DB/DBO in emerging economies and LDCs: A practical answer to

DB / DBO Workshop
March 31st 2015 – Paris
SEFI
DB/DBO in emerging economies and LDCs:
A practical answer to address the infrastructure challenge with
improved governance
Marc Frilet
Managing Partner « Frilet – Société d’Avocats »
Chair of the Management Committee of GcilA
Vice-President of the French Institute of International Legal Experts (IFEJI)
Vice-chair of CICA PPP-Working Group
Board member of ETIC-PPP
Fellow American College of Construction Lawyers
© 2015 - Frilet Société d'Avocats
03/31/2015
1
Public infrastructure needs and issues
• The UN post 2015 objectives: The need of massive investment in public infrastructure projects
 Hundred of Billion US Dollars per year
 For Africa alone 90 billion per year
• Two main issues:
1. Financing gap
 Public budget and development aid will not be able to finance the need: example: African gap =
40 billions USD
2. Implementation gap
Many projects are:
 Not implemented
 Poorly implemented
 Most projects are not implemented on time and budget are the majority (no statistics!)
 In Africa alone Public budget and development aid savings for well prepared and well
implemented projects may be evaluated to several billion USD per year
How to bridge those gaps ?
 Through private investment in public infrastructure projects (Concessions and other PPPs)
 Through better use of public and development money for infrastructure projects
© 2015 - Frilet Société d'Avocats
03/31/2015
2
How to optimize project delivery and value for money for
project directly funded by State budget and IFI’s ?
•
For repetitive or basic infrastructure, example: roads




Developing capacity building actions
Allocating much more resources to project preparation
Optimizing the use of consultants and engineers
Improving procurement process and optimize the use of standard conditions adapted
to sector, culture and legal tradition
 If those conditions are met, Design Bid Build (DBB) should remain the preferred delivery
option (i.e. traditional remeasurement contract and bill of quantity (BQ))
• For complex projects, examples: public utilities, ports, railways, bridges, stadiums,
hospitals, etc.
 Several design and related technical options and process possible
 Public Authority interested by outcome: service delivery is of the essence
 Defining in advance all technical specifications, process and O&M conditions is costly
and limit optimization of the infrastructure design and operation by the bidders
 DB and DBO may deliver best value for money (BVFM)
© 2015 - Frilet Société d'Avocats
03/31/2015
3
Private participation in public infrastructure projects:
DB and DBO position
MINIMUM PRIVATE RISKS
AND BENEFITS
MAXIMUM PRIVATE RISKS
AND BENEFITS
PPI
Contracting
(Short term contract)
PUBLIC ASSETS
FOR PUBLIC
ACCOUNTING
PURPOSES

Public financing
Immediate
payment (full
direct impact on
current tax
budget)
PPP
(Long term venture)
Privatisation
Simple
Contracting
Design
Build
Turnkey

Dividing line
between Public
and Private
assets
PRIVATE
ASSETS FOR
PUBLIC
ACCOUNTING
PURPOSES

Private financing
then direct
payment by
Public Authority
based on output
or quality of
service (full direct
impact on future
tax budget)
PFI PPPs
Leases, BOT,
French
Partnership
Contracts
Private financing
then no or limited
payment by
Public Authority:
main cost
recovery from the
users of the
service (no or
limited impact on
current or future
tax budget)
CONCESSION and assimilated
PPPs
(ROT, affermage)
Traditional Procurement
(competitive award based mostly on
physical specifications and price of the
physical infrastructure)
DB
© 2015 - Frilet Société d'Avocats
DBO
Special Procurement (competitive award
based mostly on functional specifications,
capacity to adapt to changes and quality
and price of service in the long term)
03/31/2015
4
Respective role of public and private sector in DB/DBO
• Public sector role:
 Planning, prioritization
 Functional specification: Focus on outcome
 Conceptual design (more or less APS in the French system)
 Performance parameters during operation: O&M output and costs
• Private sector role:
1. DB
 Developing technical and industrial feasibility in an integrated manner for construction and operation
 Private sector selected on the basis of a tender design (more or less APS in the French system)
 Once selected, contractor obligation to develop detailed design (APD in France)
 Thereafter: situation similar to remeasurement contract with major lump sum element
 Contractor develops shop drawings (more or less plans EXE in France)
 Contractor build the infrastructure or plant
 Contractor paid upon completion including successful commissioning
2.
DBO: Same as above and in addition:
 Obligation to operate the infrastructure of facility in compliance with O&M parameters (and/or service
delivery obligations) (PSO)
© 2015 - Frilet Société d'Avocats
03/31/2015
5
What to expect from well prepared DB and DBO ?
1. Optimized input from the private sector
 Optimum combination of private sector skills and technologies such as:
 Design
 Construction engineering
 Optimized process
 Optimized operation of service (minimum O&M costs, guarantee of smooth
service adapted to the needs)
2.
Simplified preparation and implementation process for public sector
 Main public resources spent on planning prioritization and conceptual design:
 Shorter preparation phase limiting bad governance risks
 Less public resources on evaluation and control of design, of construction and
operation
 Conditions for successful DB or DBO projects: need of innovative procurement and
contract conditions including appropriate dispute avoidance and dispute settlement
clauses
© 2015 - Frilet Société d'Avocats
03/31/2015
6
DB / DBO : need of innovative procurement process
1. Need of a published framework which clarify and organize the role of the Public Authority for:






Planification
Definition of needs and options
Prioritization
Drafting of pre-selection documents
Drafting of the tender documents on the basis of functional specifications
Organizing the bidders information and selection process in an ethical and transparent
manner including:
 in most cases: 2 stages tender:
 technical offer
 Financial offer
 For more complex cases:
 Competitive dialogue
2. Need of clear and enforceable guarantees against misprocurement:
Ethical charter
Probity or compliance officer
Efficient judicial review
© 2015 - Frilet Société d'Avocats
03/31/2015
7
DB : need of innovative contract conditions
I.
Concept: “General contractor approach”
Lessons learnt during the last 30 years in developing countries of civil law tradition: example: Algeria
 Algeria has developed landmark Turnkey Projects for heavy plants (TKHP) in the 90’s
A. Many contract conditions deriving from underlying legal and contractual framework and practice:
a) Civil code:
 Concept of entrepreneurship contract (“contrat d’entreprise”)
 Case law on good faith obligation: contractor far reaching duty to advise
 Contract interpretation base on industry usages
 Joint and several liability of engineers, architects and contractors: strict liability for
10 years in case of structural problems in building and works or rendering them
unfit for purpose
 Entitlement to payment and price: successful completion
b) Equitable public contract law (administrative case law):
 Hardship
 Sovereign interference justified by general interest
 Special compensation rights for contractor when sovereign interference
© 2015 - Frilet Société d'Avocats
03/31/2015
8
DB : need of innovative contract conditions (2)
B. Other contract conditions:
1.
Identifying generic issues in local context of developing countries and addressing them in contractual
clauses:
 Decreasing risks for both parties
 Sharing some residual risks
 Allocating others residual risks
2.
Examples:
 Custom regime and related procedures
 Tax regime and related procedures
 Availability of land and related procedures
 Permitting and related procedures
 EISE and related procedures
 Price breakdown and related procedures for any evaluation and claim
 Variation and related procedures
 Disruption of public supply(including power, water) and related procedures
 Force majeure ad related procedures
 Performance guarantee
 Insurance
 Dispute avoidance mechanisms
 Alternative Dispute Resolution mechanisms
 Dispute settlement
© 2015 - Frilet Société d'Avocats
03/31/2015
9
DBO : need of additional innovative contract
conditions
•
2 main situations may roughly be distinguished:


Situation 1: O&M for limited duration (from 1 to 10 years) not involving delivery of the service to end users
Situation 2: O&M for duration for over 5 years involving full delivery of public service to end users
Situation 1:
 Price of construction of infrastructure partly paid at the end of operation period
 Addition of traditional clauses for “facility management contract” with bonuses and penalties
 Addition of clauses for hand over of infrastructure or facility in good operating condition at the end of O&M
period
Situation 2: Same as situation 1 and in addition:
 Several sets of clauses relating to the condition of operation of public service by private sector
 Many of those clauses similar to the series of clauses found in Concession PPP family for public service in
developing countries
Examples:
 Scope of public service
 Delivery of the service:
- Continuity
- Non discrimination
- Adaptation
 Stability of regulatory framework
© 2015 - Frilet Société d'Avocats
03/31/2015
10
Thank You !
Me Marc Frilet
Frilet – Law firm/ GcilA