BC’s New P3 Evaluation Process Drives Facility Solutions to Bend the

BC’s New P3 Evaluation Process
Drives Facility Solutions to Bend the
Healthcare Cost Curve
Interior Heart & Surgical Centre
PRESENTERS
<insert
B&W
photo>
Leslie Gamble
Clinical Coordinator
<insert
B&W
photo>
Rick Steele
Assistant Vice
President
Mike Marasco
CEO
Overview
• Project description
• Procurement process overview
• Evaluation criteria
• Desired outcomes
• How the Plenary Health team responded
• Procurement challenges from a government perspective
• How the process will evolve in BC
3
Project Overview
Interior Heart & Surgical Centre
•
152,000 ft2 facility – 3 story addition to
Kelowna General Hospital, Kelowna, B.C.
•
15 operating rooms (2 cardiac)
•
Pre- and post-operative patient areas
•
Cardiac intensive care unit
•
Central sterilization and reprocessing
department
Total Project Cost:
$110 million
Total Financing:
$80 million
Consortium:
Plenary Group, PCL, Johnson Controls
Financial Close:
June 2012
Target Completion:
March 2015
Status:
Construction Drawings
4
Scored Elements
Identify main cost drivers
Identify where design enhancements can
enhance user outcomes and operational savings
Estimate the cost savings and benefits for each
design enhancement
5
Evaluation Framework
Compliance
Scored
6
Scored Elements -- IHSC
Wellness Environment (14.5 points)
(Access to direct light and outdoor space, natural features)
Optimize Clinical Utilization (32.5 points)
(Location, orientation and distance to medication rooms, location of
storage space)
Score
Benefit
Enhanced Site Development Features (9.5 points)
(Ease of access and wayfinding, site parking, and vehicular flows)
100
Enhanced Patient Safety (43.5 points)
(Travel routes, room standardization, ability to safely monitor patients)
0
Indicative Design Features
(Baseline)
How the Evaluation Criteria was
Developed
1. “Quantifiable benefits/outcomes” were determined
through use of internal and external research/data.
2. IH priorities reflected in the weighted points/scored
element.
3. IH worked with consultants/PBC to develop scoring
methodology and min/max for each element
4. PBC determined value/point and “fair processes”
8
Weighting of Scored Elements
Enhance Patient Safety by Reducing # of Adverse Events
Data
Calculation
Annual # of Surgeries
19000
% preventable errors (BN)
X 3.3%
Average increase in LOS/AE (BN)
X 6.2 days
Cost / inpatient day (IH)
X $2528
% attributed to design (Fable)
X 20%
% attributed to scored components
(IH)
X 40%
Annual Savings
$806,876
9
10
Results
Process:
• Proponents went after all points with exception of AEDET
• Clearly defined methods of scoring were essential
• Objective/detailed scoring = time commitment from
evaluation team
Clinical Priorities:
• Efficient high risk patient transport routes
• Additional staircases to increase physician/staff access
• Patient rooms/bays/OR’s standardized – column interference
was minimal
• Natural light in all departments; healing elements
incorporated
• Major building and MDR flows optimized
11
The Plenary Health Team Response
Team Structure:
• Shifted the
structure to
make it “design
led” focus to
optimize design
• Utilized IPD to
optimize
solutions that
responded to
evaluation
criteria
12
Focus for Most PPP / P3
Procurements
40 Year Facility Cost of Operations1
29.0%
0.1%
0.9%
O&M
Refurbishment
8.7%
Planning
3.1%
Design
Construction
Transition
58.0%
Note 1: From July 2010 Healthcare BIM Consortium ,An Organization consisting of Department of Defense Military Health System (DoD MHS),
Department of Veterans Affairs (DVA), Kaiser Permanente (KP), and Sutter Health, representing $26B of Healthcare construction
13
Focus for IHSC is to Drive Total Cost
40 Year Cost of Operations1
2.5%
0.0%
Program
0.1%
O&M
0.8%
91.2%
Refurbishment
Planning
8.8%
5.1%
0.3%
Design
Construction
Transition
Note 1: From Massachusetts Hospital Association, July 2010 Update to Hospital Costs in Context
Report
14
The Plenary Health Team Response
Team Behavior
• Moved away from focusing on low NPV
• Evaluated the cost versus NPV benefit of pursuing
scored elements
• More importantly, focused on EBD and Clinical Best
Practices rather than simply meeting the output
specification
• We were concerned that some of the design solutions
we put forward that responded to the scored elements
were producing a result that IHA was not anticipating
or liked
15
The Plenary Health Team Response
16
Government Perspective – Overall
Cost
40 Year Cost of Operations1
2.5%
0.0%
Program
0.1%
O&M
0.8%
91.2%
Refurbishment
Planning
8.8%
5.1%
0.3%
Design
Construction
Transition
Government Challenges with Process
• Cost and time
•
•
•
•
•
•
•
Consistency
Compliance vs. scoring
Credibility
Obtaining data
Valuation over concession term
Tracking outcomes
Privacy and transparency
18
Lessons Learned
• Less is sometimes better
•
•
•
•
Unrealistic accuracy
Be careful what you ask for – unintended consequences
Stand back and look at the big picture
Process works!
19
How the BC Model will Evolve
• Greater acceptance of process
•
•
•
•
•
•
Planned for all upcoming health projects
Data will become more available
Integration with lean thinking
Lower costs to implement
New indicators as evidence emerges
Concept will spread to other sectors
20
Questions & Discussion
[email protected]
[email protected]
[email protected]
21