1. What is EMAS? 2. How do you do environmental impact

MB16
THIRD SEMESTER MBA SUPPLY CHAIN MANAGEMENT
EXAMINATION MARCH - 2015
Project Management
TIME: 3HOURS
MAX MARKS: 80
Section A
Answer the following questions .
2X5 =10
1. What is EMAS?
2. How do you do environmental impact assessment?
3. Briefly explain Variance analysis?
4. What is DSS?
5. List the advantages of CAM?
Section B
Answer any six questions:
6X6= 36
1) What is Network crashing? When it is used?
2) Discuss the processes and techniques used in quality planning, quality
assurance and quality control in projects?
3) What do you understand by the term project as a conversion process? Why is it
called so?
4) What according to you are the requirements of a successful project manager?
5) Describe the advantages of planning by network analysis?
6) Explain how managing creativity and risk taking go hand in hand?
7) Discuss the important provisions of the project import regulations 1986?
Section C
Answer any two questions in this section
10X2= 20
1. What are the pitfalls in the traditional method of cost accounting and expenditure
control in projects?
2. Discuss the processes and techniques used in quality planning, quality assurance
and quality control in projects?
3. What are the different types of project organisations? Discuss briefly each with
its merits?
4. a. What is PERT? What for it is used?
b. Draw a pert diagram using the following details and calculate the expected
time and the variance:
Activity
A
B
C
D
E
F
G
Optimistic
time
2
3
3
3
7
3
7
Most likely Pessimistic time
4
4
5
4
9
5
10
7
7
8
8
14
8
15
Section D
Answer one question in this section.
1X 14 = 14
1. ‘S’ curves alone can help the management in monitoring the progress of the
projects by depicting the under or over spending and delays etc., “ discuss
2. The normal and crash point for each activity for a project are given in a table below:
Activity
Normal
Crash
i, j
Duration
Cost
Duration
Cost
A (1,2)
8
100
6
200
B(1,3)
4
150
2
350
C(2,4)
2
50
1
90
D(2,5)
10
100
5
400
E(3,4)
5
100
1
200
F(4,5)
3
80
1
100
Duration in days and cost in rupees. Indirect cost being . 100 per
day.
i)
Draw the network diagram for the above project?
ii)
Determine the normal project duration and the total normal cost of the
project?
iii)
Find the minimum cost and corresponding project duration ?
iv)
Find the minimum project duration and corresponding cost?
**************************?