Annexure-PFR

Pre Feasibility Report
Table of Contents
1. Executive Summary ........................................................................................................................... 1
2. Introduction of the Project/ Background Information ....................................................................... 2
3. Project Description............................................................................................................................. 4
4. Site Analysis ...................................................................................................................................... 5
5. Planning ............................................................................................................................................. 6
6. Proposed Infrastructure ...................................................................................................................... 7
7. Rehabilitation and Resettlement (R&R) Plan .................................................................................... 7
8. Project Schedule & Cost Estimation .................................................................................................. 8
9. Analysis of proposal (Final recommendation) ................................................................................... 8
1. Executive Summary










Upper Bhadra Project is a major lift irrigation Scheme under implementation in the central
region of Karnataka State. It envisages lifting upto17.40TMC of water in first stage
from Tunga to Bhadra and lifting 29.90TMCof water in second stage from Bhadra to Tunnel
near Ajjampura, in Tungabhadra sub-basin of Krishna basin. It is planned to irrigate an extent of
2,25,515 hectares by micro irrigation in drought-prone districts of Chikmagalur, Chitradurga,
Tumkur and Davangere.
The primary objective of the project is providing sustainable irrigation facility in Kharif
season and the other objective of the project is to recharge the ground water table and provide
drinking water by filling 367 tanks in drought-prone taluks of the above said districts.
The overall climate of the Chikkamagalur project site area is very agreeable and cool, as it
comprises of a large extent of hilly terrain. The cold season is from December to February,
followed by the hot season from March to May. The period from June to September
constitutes the Southwest monsoon season. October and November may be termed the post
monsoon or retreating monsoon season. The humidity is very high during the monsoon
season, generally exceeding 90 percent. It is comparatively less during the rest of the year. The
driest part of the year is the period of January to March.
The overall climate of the Chitradurga project site area including Command Area is very hot
and semidry, as it comprises of some extent of rocky hilly terrain. The cold season is from
December to February, followed by the hot season from March to May. The period
from June to September constitutes the Southwest monsoon season. October and
November may be termed the post monsoon or retreating monsoon season. The humidity is very
high during the monsoon season, generally exceeding 80 percent. It is comparatively less during
the rest of the year. The driest part of the year is the period of March to May.
The Tumkur district falls in the eastern dry agro climatic zone. The temperatures start rising
from January to peak in may, around 400 C is common. There after it declines during
the monsoon period. The humidity is lowest during the dry season and highest during
the monsoon period.
The Davangere district falls under central dry agro-climatic zone of the Karnataka state and is
categorized as drought prone. Normal climatic parameters of the district are increasing
temperature from March to May, usually maximum April month and minimum temperature that
is coldest month during month of December.
The Average Annual Rainfall in Chikkamagalur areas is 758 mm. It varies from a low of 595
mm in Kadur Taluk to a high of 2379 mm in Mudigere. Average Annual Rainfall in
Chikkamagalur District is 1904mm.
The Average Annual Rainfall in Chitradurga areas is475 mm and Average Annual Rainfall in
Chitradurga District is 486.7 mm. The maximum precipitation of over 80% of total annual
rainfall occurs in four months between April and October.
The probability of occurrence of Annual Rainfall of Tumkur areas between 500-800mm
is 75%. September is the wettest month with monthly rainfall in excess of 170 mm.
Annual Rainfalls in the district varies from over 900mm in Tumkur to around 600mm in
Pavagada.
The comprehensive project envisages providing irrigation and drinking water to the parched
1
lands of Central Karnataka plateau and in specific:
(i) Providing irrigation facility for an area of 2,25,515 Ha of land in Tarikere, Kadur taluks of
Chikkamagalur district, Hosadurga, Hiriyur, Chitradurga and Challakere taluks of
Chikkamagalur district, Hosadurga, Hiriyur, Chitradurga and Challakere taluks of
Chitradurga district, Jagalur taluk of Davangere district and Sira, Chikkanayakanahalli
taluks of Tumkur district. The total requirement of water for irrigation in the command
area is 539.07 MCM (19.04 TMC).
(ii) Filling up of 367 Nos of Tanks to their 50% of live capacity are proposed. The
requirement of water for the purpose is 307.48 MCM (10.86 TMC) including
augmentation of 2.00 TMC for Vani Vilas Sagar Reservoir. The filling up of tanks will
facilitate recharging of ground water besides diluting the fluoride content.
 The site is located at 13018’0’’ N Latitude and 750 28’0’’ E Longitude. The entire project site
includes the area from the offtake of Tunga River in Chikkamagalur District to
Command Area under Chitradurga District, Tumkur District & Davangere District. The
proposed Canal alignment, intake structure, various lift points, delivery chambers, tunnel
and command areas will pass through State and Reserved Forests. This project falls under K-8
Sub-basin.
 The project involve submergence and about 364.50 forest land is required for the project. The
Bhadra Wildlife Sanctuary is nearby to the project canal towards south direction hence the
project attracts general condition as mentioned in the Environmental Impact Notification -2006
and its subsequent amendments and falls under ‘A category’.
 The proposed irrigation is only in Kharif period and the intensity of irrigation is 100%.
 Villages benefited by the proposed project:
• Total villages benefited under Chikkamagalur District = 199 No.s
• Total villages benefited under Chitradurga District = 442 No.s
• Total villages benefited under Tumkur District = 110 No.s
• Total villages benefited under Davangere District = 36 No.s
• Total villages benefited = 199+442+110+36 = 787 No.s
2. Introduction of the Project/ Background Information
2.1
Identification of project and project proponent.
Karnataka Neeravari Nigam Limited (KNNL) has been registered as a completely owned company
under Government of Karnataka as per the provisions of The Companies Act, 1956 with effect from 9th
December 1998. It has its Registered Office at 4th Floor, Coffee Board Building, No.1, Dr. B R
Ambedkar Veedhi, Bangalore – 560 001.
2.2. Brief description of nature of the project.
The comprehensive project envisages providing irrigation and drinking water to the parched lands of
Central Karnataka plateau and in specific:
(i) Providing irrigation facility for an area of 2,25,515 Ha of land in Tarikere, Kadur taluks of
Chikkamagalur district, Hosadurga, Hiriyur, Chitradurga and Challakere taluks of Chikkamagalur
district, Hosadurga, Hiriyur, Chitradurga and Challakere taluks of Chitradurga district, Jagalur
taluk of Davangere district and Sira, Chikkanayakanahalli taluks of Tumkur district. The total
2
requirement of water for irrigation in the command area is 539.07 MCM (19.04 TMC).
(ii) Filling up of 367 Nos of Tanks to their 50% of live capacity are proposed. The
requirement of water for the purpose is 307.48 MCM (10.86 TMC) including augmentation of
2.00 TMC for Vani Vilas Sagar Reservoir. The filling up of tanks will facilitate recharging of
ground water besides diluting the fluoride content.
 The project involves submergence and about 364.50 forest land is required for the project. The
Bhadra Wildlife Sanctuary is nearby to the project canal towards south direction hence the
project attracts general condition as mentioned in the Environmental Impact Notification -2006
and its subsequent amendments and falls under ‘A category’.
2.3. Need for the project and its importance to the country and or region.
Major economic activity of the region is due to agricultural activities, which are heavily monsoon
dependent. However, due to the inconsistent monsoons and erratic rainfall, the overall agricultural
production and consequently the per capita income and the overall economy of the region is low. In
addition, the area situated in central part of the State, like many other areas is highly drought prone.
Irrigation projects have to a large extent mitigated the problems due to monsoons and droughts in many
areas in the region. This proposed project similarly will provide irrigation facilities to the 2,25,515 Ha of
land in Tarikere, Kadur taluks of Chikkamagalur district, Hosadurga, Hiriyur, Chitradurga and
Challakere taluks of Chikkamagalur district, Hosadurga, Hiriyur, Chitradurga and Challakere taluks
of Chitradurga district, Jagalur taluk of Davangere district and Sira, Chikkanayakanahalli taluks of
Tumkur district in addition to providing drinking water and sub-soil replenishment. Thus improving the
agricultural output and increasing the per-capita income of the people of the region while also improving
groundwater scenario and clean drinking water to the people of the villages in the taluks.
2.4. Demand-Supply
.The total requirement of water for irrigation in the command area is 539.07 MCM (19.04 TMC).
Filling up of 367 Nos of Tanks to their 50% of live capacity are proposed. The requirement of
water for the purpose is 307.48 MCM (10.86 TMC) including augmentation of 2.00 TMC for
Vani Vilas Sagar Reservoir. The filling up of tanks will facilitate recharging of ground water
besides diluting the fluoride content.
2.5.
Imports vs. Indigenous production
Not Applicable
2.6.
Export possibility
Not Applicable
2.7.
Domestic/ Export markets.
Not Applicable
2.8.
Employment Generation (Direct and Indirect) due to the project.
Around1000 people (200 Technical and800 construction labourers) are expected to be employed
temporarily for the construction work of Construction of 6.9 KM (approximate) length of tunnel
near Ajjampura to feed Chitradurga and Tumkur Branch Canals, tunnel in Tarikere taluk,
Construction of Chitradurga Branch canal, and Construction of Tumkur Branch Canal for
providing necessary infrastructure for drip irrigation to 2,25,515 Ha in Kharif season only.
3
3. Project Description
3.1.
Type of project including interlinked and interdependent project, if any.
The projects that are linked to Upper Bhadra Project by being in the same sub-basin as
Tungabhadra sub-basin (K-8) and by virtue of contributing the water savings to Upper Bhadra
Project are (1) Bhadra Project, (2) Gondi Anicut, (3) Tunga Anicut, (4) Vijayanagar Channels. The
savings of 13 TMC water has to come by modernizing these schemes. The utilization for Bhadra
Project,
The
modernization
of
which
is
cleared
by
CWC,
vide
Lr.
No.2(66)/2008/WR/GOI/Planning Commission/ Water Resources Department/ dated 31.03.2008.
3.2. Location (map showing general location, specific location, and project boundary &
project site layout) with coordinates.
The command area of the proposed project is enclosed as Annexure 1.
3.3. Details of alternative sites, considered and the basis of selecting the proposed site
particularly the environmental considerations gone into should be highlighted.
Not applicable
3.4.
Size & magnitude of operation
The entire proposed
components:
project
comprises
of
implementing
the
scheme
with
following
• Lifting water from Tunga River to Bhadra Reservoir in two stages.
• Construction of canal from Bhadra Reservoir to Delivery Chamber including two lifts and a tunnel
of 6.90 Km length and
• Tarikere lift and flow canals provide irrigation facility to 20,150 Ha of land in
Chikkamagalur district including Restoration of 33 Tanks coming within the Command Area
and filling of 46 Tanks.
• Canal network to provide irrigation facility to 2,25,515 Ha of land in Chikkamagalur and
Chitradurga, Tumkur and Davangere Districts including filling 254 tanks situated within the
command area.
3.5. Project description with process details (a schematic diagram/flow chart showing the
project layout, components of the project etc) should be given.
Enclosed as Annexure-1 and Annexure-2
3.6. Raw material required along with estimated quantity, likely source, marketing area of
final products, mode of transport of raw material and finished products.
Not applicable
3.7. Resource optimization/recycling and reuse envisaged in the project, if any, should be
briefly outlined.
Not applicable
3.8.
Availability of water its source, Energy/power requirement and sources should be given.
4
Water Requirement
The total requirement of water for irrigation in the command area is 539.07 MCM (19.04 TMC).
Filling up of 367 Nos of Tanks to their 50% of live capacity are proposed. The requirement of
water for the purpose is 307.48 MCM (10.86 TMC) including augmentation of 2.00 TMC for
Vani Vilas Sagar Reservoir.
Power Requirement
Power requirement for lifting water from Tunga to Bhadra Reservoir (Package - I) is about84484.39
HP and lifting water from Bhadra to Tunnel near Ajjampura (Package - II) is about
163604.69 HP Further, Power requirement for total drip irrigation to an extent of ICA of 2,25,515 Ha,
considering 39% of the area by pressurized system, is about 13986.86 HP . Thus total
requirement of power under UBP including Tarikere lift scheme is about 268204.41HP.
Source- After implementation of this scheme captive power generated out of wind energy will
be utilized for the project for the entire scheme including drip irrigation instead of power of
KPTCL
3.9. Quantity of wastes to be generated (liquid and solid) and scheme for their
Management/disposal.
Sewage generated from the labour camps will be treated in septic tank and soak pits that will be
designed and constructed as per IS 2470 Part-I and Part-II.
Domestic solid wastes proposed to be generated from labour camps will be disposed to nearby
Municipal Landfills.
3.10. Schematic representations of the feasibility drawing which give information of EIA
purpose
4. Site Analysis
4.1. Connectivity
The headwork at Tunga River near Muttinakoppa is accessible through State Highway (SH) from
Shivamogga to Mangalore.
Bhadra reservoir is accessible through Tarikere - Mangalore road (SH) from Tarikere. Upper Bhadra
main canal from Bhadra reservoir is approachable by T-M Road (SH) and South Central
5
railway. Nearest railway station is Tarikere. Tunnel reach is approachable through Tarikere Hosadurga Road and from Ajjampura Railway station by rail. Command area of Chitradurga Branch
canal is approachable by NH - 4 and NH - 206. Tumkur Branch Canal is approachable by various
major district roads. Nearest airports to project site are Bangalore and Mangalore.
4.2.
Land form, land use and land ownership.
Nearly 60% of the total land is cultivable and majority of this area is in rainfed agriculture. The major
crops grown are Jowar, Groundnut, Maize, Pulses and Sunflower. There are no major mines or
industries in the area.
.4.3. Topography (along with map)
Topography is relatively plain area with gentle to mild slopes. Toposheet is attached as Annexure-3.
4.4. Existing land use pattern (agriculture, non agriculture, forest, water bodies (including
area under CRZ), shortest distances from the periphery of the project to periphery of the
forest, national parks, wild life sanctuary, eco sensitive areas, water bodies (distance from, the
HFL of the river)). In case of notified industrial area a copy of the Gazette notification should
be given.
The existing land use pattern of the command area is agriculture. The Bhadra Wildlife Sanctuary is
nearby to the project canal towards south direction.
4.5. Existing Infrastructure
The project area mainly comprises of farmlands and villages.
4.6. Soil Classification
The soil in the command area is red soil with low water holding capacity, moderately deep fine
textured and heavy black cotton soils with high water yielding capacity but with poor internal
drainage. All these soils are generally suitable for irrigating the Kharif crops.
4.7.
Climatic data from secondary sources
The climate of the major command area which lies in Chitradurga and Tumkur districts is
characterized by dryness in major part of year and hot summer. The period from December to
February is the dry and comparatively cool season. The summer season from March to May is
followed by South-West monsoon season, from June to September. October and November
form the retreating monsoon or post monsoon season.
.4.8. Social Infrastructure available
Nearly 60% of the total land is cultivable and majority of this area is in rainfed agriculture. The major
crops grown are Jowar, Groundnut, Maize, Pulses and Sunflower. There are no major mines or
industries in the area.
5. Planning
5.1. Planning concept (type of industries, facilities, transportation, etc.,) Town and Country
Planning Development authority classification.
Not applicable.
6
5.2. Population Projection.
Influx of people will be only during construction phase, only few people will be employed for
operation and maintenance of the project.
5.3. Land use planning (breakup along with green belt etc.)
2,25,515 Ha of agricultural land will come under this scheme.
5.4. Assessment of Infrastructure Demand (Physical & Social).
The proposed project envisages the lifting of 29.90TMC of water from upper Bhadra and providing
irrigation facility to 2,25,515 Ha dry area which in turn improves the cropping pattern and crop yield.
5.5.
Amenities/facilities
Not applicable
6. Proposed Infrastructure
Proposed infrastructure includes canals, delivery chambers, pumphouses as well as office facilities
and access roads for easy access to project site.
6.1. Industrial Area (Processing area)
Not applicable
6.2. Residential Area (non processing area)
Not applicable
6.3. Green Belt
2,25,515 Ha of agricultural land will come under this scheme.
6.4. Social Infrastructure
Labour camps during construction will be constructed
6.5. Connectivity Traffic and Transportation Road/Rail/Metro/Water ways etc
Existing village roads will be used to transport men and materials to the project site. Wherever
applicable, roads will be developed or constructed.
6.6. Drinking water management (Source & Supply of water)
Drinking water for labour will be procured from existing local sources such as nearby wells/ tankers/
local water supply.
6.7.
Sewerage System
Sewage generated from the labour camps is proposed to be treated in Septic Tank and Soak Pits
designed and constructed as per IS 2470 Part-I & Part-II
6.8. Industrial waste management
Not Applicable
6.9.
Solid waste management
Domestic solid waste will be disposed to nearby municipal landfills.
6.10. Power requirement & Supply/Source
Power requirement for lifting water from Tunga to Bhadra Reservoir (Package - I) is about 84484.39
HP and lifting water from Bhadra to Tunnel near Ajjampura (Package - II) is about
7
163604.69 HP Further, Power requirement for total drip irrigation to an extent of ICA of 2,25,515 Ha,
considering 39% of the area by pressurized system, is about 13986.86 HP . Thus total
requirement of power under UBP including Tarikere lift scheme is about 268204.41HP
Source- After implementation of this scheme captive power generated out of wind energy will
be utilized for the project for the entire scheme including drip irrigation instead of power of
KPTCL
7. Rehabilitation and Resettlement (R&R) Plan
7.1. Policy to be adopted (Central/State) in respect of the project affected persons including
home oustees, land oustees, and landless labourers (a brief outline to be given).
The proposed project does not involve displacement of the families/houses for the project activities.
The total land required for the project is 5222.860 acres shall be acquired as per Right to Fair
Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act
(RTFC&LARR Act), 2013.
8. Project Schedule & Cost Estimation
8.1.
Project Schedule
The total developmental period of the entire proposed project will be about 5 years.
8.2. Cost Estimates
The total cost estimated for the proposed project is 12,340 Crores.
9. Analysis of proposal (Final recommendation)
9.1. Financial and social benefits with special emphasis on the benefit to the local people
including tribal population, if any, in the area
BC Ratio is estimated at 1.263 calculations for the project is as given in Annexure 4.
8
VILLAGES BENEFITED UNDER THE COMMAND AREA OF TARIKERE LIFT AND GRAVITY FLOW
VILLAGES BENEFITED UNDER THE COMMAND AREA OF CHITRADURGA BRANCH CANAL
VILLAGES BENEFITED UNDER THE COMMAND AREA OF TUMKUR BRANCH CANAL
VILLAGES BENEFITED UNDER THE COMMAND AREA OF JAGALUR BRANCH CANAL