SESI LTHW Building Conversions Construction Update

SESI LTHW Building Conversions
Construction Update - December 22nd, 2014
(Update for the remaining 2014 SESI work)
Sunday's GALE helicopter pick.
SESI LTHW Building Conversions
Construction Update - December 22nd, 2014
(Update for the remaining 2014 SESI work)
Work For The Upcoming Week
Construction Impacts
• Cubberly: Laying pipe, backfilling trench, boiler pad work,
(weather permitting), installing pipe and conduit inside
mechanical room.
• Cubberly: Walkway bordering Green Library and Cubberly
is closed. Crews working throughout the first floor,
basement, and crews / heavy equipment outside between
Green Library and Cubberly.
• Forsythe: Painting enclosure and landscaping (weather
permitting).
• Forsythe: Crew working intermittently outside of Forsythe
by the new skid.
• Encina Commons: 12/20 Crane pick, riser insulation, and
POC connections to rebuilt skid. Steam Startup 12/29.
• Encina Commons: 12/20 Crane pick: Crothers Way
closed from 8:00AM-10:00AM, evacuation of offices under
crane swing from 8:30-8:45 during pick.
• Braun Corner: Punchlist work.
• Braun Corner: Crews working intermittently throughout
the building.
• Wilbur: Mechanical room steam pipe demo.
• Wilbur: Crews working in mechanical room.
• GALE: Installing pipe and waterproofing roofs.
• GALE: Crews working in mechanical rooms and roofs.
*Chemical odors from roof waterproofing chemicals*
• Main Quad: Punchlist work.
• Main Quad: Crews working in the attics.
• Hoover Tower: Minor punchlist work.
• Hoover Tower: Crews working throughout the building.
• TW Art Gallery: Balancing and punchlist work.
• TW Art Gallery: Crews working in the mechanical room.
• Roble Hall: Punchlist.
• Roble Hall: Crews working in the basement.
• Branner: Minor work in mechanical room.
• Branner: Crews throughout basement.
• Lagunita: Steam/condensate work.
• Lagunita: Crews working in the basement.
• Toyon: Minor work in mechanical room.
• Toyon: Crews working in the mechanical room.
• Durand: Painting exterior shaft
• Durand: Crews working inside the mechanical room.
• Mudd Chemistry: HHW piping phase 2.
• Mudd Chemistry: Crews working around exterior of the
building.