environment Operations Act 1997 (NSW)) where Work under the Deed is performed. B3 Reuse and/or recycling of waste materials All in relation to the Work under the Deed. B4 Waste classification and disposal All in relation to the Work under the Deed. 220 DA Ref Subject matter Contractor’s Responsibility Principal’s Responsibility Minister for Planning and Infrastructure, Project Approval 18th July 2011, Application #: MP 10_0141 B5 Storage and handling of dangerous goods, combustible liquids and other hazardous materials All in relation to the Work under the Deed. C1 Pre and post construction road dilapidation reports and repair of damage All in relation to the Work under the Deed. C2 Consultation with infrastructure owners regarding impacts C3 Non interference with infrastructure and allowance for impacts The Contractor must comply with this condition in relation to the Work under the Deed. The Principal must satisfy this condition in relation to work not under the Deed. C4 RailCorp Rail Party Access Authority. The Contractor must comply with terms of this instrument which relate to Work under the Deed. The Principal must obtain this instrument. C5 Advise the Director General after a RailCorp authority issued The Principal must satisfy this condition. C6 Enrty into interface agreements Without limiting the operation of clause 6.2 of the General Conditions of Deed and Schedule 17 – Schedule of Interface Agreement Responsibilities, the Principal must satisfy this condition. C7 Advise the Director General of entry into interface agreements The Principal must satisfy this condition. C8 Note regarding scope of interface C9 Environmental Representatives The Principal must satisfy this condition. Interpretation condition only. Interpretation condition only. The Principal must satisfy this condition. 221 DA Ref Subject matter Contractor’s Responsibility Principal’s Responsibility Minister for Planning and Infrastructure, Project Approval 18th July 2011, Application #: MP 10_0141 C10 Construction Environmental Management Plan (CEMP) The Contractor must prepare the CEMP addressing Works under the Deed in consultation with the Environmental Representative and the Principal and implement the CEMP in respect of the Work under the Deed. The Contractor must allow the Principal 1 week to review the CEMP before approval is sought. The Principal must submit and obtain approval for the CEMP. The Principal must prepare and submit further CEMP‟s relating to works not under the Deed. C11(a) Construction Noise and Vibration Management Plan All in relation to Work under the Deed. C11(b) Traffic Management Plan All in relation to Work under the Deed. C11(c) Air Quality Management Plan All in relation to Work under the Deed. C11(d) Water Quality Management Plan All in relation to Work under the Deed. C11(e) Groundwater Management Plan All in relation to Work under the Deed. C11(f) Spoil Management Sub Plan All in relation to Work under the Deed. C12 Urban Design and Landscaping Sub-Plan The Principal must satisfy this condition. C13 Landscaping works The Principal must satisfy this condition. C14 Property inspections All in relation to Work under the Deed, notwithstanding the references to "Ausgrid" in the condition. C15 Risk assessment All in relation to Work under the Deed. 222 The Principal is responsible for providing operational stage groundwater control measures. DA Ref Subject matter Contractor’s Responsibility Principal’s Responsibility Minister for Planning and Infrastructure, Project Approval 18th July 2011, Application #: MP 10_0141 C16 Rectification of property damage The Contractor is responsible for rectification of, or payment of compensation for, property damage caused by the performance of the Work under the Deed. The Contractor may negotiate compensation with the property owner for property damage caused by Work under the Deed, but must permit the Principal to attend any settlement negotiations and must not agree to a settlement or resolution without the Principal's prior written approval. C17 Maintenance of access to properties All in relation to Work under the Deed. C18 Utilities and services All in relation to Work under the Deed other than those aspects for which the Principal is responsible. C19 Cathodic protection systems and stray currents All in relation to Work under the Deed. C20 Contingency plans for accidental damage and repair of services All in relation to Work under the Deed. C21 Minimise disruption to services and advise affected customers. The Contractor must minimise disruption of services. The Contractor must provide the Principal with details of any proposed service disruptions which may arise from the Work under the Deed to facilitate customer notification. 223 The Principal is responsible for rectification of, or payment of compensation for, property damage caused solely by Operation of the Works. The Principal may negotiate with property owners in respect of any property damage caused solely by the Operation of the Works. The Principal is responsible for any nessecary diversion of any utilities and services. Advise affected local residents and businesses of service disruption to the extent that the Contractor has provided the relevant notification to the Principal. DA Ref Subject matter Contractor’s Responsibility Principal’s Responsibility Minister for Planning and Infrastructure, Project Approval 18th July 2011, Application #: MP 10_0141 C22 CEMP and Operational Environment Management Plan: Waste Management and Reuse Sub-Plans The Contractor must prepare a Waste Management and Reuse Sub-Plan for the CEMP. D1 Minimise noise emmissions and vibration All in relation to Work under the Deed. D2 Acoustic enclosure All in relation to Work under the Deed. D3 Hours of work All in relation to Work under the Deed. D4 Hours of noise intensive activities All in relation to Work under the Deed. D5 Tunnelling 24 hours per day All in relation to Work under the Deed. D6 Out of hours construction work All in relation to the Work under the Deed except that, in relation to D6(c), the Contractor must inform the Principal of any notification (together with nessecary accompanying details) to be provided to affected residential receivers. D7 Construction noise objectives All in relation to Work under the Deed. D8 Regenerated noise criteria All in relation to Work under the Deed. D9 Construction noise All in relation to Work under the Deed. D10 Vibration limits All in relation to Work under the Deed. D11 High vibration levels All in relation to Work under the Deed. 224 The Principal must prepare a Waste Management and Reuse Sub-Plan for the Operational Environment Management Plan (OEMP). The Principal must notify affected residential receivers to the extent that the Contractor has provided the relevant notification to the Principal of any proposed out of hours activities. DA Ref Subject matter Contractor’s Responsibility Principal’s Responsibility Minister for Planning and Infrastructure, Project Approval 18th July 2011, Application #: MP 10_0141 D12 Vibration levels at heritage buildings and sensitive structures All in relation to Work under the Deed. D13 Unidentified Aboriginal objects All in relation to Work under the Deed. D14 Unexpected historical relics All in relation to Work under the Deed. D15 Soil and water quality impacts All in relation to Work under the Deed. D16 Acid sulphate soils management All in relation to Work under the Deed. D17 Contaminated land All in relation to Work under the Deed. D18 Lighting All in relation to design, installation and control of temporary construction lighting and the installation of permanent lighting. D19 Blasting All in relation to Work under the Deed. D20 Dust generation All in relation to Work under the Deed. All in relation to Operation of the Works. E1 Operational Environment Management Plan The Contractor must provide all relevant information requested by the Principal in respect of the Work under the Deed. The Principal must prepare, submit and obtain approval for the OEMP. E2 Certification of Tunnel The Contractor must obtain, and provide the Principal with, the nessecary certification from a suitably qualified structural engineer at least one month prior to the time notified by the Principal as the time it proposes to submit the OEMP. The Principal must include the certification in the OEMP. 225 All in relation to the design and operation of any permanent lighting. Notes: 1. For the purposes of this Schedule 16A – Schedule of CECT Development Approval Responsibilities, a reference to "All in relation to Work under the Deed" means "The Contractor must comply with all of the requirements of the condition as part of the Work under the Deed". 2. Nothing in this Schedule 16A - Schedule of CECT Development Approval Responsibilities limits any of the parties obligations elsewhere in the Deed. 226 Schedule 17 Schedule of Interface Agreement Responsibilities 1. 2. Interface Agreements (a) Draft Interface Agreement between the Principal and Sydney Water (b) Draft Interface Agreement between the Principal and State Library (c) Draft Interface Agreement between the Principal and Domain Trust (d) Draft Interface Agreement between the Principal and RailCorp (e) Draft Interface Agreement between the Principal, RTA and CCM Principal's obligations under Interface Agreements which are not the responsibility of the Contractor and are the Principal's responsibility for the purposes of the Deed Interface Agreements Draft Interface Agreement between the Principal and Sydney Water Allocation of responsibilities Category A: Obligations to be performed by the Principal All obligations other than those contained in paragraphs 1, 2, 3 and 4. Draft Interface Agreement between the Principal and State Library Category A: Obligations to be performed by the Principal None stated Draft Interface Agreement between the Principal and Domain Trust Category A: Obligations to be performed by the Principal None stated City East Cable Tunnel Interface Deed with RailCorp, draft dated 12 October 2011 Category A: Obligations to be performed by the Principal Clauses 2, 3.1, 4, 5, 6, 7.4 Category B: Obligations where the Contractor must assist as required Clauses 3.2, 3.3, 7.2, 7.3, 9.1, 9.2, 9.3, 9.4, 12, 17.1, 22.2 Interface Agreements Allocation of responsibilities RTA / CCM City East Cable Tunnel Stakeholder Deed, draft dated 29 September 2011 Category A: Obligations to be performed by the Principal Clauses 2, 3.1(b) and (c), 3.3, 3.4, 3.4,4.3(b), 4.4(a), (i) and (k), 4.4(n), 4.5, 5.1 (to the extent only that the Principal is responsible for the design of the Works), 5.2 (to the extent only that the Principal is responsible for the design of the Works), 6.3(b), 6.6, 6.7, 7.1(b), 7.4(b), 8.1, 9.1(b)(ii) and (iii), 9.1(c)(i), 9.2, 10, 11, 12.1 and 13.1 (but without limiting Principal's rights against the Contractor under the Deed or the operation of clause 41 of the General Conditions of Deed), 14 (in respect to any insurance obligations additional to the Contractors obligations under the Deed), 16.3(a), 17, 18 and 19. Category B: Obligations where the Contractor must assist as required Clauses 3, 3.1(b) and (c), 3.3, 3.4, 4.3(b), 4.4(a) and (k), 4.5, 5.1(b) (to the extent the Contractor is responsible for the design of the Works), 6.3(b), 6.6, 6.7, 7.1(b), 7.4(b), 8.1, 9.1(b)(ii) and (iii), 9.1(c)(i), 9.2, 10, 11, 14.2(i), 16.3(a) and 17. 1 The Contractor acknowledges that in order to comply with its obligations under clause 6.2(a)(iv) of the Deed, it shall assist the Principal in any way that the Principal may reasonably require to allow the Principal to perform the obligations specified in category B in the tables above, in accordance with the terms specified in this schedule 17. 2 Where the Interface Agreement requires or permits the Principal to request, obtain or provide information, reports, material, documents, notice or an approval („information‟) to or from the Interface Party, then the Contractor must: (a) make such request of the Principal setting out the need for such information (who in turn shall make the request from the Interface Party); and (b) provide such information to the Principal not less than 2 business days‟ prior to the time the Principal is required to give such information to the relevant Interface Party to allow the Principal to comply with its obligations under the Interface Agreement, provided that if the time frame for provision of information to an Interface Party is less than 2 Business Days, the Contractor must provide such information to the Principal in a time frame as reasonably agreed between the Principal and the Contractor. 228 3 Where the Interface Agreement requires that the Principal and the Interface Party meet, confer, co-operate, negotiate or discuss, then the Contractor must participate in such activities if and when required by the Principal. 4 Terms defined in each Interface Agreement shall apply with respect to the Deed unless it is expressly provided otherwise. 229 Design and Construction of Civil Works and Services for the City East 132kV Cable Tunnel EXHIBITS EA 0933/09 Exhibit A Specification Refer to attached Specification. Due the substantial size of the information comprised in this Exhibit of the contract, the information has not been published. Should you wish to be provided with a copy of this Exhibit please contact the GIPA coordinator on 9269 2673. Exhibit A1 Alternate specification Refer to attached alternate specification. Due the substantial size of the information comprised in this Exhibit of the contract, the information has not been published. Should you wish to be provided with a copy of this Exhibit please contact the GIPA coordinator on 9269 2673. Exhibit B Environmental Assessment Refer to attached Environmental Assessment. Due the substantial size of the information comprised in this Exhibit of the contract, the information has not been published. Should you wish to be provided with a copy of this Exhibit please contact the GIPA coordinator on 9269 2673. Exhibit C Geotechnical Baseline Report Refer to attached Geotechnical Baseline Report. Due the substantial size of the information comprised in this Exhibit of the contract, the information has not been published. Should you wish to be provided with a copy of this Exhibit please contact the GIPA coordinator on 9269 2673. Exhibit D Interface Agreements and Draft Interface Agreements Refer to the following attached Interface Agreements: Item 1 - Draft Interface Agreement between the Principal and Sydney Water; Item 2 - Draft Interface Agreement between the Principal and State Library; Item 3 - Draft Interface Agreement between the Principal and Domain Trust; Item 4 - Draft Interface Agreement between the Principal and RailCorp; and Item 5 - Draft Interface Agreement between the Principal, RTA and CCM. Exhibit D, Item 1: Draft Interface Agreement between the Principal and Sydney Water Due the substantial size of the information comprised in this Exhibit of the contract, the information has not been published. Should you wish to be provided with a copy of this Exhibit please contact the GIPA coordinator on 9269 2673. Exhibit D, Item 2: Draft Interface Agreement between the Principal and State Library Masked for Confidentiality Masked for Confidentiality Masked for Confidentiality Masked for Confidentiality Exhibit D, Item 4: Draft Interface Agreement between the Principal and RailCorp Due the substantial size of the information comprised in this Exhibit of the contract, the information has not been published. Should you wish to be provided with a copy of this Exhibit please contact the GIPA coordinator on 9269 2673. Exhibit D, Item 5: Draft Interface Agreement between the Principal, RTA and CCM Due the substantial size of the information comprised in this Exhibit of the contract, the information has not been published. Should you wish to be provided with a copy of this Exhibit please contact the GIPA coordinator on 9269 2673.
© Copyright 2024