In 2003, these seventeen men performed the impossible. CTB

CTB
C O M M U N I C AT I O N S
T E C H N O LO G Y
B R O AD C AS T I N G c a s e s t u d y
In 2003, these seventeen men performed the impossible.
C o m m u n i c a t i o n s Te c h n o l o g y
Broadcasting here demonstrates how
their formidable and uncontested
experience in the broadcast technology
industry enabled them to literally
achieve the impossible: to relocate a
TCI 611 SW antenna system originally
installed in the 1980's.
Published by Communications Technology Broadcasting 2011
C O M M U N I C AT I O N S
T E C H N O LO G Y
B R O AD C AS T I N G c a s e s t u d y
CUSTOMER PROFILE
The scope of work was as follows:
Customer: Official carrier of Broadcasting signals in South
Africa
Location:
1. Lower the three SW antenna curtain arrays suspended
between the four 100m lattice masts.
THE CHALLENGE
2. Package, transport and store antenna materials for reinstallation approximately 2km from the existing site.
To dismantle, relocate by 2 kilometres and re-install a TCI
611 SW antenna system originally installed in the 1980's
3. Dismantle the four the 100m masts, transport and store
at new site.
THE RESULTS
4. Dismantle approximately 1000m of open wire feed-line,
transport and store for re-installation at the new site.
The project was deemed to have been a huge success,
and what was thought to not be possible was achieved.
The antenna manufacture described the success as a
modern engineering marvel and congratulated
Communications Technology Broadcasting (Pty) Ltd on a
job very well done.
5. Dismantle three slew switches, transport to the new
Site.
6. Survey new site for antenna placement, taking into
account the desired target area (central and northern
Africa).
The antenna system is directional so the correct
placement of the foundations of the antenna curtain and
masts was of critical importance. Incorrect surveying
would result in the broadcast signal missing the desired
target area and as a result making the entire relocation
process worthless.
7. Excavate for foundations, manufacture of foundation
hardware, preparation of re-enforcing and casting of all
concrete (in total 350 cubic metres of concrete)
8. Survey in of new antenna feed-line positioning,
complete all civil works including re-bar, foundation
hardware, shuttering and concrete pouring.
9. Re-paint the 4 x 100m masts and re-install in their new
location taking into account the ground level to achieve
the same “balance” as the old site.
10. Raise the 3 SW antenna curtains, ensuring that the
dipoles are horizontal and the correct height from the
ground.
Project description:
In 2003, Communications Technology Broadcasting (Pty)
Ltd was approached by the official carrier of Broadcasting
signals in South Africa to evaluate and report back on the
possibility of dismantling, relocating and re-installing and
TCI 611 SW antenna system originally installed in the
1980’s (also by Communications Technology Broadcasting
(Pty) Ltd).
After due consideration Communications Technology
Broadcasting (Pty) Ltd decided that the project was
feasible and together with the customer decided to take on
a very ambitious project, deemed to be not possible by
many since the antenna system was almost 20 years old.
11. Re-install the feed-line
12. Re-install slew switches, transformers and horizontal
feed-lines.
13. Install new aviation lighting and wire all lights and
switches to transmitter building
14. Test and commission antenna system.
Published by Communications Technology Broadcasting 2011
C O M M U N I C AT I O N S
T E C H N O LO G Y
B R O AD C AS T I N G c a s e s t u d y
OVERVIEW
PROJECT DURATION
During the dismantling, transportation, storage and
installation phases, many hurdles had to be overcome.
The project duration spanned over two years.
Due to the age of the antenna many components had
become brittle and special care had to be taken to
eliminate the degree of breakages, which were inevitable.
As a result the dismantling was kept to a minimum and an
ingenious storage facility was created to house complete
dipole sections. Mast sections were kept complete and the
1000m of feed-line was transported using hundreds of
labourers carrying it by hand through the field.
This could have been greatly reduced had it not been due
to delays beyond the control of Communications
Technology Broadcasting (Pty) Ltd.
Design issues, theft and other technical issues forced
delays here and there.
Nevertheless the project was deemed to
have been a huge success, and what was
thought to not be possible was achieved.
The antenna manufacture described the success as a
modern engineering marvel and congratulated
Communications Technology Broadcasting (Pty) Ltd on a
job very well done.
By successfully completing this project Communications
Technology Broadcasting (Pty) Ltd has made its mark on
the Broadcasting industry.
Our reputation as Broadcasting and Communications
specialists was given yet another boost and put us into
different league where SW installations are concerned.
Communications Technology Broadcasting (Pty) Ltd can
say with confidence that no job is too big and if it is
possible, we can do it, we have done it!
Manual Labourers carrying feed line.
Although there were some breakages, this was kept to a
minimum and Communications Technology Broadcasting
(Pty) Ltd was able to manufacture and replace all
damaged items.
PLEASE PROCEED OVERLEAF TO OUR GALLERY
CONTACTS
Tel Nr : +27 11 425 6656
Fax Nr: +27 11 425 6845 / +27 86 693 1417
E-mail: [email protected]
Grant Chambers - Tel: +27 82 453 5216
Postal Address: Box 13299
Northmead
Benoni
1511
Physical Address: 237/1 Robin Road
Rynfield Agricultural Holdings
Benoni
1501
Typical replacement part made by CTB.
Published by Communications Technology Broadcasting 2011
C O M M U N I C AT I O N S
T E C H N O LO G Y
B R O AD C AS T I N G c a s e s t u d y
GALLERY
Our Gallery represents a sequential visual display of the entire project.
1. SW Antennae prior to relocation
2. Entire SW array that was relocated
3. Start of SW mast dismantling
4. Lower of top section of SW mast
5. Lowering of 1st section of SW mast
6. Mast dismantling in process
7. Winches in action used for antenna
lowering and raising
8. Loading of SW slew switch for SW
antenna system
9. Escorted transport of Slew Switch
10. Moving of antenna counterweights
11. Pegging out of Mast base
12. SW mast guy re-bar cages
Published by Communications Technology Broadcasting 2011
C O M M U N I C AT I O N S
T E C H N O LO G Y
B R O AD C AS T I N G c a s e s t u d y
GALLERY
Our Gallery represents a sequential visual display of the entire project.
13. Placing of re-bar cages
14. Casting of mast base foundation for
SW mast
15. Typical guy anchor for SW mast
16. Complete mast base for SW mast
17. Placing of 1st Section of SW mast
18. Preparing to lift a section of the SW
mast
19. Crane being used for 1st section of SW mast erection
20. Mast section being rasied on SW Mast
Published by Communications Technology Broadcasting 2011