"How to Avoid Risk and Save Money with the Right Project

"How to Avoid
Risk and Save
Money with the
Right Project
Approach”
Presented by:
Sponsored by:
Adam Wood, MTU America Inc.
Rupert Hoecherl, io-consultants L.P.
© 2014 MHI®
Copyright claimed as to audiovisual works of seminar sessions and
sound recordings of seminar sessions. All rights reserved.
Introduction – Abstract
In this seminar presented by MTU America Inc. and io-consultants, you
will learn how you can positively impact the three project objectives:
• Scope
• Budget
• Schedule
The presenters will show you how you can meet these objectives
based on a highly successful implementation project.
They will guide you through the project life cycle from the early planning
stages all the way through to a successful go-live. Using practical and
proven examples, the presenters will show you how the right level of
up-front planning, a functional bidding process and professional
execution can reduce your timeline, improve your bottom line and
reduce your risk.
Introduction – Key Takeaways
1. Risk mitigation
2. How to plan and execute large investment projects
3. Project management tools
4. Cost saving ideas for your project
5. Project on time and on budget
Content
• Introduction
• New Parts Logistics Center North America (PLCNA)
– Overview
– Approach and Timeline
– Logistics and Automation
– IT
– Project Management
• KPIs and Summary
INTRODUCTION & OVERVIEW
Introduction – Speaker Information
Adam Wood
•
Education:
– B.S. Applied Engineering Science, cognate in MLM – Michigan State University
– B.A. Physics – Albion College
•
•
•
•
•
•
16 + years in the Diesel Engine Business
Extensive background in Production and Service Logistics and
Operations
Project lead for production IT (SAP) rollout in North America
Responsible for multiple warehouse changes / relocations
Regional project owner for new After Sales IT (SAP) roll out and
Parts Distribution Center implementation in NA
Current position – Director of Service Sales & Operations NA / LA,
MTU America Inc.
Introduction – Speaker Information
Rupert Hoecherl
•
•
•
•
•
Master of Science, Industrial Engineering
6 years experience in large scale distribution center planning and
supply chain management projects in aftersales and production
related environments
International experience, assignments in Europe, USA and the
Middle East involving managing geographically distributed project
teams working in multi-cultural environments
Focus on Strategic Planning, Material Handling Design,
Implementation, Ramp-up Support and Project Management
Currently serving as Business Unit Manager for the io-consultants
North American operations
Introduction – Overview
MTU America – Power, Passion, Partnership
•
•
•
Subsidiary of Rolls-Royce Power Systems AG
Manufacturer of large diesel engines and power systems
Manufacturer with global logistics operations supported by 3 main
distribution hubs worldwide (US, Germany, Singapore)
io-consultants – a Global Consulting Group
•
•
Founded in 1958
Provides services in Logistics, Supply Chain Management, IT
Automation and Flight Catering that are independent from hardware,
software and solution providers
PROJECT: MTU PARTS LOGISTICS CENTER
NORTH AMERICA (PLC NA)
Starting Point – MTU After Sales Logistics
• Large diesel engine manufacturer with logistics
operations focused in 3 main distribution regions
• All regions operate as separate organizations, with
different processes, systems (IT, Logistics) and locations
• North American operations and systems outsourced
• Renewal of contract for NA was evaluated
• Expected increase in sales, product portfolio and
customer service level requirements could not be
supported in existing setup for North America
• Process harmonization and integration of global after
sales logistics set up expected
Premise – Global Parts Logistics
Global After Sales Solution
3 Regions
3 Warehouses
3 Systems
Series production
Series production
Vendors
Germany
USA
1 globally
harmonized
planning and
execution
system
Region 3
Latin America
Australia
Vendors
Region 1
Australia
Singapore
Region 2
Goals and Target Definition
•
Standardized Processes
– Global process template
– Individual localization per region
•
•
•
One global IT system (EWM)
Global stock visibility
Standardized operations and
systems
– Pre-selection of systems for given
application on global basis
– Application to local requirements
•
Budget
(conf.)
Reduction in overall logistics cost
Timeline
13
months
Scope
• New DC
• New 3PL
• New IT
Overall Milestone Plan for Integration
Q3-2010
IT
Blue
print
Q4-2010
Prototype 1
Building
3PL
Prototype 2
Cut-over
Concept
Cut-Over
LOG
Q1-2011
Design
Stage
Selection /
Contracting
Bidding &
Contracting
Q2-2011
Q3-2011
Roll-In
USA
Data
migration
GoLive
Physical
move
Implementation
& Testing
Refurbishment /
Fit-out
Selection /
Contracting
Training &
Ramp-up
Less than 13 months from Kick-Off to Go-Live
Operating Model – Setup Options
Land
Building
Equipment
IT
Staffing
Remarks
MTU
Investor
3rd Party
Existing model
B
MTU
Investor
3rd Party
• Separate contracts for
building, equipment &
operations
• Process ownership (IT)
• Flexibility with 3PL
• Cost efficiency
C
MTU
Investor
3rd Party
A
Equipment
Building
Long term
dependencies
to 3rd parties
After Sales Logistics: Facts & Figures
•
•
•
•
•
•
Approx. 40,000 different SKUs
from small O-rings to 12-ton
crank cases
Up to approx. 3,000 order lines
fulfilled daily
Prepacking to streamline
outbound process
Conservation operations to
protect material
More than 1,000 different kits
produced in flexible Kit-toStock and Kit-to-Order process
Picking strategy: Work-to-Man
Recommended 3-Phase Approach
Client
Docs
Data,
Systems &
Layout
Concept
Design
Technical
Requirements
Detailed
Design
Budget &
Business
Case
Budget
Update
Phase 1
Phase 2
Functional
Bid
Package
Design
Spec
Engineering
Site
Supervision
Implementation
FAT, SAT
Testing &
Acceptance
Bidding &
Contracting
Firm
Competitive
Quote
Change Requests / Budget Tracking
Phase 3
Comparison
3-Phase Approach
Approach ‘Direct-buy’
•
•
•
•
•
•
•
•
Up front budget estimate
Competitive pricing (RFQ) for major
budget items
Transparent market
Functional system definition to allow
different technical solutions
Clear testing and acceptance scenario:
– Functionality
– Performance
– Availability
•
•
No defined basis for RFQ
RFQ for minor budget items (concept)
Non-competitive pricing for big ticket
items
No functional system definition
Limited testing (check against
proposal)
Recommended approach has positive impact on budget and timeline
Automated vs. Manual – Overview
•
•
Goal is to determine the most suitable storage system for small and medium
parts (up to 35 lbs)
Comparison of multi-order picking in a two-tier shelving system vs. a Workto-Man picking strategy in an automated storage and retrieval system
(AS/RS) loaded with trays (48in x 24in)
Manual Shelf System (2-tier)
AS/RS – Miniload
Automated vs. Manual – Operating Cost
Graph shows annual operating cost including depreciation on construction
cost and system invest from 2013 – 2021:
Savings
> 16%
Break even in annual operating cost (including depreciation) is reached
after approx. 3 years.
AS/RS
Shelf-Rack
Value
Operating
Cost
(Qualitative
comparison)
(Normalized)
3.9
1.0
3.0
1.1
Operating Cost
System Comparison – Summary
1.2
Shelf-Rack
1.0
ASRS
0.8
2.0
3.0
4.0
Value
Conclusion: The proposed automated storage and retrieval system is
the preferred picking strategy for small and medium parts
Process Standardization
• Standardize business processes at 3 sites in 3 different
time zones with different cultures / practices
• Develop global process template; allow for local
adjustments required for special processes and legal
requirements
• Dramatic changes to current processes required early
change management and communication strategy
• Improved support and comparison (KPIs) on a global
scale w/comparable operations
• Basis for improved inventory management across end-to
end supply chain
Case Study – IT
Process Standardization
Detailed process modeling
utilizing database
technologies
Local
process for
Quality
Inspection
Global process to
handle part returns
IT Standardization
Pre-GPL
PE2
Front-End
Post-GPL
Web Shop
GTS
PS3
DIBS
MS5
CMCS
Global AFS Template
PS2
CANTON
RETURNS
EXTRANET
GTS
TCMS
PAS
PE2
Returns
Core Management
Back-End
IMS
PARTS
LOC
Electronic EDI Ordering
MS5
PS2
PS3
Warehouse
Kitting
Forecasting / Planning
 Disconnected systems and information
 Non-Harmonized business processes
 Non-Harmonized data
 Non-Harmonized document types
 Uncontrollable results
 Common standardized systems
 Harmonized business processes
 Harmonized data
 Harmonized document types
 Optimized results
Procurement
Project Organization
= Global
Project Sponsors
Coordination
Global Parts
Logistics
GPL IT
(Global solution with local roll-in)
Support
= Regional
Steering Committee
PLC NA
Controlling
Quality / Integration
Global IT
Deliverable
Coordination
Management
Extension
PLC
Ueberlingen
Global
Solution
Architect
Transition Pl.
&
Phys. Move
Processes
&
Materials
3PL
Equipment
Facility
Project Management – Tools
Web-based project management tool
with:
•
Simple information exchange
•
Standardized communication and
information channels
•
Resource allocation and control
•
Permanent process tracking and
documentation of all activities
•
Access control on user level
The project team used the Project Portal in conjunction with MS-Project
(for schedules)
Controlling / Supervision
•
Risk management / Early warning
system (e.g. critical path)
•
•
•
•
Weekly status update meetings
Standardized status reports
Monthly budget tracking & control
Detailed schedule per sub-project
(with dependencies)
Integrated milestone schedule
Clear definition of deliverables
•
•
Balancing act between top down control and bottom-up sense of
ownership and responsibility
KPI AND SUMMARY
Review of Goals and Target Definition

•
Standardized processes


•
•
Budget
(conf.)
One global IT system (EWM)
– Global stock visibility
Standardized operations and
systems

•
– Global process template with
– Individual localization per region
– Pre-selection of systems for given
application on global basis
– Application to local requirements
Timeline
12
months
Scope
• New DC
• New 3PL
• New IT
Reduction in overall logistics cost
Goal met: On time and
under budget
Summary and Lessons Learned
• Spare parts profitability is significantly affected by
logistics costs
• Cultural differences pose challenge to worldwide projects
• Introduction of automation requires time to embrace all
benefits
• Consistent worldwide processes facilitate cost effective
operations and inventory management
• Standardized operations facilitate benchmarking
For More Information: