CE 332 CONSTRUCTION ENGINEERING AND MANAGEMENT PLANNING EXPLANATION ON FAQ (1) AoA and AoN Network Solutions Early Start Time of the activity Late Finish Time of the activity EETj | LETj (C) (D) EETi | LETi (A) (B) Activity Duration (d) Predecessor Corresponds to Late Finish Time of its predecessor Successor Corresponds to Early Start Time of its successor From an AoA network solution you can read only the Early Start and Late Finish times of activities directly. For Early Finish and Late Start times you should make calculations by adding or subtracting the durations of the activities. Early Start Time = A Early Finish Time = A + duration Late Finish Time = D Late Start Time = D – duration From an AoN network solution you can read all Early Start, Early Finish, Late Start, and Late Finish times directly from the node of the activity. ES Duration EF Activity Name TF LS LF (2) Float Calculations and Critical Path Affects Late Finish Time of its predecessor Affects Early Start Time of its successor EETj | LETj (C) (D) EETi | LETi (A) (B) Predecessor Activity Duration (d) A Predecessor B Successor dur Activity C Successor D Total Float: Does not constrain durations at the activities level. So the activity may take from its predecessor's or its successor's time (when predecessor can not finish late and successor can not start early). TF = Late Finish Time of Activity – Early Start Time of Activity – Activity Duration TF = D – A – duration Free Float: Should not affect early start time of its successor. So the activity may take from its predecessor's time (when predecessor can not finish late and successor can start early). FF = Early Start Time of Successor – Early Start Time of Activity – Activity Duration FF = C – A – duration Independent Float: Should not affect any other activity. So the activity can not take any duration from its successor's or predecessor's time (when predecesssor can finish late and successor can start early). IF = Early Start Time of Successor – Late Finish Time of Predecessor – Activity Duration IF = C – B – duration Critical Path: Zero float activities indicate critical path candidates but the only paths that are equal to total project duration are critical paths. PLANNING EXAMPLES Example 1. For the given AoA network draw the AoN network. C E H F G A I G D B Solution: Extract activities and their predecessors from the given network. Activities A B C D E F G H I Predecessors A A,B B,C D,E D F G,H Redraw the network according to the predecessors. A C E F START H I B D G END Example 2. For the given AoN network draw the AoA network. A F B H START J C E D G END I Solution: Extract activities and their predecessors from the given network. Activities A B C D E F G H I J Predecessors A A,C D B,E E F,G G F,I Redraw the network according to the predecessors. B F J A H I C D E G Example 3. According to the given activities and predecessors draw the AoA network. Activities A B C D E F G H I J K Predecessors A,B B,C D,C D E,F G G H,I,J Solution: D G I J A B K E C H F Example 4. How many things are wrong the network diagram shown below? F G C H A T B B D R E Solution: 1 Activity D has no arrow head 2 Event # 5 is duplicated 3 The dummy between Event #2 and Event # 5 is unnecessary 4 Activity ID B is duplicated 5 Activity G has no ending event 6 Activity H has two arrow heads 7 Activities T, R, B form a loop Example 5. Write True (T) or False (F) for the following statements; -------- Network is a diagram to represent the relationship of activities to complete the project. The network may be drawn as either an “arrow diagram” or a “precedence diagram”. -------- Activity on Node diagrams require the use of dummy activities. -------- Total Float is the amount of time an activity may be delayed without delaying the early start time of the immediately following activity. -------- In CPM calculations, Backward Pass calculations cannot be performed without ending the Forward Pass Calculations. Answer: T Network is a diagram to represent the relationship of activities to complete the project. The network may be drawn as either an “arrow diagram” or a “precedence diagram”. F Activity on Node diagrams require the use of dummy activities. F Total Float is the amount of time an activity may be delayed without delaying the early start time of the immediately following activity. T In CPM calculations, Backward Pass calculations cannot be performed without ending the Forward Pass Calculations. Example 6. What is the difference between identity dummy and logic dummy? Answer: Identity dummy is used in order to identify activities when two or more parallel independent activities have the same start and finish events. On the other hand, logic dummy is used in order to prevent the error in logic arising from chains of wholly or partly independent activities having a common event. Example 7. By using the Legend given in the Table 1 and information given in the Table 2, solve the given problem below. Table 1: Legend for the Critical Path Calculations (CPM) Early Start Total Float Early Finish Activity Name Late Start Duration Late Finish Table 2: Information about the schedule Activity Name B E X Z T A C Y D K Duration (days) 10 15 20 25 10 15 15 20 30 35 Dependence B B B E, X X, Z E, X, Z A, K T, C B a) Construct the precedence diagram (Note: All type of dependencies are finish to start). b) By using Activity on Node (AoN) methods, compute the total project duration. c) Identify the critical path. d) Find the free and independent floats of the activities C, E and K. Solution: a) b) c) 10 10 25 E 20 15 35 30 10 40 T 40 10 50 10 5 30 X 15 20 35 35 0 50 C 35 15 50 10 0 35 Z 10 25 35 35 10 50 A 45 15 60 50 0 80 D 50 30 80 80 0 80 FINISH 80 0 80 0 0 10 B 0 10 10 50 0 70 Y 60 20 80 10 15 45 K 25 35 60 Duration: 80 days Critical Path: B-Z-C-D d) Free Float C = 50-35-15 = 0 days Independent Float C = 50-35-15 = 0 days Free Float E = 30-10-15 = 5 days Independent Float E = 30-10-15 = 5 days Free Float K = 50-10-35 = 5 days Independent Float K = 50-10-35 = 5 days Example 8. Draw the AoN network of the given activities and make necessary calculations. Activities A B C D E F G H I J K L M N O P Duration (days) 6 3 4 9 12 8 3 3 4 4 3 1 6 7 4 3 Predecessors A A A B,D C,D C,D E E E G,H H N,I,J K,L Solution: 0 8 8 F 21 21 29 ES Duration EF Activity LS TF LF 0 0 0 START 0 0 0 6 3 9 B 17 11 20 15 3 18 G 20 5 23 18 6 24 M 23 5 29 6 9 15 D 6 0 15 15 3 18 H 15 0 18 18 7 25 N 18 0 25 6 4 10 C 11 5 15 15 4 19 I 21 6 25 0 6 6 A 0 0 6 12 4 16 J 21 9 25 0 12 12 E 9 9 21 12 3 15 K 23 11 26 12 1 13 L 25 13 26 Duration: 29 days Critical Path: A-D-H-N-O 15 3 18 P 26 11 29 25 4 29 O 25 0 29 29 0 29 FINISH 29 0 29
© Copyright 2024