Document 189594

Minutes of Forest Enterprise Scotland Management Board Business Meeting
held at the Dunkeld Hilton Hotel, Dunkeld on 07 August 2013
Attendees:
Simon Hodge, Chief Executive
Les Bryson, Head of Operations
Michael Hymers, Head of Corporate Support
Alan Duncan, Head of Finance
Moira Baptie, Head of Environment
Jo Ellis, Head of Planning
Alan Stevenson, Head of Communities, Recreation and Tourism
Laurie Tyson, Head of Estates
Michael Ansell, Head of Forest Renewables
Niall Browne, HR Business Partner (Scotland)
Mary Lindsay, Lead Area Land Agent
Hilda Todd (Secretary)
Apologies: None
1.
MINUTES OF LAST MEETING
The minutes of the meeting held on 10 July were accepted as a true and accurate
record.
2.
MATTERS ARISING
AP 2.2: Revised JEG's/Benchmarking Process - Niall has met with Oriana and will
now revert to Recruitment Panel re cleansing of job titles.
AP Discharged
AP 2.3: Jo to firm upon on figures for woodland creation and revisit at the next
board meeting in August.
Figures are prepared but still have to be put in - however, there is a problem with
marrying up District direct planting figures and figures coming from finance, but
discussions between Planning and Alan D will be able to resolve this. AP Discharged
AP 2.8: Jo/Michael H to propose a 3 year rolling target for woodland creation.
AP Discharged
As above
AP 2.9: Les/Michael H to propose adjusting timber production target to a timber
marketing target, which would be less affected by poor customer uplift; and to
consider an alternative to the DP unit cost as an indicator of business
competitiveness. Done
AP Discharged
AP 2.12: Health & Safety - Les to engage with the Safety Committee on safety boots
and use of safety glasses.
1
|
FESMB BoardMinutes |
Hilda M Todd
|
18/09/2013
Emily has commenced review of safety footwear. Safety glasses guidance has been
issued.
AP Discharged
AP 2.14: Organisational/Functional Update (Web Commerce) - Alan D to resume
discussion on web commerce once analysis is available.
AP Rolled Over
Alan passed round a paper, giving a crude breakdown of the scope of work; Estate
permissions, firewood and Niche marketing could benefit from the Internet platform.
FAS are already supporting the development of a web payment platform for wood
sales, which should be looked at to expand its suitability for other web-commerce
areas. Alan D, Laurie, Alan S and a representative from Les’s side will explore.
The new web platform can support a standard payment module with ‘Payphone’ as an
option. The platform launch was held back due to staff moves before the next stage of
the development. England use a web based platform for concert ticket sales.
AP: 2.14 (1): Alan D to establish a working group to examine the business needs
and opportunity. Laurie, Alan D, Alan S and an Ops rep to hold an exploratory
meeting.
Michael asked that a representative from IS be asked to join the group. Any software
development identified by the project group will need to be prioritised and agreed by
FES/FCS before any work is commissioned.
AP: 2.14 (2): Alan D to ensure a representative of IS is asked to join the group.
AP 2.15: Organisational/Functional Update (DNB chemical spraying trial) - Jo to
check with Hugh Clayden re community engagement.
AP Discharged
AP 3.1: Donald to review recent sales and ascribe indicative values to future
scenarios.
AP Discharged
AP 4.1: Jo to discuss with Les and feedback to Simon on future restocking
requirements.
Zoe Laird supplied figures on future restocking levels which were extracted from the
RS layer. The was some inconsistency when compared to the BP inputs from FDs It
was agreed the best short term approach was to see what business plan comes up
with and compare the two sets of data seeking explanations from FDs over any mismatches. In the longer term there is still a need for Jo to work through the strategic
programme issues
AP Rolled Over
AP 4.2: Michael H to look into how ERMS system might help us better manage our
use of legal advice. Michael hasn’t taken this forward yet but will before Jo Clark
leaves the organisation.
AP Discharged
AP 4.3: Michael H, Alan D and Niall to review gate keeping of contacts to solicitors
AP Rolled over
AP 4.4: All Board Members - To consider the ragging of priority posts.
2
|
FESMB BoardMinutes |
Hilda M Todd
|
18/09/2013
AP Discharged
AP 4.5: Les - To consider CECS and MECS country requirements and staffing
implications going forward
AP Discharged
Later in the year with intention to review both activities
AP 5.1: All Board Members - Ensure that staff within their specific teams are
involved in the H&S briefing and that it is done in a way that ensures that staff get
both the wider briefing and a discussion session relevant to their domain of work.
Team leaders should ensure all of the team gets briefed. Les asked all to remind
teams to return feedback forms to Alice Cheyne in Bristol.
AP Discharged
AP 7.1: Doug Knox to provide evidence to the October meeting on our practices
around contingency levels and optimum bias.
AP Discharged
AP 7.2: Doug Knox to collate and present a list of potential new projects to the next
board meeting on 15 August for prioritisation and subsequent project planning.
On agenda.
AP Discharged
AP 7.3: Laurie to confirm and clarify insurance cover at Galloway VCs.
AP Discharged
3.
TELECOMMUNICATIONS ON THE NFE UPDATE
Simon welcomed Mary Lindsay to the meeting.
Mary gave a Power Point presentation titled ‘Telecommunications Portfolio Update’ to
inform the Board of approaches from Orange and Vodafone to assign their leases to
recently formed Joint Venture Companies as well as a new Mobile Network Rollout
called the Mobile Infrastructure Project (MIP), which is partially funded by the
Westminster Government.
Mary and CKD Galbraith are working with the telecommunication companies to
safeguard our interests during this period of telecoms consolidation. The issue of
contract assignation was discussed.
MIP is a Government initiative project which will be rolled out by Arqiva to "not spots",
areas where buildings and homes suffer from lack of mobile connection ability by the
end of 2015. Phase 1: Aberdeenshire, Cumbria and Wales. Phase 2-5 covers the A82.
Due to market conditions the companies are seeking to consolidate their portfolio of
sites and the Board approved the recommendation to proceed with negotiations on
the assignation requests.
The Board also agreed for Mary to negotiate with Arqiva to agree terms for the new
MIP sites. Simon suggested keeping FCS policy in the loop given the public interest
dimensions of telecoms networks. Michael pointed out that resolving connection
issues could mean we get boosted signals to our outstations.
3
|
FESMB BoardMinutes |
Hilda M Todd
|
18/09/2013
AP 3.2: Mary to progress negotiations with the telecoms companies, keeping FCS
policy in the loop as appropriate.
4.
ACQUISITIONS AND DISPOSALS
Laurie did a break down on an exceptions basis.
•
Bid at the closing date for West Cameron was successful.
•
Acquisition of Mull pier is now progressing well and Donald is hoping date of
entry will tie in with the completion of the contract for construction of the
pier and hand over of the site.
•
There is a low level of activity for new repositioning acquisitions at present.
WEAG guidance on farmland planting is expected to be finalised in next
couple of weeks.
•
Leases have been concluded at several woodland creation sites.
Acquisitions involving agricultural land will not be moved to completion until the WEAG
guidance is published.
The disposals programme is on track, but needs constant monitoring. Headlines are:
•
•
•
•
•
•
•
We currently have £9.1m of plantation sales on the market
We have closing dates for North Otter and Ormidale on 14 August and good
interest in the Moray and Aberdeenshire woods.
Rosal is due to be marketed in late August or early September with the
Scottish Lowlands blocks to be offered shortly after.
A number of blocks due for sale in 13/14 now have confirmed interest under
NFLS.
Intention is to begin marketing the main 14/15 subjects in November 2013.
Craighead in Tay has renewables interest.
Market interest in the various ‘resale’ properties is good and closing dates
have been set on four farm houses which if successful will provide an
important part of our £1.5m target for the year.
Simon put a paper up to the FCSMB on 15/16 repositioning identifying options for the
future scale of the programme. The production forecast figures are currently being
worked on and functional leads have been asked by Donald to feedback on the
proposals.
AP 4.1: Michael A to advise on the wind farm potential at Craighead
5.
FINANCE REPORT – FY 13/14
Alan D presented his report to the board.
4
|
FESMB BoardMinutes |
Hilda M Todd
|
18/09/2013
There are a number of significant P3 variances, complicated by the uncertainty over
Scottish Government funding to cover Fannyside Muir. Extra resource is required to
fund Capital Building projects (mainly carry over from 12/13), restocking carry over,
road building and harvesting for phyto-sanitary felling programmes.
Phytophthora in Galloway will affect the sales plan income levels and increase costs,
but the underlying fundamentals of the timber market remain positive.
Variances have also been built in to make provision for the coal situation, and VME
commitments early in the year. A request for additional civil engineering resources to
be considered by Les, particularly a costly bridge project in Knapdale.
AP 5.1: Les to discuss the requirement of a bridge at Dunardy, West Argyll (£120k).
with Morven.
SNH are planning to co-locate at the Torlundy Office and will fund the cost of the
extension (£250k).
AP 5.2: Laurie will check the Lochaber extension is within our project portfolio.
Key Agency Targets and other KPIs will now be reported to the board on a quarterly
basis by Michael H. It was agreed that the targets sheet can be dropped from the
Finance report.
6.
RISK MANAGEMENT
Thanks to all who fed back comments to Linda allowing an updated Risk Register to be
presented to the ARC on 19th July. A few changes were requested by the ARC to
increase residual risk scores. An independent review of the register centred around
controls is due to begin shortly. Internal audit will carry out a review of the risk
register over the next couple of months. Pamela Brown is leading and will contact
functional heads to discuss controls under their own risks.
Jo will update risks 41 and 44, Tree Health Risks.
Top Risks
• Agreed to drop “Failure to meet Woodland Creation target” as a top risk.
• Risk 31: Reduction in timber costs residual risk score to be reduced.
• Risk 35: Scottish Coal Industry collapse. Alan D to check and input controls
AP 6.1: Alan D to check and input controls.
• Risk 46: Landslip/flood, is this risk reducing? Les said it was early days as
survey work is residual work, once we get into mitigation it will reduce.
• Risk 48: Les and Bruce are meeting Simon next week in regards to
restocking.
Emerging Risks
•
5
|
The emerging risks are the same as last month. Alan D talked to Ian Hood
re dates for the Cairnbaan project. Les said the situation at the moment is
FESMB BoardMinutes |
Hilda M Todd
|
18/09/2013
projected to run £50k over budget and scheduled to complete outwith the
agreed timetable. We need to run an evaluation engineering exercise to
bring the budget back into line to complete before 31st March. At the project
board last week it was more optimistic about achieving this. As a side issue
investigations on site identified found an outflow where a pipe discharged
directly into the canal. This cost should not be attributed to the project.
•
Ability to fill certain posts should be removed as an emerging risk.
•
Michael said there were issues with Robertsons regarding projects going
‘outwith budget’ and emerging issues delivering KPIs. Brent has met with
the Director of Robertsons regarding these guarantees. There are currently
issues with the Queen's View visitor centre and Cuningar Loop.
•
Consequentials of Tree Health issues in terms of landscaping/visual impacts
to be added as an emerging risk.
Alan S asked how we will cope with the aftermath of Phytophthora and what we will
do in regards planting.
AP 6.2: Jo will liaise with Alan D and see if it is OPS or CRT that will pay for
replanting as restocking goes through the forest design plan.
Thanks to all who fed back comments to Linda allowing an updated Risk Register to be
presented to the ARC on 19th July. A few changes were requested by the ARC to
increase residual risk scores. Internal Audit have been invited to review of the register
controls over the next couple of months.
Jo will update risks 41 and 44, Tree Health Risks.
Top Risks
• Agreed to drop “Failure to meet Woodland Creation target” as a top risk.
• Risk 31: Reduction in timber income residual risk score to be reduced.
• Risk 35: Scottish Coal situation
AP 6.1: Alan D to check input for risk 35 regarding coal operations.
•
•
Risk 46: Landslip/flood risk rating was discussed. Les suggested it was too
early to reduce the residual risk as we have yet to move from the survey to
the mitigation phase.
Risk 48: Les and Bruce are meeting Simon next week in regards to
restocking.
Emerging Risks
The emerging risks are the same as last month. The project board are actively
managing risks around the Cairnbaan project in terms of scope (including interaction
with wider issues on this WWII depot site), cost estimates and timetable.
•
6
|
Ability to fill certain posts can be removed as an emerging risk.
FESMB BoardMinutes |
Hilda M Todd
|
18/09/2013
7.
•
Michael flagged issues with the SCAPE process around tender submission
delays. Brent has met with the Director of Robertsons regarding these
concerns at Cuningar Loop. It is also an issue at the Queen's View visitor
centre.
•
Managing the consequentials of tree disease impacts to be added as an
emerging risk.
HEALTH & SAFETY UPDATE
Les brought four points of information to the table.
Roll out of the Forestry H&S strategy has had good feedback.
Draft of action plan, coms plan and training plans for discussion at the Safety
Committee next week along and will be presented to FESMB for sign off.
There were 5 accidents this period compared to 11 the previous and 3 Ridor compared
to 11. The majority were slips and trips. Staff ideas to tackle this include:
•
•
•
Issuing of walking poles is being trialled.
Safe access into machine cabs needs investigation as a result of an accident
in M&A.
Ensuring best choice of footwear.
Currently completing annual H&S report which will go to the FCSMB and FESMB.
There was a slight increase in accidents involving members of the public, especially in
regards to mountain biking.
It was agreed last year that board members should attend H&S days at District level.
This was well received and suggested that it should be built into the annual H&S days.
8.
FOREST RENEWABLES MANAGEMENT BOARD UPDATE
The current NFE installed capacity is 601MW and will to rise to 840MW by year end,
with Harestanes, Beinn an Tuirc 2, Mid Hill, and Rothes coming on stream. Despite
probability factors being reduced recently, the development portfolio still points to
2GW installed capacity being possible by 2020. However, PfR's appeal in relation to
Carron Wind farm has recently been rejected by the Reporter.
FCA inspired changes designed to protect investors (necessitating introduction of
limited company documentation as well as LLPs) is likely to increase costs by c£50k
and reduce income by c£300k for this financial year (delays in signing options).This
remains an issue under discussion with developers. Residual renewable potential to be
marketed for wind, hydro and possibly solar PV. To be as 'light touch' as possible. To
be presented to NCS 4th September if possible then briefed to Ministers.
There are indications that Morvern Community may proceed to take an active stake of
c11% in Abhainn Shalachain hydro scheme. It was agreed by the FESMB that FCS
7
|
FESMB BoardMinutes |
Hilda M Todd
|
18/09/2013
would not insist on a joint venture possibility for small hydro schemes where
neighbouring landowners were involved. There was a recent visit by the FoRe
Management Board to Harestanes wind farm site and an upcoming NCS visit to
Whitelee.
Project Transmit looks like reducing transmission costs in the north of Scotland,
meaning that wind farms are more likely to proceed there. It now transpires that
under EMR, contract for different strike prices will only be guaranteed for 15 years.
It was agreed that FoRe should be responsible for working with Solar PV should this
look like being a realistic possibility.
9.
PRIORITISATION OF ‘NEW’ CAPITAL WORKS PROJECTS
We want to be ready for any further phase of ‘Shovel Ready’ project funding. The
Board was presented with a list of potential ‘Shovel Ready’ project suggestions. The
Board identified projects with most potential for 14/15 for further development. A
number of longer-term projects need consideration by functional leads before being
considered by the Board. This process will be integrated into our project development
mechanism.
AP 11.1: Alan S, Laurie and Les will feed back over the next month. The Board will
see a refined version with recommendations from a Board member set within the
context of likely affordability.
The Board noted that work was underway to record the FTE’s stimulated by ‘shovel
ready’ funded projects.
10.
ORGANISATIONAL / FUNCTIONAL UPDATE
Les:
•
•
Ian Hood has taken up the post of Country Mechanical Engineer.
A Brash and stump harvesting tender is about to be launched in M&A.
•
A Phytophthora update was given. A new site of about 500m3 of Hybrid larch has
been added at Braes of Gight in M&A. A Harvester is currently on site and the site
will be felled by Monday. Cordiners will take the material to their sawmill. There is
a possibility Phytophthora emanated from the car park.
Michael H informed the Board that Zoe Stephens will take up the post of Corporate
Support Officer in September. Zoe will be based in SH but will work one or two days in
FESHO.
Alan S:
•
8
Advised that following a further round of tenders two local businesses had been
successful in securing leases to operate the catering services at the new centres in
Galloway Forest Park, and a further business at Queen’s View.
|
FESMB BoardMinutes |
Hilda M Todd
|
18/09/2013
•
Robertsons are due to finish at The Lodge this Sunday. It was suggested the Board
members may wish to consider attending the official opening scheduled for 27
September.
•
The ‘Tourism development framework for Scotland – role of the planning system in
delivering the visitor economy’ has been published and will be launched by the
Tourism Minister. The document benefitted from considerable input by FES and
highlights current opportunities for tourism on the NFE and also flags up potential
scope for future developments.
Niall:
•
Informed the Board that Mike Cowan’s replacement had been appointed. Janette
Hill starts on Monday.
•
The talent management programme will be launched at the end of the month. It is
based around the new Civil Service competency framework and will be overseen by
Capita.
•
Updated the board on themes emerging from the men’s focus groups, and their
similarity with issues raised by the focus groups for female staff.
The Annual Accounts for 12/13 were signed off by Simon on 19 July and have been
published on the Internet. A thorough audit was carried out by Audit Scotland and we
received good feedback from them.
Laurie provided an update on the latest developments following liquidations in the coal
industry. The liquidator has now confirmed that the preferred bidder, Hargreaves,
have now taken ownership of part of the Scottish Coal portfolio, with other sites being
put into the name of holding companies. This deals with most of the sites where SCL
had leases from the National Forest Estate, Rob, Laurie and our advisors are
continuing to work with Hargreaves, the respective local authorities and other
interested parties. One piece of positive news concerns Thornton Wood in SLFD,
where an excambion seems close to conclusion, once completed this will remove
remaining liabilities for this location. Dunstan Hill remains with the liquidator KPMG for
the time being.
11.
PRIORITISATION OF ‘NEW’ FES POSTS
The new table is based on the 2013 pre-business plan round of meetings. It shows
every post mooted at the meetings, however speculative.
Board members ran through the table prioritising the posts.
Two posts were approved, one Environment Ranger in Tay and one Operations FM
Forester in North Highland.
9
|
FESMB BoardMinutes |
Hilda M Todd
|
18/09/2013
12.
ORGANISATIONAL STRUCTURE / STAFFING
The Board discussed staffing issues.
13.
AOB
The next meeting of FESMB is on 12th September 2013.
10
|
FESMB BoardMinutes |
Hilda M Todd
|
18/09/2013