2015 Annual Meeting Presentation

March 5, 2015
AGENDA










Introductions
2014 Diversion Report
2014/2015 Maintenance Activities and Flood Repairs
Budget Update
CIP Update
FEMA Update
Staffing and Authority Reorganization
2015 Run Season Plan
Delivery Process
Reminders
2014 Church Ditch Diversions at
Clear Creek
 Total Water Diverted
 Delivery per Inch
 Cost to User per Inch
 Average Delivery 2005- 2014
7,461.40 AF
0.98 AF/Inch
$91.84 per AF
1.10 AF per Inch
2014 Maintenance Activities
 Replaced Headgate 11
 At Headgate 60
 Installed riprap check structure
 Reworked headgate to take sufficient water for all
incholders.
 Placed bentonite in ditch banks in flood damaged
areas.
 Placed bentonite in ditch banks in the headworks area.
 Installed concrete check pads at Headgates 80 and 84.
2015 Completed Maintenance
 Removed fallen trees in Westwoods Golf Course
 Made flow improvements at Farmer John’s property
and from Denver Kickers Club to 4380 Easley Way.
 Also removed a down tree and boulders that were
restricting flow.
 Placed bentonite in banks at Quaker and 64th Ave.
 Removing fallen tree from easement at 4390 Easley Rd.
 Repaired trash rack at the Narrows.
Planned 2015 Maintenance
 Clear cutting vegetation
 74th Ave. East of Kipling
 North of Legacy Farms
 Westwoods Golf Course
2015 Planned Maintenance
 Ditch Reshaping
 West of Ralston Valley
High School
 West of 76th Drive
 North of Headgate 60
 North of Legacy Farms
2015 Planned Maintenance
 Headgate Replacements:
 Gate 40 – complete
replacement, gate is not
attached.
 Gates 56 and 57
 Will start working on
replacing ALL slide type
gates along the ditch.
Headgate 57
Budget Update
Revenue
2014 EOY Forecast
2015 Adopted Budget
WCRA Reimbursements
$26,500
$12,000
CDWA Reimbursements
$45,500
$5,000
Assessments
$516,064
$770,936
Transfer Fees
$490
$100
Crossing Fees
$1,500
$1,000
$175
$175
$60,000
$76,175
CDWA Loan Reimbursements
$600,000
$0
FEMA Reimbursements
$250,000
$0
Miscellaneous Revenue
$167
$6,000
$1,499,896
$871,386
Interest Earned
Bypass Reimbursements
Total Revenue
Operating Expenditures
2014 EOY Forecast
2015 Adopted Budget
Legal Services
$9,000
$10,000
Engineering Services
$15,000
$25,000
$1,500
$2,000
Contracted Services
$150,000
$150,000
Ditch Maintenance
$240,957
$218,500
$9,000
$9,000
Operating Supplies
$25,000
$35,000
Energy/Utilities/Fuels
$30,000
$30,720
$0
$43,000
$15,000
$4,000
$495,457
$560,000
General Services
Vehicle Repair
Capital Equipment
WCA Operating Supplies
Total Operating Expenditures
Capital Improvement Projects
2014 EOY Forecast
2015 Adopted Budget
Headworks
$158,465
$320,000
Flood Damage Repairs
$527,558
$200,000
$10,000
$40,000
$250,000
$0
$0
$25,000
$946,023
$560,000
Master Plan Update
FEMA Payments
Headgate/Flume Replacement
Total CIP Expenditures
FEMA Update
 Continue to receive reimbursements from FEMA for work
done to repair structures.
 FEMA approved a mitigation project for the Leyden Creek
Crossing.
 Work at Leyden Creek will begin this month.
 Install box culvert in the ditch.
 Armor bank to protect culvert from future high flows.
 Reseed disturbed area.
 There are some issues getting funding for the block wall
installed near Headgate #53.
 FEMA process will continue until all projects including the
mitigation at Leyden Creek are completed.
Authority Staffing and
Reorganization
 Retirement/resignation of two staff.
 Jim Manley
 Eve Craven
 Northglenn and Westminster would like the Authority to
be more autonomous.
 Staff will no longer be Northglenn employees.
 Hiring 2 full-time and 1 part-time employees.
 General Manager
 Ditch Superintendent
 Secretary.
 Staff will run the ditch separate from the Cities.
 City staff will continue to sit on the Authority board.
2015 Run Season Operations
 Authority is very short staffed.
 New staff is not anticipated to be hired and working
until July 2015.
 City of Northglenn will provide a few staff to help
when needed.
 Authority will contract with Farmers Highline Canal
and Reservoir company to help with 2015 run season.
Delivery Process
 Unique conditions in 2014 pointed out ineffiencies in
delivering water to inch-holders.
 Too much water going down Dry Creek Valley Ditch means
more water is available to inch-holders.
 Developed a new delivery spreadsheet to help determine
pro-rata share for each inch-holder based on:
 Diversion from Clear Creek.
 Number of inches calling for water.
 Inch-holders who have not called for water, will not have
their gate unlocked.
 Water will be distributed to all calling inch-holders based
on the pro-rata share available.
 Laterals/headgates that do not have adequate measuring
devices will need to be replaced.
Reminders
 Assessments are due by April 1, 2015.
 Please call or e-mail to request your water. We will not
open your gate without a formal request.
 Please make sure that your flume and laterals are
cleaned prior to April 1, 2015 in preparation of water
deliveries.
 We cannot deliver water to a headgate that cannot
measure it’s deliveries. Please maintain these structures.
 The website will be updated frequently with updates
on projects and with important information.
www.churchditch.org
QUESTIONS?
THANK YOU