2012 Bond Oversight Committee DPS Sustainability Discussion, MWBE and Project Goals Update, Construction Project Status April 17, 2015 Meeting Agenda • Public Comment 5 minutes • Sustainability Update 30 minutes • MWBE Update 30 minutes • Construction Projects Update 25 minutes -2- Sustainability Presentation Outline Sustainability Department Overview 2012 Bond Involvement & Support – Highlight Program: Xcel Energy, Energy Design Assistance (EDA) – Focus on Emily Griffith Shops project – Project Example (Rebate Funded): Palmer Gym Lighting Upgrade Sustainability and District Data Comparisons: Square Footage, Student Growth, Energy Additional Sustainability Initiatives including Student Support Programs -3- Sustainability Vision and Goals Develop and implement a comprehensive district-wide energy efficiency, education and conservation plan focusing on: Programs – involving students/staff Reporting: Effective and Timely Environmental standards and energy code requirements Conservation Efforts: Protect Natural Resources Mitigate against rate increases Bond Projects - coordination: Equipment efficiencies Rebates – Energy and water efficiency programs Partnership Development: Xcel Energy Denver Water Link to Denver Plan: added emphasis on alignment with Strategic Management of Financial Resources -4- Sustainability – 2012 Bond Program Involvement Energy. A major focus of the bond program is reducing energy consumption and increasing operational efficiencies. DPS Bond Program. The Sustainability Team and project efficiency goals have been an integral part of efficiency upgrades in new construction and renovations. Energy and Water Rebate + Grant Program. The DPS Sustainability program has received over $3M in rebates and grants from Xcel Energy, Denver Water and various providers. Denver Water High efficiency fixture replacement Program. Denver Water rebates offset cost of low flow fixtures installed in 45 schools. Water savings have exceeded 40% at each school with expected overall end of project savings to exceed 55 million gallons per year with reduced costs of over $200,000/year. -5- Sustainability – 2012 Bond Programs – Building Efficiency Options Sustainability and energy infrastructure upgrades (new boilers, HVAC controls, high efficiency lighting and motors, low-flow water fixtures) have been responsible for overall building efficiency improvements. These upgrades along with district-wide energy conservation and education programs, competitions among school based green teams, and building optimization initiatives have resulted in higher efficiencies, reduced consumptions and cost avoidance in the midst of increased student population and square footage. Xcel Energy (New) Energy Design Assistance (EDA): Xcel Energy (Remodel) Energy Efficient Buildings (EEB): EPA’s Energy Star™ Design DPS Sustainable Building Practice Options Colorado Collaborative for High Performance Schools (CO-CHPS): USGBC Leadership in Energy and Environmental Design (LEED): Denver Water : Rebate and Efficiency Programs -6- Highlight Program: Xcel Energy – Energy Design Assistance (EDA) Xcel Energy supports energy engineering consultant assistance to design process of new and remodel construction. Xcel pays up front consultant, engineering fees and follow up incentives after construction. Comparative analytical models used in high efficiency design of new construction projects (EDA) Program focus: Emily Griffith Shops Project -7- Emily Griffith Shops Project – EDA Example -8- Emily Griffith Shops Project – EDA Example -9- Emily Griffith Shops Project – EDA Example - 10 - Sustainability Projects – Rebate & Grant Funded 2012 Bond Term – Rebates received $944,573. Grants received $439,776. • These rebates and grants are used to fund additional energy and water efficiency projects, enhance existing projects and fund student garden and green team education programs. • Palmer gym before (old lighting – 15 foot candles) • Palmer gym after (new LED lighting – 55 foot candles) • 4,560 watts electric consumption • 1,340 watts electric consumption - 11 - District Change – Percent 2009 - 2015 Percent Increase from 2009 to 2015 in Utility Rates, Student Population and Square Footage 30% 25% 25% 24% 20% 17% 15% 11% 10% 5% 0% 2009 2010 Student Enrollment 2011 2012 Square Footage 2013 Denver Water 2014 2015 Xcel Energy Electric Graph shows utility rates escalation in comparison to district growth. Utility rates significantly outpace district growth rates. - 12 - District Utility Cost History: 2009 through 2015 Total Annual Utility Costs (spent) in $ $20,000,000 $15,000,000 $10,000,000 $5,000,000 $0 2009 2010 2011 2012 2013 2014 2015 (Projected) Amount Utility costs remained fairly flat until 2014, due in part to energy infrastructure improvements in bond program plus energy education and conservation programs. Recent additions in square footage, student population and spike in natural gas rates sent 2014 costs much higher. Recent drop (2015) due to energy efficiency improvements and very low natural gas rates. Percent Increase in Utility Costs Since 2009 20% 11% 10% 0% -10% 2009 2010 2011 2012 2013 2014 2015 (Projected) This chart is very positive considering rate increases of 24% for electric and 25% for water, along with a 17% increase in student population growth and 11% increase in square footage. Essentially, this chart demonstrates a reduction in the per pupil cost of utilities. - 13 - Sustainability – Initiatives Solid Waste LargeScale Composting 20 schools across the district; provide schools with the opportunity to further reduce their impacts on landfills and the environment by saving food scraps and paper goods School Waste Reduction Programs Funding partnership with organizations Green Up Our Schools, Denver Recycles, Earth Force Reduce waste by using paperboard, compostable products, reusable trays & utensils Energy Rebates Rebates = $3.1M since 2009 Reinvestment into bond and energy efficiency projects Recycled Water Program Working with Denver Water to use non-potable “recycled water” for irrigation at schools 9 schools have been converted with 73% water rate savings compared to regular water Garden & Greenhouse Program Sustainability Office partners with community groups to connect students to where food grows 100 DPS schools have gardens or urban farms Energy Challenge 10 high school and 10 elementary schools competed to reduce greenhouse gas emissions through efficiency upgrades and student actions in 2011 and 2012 - 14 - Sustainability – Initiatives Green Jobs Workforce Training Program Two cohorts of paid special education interns perform basic energy audits in elementary schools Garden of Youth Program, life and work skills training program for special education students 2011 Passport to Green Jobs, green jobs career fair for high school students Curriculum Development Collaborate with district science staff to develop HS online Sustainability Overview elective course Denver Water collaborating to develop Water Utilities Training program for students Sustainability Forums Hosted four district-wide education conferences: Energy, Waste, Composting, Gardening Focused on sharing conservatory information with interested students, parents, community Solar Photo Voltaic Program Solar arrays installed at 29 schools for a total of 4.5 megawatts of clean, renewable energy Provides 5% of total electric consumption for DPS, 20 year savings of over $1.5 million Natural Gas Purchasing Since 2009, savings of over $3.3 million through transport natural gas purchasing Upgrade Projects • Example: Montbello HS gym lighting upgrade - 15 - DPS Garden and Greenhouse Program • Over 100 gardens on school grounds and increasing • DPS School Garden Coalition – resource garden programming in partnership with 6 community organizations • DPS Garden Curriculum – district approved Math and Literacy curriculum for grades 3 to 5 around Gardening • District-wide protocol and standards for gardens, chickens, greenhouses - 16 - DPS Green Jobs Workforce Training Program • Collaboration with Special Education to provide green jobs for 18 special needs youth per year • Integrate gardening and energy efficiency lessons in to Special Education classes in 5 high schools • Garden of Youth – summer youth employment at 5 high school garden sites • DPS Energy Team and DPS Green Team – school-year youth employment in energy auditing and xeriscaping - 17 - MWBE Program Status • Policy ACE (Equitable and Inclusive Contracting Policy) adopted by Board on November 20th • Disparity Study and Aspirational Goals were reported to the Board on February 19th and accepted • DPS Goals Committee has convened 7 times over the past 4 months • Currently 45 projects have MWBE project goals (see next slides for details ) – 34 Construction goals, 11 A&E goals • Bid documentation has been updated to include MWBE commitment, Letter of Intent process • Compliance Coordinator and Compliance Analyst hired (2 new FTEs to support program efforts) • Implementation of compliance management system (B2G) to track MWBE project goal and payment data underway, April 13th Go-Live • Evaluation of SBE Sheltered Market qualifier Equitable & Inclusive Contracting Policy Update – April 2015 18 MWBE Project Goals - Construction Project # PP2257 PP2385 PP2274 PP2381 PP2393 PP2267 PP2384 PP2132 PP2269 PP2273 PP2378 PP2265 PP2362 PP2377 PP2379 PP2382 PP2259 Project Name Lowry Elementary East HS Randolph & Manual North HS Ellis, Hamilton, Roberts, Whittier and Howell DSA and Phillips JFK Park Hill Smith GWHS Pool Renovations Pioneer Charter Place Bridge Multi Site - Ash Grove Hill MS FD Columbine FD Philips FD Ash Grove FD Ellis Centennial Reroof (Under Warranty) Engineers Estimate $4,045,600.00 $2,397,637.15 $1,397,955.97 $1,633,821.00 $295,131.00 $420,750.00 $2,990,882.00 $701,377.00 $320,000.00 $590,000.00 $1,190,000.00 $647,601.00 $1,500,000.00 $346,019.00 $195,838.00 $231,898.00 $357,692.00 $98,000.00 Project Goal 25% 20% 20% 30% 25% 33% 20% 30% 10% 30% 35% 30% 30% 0% 0% 0% 0% 0% MWBE Commitment 50% 62% 20% 30% 25% 33% 20% 30% 5% 30% 52% TBD TBD * * * * * * - 0% Goal based on Specialized Scope of Work Equitable & Inclusive Contracting Policy Update – April 2015 19 MWBE Project Goals – Construction cont. Project # PP2353 PP2438 PP2260 PP2268 PP2262 PP2380 PP2448 PP2194 PP2272 PP2446 PP2365 PP2361 tbd PP2520 PP2383 PP2460 Project Name JFK - Tech Lab GALS @ Del Pueblo Centennial Eagleton Schenck Cory - Merrill Place Bridge Academy Modular West HS - Wood Flooring Grant MS Reno West HS - Digital Pathways Barrett/PREP/Oakland Columbine/Garden Place/ Harrington Recycled Water Conversions (6 Schools) Bryant Webster - Boiler Replacement Steele - Hallet Reno Skinner - Beach Court Cooling Engineers Estimate $170,000.00 $2,744,252.00 $1,969,236.00 $940,738.00 $220,000.00 $826,803.00 $60,000.00 $282,500.00 $545,095.00 $281,240.00 $389,623.00 $853,355.00 $200,000.00 $572,226.00 $943,263.00 $326,850.00 Project Goal 25% 25% 15% 15% 30% 15% 20% 10% 0% 10% 20% 18% 10% 0% 15% 15% MWBE Commitment 25% TBD TBD TBD 30% TBD TBD 10% * TBD TBD TBD TBD TBD TBD TBD * - 0% Goal based on Specialized Scope of Work Equitable & Inclusive Contracting Policy Update – April 2015 20 MWBE Project Goals – A&E Project # PP2503 PP2504 PP2505 PP2506 PP2507 PP2508 PP2509 PP2510 PP2511 PP2512 PP2513 Project Name A.1 - Manual A.2 - Skinner A.4 - Hilltop and Yuma A.5 - Randolf A.6 - Fairmont A.9 - 5 Schools (Force, College View, Denison Doull and Gust) A.10 - Beach Court and CEC Middle College B.1 - Rishel and Valverde B.3 - 4 Schools (Roberts, Westerly, Howell and Ashley) B.4 - University Park B.5 - Ashbury and Rosedale Engineers Estimate $1,431,667.00 $1,780,530.00 $1,265,419.00 $1,091,602.00 $900,999.00 $1,164,624.00 $1,843,196.00 $802,377.00 $806,158.00 $816,851.00 $887,346.00 Equitable & Inclusive Contracting Policy Update – April 2015 Project Goal 35% 20% 30% 35% 20% 35% 24% 20% 35% 24% 35% MWBE Commitment TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD 21 DPS Program Elements underway DPS Response • In the first months of full implementation of the DPS MWBE program – a crossdepartmental team is assigned to addressing various elements of the new program’s design and execution. • New processes, procedures and visibility of more detailed data will lead to significant increases in the utilization of women and minority-owned businesses for construction and construction-related professional services within the district. • To create a program that is sustainable over time and focused on MWBEs… • MWBE Project Goals • Create a sheltered market for certain projects – in planning (not final) – Project of $750,000 or less – Must be a certified SBE firm with earnings of a percentage of the SBA Federal requirement ($36.5 million annual receipts) to encourage meaningful work opportunities for underutilized small businesses (Example – architectural firm at 15% of SBE, GC at 30% of SBE qualifier) – Must provide proof of gross receipts at time of bid/proposal • Establish Teaming Agreement for at least one project on annual basis – At least one project a year over $1 million that must include teaming agreement Equitable & Inclusive Contracting Policy Update – April 2015 22 Next Steps • • • • Track 2015 project goal process for all prime contractors Establish the requirements for SBE Sheltered Market Train vendors on B2G software and compliance process Lessons Learned with Construction Services at end of construction season to determine improvements to program • Establish communication plan to ensure stakeholders are kept abreast of diversity program status • Annual Review of Business Diversity program – Measure progress towards Aspirational Goals – Make necessary changes to procedures, processes, documentation Equitable & Inclusive Contracting Policy Update – April 2015 23 Appendix - Goals Committee • Goals Committee Members – Nine (9) member goals committee of external stakeholders in construction or architectural/engineering services • • • • • 3 MBE: Michael Roybal, Raymond Garcia, Jeffrey Knight 3 WBE: Rebecca Arisitizabal-Sandstrom, Janelle Martinez, Heather Noyes 3 Majority: Gary Constant, Tom Stone, Julie Witecki Staggered 2-year and 3-year terms Goal Setting Process – – – – – – Goals Committee receives project scope breakdown and data showing market availability PM reviews project scope breakdown and any special requirements during Goals Committee meeting Goals Committee member motions for project goal, majority vote to recommend goal Recommended project goals and disclosure of Committee member interest in projects are documented Committee Chair (Trena Deane) records and approves recommended goal The Project Manager has opportunity to request/justify amendment of goal to Chair Meet 2x month to review upcoming projects Provide goals recommendations for upcoming projects Equitable & Inclusive Contracting Policy Update – April 2015 Committee Chair approves goals 24 East Quad High School Campus Phase I (PP-2234) Construct Phase I - 500 Student High School Plan Phase II Expansion to 1,000 Students Project Budget $24.1M Construction On-site Start: 10-3-2014 Construction Completion = 25% Planned Substantial Completion Date: 12-15-2015 Building will house KIPP FNE High School and STRIVE FNE High School - 25 - Near the corner of 51st and Tower, NE of Evie Dennis Campus in Green Valley Ranch Paul Sandoval Campus – Phase I* (PP-2037) 5450 N Central Park Blvd Construct Phase I – 900-1,000 Student High School Plan Phased Expansion up to 2,400 Students Project Budget $39.8M Construction On-site Start: 4-1-2014 Construction Completion = 80% Estimated Completion Date: 8-1-2015 Northfield High School to open in August 2015 Note: Does not include additional funds applied to this project from the 2012 premium reserve in January 2015 - 26 - Loretto Heights Campus - CHU Phase II (PP-2035) Construct Phase I – Middle School 450 Students (08GOB) Phase II - High School 500 Students Project Budget $13.4M Construction On-site Start: 6-24-2013 Construction Completion = 100% Actual Substantial Completion Date: 12-4-2014 DSST College View Middle School currently open (high school to open Fall 2015) - 27 - 3111 W Dartmouth Ave Hampden Heights - Joe Shoemaker School (PP-2036) Construct Elementary for 550 Students Project Budget $21.0M Construction On-site Start: 1-15-2014 Construction Completion = 65% Estimated Completion Date: 6-26-2015 Joe Shoemaker Elementary to open in Fall 2015 - 28 - 3333 S Havana St Florence Crittenton HS Renovation (PP-2187) Construct New High School & ECE Center 250 HS Students and 100+ ECE Students Renovate portions of Existing Building Construct Parking Lot & ECE Playground Project Budget $7.9M Construction On-site Start: 10-1-2014 Construction = 55% Planned Substantial Completion Date: 8-14-2015 - 29 - 55 S. Zuni & 96 S. Zuni St Valdez Renovation & Addition (PP-2159) Open Planned School Renovation Cafeteria Addition Project Budget $5.7M Construction On-site Start: 7-7-2014 Construction = 80% Estimated Completion Date: 7-15-2015 Valdez Elementary to relocate back from Smedley building in summer 2015. - 30 - 2525 W 29th Ave Renovation 2626 W Evans Phase I & II (PP-2322 & 2430) Construct Phase I – 1st Floor & ½ Basement Phase II – 2nd & 3rd Floors & expand to full Basement Project Budget $16.2M (includes $2.3M for building purchase) Construction On-site Start: 12-15-2014 Construction = 45% Estimated Completion Date: 8-3-2015 STRIVE Ruby Hill elementary currently open. STRIVE Federal middle school to relocate summer 2015. - 31 - 2626 W. Evans BOC Next Steps Next Steps • Joint meeting with Mill Levy Oversight Committee on Wednesday May 6th at 4pm in Emily Griffith Campus room 1035 - 32 -
© Copyright 2024