CONSTRUCTION PROJECT TIMELINES
Revised March 16, 2015
Boilers – Edison, Jennings, Stoy, Strawbridge, Van Sciver and HTHS
Replace boilers with modular units, controls, piping, new pump systems etc.
Friday
02/20/15
Bid packages available for Pick-up
Tuesday
02/24/15
Pre-bid meeting at 3:00 P.M. at the Haddon
Township School District, Administration Building, 500 Rhoads Avenue, Westmont,
New Jersey 08108. Attendance at the Pre-Bid meeting is not mandatory, but
strongly recommended.
Wednesday
03/04/15
Deadline for Questions at 5:00 P.M. (Fax to
Garrison Architects 856-396-6205)
Thursday
03/05/15
Addendum Faxed to Bidders, if necessary
Tuesday
03/17/15
Bids Due at 3:00 P.M. at Haddon Township
School Administration Building Westmont, New Jersey 08108
Wednesday
09/30/15
Project Completion
Phase One- Edison, Jennings, Stoy, Strawbridge, HTHS
Roofing, elevators, building systems at all five schools, re-configure new corridors
and replace VAT with VCT on stair landings at Jennings, MPR additions and student
drop off areas at Stoy and Strawbridge, Replace existing Greenhouse at HS.
Thursday
04/02/15
Bid packages available for Pick-up
Tuesday
04/07/15
Pre-bid meeting at 3:00 P.M. at the Haddon
Township School District, Administration Building, 500 Rhoads Avenue, Westmont,
New Jersey 08108. Attendance at the Pre-Bid meeting is not mandatory, but
strongly recommended.
Wednesday
04/15/15
Deadline for Questions at 5:00 P.M. (Fax to
Garrison Architects 856-396-6205)
Friday
04/17/15
Addendum Faxed to Bidders, if necessary
Wednesday
04/29/15
Bids Due at 3:00 P.M. at Haddon Township
School District, Administration Building, 500 Rhoads Avenue, Westmont, New Jersey
08108.
Friday
08/12/16
Project Completion
Phase One A - Van Sciver School
Roof, electrical construction and service, new MPR and classrooms, corridor link,
kitchen, toilets and storage, new student drop off loop
Thursday
03/12/15
Bid packages available for Pick-up
Friday
03/20/15
Pre-bid meeting at 3:00 P.M. at the Haddon
Township School District, Administration Building, 500 Rhoads Avenue, Westmont,
New Jersey 08108. Attendance at the Pre-Bid meeting is not mandatory, but
strongly recommended.
Wednesday
03/25/15
Deadline for Questions at 5:00 P.M. (Fax to
Garrison Architects 856-396-6205)
Friday
03/27/15
Addendum Faxed to Bidders, if necessary
Tuesday
04/14/15
Bids Due at 3:00 P.M. at Haddon Township
School District, Administration Building, 500 Rhoads Avenue, Westmont, New Jersey
08108.
Friday
08/12/16
Project Completion
CONSTRUCTION PROJECT TIMELINES
Revised March 16, 2015
Phase Two- Interior and Exterior Renovations Edison, Jennings, Stoy,
Strawbridge, Van Sciver, HTHS– playground surfaces, fencing, interior and
exterior doors, lintels, brick pointing & stucco at VS, concrete curbing, fire rated
stair tower doors, lavatories, HVAC, perimeter radiation and ductless splits (air
conditioning), security cameras, GPS clocks, water heaters, replace carpet and VAT
with VCT, fire alarm systems, PA systems, replace ceiling tiles, replace water coolers,
office space reconfiguration at Van Sciver and Strawbridge, HS auditorium- re-build
back control booth for lights, aisle lights, stage refinishing and lighting system,
reconfigure metal shop space into new classrooms, re-configure bottom floor
Science room, reconfigure and renovate kitchen and replace equipment, some
renovation to cafeteria.
Bid Schedule TBD – fall 2015