The Office of Urban Assistance Residential Weatherization Program Procedure Manual Urban Weatherization Initiative

Illinois Department of Commerce and Economic Opportunity
The Office of Urban Assistance
Urban Weatherization Initiative
Residential Weatherization Program
Procedure Manual
RESIDENTIAL WEATHERIZATION PROGRAM
TABLE OF CONTENTS
SECTION I – PROGRAM OVERVIEW
PAGE
Purpose
1
Legislative Background
1
Program Design
1
How the Program Works
1-2
Mechanical System
2
Architectural Shell Work
2
SECTION II – ELIGIBILITY AND BENEFITS
RWP Eligibility
1
Prioritization
1
Definition of Income
1-2
Categories of Weatherization Measures:
2
1. Retrofit Measures
2. Air Sealing Measures
3. Health and Safety Measures
Water Heater Repair
2
2
2-3
3
RENTAL UNITS
3
Multi-Family Housing Units (maximum of 6 Units)
3-4
Furnace Assistance
4-5
SECTION II – PROGRAM ELIGIBILITY AND BENEFIT EXHIBITS
RWP Income Guidelines
Mechanical Cost Waiver Form
SECTION III – OUTREACH
Outreach
1
SECTION IV- INTAKE
Intake
1
General Instructions
1
RWP Application Instructions
1-2
Income Verification Documents
2-3
Residential Weatherization Checklist
5
Applicant Health and Safety Questionnaire
5
Completion of Consent Forms
5
SECTION V – CLIENT DETERMINATION
Determination of Client Eligibility
1
Work-Flow for Clients
2
Documentation
2
Household Income Information
2
Architectural Work
3
Multi-Unit Buildings
3
SECTION VI – RWP W0RK AUTHORIZATION
Client Notification
1
Application Processes
1
Multi-Family Building Approval
2
Approvals and Denials
2
Weatherization Timelines
3-4
SECTION VI – WORK AUTHORIZATION – EXHIBITS
Approval Letter
5
Denial Letter
6
Denial of Furnace Work
7
Furnace Weatherization Program Contract
8
SECTION VII - PROGRAM COMPLIANCE AND COORDINATION
Training
1
Training and Certification Program Policy
1
Continuing Education (CE) Classes
1
Classes
2
Staffing
2
Outreach Activities
2-3
Intake Process
3-5
Coordination of Activities:
5
a. Referrals and Agency/Organization Contacts
Contract Monitoring:
5
5
a. Grant Agreement Enforcement
Findings Matrix:
5-7
7
a. Minor Findings
a. Major Findings
High Risk Status or Grant Default Status
7-8
8-9
9-10
Additional Requirements
10
Quality Control:
10
Production
10-11
Production-Related Costs
11-12
Performance
12-14
SECTION VIII – ASSESSMENT
1
Assessment Overview
1
Required Color Photographs
1
Required Floor Plan
1
Exterior Inspection
2
Interior Inspection
2-3
Building Diagnostics
3-4
Health and Safety
4-7
Inspection and Testing of Combustion Appliances
7
Smoke Detectors
8
Carbon Monoxide Detectors
8
Moisture Control
8
Worker Protection
8
Fire Extinguishers
8
Exhaust Fans
8
Gutters and Downspouts
8
Deferral/Walk-Away Policy
8-9
SECTION VIII – ASSESSMENT EXHIBITS
Notice of Hazardous Condition
Dwelling Assessment: Moisture and Mold Checklist
SECTION IX – POST WORK AUDIT
1
Overview
1
Post Work Auditors Job
1
Evaluating the Initial Audit
2
Reviewing the Audit Document
2
Required Documentation Review Prior to Post Audit:
2
Mechanical Documents:
2
Mechanical Work Order
2
Mechanical Change Order Document
3
Mechanical Invoice
3
Assurance and Guarantee of Work
3
Release of Lien
3
Mechanical Contractor Checklist
4
Heating System Replacement Sizing Chart
4
Architectural Documents:
4
Architectural Work Order
4
Architectural Change Work Order
4
Architectural Invoice
5
Assurance and Guarantee of Work
5
Release of Lien
5
Immediate Blower Door Measurement
5
Verification of Work Order Completion
6
Verification of Completed Work
6
Accounting for the Work
6
Work Order Check-Off
7
Completing the Final Post-Work Audit Form
7
SECTION IX – POST WORK AUDIT EXHIBITS
Contractor Assurance and Guarantee of Work
Contractor Release of Lien
Post-Work Audit Attempt Letter
Contractor Checklist
Change Order Request
SECTION X – FILING SYSTEM
Required Subject Files
1
The Grant Agreement File
1
Applicant File
2-3
Ineligible Applicants
4
Multi-Family Building
4
Insurance
4
Personnel
4
RWP Correspondence
4
Procurement
5
Homes Previously Weatherized
5
Release and Retention of Records
5
SECTION X - FILING SYSTEM EXHIBITS
Application Checklist
SECTION XI - INVENTORY
Inventory Control
1
Grantee Inventory Control
1
Contractor Inventory Control
1
Equipment Acquisition Form
1-2
SECTION XI – INVENTORY EXHIBITS
Grantee Inventory Tracking Form
Contractor Inventory Tracking Form
RWP Equipment Acquisition Form
SECTION XII – PROGRAM REPORTING
Residential Weatherization Program Reporting
1
Project Status Report
1
Financial Status Report
1
Final Financial Status Report
1-2
Inventory Forms
2
Additional Information
2
SECTION XII – PROGRAM REPORTING EXHIBITS
3
Project Status Report
Financial Status Report
SECTION XIII – GRANT MODIFICATION PROCEDURES
Grant Modification Procedures
1
Budget Modification
1-2
Scope of Work
2
Date Extensions
2
Other
2
SECTION XIV – INSTALLATION AND RETROFIT MATERIAL STANDARDS
Diagnostic, Architectural, and Mechanical System Standards
1
Diagnostic Standards
1
Blower Door House Set-Up
1
Basements
1-2
Blower Door Test
2
Existing Leakage Rate
2-5
Zone Pressures
5-8
Pressure – Pan Duct Test
8-9
Duct-Induced Room Pressure Test
9-10
Exhaust Fan Flow Meter Test
10
Architectural Standards
11
Thermal Boundary
11-12
Reducing Air Leakage
12-18
Attic Insulation
18-26
Wall Insulation
26-33
Basement Insulation
33-35
Windows
35-38
Doors
39-43
Mechanical Standards
43
Combustion Efficiency and Venting
43-49
Combustion Safety Testing
49-50
Worst Case Depressurization
50-53
Carbon Monoxide (CO) Testing
54
Solutions to Combustion Safety Testing
54-57
Heating Appliance Venting
57-58
Masonry-Chimney Liners
58
Forced Air System Standards
58-60
Ducts
60-62
Central Air Conditioners
62-63
Heat Pumps
63-64
Room Air Conditioners
64
Hydronic Standards
64-65
Retrofits
65-67
Heating System Replacement Standards
67-71
Water Heater Retrofits
71-73
SECTION XIV – INSTALLATION AND RETROFIT MATERIAL STANDARDS – EXHIBITS
Appendix A Part 440 – Standards for Weatherization Materials
SECTION I
PROGRAM OVERVIEW
SECTION I
PROGRAM OVERVIEW
Purpose
The Urban Weatherization Initiative is designed to increase energy savings (reduce cost of energy) in low-income
households, increase employment and entrepreneurship opportunities in targeted communities, and support
local businesses by performing weatherization services including but not limited to, the installation of low-cost
weatherization materials such as insulation, air sealing material, weather-stripping, furnace repair, cooling units
and doors, minor repairs to walls, roofs, ceilings, floors, and windows (hereinafter referred to as
“Weatherization Services”). The initiative is intended to weatherize owner-occupied, single family homes and
multi-family units (6 units or fewer) that are located in areas with high rates of unemployment,
underemployment, and poverty as defined by the 2010 census and are identified by the Urban Weatherization
Initiative Board of Directors.
Legislative Background
The Urban Weatherization Initiative Program is administered by the Department’s Office of Urban Assistance as
authorized under the provisions of the Urban Weatherization Initiative Act (30 ILCS 738) (Act) and is overseen by
the Weatherization Initiative Board. The Act authorizes DCEO to plan, establish, administer, and expand the
delivery of weatherization services to eligible households within the identified areas.
Funds for the Residential Weatherization Program are made available to the Department from the Build Illinois
Bond Fund.
Program Design
This overview provides a general idea of how the program works and a review of the rules and procedures which
will govern the Residential Weatherization Program (RWP).
How the Program Works
The Residential Weatherization Program is geared to assist families residing in communities where 20% or more
of the population is living in poverty and that suffer from disproportionately high rates of unemployment,
underemployment, and poverty as identified by the 2010 Census. In addition, this grant will service areas with
high concentrations of families with income equal to or less than 60% of the Area Median Income. Although
most dwellings waste energy, different types of houses and apartments have different energy issues that can
include heat loss; cold air seeping in through cracks, around doors, walls, and ceilings. Depending on the
circumstance and condition of the dwelling, weatherization services include:







Addressing of air filtration with weather stripping, caulking, thresholds, minor repairs to walls,
roofs, ceilings, and floors;
Insulating attics, walls, and floors;
Repairing windows and doors;
Replacing non-repairable windows or doors;
Repair or replacement of inefficient heating and cooling units;
Repair or replacement of water heaters; and
Pipe, duct, or pipe and duct insulation.
I.1
The Weatherization Program has seven basic steps:
1. A potential applicant will apply at a location identified by the Grantee by completing an application
for the program.
2. The Grantee determines if the potential applicant meets the eligibility requirements based on the
income specifications as set by the legislation.
3. A Home Energy Audit will be conducted on the home, and the weatherization measures that will
save the most energy are printed on a Work Order. The Supervisor will be responsible for reviewing,
approving and signing off on all work orders completed before any work is initiated on the home.
4. All work orders will be competitively bid out by the Grantee in groups of 5-10. Those contractors
who have won the bid will take the Work Order and complete the weatherization repairs, using
high-quality materials that meet federal energy savings standards.
5. A HVAC (Heating Ventilation and Air Conditioning) certified contractor will inspect the furnace to
make sure that it is safe and in good working order and make the necessary repairs, retrofits, or
replace the furnace. The Architectural contractor will complete work on the shell of the unit to
reduce conductive and/or air infiltration heat loss.
6. A post-work audit will be completed by an auditor separate from the auditor who completed the
initial assessment
7. The office of Urban Assistance will randomly select a number of jobs to assess for Quality assurance
Mechanical Systems
Heating system work in the weatherization program is completed by an experienced HVAC/mechanical
contractor. The intent is to put the client's HVAC system in good operational order for the least amount of
money. This means that the work must pay for itself in future energy savings.
Architectural Shell Work
Architectural shell work (insulation, air-sealing, etc.) will be completed by a skilled architectural contractor, as
well as those who have secured their Building Performance Institute (BPI) Residential Building Envelope Whole
House Air Leakage Control Installer via the Weatherization Training Specialist Program. The applied work will
help reduce future energy costs of the client and increase comfort, and health and safety of the dwelling and
family.
I.2
SECTION II
PROGRAM ELIGIBILTY AND BENEFITS
SECTION II
PROGRAM ELIGIBILITY AND BENEFITS
RWP Eligibility
Eligibility for RWP is limited to households at or below 60% of the Annual Median Income level as specified in
Exhibit RWP Income Guidelines Section II. This income test will be based on the household's income (inclusive
of the owner(s) as identified on the mortgage or renter(s) as identified on the Lease Agreement) for the past 3
months which must be documented via pay check stubs.
(30 ILCS 738/) Urban Weatherization Initiative Act states that weatherization services will only be provided to:
1) a family unit whose income is at or below 60% of the Annual Median Income as identified in the 2010 Census;
2) owner-occupied single family homes in the areas which have been identified by the Board of Directors that
meet the income level identified via the 2010 Census; and 3) multi-family (6 units or fewer) in the areas which
have been identified by the Board of Directors that meet the income level as specified via the 2010 Census.
“For Sale” Status or Foreclosure
A home may not be weatherized if the unit is for sale, or in the process of being sold. This would include a sign
in the yard, or other public posting. If the Grantee discovers that the home is listed “For Sale” during the
process of Weatherization, all work should be stopped, and the Job should be closed out. The process should be
well documented with narrative and/or digital photos of a for sale sign, if applicable, and placed in the file.
Additionally, a Notice to Cease Weatherization Services will be forwarded to the assigned grant manager,
homeowner and/or renter.
A home may not receive Weatherization services if it is in the process of foreclosure.
Prioritization
Applications will be based on income eligibility as identified in the Urban Weatherization Initiative Act
Definition of Income
For the purpose of the RWP, income is defined as including money, wages and salaries before any deductions.
Income also includes regular payments from social security, railroad retirement, unemployment compensation,
strike benefits from union funds, worker's compensation, veteran's payments, alimony, and military family
allotments; private pensions, government employee pensions (including military retirement pay), and regular
insurance or annuity payments; dividends, interest, net rental income, net royalties, periodic receipts from
estates or trusts, and net gambling or lottery winnings. Note: Child support payments are considered as income.
Income excludes, (1) capital gains, (2) any assets drawn down as withdrawals from a bank, (3) the sale of
property, a house, or a car, (4) one-time payments from a welfare agency to a family or person who is in
temporary financial difficulty, (5) tax refunds (6) gifts, (7) loans, (8) lump-sum inheritances, (9) one-time
insurance payments, or (10) compensation for injury, less than $10,000.00. Income also excludes non-cash
benefits, such as the employer-paid or union-paid portion of health insurance or other employee fringe
II.1
benefits, food or housing received in lieu of wages, training stipends for Title V Senior programs or WIA (JTPA),
and such federal noncash benefit programs as Medicare, Medicaid, Food Stamps, school lunches, and housing
assistance. Note: Earned Income of dependent minors (children under 18 years of age) and college scholarships
are not considered as income and are excluded.
Categories of Weatherization Measures
There are three common categories of weatherization measures for the Residential Weatherization Program.
The three common categories are Retrofit Measures, Air Sealing Measures, and Health and Safety Measures. All
measures must be placed in one of these following categories:
1.
Retrofit Measures: These measures address conductive heat losses of a structure or generate heat for the
structure. Any measure that produces an energy savings is a Retrofit Measure. All Retrofit Measures generate a
Savings-to-Investment Ratio (SIR). The Retrofit measure MUST include all Tasks that are necessary to install that
measure. An example would be that a replacement heating system would include the furnace, mounting blocks,
plenum, thermostat, wiring, any transition ductwork, etc. These items would all be detailed and listed separately
within a Retrofit package, but would be included in the SIR calculation.
2.
Air Sealing Measures: These measures stop outside air or conditioned inside air from penetrating the thermal
boundary of the home. The result of completing these measures is determined by the air sealing measurements
completed with the use of a Blower Door. Air leakage estimates are used to calculate a single Air-Sealing SIR rating
for the home. Because of this all air infiltration measures installed on the home are combined together to generate
a single SIR value. Some examples of Air-Sealing measures would include weather stripping, caulking, foam,
thresholds, door sweeps, sash locks, etc.
3. Health and Safety Measures: These measures are to be identified during a health and safety check
before weatherization services are initiated in order to protect the applicant, their family, and the
workers performing the weatherization services/repairs:







Identification of operable smoke and carbon monoxide detectors
Identification of leaking fuel supply lines;
Identification of improper or ineffective Water Heater venting (such as installing a chimney liner
that is NOT part of a new furnace installation);
Identification of conditions that may lead to or promote biological concerns and unsanitary
conditions;
Identification of minor electrical repairs/upgrades that are needed before weatherization repairs
can be initiated;
Identification of the need to have correction of moisture and mold creating conditions when
necessary to ensure the long-term stability and durability of the weatherization measures and the
clients long-term health and safety (gutters and sump pumps are not allowed); and
Identification of needed water heater repair.
II.2
Water Heater Replacement/Health and Safety
Water Heater Repair
Repair work on a water heater includes the gas valve, venting, burner adjustment, burner door replacement,
minor repairs, etc. The Water Heater Repair costs do NOT include the installation of a chimney liner (or Class B
flue), if needed.
If the chimney liner is part of a Retrofit measure for a new heating system, then the cost is included in the cost
of the Retrofit.
Gas lines, sediment traps, flexible connectors, temperature/pressure discharge pipes, temperature/pressure
valves, or gas shut off valves are not allowed to be replaced unless they are damaged or leaking. If any of the
previously mentioned items are necessary to install, their costs cannot exceed a $200 Water Heater Repair limit.
RENTAL UNITS
When Weatherization Services are being requested on a rented dwelling, there will be no cost assessed to the
owner of the dwelling, however the owner of the residence must reside in the building per the statute. In
addition, the applicant must submit a copy of the Lease Agreement, along with a written and notarized letter of
authorization from the owner granting approval for a home energy audit to be completed on the property.
Once the audit has been conducted and before any weatherization service is performed on the home, the
Applicant must submit a second written and notarized letter of approval from the owner of the property,
authorizing the Grantee to perform the work as specified via the Work Order. All authorizations must be stored
in the applicant file accordingly.
Multi- Family Housing Units (maximum of 6 units)
As identified in the Urban Weatherization Initiative Act (30 ILCS 738), owner-occupied multi-family housing units
(6 units or fewer) are eligible to receive weatherization services if occupied by income-eligible tenants. The
allowable expenditures for work on multi-family housing units (up to a maximum of six units) are derived by
multiplying the maximum material and labor limit ($6500.00 per unit) times the number of income-eligible units
within the building. The maximum expenditure for the Site (building) is then spread equitably between all units
within the building. Vacant units are to be counted as eligible units if the Landlord has signed and agreed to rent
the vacant unit(s) to income eligible clients up to 30 days of the initial assessment of the property. The Landlord
must show proof of deposit received from the renter in the form of a certified check, along with a signed Rental
Agreement in order to have the vacant unit(s) included in the allowance.
In order to weatherize an entire multi-family housing unit, at least two-thirds (66%) of the building’s units or
apartments must be occupied by income-eligible tenants, unless the landlord
provides a rental agreement and a deposit check from the soon to be renter stating they will occupy the
residence within 30 days of the assessment. The only exception to the two-thirds (66%) rule is when the
residence is a duplex. In a duplex, one unit (50%) must be income-eligible. Example: in a triplex, two units (66%)
would need to be income-eligible; in a four or five unit building, three units (66%) would need to be incomeeligible; in a six unit building, four units (66%) would need to be income-eligible.
II.3
Furnace Assistance
As identified in the Urban Weatherization Initiative Act (30 ILCS 738) a heating unit can be replaced if it is nonrepairable and the total cost for purchase and insulation does not exceed the total maximum allowance of
$6500.00. This benefit will only be available to those income eligible households whose utility services have not
been disconnected. If the total cost exceeds the maximum allowable expense, no work will be completed by the
RWP. The family will be referred to the LIHEAP Furnace Assistance Program that is operated through the Illinois
Home Weatherization Assistance Program (IHWAP). The Furnace Assistance component will only be operated
from October 1 through April 30.
No furnace work will be performed on any furnace in a home that has been condemned or otherwise deemed
uninhabitable by the State or any unit of local government or by any department or subdivision of the State or
local government. In addition, no work will be done on any furnace in any household that is pending foreclosure
sale within 90 days.
A post-work audit will be conducted within 15 working days to ensure that all work was completed in a safe and
effective manner.
Only one furnace replacement benefit per dwelling is allowed for a period of 10 years. Agencies will need to
keep an electronic file listing the address of households receiving a furnace and maintain their records for a
period of 10 years.
If a replacement heating system is required, a 90% plus “two pipe” (sealed combustion) system must be
installed. An 80% plus system is only to be installed if the contractor has provided sufficient documentation as
to why a 90% plus system could not be installed, and a waiver must be approved by the grant manger and a
copy maintained in the applicant file. If an 80% plus system is installed in a location that uses a masonry
chimney, a metal flue liner must also be installed. A flue liner must be installed for the water heater if a 90%
system is installed, and the water heater remains as a stand-alone (orphaned) unit. The heating contractor must
complete a heating system sizing calculation to ensure that a properly sized heating system is installed. Copies
of these calculations are to be maintained in the client file.
A Health and Safety review shall be done in conjunction with the assessment and one (1) copy will be
provided to the homeowner or renter and one (1) copy will be placed in the Applicant file. If any health or
safety concerns are identified, no weatherization services will be performed. This program will not pay to
repair health and/or safety problems identified. The Applicant may reapply once the health and/or safety
concern(s) have been properly addressed and proof of repair(s) are provided. All proof of repairs must be
placed in the applicant’s file, this must include receipt of services completed and paid for.
The furnace section of the Applicant client file must contain:
 a completed Furnace Assistance Final Inspection form
 a copy of the contractor’s itemized invoice
II.4
 for furnace replacements, a written estimate for documentation of needed repairs vs. the new
furnace costs to compare and validate repairs the home ownership documentation which may
include, but is not limited to: a copy of the deed; the property tax bill; a mortgage payment
book coupon; an authorization statement from the executor of a blind trust, or other legal
documentation on home ownership that has been filed with the County Clerk.
 a sizing chart for furnace replacement
 if an 80% plus furnace was installed, the file must contain an OEA-approved waiver
documenting as to why a 90% plus system could not be installed, Any work completed
exceeding the mechanical cost limits that do not have prior authorization from OEA are
considered disallowed costs.
 the Contractor Release of Lien
 the Contractor Assurance & Guarantee of Work
 the Contractor Checklist (signed and dated by the HVAC contractor)
 the Assessment Worksheet
 the Client Information Worksheet
 the Furnace Assistance Rating Sheet
II.5
SECTION II
PROGRAM ELIGIBILITY AND BENEFITS
EXHIBITS
RWP Income Guidelines
Mechanical Cost Waiver Form
RWP INCOME ELIGIBILITY GUIDELINES
Illinois Housing Development Authority
60% AMI Effective December 31, 2012
Family size
1 PERSON
2 PERSON
3 PERSON
4 PERSON
Chicago
$30,960
$35,340
$39,780
$44,160
East St. Louis
$29,100
$33,240
$37,380
$41,500
Kankakee
$26,100
$29,820
$33,540
$37,400
Peoria
$28,020
$31,980
$36,000
$39,960
Rockford
$25,680
$29,340
$33,000
$36,660
(for each additional family member add the following)
Chicago-$4,380
East St. Louis- $4,140
Kankakee- $3,720
Peoria- $3,960
Rockford- $3,660
Residential Weatherization Program
Mechanical Cost Waiver
Failure to complete the Mechanical Cost Waiver in its entirety will delay the time frame for processing. All
Mechanical Cost Waivers must include the following information
Agency ________________________________
Date Assessed _______________Funding Source _________
Contractor _____________________________
Contractor's Address ________________________________
Client Name ____________________________
Address
___________________________________________
Job # ___________________________________
City ______________________________________________
Reason for the replacement:
_____________________________________________________________________________________
_____________________________________________________________________________________
Please be clear, concise and thorough on the reason for replacement. Provide a detailed cost breakdown of
material/labor descriptions is required. This includes brand name and size of heating system and detailed work
to be performed - no general classification. Detailed Color Digital photos of the existing conditions showing why
the replacement is required - No small photos will be accepted. If duct work is required, take photos of the
ducts (or lack of ducts.) If no furnace is present, state what was used to heat the home previously. Provide the
Heat Load calculation and Manual information.
Material/Labor Description
QTY
Material
Labor
Total
Other Weatherization Measures to be completed:
Complete and through description why the waiver is required:
___________________________________________________________________________________________
______________________________________________________________________________ ____________
Auditor’s Name _______________________________________ Date _________________________________
SECTION III
OUTREACH
SECTION III
OUTREACH
As outreach will be the Grantee’s first contact with a potential applicant, planned outreach activities is an
expectation of the program. Grantees are to publicize the date, time, and location where applications will be
accepted. This information must be publicized at least two (2) weeks in advance of the application acceptance
period. It is expected that a minimum of 1 outreach program is sponsored by the Grantee, prior to the
application period and a minimum of four (4) outreach activities that include speaking with the community
providers are planned. Outreach responsibilities include, but are not limited to:
 Ensuring persons within the service area are notified about the program via planned presentations at
a location that is accessible to the public
 Publishing information pertaining to the RWP in the local newspapers and other media outlets
 Distributing approved RWP marketing material to local churches, community providers, etc.
 Coordinating with and referring to other energy-related services
 Providing energy-related consumer education throughout the agency's service area
Further, outreach is intended to let the general public know of the weatherization services offered by the
Grantee. As the Residential Weatherization Program is operated on a first come first served basis and does not
have a prioritization system, Grantees must develop outreach procedures that ensure the families within their
service areas are aware of the Residential Weatherization Program. As such, it is important that each Grantee
develop positive working relationships with those groups in the community that are in regular contact with the
general population.
Grantees are expected to maximize their efforts to inform potential applicants, neighborhood organizations, and
local units of government about the Residential Weatherization Program. Distributing approved weatherization
brochures and local agency printed information shall be done to encourage community members to apply to the
program. Outreach to potential applicants shall be done on an equitable basis to all communities within the
Grantee’s targeted service areas. Each Grantee is expected to maintain a visit log that documents the audience,
date, and time of all outreach visits that promote the Residential Weatherization Program.
Each Grantee shall prepare written materials that describe how the program operates, the application period,
where applications will be accepted, the application process, along with eligibility requirements and type of
income documentation that is required.
III.1
SECTION IV
INTAKE
SECTION IV
INTAKE
Every Grantee must establish an intake system that will collect and secure the data needed to certify each
applicant as eligible for weatherization services. The Residential Weatherization Program application is the
official and only application form that is to be used.
All intake services must be performed according to the instructions prescribed by the Residential Weatherization
Program as identified in the Residential Weatherization Program Procedure Manual. During intake, an applicant
may be deemed ineligible, pending eligibility, or eligible as detailed in Section V of the procedure manual. It
must be noted that all intake and weatherization services are free of charge to the applicants.
Intake responsibilities cover the following areas:





General instructions
The Residential Weatherization Program Application
Completion of the RWP checklist
Income Verification
Completion of the Applicant Health and Safety Questionnaire
 Completion of Consent Forms
General Instructions
All applicants must be provided a program overview as detailed in Section I of the procedure manual. During
the application process, all households must be given the opportunity to apply for the program, regardless if
they do not have all the necessary information at the time of application. In the event the applicant is without all
required documents, the applicant will be categorized as “pending eligibility” and be allowed a grace period of
ten (10) calendar days to supply the necessary documentation. A letter specifying specific documents and any
outstanding information will be given to each applicant. If the applicant does not provide the required
documentation within the 10 day grace period, the application must be denied. Grantees are reminded that
information received on all applicants is confidential and is obtained only for use by the Residential
Weatherization Program. Grantees are hereby advised NOT to give out information about the applicant or
his/her application to anyone outside of the applicant or DCEO which will be used for report purposes only. All
documents received from applicants must be date stamped.
Residential Weatherization Program Application Instructions:
Please PRINT all responses clearly and legibly. Please note that applications are not to be completed in pencil.
DO NOT USE CORRECTION FLUID TO MAKE CORRECTIONS. To make corrections, draw a horizontal line through
the mistake and write corrections to the side of the box.
Application Date:
Enter the date the application is taken. This will be eight-digit number. The first two digits represent the month
(e.g., January will be 01, February will be 02, etc.). The second two digits will represent the day of the month
(01/31). The final four digits represent the calendar year. Example: February 18, 2012, will be recorded as
02/18/2012.
IV.1
Grantee Name; Applicant Name and Address:
Enter the Grantee Name, Applicant Name, Address, and Zip Code. Enter the Applicant Last name, First name.
County/ Area:
Indicate the County that the dwelling is located. Also indicate the area which the dwelling is located.
Home Phone and Alternate Phone:
Indicate the primary and alternate phone numbers.
Dwelling Type:
Indicate the type of dwelling with a check mark:
Single Family Unit means a structure containing no more than one household
unit.
Two to Six Dwelling Unit means a structure containing 2-6 units within the dwelling
Ownership:
If an applicant owns his/her home, documentation must be provided by the household to verify home
ownership. If the applicant rents, the landlord must supply proof of property ownership. This documentation
may include a copy of the deed, property tax bill, mortgage payment book, or an authorization statement from
the executor of a blind trust, etc.
If the applicant rents, the landlord must provide a copy of the rental agreement
These forms must be placed in the applicant’s file and a copy given or mailed to the applicant and/or landlord.
Applicant must indicate appropriate category with a checkmark
Own – Yes or No
Rent – Yes or No
Property Owner’s name and Address:
List the owner’s name and address. Owner must reside in the building in order for the applicant to be eligible.
List of Household Member(s):
This area should contain all of the information for all household members. If there are more than 6 members in
the household, you must use an additional application or supplemental sheet to record the additional household
information.
Total Number of Household Members:
Add names of household members and enter total.
IV.2
Income Verification Documents: Check all that is applicable and attach supporting documents.
Family income may not exceed 60% Area Median Income for the number of residents per household. At the
time of application, gross income documentation must be provided for each person in the household who has
received income during the last 12 months. If a household is on a fixed income (income that does not change), it
is acceptable to verify one payment as income and multiply the amount by twelve to obtain an annual amount.
Examples of fixed income include:




SSA and SSI
VA Benefits
IDHS payments (TANF, AABD, RRA)
Pensions
Documentation must be based on at least three months income prior to the date of the application. For
example, the previous year’s tax return may not be acceptable, unless it was filed near the time that the RWP
application was completed. If an applicant does not have proof of income for the full 3 months, the best and
quickest way to handle this is to have the applicant go to the source of the income(s) and have the source
complete an Income Statement.
Social Security Administration (SSA):
When using the award letter as documentation, subtract the monthly Medicare amount from the gross
monthly amount to get the 30-day income. Be careful not to confuse SSA benefits with those of
Supplemental Security income (SSI). Some monthly amounts may change.
Unemployment:
Enter the previous 30-day/3 month total of payments for unemployment.
Supplemental Security Income (SSI):
Enter the total of payments from SSI, excluding Medicare payments.
Temporary Assistance for Needy Families (TANF):
Enter the total of payments from TANF for the most previous 3 month period.
Other:
Enter the total of all other sources of income not listed above.
The Following are Not Considered as Income:








Reimbursements for vocational rehabilitation transportation and maintenance
Reimbursement for other expenses incurred (such as for medical expenses)
Scholarships, student living allowance, student grants, or student loans
Loans
Sale of property
Sale of house or car
Tax refunds
One-time insurance payments or compensation for injury
IV.3





One-time payments e.g., Death Benefits, Circuit Breaker Benefits, LIHEAP, etc.
Foster Parent reimbursement (Note: Do not count children as household members)
Food Stamps
Job Training Partnership Act
Earned Income of dependent minors (children under 18 years of age)
3 Month Household Income:
Enter the previous 3 month and annual gross total of all money, wages, and salaries (before any deductionsexcluding food or rent in lieu of wages). Wages earned by child care and other odd jobs should also be entered
on this line.
ANNUAL INCOME:
Indicate the total annual income
Social Security Number:
Enter the household member’s Social Security Number. Hard copy proof of SSN may include a copy of the Social
Security card, a copy of a valid driver’s license that shows the Social Security Number, or any other form of
government-issued identification that shows both name and number. The Department of Commerce and
Economic Opportunity (DCEO) is committed to protecting the privacy of its vendors, grantees and beneficiaries of
programs and services. At times, DCEO will request social security numbers (SSNs) or other personal identifying
information. Federal and state laws, rules and regulations require the collection of this information for certain
purposes relating to employment and/or payments for goods and services, including, but not limited to, grants.
DCEO also collects confidential information for oversight and monitoring purposes.
Applicant Signature:
The Applicant must sign the form indicating that all information presented is accurate.
If the applicant cannot read the Acknowledgement on the application, the Intake Worker is responsible for reading
and explaining the information. The application must then be signed and dated by the applicant.
If another person provides the information for the applicant, that person (18 years or older) shall sign the
applicant’s name, then their own name and indicate their relationship to the applicant (e.g., John Jones by Mary
Smith, daughter).
If the person giving the information is other than an immediate household member, the applicant must give
written permission for the application to be signed by the person. The applicant/signer must then enter the
date.
If applicants are unable to sign their name to the application and have no representative to sign for them,
applicants must sign with an X. The intake staff must then initial the applicant’s X.
IV.4
The intake staff must present a copy of the application to the applicant and place a copy in the applicant file.
If any documentation is not provided as required in the documentation section, the intake worker must give the
applicant written notice of documentation that the applicant must provide and the time in which it must be
provided (no less than ten (10) calendar days). A copy of this notice provided to the applicant must also be
placed in the applicant’s file.
Completion of the Residential Weatherization Checklist
The Applicant Checklist is to be completed by the intake staff in order to document that all required information
has been secured from the applicant in order to verify eligibility and proceed with the weatherization services
on the applicant’s home. When completing the form, the intake staff is to indicate the date which all items are
received. This form is to be placed in the applicant file accordingly.
Completion of Applicant Health and Safety Questionnaire
The intake staff is responsible for completing this questionnaire with the applicant during intake. The form will
then be filed in the applicant’s file accordingly. A copy must be given to the Home Energy Auditor prior to the
audit being performed.
Completion of Consent Forms
Prior to any weatherization work being performed on the homes, there are two consent forms which must be
completed by the owner and submitted to the intake staff and placed in the applicant file. Both consent forms
give the Grantee authority to complete the home energy audit, as well as the weatherization work identified as
a result of the audit. The Grantee nor contractor is permitted to begin any work on the home until both consent
forms are received by the Grantee.
The following consent forms must be completed by the owner and a copy placed in the file:
 Residential Weatherization Program Work Authorization; and
 Residential Weatherization Program Home Energy Audit Authorization.
IV.5
SECTION IV
INTAKE
EXHIBITS
Residential Weatherization Program Applicant Checklist
Residential Weatherization Program Application
Residential Weatherization Program Income Statement
RWP Applicant Health and Safety Intake Questionnaire
Residential Weatherization Program Consent for Audit
RWP Consent for Work Authorization
RESIDENTIAL WEATHERIZATION PROGRAM
APPLICANT CHECKLIST
Head of Household
SS#
Household Members: _________________________________________________________
Name
Age
Relationship
to Head of
Household
Birth Date
Social
Security #
Source of
Income
Affidavit
In
File
Sent
For
___________________________________________________________________________________
__________________________________________________________________________
__________________________________________________________________________
__________________________________________________________________________
VERIFICATION OF INCOME AND IDENTITY:
______PHOTO ID (CURRENT WITHIN LAST 12 MONTHS)
INCOME VERIFICATION FOR EVERYONE IN HOME (One of the following):
______TANF AWARD LETTER
______PAYCHECK STUBS (3 Prior Months)
______RETIREMENT/DISABILITTY AWARDS LETTER
______SSI AWARDS LETTER
______SOCIAL SECURITY VERIFICATION
______UNEMPLOYMENT
______OTHER
VERIFICATION OF UTILITY BILLS:
______MOST RECENT GAS BILL (3 Months)
______MOST RECENT ELECTRIC BILL (3 Months)
CONSENT FOR RELEASE OF INFROMATION (Most Recent 12 Months)
PROOF OF OWNERSHIP (One of the following):
______PROPERTY DEED
______CURRENT HOMEOWNERS’S INSURANCE POLICY
______MORTGAGE AGREEMENT
______PAID REAL ESTATE TAX
______LEASE CONSENT
COPY OF CONSENT FROM OWNER:
_____CONSENT TO PERFORM AUDIT
_____CONSENT TO PERFORM WROK (As identified in the audit)
COPY OF APPLICATION_____
INTAKE QUESTIONS/PROCEDURES:
_____Was the verification and notification process explained?
_____Was the applicant given a copy of his or her application?
_____Was the Applicant Health and Safety Questionnaire complete?
RESIDENTIAL WEATHERIZATION PROGRAM APPLICATION
Date____________
Grantee Name__________________
Applicant Name:____________________ Address:___________________
Zip Code:______
County________________ Area_________
Home Phone_________________ Alternate Phone__________________
Dwelling Type: Single-Family Dwelling______ Multi-Unit Dwelling________ # of Units____
Ownership: Own________
Rent________
Property Owner’s Name:____________________
Address:________________________________
LIST OF HOUSEHOLD MEMBERS
Name
Birthdate
Relationship
Income
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
Total Number in the household________
INCOME VERIFICATION: SSI Letter____ SSA Letter____ Check Stubs____
Unemployment____ Prior year tax return________ Other_______________
3 Month Household Income $____________ Annual Income $___________
ACKNOWLEDGEMENT


I hereby declare that I have not received weatherization services at my current address. I understand that these
services are at NO COST to me. I understand that all information contained on this application is confidential and
will not be revealed without my written consent.
It is further understood that my house can be rejected to receive weatherization services, if all of the required
program measures cannot be completed within cost limits or if the conditions of my home has deteriorated beyond
repair, or if circumstances exist that threaten the health of workers and/or occupants.
I also certify that the information contained in this application is accurate.
_____________________________________________________________________________________________
Signature of Applicant
Social Security Number
Date
______________________________________________________________________________
Intake Staff
Date
RESIDENTIAL WEATHERIZATION PROGRAM
INCOME STATEMENT
Wages, Social Security, etc.
________________________________________
Person, Company or Agency
________________________________________
Address
________________________________________________________
City, State, Zip
_______________________________________________________________
To whom it may concern:
Re: (Applicant Name)
I hereby authorize the above person and/or agency to provide a verification as provided below of my
income from ______________________________________________ the
past
3
months
(Income Source)
as part of my application process for the Urban Weatherization Initiative (UWI). I understand the
noncompliance with this request for income information may result in the denial of assistance.
Signature ________________________ Social Security #
Address
__________________________
__________________________________________
__________________________________________
Please mail or deliver to:
__________________________________________ received
the
following
gross
income from
Name
__________________________________________ for the past 3 months.
Income Source
/
/
to
/
Did the person work the entire 3 months?
/
__ Yes
$ _____________________
__ No
____________________________________
_________________________________
Signature
Title
___________________________________
________________________________
Phone Number
Date
RESIDENTIAL WEATHERIZATION PROGRAM
HEALTH AND SAFETY QUESTIONNAIRE
Name:
Phone:
Address:
Ventilation:
1. What type of heating system does the residence have:
☐Gas ☐Propane
☐Kerosene ☐Electric ☐Hot Water
☐Other
2. Is the heating system properly ventilated?
☐Yes
☐No
 If No, what will be the corrective action taken to properly ventilate the residence and
time frame to have work completed:
3. Which of the following does the residence have?
☐Crawl Space
☐Attic
☐Basement
4. Are these properly ventilated?
☐Yes
☐No
 If No, explain:
(Check all that apply)
5. Are there working Carbon Monoxide detectors within the residence?
☐Yes
☐No
Fire Hazards:
6. Are there any exposed electrical outlets and/or exposed electrical wires within the residence?
☐Yes
☐No
 If Yes, explain:
7. Are all the electrical wiring and circuits in compliance with building codes?
☐Yes
☐No
 If No, explain:
8. Does the residence have a fire extinguisher?
☐Yes
☐No
9. Are there working smoke detectors located in the residence?
☐Yes
☐No
Water/Mold Hazards:
10. Are you aware of any mold in the residence?
☐Yes
☐No
 If Yes, what has been or will be the corrective action taken and time frame to have work
completed:
11. Are you aware of any water damage within the residence?
☐Yes
☐No
 If Yes, what has been or will be the corrective action taken and time frame to have work
completed:
12. Is there currently any standing water within the residence?
☐Yes
☐No
 If Yes, explain:
Lead Based Hazards:
13. Was this residence built before 1978?
☐Yes
☐No
14. Are you aware of any lead based paint within the residence?
☐Yes
☐No
 If Yes, are you aware of any corrective actions taken to remove lead from the residence?
Pets/Allergens:
15. Do any of the occupants within the residence have allergies?
☐Yes
☐No
 If Yes, will the type of allergy be affected by any work being done within the residence
(i.e. dust, insulation, odors):
16. Are there any pets within the residence?
☐Yes
☐No
 If Yes, what type of pets:
17. Will the homeowner be able to take precautionary measures and secure the pets while the
worker(s) are at the residence?
☐Yes
☐No
 If No, explain how the homeowner will ensure the safety of the worker(s):
Illness Hazards:
18. Are any of the occupants within the residence ill or have been ill?
☐Yes
☐No
 If Yes, will this illness potentially interfere with the health and safety of the occupant
and/or worker? Please explain:
General Hazards:
19. Are there any structurally unsound/weak areas within the residence that will pose a potential
hazard which include, but are not limited to the following:
☐Stairs
☐Floors
☐Ceilings
☐Other
(Check all that apply)
 If so, please explain all that apply:
20. Has the residence ever had a cited violation/housing violation/repair violation?
☐Yes
☐No

If Yes, explain:
RESIDENTIAL WEATHERIZATION PROGRAM
CONSENT FOR HOME ENERGY AUDIT
I,
____
, certify that I am the owner
print homeowner’s name
of record for the property located at:
_____________________________________________________________________.
I further certify that I have given my permission to the Residential Weatherization Grantee or its
designated agent to perform a home energy audit on the property listed above in accordance with the
Residential Weatherization Program standards and procedures, and other requirements that may be
attached to this agreement.
Homeowner’s Signature___________________________
Homeowner’s Phone # ______________________________
Date__________________
RESIDENTIAL WEATHERIZATION PROGRAM
CONSENT FOR WORK AUTHORIZATION
I,
____
, certify that I am the owner/authorized agent
print homeowner’s name
on file for the property located at _____
.
I further certify that I have given my permission to the Residential Weatherization Program Grantee or
its designated agent to allow weatherization work to be completed on the dwelling and/or primary
heating system at the property listed above in accordance with the standards and procedures of the
Residential Weatherization Program and other requirements that may be attached to this agreement.
I understand that all work that may be done to the primary heating system will be guaranteed for a
period not to exceed one year. After that time, I agree to be responsible for any related costs to the
primary heating system.
Homeowner’s Signature________________________
Homeowner Phone # __________________________
Date________________
SECTION V
DETERMINATION
Section V
DETERMINATION
Determination of Client Eligibility
Intake is the initial step in the application process which ensures that the household is eligible for
weatherization services. Intake instructions require all documentation to be date-stamped based upon the date
of receipt. This is imperative as it will establish the beginning of the processing timeline. At intake one of three
actions may occur .The application will be deemed ineligible, pending eligibility, or eligible.
If the application is deemed ineligible, a letter will be forwarded citing the reasons for ineligibility and a copy will
be placed in the applicant’s file.
If additional documents are required, the application will be identified as “Pending Eligibility” until all
documents are submitted to the intake staff. A letter citing what documents are outstanding will be forward to
the applicant and a copy placed in the applicant’s file. If it is determined that required documents are missing,
the applicant must submit those documents to the intake staff within ten (10) calendar days from the date of
the letter. If the information is not submitted within the required time frame, the application will be deemed
ineligible, and the intake worker will forward a letter of ineligibility to the applicant within two (2) business days,
while citing their ineligibility as a result of the applicant’s failure to forward the required documents.
The intake worker has eight (8) calendar days to determine an applicant’s initial eligibility. Once it is determined
that an applicant is eligible, the intake worker will draft a letter citing the applicant’s eligibility for the program
and the next steps that will follow. After review, the intake worker will forward the letter, along with all
supporting documents, to the supervisor for final eligibility determination. The supervisor must provide final
eligibility determination by signing off on the eligibility letter within 48 hours of the intake worker’s initial
approval. A copy of the eligibility letter must be placed in the applicant’s permanent file before being forwarded
to the applicant.
Please note that the final eligibility determination is for the agency's protection. By having two people review
the file, it is less likely a site-visit or audit will discover ineligible clients. For this reason, final eligibility
determination for each applicant must be made by the supervisor as previously stated.
Determination responsibilities include the following:




Reviewing the application form to ensure that it is thoroughly completed
Assuring all documentation is provided with the application
Intake worker will ensure all documentation provided is valid
Once the intake worker provides initial application approval, the supervisor must review and approve
final eligibility
V.1
Work-Flow for Eligible Clients
Once intake is completed within ten (10) business days, a home energy audit must be completed
within ten (10) business days from the date of the final eligibility determination. The intake process
and audit must be completed within thirty (30) days from the date the intake process began.
Work-Flow for Pending Eligible Clients
Once the intake staff is in receipt of all requested documents, she/he must determine the applicant’s
eligibility with 24 hours of receipt of documents. The intake worker must then forward the eligible
application to the supervisor for final eligibility determination. The supervisor must make final
eligibility determination within 48 hours of receipt of the application, after which the auditor will be
allowed 10 days to complete the audit.
Assuring Documentation is Present
The applicant has seven (7) days from the date of the notice of pending eligibility to supply the
necessary documentation or the application will be denied. For this reason, it is recommended that
pending files be organized by date.
Based upon varying circumstances, it may be warranted that assistance be provided to the applicant,
by the intake worker, in an effort to obtain the requested documentation. All efforts to assist with
securing documentation must be documented and placed in the client file. When documentation has
not been received within the required timeframe, the Grantee must forward written correspondence
to the applicant indicating that the application has been denied weatherization funding, as a result of
their failure to submit the requested information and a copy placed in the file.
Verifying Household Income Information:
The number of persons documented in the file as receiving acceptable types of income listed is to be
verified with the application information.
Determination of Unit Eligibility:
In addition to determining a client's income eligibility, it is also necessary to assure proper
documentation is obtained and proper procedures are followed for weatherizing various dwelling
types. Prior to authorizing the work, then the grantee must follow the requirements below per
dwelling type:
Single Family Owner-Occupied: Dwellings shall be assisted if they are occupied by an incomeeligible owner. The owner must supply proof of property ownership.
Single Family Renter-Occupied: For dwellings occupied by income-eligible renters, a rental
agreement signed by the landlord is required. The weatherization process cannot move forward
until the Rental Agreement is signed.
V.2
NO ARCHITECTURAL WORK IS TO BE DONE ON ANY UNIT WHERE THE HEATING SYSTEM HAS
BEEN DETERMINED TO BE UNSAFE.
2-6 Unit Rentals. If 50% of the 2-unit building is occupied by income-eligible renters, and the
building has a common foundation, then the entire building may be weatherized. If this is the case,
then the landlord must sign a rental dwelling unit agreement. If only one of the units in a 3 to 6
unit building is occupied by an income-eligible client, then the one unit shall be eligible for
weatherization and treated as a single family renter-occupied unit. The “66% or greater” rule
applies in the case of 2,3, 4,5, and 6-units. However, no furnace work may be done on a central
heating system. NO ARCHITECTURAL WORK IS TO BE DONE ON ANY UNIT WHERE THE HEATING
SYSTEM HAS BEEN DETERMINED TO BE UNSAFE.
Multi-Unit Buildings. Entire multi-unit buildings (2 to 6 units) shall be assisted if: (1) more than
66% of the tenants are income-eligible for Urban Weatherization Initiative (2) the grantee has
obtained written permission from the landlord; (3) the grantee has received written or email
approval from their Grant Manager approving the Multi-Family Building Plan; and (4) the landlord
has signed the Rental Agreement.
SRO, Group Home, and Shelters. Residents of a privately owned or not-for-profit operated single
room occupancy (SRO) building, group home, or shelter are not eligible for weatherization services
under the Urban Weatherization Initiative.
Re-determination of Eligibility
If actual weatherization work has not begun on the unit within 6 MONTHS from the date eligibility
determination was made, the income eligibility must be re-determined. Unless a substantial amount of
information on the application has changed, a new application will not need to be completed. In this
case, sign and enter this date to complete the application.
If the client is over-income or otherwise determined ineligible after re-determination, the application is
denied. It is not necessary to re-determine client eligibility if work has begun within the required
timeframe on the mechanical system.
Re-weatherization Prohibition
Agencies are prohibited from weatherizing any housing unit that received Urban Weatherization
Initiative assistance previously.
V.3
SECTION VI
URBAN WEATHERIZATION INITIATIVE: WORK AUTHORIZATION
SECTION VI
URABN WEATHERIZATION INITIATIVE: WORK AUTHORIZATION
All Urban Weatherization Initiative contractors are required to be certified with the State of Illinois, insured, and
bonded before starting on any contractual weatherization work.
Client Notification
The Intake Worker will forward the residential occupant a copy of the Final Eligibility Determination Letter which
must detail the following: The date which the final eligibility was determined; The date which the home energy
audit must be completed; The start and conclusion dates in which the weatherization work on the home must
be completed; Information pertaining to the post-work audit, i.e. the date of completion and auditors name;
and finally agency contact information in order for the applicant to express concerns or make inquiries regarding
weatherization services being received.
As previously indicated in Section 5-Determination, the Home Energy Audit must be completed within 10 days of
the final eligibility determination. The weatherization work on the home must be completed by the contractor
within 45 days after the award has been accepted. The Post-work Audit must be completed within 14 calendar
days after the weatherization services have been completed.
Multi-Family Building Approval Process
Before any weatherization services are initiated, the owner of the building must provide written consent
authorizing the Grantee and subcontractors permission to perform the work. This form gives the Grantee, along
with the contractors, permission to complete the home energy audit, as well as the weatherization services on
the property. In addition, a notarized letter from the owner stating that the owner will not raise the rent on the
property for 5 years after completion of the weatherization services on the home.
Prior to scheduling work on multi-family buildings, Grantees are required to obtain written approval from the
Urban Weatherization Initiative Grant Manager prior to commencing weatherization services.
The Grantee must complete a Multi-Family Building Plan, place a copy in the file, and submit a copy to grant
manager for approval. The following information must be included in the Multi-Family Building Plan:
1.
2.
3.
4.
5.
6.
7.
8.
Name of owner of the property
Address of building
Total number of units
Apartment numbers of all income eligible units
Heating system type/configuration
Estimated materials and labor costs for each unit
Photos of the units to be weatherized.
Work that will be completed on the property.
In addition, the grantee must tender copies of the final eligibility determination letter in conjunction with the
Multi-Family Building Plan for approval before work commences.
VI.1
Work Authorization Flow Process for Single Family Homes
Work Authorization Flow Process for Multi Family Homes
VI.2
Reversing Approvals and Denials
The following criteria shall determine the status of the dwelling unit should a client vacate the dwelling unit
after work on the unit has started, or before work on the unit has been completed:
1. If a client is a homeowner, work shall be discontinued, and the unit shall be counted as a completion.
2. If the landlord signs an agreement to rent to another low-income eligible client within thirty (30) days of
vacation, and presents a new rental agreement, along with a notarized rent guarantee, work shall be
continued and the unit shall be counted as a completion.
3. If the landlord refuses to sign the agreement, work shall be discontinued.
Urban Weatherization Initiative: Timelines
Work Authorization includes the responsibility of the Grantee to follow the required timelines as described
below:
Eligibility Determination: The Grantee has up to 30 CALENDAR DAYS from the date an application is
received to determine eligibility and notify the client of their application status. If documentation is
incomplete at time of application, the applicant has at least ten (10) CALENDAR DAYS to provide the
necessary information. If the required documentation is not provided, the application will be denied. NOTE:
Timeframes for eligibility determination for clients residing in Multi-family buildings is the same.
Home Energy Audit: The audit for architectural, shell (basic), and mechanical systems work
shall be done prior to beginning any weatherization work. It is required that both the architectural shell and
mechanical systems assessments be done at the same time.
Six Month Re-determination: If actual audit weatherization work (materials installed) has not begun on
the unit within 6 months from the date eligibility determination was made, the income eligibility must be
re-determined. Unless a substantial amount of information on the application has changed, a new
application will not need to be completed. If the client is over-income or otherwise determined ineligible
after re-determination, the application is denied. It is not necessary to re-determine client eligibility if work
has begun within the required timeframe. Failure to re-determine the income, if more than 12 months has
elapsed since work began, will result is disallowed Weatherization costs.
Work Began: Under the above guidelines, actual weatherization work must begin within 6 months of the
date eligibility determination was made. No work can begin on a multi-family unit building until it is
determine that the cost to weatherize will not exceed $19,500 in repairs, and all required documents are
forwarded to the grant manager and written approval is provided. The final costs for mechanical work must
be determined before architectural work begins to avoid exceeding per unit costs maximums.
Work Completed: All weatherization work must be completed on each unit within 45 days from the bid
being awarded to the contractor. All work must be finished within 6 months of the date work was begun on
that unit.
Post-Audit: The post-work audit must be done within 10 calendar days after work on the unit has been
completed. In the event the Final Inspector determines the unit is a call-back due to workmanship or missed
measure the ten day (10) day time frame is nullified; and will re-start upon completion of the workmanship
or call-back measure(s) being remedied, which must be completed within 45 calendar days.
VI.3
Reassessment: If weatherization work has not begun within a 5 month timeframe, a new audit is
necessary. The audit must be recalculated and a new Work Order printed.
Data Entry: Grantees are required to complete data entry on the spreadsheet or computer based system on
each unit within fifteen calendar days of the post-audit. The completed unit is to have final costs entered
into the Costs Reporting Spreadsheet within five (5) working days of the post-audit.
VI.4
SECTION VI
WORK AUTHORIZATION
EXHIBITS
Eligibility Letter
Denial Letter (General)
Denial Letter (Furnace)
URBAN WEATHERIZATION INITIATIVE PROGRAM
ELIGIBILITY LETTER
Date
Applicant's Name
Applicant's Address
Dear (Applicant):
Your application for the Urban Weatherization Initiative has been approved for assistance to improve your
home's energy efficiency. A staff member will contact you to set a time to inspect your home to determine if it
can be weatherized.
The steps taken in weatherizing a home are as follows:
1. One of our staff members will assess your home and conduct a computerized energy audit
that will determine the work to be done.
2. An audit will be conducted within 10 days after notified of your eligibility. Once the audit
has been finalized, the work to be done will be placed on a schedule. You will be called and
advised of the date when work will begin on your home.
3. When the weatherization work is complete, a staff member will come to inspect the quality
of work within 2 days. You will then be asked to sign the final form that indicates that an
inspection was done.
The purpose of this program is to reduce your home's heat loss, which can be reduced by:
1. Stopping infiltration
2. Adding insulation
3. Ensure the furnace is working properly
The work generated by the energy audit will be completed.
weatherization work is provided to the applicant at no charge.
The labor and materials to perform the
If you have any questions about the Residential Weatherization Program, please contact ____________
at _____________________________.
Intake Staff Phone Number
We appreciate this opportunity to serve you.
Sincerely,
(Agency Representative)
cc: Applicant's File
URBAN WEATHERIZATION INITIATIVE PROGRAM
DENIAL OF ASSISTANCE LETTER
Date
Applicant's Name
Applicant's Address
Dear (Applicant):
Your application for the Urban Weatherization Initiative Program has been considered and a determination was
made that your household is ineligible because:

Your household's total income was over the allowable limit for your household size.

Your residence has already received Weatherization Assistance on_______
Enter Date

Your household did not submit all required documents and/or information by the required date for
submission______________________
Enter Date

There are insufficient funds available in this program year.

Your home is not structurally sound and the energy conservation measures that could be installed would
not be effective.

Other___________________________________________________________________
Remember, you have a right to reapply for assistance.
Sincerely,
(Agency Representative)
cc: Applicant's File
URBAN WEATHERIZATION INITITIVE PROGRAM:
URBAN WEATHERIZATION INITIATIVE PROGRAM
DENIAL OF FURNACE WORK
Date
Applicant's Name
Applicant's Address
Dear (Applicant):
Your application for the Urban Weatherization Initiative Program has been considered and determination was
made that:
Heating system work cannot be done because repair, retrofit or replacement costs
exceed the allowable limits for our program. If you can obtain funding by
_______________, you will receive assistance.
Insert Date
Your heating system was determined unsafe. It is the policy of the Urban Weatherization Program that no
weatherization work be performed on housing units with unsafe heating systems. Once the furnace has been
repaired you may reapply for weatherization assistance.
Agency Representative
Sincerely,
(Grantee)
cc: Applicant's File
Enclosure: "Your Rights" brochure
PROGRAM COMPIANCE AND COORDINATION
Section VII
PROGRAM COMPIANCE AND COORDINATION
The Grantee agrees to comply with the program requirements as outlined in the following sections for the
Residential Weatherization Program. This includes all program manuals, policy, procedure and technical
assistance memoranda, electronic communication and other directives, as provided by the Urban
Weatherization Initiative Program.
Training
1. The Grantee will establish and maintain a complete set of program manuals, policy and procedure
letters, technical assistance memoranda and other directives, as provided by the Residential
Weatherization Program. Sufficient quantities must be available to ensure accessibility to all your staff.
2. The Grantee will ensure that there is a representative present for all workshops and meetings called by
the office Urban Assistance.
3. The Grantee will ensure that, all Weatherization Specialists, and Auditors have either their BPI Building
Analyst Certification, or their BPI Building Whole House Air Leakage Control Installer Certification. Their
successful completion of the certification is required in order to work as a Home Energy Auditor or
Weatherization Specialist. In addition, the grantee will ensure that 50% of the Home Energy Auditors
and Weatherization Specialists are hired from the UWI training programs.
Staffing
1. The Grantee will retain a Project Manager for the duration of the Residential
Weatherization Program. This person will be responsible for all programmatic components of the
awarded grant. The Grantee will secure an adequate number of personnel (full and part-time, paid and
volunteer) to serve as outreach workers, intake workers, auditors, clerical support and
accounting/bookkeeping staff.
2. Written job descriptions will be on file for all of the above named positions. These job descriptions will
be on file regardless of the position’s funding source, full or part-time status, or paid or volunteer status.
3. An organizational chart for the grantee describing how the staff will fit into the overall agency structure
is required. The chart must identify job titles and reporting structures and must be kept on file by the
Grantee. This chart will be kept updated by the Grantee and a current copy will be provided to the grant
manager.
4. Any weatherization specialist and/or home energy auditor whose salary is paid in part or in full with
Residential Weatherization Program funds will not be allowed to complete the same or similar job
function with the Grantee as a contracted employee.
VII.1
5
Each Grantee must have an internal document that contains a Code of Standards of Conduct regarding
procurement procedures. This Code of Standards should describe specifically how the Grantee will
maintain segregation of responsibilities during the procurement and overall weatherization process. The
Grantee shall describe their policy regarding Nepotism (the act of favoring a related family member for
employment, or any weatherization services/work) in detail.
Outreach
1. The Grantee will conduct outreach activities designed to assure that households within the service area
are aware of opportunity to apply and what the eligibility requirements are. Concerted efforts must be
conducted for allowing qualified residents to be aware of assistance available under the Residential
Weatherization Program.
2. The Grantee will disseminate general information and brochures which will include the Grantee's
name, intake staff’s name and telephone number throughout the serviced area. Some materials will
be furnished by Urban Assistance’s staff, but may also be developed by the Grantee. All marketing
information developed by the Grantee must contain the UWI logo and be preapproved by the
assigned grant manager before distribution. A record of who and how the marketing information that
was distributed must be kept in a file identified as outreach activities. The file contents must be
organized by date of activity. The activity notes must specify where the activity was held, the date,
and time.
3. The Grantees are to contact the local officers of other specified agencies to coordinate
outreach/publicity efforts and to implement referral mechanisms.
4. It is expected that the Grantee contact other groups, clubs, churches, schools, and local units of
government to coordinate outreach/publicity efforts to the residents within the communities served.
5. The Grantee will develop news releases about the program (news releases must contain the Urban
Weatherization Initiative logo, general description, eligibility criteria, and application procedures, as
well as, the information to be provided to the applicant). All news releases or media
interview/contacts/events must be pre-approved by the assigned grant manager prior to any releases
to the media. A record of news releases and to whom they are sent must be kept and filed in the
outreach file to be presented to the monitor during monitor review.
6. The Grantee will contact other local agencies to arrange sites for intake, which are preferably
accessible to disabled persons and visible at the community level, within the serviced area.
7. The Grantee will contact local resources to arrange for interpreters as needed, e.g., second
language, signers. These could include county DHS offices and community
college/universities.
8. The Grantee will, where appropriate, conduct door-to-door canvassing to identify potential
applicants.
VII.2
Intake
1.
The Grantee will ensure that applicants are assisted as understood to be necessary.
2.
The Grantee may provide home visits to those potential applicants who, due to disability or lack of
transportation, could not otherwise file an application. Under exceptional circumstances, applications
may be taken by other means; however these procedures must be approved by the Grant Manager.
3.
The Grantee will develop a systematic approach to the intake, and application process. The Grantee
must provide notification to potential applicants of the application period 30 days before the applications
will be accepted. An outline of the intake and processing systems to be used by the Grantee will be
properly displayed for the public to view and kept on file.
4.
All brochures and advertisement must be pre-approved by the grant manager before dissemination.
Application Process
1.
No household may be denied the right to apply for Weatherization assistance.
2.
The Grantee will utilize the application form provided by the Office of Urban Assistance and
ensure that it is filed in each applicant’s file.
3.
The Grantee will assure that all applicants are provided assistance, when needed, for completing
the application form, and/or in obtaining required documentation as outlined by the Residential
Weatherization Program.
4.
The Grantee will ensure that the Residential Weatherization Program applicants Health and
Safety Intake Questionnaire are completed with the applicant at the time of the application.
5.
The Grantee will take and verify an application, make a determination of eligibility and notify
the applicant within 10 days from the date of application.
6.
The Grantee will assure that all applicants are informed of eligibility requirements. A handout
outlining this information will be provided.
7.
If applicable, the Grantee will provide assistance to Spanish speaking applicants in order to
ensure that they understand the application process and requirements.
8.
The Grantee will provide, as needed, communication assistance to households with individuals,
who are hearing, vision, or speech impaired or who have low literacy levels. The resources to be used
by the Grantee to assist the visually, speech, or hearing impaired will be kept on file by the Grantee.
VII.3
9.
The Grantee will verify income eligibility for all applications submitted as prescribed and defined
by the Residential Weatherization Program.
10.
The Grantee will designate the supervisor as the person who will make the final eligibility
determination for each eligible applicant.
11.
The Grantee will establish and maintain a filing and tracking system. Grantees are expected to
use classification folders and each action must be labeled with a table of contents. The method for
filing and tracking the applications will be kept on file by the Grantee.
12.
The Grantee will survey and identify energy conservation programs in its service area and
compile a resource directory that will be shared with all applicants.
13.
As appropriate, the Grantee will provide contact information to the Applicants for other benefit
and social service programs as administered by the federal government and this state, particularly
low income energy-related programs under Subtitle VI (relating to Community Services Block Grant
Program) under the Supplemental Security Income Program, under Part A of Title IV of the Social
Security Act, under Title XX of the Social Security Act, under the Low Income Energy Assistance Act of
1981 and the Illinois Energy Assistance Act of 1989, as amended, or any other provision of law which
carries out programs which were administered under the Economic Opportunity Act of 1964, which
may be beneficial to the families energy needs..
14.
The Grantee will secure written agreements with all agencies/organizations which assume any
of the following activities:
 provide facilities for intake sites
 provide outreach and/or intake services
The agencies/organizations which will be conducting any of the above noted activities will be
kept on file by the Grantee.
Contract Monitoring
Grant Agreement Enforcement:
When a Grantee repeatedly shows an inability or refusal to comply with applicable standards are grounds for
the Office of Urban Assistance to suspend, terminate or otherwise apply special condition(s) and a corrective
action plan to the Grantee’s grant agreements. Such administrative actions will be administered for the purpose
of ensuring weatherization services will be completed as agreed upon and prescribed by the Residential
Weatherization Program.
VII.4
Monitoring by Office of Urban Assistance
General Monitoring Procedure:
The assigned grant manager will conduct monitoring visits, at the discretion of the Office of Urban Assistance,
for the purpose of determining compliance with all Residential Weatherization Program Policies, Guidelines,
Rules and Regulations. These monitoring visits include but not be limited to; Quality Control Monitoring, File
Reviews, Audit Monitoring, Procurement Monitoring, Lead Safe Weatherization Monitoring, EPA Lead
Renovator Compliance Monitoring, Fiscal Monitoring, or any other monitoring deemed necessary by the Office
of Urban Assistance.
1. Quality Control Monitoring will evaluate the overall effectiveness of retrofits selected, safety practices,
workmanship, overall appearance and compliance with the Residential Weatherization Program’s policy
and procedures. This Monitoring will also evaluate the overall quality of the initial assessment. The final
evaluation of the home will be rated as either Acceptable, Acceptable with Recommendations, or
Unacceptable. The quality control monitoring will be performed by DCEO staff, as well as contracted
staff.
2. File Review Monitoring will evaluate the overall organization, completeness, and accuracy of the
grantee’s client files. These reviews will include documentation review and verification and will be
performed by the assigned grant manager.
3
Audit Monitoring will evaluate completed assessments in the field. Audit monitoring will also include
proper data entry and proper retrofit selection based upon the Savings-to-Investment Ratio (SIR) for
that property. The final evaluation of the audit will be rated as either Acceptable, Acceptable with
Recommendations, or Unacceptable. The audit monitoring will be performed by the assigned grant
manager or other DCEO staff.
4
Procurement Monitoring will evaluate the Grantee’s implementation of the Procurement Policy.
Procurement Monitoring will include but not be limited to; Contractor file reviews and material/labor
bid survey review. This review may also include a Weatherization Material and Labor price review. If
Urban Assistance determines that the procured prices are too high, those costs may be disallowed and
only approved up to an acceptable cost by DCEO standards.
5
Urban Assistance’s staff will review and ensure that staff of the Grantee provides
oversight to the data entry of certified payroll and conduct employee interviews to that
Residential Weatherization Program Compliance is adhered to at the contractor/crew level as developed
by RWP. This monitoring may also include data entry review of payroll information into any electronic
systems utilized for certified payroll. The grant manager will monitor for ensuring that Davis Bacon
wage compliance is maintained.
VII.5
6
Lead Safe Weatherization Monitoring will be conducted to ensure compliance with mandated Lead Safe
Weatherization Practices and training of such statutes.
7
EPA Lead Renovator (RRP) Compliance Monitoring will be conducted to ensure compliance with
mandated EPA Lead Renovator practices and training of such statutes.
Residential Weatherization Program– Monitoring Details






The dwelling units inspected will be selected randomly from a list of eligible clients that will
allow for a comprehensive sample of weatherization services being provided.
Monitoring visits may focus on problem areas as identified in previous monitoring visit reports
to ensure that prior deficiencies have been remedied.
Recommendations or required corrective action will be issued to grantees based on findings
identified during said monitoring visits and such requirements/recommendations will be
detailed on a monitoring visit report provided to the grantee.
Any measure or repair initiated by the Grantee that is not in compliance with the Residential
Weatherization Initiative’s policy and procedures will result in disallowed cost.
Deficiencies identified during Urban Assistance monitoring that results in Major findings or
repetitious Minor findings will be considered justification for re-inspection of the dwelling.
Continuous/systematic deficiencies identified by Urban Assistance will require immediate action
by the respective Grantee and the development of a corrective action plan, with designated
times frames to remedy identified and documented issues of non-compliance.
Findings Matrix
Minor Findings:




All areas of noncompliance with the Residential Weatherization Program policy and procedures
not considered Major will be referred to as Minor findings.
Minor findings may include but are not limited to substandard work, missing
attic insulation measuring sticks, incorrect documentation, etc.
Minor Findings will require a response from the Grantee, detailing the corrective action taken to
alleviate the deficiency identified, if specifically noted in the Monitoring Review Report.
When similar Minor Findings are found on two or more consecutive Monitoring Visits, those
Minor Findings will be elevated to Major Findings, and the grantee will be required to develop a
Corrective Action plan, or modify one which may already in effect.
Minor Findings could result in the requirement of additional training for the grantee and/or
contractor personnel, or other disciplinary actions leading up to termination.
VII.6
Major Findings:
1. Any of the following criteria constitutes a Major Finding;

The health and safety of clients, grantee’s staff and contractor/crew staff, or the structural
integrity of the building is compromised by the work completed with Residential Weatherization
Program Funds.

A health and safety problem is created by, exacerbated by, or not corrected by the delivery of
Residential Weatherization Program’s funded services.

The omission of a required procedure that addresses health and safety concerns that are within
the scope of weatherization.

Weatherization jobs that are paid for with Residential Weatherization Program Funds ; yet are
not applied to the dwelling.

Expenditure of Residential Weatherization funds for items that exceed the stated cost limits,
without prior written authorization by the Grant Manager.

Additional funds that exceed the cost limit specified will be considered as disallowed costs and
deleted from the line item cost of Residential Weatherization or refunded to the Residential
Weatherization Program. All fiscal files, records, and documentation must be revised
accordingly.

Poor quality workmanship that significantly affects the performance of weatherization
measures.

Expenditure of Residential Weatherization Program funds on Retrofit measures that are not
approved under RWP, or required for mitigation of health and safety concerns.

Expenditure of Residential Weatherization funds on Retrofit that were not approved and
identified in the scope of work.

Any action or lack of action that would threaten the integrity of the Residential Weatherization
Program and/or discredit its ethical standards.
A monitoring visit report from an Urban Assistance Grant Managers that contains Major Findings:


Requires an immediate response from the grantee receiving the finding as defined in the
Monitoring Visit Report generated by the Residential Weatherization Program. When feasible,
or construed to be necessary, a corrective action plan should accompany the grantee’s
response.
Requires that corrective action must be taken
VII.7

Could result in disallowed costs that the grantee would have to refund to Residential
Weatherization Program.
 Could result in an increased monitoring frequency by Urban Assistance grant manager.

Could result in the requirement of additional training for the grantee and/or grantee’s
contractor personnel as specified by the Residential Weatherization Program.

Could result in the recommendation of High Risk status or Grant Default Status for the grantee
receiving the Major Finding. Subsequently, special conditions will be placed on the grantee’s
grant agreement(s).

Continued Major Findings may result in the termination of the grantee’s grant agreement with
DCEO.
High Risk Status or Grant Default Status:
 The occurrence of a substantial number of, or repeated, Major Findings may result in a decision by
the Grant Manager to place a grantee on High Risk status or Grant
Default status.
 If a grantee is placed on High Risk status or Grant Default Status, special conditions will be placed on
the grant which will affect their ability to receive Residential Weatherization Program funds. Those
special conditions will include but not be limited to additional reporting requirements as specified by
the Residential Weatherization Program and a detailed corrective action plan to remedy monitoring
deficiencies and limited or total restrictions on the availability of cash requests from the appropriate
Residential Weatherization Program grant, or all RWP funding.
 If a grantee is placed on High Risk status or Grant Default Status, the grantee will be placed on
probationary status for up to two years following the date of the probation period initiation.
 Failure to comply with the special conditions placed on the grant agreement and/or continued noncompliance or Major Findings will be grounds for termination of the grant agreement between the
grantee and DCEO.
 After failing to comply with the Residential Weatherization Program grant conditions, or the
correction of grant deficiencies, an administrative meeting will be convened between grantee and
the Grant Manager.
VII.8
 Notwithstanding any of the above, Urban Assistance may suspend or terminate a contract without
prior written notice upon a finding of substantial non-compliance or substantial breach of grant
agreement.
Additional Requirements
1. The Grantee will comply with all other program components outlined by Residential Weatherization
Program’s policy and procedures.
2. If a materials inventory is utilized, a first-in, first-out perpetual inventory system must be used by the
Grantee to track and account for all weatherization materials. The inventory should be carried as an
asset on the fiscal records of the Grantee, and adjusted as used for the residential weatherization
completion of an applicant’s dwelling. A physical count of all inventory, including hand tools and
equipment, is to be done once per quarter to verify the accuracy of the physical count of the perpetual
inventory record. This must be filed and presented to the Grant Manager during the review.
3. The Grantee will weatherize homes according to the guidelines and agreement established by the
Residential Weatherization Program to ensure the highest quality of work and most efficient energy
conservation measures are conducted.
4. Additional sub-contractual agreements are prohibited, with the exception of labor to install
weatherization materials without the prior written approval from Urban Assistance Administrative staff.
5. The Grantee will ensure that approved bidding procedures are followed when purchasing materials and
procuring labor under this work statement. These procedures are outlined by the Residential
Weatherization Program.
Quality Control
The Grantee will ensure that services agreed upon through grant agreement with the Residential Weatherization
Program are provided in a quality manner. Specific procedures to monitor review and evaluate assessments,
workmanship and, audit and post-work audit will be on file for review.
Production
The grantee will weatherize all homes assigned for weatherization, and utilize allocated funds made available via
Residential Weatherization Program for each respective RWP grant. The grantee agrees to spend all budgetary
funding within the designated county as identified by the Residential Weatherization Program.
VII.9
1. The Grantee will weatherize an appropriate number of homes to utilize all funds made available by
each Residential Weatherization Program Grant. The grantee will ensure that funds are spent in the
county to which they were allocated.
2. The Grantee will submit a production plan as specified in the awarded Grant. The production plan will
provide specificities, and agreement to revise the plan on record with the Residential Weatherization
Program as needed or required by RWP.
Production-Related Costs
1. The Grantee will not exceed $6,500 on “Weatherization” work on any home weatherized. Costs per
completed unit shall include program support costs and actual costs of materials and labor applied.
2. The mechanical costs for a weatherization unit may not exceed $2600. The Mechanical costs for a unit
that contains a boiler or conversion/gravity heating system replacements may not exceed $3200.
Mechanical costs for an Energy Related unit may not exceed $3,500. In certain instances such as a
home with no existing ductwork, or an existing boiler system with complete radiator and pipe
replacement, a case-specific cost waiver must be applied for through the Office of Energy Assistance.
Expenditures in excess of the amounts listed above will result in disallowed costs.
3. The Grantee agrees not to exceed the maximum per unit costs for the weatherization which has been
established in writing by the Residential Weatherization Program. Exceptions to this policy will not be
honored, unless a written waiver has been obtained from the assigned grant manager.
4. Administrative funds will be earned at a final rate of the amount of the grant that was properly
expended. For example: If a grantee was only able to complete 80% of a grant’s production, they
would only be able to receive a total reimbursement of 80% of the administrative funds for that grant.
Performance
The Grantee will provide complete weatherization services to all eligible households throughout the
identified service areas. This will be a critical factor in evaluating the overall performance of the Grantee
under the Residential Weatherization Program. The Grantee will ensure that required efforts and provisions
are made to recruit and provide weatherization services to all eligible households throughout the targeted
service area. These activities of the Grantee will serve as an instrument to effectively measure overall
performance of the Grantee.
General Residential Weatherization Requirements
1. Under no circumstances is the Grantee to complete the Architectural portion of a home without first
making certain that there are no fuel leaks are present, the heating system is operating safely
and/or the water heater is properly venting.
VII.10
2. No Weatherization material is to be left at the job site for the client to install. If a weatherization
material cannot be installed, notation is to be made on the Work Order as to why installation was
not possible. Uninstalled material is to be returned to the warehouse or vendor with a credit for
the material made to the Residential Weatherization Program.
3. Weatherization waste byproducts should be remediated on a daily basis and are to be removed
from the job site once the work is completed.
4. The Grantee will ensure that the Grant Manager is provided an accounting journal that has
completed entries of all current negotiated/competitive prices for all materials and labor. The
Accounting Journal’s entries should adhere to the following:
a. Not have reference to installation of storm doors. Storm doors are not to be installed in
the program.
b. Reference replacement windows, doors, and storm windows as Retrofit Measures, not
as Health and Safety or Air-Sealing Measures. All windows (including storm
windows/inserts) must receive a positive Savings to Investment Ratio greater than a
value of “1”.
5. All duct work (except duct insulation as a Retrofit) is considered an Incidental Repair Measure and a
mechanical cost.
6. Switching primary fuel sources can only be done after approval in writing is provided by the assigned
grant manager
7. When primary sashes (on a site-built home) are not assessed for replacement or when the
window did not receive a positive SIR (greater than “1”) for replacement, the check rails of
the window at the point of the sash lock shall meet and be flush.
8. This may require that the lower sash be planned on the bottom to allow the checkrails to be flush
with one another at the sash lock. It is prohibited to shim and “space” sash locks.
9. If rolled metal is used for the heat barrier on attics insulated with cellulose, the barrier must be
fastened securely to the attic joist in such a manner as to not allow the barrier to collapse and
touch the heat source. Batt insulation may not be used as a heat barrier. All heat barriers must be
anchored in such a manner as to provide a three-inch air space between the barrier and the heat
producing source.
10. Duct repair refers to situations where major duct work installation is required to balance the heat
delivery of the furnace. This usually occurs when a replacement furnace is installed and the existing
duct work is oversized or major pieces of the duct system are missing. Duct repair includes supply
and return air registers. Duct replacement with the installation of a new furnace is considered as
part of the overall Retrofit measure costs. Duct installation on an existing HVAC system is
considered as an Incidental Repair measure and is subject to the appropriate limits.
VII.11
11.
Electrical refers to the installation of electrical wiring needed to allow the installation of
insulation. The installation of electrical wiring includes all junction boxes and conduit needed to
complete the work. All electrical work must be completed by a certified electrician.
12.
Plumbing refers to the installation or correction of plumbing problems that may cause any
weatherization measure not to be installed. Plumbing also includes the repairing of the plumbing
pipe if the water or sewage is backing up and creating a moisture problem for installed
weatherization material.
13.
Roof refers to the replacement or repair of roofing so that insulation may be installed.
Limitations do apply. Please contact your assigned grant manager for prior approval.
14.
Water heater work refers to no fuel leaks are present and the water heater is properly
venting.
15. New furnaces installed by the Residential Weatherization Program are to have the flue gases
checked for Carbon Monoxide and Oxygen after installation and the tape of the Post-test included in
the client file and taped to the gas appliance. These two (2) measurements will indicate whether
the new furnace is operating to manufactured specifications. The heating system efficiency and
Oxygen percentages will vary depending on the individual manufacturer and system design
specifications. On new heating system installations, the PMI manual is to be attached to the HVAC
system, and available for inspection. Furnace filter racks are to be installed in accordance with the
system’s PMI manual.
90 Plus Furnace Installations – 90 plus heating systems will be installed only as 2-pipe systems with
separate exterior combustion air intake and flue gas exhaust. The Oxygen (O2) and Carbon
Monoxide (CO) measurement will be taken at the flue on the outside of the house. Normally the
furnace will be side-vented through the foundation of the home. If the furnace is vented through
the roof and it is difficult to access or hazardous, the flue test may be omitted. When the flue has
been drilled, the hole is to be sealed with high temp RTV sealant, nylon plug, or butyl-backed
Adhesive tape. Standard adhesive aluminum tape is not to be used. In cases where
The Oxygen and/or Carbon Monoxide measurements do not fall within the perimeters established by the
manufacturer, the mechanical contractor is to correctly adjust the furnace to proper specifications.
80 Plus Furnace Installations: The Carbon Monoxide (CO) measurement will be taken at the furnace, unless the
manufacturer specifies that drilling the flue will invalidate the warranty. No draft test is needed on these power
vented systems. 80% furnaces may only be installed with a waiver from the assigned grant manager.
Appropriate forms, documentation, and digital photos are required. The maximum material cost for the 80%
furnace may not exceed $750.
VII.12
SECTION VIII
ASSESSMENT
ASSESSMENT
Assessment Overview
The assessment is one of the most important steps in the weatherization process. It
is the first point at which the agency enters the client's home and determines the structural
condition of the home. The auditor’s job is to conduct a thorough review of the home so that the
weatherization measures to be installed will save the most energy, while ensuring the health and
safety of the household.
During the process of conducting an audit of the home, both the architectural and the HVAC system
is required to be done at the same time.
Required Color Digital Photographs
Digital color photos are required to be taken and placed in the Residential Weatherization Program
Applicant’s file under the contractor's section. Photographs of all sides of the home, including
specific photos of all windows and doors are mandatory. Photos should also document any
problematic areas that the contractor must address. Color photos of any problem areas are to be
attached to the work order so the contractor can review them. Digital, color photos must also be in
the file for any retrofit or other measures that is assessed to be replaced.
When a change order is requested by the contractor, color digital photographs are required to
support those changes. The photographs must clearly document the need for change and have to
be affixed to the change order with legible copies in the Applicant's file.
Required Floor Print
An accurate illustration of the homes footprint must be drawn by the assessor for each level of the
home, including the basement and attic. All footprints must be placed in the Applicant's file under
the contractor's section. All doors and windows must be identified on the foot print and labeled as
specified. Un-conditioned spaces must be noted on the footprint with dashed lines (i.e. unconditioned porches, attached garage, etc). Accurate directional orientation must be labeled on the
footprint as well.
•The identification of doors must start with the front door of each home. Continue labeling the
doors in order counter clockwise around the home. The labeling convention for doors must be in
the following format:
1. The first character identifies the living level of the home
2. The second character identifies the reference item i.e. door(D) or window (W), etc.
3. The third and fourth characters will represent specific item on that living level of the home, for
example:
BD01= basement door 1.
1DO3= first level door 3.
2DO2 = second level door 2.
 The identification of windows must start with first window to the right of the front
door represented as 1DO1. Continue labeling the windows in order
counterclockwise around the home.
VIII.1
4. The second character identifies the referenced item (i.e. door(D) or
window(W), etc.
5. The third and four character represents specific item on that living level of
the home. For example:
BWO1=Basement window 1.
1WO6= First level window 6.
2WO2= Second level window 2.
Exterior Inspection
 Inspect home for site drainage problems.
 Inspect walls for cracks, holes, or any other air sealing opportunities that may be present. Moreover,
photographs must be taken of all Air Sealing opportunities on the exterior of the home ( i.e. holes in
the foundation, electrical penetrations to be addressed, etc). Photographs are required for all
preexisting damages to the home (i.e. damage siding, broken glass, etc).
 Drill an inspection hole on each side wall (under the siding) to determine if walls have existing
insulation. Inspection holes may be drilled in an inconspicuous location on the inside of the home,
such as a closet on an exterior wall. All inspection holes drilled on the interior of the home shall be
noted and repaired by the contractor.
 Inspect foundation for above grade measurements. Check foundations for cracks and/or utilitiy
penetrations for air sealing opportunities that may be present.
 Inspect crawlspace (when accessible for the exterior), if applicable, to identify retrofit, incidental
repair or air sealing measures needed. For example, identify the need for rim joist or crawlspace wall
insulation, vapor barrier, etc. Photographs are required for verification.
 Record identifying information fr0m central air conditioner and/or window air conditioning units, if
applicable. Information required for central air units is make, model, age, SEER rating, size (tons).
Information required for window air conditioning units is make, model, age, EER Rating, size (BTUs).
it may be necessary to inquire with the homeowner regarding window air conditioners that are not in
place dependent upon the current season. A photograph of the central air conditioning and/or
window unit must be included in the applicant's file.
Interior Inspection
The objective for the interior inspection is to obtain information specific to the home's
thermal performance and identify potential energy saving opportunities that can be
addressed during the weatherization process. Following are the steps required for
conducting an interior inspection:
 Make a visual inspection walk through of the home. During the walk
through, the auditor must identify the thermal boundary, noting the
structural integrity of the interior walls and identify obvious air sealing opportunities. Note:
the thermal boundary is the separation of conditioned space from un-conditioned space.
 Measure the doors identified during the exterior inspection of the home that are a part of
the thermal boundary. All required Air Sealing, Incidental Repair and Retrofit measures must
be documented.
 Measure the windows identified during the exterior inspection of the home that are part of
the thermal boundary. All required Air Sealing Incidental Repair and Retrofit must be
documented.
VIII.2
 Inspect the attic, finished/unfinished, for existing insulation and determine the existing effective rvalue(s).
o
Unfinished attics (Open joist or Floored joist): Document the additional insulation needed in the
attic based on the existing r-value. If Knob and Tube wiring exist, testing is required to
determine if lines are active. Document the presence of active Knob and Tube wiring, if
applicable, and the need for additional attic insulation. The attic foot print and pictures of the
attic are required. This information is to be filed in the Applicant's file under the contractors
section.
o
Finish Attics: identify the finished attic building components that make up the thermal
boundary (i.e rough rafters, Outer Ceiling Joist, Kneewall, Collar Beam) and the existing
insulation. Identify and document the insulation opportunities in all applicable finished attic
components. if a Knob and Tube wiring exist, testing is required to determine if lines are active.
Document the presence of active Knob and Tube wiring, if applicable, and the need for
additional attic insulation. The attic foot print and colored photographs of the attic are
required.
 Unfinished attics (Open joist or Floored joist): Document the additional insulation needed in
the attic based on the existing r-value. If Knob and Tube wiring exist, testing is required to
determine if lines are active. Document the presence of active Knob and Tube wiring, if
applicable, and the need for additional attic insulation. The attic foot print and pictures of
the attic are required. This information is to be filed in the Applicant's file under the
contractor’s section.
 Finished Attics: Identify the finished attic building components that make up the thermal boundary
(i.e rough rafters, Outer Ceiling Joist, Kneewall, Collar Beam) and the existing insulation. Identify
and document the insulation opportunities in all applicable finished attic components. if a Knob and
Tube wiring exist, testing is required to determine if lines are active. Document the presence of
active Knob and Tube wiring, if applicable, and the need for additional attic insulation. The attic foot
print and colored photographs of the attic are required.
 Inspect the basement for existing conditions (if applicable), i.e. water problems, existing
insulation, etc. Document all potential air sealing incident repair(s) and/or retrofit measures. Note
the obvious bypass on the foot print. Basement bypasses must be identified by hanging surveyor’s
tape below the bypass location from the floor joist or near the leakage area in the rim joist.
 Inspect the crawl space for existing condition (if applicable and accessible), i.e. water problems,
existing insulation, etc. Document all potential air sealing, incidental repair(s) and/or retrofit
measures. Note the obvious bypass on the footprint. Basement bypasses must be identified by
hanging surveyors tape below the bypass location from the floor joist or near the leakage area in the
rim joist.
Building Diagnostics
Building diagnostics are crucial to the homes thermal performance. Identifying and sealing bypasses
may have the biggest impact on the homeowner's energy usage. Building diagnostics also identifies
potential risks to the home's occupants due to the tightness of the home and the potential indoor
air quality issues that can stem from the lack of fresh air. Following are the steps required for
conducting the Building diagnostics:
VIII.3
 A blower door test is required on every home. Run the lower door and record the CFM50 rate. A
picture of the blower door set up and a picture of the manometer reading are mandatory and must
be included in the applicant's file, in the appropriate section.
 With the blower door running, identify all bypasses that need to be addressed and the measures
required to effectively seal the bypasses. Document the bypasses, again bypasses must be marked
with surveyor's tape in attic sections, basements and crawlspaces. It may be necessary to go back
into the attic to identify leakage areas. Pressurizing the home, changing the direction or flow of the
fan, can assist in identifying attic bypass locations. Observe the home with an infrared camera as
well as using smoke pencils or chemical smoke to help identify insulation deficiencies and bypass
locations.
 Duct pressure pan readings are mandatory in homes with ductwork that extend through
unconditioned spaces. Record pressure pan readings for each register. If the duct pressure pan
readings are not within the allowable limits, record the measures necessary to correct the duct
leakage as well as installation opportunities.
 Zone pressure tests must be conducted in all applicable zones such as attic, crawl space, attached
garages, etc. Record the zone pressure readings, as well as the action needed in order to seal the
thermal boundary between conditioned and un-conditioned spaces. Note: Conducting these tests
should confirm the location of the thermal boundary.
 By pass locations and corrective measures must be detailed by the auditor.
Health and Safety
Health and safety is the number one priority in the Residential Weatherization Program. During the
assessment, the auditor may encounter a variety of hazardous health and/or safety conditions.
These hazardous conditions are classified as either "immediate" or "potential" depending on their
severity and must identified. The Urban Weatherization Initiative will allow the use of funds to
abate specific types of health and safety hazards that may exist in dwellings to be weatherized, as
long as it is directly related to the weatherization of the home. The following are the steps required
for identifying a home's health and safety needs:

All appliances must be inspected to ensure compliance.

All homes must be inspected for placement and proper operation of Carbon Monoxide detectors and
smoke detectors.

Inspect for proper installation of exhaust fans. All exhaust fans must be vented to the exterior of the
home. Exhaust fan vents that run through un-conditioned spaces must be insulated.

Measure the exhaust fan flow rate of the existing vented exhaust fans in order to determine the
required ventilation for the dwelling if ASHRAE 62.2 is required.

Using all pertinent data required per ASHRAE 62.2, determine the required ventilation rate for the
dwelling to ensure compliance with ASHRAE 62.2.

All homes must be reviewed for bulk moisture and/or mold problems. The Mold and Moisture
Checklist must be completed, signed and placed in the applicant's file in the appropriate section.

Any existing un-vented space heating appliances must be removed from the premises prior to
weatherization services proceeding. A Hazardous Conditions Form must be completed to make the
applicant/ homeowner aware of the issues. If the applicant refuses to allow the removal, the home
must be deferred, which will be discussed in the next section.
VIII.4
Immediate and Potentially Hazardous Conditions
During the assessment, the Auditor may discover a variety of hazardous health and/or safety
conditions. These hazardous conditions are classified as either "immediate" or "potential"
depending on their severity. They are defined as follows:
Immediate Hazard Conditions: Conditions that reasonably represent an immediate risk of harm
to person or property.
Potentially Hazardous Conditions: Conditions that reasonably represent a potential risk of harm
to person or property.
All conditions an Auditor believes constitute an immediate or potential risk to an individual or
property, shall be documented on the Hazardous Conditions Form listed in the Exhibits section at
the time of an audit and a copy given to the applicant and landlord, if applicable. The original copy
of the Hazardous Conditions Form must be included as part of the client file.
IF AN IMMEDIATE HAZARD IS DISCOVERED, NO WORK, ARCHITECTURAL OR MECHANICAL,
IS TO BE DONE ON THE UNIT UNTIL THE IMMEDIATE HAZARD HAS BEEN CORRECTED! IF
THE HAZARD CAN BE CORRECTED, AS AN ALLOWABLE RESIDENTIAL WEATHERIZATION
PROGRAM EXPENDITURE, THE HAZARD REMEDIATION WILL TAKE PRIORITY!
The following listing is examples of Immediate and Potentially Hazardous conditions. This list is not
an all-inclusive list of hazards that an auditor may encounter during an assessment, but should be
used as a guide for use during an audit to notify applicants and landlords, if applicable, of hazards
that presently exist in a building.
General
Immediate Hazards
1. Single wall vent going through wall or floor
2.
3.
4.
5.
6.
7.
8.
Outside vent terminating 2 foot above grade (conventional appliances)
Single wall vent less than 6" from floor joist
Dryers exhausting into chimney
Vent connectors not vented to proper chimney
Gas leaks
Missing or capped/sealed Water Heater T&P valve
Ambient Air C.O. reading greater than 25 PPM
Water Heater
Immediate Hazards
1.
CO reading above 100 PPM in vent
2.
3.
4.
5.
6.
7.
Draft less than 2 inches negative water column reading in vent
Water heater burner less than 18 inches off garage floor
Insufficient secondary air in the Combustion Appliance Zone (CAZ)
Two draft hoods on water heater or furnace
Missing or reduced discharge pipe off T&P valve
Water Heater in a bathroom (with door closed and water heater operating)
VIII.5
8.
9.
10.
11.
12.
13.
T&P valve located in a branch line, more than 6 inches from the top of the
tank or in a cold water line on a water heater designed without tap
Combustion air coming from a bathroom, bedroom or sleeping quarters
All doors, panels and drawers not in place
Water Heater not vented
Draft hood not in same room as appliance
Discharge pipe more than 6 inches off the floor and/or threaded on the bottom
Potential Hazards
1.
2.
No manual shutoff on fuel line
Improper pipe for gas line (copper for natural gas, or galvanized water pipe).
Heating Equipment
Immediate Hazards
1. CO reading above 100 PPM in vent
2. Draft less than 2 inches negative water column reading in vent
3. Cracked heat exchanger
4. Unvented combustion space heater in interior living space
6. Gas vent extending through an exterior wall of a building
7. Cold air return terminating at furnace (within CAZ)
8. Defective limit control or no limit control
9. No safety interlock between heating equipment and power exhauster
10. Combustion air coming from bathroom, bedroom, or sleeping quarters
11. All doors, panels, and drawers not in place
12. Heating system is Not vented
13. Draft hood not in same room as heating equipment or draft hood is inverted
14. Venting system blocked, rusted, disconnected, or not sealed
15. Solid fuel-burning appliance vented into type "B" or "BW" gas vents or into a chimney
above any gas burning appliance
16. Heating equipment less than 18" off garage floor
Potential Hazards
1.
2.
3.
4.
No manual shutoff on fuel line
Venting not properly supported
Venting connections not screwed together
Improper pipe for gas line (copper for natural gas, or galvanized water
pipe).
Gas Ranges
Immediate Hazards
1.
2.
3.
4.
Connector not in same room
Missing doors, panels, and drawers
More than one flex connector in series
CO reading in ambient air above range above 25 PPM
VIII.6
Potential Hazards
1. Improper gas/air adjustment causing discoloration around burners
2. Possible gas line located behind electric range
3. Improper pipe for gas line (copper for natural gas, or galvanized water
pipe) Sediment Traps
Gas lines supplying gas appliances that do not leak are to be left in place without modification.
When installing new gas appliances a sediment trap may be installed.
Flexible Gas Line Connectors
Gas lines supplying gas appliances that do not leak are to be left in place without modification.
Install a flexible gas line connector when an existing connector is leaking gas. Flexible gas line
connectors are not to be installed on water heaters or furnaces.
Gas Line Replacement
Gas lines of gas appliances that do not leak are to be left in place without modification. Replace gas
lines only in cases where the gas line is leaking. When replacing gas lines use black pipe of the
correct diameter to allow adequate amount of gas to appliances. Flexible gas pipe (Trac Pipe, etc.) is
to be used only in crawlspace areas where installing black pipe is not feasible.
Any gas line that is leaking or damaged, is considered an Immediate Hazard and must be remedied.
This includes black pipe, copper, galvanized, etc.
Any functional, but improper type of gas piping, such as copper used in natural gas lines, galvanized,
etc. is considered a Potential Hazard. This condition should be noted on the Hazardous Condition
Form and a copy of this form should be given to the client, owner of the building, and grantee. Total
copper gas line replacement is not an allowable Residential Weatherization expenditure.
The type of work allowed under the Residential Weatherization Program’s Health and Safety P shall
include:
Inspection and Testing of Combustion Appliances
•
Checking combustible fuel lines for leaks for all combustion appliances. This
includes the heating appliance, water heater, and gas dryer.
•
Performing a flue gas analysis test on the heating appliance, gas stove, and
water heater to determine the parts per million of carbon monoxide and
ensure adequate draft in both the heating appliance and water heater vent
pipes.
IF A HIGH LEVEL OF CARBON MONOXIDE IS FOUND TO BE PRESENT (over 100 ppm) IN THE
WATER HEATER OR FURNACE VENT, THEN THE APPLICANT SHOULD BE NOTIFIED THAT THE HOME
CANNOT BE WEATHERIZED UNTIL THE WATER HEATER, OR GAS APPLIANCEIS REPAIRED OR
REPLACED. AT THAT TIME, THE TESTS WILL BE RECONDUCTED AND WEATHERIZATION WILL
PROCEED, IF THE CO LEVELS ARE ACCEPTABLE.
Smoke Detectors
At least one smoke detector will be installed on each level of the home. The costs of installing these
units will be charged to Health and Safety costs.
VIII.7
Smoke Detector Specifications
1. Ionization and photoelectric smoke detectors that are powered by a 9 volt battery and
emit a signal when the battery is losing power are required.
2. The unit is to include a screw mounting bracket; all installation hardware
is to be included.
3. The product is required to be approved by the Underwriters Laboratory.
CO Detectors
CO detectors shall be installed according to the manufacturer's recommendations on
every job where fuel-burning appliances are present. Detectors are required to be purchased by the
owner.
Moisture Control
Excess moisture will be controlled by implementing the following measures:
1. A visqueen ground cover is required in all accessible crawlspaces.
2. Exhaust fans in kitchens and bathrooms shall be replaced when necessary.
Worker Protection
The Health and Safety Plan also allows for worker protection and training that includes:
1. Provide safety training for auditors.
2. Require documentation from contractors that their workers received
training on safety issues associated with weatherization.
3. Requiring material suppliers to provide Material Safety Data Sheets for their products.
Fire Extinguishers
The installation of Fire Extinguishers is not an allowable expenditure.
Gutters and Downspouts
The installation of gutters and/or downspouts is not an allowable expenditure.
Gutters and
downspouts can only be replaced if they are associated with the weatherization work being
completed on the homes.
Deferral/Walk-Away Policy
The decision to defer work in a dwelling or, in extreme cases, provide no weatherization services, is
regretful but necessary in some cases. This does not mean that assistance will never be available,
but that work must be deferred or postponed until the problems can be resolved. Grantees are
expected to pursue all reasonable options on behalf of the applicant.
Deferral conditions may include but are not limited to the following:
1.
The applicant has known health conditions that prohibit the installation of insulation and/or
other weatherization materials.
2.
The building structure or its mechanical systems, including electrical and plumbing, are in
such a state of disrepair that conditions cannot be resolved in a cost effective manner.
3.
The home has sewage or other sanitary problems that would further endanger the client
and weatherization installers if weatherization measures were installed.
VIII.8
4.
5.
6.
7.
8.
9.
10.
11
12.
13.
The home has been condemned or electrical, heating, plumbing, or other
equipment has been "red tagged" by local or state building officials or utilities.
Moisture problems are so severe they cannot be resolved under existing
allowable health and safety measures or with minor repairs.
Dangerous conditions exist due to high carbon monoxide levels from
combustion appliances, and cannot be resolved under existing health and safety
allowable limits.
The client is uncooperative, abusive, or threatening to the crew, subcontractors,
auditors, inspectors, or others who must work on or visit the house.
The extent and condition of lead-based paint in the house would potentially
create
Further health and safety hazards for the applicant or workers and could not be
corrected with Weatherization.
Illegal activities are being conducted in the dwelling.
Client has an unvented space heater and refuses removal of the unit prior to
weatherization services being conducted.
Applicant refuses installation of any weatherization measures that have been
approved and eligible for the Residential Weatherization Program.
Any other health or safety condition present or created by, exacerbated by, and
cannot be corrected by the delivery of Residential Weatherization Program
funded services.
When a Grantee determines that invoking the Deferral Policy is necessary, the following steps must
be followed;
1.
When a situation exists that causes the deferral of work, the applicant must be notified
within 48 hours in writing via certified mail stating the reason(s) for invoking the Deferral
Policy. In addition, a copy must be forwarded to the grant manager within 48 hours.
2.
The Grantee is required to notify the applicant that work may proceed if the reason(s) for
deferral are properly remedied. The resident is required to contact the Grantee upon
completion of such remedies. When the matters have been mediated, the resident is
required to provide proof of remediation to the Grantee before work can begin.
VIII.9
SECTION VIII
ASSESSMENT
EXHIBITS
Notice of Hazardous Conditions Form
Moisture/Mold Form
Urban Weatherization Initiative
RESIDENTIAL WEATHERIZATION PROGRAM
NOTICE OF HAZARDOUS CONDITION FORM
Name _______________________________
Job# ______________________________
Address _____________________________
City _________________________________
Date_______________________________
Phone _______________________________
Time ______ a.m.______ p.m.
Fill out the appropriate section:
The condition described below presents an IMMEDIATE HAZARD*
and must be corrected by a competent repair person.
________________________________________________________________
________________________________________________________________
________________________________________________________________
The condition described below presents a POTENTIAL HAZARD
under certain situations. This condition should be corrected by a
a certified technician or journeyman repair person.
________________________________________________________________
________________________________________________________________
________________________________________________________________
* NO WEATHERIZATION WORK CAN BE PERFORMED UNTIL
THE HAZARD IS CORRECTED.
PLEASE CALL THIS OFFICE AT ____________________ AFTER
CORRECTIONS HAVE BEEN MADE TO RESCHEDULE THE
AUDIT.
Owner's Signature _________________________________________________
Auditor’s Signature _________________________________________
Original - Client
Copy - Client File
THIS PAGE HAS INTENTIONALLY BEEN LEFT BLANK
Dwelling Assessment: Moisture and Mold Checklist
Applicant: _______________________
Address: ________________________
Date: ____________________
I. Winter Moisture Problems
Are there signs of excess moisture in the winter, leading to mold and staining?
A. Exterior wall in closets. (Move belongings as required.)
B. Behind beds, sofas, and heavy drapes on exterior walls.
C. Wall/Ceiling juncture on exterior walls.
D. Moisture damage on roof sheathing (attic).
E. Excessive condensation on interior window frames
Total:
If yes to any location A thru D, can the location be insulated to prevent condensation?
Potential Actions: 1. Add insulation to eliminate chilled surfaces whenever possible.
2. Reduce moisture sources whenever possible. See Section II.
3. Do no air sealing unless 1 and/or 2 addressed.
II. Moisture Sources
Check for excess moisture sources. Address the sources as required.
A. Is there an efficient bathroom exhaust fan?
B. Is the clothes dryer vented to the exterior?
C. Is there a kitchen exhaust fan?
D. Is there an uncovered dirt crawl space?
E. Is there signs of water infiltration into a basement?
F. Is the house overcrowded?
G. Is there a humidifier operating during the winter?
Yes
No
Action Taken
Yes
No
Action Taken
Potential Actions: 1. Reduce moisture sources by adding local exhaust ventilation, covering
crawl spaces, disconnecting humidifiers, solving foundation moisture
entry.
III. Bathroom Mold
A. Is there excessive mold on bathroom walls and ceilings?
B. Does it appear that the tub/shower surround is leaking?
Potential Actions: 1. Install efficient bathroom fan and controls.
Yes
No
IV. Bulk Moisture Problems
Is there mold or water damage from the following bulk water entry areas?
A. Plumbing (Check bathrooms, kitchen, and laundry area)
B. Roofs (Check ceilings in all rooms)
C. Window or Door leakage (Check walls around openings)
D. Basement and crawl spaces (Dampness and water entry)
Yes
No
Action Taken
Potential Actions:
1. Make repairs to eliminate leaks if practical.
2. Address exterior drainage to improve foundation dryness
(See Section V).
V. Exterior Improvements for Foundation Moisture
A. Is there a functioning gutter system?
B. Are repairs required to improve drainage away from house?
Yes
No
Action Taken
Potential Actions:
1. Repair gutters, downspouts, and leaders to assure drainage away.
2. Perform minor grading to relieve foundation water entry.
VI. Notifications and Official Business
Assessor’s Signature: ______________________________________________________
Date: _____________________________
THIS PAGE HAS INTENTIONALLY BEEN LEFT BLANK
SECTION IX
POST-WORK AUDIT
SECTION IX
POST-WORK AUDIT
Every home weatherized must have a Post-Work Audit. The home cannot be considered complete
until the post-work audit has been successfully completed. The Post-Work Audit is to be conducted
as thoroughly as the initial home energy audit. Keep in mind post-work auditors not only are
evaluating the quality of the work, they are also checking the quality of the original audit. Post-work
auditors should look for problems that the crew or contractor may have to correct and check for the
installation of materials that meet the specifications as identified in Section XIV. As part of the postwork audit process, the applicant's satisfaction survey should be given to the resident. The survey
will solicit the applicant’s suggestions and/or concerns regarding the services provided.
Considering the potential for vandalism, weather-related damage and safety problems, it is required
that the post-work audit be done on each unit within twelve (12) working days after all
weatherization work is completed. The post-work audit cannot proceed until the Work Order and
support documentation for work completed has been returned to the Grantee by the contractor. As
such, the contractor must submit all documentation to the grantee within 2 working days after the
work is completed. The Grantee is then responsible for completing the post-work audit on the
home within ten working days.

To ensure an objective post-work audit is completed on every home, the staff member
performing the post-work audit cannot be the same person who completed the initial Home
Energy Audit. Under no circumstances, may the post-work audit be done by any person
who performed the work. If it is determined during the post-work audit that the job was
not completed properly, then a call-back must be ordered on the contractor, who will
perform the additional work at no extra charge.
The Post-Work Auditor’s job is to ensure the following:
 The initial Auditor has correctly evaluated each residence in accordance with the
Residential Weatherization Program’s procedures.
 The work completed has been accomplished to a "workmanlike standard" in accordance
with the quality control standards and specifications set forth by the Residential
Weatherization Program.
 Materials applied, labor hours, and actual costs for the unit are accounted for and entered
by the crew/contractor on the architectural and mechanical work orders.
 The completed work is checked off by the crew/contractor on the Work Order for
architectural and mechanical work; and the mechanical contractor checklist is
completed.

A post-work efficiency test with the flue gas analyzer (if applicable to the fuel source) is
conducted on the heating system, and entered on the Post-Work Audit form. A final
diagnostic reading with the blower door must be taken at the time of the post-work audit
and compared to the initial readings to validate the work has been completed satisfactorily.
IX.1

If the fuel source is natural gas, the meter must be clocked and measured input entered on
the Post-Work Audit Sheet.
Evaluating the Initial Audit
Reviewing the Audit Document
The Post-Work Auditor must review the Home Energy Audit Form to verify the initial audit was
conducted properly. Any section of the audit document not completed indicates the Initial Auditor
did not complete a full audit. Notations must be made by the Post-Work Auditor on the audit
document as to why a section of the audit was not completed. In cases where the Auditor did not
complete a full audit of the unit, the Post-Auditor is to return the audit document to the supervisor
of the initial Auditor for completion of the audit.
If a Change Order is required a supplemental Change Work Order is then generated to address
missing weatherization measures. The supplemental Change Work Order is to be attached to the
original Work Order and becomes part of the Client File.
The weatherization crew/contractor is provided the Change Work Order to complete any additional
measures identified to be installed. In instances where no program funds remain to complete the
needed measures the Grantee will pay for the measure with agency funds.
Required Documentation Review Prior To Final Inspection
The Post-Work Auditor must insure the weatherization crew/contractor has submitted all of the
required documentation regarding the work completed before the post-work audit may begin. This
will require the post-work auditor to complete a file review for the documents. If any of the
required documents are not in the client file the crew/contractor is to be notified as the post-work
audit of the home cannot be completed until the missing documentation is submitted. The required
documentation and definitions by Mechanical Contractor and Architectural Crew/Contractor are
listed below:
Mechanical Documents

Mechanical Work Order: Weatherization measures to be completed by the Mechanical
Contractor are printed in list form on a “Work Order”. The Work Order provides cost
estimates for each weatherization measure and summarizes total costs by category. There
is an “Estimated Grand Total” at the bottom of the work order that provides an estimated
total cost for the job. When estimated costs have not changed “Estimated Grand Total”
becomes “Actual Grand Total”. The “Actual Grand Total” must match the grand total on the
mechanical contractor's invoice. Where changes to the work order effect material and labor
costs, the change work order must be reconciled to insure the “Actual Grand Total” is
correct based on those changes. When a weatherization measure is completed, a checkbox
is checked” by the contractor next to the measure to indicate completion. The post-work
auditor also checks a box next to the measure to indicate final review. All of the
“completion” and “post-work audit" checkboxes must be checked to show completion of
work.
IX.2

Mechanical Change Order document(s): There are certain circumstances where the
mechanical contractor cannot install a weatherization measure listed on the Work Order, or
a measure may need to be added. When changes to the Work Order are needed the
mechanical contractor must first obtain permission to make the change by contacting the
Grantee. Making changes to the Work Order is known as the “Change Work Order
Process”. The process includes the completion of a “Change Work Order Form” that must
be submitted to the Grantee in order to secure approval. The Grantee will place the change
work order form into the applicant's file. The document will list the measure(s) subtracted
or added to the Work Order with the labor and material costs for each measure stated
separately. The bottom of the change work order must provide a “Grand Total” indicating
the sum balance of all changes. Weatherization measures listed on change work orders
must be reconciled with the invoice work order. The Work Order must reflect the
information on the Change Work Order form(s). For example: If the Change Work Order
subtracts, a weatherization measure from the Work Order a notation must be made on the
Work Order at the location of the measure directing the reviewer to refer to the Change
Work Order. With the measure deleted from the Work Order the total costs for the category
in which the measure appeared would be over written with a new total cost. If a
weatherization measure is added, the same procedures above are to be followed.

Mechanical Invoice: The mechanical contractor is to submit an invoice summarizing, by
labor and material, the cost of each measure applied to the home. The costs summaries of
the invoice are to match the detail and costs summary of each measure on the Work Order.
For example: The replacement furnace on the Work Order states the summary cost for
furnace labor is $500.00 and summary costs for material is $950.00. The invoice would say
“Installed 80,000 BTU 90% Furnace” with the labor column showing $500.00 and the
material column showing $950.00. The invoice is to also show a “Grand Total” at the
bottom which is to match the “Grand Total” of the mechanical Work Order.

Assurance and Guarantee of Work: Labor and materials applied to client homes are
guaranteed for one year starting on the final inspection date. The guarantee is valid for one
year where there is no misuse by the client of weatherization services (breakage, etc.). The
Assurance & Guarantee of Work document does not supersede any manufacturer
warrantee for a weatherization measure guaranteed beyond the twelve month period. The
Assurance and Guarantee of Work document is a required document that must be
completed by the Mechanical Contractor, with the original document given to the owner of
the property and a copy, or duplicate, placed in the client’s file.

Release of Lien: A lien is a claim against property that must be paid before the property
can be sold or transferred. The Residential Weatherization Program is a “Grant Program”
that pays labor and material costs for energy conservation measures installed on client
homes. Because the “Grant Program” pays labor and material costs on behalf of low income
client, a lien for payment of weatherization labor and materials by the contractor is
prohibited. The Release of Lien document is used to waive the right of a contractor to place
a lien on the client’s home for weatherization labor and materials. The Release of Lien
document is a required document that must be completed by the contractor, with the
original document given to the owner of the property and a copy, or duplicate, placed in the
client’s file.
IX.3

Mechanical Contractor Checklist: The mechanical contractor will document the condition
of the heating system with a “Contractor Checklist” by taking various readings and
measurements outlined on the checklist. Corrective repairs or replacement of the heating
system may be determined by the results of the readings and measurements. The
Contractor Checklist must be completed and signed by the Mechanical Contractor
completing the work for every heating system.

Heating System Replacement Sizing Chart: To insure the mechanical contractor
replaces the heating system with one that will properly heat the home a “sizing chart” will
be completed. Replacement furnace sizing calculations must incorporate the architectural
work to be completed on the home. The sizing chart contains a series of questions about the
structure of the dwelling that will provide the mechanical contractor with an estimated BTU
(British thermal unit) usage of the home. Allowable sizing charts must be scientific and
answer detailed questions about the dwelling (window size, door size, or by the
manufacturer of the heating system to be installed). Sizing charts written and/or drawn on
note book paper are not acceptable.
Architectural Documents

Architectural Work Order: Weatherization measures to be completed by the Architectural
Contractor/Crew are printed in list form on a “Work Order”. The Work Order provides cost
estimates for each weatherization measure and summarizes total costs by category. There is
an “Estimated Grand Total” at the bottom of the work order that provides an estimated total
cost for the job. When estimated costs have not changed “Estimated Grand Total” becomes
“Actual Grand Total”. The “Actual Grand Total” must match the grand total on the
Architectural Contractor invoice. Where changes to the work order effect material and labor
costs the work order must be adjusted accordingly to reflect changes and to insure the
“Actual Grand Total” is correct. When a weatherization measure is completed a checkbox is
“checked” by the contractor next to the measure to indicate completion. The Post-Work
Auditor also checks a box next to the measure to indicate final review of completed work.

Architectural Change Order document(s): There are certain circumstances where the
Architectural Contractor cannot install a weatherization measure listed on the work order, or
a measure needs to be added.
When changes to the work order are needed the
Architectural Contractor must first obtain permission to make the change by contacting the
Grantee. Making changes to the work order is known as the “Change Order Process”. The
process includes the completion of a “Change Order Document” that must be submitted to
the grantee upon completion of the weatherization work. The grantee will place the change
order document into the client file. The document will list the measure(s) subtracted or
added to the work order with the labor and material costs for each measure stated
separately. The bottom of the change order must provide a “Grand Total” providing the sum
balance of all changes. Weatherization measures listed on Change Orders must be reconciled
with the Work Order. The Work Order must reflect the information on the change order(s).
For example: If the change order subtracts a weatherization measure from the work order a
notation must be made on the work order at the location of the measure and identify the
Grantee authorizing the change order. With the measure deleted from the work order, the
total costs for the category in which the measure appeared would be adjusted accordingly to
reflect changes and the new actual grand total cost. If a weatherization measure is added,
the measure is to be written in at the location on the work order where it would appear. The
written measure would include the description, labor and material costs, and name of the
Grantee authorizing the change order. The category for the added weatherization measure
would include the new total.
IX.4

Architectural Invoice: The architectural contractor is to submit an invoice summarizing by
category (windows, doors, etc.) the cost of labor and materials applied to the home. The cost
summaries of the invoice should mirror each category on the work order. The invoice is to
also show a “grand total” at the bottom which matches the “grand total” of the architectural
work order.

Assurance and Guarantee of Work: Labor and materials applied to the applicant is home
is guaranteed for one year starting from the final date of the post-work audit. The guarantee
is valid for one year where there is no misuse by the applicant of weatherization services
(breakage, etc.). The Assurance & Guarantee of Work document does not supersede any
manufacturer warrantee for a weatherization measure guaranteed beyond the twelve month
period. The document used to provide the guarantee is the “Assurance and Guarantee of
Work” document. The Assurance and Guarantee of Work document is a required document
that must be completed by the Contractor, with the original document given to the owner of
the property and a copy, or duplicate, placed in the applicant's file. The owner/resident must
notify the grantee once they become aware of any issue(s) with the work completed within
the first year. The grantee will then notify the contractor in writing of the issues noted and
request repair services. This notice will be forwarded to the owner/resident and a copy
placed in the file. The Urban Weatherization Initiative will take no financial responsibility in
repairing homes that have been weatherized under this program.

Release of Lien: A lien is a claim against property that must be paid before the property
can be sold or transferred. The Weatherization Assistance Program is a “Grant Program” that
pays labor and material costs for energy conservation measures installed on applicant's
homes. Because the “Grant Program” pays labor and material costs on behalf of low income
clients, a lien for payment of weatherization labor and materials by the contractor is
prohibited. The Release of Lien document is used to waive the right of a contractor to place a
lien on the applicant's home for weatherization labor and materials. The Release of Lien
document is a required document that must be completed by the contractor, with the
original document given to the owner of the property and a copy, or duplicate, placed in the
applicant's file.

Intermediate Blower Door measurement: Architectural Contractors complete work on
homes that seal interior air bypass openings to the outside. Sealing the openings is known as
“Air Sealing Measures”. Air Sealing Measures stop outside air or conditioned inside air from
penetrating the thermal/pressure barrier of the home. The Architectural Contractor will be
provided a work order that will identify the openings to be sealed. After sealing the openings
the Architectural Contractor will complete at least one measurement with a blower door and
manometer to determine if the air sealing work completed has been successful and to
measure the reduction of outside air into the home. The measurement is a four (4) digit
number known as the “Intermediate Blower Door Measurement”. The Architectural
Contractor will write the four digit number on the first page of the Work Order. The
Intermediate Blower Door measurement must be entered into the “Blower Door” tab of the
Energy Audit before the home can be closed and reported. If the Intermediate Blower Door
measurement could not be completed a notation on the first page of the Work Order
explaining why will be provided by the Contractor.
IX.5
Verification of Work Order Completion
The Post-Work Auditor must review the work order before the post-work audit begins to insure it is
completed correctly and to familiarize him/herself with the home to be inspected before arrival. If
the work order indicates weatherization measures were not completed, and there is no support
documentation explaining why it was not completed, return the work order to the contractor for
completion of the weatherization measures.
Below is a list of items that the post-work auditor must review before completing the audit:
•
•
•
•
•
•
Have all of the completion check boxes been checked?
Has the labor and material for each weatherization section been tallied?
Has the total labor for the job been written at the bottom of the Work
Order?
Has the total material for the job been written at the bottom of the Work
Order?
Has a grand total for labor and material been written at the bottom of the
Work Order?
If a change was made to the Work Order, were a date, time and name of the
Grantee or authorized agent giving approval for the change written on the
Work Order?
During the post-work audit, if it is determined that the work completed by the contractor was
incomplete and/or there was no significant reduction in the diagnostic readings, the contractor must
be called back to complete the work which they were contracted to provide at no additional cost to
the Grantee or the resident.
Verification of Completed work
Determine whether completed work meets the specifications identified via the work order. In most
cases, the job of the Post-Work Auditor will be to determine that the assessment and the
weatherization measures on the Work Order and invoice have been installed correctly.
In circumstances when the work is clearly unacceptable a call-back must be ordered. In
circumstances where there is a question whether a completed measures meets quality control
standards, document the measure in question and discuss it with the contractor completing the
work.
Accounting for the Work
Materials applied and actual costs must all be accurately accounted for. It the responsibility of the
Post-work Auditor to ensure these items are correctly and safely installed. The correct numbers and
costs are to be entered on the Work Order and placed in the file. The Contractor’s invoice must be
detailed and broken out by measure in the same order and format as the Work Order. These figures
are the basis for reporting proper usage of Residential Weatherization Program funds.
Work Order Check-off
The Post-Work Audit should include checking off the items printed on the Work Order. If used
correctly, verifying the items on the Work Order can help improve the quality of a contractor's work
by identifying the source of any problems. Because the grant manger reviews only a percentage of
the agency's work, the post-work auditor is in a much better position to detect the problem when
issues reoccur. Post-Work Auditors are to check off each building section item to see if it has been
completed in accordance with the work order and the Residential Weatherization Program’s
Standards and Procedures.
IX.6
Completing the Final Post Work Audit Form
The Post-Work Auditor is to complete the post-work audit after any call-back work has been
successfully completed. This form should, ideally, be completed in the presence of the applicant.
Every effort must be made to fully inspect the unit and to obtain the applicant's signature on the
Post-Work Audit Sheet. A copy of this form is to be left with the applicant and one placed in the
applicant’s file.
The Post-Work Auditor is to attach the final Flue Gas Analyzer readings to the Post-Audit Form, and
a copy is to be attached to the heating system. The Post-Work Auditor is to ensure that the
Intermediate and Final Blower Door readings are entered on the Post-Work Audit Form.
In the event that repeated trips to the home do not result in a final sign-off, the grantee must
document the efforts made and attempt to get the client’s signature via certified mail. Retain a
copy of the letter sent to the applicant requesting a post-work audit date and/or signature on the
Post-Work Audit Sheet. If the grantee does not receive a response from the applicant, the home
may be reported as a final audit, using the date of actual inspection, or the date the response to the
letter was due back to the grantee.
IX.7
SECTION IX
FINAL INSPECTION
EXHIBITS
Contractor Assurance & Guarantee of Work
Release of Lien
Contractor Checklist
Sample Final Inspection Attempt Letter
Change Order Form
Example of Change Order Documentation
Applicant Post Work Survey
URBAN WEATHERIZATION PROGRAM
CONTRACTOR ASSURANCE AND GUARANTEE OF WORK
(Give original to the applicant; retain a copy for the file)
I, __________________________________________________________of the following
Print Name
organization:_________________________________________ guarantee the workmanship
for installation of:______________________________________________
at_________________________________________________________________ for one
Applicant Address
year beginning __________________________and ending _________________________
Insert Beginning Date
Insert Ending Date
in accordance with manufacturers instruction and the American National Standards Institute
(ANSI) procedure.
_________________________________
Signature
____________________
Date
Failure to complete this form correctly could result in delay of payment.
URBAN WEATHERIZATION PROGRAM
CONTRACTOR RELEASE OF LIEN
WHEREAS, we the undersigned, have installed materials and furnished labor and/or
equipment for the Furnace Retrofit project for:
________________________________________________________________
(Applicant's Name & Address)
WHEREAS, all materials were installed and labor was furnished according to a written
agreement dated ____________________ between ___________________
_______________________________________(herein referred to as the Grantee)
and _________________________________ (hereafter referred to as the
contractor); WHEREAS, we the undersigned have agreed to release any and all
claims and liens which we have, or might have, against the owner of said property,
the occupier of said property, and the Grantee by reason of the labor, materials, and
equipment furnished by us in connection with said Weatherization Project.
NOW THOSE PRESENT WITNESSETH that we, the undersigned, in consideration for
the sum listed on the contract and any attached change Work Orders, the receipt
whereof we do hereby acknowledge, do hereby release, remiss, and forever quit any
or all manner of liens, claims, and demands whatsoever which we now have, or
might have in the future against the owner and occupier of said property and the
Grantee.
_______________________________
(Contractor Name)
Date Job Started:
_______________________________
(By)
____________________
Date Job Completed: ____________________
URBAN WEATHERIZATION PROGRAM
FINAL POST-WORK AUDIT ATTEMPT LETTER
Date:
Dear Mr./Mrs._______________:
Enclosed, please find a Final Post Work Audit Form for the Weatherization work that was done to
your home. We have made several attempts to contact you to perform the post-work audit on your
residence, but have been unsuccessful.
At this time, we are requesting for you to review and sign the Post-Work Audit Form and returned to
our agency. If you wish, please make comments about the work that was done.
Please mail the signed form to our office in the enclosed self-addressed stamped envelope. If the
signed post-work audit form is not returned by (insert date), we will consider the work to be
satisfactory and your file will be closed.
Thank you for your assistance and if you should have any questions, please contact the Grantee’s
Office at
_______________________________.
Sincerely,
Urban Weatherization Initiative
Residential Weatherization Program
CONTRACTOR CHECKLIST
Job#
Applicant Name
Phone________________ Furnace Brand Name______________________ Serial # _______________
Residential Furnace ______________Boiler_____________
Natural Gas_____ Propane________ Electric________ Clean & Tune ______ Replacement________
Inspect vent system & vent connection?
Yes No
Electric shutoff switch present?
Yes No
Manual gas shutoff value present
Yes No
w/handle and operational?
Manual gas shutoff value present w/handle Yes No
and operational?
Clean and insect pilot & burner?
Yes No
If no, state reason__________________________
Clean and inspect heat exchanger?
Yes No
Cooper gas line inspected & tested
Yes No
or leaks?
No Leaking gas lines replaces &
Yes No
tested for leaks?
Uncoated brass flex connectors replaced
Yes No
& tested for leaks?
Vision impaired thermostat installed?
Yes No
Set back thermostat installed?
Yes No
Thermostat calibrated & leveled?
Yes No
Class B vent installed?
Yes No
Flue liner installed with cap?
Yes No
Is there an ID vent damper present?
Yes No
Are all rooms receiving heat?
Yes No
Is adequate return air present?
Yes No
Inspect wiring?
Yes No
Replace thermocouple?
Yes No
Vent termination installed per PMI?
Yes No
Clean & Tune Blower?
Yes No
Unit installed on blocks?
Yes No
Combustion Blower cleaned?
Yes No
Gas leak test conducted on all
Yes No
Gas appliances & supply lines?
Rated Input__________ Clocked Input___________
Draft Reading (see table) _______CO Reading ________
Condition of Flame_____________________________
Fan Off Temp _________ Fan on Temp ___________
BOILER
Inspect vent system & vent connections? Yes No
Manual gas shutoff valve present and
Yes No
Operational
Sediment trap present?
Yes No
ELECTRIC HEAT
1. Condition of elements & Links? _________
2. Voltage? _______
3. Rated AMP Draw________
4. Measured AMP Draw
Temperature Rise per Manufacturer’s
Specification:
1. Supply Temp. _______
2. Return Temp. _______
3. Temp. Rise__________
Appliance:
Gas Dryer Gas Stove
Manual shutoff w/handle
present and operational? Yes No Yes No
Is Sediment trap present? Yes No
Yes No
Is Uncoated brass flex
Connectors replaced
Yes No
Yes No
Is Gas leak test conducted? Yes No
Yes No
Is Rigid vent present &
Connected?
Yes No
Yes No
Below 21F
-5.0 PA (0.020”WC)
21F TO 40F
-0.40 PA (0.016”WC)
41F to 60F
-0.30 PA (0.012”WC)
61F to 80F
-1.20 PA (0.008” WC)
Above 80F
- 1.0 PA (0.004” WC)
OIL HEAT
Oil Nozzle replaced?
Yes No
Chimney cleaned?
Yes No
Change Oil Filter?
Yes No
Barometric damper operational? Yes No
Class A vent installed?
Yes No
Draft over flame? ___________________
Oil Nozzle size______ Smoke Test reading _______
Efficiency______ CO Reading____________ ppm
Electric shutoff switch present?
Yes No
Clean & Inspect burners and pilot
Yes No
Clean & Inspect heat exchanger
Yes No
Inspect wiring?
Yes No
Leaking Gas lines replaced?
Yes No
Repair water-stream leaks?
Yes No
HD/Vent Damper installed?
Yes No
Pressure Temp. Valve operational?
Yes No
Expansion tank drained?
Yes No
System bled?
Yes No
Low Water cutoff cleaned?
Yes No
Is low Water cutoff operational?
Yes No
Is water sight glass visible & cleaned?
Yes No
Pigtail removed & cleaned (Stream)
Yes No
Fill Valve operational?
Yes No
Fuel Pressure _____________ iwc
Yes No
System pressure __________ PSI
CO Reading ____ppm Condition of Flame__________
Flue Temperature________________ Degrees
Circulator on Temp ______Circulator off Temp ______
Rated Input __________ BTU Clocked Input _________
Heat Anticipated setting________________
Outdoor Temp. Controls Checked
Yes No
Draft Reading__________(See Table)___________
Condition of fuel lines? _____________________
Stack control drop out time? _________________
Condition of Electrodes? _____________________
Condition of Chimney? _______________________
WATER HEATER
GAS
ELECTRIC
Draft Reading _____________________ iwc
Temperature in Flue _____________ Degrees
CO Reading ______________________ ppm
Conditioning venting __________________
Condition of burner____________________
Is Electronic disconnect installed? Yes No
Is manual shutoff w/handle
Yes No
installed & operational?
Is Drip Pan Installed
Yes No
Is T/P valve discharge pipe installed? Yes No
Is T.P. Valve operational?
Yes No
Is sediment trap installed?
Yes No
Gas leakage test conducted?
Yes No
Is Burner Door/Panel in Place?
Yes No
Flue liner installed?
Yes No
Replace Thermostat
Yes No
CLIENT INORMATION
Guarantee form were left with applicant? Yes No
PMI were left with the applicant?
Yes No
Furnace Filters were left applicant?
Yes No
Sizing Chart was completed?
Yes No
I certify that I have inspected all existing and newly installed gas lines and gas appliances for any gas leaks, and that all
combustion appliances are working safely within the specific IHWAP parameters. I understand that all invoices must be
itemized with Labor/ Material invoices must be itemized with Labor/Material cost and submitted with the Work Order.
____________________________________________
Technician Signature
Date
URBAN WEATHERIZATION PROGRAM
Residential Weatherization Program
CHANGE ORDER REQUEST
Applicant Name: __________________________________________
Applicant Address: ________________________________________
Job #: ________________________
This is an agreement between the undersigned contractor and ______________________
(Grantee)
to approve and carry out work that is substantially different than the original project scope. Both
parties understand that the requested changes, as specified below, may alter the project’s price and
schedule. It is also understood that any differences in estimated costs due to this change order will
be accounted for in the regular payment schedule.
Changes either adding or deleting material/Labor from the home will change the estimated total
costs on the work order. Contractor will contact Grantee and receive authorization before making
changes to work order. Contractor will calculate new costs at bottom of work order to reflex
changes. Contractor will also write changes, added or subtracted, at location on work order where
changes take place and enter new costs, greater or less than, those costs printed on work order.
Explanation for addition or deletion of work:
__________________________________________________________________________
___________________________________________________________________________
Contractor will provide all labor and material for the following work:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Labor Costs: _________ (Add/Deduct) Material Costs: _________ (Add/ Deduct)
Does Change Affect Schedule?
Yes / No
New Estimated Completion Date: _____________
Submitted by: __________________________________ ________________
(Contractor Name)
(Date)
Approved: __________________________________ ________________
(Grantee Name)
(Date)
When a “Change Order” is authorized which adds or deletes a measure from the Work Order the
contractor will write an explanation of the change in the “Building Section” of the measure. The
explanation will identify the measure added or deleted, who the crew/contractor contacted to
authorize the change, date of change, and the amount of labor and material dollars added or
deleted. The crew/contractor will also initial the explanation. The process for mechanical work and
architectural work is the same.
Residential Weatherization Program
Applicant Post- Work Survey

During the intake process was everything explained clearly (the time and all the steps during
the process)?
☐Yes
☐No
If No, please explain:_______________________________________________________

Was the auditor on time and was he or she helpful and or respectful while in your home?
☐Yes
No
If No, please explain:_______________________________________________________

When the contractors came to your home did they:
 Complete the work on time?
☐Yes
☐No
If No, please explain:____________________________________________________
 Were they respectful?
☐Yes
☐No
If No, please explain:____________________________________________________
 Did they clean up the area before they left your home?
☐Yes
☐No
If No, please explain:____________________________________________________

Were you satisfied with the work that was done?
☐Yes
☐No.
If No, please explain:_______________________________________________________

Have you been able to maintain your heat at the same temperature before the work was
completed, or have you adjusted the temperature in your home either higher, lower, or was
there no change?
Please explain:___________________________________________________________
SECTION X
FILING SYSTEM
SECTION X
FILING SYSTEM
The mission and goal of the Office of Urban Assistance is to skillfully operate a program that will ensure that
grantees maintain sound management and administrative procedures. Partnership with the Office Urban
Assistance is a business venture and must be treated as such. Therefore, records must be classified, arranged,
and stored as required by the procedures set forth in this section of the manual.
This section of the procedures is to provide guidance for establishing and maintaining effective filing systems
and will concentrate on two areas. These areas entail required subject files and release and retention of
records.
Required Subject Files
The subject files required are intended to maintain only the basic records needed. Subject headings under which
records are to be retained include:










Grant Agreement File
Applicant File
Ineligible Applicant
Multi-Family Housing Structure
Insurance
Personnel
Correspondence
Regulations
Procurement Methods
Homes Previously Weatherized
The Grant Agreement File is one of the most important files in the system, which contains the
documents that give the Grantee it's authority to operate the Residential Weatherization program. This
file must contain the following documents:
A. A copy of the signed Residential Weatherization Program Grant Agreement
B. A copy of any Budget Modification sheets (in chronological order)
C. Quarterly Project Status Reports (Most recent report on top).
D. Quarterly Financial Status Reports ( Most recent report on top).
E. Quarterly Grantee Inventory Tracking Form
F. Subcontract Agreement (if applicable) each agreement must be separated by a partition with
subcontractor's name.
G. Outreach File
The original grant agreement, along with copies of the other above noted documents are to be filed
with the Residential Weatherization Program.
X.1
Applicant File. The Office of Urban Assistance is requiring that a standardized residential weatherization
applicant file system be adhered to. This filing system will serve several purposes: 1) Standardization, 2)
Continuity, and 3) File Audit Simplicity. The applicant files should be set up with a separate file folder for each
residence. All file folders must be organized based upon areas served within the identified county, in
alphabetical order (by applicant's name). If the applicant resides in a multi-family unit, each applicant must have
a separate file folder and all folders must be stored and arranged by unit floor levels.
The Grant Manager from the Office of Urban Assistance will routinely check with the designated Grantees for an
organized and accurate filling system as it pertains to storing and maintaining pertinent documentation and
information. Below are a list of items that will be required, yet other documents and information may be
requested as warranted:
Applicant Information
Hazardous Materials and Pre-Audit Measurements
Application
Hazardous Conditions Form (if applicable)
Approval/Denial
Water Heater and Heating Systems Draft Test
Application File Checklist
Intermediate Blower Door Readings
Applicant Health and Safety Questionnaire
Mold & Moisture, Pressure Diagnostic Checklist
Applicant Satisfaction Survey
Primary Flue gas Measurements
Homeowner Authorization Form
Primary Blower Door Readings
Income Documentation
Roof Survey and Roof map (if applicable)
Multi-Family Building Plan (if applicable)
Post Work Audit Information
Pending Eligibility Letter
Post Work Audit
Proof of Ownership (if applicable)
Final Flue Gas Measurements
Rental Agreement (if applicable)
Final Blower Door Readings
Utility Release Form
Inspection Deficiency Report
Utility Bills (Last two months)
Work Authorization
Other Client Documentation
Contractor Information
Award letter
Change orders
Color Digital Photos
Contractor Assurance and Guarantee Form
Contractor’s Bid Information
Contractor Checklist
Contractor’s Lien Release
Contractor Inventory Tracking
Copy of Certificates validating work experience
Copy of cancelled checks to contractors
Floor Prints: All levels of the home, including attic, basement, walls, foundations, windows, doors
Invoices
Proof of Insurance
Scope of Work
State License
Work order(s): original and final if applicable
At minimum, the applicant file must utilize an eight pronged classification folder with fasteners on each side.
The Grantee must use adhesive labels to distinguish the various sections of each file. The fasteners must be
used to attach and secure file documents. The Office of Urban Assistance will conduct file reviews on a
minimum of a quarterly basis in order to monitor file structural compliance.
X.2
The Applicant File must be organized as follows:
EXHIBITS
Section
1
2
2
3
4
DESCRIPTION
Application Information
Application
Approval/Denial Letter
Application File Checklist
Applicant Health and Safety Questionnaire
Homeowner Authorization Form
Income Documentation
Multi-Family Building Plan (if applicable)
Pending Eligibility Letter
Proof of Ownership (if applicable)
Rental Agreement (if applicable)
Utility Release Form
Utility Bills (Last two months)
Work Authorization
Other Client Documentation
Contractor Information
Award Letter
Change Orders
Color Digital Photos
Contractor's Bid information
Contractor Lien Release
Contractor Inventory Tracking Form
Copy of certifications validating contractors work experience(BPI,LEAD,etc)
Copy of Canceled Check(s) to Contractor
Fiscal Detail Report
Floor Prints: Attic unfinished/finished, Walls, Foundations, Windows, Doors,
All Invoices
Proof of Insurance
Scope of Work
State license
Work Order(s): Original and Final (only)
Contractor Assurance and Guarantee of Work Form
Contractor Checklist
Hazardous Materials and Pre-Audit Measurements
Hazardous Conditions Form (if applicable)
House Depressurization Draft Testing: Water Heater and Heating Systems
Intermediate Blower Door Readings
Mold & Moisture, Pressure Diagnostic Checklists
Primary Flue Gas Measurements
Primary Blower Door Readings
Roof Survey and Roof Map (if applicable)
Post-Work Audit Information
Post Work Audit:
Final Flue Gas Measurements
Final Blower Door Readings
Inspection Deficiency Report
X.3
Ineligible Applicants: The grantee must maintain files containing applications and other pertinent
information, including the denial letter. All ineligible applications must be stored in a manila folder and kept
separate from the eligible applicant files. All applications are to be filed according to the date (month/year)
which the application was deemed ineligible. All ineligible files must be stored and retained for a minimum of 4
years.
Multi-Family Buildings: The system outlined below applies only to multi-family buildings completed under
the “Sixty six percent (66%) or greater rule”. Agencies are required to keep a file on each building. A separate,
complete application and assessment form are required for each unit. Grantees will be required to develop a
building "lead file". This file must contain:
A.
B.
C.
D.
Copy of the building eligibility approval or denial
Applicant’s Certifications
Copies of the Residential Weatherization Program energy audit; and,
Individual unit files which include all documentation listed below:
The following documents shall be maintained for each unit in a multi-family building:
A. Client application/income documentation
B. Multi-family Building Plan
C. Building Post-Audit for architectural/mechanical systems
D. Building ownership document
E. Rental Agreement
F. Applicant’s notification
G. Work Orders
H. Post-Work Audits
I. Building owner acknowledgment of completed work
Insurance: It is required that each Grantee maintains a file on insurance coverage. The file will contain at least
the following information:
A.
B.
C.
D.
Type of required insurance requirements
Agent or company providing coverage and telephone number
Policy number and date of expiration
A copy of the policy
Personnel: Each person employed as a part of the Residential Weatherization Program shall have a file which
contains those necessary items for proper personnel management. This information must include job title and
description, resume, completed application, annual evaluations, and salary information. All personnel
information must be kept secured by the Grantee.
RWP Correspondence: The Grantee must maintain a file that contains all correspondence for the Residential
Weatherization Program. Examples of file subjects are as follow:
A.
Urban Assistance memorandums and other pertinent, and significant correspondence regarding the
program;
B. Correspondence concerning any marketing and/or media publications (i.e. all marketing information
must be preapproved by the grant manager, approval for market distribution, copies of e-tear
sheets).
X.4
Procurement: This folder will include a listing of all services which have been procured, methodology of
publication, name of all bidders, bid amounts, date of award, and name of awardee. In addition, the grantee
must list by contractor all jobs completed and job number. This list must be updated on a monthly basis, as
applicable.
Homes Previously Weatherized: A file must be established listing the addresses of all units previously
weatherized by the Residential Weatherization program. All information must be organized by area.
Release and Retention of Records:
There are three areas the Grantee must be aware of relative to the release and retention of records. These
areas are freedom of information, the right to privacy, and record retention.
Freedom of information makes it easier for individuals, legal representatives, advocacy groups, investigators,
and other interested parties to gain access to information in government program files. First, the applicants
have a right to see what the Grantee has on file about them. Second, anyone who files a written request can
obtain certain program information that does not violate the client's right to privacy. (DCEO’S legal counsel has,
in the past, interpreted this to include addresses of units weatherized.)
The provision for a client’s right to privacy is also important. In accordance with the Client Privacy Act of 1974 (5
USC 552a), the Grantee may not release the client's name, phone number, social security number, income
information, etc. to other entities (including service agencies), even with the best of intentions.
The information retained by the Office of Urban Assistance is also confidential. The Office of Urban Assistance
does not use this information for anything other than the authorized purpose. If you receive a request for
information from outside groups or individuals, contact The Office of Urban Assistance prior to supplying any
information.
Proper record retention is paramount. Grantees are to keep program files for a minimum of four years or until
that program year's audit is finally resolved to the satisfaction of DCEO. The Office of Urban Assistance may
require a Grantee to retain records longer than four years by specific request.
X.5
SECTION X1
INVENTORY
Inventory control is a vital responsibility of the grantee and consists of several functions including the general areas of inve
addition, all grantees are responsible for securing Contractor Tracking Inventory Forms in order to ensure proper purchases a
Inventory Control
Grantee Inventory Control
The grantee is responsible for completing the Grantee Tracking Form on a quarterly basis which is to be submitted to the gran
invoices must be attached to each tracking form completed. The Grantee Inventory Tracking Form list the items purchased, t
The tracking form will be completed at the beginning of the quarter and then verified at the conclusion of the quarter. This fo
Contractor Inventory Control
Storage of materials may be necessary because the contractor needs an adequate supply of items frequently used which will
complete a Contractor Inventory Tracking Form at the beginning and conclusion of each month. This form must be submitted
Inventory Tracking Form must list the items purchased, the number of items purchased, the cost of each item, and the total.
Equipment Acquisition Form
Before the grantee purchases any equipment, they must secure written approval from the Grant Manager, which will then be
the
Grantee must secure written permission from the Grant Manager before purchasing any equipment. This purchase will not h
Once equipment has been purchased, Grantee is required to submit an Equipment Acquisition Form to the Grant Manager.
GRANTEE INVENTORY TRACKING FORM
(This form must be c
Grantee Name: _________________
Beginning of Quarter Inventory
Items (list all
#
Cost of Total Cost
items and attach of
Each
paid invoices or Items
Item
lease agreements)
Other
Grant #:______________
End of Quarter Inventory
Actual Remainder
Items
on Hand
Applied
Total $
Beginning of Quarter Inventory
Signatures:
Inventory Staff/Date___________
Supervisor /Date_____________________
End of Quarter Inventory
Signatures:
Inventory Staff/Date
Supervisor/Date
*Comments_________
(This form must be completed for each job and submitted to the Grantee by the 10th of each month. Origina
Job # ___________________
Items
Address: ________________________________________
Beginning of Month Inventory
# Cost
Item
Total
Each
#
Cost
End of Month Inventory
Actual Remainder
Applied on Hand
Total
$
Signatures:
Inventory Clerk/Date______________
Crew Leader/Date_____________________
*Comments:
_____________________________________________________________________________________________
________
_______________________
Grantee:
Grant # ____________________
Date Purchased: _______________________________________________________________ :
Equipment Purchase(s)
$_________________
_________________________________ ________________________
$_________________
__________________________________________________________
$_________________
__________________________________________________________
$_________________
__________________________________________________________
$_________________
Purpose Used _________________________________________________________________
______________________________________________________________________________
Brief Description
Agency Inventory Control or Tag Number
Once completed, this form will attest that the purchase of the above equipment has been pre-approved by the grant ma
form and a copy maintained with the grantee.
SECTION XII
PROGRAM REPORTING
SECTION XII
PROGRAM REPORTING
Residential Weatherization Program Reporting
The Grantee's reports shall be structured to provide for accurate, current, and complete disclosure of the results
of the project funded under this grant program. The Grantee is accountable to ensure that all grant funds
received are used for the purpose of administering this program and must be reported to the grant manager, at
minimum, on a quarterly basis. The Grantee shall maintain effective control and accountability over funds,
equipment, property, and other assets under the grant as required by the Department. The Grantee shall keep
records sufficient that will permit the tracking of program outcomes as specified in the scope of work. In
addition, the Grantee shall keep records sufficient that will permit the tracking of all expenditures in order to
ensure that funds have not been inappropriately disbursed.
All Grantees are required to comply with the program reports as specified below:
Project Status Report
In a report provided by DCEO, the Grantee must identify and document all activities that have taken place during
that reporting period and submit to the Grant Manager on a quarterly basis, as specified in the Welcome
Package Reports Deliverable Schedule. This report must be completed as indicated from the preparation
instructions which can be found in the Welcome Package. This report must detail all outcomes that have been
achieved during this reporting period. In addition, the Grantee must identify any challenges which they have
experienced during that respective reporting period that may have had an adverse effect on the achievement of
their outcomes and recommendations made to address the identified challenges.
Financial Status Report
In a report provided by DCEO, the Grantee must document all expenses per budget line item that have been
disbursed during that reporting period. In addition, the Grantee must submit copies of ledgers, invoices, payroll
information, and cancelled checks which will be used to reconcile all expenditures made during that reporting
period. This report must be completed as indicated from the preparation instructions which can be found in the
Welcome Package. The financial status report must be tendered to the assigned grant manager on a quarterly
basis, as specified in the Welcome Package Reports Deliverable Schedule. The Grantee must have internal
controls consistent with generally accepted accounting practices adopted by the American Institute of Certified
Public Accountants. It must be noted that if the Grant Manager identifies any disallowable expenses during the
reconciliation process, these expenses will become the responsibility of the grantee to be paid for outside of the
RWP funds awarded.
Final Financial Status Report
The Grantee shall complete and submit a Final Financial Status Report on forms provided by DCEO, within fortyfive (45) days of the conclusion of the Grant Agreement. For the Grantee's convenience, the due date of the
report can also be found in the Welcome Package Reports Deliverable Schedule. The Grantee must report on
the expenditure of grant funds provided by the State.
The Grantee is responsible for taking the necessary steps to correct any deficiencies disclosed by such final
financial status report, including any actions that the grant manager or DCEO have identified based on reviews
of the report.
Inventory Forms
The Grantee is responsible for submitting both the Grantee Inventory as well as the Contractor Inventory Forms,
along with invoices stipulating item numbers and costs, on a quarterly basis.
XII.1
Additional Information
Upon request by the grant manager or DCEO, the grantee must, within the time specified, submit additional
written reports regarding the project, including but not limited to, supportive materials that will document
information provided by the grantee.
XII.2
SECTION XII
PROGRAM REPORTING
EXHIBITS
Project Status Report
Financial Status Report
Department of Commerce and Economic Opportunity
Project Status Report
Grantee:
Grant Number:
DCEO Program Name:
Report Period:
Prepared By:
Contact Number/Email:
Date Prepared:
Send Report to DCEO email address or hard copy address listed below:
Email:
Hard Copy:
From:
To:
Check box if this is the final report:
Check box if another DCEO reporting system has
been updated with current information, if
applicable to grant. If checked, detailed
information is not required in this report.
Indicate all systems updated to meet reporting
requirements (i.e. eGrants, etc.):
Indicate which reporting requirements are met
(i.e. ARRA Section 1512):
SECTION I: KEY DELIVERABLE or TASK ITEMS
I.A. Complete this section with each required item from the Scope of Work (SOW).
Statement of Work Deliverable, Task or Activity Planned Completion Date
%
Actual
Provide explanation if
Provide Brief Narrative of
Item
(PCD)
Complete Completion missed Completion Date
Deliverable/Task Status and Indicate
Required
Estimated
Date (ACD) or if not on target to meet Documentation included with Report to
Support Deliverable/Task
I.B. Complete this section with all required program specific reports and schedules.
Program Specific Report/Schedule
Submittal Date (SD)
Required
Estimated
SECTION II: PERFORMANCE MEASUREMENT REPORTING
II.A. Complete this section with each performance measurement.
Performance Measure (PM)
Target
Required
Estimated
Previous
Actual
Provide explanation if missed Submittal Date or if not on target to meet
Current
Actual
Actual to Provide explanation if not
Date
met or not on target to meet
Indicate Documentation
included with Report to
Support Attainment of PM
0
0
0
II.B. Complete this section with number of jobs created and/or retained as a result of this grant (if applicable).
Jobs Created
Target
Required
Estimated
Previous
Actual
Current
Actual
Actual to
Provide explanation if not
Date
met or not on target to meet
Jobs Created
0
Jobs Retained
0
Indicate Documentation
included with Report to
SECTION III: SUCCESS STORIES/ADDITIONAL ACTIVITIES ACCOMPLISHED
SECTION IV: ADDITIONAL CONCERNS AND/OR FEEDBACK
GRANTEE CERTIFICATION: Grantee certifies that all information reported to DCEO on this form and in any required systems is accurate; supporting documentation has
been submitted as required by Program; all supporting documentation is on file with the grantee and individual submitting report has full signature authority to sign on
behalf of this grantee as previously identified to the Department. The Grantee acknowledges that the Department’s approval for any item described herein shall be
considered conditional and subject to further review and verification in accordance with Monitoring and Records Retention Sections of the Grant Agreement.
Signature
Name & Title
Date
Department of Commerce and Economic Opportunity
Financial Status Report
Grantee:
Grant Number:
DCEO Program Name:
Report Period:
Prepared By:
Contact Number/Email:
Date Prepared:
Send Report to DCEO email address or hard copy address listed below:
Email:
Hard Copy:
From:
To:
Check box if this is the final report.
Check box if GRS (Grantee Reporting System) has been updated with
current information if applicable to grant. If checked, detailed
information is not required in this report.
Check box if there is no change in the reporting information for this
reporting period.
SECTION I: EXPENDITURE REPORTING
Subpart A: GRANT AMOUNT
1
Cost Category Number
Cost Category Description (Specific)
2
Current
Approved
Budget
Total
3
Previously
Reported
Expenses
$0.00
Current
Reporting
Period
Expenses
$0.00
4
Total Grant
Expense to
Date
(2+3)
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
5
Amount of
Accruals
included in
Column 3 (If
Applicable)
6
List Documentation included with
Report to Support Expense Amount
(see guideline document) and/or
explain any adjustments from prior
reporting periods.
$0.00
Subpart B: MATCH AMOUNT if applicable
1
Cost Category Number
Cost Category Description (Specific)
Current
Approved
Budget
Total
Previous Cash Requested or
Grant Funds Received
3
Current Cash
Request or
Grant Funds
Received
SECTION III: INTEREST INCOME or GRANT PROGRAM INCOME if applicable
1
Prior Earnings Balance
2
3
Previously
Reported
Expenses
$0.00
SECTION II: CASH REQUESTED OR GRANT FUNDS RECEIVED
1
2
Grant Amount
2
Current
Reporting
Period
Expenses
$0.00
4
4
Total Match
Expense to
Date
(2+3)
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
5
Amount of
Accruals
included in
Column 3 (If
Applicable)
List Documentation included with
Report to Support Expense Amount
(see guideline document) and/or
explain any adjustments from prior
reporting periods.
$0.00
5
Remaining
Grant Funds
Grant Funds on
[1-(2+3)]
Hand
$0.00
$0.00
$0.00
$0.00
3
4
Current
Current Period Current Period Earnings
Receipts
Disbursements Balance
Grant Program Income
Grant Program Interest
6
List Documentation included with Report to Support Expense Amount
(see guideline document) and/or explain any adjustments from prior
reporting periods.
$0.00
$0.00
GRANTEE CERTIFICATION:
Grantee certifies that all expenditures from these project funds are for approved project costs only; supporting documentation has been submitted as required by the Program; all supporting
documentation is on file with the Grantee and the individual submitting report has full signature authority to sign on behalf of this Grantee as previously identified to the Department. The
Grantee acknowledges that the Department’s approval for any expenditure described herein shall be considered conditional and subject to further review and verification in accordance with
Monitoring and Records Retention Sections of the Grant Agreement.
Signature
Name & Title
Date
PROGRAM CERTIFICATION:
Program Manager has reviewed the report and supporting documentation for any major discrepancies and/or unusual items. All budget items are in accordance with grant agreement and
appropriate budget modification procedures. Program may sign below or capture approval in e-Grants.
Signature
For Program Use on Review Process
Name & Title
Date
SECTION XIII
GRANT MODIFICATION PROCEDURES
SECTION XIII
GRANT MODIFICATION PROCEDURES
If it is determined that the grant agreement requires modification in any manner, a modification form must be
completed by the grantee and submitted to the grant manager for review. If it is determined that the
modification being requested is within acceptable guidelines, the request will be submitted to the Board of
Directors for approval or denial. If the modification is approved by the Board, the grant manager will complete
the necessary steps in order to ensure the modification is executed per DCEO policy. Once the modification is
executed by the grant manager, a copy of the signed modification will be forwarded to the grantee. The grantee
must maintain copies of all approved modifications. If the Board of Directors is not in agreement with the
Grantee's request, the grant manager will notify the grantee that their modification has been denied and the grant
agreement cannot be modified.
When completing a modification, the Grantee must include the following:




A formal written request providing justification for the modification;
Grant Agreement Modification form (found in the Welcome Package);
If the grantee is submitting a budget modification, a revised budget must accompany the request,
outlining the monetary changes to each cost category as applicable.
The modification must be signed by the Grantee's authorized agent, usually the Executive Director
Please note that no budget increase will be allowed in this grant agreement; however there are four types of
modifications that can be requested by the grantee which include:
 Budget
 Scope of Work
 Date Extension
 Other
All four types of modifications are discussed below:
Budget Modification
The Grantee is required to report fiscal information regarding expenditures for the program. The fiscal reporting
requirements are detailed on the link identified in the welcome package. If it becomes necessary for the Grantee
to modify the cost categories within the program budget, a budget modification is required, along with a
statement of justification.
When it is determined by the Grantee that a budget modification is required, they must first communicate this
discovery with their grant manager. After discussion, the grant manager will direct the grantee as to whether
the modification is allowable. Once this information is determined, the grantee must submit a budget
modification form, along with a statement of justification to the grant manager and wait for final Board
approval. No budget modifications
can be made before the Board renders the final decision. Any budget modifications that were initiated prior to
the Board's approval will be identified as disallowable expenses.
Scope of Work
A scope of work change is a change made to the original terms or conditions of the grant agreement as specified
within the scope of work. Changes in the scope work can include, but are not limited to, altering the number of
XIII.1
applications to be accepted; number of homes audited; number of staff employed from the training programs,
areas served, number of homes repaired, etc.
Date Extensions
Date extensions can be initiated by the Office of Urban Assistance or can be requested by the Grantee. If the
Date Extension is requested by the Grantee, they must submit a letter of justification detailing why the services
outlined in the grant agreement cannot be fulfilled within the originally established time frame.
Other
Use this category for modifications that are being requested outside of the three mentioned above (i.e. payment
provision, audit waiver, etc.). If this form of modification is requested, the grantee must attach a separate page
identifying the provision requested, in addition to a written explanation supporting the modification request.
It is imperative to note that no modification will be completed within 45 days prior to the conclusion of the grant
period.
XIII.2
FISCAL PROCEDURES
EXHIBITS
DCEO Grant Program Request for Modification/Waiver
Illinois Department of Commerce and Economic Opportunity
DCEO GRANT PROGRAM
REQUEST FOR MODIFICATION/WAIVER*
GRANTEE NAME:
DCEO GRANT#:
(the “Agreement”)
GRANT BEGIN DATE:
GRANT END DATE:
STEP 1 – A written justification for this modification/waiver must accompany this document.
STEP 2 – Select the Purpose of the Modification/Waiver Requested:
A. SCOPE OF WORK Please attach a revised scope of work with modifications noted.
B. BUDGET On an additional sheet, please present the original budget as well as the revised budget, indicating the
requested changes.
C. DATE EXTENSION If you require additional time to complete the scope of work outlined in the Grant Agreement,
indicate the date to which you wish to extend the Grant Agreement here:
. In addition, please check one of
the two boxes below to indicate the type of payment provision applicable to your Grant Agreement:
Variable/advance grant only. Grantee acknowledges that it has expended/legally obligated grant funds in
performing the Scope of Work required by the Grant Agreement during the original grant term and that, if granted,
the extension of time cannot exceed two (2) additional years. Please attach a signed legal obligation document if the
extension exceeds the original two year period.
Reimbursement grant - Obligation documents not required.
D. OTHER Please check one of the boxes below and attach a separate page identifying the provision(s) that you wish to
modify and a written explanation supporting the request for a change.
Interest Retention:
Payment Provision:
Audit Waiver:
Waiver of Interest-Bearing Account:
Other:
To be compliant with Illinois’ Comptroller Accounting Bulletin 161, the Grant Agreement shall be amended in accordance with the
following. Notwithstanding any language in the existing Grant Agreement to the contrary, the following provisions shall be
incorporated into the Grant Agreement:
The Grant Agreement’s signature block shall be stricken in its entirety and replaced with the following language:
Grantee’s execution of this Agreement shall serve as its certification under oath that Grantee has read, understands
and agrees to all provisions of this Agreement and that the information contained in the Agreement is true and
correct to the best of his/her knowledge, information and belief and that the Grantee shall be bound by the same.
Grantee acknowledges that the individual executing this Agreement is authorized to act on the Grantee’s behalf.
Grantee further acknowledges that the award of Grant Funds under this Agreement is conditioned upon the above
certification.
Submittal of Reports Submittal of all reports and documentation required under this Agreement should be
submitted to the individual as directed by the Department. Grants in excess of $25,000 require, at a minimum, the
filing of quarterly reports describing the progress of the program, project, or use and the expenditure of the grant
funds related thereto.
Records Retention This Agreement and all books, records and supporting documents related hereto shall be available
for inspection and audit by the Department, the Office of Inspector General, the Auditor General of the State of
Illinois, the Illinois Attorney General or any of their duly authorized representative(s), and the Grantee agrees to fully
cooperate with any audit performed by the Auditor General or the Department. Grantee agrees to provide full access
to all relevant materials and to provide copies of same upon request. Failure to maintain books, records and
supporting documents required by this Agreement shall establish a presumption in favor of the Department for the
recovery of any Grant Funds paid by the Department under this Agreement for which adequate books, records and
supporting documentation are not available to support their purported disbursement or expenditure.
If the Department approves this request as either a modification or waiver, the Grantee acknowledges and agrees to the
following:
1.
All terms and conditions of the Grant Agreement remain in full force and effect until all performance required by the
terms of the agreement are completed.
2.
If the period for performance has been extended, the close-out package/final financial status report must be
submitted no later than 45 days following any extended performance date.
3.
This request is limited to the provisions described herein and in no way impairs the Department’s ability to seek legal
recourse against the Grantee for non-compliance with either the provisions stated herein or any other provisions of
the Agreement.
STEP 3 – Signature
I hereby certify that the supporting documentation for the above modification or waiver request is on file in our office and that I
have full signature authority to bind and sign on behalf of the grantee.
Authorized Signature for Grantee
Printed Name and Title
Printed Name and Title of Signatory Designee*
Date
* If the Grantee has authorized and designated signature authority to another person, the signatory must print his/her name
and title on the appropriate line.
STEP 4 – Return this form, your justification letter and all supporting documentation to your assigned Grant
Manager.
DEPARTMENT ACTION:
Approved as a Modification, subject to any conditions as imposed by the Department
Approved as a Waiver, subject to any conditions as imposed by the Department
Denied (see attached)
Adam Pollet, Director
Date
NOTE: Due to the Time Limit on Expenditure of Grant Funds imposed by the Grant Funds Recovery Act (30 ILCS 705/1 et seq.),
the extended grant term granted herein shall be deemed to take effect on
________________ .
Cc:
_________________________
(Grant Manager); Accounting
* Waivers will only be approved when the Department determines that it is in the best interest of the State of Illinois
Section XIV
Installation and Retrofit Material Standards
Section XIV
Diagnostic, Architectural, and Mechanical System Standards
The Urban Weatherization Initiative has incorporated standards from the Department of Energy as well as the
Illinois Home Weatherization Standards Field Guide in order to complete this section. The standards presented
in this section are to be utilized when completing weatherization services for the Residential Weatherization
Program. Grantees must ensure that all contractors have access to this section and are aware that the postwork auditors will use these standards in order to gauge the quality of all weatherization work completed.
Standards for Weatherization Materials (Appendix A to Part 440) are located in the exhibits section.
Diagnostic Standards
Blower Door
House Set-Up
Preparing the house for a blower door test involves putting the house in its heating condition with conditioned
spaces open to the blower door. The house should be tested in the “as found” condition to determine its
existing leakage rate.
•
Identify location of the thermal boundaries and house zones that are conditioned (see section “Thermal
Boundary”).
•
Deactivate all vented combustion appliances by turning the thermostat down or the appliance off.
•
Prevent ashes of wood/coal burning units from entering the living space by closing/sealing doors and
dampers or by cleaning out ashes.
•
Inspect house for loose or missing hatchways, paneling, ceiling tiles or glazing panes. Secure any items
that may become dislocated during the test.
•
Remove one ceiling tile on suspended ceilings to relieve pressure.
•
Close all primary windows, self-storing storm windows, exterior doors and latch them as they normally
would be found during the winter.
•
Open interior doors so that all indoor areas within the thermal boundary are connected to the blower
door.
•
Do not seal intentional exhaust air openings, such as combustion appliance flues, dryer vents or exhaust
fans.
•
Do not temporarily seal large obvious leaks such as missing or broken glass (this represents the “as
found” condition of the home).
•
If window air-conditioning units are left in place over the heating season, conduct blower door test with
the “as found condition”. If occupants remove air-conditioning units over the heating season,
temporarily air-seal around units for blower door test.
Basements
Basements may be used as living space. Furnaces and boilers and their respective distribution systems, water
heaters and washers/dryers are often located in the basement. Heat from these items as well as heat from the
space above helps condition basements during the winter. Therefore, basements are usually considered
XIV.1
conditioned space and basement doors should be open during the blower door test unless of one the following
conditions are present (even if the basement door is generally closed during the winter):
•
•
None of the above mentioned appliances are located in the basement, or
It is clear that the occupants do not use the basement on a regular basis; for example, access to the
basement is through an exterior door or hatch or through an unconditioned porch.
If you’re not sure whether the basement door was open or closed during the assessment, check the
work order as the assessor may have noted how the test was done. Call the assessor if necessary.
Blower Door Test
The blower door measures the total leakage rate of a home, indicates the potential for air leakage reduction in a
home and assists in finding air leakage locations. Four leakage rate numbers are associated with the blower door
test:
•
Building Tightness Limit (BTL),
•
Existing Leakage Rate,
•
Target Leakage Rate, and
•
Intermediate Leakage Rate.
Manometers must be calibrated per manufacturer’s recommendations. Generally, a label affixed to the
manometer indicates when the manometer is to be calibrated.
Existing Leakage Rate
Conduct a blower door depressurization test to determine the existing CFM50 leakage rate of home. Record the
existing CFM50 leakage rate. The average existing leakage rate in Illinois’ homes prior to weatherization is about
3900 CFM.
Depressurization Test
A depressurization test is required (unless it is determined that a pressurization is necessary – see next section)
as it is the standard test in the low-income weatherization program. If there are concerns about doing a
depressurization test, perform a pressurization test or gradually depressurize the house to 50 Pa while checking
the condition of the suspect areas. If, during this gradual depressurization, it is believed that further
depressurization is likely to cause a problem, depressurize as much as possible and use the corrected CFM50
(done automatically when using the DG700 manometer in PR/FL@50 mode).
Pressurization Test
A pressurization test should be done, rather than a depressurization test, if one of the following conditions is
present in the home:
•
Wood or coal fired-heating appliance operating,
•
Animal or bird feces is found in the attic that may be a health hazard,
•
Hole in top floor ceiling that may result in insulation being pulled into the home,
XIV.2
•
•
•
•
Interior wall or ceiling finishes might be pulled down by a depressurization test,
Open sump in basement,
Open sewer line in the home, or
Harmful pollutants could be introduced into the home by the operation of the blower door.
Mold on walls is not a reason to pressurize. A depressurization test is acceptable in such cases.
Can’t Reach 50 Pascals
If the blower door cannot achieve -50 Pa house pressure, re-inspect the home to assure that all windows and
doors are closed.
If the DG700 manometer is being used, the CFM50 value shown on the right-hand display will have already been
adjusted.
If the older style DG3 manometer is being used, get the house pressure to the highest possible multiple of five
(25, 30,35, 40, or 45 Pa). Multiply the flow rate (cfm) by the “Can’t-reach-fifty (CRF)” factor listed in Table 100-1
and record. For example, a house can only be depressurized to -25 Pa. The CFM reading is 4600. Converting to 50 Pa, the house leakage is 7360 CFM50 (4600
CFM25 x 1.6 = 7360 CFM50).
Target CFM50 Rates
Target CFM50 levels based on a range of existing leakage rates are shown in Table 100-2. Target CFM50 levels
relate existing CFM50 leakage rates to expected post-weatherization leakage rates. The premise is that homes
with high leakage rates have a potential for larger cost-effective leakage reductions than tighter dwellings.
Two sets of Target CFM50 rates are shown in Table 100-2. The first set is target rates prior to the
implementation of ASHRAE 62.2. Targets following the implementation of ASHRAE 62.2 are shown in the last
column and are based on a 20% improvement over the existing Target Rates.
Air sealing work should continue when the target has been achieved and additional air sealing
opportunities are present.
A concerted attempt to reach the target CFM50 must be made in every home. The most cost-effective air sealing
involves addressing the largest leakage paths first and sealing leaks in the top part of the home. Confirm
effectiveness of air sealing strategies by performing intermediate blower door tests.
Intermediate Blower Door Test
Contractors and crews are required to take, record and submit CFM50 readings to Weatherization Agencies.
Known as “intermediate readings”, these readings can provide immediate feedback to those doing the air
sealing work and where the leakage rate is with respect to the Target CFM50.XIV.3
Existing CFM50
0 to 1250
1251 to 1560
1561 to 2750
2751 to 4250
4251 to 5500
5501 to 7500
> 7500
Table 100-2 Target CFM50 Rates
Target CFM50 Rates
ASHRAE 62.2 CFM50 Rates
No air leakage
80% of existing CFM50
CFM50 not to drop below 1250
72% of existing CFM50
80% of existing CFM50
64% of existing CFM50
70% of existing CFM50
56% of existing CFM50
60% of existing CFM50
48% of existing CFM50
55% of existing CFM50
44% of existing CFM50
50% of existing CFM50
40% of existing CFM50
Deferred Air Sealing
Air sealing should be done in all homes; however, air sealing work may have been deferred until the following
conditions are corrected.
• Presence of unvented space heaters (note that no weatherization may occur in the home
until unvented space heaters are removed).
• Worst case depressurization limit exceeded (see section titled, “Worst Case
Depressurization”),
• Appliance fails spillage test-out (see section titled, “Spillage Test-Out”)
• Measured drafts of combustion appliances do not meet standards under worst case
conditions (see section titled, “Draft Test”),
• Carbon monoxide levels exceed suggested action levels (see section 3124, “Carbon Monoxide
Testing”),
• Evidence of serious mold issues (an area of mold greater than 10 ft) or
• The existing CFM50 leakage rate is lower than the Building Tightness Limit and
.
mechanical ventilation cannot be provided
Post-Blower Door Test
The following items should be checked prior to leaving the home following a blower door test.
• Inspect all pilot lights of combustion appliances to ensure that blower door testing did not
extinguish them.
• Reset thermostats of heating appliances and water heaters that were turned down or off for
testing.
ASHRAE 62.2-2010
ASHRAE 62.2-2010, “Ventilation and Acceptable Indoor Air Quality in Low-Rise Residential Buildings”,
defines minimum requirements for mechanical and natural ventilation intended to provide acceptable
indoor air quality in low-rise buildings. Low-rise buildings are defined as buildings that are three
stories or less, including single-family homes.
The type of ventilation system and required ventilation rate will be specified by the Weatherization Agency
for each house. This information will be included on the work order. Ventilation systems and installation
standards are found in Section 511, “ASHRAE 62.2-2010”.
All homes weatherized must meet the requirements of ASHRAE 62.2-2010. All architectural and
XIV.4
mechanical contractors should familiarize themselves with these requirements. A summary of those
requirements is provided here.
• Whole house continuous ventilation may be required (includes apartments)
• Required base ventilation is determined by house size and number of bedrooms (Table 100-3) or by
number of people living in the home (occupancy)
• Required ventilation must be increased if bathroom and kitchen exhaust fans are not
existing or existing exhaust flow rates are insufficient
• Required ventilation may be reduced based on flow rates of existing bathroom and kitchen
exhaust fans (fans must be measured to get full credit)
• Required ventilation may be reduced based on the air leakage rate of home as determined by a
blower door test
• If the required fan size is 15 CFM or less, continuous ventilation is not required
Zone Pressures
The blower door can be an effective tool at finding direct leaks by depressurizing the house and looking
or feeling for airflow through leaks. However, leaking air often takes a path through two surfaces that
have a space, or zone, between them. These leakage sites may be difficult to find because they are in
unconditioned spaces of a house. Once found, these leaks may be the largest and easiest leaks to seal.
Table 100-3 Ventilation Air Requirements (CFM)
Floor Area (ft2)
<500
501 - 1000
1001 - 1500
1501 - 2000
2001- 2500
2501 - 3000
3001 - 3500
3501 - 4000
4001 - 4500
4501 - 5000
5001 - 5500
5501 - 6000
6001 - 6500
6501 - 7000
7001 - 7500
> 7500
Bedrooms
1
2
3
4
5
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
105
27.5
32.5
37.5
42.5
47.5
52.5
57.5
62.5
67.5
72.5
77.5
82.5
87.5
92.5
97.5
112.5
35
40
45
50
55
60
65
70
75
80
85
90
95
100
105
120
42.5
47.5
52.5
57.5
62.5
67.5
72.5
77.5
82.5
87.5
92.5
97.5
102.5
107.5
112.5
127.5
50
55
60
65
70
75
80
85
90
95
100
105
110
115
120
135
A “zone” is a space that separates a heated space from the outdoors. Typical zones include attics, knee wall
spaces, crawl spaces and enclosed garages. The inner boundaries of these zones are building components
XIV.5
such as walls, ceilings or floors that separate these zones from the conditioned space. The outer boundaries
of these zones are the walls, roofs and foundation walls that separate a zone from the outdoors.
Zone-to-outside pressure readings provide information on the relative leakiness between the house and
zones and are described in a later section, “Zone-to-Outside Readings”. Zone pressure testing procedures
are described in a later section. The area of the “hole” between the house and the zone can then be
determined by “adding a hole”. That procedure is described in the section titled “Add-a- Hole” Method.
Zone-to-Outside Readings
A pressure difference from the zone to the outside is measured with the blower door depressurizing the
house to -50 Pa. The pressure measured between the zone and the outside can indicate the relative
leakiness of the zone.
Zone-to-outside readings of 0 to -25 Pa indicate that the air barrier between the living space and zone is
tighter than the boundary between the zone and outside (for example, the ceiling is tighter than the roof
in an unfinished attic). For zones that should be outside the thermal boundary, this is good because the
air barrier is in line with the thermal barrier. However, the air barrier (ceiling) should be made tighter if
the pressure reading is more negative than -5 Pa. Pressure readings more negative than -5 Pa indicate
that bypasses are present in the ceiling. Bypasses must be sealed.
Zone-to-outside readings of -25 Pa to -50 Pa indicate that the air barrier between the zone and outside is
tighter than the air barrier between the living space and zone. For example, the crawl space foundation
walls are tighter than the floor between the crawl space and conditioned area. If the crawl space
foundation walls are the thermal boundary, holes in the foundation wall should be sealed until the
pressure difference between the crawl space and outside is more negative than -45
Pa.
Zone-to-outside readings around -25 Pa indicate that the air
barrier between the zone and conditioned space and the air
barrier between the zone and outside are equally leaky.
Zone pressure readings unto themselves may be misleading. For example, an attic-to-outside reading of 15 Pa may seem to indicate significant bypasses. However, when tested with the “Add-a-Hole” method,
the size of the hole may be small and not worth the effort to air-seal
Zone Pressure Testing Procedures
Utilize the following procedures for measuring zone pressures and determining leakage areas with the
“Add- a-Hole” method in attics, knee wall spaces, crawl spaces and attached or tuck-under garages.
Measuring Zone Pressures
• Identify zones to be measured.
• Set-up blower door for house air leakage test.
• Set-up a hose to measure pressure in a zone. Make sure that end of hose extends beyond
insulation, flooring or other obstructions in the zone.
• Close opening (door, access hatch) between zone and conditioned space, taking care not to pinch
hose.
XIV.6
• Depressurize house to -50 Pa.
• Record CFM50 of house (CFM501).
• Connect hose from zone to “input” tap on manometer. Connect hose from the outside to
“reference” tap on the same channel as the hose from the zone.
• Record pressure of zone with reference to the outside - Z/O1.
• Compare readings to those shown in Table 100-4.
• Continue with the “Add-a-Hole” Method to determine cumulative hole size.
Table 100-4 – Zone Pressure Readings
Zone
Attic
Knee wall space
Crawl Space
Attached or tuck-under garage
Basement
Thermal Boundary Location
Top floor ceiling and attic space
Knee wall and knee wall cavity,
or
Knee wall space and roof
Foundation wall and crawl space, or
Floor between house and crawl
space
Between house and garage
Basement foundation walls
Zone Pressure Reading
0 to -5 Pa wrt outside
0 to -5 Pa wrt outside
- 45 to -50 Pa wrt outside
- 45 to -50 Pa wrt outside
0 to -5 Pa wrt outside
0 to -5 Pa wrt outside
-45 to -50 Pa wrt outside
“Add-a-Hole” Method
The “Add-a Hole” Method is method to estimate the total size of all the holes and bypasses in a zone being
measured. This will provide guidance towards existing opportunities for air sealing in the zone. Continue
with the following procedure to determine the cumulative hole size between the house and a zone.
• Turn-off blower door and partially open door or access opening between house and zone.
• Turn-on blower door and record new CFM50 of house (CFM502).
• Connect hose from zone to input as described above and record zone pressure (Z/O2). If the zone
pressure has not changed by more than 6.0 Pa, make the opening larger.
• Determine CFM50 difference (CFM502 – CFM501)
• Identify multiplier from Table 100-5 based on Z/O1 and Z/O2. Use Table 100-6 if an opening was
created between the zone and outside (opening an exterior crawl space hatch, for example).
• Use tables 100-7 or 100-8 if measuring an attached or tuck-under garage.
• Multiply CFM50 difference by multiplier to determine total leakage from zone to house.
This is the total CFM50 leakage between the zone and house.
• Divide total leakage by 10 to determine cumulative hole size in square inches.
2
• If relative hole size is less than 20 in (200 CFM50), no air sealing is required
regardless of zone pressure reading.
Zone Pressure Standards
General thermal boundary (air barrier and insulation) locations and required zone pressure readings
XIV.7
following weatherization work are shown in Table 100-4. If cumulative hole size is less than 20 in2 (200
CFM50), no air sealing is required regardless of zone pressure reading.
Pressure-Pan Duct Test
The pressure-pan test is a duct leakage diagnostic tool that is used with the blower door and digital
pressure gauge to identify duct leakage to outside the pressure boundary of the home. A gasketed pan is
placed over each register or grille with the air handler fan off and the blower door depressurizing the
house to -50 Pa2. A pressure measurement between the duct and the room where the duct register or
grille is located provides an indication of whether duct leakage to the outdoors exists.
Note that you must first turn off or push the “CLEAR” button on the DG700 manometer after doing the
blower door test to eliminate the “Adjusted Baseline Pressure” before taking pressure-pan readings. There
is no need to use or establish a new baseline as you’re simply measuring the pressure difference between
the ducts and conditioned space. This is not an issue if using the older DG3 manometer.
Pressure-pan testing is required when ducts are found in:
• Unconditioned spaces (some examples include attics, behind knee walls, tuck-under garages, crawl
space where the floor is the thermal boundary), or
• On basement return ducts when a hazardous venting or indoor air quality problem has been
identified such as:
 worst case depressurization limits have been
exceeded,
 poor draft with the furnace air handler
operating, or
 elevated moisture levels in the home
associated with wet basements.
Pressure-pan testing is not required on ducts located in conditioned spaces.
Pressure-Pan Procedures
• Install blower door and set-up house for winter conditions. Open all interior doors (see house SetUp”).
• Turn furnace off. Remove furnace filter and tape filter slot. Ensure that all grilles, registers, and
dampers are fully open. If the pressure-pan test is being done on a house with ducts in an
unconditioned space, seal supply and return air registers in the unconditioned space with tape. If the
test is being done on return ducts in a basement, only seal supply registers in the basement but leave
return grilles open.
• Temporarily seal any outside fresh-air intakes to the duct system.
• Open attics, crawl spaces that are intended to be outside of the pressure boundary (e.g. vented
crawl spaces with insulation under the floor of the house), and garages as much as possible to
the outside.
• Close door to basement if testing ducts in basements. If possible, open a basement window or
basement door to the outside. Tape the bottom of the basement door to further isolate the
basement from the living space if necessary.
If using DG700 manometer, turn-off to eliminate the “Adjusted Baseline Reading” from the blower
door test as noted above. Turn manometer back- on; do not establish a new baseline reading.
XIV.8
•
Connect a hose between the pressure-pan and the input tap on the digital manometer. Leave the
reference tap open.
With the blower door at -50 Pa, place the pressure-pan completely over a grille or register
to form a tight seal. Record the reading. Note that only one register is sealed at a time.
•If a grille is too large or a supply register is difficult to access (under a kitchen cabinet, for example) or
a pressure pan is not available, seal the grille or register with duct-mask tape or duct tape. Insert a
pressure probe through the duct-mask tape and record reading. Remove tape following reading.
Note that no air should be coming out of registers when the blower door is operating. If air is felt coming out of
a register, check to ensure that air handler is not operating. Otherwise, it’s a duct leak.
Pressure pan readings greater than 2.0 Pa may indicate a leak between the duct boot and subfloor/wall/ceiling
rather than a breach in the duct system. Remove registers on ducts with elevated readings and inspect the boot
connection. Seal boots and re-test with the pressure-pan.
Pressure-Pan Standards
Following weatherization work;
• No more than half of the pressure-pan readings shall be higher than 4.0 Pa and
• No readings shall be greater than 8.0 Pa.
Duct-Induced Room Pressure Test
An improperly balanced air-handling system can cause comfort, building durability and indoor air quality
problems. An imbalance between the supply and return sides of the distribution can be caused by duct
leakage to the outside, restricted/inadequate returns and/or the restriction of supply flow back to the main
living spaces of the house. This test measures pressure differences between the main body of the house
and each room, including the combustion appliance zone (or basement). This test is required as part of the
worst case depressurization test (see section titled, “Measuring Worst Case Depressurization).
Duct-Induced Standards
Pressure differences greater than +3.0 Pa or more negative than -3.0 Pa shall be corrected.
Interpreting Room Pressures
Provide pressure relief when pressures are more than + or -3.0 Pa between a room and the main body of
the house with the air handler operating.
To estimate the amount of pressure relief, slowly open door until pressure difference drops between +3.0
Pa and -3.0 Pa. Estimate area of open door. This is the area required to provide pressure relief. Pressure
relief may include undercutting the door, installing transfer grilles or installing jumper ducts.
Transfer areas and ducts are sized based on the equation shown below. If grilles are being installed to
correct room pressures, assume that the free ventilation area of the grille is no more than 80% of its total
area.
XIV.9
To calculate the finished grille size, divide the transfer area – A –by 0.8.
A = Q/1.853
where:
A = area in square inches
Q = air flow rate (ft3/min)
For example, a bedroom supply register has a flow rate of 100 CFM. The free area required for return air
is 54 in2 (100/1.853 = 54). If a transfer grille is to be installed between the bedroom and hallway, the
area of the grille should be at least 68 in2 (54/0.8 = 68).
Exhaust Fan Flow Meter Test
The exhaust fan flow meter is used to measure the air flow through bathroom exhaust fans. The flow
meter is used with the digital manometer. This test must be done to confirm flow rates if exhaust fans
are used to meet ASHRAE
62.2-2010.
Exhaust Fan Flow Meter Procedures
• Connect one end of hose to pressure tap on the flow hood.
• Slide door on flow meter to either the E1, E2 or E3 position.
• Connect other end of hose to input tap on left side of manometer.
• Select E1, E2 or E3 on the manometer to match door opening on flow meter (see
manometer instructions for selection process).
• Place flow meter completely over fan forming an air- tight seal (flow meter will not work
for kitchen exhaust fans).
Spillage Test-Out
Architectural contractors and crews are required to conduct a spillage test-out every day following
completion of work. This test is to ensure that architectural work done that day has not adversely affected
natural draft appliance venting. This test is only required for natural draft appliances.
Note that this test is required following completion of work every day – not only at job completion.
1. Close all windows and exterior doors. Close fireplace damper.
2. Close all interior doors, including door to combustion appliance zone (CAZ)3. Leave doors to
rooms with exhaust fans, such as bathrooms and kitchens, open.
3. Turn on clothes dryer. Turn on all exhaust fans, such as bathroom and kitchen exhaust fans,
such that they operate at maximum speed. Do not turn on whole house fans.
4. Turn-on natural draft appliance. Test for spillage at the draft diverter or draft hood with a mirror
or smoke pencil.
5. Draft must be established within three minutes. If appliance begins drafting within three
minutes, the appliance passes the test. If appliance does not begin drafting within three
minutes, turn-off appliance and open window if possible. Check for blocked flue or chimney. If
blockage is found and removed, repeat spillage test. Appliance that fails spillage test-out may
not be left in that condition.
XIV.10
Architectural Standards
The architectural standards include insulation and air sealing measures. Insulation retrofits are designed to
reduce heat loss by conduction. Air sealing measures are designed to reduce infiltration heat loss. It is
important that both conduction and infiltration measures work together. If insulation is added to an attic
but bypass air sealing is not done, the effectiveness of the insulation is greatly diminished. It is critical that
insulation and air sealing be done in the same building plane if the thermal boundary is to be effective.
Thermal Boundary
The thermal boundary separates conditioned space from
unconditioned space. Typically,
the thermal boundary in a house consists of the exterior
walls, top floor ceiling and foundation walls. The thermal
boundary is defined by the placement of insulation. The
building component that separates the conditioned space
from the outdoors or unconditioned space is the primary
pressure boundary. In order to maximize the effectiveness
of the thermal boundary, the pressure boundary must be
aligned with it. That is, the pressure boundary must be part
of the thermal boundary. If the insulation and air barrier are
not aligned; that is, located in different building
components, air can pass around or through thethermal
boundary, making the insulation less effective.
Basement walls are generally part of the home’s thermal boundary (see section titled, “Basements”). As
such, the basement ceiling is not insulated nor are bypasses in the basement ceiling air sealed for energy
savings. If it is determined that the basement walls are not part of the thermal boundary, the basement
ceiling may be insulated and air sealed. Ceilings in basements with the following characteristics may be
considered the thermal boundary:
• Space heating and water heating appliances are not located in the basement,
• It is clear that the occupants do not use the basement on a regular basis; for example, access to the
basement is through an exterior door or hatch, or
• Basement moisture problems that weatherization work cannot solve.
The work order will define the thermal boundary of the home as determined by the assessor. In some
cases, there is no right or wrong answer; only implications to the assessor’s decision. How does the home
owner use the space (is it a living space even though it was not originally intended to be)? Does the budget
or SIR priority permit for the ideal thermal boundary or does a concession need to be made (the assessor
would like to insulate the floor above the crawl, water lines and duct work but can only afford to insulate
the walls and install a ground cover)?
Do we want to expand the heated area of the home (insulating the rafter cavity rather than insulating
and air sealing the knee walls and outer ceiling joists, for example)? What are the costs?
XIV.11
The work order will reflect these decisions. Contractors should contact the assessor to further discuss the
thermal boundary definition if there are questions. Under no circumstances shall the contractor change
the thermal boundary location without first discussing the implications with the assessor.
Reducing Air Leakage
Air leakage reduction has always been one of weatherization’s most important functions. Measures in the
early days of Weatherization were limited to storm windows, storm doors, weather-stripping and caulking
– all with the intention of reducing air leakage. But these measures were not always very successful.
Later came the blower door and advanced air sealing, again with the intent of reducing air leakage. Air
sealing was much more successful, but now it was possible to make a home too tight. Air sealing had to be
balanced against making a home too tight and creating indoor air quality problems.
As required by the US Department of Energy, the Illinois WAP will adopt ASHRAE 62.2, “Ventilation and
Acceptable Indoor Air Quality in Low-Rise Residential Buildings”, in July 2012. This Standard requires the
installation of mechanical ventilation systems in most homes. Homes can now be made much tighter (as
tight as you can get them) increasing energy savings without creating indoor air quality problems.
Objectives of air leakage reduction are to:
• Save energy by cutting air leakage,
• Maximize insulation’s thermal resistance by reducing air movement through it,
• Avoid moisture migration into building cavities, and
• Increase comfort.
Combustion appliances still have to vent properly, especially now that homes can be much tighter.
Testing
Architectural contractors are required to conduct the following two tests;
• Intermediate blower door readings and
• Spillage Test-Out
Contractors are required to take intermediate blower door readings (see section titled,
“Intermediate Blower Door Test”) to measure effectiveness of their air sealing work.
It is required that contractors conduct Spillage Test-Out following work each day to ensure that spillage
will not occur in the combustion appliance zones as a result of tightening the home (see section titled,
“Spillage Test-Out”).
Air sealing work must also be inspected to ensure that the work was done properly and the work is
effective at air sealing.
Depressurize the home. While in the attic, for example, air will be drawn into the home. Bypasses can be
sealed while the home is being depressurized. Spray foams (both 1- and 2-part) will be drawn into the
joint to help seal it.
Alternately, turn the blower door around to pressurize the house (older fans have a direction switch that
XIV.12
can be used to reverse the direction of air flow). Move around the attic with a smoke stick. Air will be
moving up into the attic and those are the bypasses that need to be sealed. Be sure the attic hatch or door
is closed to increase pressure in the home. Pressure testing the house may assist in finding air leakage
locations if air sealing efforts are not effective, particularly in attics, knee wall cavities and attached or
tuck-under garages.
Sealing Bypasses
Bypasses are holes and gaps in the thermal boundary that
connect conditioned space with unconditioned space. The effort
worth expending to seal a bypass depends primarily on its size
and location. Bypasses will be found between the conditioned
space and attic, conditioned space and crawl space and
conditioned space and attached garages.
Seal larger bypass openings first to achieve larger air leakage reductions. There will be cases where sealing an
important bypass won’t necessarily reduce air leakage. For example, a chaseway in a plumbing wall tightly
sealed from the house but very leaky to the attic acts as an insulation bypass without actually leaking air
between the house and the attic. Even though the house air leakage may not be reduced, the attic insulation
performance will improve after this attic bypass is sealed.
It is always preferable to use strong air-barrier materials like plywood or gypsum board to seal bypasses. These
materials should be attached with mechanical and/or adhesive bonds. Strong materials with strong bonds are
best practice because air barriers must be able to resist severe wind pressures. When bypasses are not easily
accessible, blow dense-packed cellulose insulation into surrounding cavities so that the cellulose will resist
airflow and clog cracks between buildings.
All bypasses are to be sealed prior to insulating except where dense-packed cellulose is also being used to
seal bypasses.
•Joist spaces under knee walls in finished attic areas:
Connect knee wall air barriers on two floors by creating a
rigid seal under the knee wall in one of two ways.
 Install minimum 1inch thick rigid foam board
insulation blocks between ceiling joists. The
perimeter of the foam blocks should be
sealed with two-part foam.
 Tightly fill garbage bags or empty cellulose
bags with cellulose or fiberglass; stuff
between ceiling joists under knee wall and
seal perimeter with two-part foam.
•Kitchen or bathroom interior soffits: Seal the top of the
soffit with plywood, gypsum board or rigid foam board
insulation; fasten and seal to ceiling joists and soffit
framing with two-part spray foam.
•Two-level attics in split-level houses:
 Seal the wall cavity with a rigid material
fastened to studs and wall material, or
 block stud cavity with scrap batt insulation
and cover with 2-part spray foam (Figures
200-4 & 200-5), or
 Tightly fill garbage bags or empty cellulose
bags with cellulose or fiberglass; stuff in wall
cavity and seal perimeter with two-part spray
foam.
•Tops and bottoms of balloon framed interior partition
wall cavities, missing top plates:
 Seal with rigid barrier, like ¼ inch plywood,
gypsum board or rigid foam board
insulation and caulk or foam to surround
materials, or
 Block stud cavity with scrap batt insulation
and cover with 2-part spray foam, or tightly
fill garbage bags or empty cellulose bags
with ceullulose or fiberglass; stuff in wall
cavity and seal perimeter with two-part
spray foam.
Figure 200-4: Stud cavity sealed
with 2- part spray foam
Figure 200-5: Study cavity
blocked with batt insulation and
sealed with 2-part spray foam
•Fur cavity in masonry buildings: Seal cavity with two-part
foam around perimeter of attic/roof cavity.
•Chimney passing through attic floor: Seal chimney and
fireplace bypasses with sheet metal (minimum 26 gauge
thickness) and seal to chimney or flue and ceiling structure with
high temperature sealant or chimney cement. This requirement
does not apply to chimneys that are no longer used and have
been permanently sealed with concrete both at the vent
connector to the chimney and at the top of the chimney.
•Soil stacks, plumbing vents, open plumbing walls: Seal joints
with two-part foam or caulk. If joint is too large, stuff with
fiberglass insulation or seal with rigid foam board and foam over
the top (Figure 200-7).
Figure 200-7: Plumbing wall cavity
sealed with foam board and 2-part
spray foam
•Housings of existing exhaust fans and recessed lights: Caulk
joints where housing comes in contact with the ceiling (see
“Attic Insulation Standards” for boxing and air sealing around
recess lights and exhaust fan housings1).
•Duct boots and registers: Caulk, foam or use butyl or foilback tape to seal joint between duct boot or registers and
ceiling, wall, or floor finish if ducts are located in attic, crawl
space or attached or tuck-under garage.
•Wiring and conduit penetrations: Seal joint with caulk or
foam.
Figure 200-8: Duct chase sealed
with foam board and 2-part spray
foam
•Duct chases: If chase opening is large, seal with rigid barrier
such as plywood, gypsum board or rigid foam board and seal to
ducts and ceiling materials (Figure 200-8). Smaller openings
may be foamed or stuffed and caulked.
•Joists between floors: Air seal perimeter of building at band
joist areas with dense pack cellulose or fiberglass.
•Bathtubs and shower stalls: Seal from crawl space or
basement in one of two ways:

Seal with two-part foam or rigid material for
larger openings.
Cover opening with gypsum board. Cut hole

and dense-pack cavity. Seal hole and gypsum board to
surrounding framing materials with two-part foam
(Figure 200-9).
XIV.15
Figure 200-9: Cavity beneath
bathtub sealed with gypsum board
and dense- packed with cellulose.
•Attic hatches and stairwell drops: See section titled, “Attic Access Hatches”.
•Other openings in the air barrier: Seal with rigid material, two-part foam, one- part foam or
caulk depending upon size of opening.
Bypass Sealing Materials
Materials used to seal air leakage sites must be nearly impermeable to air movement as possible
and form a continuous, nonporous surface over the opening being
sealed. All materials must meet CFR440 specifications.
Spray Foams
Spray foams are either 1-part (sealant contained in one
canister) or 2-part (chemicals contained in two canisters and
mixed at the gun). 1-part foam is generally low or nonexpanding. 2-part foam may expand 3 to 1.
MSD sheets and manufacturer’s instructions must be closely
followed to ensure safety. Provide notification to the client of
plans to use two-part spray foam. Provide ventilation as
necessary to prevent or dilute fumes that may get inside the
home.
Figure 200-10

1-Part Foam (Figure 200-10)
 1-part foam dispensed through plastic nozzles is not permitted. 1-part foam
must be installed with a foam gun.
 Surface areas to be foamed must be cleaned of dust and debris with a rag.
 Surface areas to be foamed must be misted with water, particularly in cooler
temperatures when humidity levels are low.
 Spray foam must be installed when the ambient temperature is between 40oF
o
and 100 F, unless spray foam manufacturer recommends other temperatures.
 Bead size should be no more than 2 inches.
 1-part foam should have a Flame Spread rating of 25 or less.
XIV.16
February 2013

2 -Part Foam
 2-part spray foam should be installed when the ambient temperature is
between 60oF and 90oF, unless spray foam manufacturer recommends other
temperatures.
 Spray foam canisters should be brought to 70oF to 80oF before use.
 Surfaces to be foamed should be cleaned of debris.
 Should be used on gaps 2 inches or larger.
 2-part foam should have a Flame Spread rating of 25 or less.
Caulks/Sealants
Caulk should be applied according to the manufacturer’s instructions. Caulk should be
applied to a smooth, clean, dry surface. It should always be applied in a continuous bead
and free of voids, with a smooth and neat appearance. Excess caulk should be removed
before it cures.
All openings 3/8 inch to 7/8 inch wide should be filled to within ½ inch of the surface with
an appropriate packing material specifically manufactured as a packing material prior to
caulking. All packing material should be compatible with the type of caulk used.
 Latex/Acrylic/Silicone Hybrids – must conform to ASTM C834
 Acrylic (solvent type), chlorosulfonated polyethylene – must conform to F.S.
TT-S- 00230C
 Butyl Rubber – must conform to F.S. TT-S-001657
Packing Materials
Packing materials used to fill gaps too large for caulks or sealants to seal properly must be
flexible closed cell or otherwise nonporous materials that will not absorb moisture and will
remain flexible at low temperatures. Packing materials include flexible polyurethane,
oakum, butyl rod or similar foam rod stock.
Fiberglass is not to be used as an air sealing material, but may be used to stuff larger
openings as a backer material with spray foam applied over the top of it. Tops of open wall
cavities may also be stuffed with fiberglass which will be dense-packed with insulation.
Air Barrier Materials
The following air barrier materials shall be used for the following conditions:
 Polyethylene
 Should have a minimum thickness of 6 mil and be used as an interior
barrier material when moisture must be kept out of the conditioned
space.
 Spun olefin (Tyvek, Typar, etc)
 Spun olefin membrane air infiltration barrier should be used when
moisture must escape from the conditioned space. These materials
are not recommended for use in a location where they remain cool
for most of the year, such as the floor above the crawl space or
basement ceiling. Water vapor will not move through these materials
if they are at or below the dew point temperature.
XIV.17
February 2013




Wood or wood composites
 Wood or wood composites should be used where flame retardant
characteristics are not important. When exposed to moisture or
weather, all raw exposed wood must be an exterior grade material
and primed on all sides.
Gypsum board
 Gypsum board should be used in interior applications where
excessive moisture is not a problem and where flame retardant
abilities are important.
Rigid foam board insulation
 Air sealing materials such as rigid foam board must be sealed in place
with caulk or spray foam to make it air tight. Polystyrene shall
conform to ASTM C576. Polyurethane and polyisocyanurate with foil
facing shall conform to F.S. HH-1.
Metal flashing
 Metal flashing should be used when high temperature or high
moisture is a factor.
General Air Sealing
The following general infiltration items are done as air sealing measures when identified
with the blower door.
•
Joints in sill plate (mud sill) and around utility openings in siding and foundation
shall be sealed in an appropriate manner. When a space between two metal
surfaces is to be sealed, only a butyl or silicone caulk shall be used. Cracks
between two masonry surfaces shall be sealed with cement patching compound
or mortar mix. If the opening is deeper than 3/8 inch, follow procedures
described above.
•
Interior joints shall be caulked. These joints include where baseboard, crown
molding and/or casing meet the wall/ceiling/floor surfaces. Gaps around
mounted or recessed light fixtures and ventilation fans shall be caulked. Cover
gap between the chimney and structural members (chaseways) in the
basement/crawl space with a heat resistant material (flashing, gypsum board,
etc.) and seal with a compatible sealant.
Attic Insulation
Safety
Comply with fire and electrical safety procedures before insulating.
•
Recessed light fixtures must be enclosed with gypsum board to prevent
overheating and/or fire. Provide a minimum 3 inch clearance between
the box and the sides of the fixture. The box should be constructed to a
height that will be 4 inches above the installed insulation. Cover the box
with gypsum board and seal to the sides of the box. The box is not to be
covered with insulation. If there is insufficient clearance to install a box 4
inches higher than the insulation, do not cover the box and use an
appropriate barrier to keep the insulation 3 inches away from the fixture.
XIV.18
February 2013
•
•
•
•
•
•
•
•
•
•
•
If recessed lights are certified as Insulation Contact (IC rated) and airtight, they may have insulation installed directly over them. The blower
door should be utilized to test the air seal of the light. Many times, the
light fixture itself still needs to be air-sealed around the perimeter base
where it meets the ceiling.
Existing bathroom exhaust fans do not have to be enclosed as described
above unless the fans include a heat lamp and/or have incandescent
lamps.
New bathroom exhaust fans installed by the Weatherization Program
must be rated such that they may be covered with insulation.
Seal bypasses around chimneys and metal flues with 26 gauge galvanized
metal sealed with high temperature caulk to chimney or vent and
surrounding framing materials.
Vertical metal used as a barrier around heat producing devices or
chimneys must be fastened securely to attic joists in such a manner as to
not allow the barrier to collapse when insulation is installed.
Clearance of insulation from attic furnaces must be provided in
accordance with the governing code.
Ventilated insulation shields should be installed around wood-stove
manufactured chimneys.
Install insulation beneath active knob-and-tube maintaining a one-inch
air space between insulation and wiring. Alternately, non-metallic
channels or barriers should be installed to maintain minimum one- inch
air space alongside of knob-and-tube wiring.
Frayed wiring must be repaired before adding insulation. Wiring splices
must be enclosed in metal or plastic electrical boxes, fitted with cover
plates. Closed electrical junction boxes may be covered with insulation, if
appropriately marked.
The perimeter of attic fans should be dammed with 1 inch thick nominal
common lumber, plywood, metal shielding or minimum 1 inch thick foam
board.
OSHA-approved breather masks must be worn when blowing insulation.
Attic Insulation Preparation
Bypasses
Air leakage and convection can significantly degrade the thermal resistance of attic
insulation. All attic bypasses as previously described must be sealed before attic insulation
is installed. Where existing attic insulation is present, consider pressurizing the house
with the blower door to help identify attic bypass locations (see section titled, “Testing”).
Roof Leaks
All roof leaks must be repaired before insulating attic. If roof leaks cannot be repaired,
contact the Weatherization Agency.
Exhaust Fans
All kitchen and bath fans currently venting into the attic must be equipped with backdraft
dampers and vented outdoors through roof or eave fascia boards. Appropriate exterior
termination kits such as wall caps, roof jacks and eave mounted vents shall also
XIV.19
February 2013
be installed if not present. Fans without operating dampers should be repaired or the fan
should be replaced with an ENERGY STAR rated fan. For additional information regarding
bathroom exhaust fans and exhaust fan duct installation, see sections 511, “ASHRAE 62.2”
and 513, “Exhaust Fan Ducts”.
Top Plates
Existing batt insulation over top plates is not to be compressed with scrap wood or gypsum
board. Compressed or ineffective insulation over top plates is to be replaced.
Eliminate wind washing through insulation where soffit venting exists. Block cavity over top
plate to prevent blown insulation from falling into soffit and to maximize insulation over
top plates.
Cavity may be blocked with two-part spray foam, rolled fiberglass insulation or other rigid
materials.
Mechanically fasten eave chutes between foam or blocking and roof sheathing to maintain
ventilation passageway. Chutes or blocking material is not to compress insulation.
In rafter cavities where a chute is not installed, ensure that cavity is blocked with a rigid
barrier as described above to prevent over-spill into the soffit area. Where possible, place
eave chutes in every rafter cavity that is vented. Chutes must be long enough to extend
above the level of the finished insulation
Unfinished Attics
Blowing Attic Insulation
It is recommended that blown insulation be used instead of batt insulation whenever
possible because blown insulation forms a seamless blanket.
Attic insulation shall achieve a total R-value of 49 or the maximum amount with an SIR
greater than 1.0 on the work order.
Insulation shall be installed to a uniform depth according to manufacturers’ specifications
for proper coverage (bags per square foot ratio) to attain the desired R-value at settled
density. Contractor shall install attic insulation markers throughout the attic area to ensure
that insulation is installed to both a uniform and proper depth. At a minimum, one marker
shall be installed for every 300 ft2 throughout the attic. Markers shall be affixed to trusses
or joists with the numbers a minimum 1 inch in height. Markers shall face such that they
can be read from the attic access opening.
Cellulose, blown rock wool or blown fiberglass insulation may be used to insulate
unfinished attics. If cellulose insulation is used, it must be treated with boric acid which is
used as a fire retardant (termed “borate only”).
Blown fiberglass may be used, but note that the R-value begins to decrease significantly
when the attic temperature drops below 30oF2 and be reduced by half when the attic
XIV.20
February 2013
temperature is -8oF3. The loss of R-value is due to establishment of convective air currents
in the insulation. This is not a problem with cellulose insulation or fiberglass batt insulation.
Do not blow loose-fill insulation tight against roof deck over top plates. Cellulose should
not be used where it may come in contact with exposed metal roofing.
Dense pack all attic cavities, such as slopes, window bays, flat roofs and attics if not
accessible for other installation methods. Install blown cellulose to 3.50 to 4.00 lbs/ft3.
Access these areas by drilling or removing the fascia board and tube filling each cavity.
Ventilation is not needed when dense packing flat roofs.
Floored Attics
Insulation shall not be blown more than 3 feet in any direction. Do not insulate cavity if live
knob-and-tube wiring is present beneath attic flooring.
Flooring should be removed at bypass locations for proper air sealing before insulation is
installed. Insulation should completely fill the floor cavity. Install blown cellulose to
3.50 to 4.00 lbs/ft3. Flooring boards that have been removed are to be re-installed. With
owner permission, flooring boards may be drilled and the cavity filled with blown
insulation. Entry holes are to be sealed with plastic or wood plugs.
Insulation may be blown over flooring with client’s permission. Blowing insulation over the
flooring may be done in addition to blowing the floor cavity – not in lieu of blowing the
floor cavity.
Batt Insulation
Batt insulation must be installed in such a manner to ensure proper fit between ceiling
joists. There must be no voids or gaps between batts or between batts and ceiling joists.
Insulation must fill joist cavity and provide uniform and complete coverage. If insulation
has vapor barrier backing, the vapor barrier shall be toward heated space. When insulation
with vapor barrier is installed over existing insulation, the vapor barrier shall either be
removed or slashed.
Cathedral Ceilings
Damaged ceiling areas must be repaired before insulating. Contact Weatherization Agency
if ceiling cannot be repaired. Do not insulate cathedral ceiling cavities that contain active
knob and tube wiring and have not been tested for safety, thermal bypasses, open
electrical boxes, blocking or recessed lighting fixtures.
Access to rafter cavities in cathedral ceilings may be gained through the soffit/fascia or
interior ceiling.
Top and bottom of open rafter cavities shall be blocked with fiberglass or other blocking
material. Dense pack cavities with cellulose insulation installed to a density between 3.50
to 4.00 lbs/ft3. Blown fiberglass is not recommended as it does not restrict the movement
of air through it. Interior access holes shall be plugged and sealed such that they can be
painted by the client.
XIV.21
February 2013
Attic ventilation is not needed when dense packing cathedral ceilings
Attic Access Hatches
Install permanent blocking around the attic access hatch. Use rigid materials such as
plywood that will support the weight of a person when accessing the attic. The barrier’s
purpose is to prevent loose-fill insulation from falling out of the attic when the attic hatch
is opened.
Attic hatches installed during weatherization should be large enough for a person to pass
through and allow for a thorough inspection of the attic. Openings must be at least 4
square feet and at least 20 inches in width or length.
An insulated box shall be built and installed over retractable attic stairways. Hatches to
attics shall be insulated to a minimum R30 with foam board insulation – hatches are not to
be insulated with batt insulation. Blocking around attic hatch shall also be insulated. Attic
insulation blown against and to the top of the blocking will suffice. Foam board may also be
used to insulate the blocking if the attic insulation does not insulate to the top of the
blocking.
Weatherstrip, other than peel-&-stick foam, shall be used to seal the attic hatch. Latches,
sash locks, gate hooks or two ½ inch thick pieces of gypsum board attached to the hatch
are to be used to provide positive closure.
Attic hatches must not be permanently sealed.
If attic is accessed by a stairwell and a standard vertical door, dense-pack cellulose
insulation should be blown into walls of the stairwell leading to passage door of the
unheated attic. Install threshold or door sweep and weatherstrip door.
Dense-pack cellulose insulation should also be blown into the cavity beneath the stair
treads and risers. Determine if blocking exists to stop insulation from filling other areas by
mistake when planning to insulate walls and stairway.
Finished Attics
The finished attic consists of five sections:
• Exterior finished attic walls (end walls of finished attic)
• Collar beams (above finished attic)
• Sloped roof (where wall/roof finish is installed directly to roof rafters)
• Knee walls (between finished attic and unconditioned attic space)
• Outer ceiling joists (between knee wall and top plate of exterior wall)
Attic bypasses shall be sealed before insulating.
Exterior Finished Attic Walls
Insulate exterior finished attic walls per section 214, “Wall Insulation”.
Collar Beams & Outer Ceiling Joists Insulate collar beams and outer ceiling joists per section
2133, “Unfinished Attics”.
XIV.22
February 2013
Sloped Roof (roof rafters)
Sloped roofs (roof rafters) shall be tightly stuffed with fiberglass or some other stuffing
material at either the top or the bottom of each run. Where possible, insulate sloped roof
with dense pack cellulose installed to density of 3.50 to 4.00 lbs/ft3.
If the sloped areas have existing fiberglass insulation, the top and the bottom of each cavity
may be sealed and the cavity insulated with dense-pack cellulose.
Knee Walls
Open knee wall cavities may be insulated in one of four manners. One method may be
used for closed cavity knee walls.
• Open Cavity – Single Batt
• Open Cavity – Double Batt
• Open Cavity – Spray Foam
• Open Cavity – Dense Packed
• Closed Cavity Knee Wall
Knee walls may also be within the conditioned space. If so, roof rafters shall be insulated
rather than the knee walls. See “Knee Wall within Conditioned Space”.
Open Cavity – Single Batt
Insulate knee walls with maximum R-value as allowed by stud cavity depth. Extend batt
insulation down to bottom plate of knee wall. Ensure that joist cavity beneath knee wall
has been air sealed (see section titled, “Sealing Bypasses”). Insulation shall fit snugly
between the studs.
Batt insulation should be installed with the kraft paper installed towards the conditioned
space. Batt insulation installed with fibers exposed to the knee wall cavity shall be covered
with an air barrier material to prevent convective looping within the insulation and to
prevent fiberglass exposure. House wrap material, “belly patch” or ½ inch insulated foam
sheathing may be used to cover the insulation.
Open Cavity –Double Batt
Knee wall insulation R-value may be increased with the addition of another layer of batt
insulation.
• Install first layer of batt insulation as described above but with the kraft
paper facing out towards the knee wall cavity.
• Secure insulation by stapling the flanges to the face of the knee wall
studs – no inset stapling.
• Install second layer of faced batt insulation horizontal to the first layer of
insulation. Kraft paper should face towards the knee wall. Secure second
layer of insulation by face stapling insulation flanges to the knee wall
studs.
• Enclose exposed fibers of insulation with a house wrap air barrier as
described above.
Open Cavity – Spray Foam
XIV.23
February 2013
Install closed-cell spray foam to back side of knee wall finish. Insulation shall be a minimum
3 inches thick (R18). An air barrier over the insulation is not required. However, insulation
shall be covered with a fired-rated material if required by local code.
Open Cavity - Dense Packed
Close-in knee wall studs with house wrap material, “belly-patch” or ½ inch insulated foam
sheathing using plastic-ring head nails. Spacenails no more than 3 inches apart. Secure
material to top and bottom of knee wall to keep insulation in knee wall. If necessary, install
additional horizontal or vertical strapping to secure material to studs prior to dense
packing. Polyethylene or similar vapor barrier material shall not be used for knee wall
enclosure.
Cut holes in knee wall material and insulate with dense pack cellulose (3.5-4.0 lbs/ft3).
Closed Cavity - Knee Wall
Insulate closed cavity knee walls per section titled, “Wall Insulation”.
Knee Wall within Conditioned Space
Insulate rafter cavity with maximum R-value as allowed by rafter cavity depth when space
behind the knee wall is considered part of the conditioned space. The attic floor cavity over
the top plate must be air sealed and insulated to connect the thermal boundary from the
sidewalls to the roof .Use rigid foam board or 2-part spray foam insulation.
Knee Wall Hatches
The access should be properly framed, be as wide as the knee wall stud cavity and be 20
inches high. The access cover should be a durable, rigid material and securely attached
with appropriate hardware. Access hatch should be weatherstripped with something other
than peel-&-stick foam. Hatches should be insulated to the same R-value as the knee walls
with a minimum of R-value of
13. Batt or foam board insulation may be used. Window casing may be used as interior trim
around hatch opening. Joints in the casing should be caulked prior to painting.
Existing knee wall access hatches should be weatherstripped (no peel-&-stick foam) and
insulated with a minimum of R13 batt or insulated foam board. A new access cover of a
durable rigid material should be installed if necessary.
Attic Venting
Installing attic ventilation or increasing attic ventilation is an optional measure and is left to
the discretion of the Weatherization Agency. There are very few reasons to install attic
ventilation. The actual color of the roofing medium or shingles has the most impact on
solar heat gain or reflection. The focus should be on controlling indoor relative humidity
issues and sealing attic
bypasses rather than calculating vent area and determining vent locations. If attic vents are
included as part of an overall attic air sealing/insulation strategy, the following guidelines
are to be met:
 Vent devices are not to permit rain or snow to enter the attic.
 Ridge vents are not to be installed on hip rafters.
 The structural integrity of a roof system should not be compromised for the sake of
XIV.24
February 2013


installing attic ventilation.
Venting in an attic does not make it acceptable to terminate bathroom, kitchen or
dryer vents in the attic.
If roof vents must be installed, an effort is to be made to install them on the least
visible roof surface.
Note that the installation of attic vents may be called for on the work order if an attic fan is present and
there are insufficient vents for make-up air when the fan is operating.
Existing Vents
Ensure that existing vents are not blocked, crushed or otherwise obstructed. If the net free ventilation
area of existing vents is not known, assume that it is half the area of the vent opening.
New Vents
If attic ventilation is to be installed, the vents shall be installed so there are equal amounts of low intake
vents through soffit or eaves and higher exit vents on the roof. All separate attic spaces are to be crossventilated with one inlet and one outlet vent.
Low/High Venting
Low (intake) vents should be placed at a minimum of 12 inches above the finished level of attic
insulation. Eave chutes or baffles should be provided over top plates where soffit and other low vents
could cause blowing of loose fill insulation.
High (exhaust) vents should be installed as close to the roof peak as possible in conjunction with lower
intake vents. If eave vents are not practical, other vents should be installed low on the roof.
Consideration should be given to maximizing cross ventilation.
Vents should be installed in accordance with manufacturers’ instructions and sealed with an appropriate
sealant. Vents should be installed in a manner to prevent the entrance of snow, rain, insects and
rodents.
Soffit Vents
Soffit vent products specifically designed for this purpose shall be used. Soffit vents should be installed
with the louvers facing toward the house. Vents may be nailed or screwed to the soffit.
Open area between eave chutes or baffles and the top plate must be blocked with a material, such as
rolled fiberglass or two-part foam, to prevent spillage of loose fill insulation into the soffit area and
potential blockage of the soffit vents.
Gable Vents
Gable end vents shall be installed as high in the gable end as possible and above the level of the attic
insulation. Existing gable vents should be boxed if insulation comes up to the bottom of the vent.
Framing members are not be cut or removed if gable vents are placed over them. Vent openings must
be neatly cut. The vent must be installed with nails or screws. Framing must be provided for the vent if
there is no sheathing behind the siding.
The perimeter of the vent must be properly caulked to prevent water entry. A gable vent used as an
attic access must be attached by screws and easily removable.
If gable vents are prone to wind driven rain or snow entry, exterior baffles shall be installed.
Roof Vents
Roof vents should never be installed on a roof that is in poor condition.
Roof vents are not to be installed over rafters. Vent openings must be neatly cut with close tolerance to
ensure a proper fit. High-mounted vents must be installed as high on the roof as practical. Vents should
be tucked under shingles as much as possible and may be either fastened with shingle nails and tarred
with roofing cement or nailed with neoprene-washer nails to ensure a leak-free installation. Surfacemounted roof vents are not allowed.
XIV.25
February 2013
Turbine vents may only be used as exhaust vents, i.e., in conjunction with soffit, gable or roof vents.
Ridge Vents
Pre-fabricated aluminum ridge vents are not permitted. Only ridge vents that can be capped with
shingles are to be installed. Manufacturer’s installation recommendations shall be followed, especially
with regards to the presence of a ridge board and terminating cuts from end walls and hip and ridge
intersections. Roof shingles and sheathing shall be cut without cutting roof rafters. Ridge cap shingles
shall be installed according to shingle manufacturer’s instructions.
Attic Insulation Certificate
Contractors installing blown-in insulation must permanently fasten to the roof side of the attic access (or
other accessible location specified by the Weatherization Agency) a signed certificate that attests to the
company name, date installed, insulation brand name, R-value added, square footage, thermal
resistance chart, conformance to
federal specifications and the number of bags installed in the attic.
Attic insulation markers shall be placed in locations throughout the attic such that insulation depth and
uniformity of coverage can be inspected.
At a minimum, one marker shall be installed for every 300 ft2 throughout the attic. Markers shall be
affixed to trusses or joists with the numbers a minimum 1 inch in height. Markers shall face such that
they can be read from the attic access opening.
Wall Insulation
Wall Insulation Preparation
Inspect walls for evidence of moisture damage. If existing condition of the siding, sheathing or interior
wall finish indicates an existing moisture problem, contact Weatherization Agency.
•
•
•
•
•
•
•
•
•
•
•
•
Inspect indoor areas on exterior walls to assure that they are strong enough to
withstand the application process. Contact Weatherization Agency if problems
are found on walls that would prevent sidewall insulation from being installed.
Inspect wall cavities for active knob-and-tube wiring. Wall cavities that contain
active knob-and-tube wiring are not to be insulated. Gaps in external window
trim and other areas that may leak water into the wall
must be sealed.
Seal interior openings from which insulation may escape, such as pocket doors,
balloon framing and unbacked cabinets, soffits, and closets.
Remove siding and drill through sheathing.
If siding cannot be removed, contact
Weatherization Agency.
Asbestos siding may be removed. Decision to remove asbestos siding should be
made on a home by home basis considering condition of siding.
Precautions shall be taken so as not to damage siding. Asbestos siding should
never be cut or drilled. If possible, insulate walls from the interior (see next
bullet point).
Insulation may be installed from the interior after written approval from the
homeowner is obtained by the Weatherization Agency. Interior holes drilled for
insulation must be finished and returned to condition as close to original as
possible.
Wall cavities must be probed to identify fire blocking, diagonal bracing, and
other obstacles. Drill additional holes as necessary to ensure complete
coverage.
Pulley wells no longer used for window operation must be packed with
insulation. Holes may be drilled through the jamb and sealed with plugs
following installation of insulation.
Dense-Packed Wall Insulation - Cellulose
• Contractors and crews installing dense-packed cellulose wall insulation must be
certified.
• Install insulation in accordance with the manufacturer’s recommended
application procedures.
• Drill minimum two- to three-inch diameter holes to access stud cavities. Avoid
drilling holes in vicinity of electrical outlets and switches.
February 2013
•
•
•
•
•
•
•
•
Dense-packed wall insulation is best installed using a blower equipped with
separate controls for air and material feed. The recommended insulation
blower takeoff pressure should be at least 3.5 pounds per square inch at
the exhaust port (96 inches of water column).
Cellulose insulation must be blown to a minimum of 3.50 pounds per cubic
foot density. This minimum density translates into just over one pound per
square foot in a two-by-four wall cavity. Blowing cellulose insulation this
densely requires a fill- tube. An eight-foot cavity should hold a minimum of
10 pounds of insulation.
The fill tube should be 1 inch or 1 ¼ inch inside diameter tubing with the
appropriate stiffness for the job and outdoor temperature.
Fill-tubes should be marked with one-foot intervals to verify the correct
penetration of the tube into the wall.
Except as previously noted, fill all wall cavities. In some cases wall cavities
close to critical framing junctures will take more insulation to plug and fill,
which is often necessary in order to assure the proper air sealing of the
house.
All wall cavities shall be completely filled with insulation leaving no voids.
Cut additional holes above or below stud cavity obstructions if necessary to
fill cavity.
Seal the holes with expandable foam or stuff tightly with fiberglass and cover
with sheathing tape. Cover the hole with adhesive backed roofing paper,
such as “ice & water shield”. Attach with minimum two staples to hold in
place.
Two-hole method
If the interior wall finish is too weak for dense-pack installation, the two-hole method is permitted
only if approval is received in advance of the work from the Weatherization Agency. Examples of
weak interior finish include plaster and lath in poor condition, drywall that is less than 1/2” thick
and in poor condition and wall paneling used as the interior finish.
• Drill 2 one-inch diameter holes into each stud cavity.
• Holes are to be located no more than 2 feet between the top plate and the
top holes; 2.5 feet between the bottom plate and bottom holes.
• Examine wall cavity with wire probes or steel tape to determine location of
cavities around window and door areas.
• Insulation to be installed in accordance with manufacturer’s recommended
application procedures.
• All wall cavities shall be completely filled with insulation leaving no voids.
• All wall cavities around windows and doors are to be filled with insulation.
Dense-Packed Wall Insulation – Fiberglass
• Contractors and crews installing dense-packed fiberglass wall insulation must
be certified to do so by the insulation manufacturer.
• Access to wood frame sidewalls shall be per section 2141, “Wall Insulation
Preparation”.
• Install insulation in accordance with the manufacturer’s recommended
XIV.27
February 2013
•
•
•
•
•
application procedures.
Dense-packed fiberglass wall insulation must be installed to a density of 2.25
pounds per cubic foot density. One 30 pound bag should fill 5 typical 2” x 4”
x 8’ stud cavities to achieve this density.
Drill minimum two- to three- inch diameter holes to access stud cavities.
Avoid drilling holes in vicinity of electrical outlets and switches.
The fill tube should be 1 inch or 1 ¼ inch inside diameter tubing with the
appropriate stiffness for the job and outdoor temperature.
Cut additional holes above or below stud cavity obstructions if necessary to
fill cavity.
Seal holes with tapered wood plugs. Seal the plug to sheathing to maintain
water seal integrity with caulk or other suitable patching material.
Injection Foam
•
•
•
•
•
•
Contractors and crews installing injection foam wall insulation must be
certified to do so by the insulation manufacturer.
Access to wood frame sidewalls shall be per section 2141, “Wall Insulation
Preparation”.
Install insulation in accordance with the manufacturer’s recommended
application procedures.
Wall cavities shall be completely filled with no voids or gaps.
Walls with existing batt insulation may be insulated with injection foam.
Seal holes with plastic, foam or wood plugs. Seal the plug to sheathing to
maintain water seal integrity with caulk or other suitable patching material.
Band joist Insulation
The band joist is the area between floors in a multi-story home. The band joist should be included as
part of a sidewall insulation retrofit. Only those parts of these floor cavities that border the exterior
must be insulated.
In platform-framed buildings, these cavities must be accessed from the rim or band joists. In balloon
framed buildings, these cavities are usually open to the walls, allowing access from the rim or band
joists and also from the wall cavities above or below these floor cavities. The R-value of the insulation
in these floor cavities must be at least equal to the R-value of the insulation installed in the adjacent
wall cavities.
Follow “Preparation” guidelines as described in section titled, “Wall Insulation Preparation”. Pay
particular attention to location of light fixtures, exhaust fans, wiring and ductwork located in ceilings
between floors.
•
•
•
Remove exterior finish material as described above in section titled, “Wall
Insulation Preparation”.
Drill 2 inch or 2-1/2 inch diameter holes to access each cavity between ceiling
joists.
Insert hose nozzle in cavity. Reduce air setting and raise flow on the hopper.
Spray insulation into cavity. The objective is to create an “insulation plug” in the
ceiling cavity usually within 3 feet to 4 feet from the band joist. Alternately, a
90o nozzle may be inserted into the cavity. An “insulation plug” will be created
closer to the band joist by spraying insulation up against the subfloor.
XIV.28
February 2013

Joist cavities on the remaining two sides of the home (where joists are parallel
to band joist) should be completely filled with insulation. Insert rigid fill tube
half the width of the cavity. Pack the joist cavity with insulation.
Open-Cavity Wall Insulation
Batt insulation must be cut to the exact length of the cavity. Each wall cavity should be completely
filled with batt insulation.
• If possible, use unfaced friction-fit batt insulation. Fluff to fill entire wall cavity.
• Staple faced insulation to outside face of studs - no inset stapling.
• Split batt around wiring rather than letting the wiring bunch the batt to one side
of the cavity.
• Insulate behind and around obstacles with scrap pieces of batt or spray foam
before installing batt.
• Install vapor retarder if required. Vapor barrier shall have a perm rating less
than one on the warm in winter side of the insulation. Vapor retarder should be
well fastened at all seams and edges.
• Installed fiberglass insulation exposed to the interior living space must be
covered with minimum 1/2-inch drywall or other material that has an ASTM
flame spread rating of 25 or less.
Completion of Wall Insulation
Ensure that no insulation dust or debris have been left in or around the house.
Duct system shall be inspected to assure that ducts are free of insulation. Turn on air handler and
look for signs of insulation. Provide information on the wall insulation application levels (R-value,
quantity of insulation, etc.) required by the certificate of insulation to be given to the client.
Crawl Space Insulation
The following items are required regardless of the location of the crawl space thermal boundary.
•
An effective ground moisture barrier must be present or one should be installed as part
of weatherization. See section 2154, “Ground Moisture Barrier.”
•
Exhaust fans that vent into a crawl space must be ducted to the outside before crawl
space insulation is installed. See section 513, “Exhaust Fan Ducts”.
Crawl Space Foundation Insulation
Crawl space foundation walls are not to be insulated unless existing crawl space moisture problems
can be corrected. Contact the Weatherization Agency if existing moisture problems are found.
Foundation wall insulation shall be a minimum R10 and should extend from the top of the foundation
wall down to the crawl space floor.
Extruded polystyrene and polyisocyanurate insulation are the most appropriate insulation types
for flat concrete or concrete block walls. For rubble masonry walls, three-inch or six-inch thick,
vinyl- XIV.29
February 2013
faced, metal-building insulation may be used. Two-part foam is also an option for insulating
foundation walls and care must be taken to assure that the proper thickness is obtained. Fiberglass
batts are not to be used for foundation wall insulation.
Concrete block walls foundation walls may also be insulated with injection foam. Injection foam
insulation shall have a minimum R-value of 4.4 per inch. Access to block cores shall be gained by
drilling through mortar joints or through cores at the top of the foundation wall. Cores shall be
completely filled with insulation. Contractors and crews installing injection foam insulation in
concrete block walls must be. No additional foundation wall insulation is required if injection foam
insulation is used.
•
•
•
•
•
•
•
•
•
Existing foundation vents are to be sealed. If foundation vents cannot be sealed,
contact the Grantee. Foundation wall insulation is not to be installed unless the
crawl space vents can be sealed.
Air sealing the foundation wall is to be completed before foundation insulation
is installed.
A ground air-moisture barrier shall be installed that runs up the foundation
walls at least 6 inches. The barrier shall be sealed to the foundation walls with
an appropriate sealant. See section titled, “Ground Moisture Barrier.”
Insulation should be attached to the entire wall surface with appropriate
fasteners.
Install insulation with no significant voids or edge gaps.
All foundation insulation must be covered with a material that has an ASTM
flame spread rating of 25 or less. FSK paper or 1/8 inch masonite meet this
requirement. Vinyl facing on the metal fiberglass insulation also meets this
requirement.
If heating system is located in crawl space or combustion air is drawn from the
crawl space, precautions must be taken to assure that adequate combustion air
is available see section titled, “Combustion Air”. Consideration should be given
to insulating the floor above the crawl space if a combustion appliance is
located within the crawl space or if combustion cannot be drawn directly from
the exterior.
Exposed pipes and ducts are to be insulated if combustion air is provided to a
heating system located in the crawl space.
Exhaust fans or dryer vents that terminate in a crawl space must be ducted to
the outside before insulating the foundation wall (see section titled, “Exhaust
Fan Ducts”).
Crawl Space Floor Insulation
Floors above crawl spaces may be insulated if they form the thermal boundary.
All appropriate measures shall be taken to establish an effective air barrier at the floor, to prevent air
from passing through or around the insulation (see section titled, “Sealing Bypasses”).
XIV.30
February 2013
•
As the floor above the crawl space is the thermal boundary, foundation vents may be
ignored except where required to provide combustion air to combustion appliances located in
the crawl space. If combustion appliances are located in the crawl space, vent sizes shall be
checked to assure adequate combustion air supply (see section titled, “Combustion Air”).
•
Insulation must contact subfloor to prevent convection above the insulation.
Crawl space floor joist cavities may be insulated in one of two manners.
•
Batt insulation
•
Spray foam
Batt Insulation
Batt insulation used to insulate floor joist cavity should be the maximum R-value structurally
allowable by the floor framing. Unfaced batt insulation is not allowed.
Batt insulation must be securely fastened to framing with insulation hangers or other supporting
material. Friction fitting or stapling of floor insulation are not appropriate methods. The
following methods are acceptable.




Wood lath and galvanized nails may be used to hold the insulation in place with
a maximum spacing of 18 inches on center.
Twine used to hold the insulation in place must be made of polypropylene,
nylon or polyester with a breaking strength of at least 150 lbs and 12 inch
maximum spacing between anchor points on the same joist.
Wire used to hold the insulation must be zinc coated, stainless or similar
corrosive resistant material with a minimum diameter of .035”. Wire must be
spaced no more than 18 inches apart. Supports and anchors must be zinc
coated, stainless steel or similar corrosion resistant material.
Wire hangers may also be used if spaced no more than 18 inches on center and
have a minimum thickness of .090 inches. The hanger ends must penetrate the
floor joist at least ½ inch.
 Insulation supports shall not compress insulation by more than one
inch.
 Insulation shall be fitted tightly around cross bracing and other
obstructions.
 Batt insulation shall be installed with the facing placed up towards the
floor sheathing
 Insulation shall be installed without voids or edge gaps.
 Exposed pipes and ducts must be insulated.
 Install a ground air-moisture barrier that runs up the foundation walls at
least six inches. See section titled, “Ground Moisture Barrier.”
XIV.31
February 2013
Spray foam
Two-part spray foam insulation may be used to insulate the floor. Spray foam insulation must provide a
minimum 3 inches (R18) against the floor deck. A minimum of 1 inch spray foam must encapsulate (sides
and bottom) the floor joists and cross bracing or blocking. All members of open web floor joists shall
also be encapsulated with a minimum of 1 inch foam.
Spray foam insulation shall be covered with a fire rated material if required by local building code or by
insulation manufacturer.
Crawl Space Access
Crawl space access hatches from conditioned areas should be weatherstripped and insulated to a
minimum of R10. Peel-&-stick weatherstrip is not permitted to be used on crawl space hatches. Access
covers must be easily removable for entrance into the crawl space.
Outside access hatch shall be securely attached to foundation wall and insulated to minimum R10 if
foundation walls form the thermal boundary. Positive closure (latch, sash locks, gate hooks, etc) shall be
installed to provide substantially airtight closure.
Ground Moisture Barrier
Ground moisture barriers are required regardless of the crawl space thermal boundary location.
Crawl space moisture can lead to condensation, mold and rot. Air passing through the soil can contain
radon and pesticides. Covering the ground with an airtight moisture barrier establishes an air barrier and
seals out moisture and soil gases.
Ground moisture barriers should be minimum 6 mil polyethylene. Complete or partial coverage of
ground moisture barriers will depend on the accessibility and working conditions in the space. If the
entire crawl space floor is not accessible, cover as much as possible.
•
Ground moisture barriers must meet tear and puncture resistance standard ASTM D703.
•
Cover the ground completely with a ground moisture barrier without voids or gaps.
•
Extend air-moisture barrier up foundation wall a minimum of six inches. Seal ground
moisture barrier to foundation wall with acoustical sealant, 2-part spray foam or other
effective adhesive. Furring strips can be used to further secure ground cover to
foundation wall.
•
Seal ground moisture barrier to foundation before installing insulation.
•
Overlap ground moisture barrier at least 6 inches and seal seam with acoustical sealant
or 3M #8086 builders’ tape or equivalent.
•
Seal the ground moisture barrier to concrete footings with acoustical sealant or other
effective adhesive.
•
Duct tape may also be used to temporarily seal the ground cover to the foundation wall
and to seal joints between sheets. Embed the duct tape in duct mastic assuring that the mastic
extends a minimum of 3 inches beyond the edge of the duct tape. Duct tape by itself may not be
used to seal ground cover to foundation walls or joints between sheets.
XIV.32
February 2013
Crawl Space Ventilation
Installing crawl space vents is a non-allowable weatherization measure, unless needed to provide
adequate combustion air to combustion heating appliance located there. If combustion air to the
heating appliance is taken from the crawl space, see product manufacturer’s instructions for correct
combustion air intake size. See section titled, “Combustion Air”, for additional information.
Crawl space ventilation will not solve typical moisture problems found in crawl spaces. The source of the
moisture must be identified and, if possible, corrected.
Vents in crawl spaces with the foundation wall being the thermal barrier may be sealed with rigid
insulation.
Vents should not be sealed in crawl spaces with heating appliances unless adequate provisions for
combustion air are provided. Vents may be installed in crawl spaces that have combustion heating
systems if there are no vents or if the vents are not properly sized for combustion air. Vents should be
non-operable and the client should be informed that the vents are to remain open.
Basement Insulation
Basement wall insulation should be a minimum R10. Basement foundation insulation must be covered
with a material that has an ASTM flame spread rating of 25 or less (such as ½ inch gypsum board).
Basement walls may be insulated with rigid foam board insulation or batt insulation. Insulation should
be continuous from the top of the basement wall down to the basement floor.
Rigid Foam Board Insulation
•
Rigid foam board insulation may be installed directly to the basement wall with
mechanical fasteners and insulation compatible adhesives.
•
Joints and seams in the insulation should be sealed with sheathing tape to form an air
seal.
•
A continuous bead of sealant should be used to seal the top and base of the insulation
board to the foundation.
•
Sealant should also be used to seal the insulation to foundation around windows and
doors.
•
Foil-faced rigid insulation may be exposed as the foil may have an ASTM flame spread
rating of 25 – check with insulation manufacturer.
•
Unfaced extruded or expanded polystyrene must be covered with a material that has an
ASTM rating of 25 or less. Vertical edges of the insulation may be routed to accept a 1
inch x 2 inch or 1 inch x 3 inch furring strip. The furring strips may be used to help secure
XIV.33
February 2013
the insulation to the basement wall with power driven masonry nails. An acceptable
flame spread material such as gypsum board or FSK7 paper may be attached to the
furring strips.
•
Wood furring strips and gypsum board (if used) shall be held off the basement floor by a
minimum 1 inch to prevent capillary action from the basement floor.
Batt Insulation
•
3 inch or 6 inch thick, vinyl-faced (both sides), metal-building fiberglass insulation
sometimes referred to as “basement blanket” or “perimeter wrap” may be used. The
insulation is installed horizontally along the wall and attached to furring strips. The vinyl
facing meets the flame spread rating.
•
Window and door openings should be furred-out. The insulation should be attached and
sealed with sheathing tape. Joints between pieces of the insulation should also be
sealed with sheathing tape.
•
Note that condensation may occur on the basement walls with this technique if the
insulation is not well sealed and the basement is subject to high moisture loads.
Rim Joist Insulation
Penetrations in rim joist must be sealed before insulating. Two-part spray foam is recommended for air
sealing and insulating the rim joist. Rigid foam board or vinyl faced building insulation (vinyl on both
sides) may also be used, but the insulation must be foamed in place to provide an air seal. Kraft and foilfaced batt insulation are not permitted (Figure 200-50) unless used in combination with two-part spray
foam (see section titled, “Two-Part Spray Foam”). Unfaced batt insulation shall not be used for any rim
joist application.
Joist cavities that are parallel to the foundation wall may be sealed and blown with wall insulation unless
moisture is present. Stud cavities in balloon framed homes must be air sealed before insulating the rim
joist.
Two-Part Spray Foam
Provide minimum R6 (1 inch thick) with spray foam. Foam shall make a good seal between the subfloor
and rim joist and between the rim joist and sill plate. Spray foam shall also extend down past the sill
plate to foundation wall. Faced batt insulation may be installed over the two-part spray foam to
increase the R-value of the rim joist.
The International Residential Code (IRC) allows the exposed use of spray foam at rim joists (i.e., without
a 15-minute thermal barrier such as drywall), as long as the thickness is less than 3-¼” (see R314.5.11).
XIV.34
February 2013
High density (closed cell, 2 PCF) spray foams were approved in the 2003 IRC, and low density (open cell,
0.5 PCF) foams were approved in the 2009 IRC, as well as any intermediate densities.
Rigid Foam Insulation
Provide a minimum R10 rigid insulation. Insulation board should be placed firmly against rim joist.
Insulation should be cut to fit tightly between floor joists and between subfloor and sill plate. Perimeter
of insulation should be caulked or foamed to the floor joists, subfloor and sill plate. Both extruded
polystyrene and foil-faced polyisocyanurate may be used.
Vinyl Faced Building Insulation
Insulate rim joist with minimum R19 insulation with vapor barrier facing the warm-in-winter side of the
space. Building insulation should be cut slightly oversized for each rim joist cavity so as to form a snug fit
(be in contact with floor joist on both sides, subfloor at the top, and sill plate/foundation wall at the
bottom) without compression. Insulation should be placed in contact with the rim joist. The perimeter
of the insulation must be sealed with spray foam.
Windows
Windows were once thought to be a major air leakage problem. However, the gaps and holes in a
home’s air barrier are usually much more significant than air leakage around windows and doors.
Consequently, window and door air sealing has been deemphasized as part of weatherization. The
following air sealing measures are done when identified with the blower door.
Air Sealing
Window air sealing measures should be accomplished using lead-safe weatherization practices (see
section titled “Lead Safe Weatherization Practices”).
Caulking
•
Remove loose or brittle material before caulking.
•
If crack is deeper than 5/16 inch, install backer rod before sealing with caulk. Backing
material includes flexible polyurethane, neoprene butyl rod, fiberglass or sponge
rubber.
•
Use sealants with rated adhesion and joint movement characteristics appropriate for
both the window frame and the building materials surrounding the window. Caulking
should be applied in a manner that seals the area thoroughly and is neat in appearance.
XIV.35
February 2013
Weatherstripping
•
Large gaps between sash and sill and sash and stops may be weatherstripped. Meeting
rails may also be weatherstripped or planed.
•
Weatherstrip is to be secured by nails or staples, form a permanent airtight seal and not
obstruct the operation of the sash.
Exterior Storm Windows
Metal exterior storm windows shall have the following qualities.
•
Frame should have sturdy corners and not tend to rack out-of-square during transport
and installation.
•
The gasket sealing the glass should surround the glass edge and not merely wedge the
glass in place against the metal frame.
•
Storm window sashes must fit tightly in their frames.
•
The window should be sized correctly and fit well in the opening.
•
Storm windows shall be caulked around the frame at time of installation except for
weep holes that shall not be sealed. If weep holes are not manufactured into new storm
window, weep holes shall be drilled into them.
•
Storm window sashes must be removable from indoors.
•
Wood storm window inserts shall fit neatly within window frame with the appropriate
turn buttons, latches or closing hardware.
•
Fixed storm windows shall not restrict the exiting capacity and access required for
emergency exits.
Window Repair
Window repairs are considered “incidental repairs”.
Glass Replacement
•
Glass should be secured with glazing points (2 inches from each corner and not less than
8 inches apart) and puttied with latex or oil based glazing compound, or sealed with
plastic or vinyl glazing strips.
•
Glass set in metal frames should have metal-glazing clips no more than 12 inches apart
and within 4 inches of each corner and the joint between the two surfaces puttied.
XIV.36
February 2013
•
Glass over 25 inches in either dimension should not be less than “B” grade double
strength.
•
Safety glass is required in windows located within 12 inches of a door when the bottom
edge is less than 60 inches above the floor or if panes are larger than 9 ft2 when the
bottom edge is less than 18 inches above the floor.
Re-glazing
•
Window glazing compound should only be replaced if the existing glazing is deteriorated
to the degree that the window glass is in jeopardy of falling out if the sash.
•
Caulk may not be used in place of a glazing compound.
•
A coat of primer or linseed oil must be applied to wood sashes before the glazing
compound is applied.
•
Glazing compound is to be tooled smooth to form a concave surface and be neat in
appearance.
Stops
Window stops should be installed in such a way as to ensure a tight seal between the jamb, sash and
stop. Ensure that window operates smoothly following stop adjustment. Wood exposed to the weather
must be primed.
•
Wood installed should be similar in size and shape to other existing window stops in the
house.
•
Installed window stop is to be planed or sanded smooth.
•
New stop is to be painted or varnished to blend with current trim.
•
Corners of installed materials are to be mitered or coped.
•
If matching window stop is not available, then all stops on the window are to be
replaced.
Sills
Factory made sills or sills made from copper treated lumber must be used for window sill replacements.
CCA (chromated-copper-arsenate) lumber is not to be used. Wood exposed to the weather must be
primed.
•
Sill is to be beveled flush with the interior wall.
XIV.37
February 2013
•
Sill shall be the same distance from the house as other window sills.
•
Sill shall be installed at the same angle as other windows sills on the home.
•
All seams shall be caulked after installation.
•
Sills shall be painted to match the rest of the windows on the home.
Sash Locks
The meeting rails of the upper and lower sashes are to be flush.
•
Blocks under the sash lock or chiseling out part of the sash to recess the lock is not
acceptable.
•
Sash locks are to be centered on the check rails.
•
Cam-type sash locks may be used. If used, one must be installed at each side rail of the
bottom sash.
Sash Replacement
New sashes are to be installed in a manner as to allow the lower sash to stay in an open position when
raised and down when closed. The client should be able to open and close sash easily.
•
The lower sash must have the same bevel on the bottom rail as that of the sill.
•
Sashes are to be painted or varnished to match the existing sashes.
•
Glazing compound and glazier points shall be used when replacing glass.
•
Replace missing or severely deteriorated window frame components, such as stops,
jambs or sills.
Window Replacement
Replacement windows shall be ENERGY STAR rated with a U-value no higher than 0.30 and a Solar Heat
Gain Coefficient (SHGC) no higher than 0.55.
Replacement windows shall have U-values rated by the National Fenestration Rating Council (NFRC).
At least one NFRC label must be removed by the contractor and submitted with the contractor’s invoice
upon completion of the home for verification. The remaining NFRC labels shall be left on the window for
removal by the final inspector.
Windows may only be replaced if SIR is greater than or equal to 1.0.
XIV.38
February 2013
Doors
Doors have a small surface area and their air leakage is more of a comfort problem than a serious energy
problem most of the time. Doors may only be replaced if SIR is greater than or equal to 1.0.
Air Sealing
The following air sealing measures are done when identified with the blower door.
Weatherstripping
Door hardware should be tightened and door adjusted to close snugly against its stops before
weatherstripping is applied. Door should close without having to use excessive force following
weatherstrip installation.
Weatherstrip is to consist of a semi-rigid strip with vinyl or neoprene flap. A bulb type weatherstrip is
also acceptable if the bulb is made of siliconized rubber and a minimum of ¼ inch diameter. A third type
that can be used is a tough vinyl tear-resistant skinned material enclosing cellular foam.
•
New weatherstrip must form a tight seal, be neat in appearance and be fastened in such
a way as to prevent buckling or gaps.
•
All existing weatherstrip is to be removed from the door if installing new.
•
Door trimming and adjustments, including hinge tightening and strike plate adjustments
may be necessary and must be done before installing weatherstrip.
•
A small bead of caulk is to be applied to make the weatherstrip and the door stop
airtight.
•
Nails or other fasteners are to be made of a non-rust material.
Thresholds
Thresholds and door sweeps shall be installed to prevent infiltration while not preventing the door from
operating properly.
•
Thresholds are to be set entirely on the sill or a continuous shim from end to end so no
gap exists between the threshold and doorsill.
•
Thresholds are to fit snugly between the jambs and fastened to the sill and the floor
with screws.
•
Thresholds are to be caulked on both the interior and exterior to form a tight seal with
the doorsill.
•
All unfinished wood installed is to be painted or varnished to a smooth finish.
XIV.39
February 2013
Sweeps
Sweep installation is to be neat in appearance, form an airtight seal and not interfere with the operation
of the door.
•
Sweeps are to be a metal strip with a vinyl or neoprene insert, or a brush type installed
with screws on the interior side of the door.
•
Sweeps are to be cut to the same width as the door.
•
Sweep shall be secured within 2 inches of the door edge on each end.
•
Sweeps shall have a threshold or carpet bar to seal against.
Door Replacement
Doors may only be replaced if SIR is greater than or equal to 1.0.
Replacement doors must be ENERGY STAR rated with a U-value no higher than 0.27.
•
Replacement doors should not have glass panes. If homeowner is persistent, install
smallest glass pane as possible or a door viewer. Maximum glazing area shall be “half
moon” or no more than two square feet (approximately two lites).
•
All replacement doors must have a solid wood core or an exterior-grade foam core.
•
Whenever possible, 1-3/4 inch thick doors are to be used.
•
All new wood doors are to operate smoothly, be sanded and be painted or varnished to
a smooth water repellent finish.
•
Doors shall have a 5° bevel cut on the bottom to form an airtight seal between the
bottom of the door and the gasket of the threshold.
•
New 1-3/4 inch doors shall receive three new 4 inch x 4 inch butt hinges; 1-3/8 inch
doors shall have three new 3 ½ inch x 3 ½ inch butt hinges that are mortised into the
door and jamb.
When installing a new door and jamb, the hinges are to be placed at 7 inches from the
top of the door, 11 inches from the bottom of the door, and the third hinge centered
between the top and bottom hinge.
•
New door shall have a new door lock installed (whenever possible a 2-3/4 inch backset
should be used unless using a pre-hung door that is pre-drilled for a 2-3/8 inch lockset).
The client is to receive all keys - minimum two keys per lockset. If possible, multiple
locks should be keyed alike.
XIV.40
February 2013
Pre-Hung Replacement Doors
If a pre-hung door is needed, either a wood or steel foam filled door may be used. Replacement doors
must be ENERGY STAR rated.
•
All door jambs must receive at a minimum, shims behind each hinge and lockset and any
other area needed to support the door jamb.
•
New jambs must be trimmed out to match existing interior and exterior trim.
•
Galvanized casement nails must be used, counter sunk and filled.
•
All doorsills installed must be flush with the floor of the house
Door Repair
All repair work must be within excepted carpenter standards. All replacement materials are to be of the
type and size already existing on the door. Door repairs are considered “incidental repairs”.
Jambs
Remove damaged or deteriorated portion of the jamb and replace with matching materials, butting
uniformly to adjacent members. All work is to be neat and form a tight seal.
•
All loose sub members and casing is to be secured and all wood installed is to be finish
grade or factory made jamb material.
•
All installed lumber is to be planed or sanded smooth and painted or varnished to a
smooth finish to match existing.
•
Hinges are to be tightened or re-set.
•
Casing used is to match the existing casing on the house. If matching casing is not
available, then all of the casing on the door is to be replaced. Wood is to be installed
flush with the wall to insure a tight fit.
•
Any damaged interior wall is to be repaired with like materials.
•
Strike plate shall be tightened or re-set to hold the door flush with the doorstop.
•
Strike plate is to be mortised into the jamb.
Stops
Reposition stops if necessary. Seal gaps between the stop and jamb with caulk.
•
Wood used for door stop is to be manufactured as doorstop.
•
If a section of the stop is missing or must be replaced and the stop cannot be matched
to the existing stop, then the entire stop on that jamb is to be replaced.
•
Joints are to be mitered or coped to form a tight corner joint.
XIV.41
February 2013
•
Wood installed is to be sanded smooth and painted or varnished to a smooth finish and
approximately match the existing wood.
Locksets/Strikeplates
Replace missing or inoperable lock sets; or reposition the lock set/strikeplate; or install a modernization
kit so that the door can be held in a tightly closed position.
•
Lock set is to be installed between 36 inches and 39 inches from the floor with a 2-3/4
inch backset whenever possible.
•
Cover plates are to completely cover the hole drilled for the lockset cylinder.
•
Faceplate and strike plates are to be mortised flushed with the wood of the door and
jamb. Screws are to be installed straight and be flush with the face and strike plates.
•
Strike plate must be installed in a manner as to allow the door to latch easily but with
minimum play between the door and stop.
Storm Doors
Storm door installation or replacement is not allowed.
Door weatherstripping, threshold and sweep
•
•
•
•
All existing weatherstrip is to be removed from the door if installing new.
Door trimming and adjustments, including hinge tightening and strike plate
adjustments may be necessary and must be done before installing weatherstrip.
A small bead of caulk is to be applied to make the weatherstrip and the door
stop airtight.
Nails or other fasteners are to be made of a non-rust material.
Thresholds
Thresholds and door sweeps shall be installed to prevent infiltration while not preventing the door from
operating properly.
•
•
•
•
Thresholds are to be set entirely on the sill or a continuous shim from end to
end so no gap exists between the threshold and doorsill.
Thresholds are to fit snugly between the jambs and fastened to the sill and the
floor with screws.
Thresholds are to be caulked on both the interior and exterior to form a tight
seal with the doorsill.
All unfinished wood installed is to be painted or varnished to a smooth finish.
Sweeps
Sweep installation is to be neat in appearance, form an airtight seal and not interfere with the operation
of the door.
XIV.42
February 2013
•
•
•
•
•
•
•
•
•
Sweeps are to be a metal strip with a vinyl or neoprene insert, or a brush type
installed with screws on the interior side of the door.
Sweeps are to be cut to the same width as the door.
Sweep shall be secured within 2 inches of the door edge on each end.
Sweeps shall have a threshold or carpet bar to seal against.
Turn-on exhaust fan. After 10 seconds, read pressure reading on manometer.
If pressure reading on manometer is greater than 8.0 Pa, select a larger opening
on the flow meter. If E1 is already being used (the largest opening), the fan
exhaust is outside the upper range of the flow meter (124 CFM).
If the pressure reading on the manometer is less than 1.0 Pa, select a smaller
opening on the flow meter. If E3 is already being used (the smallest opening),
the fan exhaust is below the lower range of the flow meter (10 CFM).
Use chart on side of flow meter to determine the flow for the measured
pressure and the appropriate position (E1, E2, or E3).
With the blower door at -50 Pa, place the pressure-pan completely over a grille
or register to form a tight seal. Record rather than a breach in the duct system.
Remove registers on ducts with elevated readings and inspect the boot
connection. Seal boots and re-test with the pressure-pan (see section 31532,
“Duct Sealing Materials”).
Pressure-Pan Standards
Following weatherization work;
• No more than half of the pressure-pan readings shall be higher than 4.0 Pa and
• No readings shall be greater than 8.0 Pa (Figures 100-8 and 100-9).
Mechanical Standards
Combustion Efficiency and Venting
This combustion efficiency and venting section specifies maintenance, repair and efficiency
improvements to the fire side of the heating appliance. Procedures outlined here require training, skill,
experience and knowledge of the health and safety hazards associated with combustion heating
systems.
Natural Gas and Propane
Gas-burner Inspection, Testing and Correction
Perform the following inspection procedures and maintenance practices on all gas-fired furnaces,
boilers, water heaters and vented space heaters. Refer to Table 300-1 for acceptable combustion test
analysis values.
1. Inspect the burners for dust, debris, misalignment and other flame-interference problems. Look for
soot, burned wires and other evidence of flame roll-out
2. Clean, vacuum and adjust burners
XIV.43
February 2013
3. Clean and adjust thermostat and check anticipator setting.
4. Determine that pilot is burning (if equipped) and that main burner ignition is satisfactory. Test pilotsafety control for complete gas valve shutoff when pilot is extinguished.


Install new thermocouple (if an intermittent ignition device, or IID, is not present or not being
installed).
Adjust pilot flame so that the hot tip of the thermocouple is enveloped by the flame.
5. Observe flame characteristics if soot, CO, or other combustion problems are evident.

Remove causes of CO and soot, such as closed or blocked primary air intake, over-firing
and flame impingement.
6. Check venting system for proper size, pitch and connection by referencing NFPA 54.
7. Check venting system for obstructions, blockages or signs of condensation.
8. Check high limit control for proper operation.
9. Measure gas input
•
Adjust gas input if burners are over- fired or under-fired. Adjust input by adjusting gas pressure
to between 3.3” and 4.7” water column (w.c.) for natural gas and 10 “ w.c. to 11” w.c. for
propane, or replace the burner orifices.
10. Conduct Combustion Safety Test (see section title, “Combustion Safety Testing”). There are four
parts to this test.
1.Worst Case Depressurization (see section 3121); the worst case condition for a Combustion
Appliance Zone (CAZ) is established; in other words, the greatest magnitude of negative
pressure in the CAZ under which the combustion appliances might have to operate is
determined. The following three tests are conducted under these conditions.
2. Spillage, the combustion appliance is fired and checked for spillage. Spillage must stop within
three minutes after the appliance is fired (the spillage test only applies to natural draft
appliances).
3. Draft, draft must be established within three minutes.
Minimum draft pressures shown in Table 300-3 must be reached within ten minutes of
appliance operation or when the flue gas temperature has leveled-off.
4. Carbon Monoxide; maximum carbon monoxide (CO) reading is 100 parts per million (ppm).
Conduct steady state efficiency test (see section 313, “Steady State Efficiency Test”).
XIV.44
February 2013
Acceptable Combustion Test Analysis Measurements
Table 300-1
Heating Unit Type
Oxygen (O2)
Carbon Dioxide (CO2)
Net Stack
Temp.
Smoke Test
Gas
Atmospheric
4 - 9%
300-600º F
NA
Fan-assisted
4 - 9%
300-480º F
NA
Condensing
See man. Info.
(5% - 9%)
4 - 9%
Natural 9.6 - 6.8%
LPG 11.2 - 7.8%
Natural 9.6 - 6.8%
LPG 11.2 - 7.8%
See man. Info.
See man.
Info.
300-550º F
NA
325-600º F
325-600º F
2 or less
2 or less
Standard Power
Burner
Oil (No. 1 & 2)
Oil gun burner
Flame Retention
Burner
4 - 9%
4 - 7%
Natural 9.6 - 6.8%
LPG 11.2 - 7.8%
12.5 - 8.8%
12.5 - 10.3%
NA
XIV.45
February 2013
Clocking the Gas Meter
Table 300-2
Using a watch, measure the numbers of seconds for either the ½ ft3 or the 1 ft3 dial to make one
complete revolution. Timing cycle should be a minimum of 30 seconds, increase timing by larger volume
dial or multiple revolutions if necessary. Read the corresponding input rate in 1,000 of Btus/ft3.
Seconds for One
Revolution
on the Dial
½ ft
1 ft
2 ft
Seconds for One
Revolution
on the Dial
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
180
164
150
138
129
120
112
106
100
95
90
86
82
78
75
72
69
67
64
62
60
58
56
55
53
51
50
49
47
46
360
327
300
277
257
240
225
212
200
189
180
171
164
157
150
144
138
133
129
124
120
116
113
109
106
100
100
97
95
92
720
766
600
555
514
480
450
424
400
379
360
343
327
313
300
288
277
267
257
248
240
232
225
218
212
206
200
195
189
185
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
62
64
66
68
70
72
74
76
78
3
3
3
½ ft3 1 ft3
45
44
43
42
41
40
39
38
37
37
36
35
35
34
33
33
32
32
31
30
30
29
29
29
28
26
25
24
24
23
2 ft3
90
88
84
84
82
80
78
77
75
73
72
71
69
68
67
65
64
63
62
61
60
58
56
54
53
51
50
48
47
46
180
176
172
167
164
160
157
153
150
147
144
141
138
136
133
131
129
126
124
122
120
116
112
109
106
103
100
97
95
92
Minimum Draft Pressures
Table 300-3
Atmospheric Gas Appliances Only
Minimum Acceptable Draft Test Readings for Various Outdoor
Temperature Ranges
ºF
Pascals
Water Column inches
<20
-5
-.02
21-40
-4
-.016
41-60
-3
-.012
61-80
-2
-.008
>80
-1
-.004
XIV.46
February 2013
Draft Reading Location
Overfire Draft
Vent Connector or Breech
Acceptable Draft
-0.01 to -0.02 inches or -2.5 to -5 Pascals
-0.04 to -0.06 inches or -10 to -15 Pascals
Leak-testing Gas Piping
Natural gas and propane piping systems may have leaks at their joints and valves. Assessors/Mechanical
Weatherization Workers/Final Inspectors must perform a gas leakage test on all gas supply lines,
couplings, joints and connections. Find gas leaks with an electronic combustible-gas detector, often
called a gas sniffer.
• Sniff all valves and joints with the gas sniffer.
• Locate leaks using a non-corrosive bubbling liquid designed for finding gas leaks.
All gas leaks must be repaired.
Combustion Air
A combustion appliance located in a confined space, surrounded by materials that are tight or marginal
air barriers may need an outdoor source of combustion air. For every
1,000 Btu input, there should be 2 square inches (in2) of free ventilation area. For example, the furnace
and water heater are located in a furnace closet. The furnace has an input rating of 100,000 Btus. The
water heater has an input rating of 40,000 Btus. There should be 280 in2 of free ventilation area to the
furnace room [(100,000 + 40,000)/1,000= 140 x 2 in2 = 280 in2].
Fuel Oil Systems
These procedures pertain to oil-fired furnaces, boilers and water heaters.
Oil-burner Inspection and Testing
All oil burners shall be inspected and tested. Use visual inspection and combustion testing to evaluate oil
burner operation. Refer to Table 300-1 for oil heating system guidelines.
A smoke test should precede combustion testing. If the smoke number is greater than 2, efforts to
reduce smoke should precede combustion testing to protect the combustion testing equipment from
damage.
The following steps are a minimum standard for oil-burner evaluation.
XIV.47
February 2013
•
•
•
•
Inspect burner and appliance for signs of soot, overheating, fire hazards, or wiring problems.
Inspect fuel line for leaks.
Inspect heat exchanger and combustion chamber for cracks, corrosion, or dirt.
Check to see if flame ignition is instantaneous or delayed. Flame ignition should be
instantaneous.
• Sample undiluted flue gases with a smoke tester, following the smoke-tester instructions.
Compare the smoke smudge left by the gases on the filter paper with an approved scale to
determine smoke number.
• Test for CO with flue gas analyzer in undiluted flue gases upstream from the barometric draft
control. A CO reading of 100 ppm is considered the maximum acceptable level.
• Set up and operate house under worst-case depressurization identified in section titled, “Worst
Case Depressurization”, when measuring appliance draft. Measure chimney draft
downstream from the barometric draft control and over-fire draft. Minimum draft pressures
shown in Table 300-3 must be reached within ten minutes of appliance operation for each
natural draft combustion appliance.
• Determine steady-state efficiency from O2 percentage and flue gas temperature in undiluted
flue gases upstream from the barometric draft control.
• Check and clean thermostat.
• Technicians may need to perform other tests to diagnose efficiency, safety, or operational
problems—oil-pump pressure or transformer voltage, for example.
Oil burner Maintenance and Adjustment
Perform some or all of the following maintenance tasks as needed to optimize safety and efficiency.
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Verify correct flame-sensor operation.
Clean or replace burner nozzle.
Clean the burner’s blower wheel.
Clean or replace oil filter(s).
Clean or replace air filter.
Remove soot and sludge from combustion chamber.
Remove soot from heat exchange surfaces.
Clean the oil pump screen.
Clean dust, dirt and grease from the entire burner assembly.
Set oil pump to correct pressure.
Adjust air shutter for minimum smoke.
Adjust barometric damper to about 0.03-to-0.06 inches W.C. draft downstream from the
barometric draft control (see Table 300-3).
Adjust gap between electrodes to manufacturer’s specifications.
Repair the ceramic combustion chamber, or replace it if necessary.
Replace or adjust barometric damper.
Measure CO in undiluted flue gases upstream from the barometric draft control. A CO reading of
100 ppm is considered the maximum acceptable level.
XIV.48
February 2013
After these maintenance procedures, the technician shall perform the diagnostic tests described above
to evaluate improvement made by the maintenance procedures and to determine if fine-tuning is
required.
Electric Heating Systems
The following measures shall be done on all electric furnaces.
•
•
•
•
•
•
•
•
•
•
•
•
•
Check and clean thermostat.
Check, clean and oil blower motor if applicable.
Clean all filters. Replace if necessary. Vacuum and clean housing around electric elements, if
applicable.
Vacuum and clean all fins on electric- baseboard systems, if applicable.
Wood Burner Safety
Inspect stove, vent connector and chimney for correct clearances from combustible materials as
listed in NFPA 211. Ensure that stove is sitting on a noncombustible floor.
Inspect vent connector and chimney for leaks and seal leaks with a high- temperature sealant
designed for use with metal or masonry.
Inspect chimney and vent connector for creosote build-up and clean chimney if significant
creosote build-up exists.
Inspect the house for soot on seldom- cleaned horizontal surfaces. If soot is present, replace the
gasket on the wood- stove door, seal other air leaks and take steps to improve draft, as
necessary to reduce indoor smoke emissions.
Inspect and clean damper and/or combustion air intake if present
Check and replace fire door gaskets if applicable.
Check catalytic converter for repair or replacement if applicable.
Conduct Worst Case Depressurization test to check for potential back drafting.
Combustion Safety Testing
Assessors, mechanical contractors and final inspectors are required to do Combustion Safety Testing.
Mechanical contractors are required to complete these tests following completion of work each day as
well as at job completion.
Architectural contractors and crews are required to do a Spillage Test-Out (see section titled, “Spillage
Test-Out”) at the end of each work day.
The purpose of combustion safety testing is to ensure that vented combustion appliances in a home are
vented properly.
Proper venting is essential to the operation, efficiency, safety and durability of combustion appliances.
Air tightening the home can weaken draft and weatherization work can reduce the heater’s operating
XIV.49
February 2013
time, resulting in a cooler flue. Tightening a home can also reduce air to combustion appliances resulting
in backdrafting and/or “lean burns” that produce carbon monoxide.
There are four parts to this test.
1. Worst Case Depressurization); the worst case condition for a Combustion Appliance Zone
(CAZ) is established; in other words, the greatest magnitude of negative pressure in the CAZ
under which the combustion appliances might have to operate is determined. The following
three tests are conducted under these conditions.
2. Spillage; the combustion appliance is fired and checked for spillage.
Spillage must stop within three minutes after the appliance is fired (the spillage test only applies
to natural draft appliances).
3. Draft; draft must be established within three minutes. Minimum draft pressures shown in
Table 300-3 must be reached within ten minutes of appliance operation or when the flue gas
temperature has leveled-off.
4. Carbon Monoxide; maximum carbon monoxide (CO) reading is 100 parts per million (ppm).
If a house contains more than one CAZ, combustion safety testing must be performed for each area.
Additionally, if more than one vented combustion appliance is located in a CAZ, each must be tested for
safe operation under worst case conditions. Combustion appliances include furnaces, boilers, water
heaters, fireplaces and vented space heaters.
Potential solutions for Combustion Safety Testing failures are presented in section 3125.
Worst Case Depressurization
“Worst case” is defined as the configuration of the house that results in the greatest negative pressure
in the area of the vented combustion appliance or fireplace (CAZ).
Worst Case Depressurization (WCD) must be done in all homes. The following are exceptions to this
requirement:
1. If the house or mobile home is all-electric with no combustion appliances, woodstoves or
fireplaces, or all combustion appliances are sealed combustion (direct vent).
2. If the home has a boiler and has no exhaust equipment, including clothes dryers, vented bath
and kitchen fans, vented central vacuum systems, fireplaces, woodstoves, etc.
3. If the CAZ is located outside the thermal boundary and there are no return ducts in the CAZ.
However, always perform this test if the CAZ is in a vented crawl space or a basement deemed
to be outside the thermal boundary.
XIV.50
February 2013
4. If apartments have no combustion appliances other than direct-vent combustion appliances.
Manometer Set-Up
Set up the digital manometer as follows to measure pressure difference of a combustion zone with
reference to the outside.
•
Connect a hose from the “reference” tap on the digital manometer to the exterior of the home.
•
Connect a hose from the “input” tap on the digital manometer to within two feet of the
combustion appliance. This hose is not needed if measurements are taken while standing in the
CAZ.
Measurements made while doing Worst Case Depressurization testing will likelybe quite small. Trying to
take these readings on a windy day can be very difficult. Care should be taken to protect the tip of the
exterior hose from the wind. One method for countering the effects of wind is by placing a plastic “T”
fitting in the tip of the exterior hose. Run another hose to the windward side of the home and another
hose to the leeward side of the home from the “T” connection.
House Set-Up
House should be set-up for winter conditions.
•
•
•
•
•
•
•
•
All windows and exterior doors should be closed.
Open all interior doors. This includes bathroom and kitchen doors and door to CAZ.
Turn off all exhaust fans, including dryer.
Remove lint filter from dyer.
If dirty, remove filter from furnace. Otherwise, leave filter in place. Do not remove filter cap if
present.
Close supply air registers if present in the CAZ.
Close damper on fireplace, if present.
Set water heater to pilot and ensure that other combustion appliances are turned off.
Measuring Worst Case Depressurization
1. Set the adjusted baseline pressure if using the DG-700 manometer with house set- up as described
above. This is the pressure in the CAZ resulting from stack-effect air leakage. Generally, the colder the
outdoor temperature, the greater the magnitude of this baseline value.
Measure and record baseline pressure difference if using the older DG-3 manometer (P1). P1 will be 0
Pa if using the DG-700 manometer.
2. Turn on clothes dryer and all exhaust fans in house. Turn on central vacuum cleaner if present. Do not
turn on whole house fans2. Record pressure difference (P2).3. Turn on the furnace air handler, leaving
on all the exhaust fans. If cooling is present, run the air handler on high speed. Record pressure
difference (P3).
XIV.51
February 2013
4. Position all the doors. If the pressure in the room is greater than in the house (positive pressure),
close door. If the pressure in the room is less than in the house (negative pressure), open the door. If
you’re using a smoke pencil, smoke the door undercut. If smoke comes out of the room or does nothing,
leave the door closed. If smoke is drawn into the room, open the door.
Begin this test on the room furthest from the CAZ. Include bathroom doors and other rooms with
exhaust devices behind them. Bathrooms, for example, will most likely have a supply air register, but no
return. Existing bathroom exhaust fans generally have low exhaust rates such that the supply air is
greater than the air being drawn by the exhaust fan putting the bathroom under positive pressure, thus
the door would be closed.
The last door to be tested should be the door to the CAZ.
After all the doors have been positioned as described above, record the pressure difference (P4).
Additional information about reading pressures between rooms and the main body of the house may be
found in section titled, “Duct Induced Pressures”. Solutions to room imbalance problems may also be
found in that section.
5. Use highest depressurization reading for each CAZ. The baseline pressure difference (P1) is subtracted
from the largest pressure difference measured under each operating condition (P2, P3 or P4). Compare
value to the Worst Case Depressurization values shown in Table 300-4.
If depressurization is greater than the values shown in Table 300-4, the CAZ fails Worst Case
Depressurization and pressure relief will be required (see section titled, “Solutions to Combustion Safety
Testing Failures”).
Worst Case Depressurization Limits
Table 300-4
(Depressurization measurements shown are for the CAZ with reference to the outside)
Appliance
Gas fired furnace,
boiler, water heater
Oil fired furnace,
boiler, water heater
Fireplace (wood or
gas)
Airtight fireplace,
wood stove
Induced draft
appliances
Chimney
Height (ft)
13 or less
14 – 20
+ 21
13 or less
14 – 20
+ 21
all heights
Unlined Chimneys
on Exterior Wall
-5 Pa (0.02 in)
-5 Pa (0.02 in)
-5 Pa (0.02 in)
-4 Pa (0.016 in)
-4 Pa (0.016 in)
-4 Pa (0.016 in)
-3 Pa (0.012 in)
Metal Lined, Insulated
or Interior Chimneys
-5 Pa (0.02 in)
-6 Pa (0.024 in)
-7 Pa (0.028 in)
-4 Pa (0.016 in)
-5 Pa (0.02 in)
-6 Pa (0.024)
-4 Pa (0.016 in)
all heights
all heights
-10 Pa (0.04 in)
-15 Pa (0.06 in)
-10 Pa (0.04 in)
-15 Pa (0.06 in)
XIV.52
February 2013
Spillage Test (natural draft appliances only)
Fire the appliance with the smallest Btu capacity first and test for spillage at the draft diverter with a
smoke pencil. Spillage should cease within three minutes. If spillage ends within three minutes, fire all
the other connected appliances simultaneously and test the draft diverter of each appliance for spillage.
Proceed with the draft test if there is no spillage after three minutes.
The appliance fails if there is spillage after three minutes. Turn off appliance and the exhaust fans and
open all the interior doors. Allow the vent to cool and then re-test for spillage, draft and CO under
natural conditions. Operating the blower door will help cool the combustion gases. Measure the net
change in pressure from worst case to natural in the CAZ to confirm worst case depressurization.
See section titled, “Solutions to Combustion Safety Testing Failures”, for potential actions for appliances
that fail the spillage test.
Draft Test
Draft must be established within three minutes. Minimum draft pressures shown in Table300-3 must be
reached within ten minutes of appliance operation or when the flue gas temperature has leveled-off.
Draft test is only done for natural draft and induced appliances. Draft does not have to be measured for
direct vent sealed combustion appliances.
Natural Draft Appliances
•
•
•
•
•
Drill test hole 2 feet from draft hood or the first available straight run of pipe.
See section titled, “Natural Draft Appliances”, for sealing test holes.
Fan Induced Appliances
Drill test hole about 1 foot away from where the gases exit the appliance.
Hole should be in a straight piece of vent pipe away from turns (inducer fans and turns can
cause turbulence and make stable readings difficult to obtain).
• See section titled, “Fan Induced Appliances”, for sealing test holes.
If measured draft is below the minimum draft pressures listed in Table 300-3, check for flue or chimney
obstructions, disconnected vents or an improperly designed vent system. Check the National Fuel Gas
Code (NFGA) for proper vent sizing. See section titled, “Heating Appliance Venting”, for additional
information.
Take action to improve draft, if inadequate because of improper venting, leaky venting, obstructed
chimney or lack of combustion/dilution air. Seal leaks in vent connectors and chimneys with high
temperature sealant.
See section titled, “Solutions to Combustion Safety Testing Failures”, for other actions that may be taken
for appliances that fail the draft test.
XIV.53
February 2013
Carbon Monoxide (CO) Testing
CO readings are often taken at the same location in the vent connector as combustion efficiency
readings (see section titled, “Steady State Efficiency Test”). A CO reading of100 ppm is considered the
maximum acceptable level. A reading in excess of 100 ppm indicates that the appliance needs to be
adjusted or repaired.
Natural Draft Appliances
•
Readings must be taken just before the emissions are diluted by room air at the draft diverter.
Drilling a hole is often not necessary. Note that the CO reading is taken at a different
location in the vent connector than the draft test. Where the appliance has multiple burners
and cells, each cell of the heat- exchanger must be tested separately. Use the highest CO
reading (not the average) when deciding the appropriate course of action.
Fan Induced Appliances
•
Drill test hole about 1 foot away from where the gases exit the appliance. Hole should be in a
straight piece of vent pipe away from turns (inducer fans and turns can cause turbulence
and make stable readings difficult to obtain). See section titled, “Fan Induced Appliances”,
for sealing test holes.
Direct Vent Sealed Combustion Appliances (condensing)
•
•
The recommended testing point for condensing appliances is to sample the gasses at the
outside of the house by inserting the test probe into the PVC vent pipe at least 6 inches.
If testing cannot be done on the exterior because the vent pipe is not accessible, testing can be
done by drilling the PVC vent pipe near the furnace. Test hole must be drilled and tapped with
threads for 1/8” pipe threads and then sealed with a plastic pipe plug and sealant. Proper
technique and equipment must be used to seal this pipe as it is under positive pressure and
improper sealing will allow vent gasses to enter the house. Test holes can be drilled in vertical
pipes or the top half of horizontal pipes
Solutions to Combustion Safety Testing
Failures
following are potential solutions for Worst Case Depressurization, spillage and draft failures.
a. Check for blockage in the vent system and, if found, correct the problem.
b. Check vent system for leaks, including missing or loose cleanout doors or open or cracked
mortal joints. Seal vent system as appropriate. Lining a chimney may solve the problem.
c. Properly seal return duct leakage in the CAZ.
XIV.54
February 2013
d. Increase the CAZ air volume by connecting the CAZ to other areas within the conditioned
volume of house.
e. Increase the CAZ air volume by connecting the CAZ to the outdoors.
f. Install a manufacturers’ outdoor air kit for the failed appliances. This is an option with a
number of fired furnaces, boilers and water heaters.
g. Install fan to supply air to pressurize the CAZ. It is best to link the controls of such a make-up
air fan to the operation of the combustion appliance(s) in the CAZ.
h. If opening doors solve a combustion safety test failure, consider door undercuts, transfer
grilles, jumper ducts or in-door transfer grilles.
i. For high CO emissions, the appliance should be cleaned and tuned and tested for CO
emissions again. Contact Weatherization Agency if high CO emission problem cannot be
corrected.
Steady State Efficiency Testing
Combustion analyzer used for testing must be within the manufacturer’s calibration period and have a
calibration sticker with the calibration date affixed to it. The analyzer should be started-up (calibrated) in
a source of known fresh air during the calibration period – usually outside the home.
Natural Draft Appliances
The following inspection procedures and maintenance practices are required for all natural draft
appliances in addition to items 1 through 12 as noted in section titled, “Gas Burner Inspection,
Testing and Correction”.
• Test holes
 Single wall pipe is preferred location for test holes, but double wall B vent can be
drilled if necessary. Seal inner pipe with RTV and metal tape over the outer pipe.
 Single wall pipe is to be sealed with metal tape.
 Butyl tape is not to be used.
• Determine steady-state efficiency (SSE) using flue gas analyzer measuring in undiluted
flue gases below the draft diverter. Where the appliance has multiple
burners and cells, each cell of the heat-exchanger must be tested separately.
• Measure O2 level and stack temperature in undiluted gases (before they enter the draft
hood). O2 level should be between 4% and 9%. Net stack temperature should be between
300oF and 600oF.
Fan Induced Appliances
The following inspection procedures and maintenance practices are required for all fan induced
appliances in addition to items 1 through 12 as noted in section titled, “Gas Burner Inspection,
Testing and Correction”.
• Test holes
 Test hole should be located about 1 foot away from where the gases exit the
appliance.
XIV.55
February 2013

Test hole should be in a straight piece of vent pipe away from turns (inducer fans and
turns can cause turbulence and make stable draft readings difficult to obtain).
 Single wall pipe is preferred location for test holes, but double wall B vent can be
drilled if necessary. Seal inner pipe with RTV and metal tape over the outer pipe.
 Single wall pipe is to be sealed with metal tape.
 Butyl tape is not to be used.
• Determine steady-state efficiency (SSE) using flue gas analyzer.
• Measure O2 level and stack temperature. O2 level should be between 4% and 9%.
o
o
Net stack temperature should be between 300 F and 480 F.
Steady State Efficiency Testing
Combustion analyzer used for testing must be within the manufacturer’s calibration period and
have a calibration sticker with the calibration date affixed to it. The analyzer should be started-up
(calibrated) in a source of known fresh air during the calibration period usually outside the
home.
Natural Draft Appliances
The following inspection procedures and maintenance practices are required for all natural draft
appliances in addition to items 1 through 12 as noted in section titled, “Gas Burner Inspection,
Testing and Correction”.
• Test holes
 Single wall pipe is preferred location for test holes, but double wall B vent can be
drilled if necessary. Seal inner pipe with RTV and metal tape over the outer pipe.
 Single wall pipe is to be sealed with metal tape.
 Butyl tape is not to be used.
• Determine steady-state efficiency (SSE) using flue gas analyzer measuring in undiluted
flue gases below the draft diverter. Where the appliance has multiple
burners and cells, each cell of the heat-exchanger must be tested separately.
• Measure O2 level and stack temperature in undiluted gases (before they enter the draft
hood). O2 level should be between 4% and 9%. Net stack temperature should be between
300oF and 600oF
Fan Induced Appliances
The following inspection procedures and maintenance practices are required for all fan induced
appliances in addition to items 1 through 12 as noted in section titled, “Gas Burner Inspection,
Testing and Correction”.
• Test holes
 Test hole should be located about 1 foot away from where the gases exit the
appliance.
 Test hole should be in a straight piece of vent pipe away from turns (inducer fans and
turns can cause turbulence and make stable draft readings difficult to obtain).
 Single wall pipe is preferred location for test holes, but double wall B vent can be
drilled if necessary. Seal inner pipe with RTV and metal tape over the outer pipe.
 Single wall pipe is to be sealed with metal tape.
 Butyl tape is not to be used.
• Determine steady-state efficiency (SSE) using flue gas analyzer.
XIV.56
February 2013
• Measure O2 level and stack temperature. O2 level should be between 4% and 9%.
Net stack temperature should be between 300oF and 480oF.
Direct Vent Sealed Combustion Appliances
The following inspection procedures and maintenance practices are required for all direct vent sealed
combustion appliances in addition to items 1 through 12 as noted in section titled, “Gas Burner
Inspection, Testing and Correction”.
•
•
Inspect the secondary heat exchanger and clean as needed.
Test holes

•
•
The recommended test point for condensing appliances is to sample the gasses at the
outside of the house by inserting the test probe into the PVC vent pipe at least 6 inches.
 If testing cannot be done on the exterior because the vent pipe is not accessible, testing
can be done by drilling the PVC vent pipe near the furnace. Test hole must be drilled and
tapped with threads for 1/8” pipe threads and then sealed with a plastic pipe plug and
sealant. Proper technique and equipment must be used to seal this pipe as it is under
positive pressure and improper sealing will allow vent gasses to enter the house.
 Test holes can be drilled in vertical pipes or the top half of horizontal pipes.
Determine steady-state efficiency (SSE) using flue gas analyzer.
Measure O2 level and stack temperature. Adjust as necessary to meet Product Manufacturer’s
Instructions for net stack temperature and O2 (generally, O2 is between 4% and 9%).
Heating Appliance Venting
Inspect chimney, vents and vent connectors to ensure adequate draft, clearance, soundness and
freedom from combustible deposits. Clean if necessary. Repair or replace sections of the venting system
that are seriously corroded or rusted, contain cracks or holes, and/or are unsealed, loose, or
disconnected.
Ensure all venting materials meet clearances from combustible materials in accordance with the
applicable NFPA code. When called for, correct cases where vent clearance requirements are not met.
Ensure that vent/chimney connections are securely fastened. Horizontal runs in the vent connector
should have a rise of at least ¼ inch per foot. Existing connectors that do not meet this requirement are
to be repaired unless the appliance passes the Combustion Safety Tests (see section titled, “Combustion
Safety Testing”).
Venting Devices, Materials and Sizing
The National Fire Protection Association (NFPA) is the authoritative source for information on materialchoice and sizing for vent connectors and chimneys. The information in this venting section is based on
the following NFPA documents. Consult these references for specific venting requirements and tables
for vent and chimney sizing.
•
NFPA 54: The National Fuel Gas Code
XIV.57
February 2013
•
•
NFPA 31: Standard for the Installation of Oil-Burning Equipment
NFPA 211: Standard for Chimneys, Fireplaces, Vents, and Solid-Fuel-Burning Appliances 1996
Edition
Vent Connectors
A vent connector connects the venting outlet of the appliance with the chimney. Approved vent
connectors for gas- and oil-fired units are made from the following materials.
•
•
•
•
•
•
Galvanized-steel pipe (> 0.018 in. thick),
Type-B vent, consisting of a galvanized-steel outer pipe and aluminum inner pipe
(> 0.027 in. thick),
Stainless-steel pipe (> 0.012 in. thick),
Type-L vent, like Type-B only with a stainless-steel inner pipe, or
Various manufactured vent connectors.
A wye connector is the preferred connection when a common flue is used for more than one appliance.
Vent connections are not to be located directly across from each other when an induced appliance is
used.
Masonry-Chimney Liners
Masonry chimneys and clay tiled chimneys should have a liner if they are not properly sized. If an 80%
furnace or boiler has been installed, the masonry chimney will need a liner as it is probably oversized.
The liner should have a small air space between itself and the masonry structure of the chimney to
insulate the liner from rapid heat loss. A liner used to vent solid fuel may not also be used to vent liquid
or gaseous fuel.
Unlined masonry chimneys should be lined with galvanized-steel vent pipe, Type-B vent, or a flexible
liner.
Unlined chimneys or chimneys with deteriorated liners should be relined. For interior chimneys, flexible
metal liners may be used. For external chimneys, galvanized-steel vent pipe, Type-B vent or a flexible
metal liner, insulated with vermiculite or equivalent, may be used.
Sizing Vent Connectors and Chimneys
Sizing tables and procedures for chimneys and vent connectors are found in NFPA documents numbered
54, 31 and 211 as described earlier. NFPA 54, the National Fuel Gas Code, Part 11 provides tables for
sizing various types of chimneys and vent connectors.
Forced Air System Standards
The overall system efficiency of an oil or gas forced air heating system is affected by blower operation,
duct leakage, balance between supply and return air, and duct insulation levels.
XIV.58
February 2013
Furnace Repair
When possible, furnaces should be repaired to a safe and efficient operating condition. Cracked heat
exchangers should be replaced per manufacturer’s instructions. Contact the Grantee if total repair costs,
including heat exchanger replacement, exceed 50% of furnace replacement cost.
Furnace Operation Standards and Improvements
Apply the following furnace-operation standards to maximize the heating system’s seasonal efficiency
and safety. Refer to Table 300-5 for furnace operating guidelines.
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Check temperature rise between the supply air plenum and return air plenum after 10 minutes
of operation. Refer to manufacturer’s nameplate for acceptable heat rise (supply temperature
minus return temperature). The heat rise should be between 40°F and 70°F with the lower end
of this scale being preferable for maximum efficiency.
The fan-off temperature should be between 85°F and 100°F, with the lower end of the scale
being preferable for maximum efficiency.
The fan-on temperature should be 115°F if possible.
The high-limit controller should shut the burner off before the furnace temperature reaches
200°F. Operate unit with blower disconnected to check high limit control and repair as
necessary.
If needed, seal (with compatible sealing materials) unsealed blower compartment openings and
blower compartment door.
If the heating system does not conform to these standards consider the following
improvements.
Reduce heat rise by cleaning or changing dirty filters, cleaning the blower, increasing fan speed
and improving ducted air circulation.
Adjust fan control to conform to the above standards or replace the fan control if adjustment
fails.
Adjust the high-limit control to conform to the above standards or replace the high-limit control.
In all cases, the following furnace measures will be done:
Furnace filters shall be cleaned or replaced. Two extra filters of proper size and type shall be left
with the client. Filter changing procedure shall be explained to client.
The blower belt shall be adjusted or changed if necessary. Belt should be free of cracks and have
one inch of free play when measured between pulleys.
Pull the blower fan and clean. Vacuum the compartment.
Inspect the blower assembly’s electrical wiring system for bad insulation and loose connections
and repair as necessary.
Inspect the blower and squirrel cage for excessive free play and correct as necessary.
The blower motor shall be lubricated if appropriate.
The thermostat shall be checked, cleaned and leveled.
XIV.59
February 2013
Furnace Operating Temperatures
Table 300-5
Inadequate heat rise,
Heat rise good for both
Heat rise excessive. Check
Condensation and corrosion efficiency and avoidance of
fan, heat exchanger, ducts
possible.
condensation.
and fan speed.
o
o
o
o
o
20
40 40
70 70
95o
Heat rise = Supply temperature – Return temperature
Inadequate heat rise,
Heat rise good for both
Heat rise excessive. Check
Condensation and corrosion efficiency and avoidance of
fan, heat exchanger, ducts
possible.
condensation.
and fan speed.
20o
40o 40o
70o 70o
95o
Heat rise = Supply temperature – Return temperature
Excellent.
No action needed.
100o
115o
Fair. Consider fan control
replacement only if fan-off
is unacceptable.
115o
130o
Fan-on Temperature
Poor. Consider fan control
replacement.
130o
150o
Ducts
Duct Leakage Sites
The following joints should be inspected and sealed. Ducts located outside the thermal boundary or in
an intermediate zone like a ventilated attic or crawl space should be sealed.
•
•
•
•
•
•
•
Seal holes in the air handler and joints between the air handler and the supply and return ducts.
Filter slot must have system that will cover the opening but is easy for the occupant to open and
close.
Seal leaky joints between main supply and return ducts and their branches.
Seal leaky joints between building materials composing cavity return ducts, like panned floor
cavities and furnace return platforms.
Even better: replace cavity return ducts with new metal return ducts.
Seal leaky joints between supply and return registers and the floor, wall and ceiling to which
they are attached.
Secure metal duct joints with screws, seal them with mastic, and support joints with duct
hangers.
XIV.60
February 2013
•
Flex duct runs should be mechanically attached to the plenum/trunk/boot with clamps or cable
ties and sealed. Flex duct should be run as straight as possible with a minimum of long radius
turns and should be supported with appropriate hangers to prevent sagging.
• Permanently seal open supply and return registers in unconditioned areas.
• Patch or replace metal ducts that have rusted through and ducts with holes cut in them.
• Seal penetrations made by wires or pipes traveling through ducts. Even better: move the pipes
and wires and patch the holes.
• Seal return air grilles in basement. Re-check temperature rise to assure that it is within the
operating limits of the furnace.
Duct Sealing Materials
Duct sealing mastics and tapes should be UL181A or UL181B labeled.
•
Duct mastic: the preferred material because of its superior durability and adhesion. Apply at
least 1/16- inch thick and use reinforcing mesh for all joints wider than 1/16 inch or joints that
may experience some movement.

Tape: An approved aluminum duct tape may be used when duct mastic is not used. Duct
surfaces around the joint need to be clean in order for the tape to adhere properly. Tape should
never be expected to hold a joint together nor expected to resist the force of compacted
insulation or joint movement. Joints should rely on mechanical fasteners to prevent joint
movement or separation.


Butyl-aluminum tape: High quality tape designed for duct sealing is effective and
durable when applied to clean surfaces.
Cloth duct tape is not an acceptable duct sealant material because of its history of
adhesive failure.
Duct Insulation
Insulate supply and return ducts that run through unconditioned areas outside the thermal boundary
such as vented crawl spaces and attics. Use minimum R-8 insulation on supply ducts.
•
•
•
•
Always perform necessary duct sealing before insulating ducts.
Use fiberglass insulation 3 to 6 inches thick (minimum R-8) with foil-skrim-kraft facing or
vinylfacing. Vapor barrier must be placed to the outside with no exposed insulation.
Insulation should cover all exposed ducts, especially in air conditioned homes. Even a small void
in the insulation can dampen a large section of insulation through condensation.
Insulation should be fastened by mechanical means such as stuck- ups, twine, or plastic straps.
Tape can be effective for covering joints in the insulation to prevent air convection, but tape
will usually fail if expected to resist the forces of compressed insulation or the insulation’s
weight.
XIV.61
February 2013
Duct System Airflow
The airflow capacity of the air handler may be checked in relationship to the size of the furnace or air
conditioner. For combustion furnaces there should be 110 to 150 cfm of airflow for each 10,000 Btuh of
output. Central air conditioners should deliver 400 cfm of airflow per ton of cooling capacity. Heat
pumps should deliver 450 cfm of airflow per ton of heating capacity.
Central Air Conditioners
Cooling Clean & Tune
•
Measure air flow across the evaporator coil. Airflow across the indoor coil should be 400 CFM
per ton for a wet coil (condensation on coil) and 425 CFM per ton for a dry coil (no condensation
on coil), plus or minus 50 CFM.
• Check for correct amount of refrigerant. Follow the manufacturer’s specification for refrigerant
charge. The airflow across the indoor coil should be adjusted and verified before the refrigerant
charge is checked. Any refrigerant that must be evacuated must be captured rather than illegally
releasing it to the atmosphere.
• Test for refrigerant leaks using a leak detector.
• Clean the outdoor condenser coil.
• Check for and seal duct leakage in central systems. Duct sealing and insulation is especially
important for ductwork running through unconditioned spaces. Chances are high that the
weatherization workers already completed this inspection and work.
• Verify the correct electric control sequence and make sure that the heating system and cooling
system cannot operate simultaneously.
• Inspect electric terminals, clean and tighten connections and apply a non- conductive coating if
necessary.
• Oil motors and check belts for tightness and wear.
• Check the accuracy of the thermostat.
Dirty air conditioning coils located in main ducts or air handlers are a common cause of low airflow and
resultant low heating and cooling efficiency.
•
•
•
•
•
Identify the coil location and the coil surface where the air enters - most of the dirt will be
attached to this surface.
Remove access panel in air handler or duct; or cut access panel in duct; or disassemble duct to
gain access to air-conditioning coil.
Using a stiff brush, remove surface dust, dirt and lint.
Spray the coil with cleanser and after a while spray water to rinse out the cleanser and dirt.
Repeat the spraying if necessary.
Observe whether the pan and drain hose are doing their job. Water and cleanser should be
flowing out the end of the hose, not overflowing into the duct. Clean the pan and unplug the
hose if necessary.
XIV.62
February 2013
Central Air Conditioner Replacement
Replacement central air conditioners must be ENERGY STAR rated with a minimal SEER3 of 14.0. Air
conditioners shall be selected to have a rated sensible heat ratio (SHR) of 0.75 or less. Indoor coils and
line sets shall also be changed if a different refrigerant type will be used in the system. All new air
conditioners shall carry a minimum one year warranty on parts and labor and a five year warranty on
the compressor.
Each client shall receive all manufacturer’s product warranty information, clear maintenance
instructions, educational information and a local telephone number for warranty problems.
Contractor shall size the system properly utilizing the Residential Load Calculation, Manual J by the Air
Conditioning Contractors of America or other approved method. Sizing calculations must be provided to
the Weatherization Agency for inclusion as a permanent part of the client file. The following
characteristics of the house and occupants shall be considered:
•
•
•
The size of the home and the number and orientation of the windows.
The amount of existing insulation and insulation to be added as part of weatherization.
The tightness of the home. It is important to remember that the ACH4 value used in most
weatherization work in the midwest is a winter calculation. The ACH during the cooling season –
that which is used in cooling load calculations – is usually significantly less.
• The amount of shading on windows, walls and roof.
• The number of occupants and the degree of internal heat gain they generate.
Following installation of new air conditioning system, contractor shall check, test and meet the
requirements of section titled, “Cooling Clean and Tune”.
Heat Pumps
•
•
•
•
•
•
•
Measure air flow across the indoor coil in heating mode. Airflow across this coil should be 450
CFM per ton plus or minus 50 CFM.
Check for correct amount of refrigerant. Follow the manufacturer’s specification for refrigerant
charge. The airflow across the indoor coil should be adjusted and verified before the refrigerant
charge is checked. Any refrigerant that must be evacuated must be captured rather than
illegally releasing it to the atmosphere. For systems with fixed metering devices (capillary tube
of fixed orifice), the evaporator superheat method should be used along with the
manufacturer’s recommendations. For systems with thermostatic expansion valves (TXV), the
subcooling method should be used along with the manufacturer’s recommendations.
Test for refrigerant leaks using a leak detector.
Check for and seal duct leakage in central systems. Duct sealing and insulation is especially
important for ductwork running through unconditioned spaces.
Inspect electric terminals, clean and tighten connections and apply a non- conductive coating if
necessary.
Oil motors and check belts for tightness and wear.
Check the accuracy of the thermostat.
XIV.63
February 2013
•
Test for proper operation of the heat pump defrost control. This control for the outdoor coil
must be adjusted to optimize heating efficiency.
Room Air Conditioner
Replacement room air conditioners must be ENERGY STAR rated with a minimal EER5 of 9.4. All new air
conditioners shall carry a minimum one year warranty on parts and labor.
Window units shall be sized appropriately. The guide6 shown as Table 300-6 may be used to size
window units.
Table 300-6 Window air conditioning unit sizing chart
The following adjustments may be made.
•
•
•
•
Reduce capacity by 10% if room is heavily shaded.
Increase capacity by 10% if room is very sunny.
If more than two people regularly occupy room, add 600 Btus for each additional person.
Add 4,000 Btu if unit is used in kitchen.
Hydronic Standards
The following standards refer to hydronic systems commonly found in single family homes. Observe the
following standards for servicing hydronic heating systems in single family structures.
Hot Water Systems
•
•
•
•
•
Repair water leaks in the system.
Clean fire side of heat exchanger of noticeable dirt.
Lubricate circulator pump if necessary.
Boiler should not have low-limit control for maintaining a minimum boiler-water temperature,
unless the boiler is heating domestic water in addition to space heating.
Test pressure tank for its rated air pressure.
XIV.64
February 2013
•
•
•
High-limit control should deactivate boiler at 200° F or less.
Replace or add pressure-relief valve if necessary.
Bleed air from radiators and piping through air vents in elbows or radiators. Most systems have
an automatic fill valve.
• Verify that water pump, low water cutoff, automatic feed control and high pressure controls are
in operating condition and repair as necessary.
• Insulate hot water supply lines passing through unconditioned areas.
• Check, clean and level thermostat.
• Vacuum and clean baseboard unit fins if appropriate.
Steam Systems
For steam systems, observe the following.
•
•
Check or replace steam vents and steam traps.
Verify that water pump, low water cutoff, automatic feed control and high pressure controls are
in operating condition and repair as necessary.
• Replace/clean sight glass if water level cannot be seen due to dirt build-up on glass.
Unvented Space Heaters
Removal of unvented space heaters is required by the contractor, even if used as a secondary heat
source and the unit conforms to ANSIZ21.11.2. Unvented space heaters must be removed from the site
by the contractor prior to weatherization but may remain until a replacement heating system in place.
Retrofits
Heating system repairs and retrofits must not exceed 50% of the replacement cost. If
repairs and retrofits exceed 50% of the replacement costs, contact the Grantee.
Automatic Setback Thermostat
•
•
•
•
•
•
All thermostats must be installed according to manufacturers’ instructions.
Thermostats are to be level. Installation shall include an appropriate wall plate.
New setback thermostats should generally be installed in the same location as the old
thermostats. In cases where the old thermostat is located in the kitchen, in direct sunlight,
over a heat register or radiator, or other location which would impede performance, the
new setback thermostat should be relocated.
A heating/cooling thermostat must be used if the home is centrally air conditioned.
Setback thermostats should have two setback periods, allowing residents to set
temperature back (or up for air conditioning) twice a day—once for sleep and once for
vacancy, such as work and school.
Manual setback or large-lettered thermostats should be installed for seniors or people with
visual impairments as appropriate.
XIV.65
February 2013
•
Occupants should be instructed on the setting and operation of new setback thermostats
and the replacement of batteries for thermostats utilizing batteries.
Intermittent Ignition Device and Vent Damper
Intermittent ignition device (IID) and vent damper installation are only permitted on boilers. Both an
IID and vent damper can increase the steady-state efficiency of an atmospheric boiler to around 80%.
The IID and vent damper must be installed according to manufacturer’s specifications.
•
•
•
•
IID must be purchased as a complete system, consisting of control module, dual
combination gas valve, igniter-sensor and wiring.
A vent damper may not be installed without an IID.
The vent damper must be equipped with an interlocking switch to prevent gas valve
opening, in the event of vent damper failure.
The installer must watch the furnace or boiler cycle several times to ensure correct
operation of the new IID and vent damper.
Flame Retention Burners
Existing gun-type burners may be replaced with a flame retention burner in accordance with governing
code requirements and manufacturer's recommendations. In addition, the following shall be completed
as needed:
•
Size the burner and nozzle to match the building’s heat load, making adjustments for new
insulation and air sealing done during weatherization.
• Install new combustion chamber, choosing one that fits the size and shape of the burner flame.
Or, change nozzles on the new burner to produce a flame that matches an existing combustion
chamber that is still in good condition. Either way, the flame must fill the combustion chamber
without impinging on it.
• Complete clean out and sealing of boiler sections, fire doors, flue pipe joints and anywhere
excess air can infiltrate the combustion area or flue passages.
• Install new primary control.
• Over-fire draft shall be set according to manufacturer’s specifications, usually at
o or 0.02 inches of water column.
• Replace barometric damper and flue pipe as necessary.
• Replace any controls or wiring required for safe, reliable operation.
• Replace furnace filter.
Upon installation, heating appliances receiving a flame retention burner must meet the following
requirements:
•
•
An oxygen (O2) reading of 4 to 7 percent (carbon dioxide of 12.5 - 10.3 percent).
A maximum smoke of 2.
XIV.66
February 2013
•
Stack temperature between 325oF and 600oF.
Heating System Replacement Standards
All new heating appliances shall carry a minimum one year warranty on workmanship. New condensing
units must have a lifetime manufacturer warranty on the primary heat exchanger and a minimum 10year warranty on the secondary heat exchanger.
Each client shall receive all manufacturer’s product warranty information, PMI manual, clear
maintenance instructions, educational information and a local telephone number for warranty
problems.
New heating appliances that are to be installed on a concrete, dirt, or damp floor, should be raised a
minimum of 1 inch above the floor surface, or per local code. Properly remove and dispose of existing
unit. Seal openings in chimneys where atmospheric vented appliances are eliminated.
Following completion of furnace replacement, contractor shall conduct a combustion safety test (see
section titled, “Combustion Safety Testing”).
Sizing calculations must meet accepted standards such as Manual “J”. Sizing should account for lower
heating loads resulting from insulation and air sealing work. Sizing calculations must be provided to the
Grantee for inclusion as a permanent part of the applicant file.
If a home has central air conditioning and furnace is replaced, the cost for the furnace replacement work
must include reinstallation of the existing central air conditioning unit.
Replacement heating appliances should meet the guidelines and efficiency ratings as shown in Table
300-7.
Efficiency (AFUE) of Replacement Heating Appliances
Table 300-7
Natural Gas/LP Furnaces
Oil Furnaces
Gas and Oil Boilers
90%, Direct vent sealed combustion
83%
80%
Note that unvented space heaters must be removed from the site by the contractor but may remain in
place until a replacement heating system is in place. See section titled, “Unvented Space Heaters”, for
additional information.
Natural Gas and Propane Fired Heating Systems
XIV.67
February 2013
New heating appliances must be installed to manufacturer’s specifications, following all applicable
building and fire codes.
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Replacement gas furnaces shall have a minimum Annual Fuel Utilization Efficiency (AFUE) of 90%
and must be direct vent, sealed combustion (2-pipe) units.
If a 90% unit cannot be installed for whatever reason, a state approved
Replacement Waiver must first be obtained.
External static pressure should be measured. If found to be less than 0.5" w.c. (125 Pa), consider
replacement furnaces with air handlers that have electrically commutated motors (ECMs).
Gas boilers must have a minimum AFUE of 80%.
Clearances of heating unit and its vent connector to nearby combustibles shall be according to
NFPA 54, tables 6.2.3 (a) and 6.2.3 (b).
All gas piping must be installed according to the American Gas Association
(AGA) National Fuel Gas Code specifications and any other appropriate codes.
Test water heater to ensure that it vents properly after installation of direct vent sealed
combustion appliance after setting-up house for worst case depressurization (see section titled,
“Worst Case Depressurization”).
Ensure proper sediment trap on gas line.
Measure gas pressure to ensure that it is within manufacturer’s specifications.
Adjust gas pressure if necessary to obtain proper gas input. Verify Btu input by clocking gas
meter (see Table 300-2).
Set thermostat’s heat anticipator to the amperage measured in the control circuit.
Repair or replace sections of the venting system that are corroded, rusted, clogged or blocked,
contain cracks or holes or are unsealed, loose or disconnected.
Follow manufacturer’s venting instructions and NFPA 54 Chapters 7 and 10 to establish a proper
venting system.
Flexible gas appliance connectors are not to be used on furnace and boiler installations.
Repair or replace unsafe power supply to appliance.
Install a properly sized and dedicated circuit to the heating appliance if one is necessary.
Oil Fired Heating Systems
•
•
•
•
•
•
Oil furnaces must have a minimum AFUE of 83%. Oil boilers must have a minimum AFUE of 80%.
Examine existing chimney and vent connector for suitability as venting for new appliance. The
vent connector may need to be re-sized and the chimney may need to be re-lined. Venting
should be in compliance with NFPA 31, chapters 1 through 11.
Check clearances of heating unit and its vent connector to nearby combustibles, by referring to
NFPA 31, tables 4-4.1.1, 4-4.1.2 and 5-5.1.
Test oil pressure to verify compliance with manufacturer’s specifications.
Test transformer voltage to verify compliance with manufacturer’s specifications.
Adjust oxygen, flue-gas temperature and smoke number to within manufacturer’s specifications.
XIV.68
February 2013
•
•
•
•
•
Inspect oil tank and remove deposits at bottom of tank as part of new installation.
Install new fuel filter and purge fuel lines as part of new installation.
Bring tank and oil lines into compliance with NFPA 31, Chapters 2 and 3 and appropriate state
regulations.
Repair or replace an unsafe power supply to appliance.
Install a properly sized and dedicated circuit to the heating appliance if one is necessary.
Furnace Installation
Observe the following standards in furnace installation.
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
All furnace work must be in compliance with:
 The Uniform Mechanical Code
 National Fire Prevention Association (NFPA)
 Local Codes (where existing)
 Furnace Manufacturer’s Specifications
Furnace should be sized to the home’s approximate heating load, accounting for weatherization
heat loss reductions.
If funds are available, return ducts and/or supply ducts must be included with furnace
replacement to improve air distribution and to establish acceptable values for static pressure
and heat rise.
Supply and return plenums must be mechanically fastened with screws and sealed to air handler
to form an essentially airtight connection.
Heat rise (supply temperature minus return temperature) must be within manufacturer’s
specifications.
High limit must stop fuel flow at less than 200°F. Furnace must not cycle on high limit.
Fan control should be set to activate fan at 115°F and deactivate it at 90°F if possible. Slightly
higher settings are acceptable if these recommended settings cause a comfort complaint.
Static pressure, measured in both supply and return plenums, must be within manufacturer’s
specifications. Static pressure outside of manufacturer’s specifications cannot be corrected with
the installation of a grille on the return air plenum.
Blower must not be set to operate continuously.
Holes through the air handler must be sealed by installer with mastic.
Filters must be held firmly in place and provide complete coverage of blower intake or return
register. Filters must be easy to replace.
Existing air conditioning coils must be re-installed with an airtight, removable panel, providing
convenient access for cleaning.
Furnaces which do not have a readily accessible filter access/location should have a filter rack
with a cover, installed in the return air plenum, in an accessible location.
External filter racks must have a cover that seals the filter opening.
Install a condensate pump where needed to reach an appropriate drain, if necessary.
XIV.69
February 2013
•
•
No used furnaces may be installed.
Contractors must remove and dispose of equipment being replaced unless otherwise directed
by the agency.
Boiler Installation
•
•
•
•
•
•
•
•
All boiler work must be in compliance with:
 The Uniform Mechanical Code
 National Fire Prevention Association (NFPA)
 Local Codes (where existing)
 Boiler Manufacturer’s Specifications
Boiler should be sized to the home’s heating load, accounting for weatherization heat loss
reductions.
Boilers must have an IID and vent damper or be power vented.
Maintaining a low-limit boiler temperature is not permitted unless the boiler is used for
domestic water heating.
An effective air-excluding device or devices must be part of the new hydronic system.
The pressure tank must be replaced or tested for correct pressure during boiler installation.
A pressure relief valve must be installed with the new boiler.
Extend new piping and radiators to conditioned areas like additions and finished basements,
currently heated by space heaters.
Space Heater Installation
Replace combustion space heaters with sealed combustion, direct vent space heaters. If conditions in
the house do not permit the installation of a sealed combustion direct vent space heater, an
atmospherically vented space heater may be installed. The space in which the space heater is installed
shall be treated as a combustion appliance zone (CAZ). A combustion safety test (section titled,
“Combustion Safety Testing”) shall be conducted.
Install space heater exactly as specified by manufacturer. Installation of ventless space heaters is not
permitted under the Illinois Home Residential Weatherization Program.
Wood Heating Installation
•
•
•
All installations must meet manufacturer's specifications.
All wood heating units must be certified to meet the EPA phase II emission standards or local
standards, whichever are most strict.
Installed units must be certified and labeled by:
a. National Fire Protection Association under 211; or
b. International Conference of Building Officials; or
c. Other equivalent listing organization.
XIV.70
February 2013
•
All clients receive in-home operation instructions to include proper wood-burning practices,
safety information and proper maintenance, e.g., stack thermometers, the need for fire
extinguishers, etc.
Water Heater Retrofits
Tank Insulation
Tank insulation is only permitted for electric water heaters. Do not insulate water heater if the unit has
a manufacturer’s warning against adding additional insulation. The water heater must be operating in a
safe condition before adding insulation. The water heater must not be leaking.
All electric water heaters to receive tank insulation must have a temperature-and-pressure relief valve
and a safety discharge pipe. If the existing relief valve is cored or leaking, it should be replaced. Install a
relief valve and discharge pipe if none exists. The pipe must terminate 6 inches above the floor and be
made of rigid metallic material. There shall be no threads on the end of the discharge pipe.
Electric water heaters shall be insulated to at least R10. Insulation must be mineral fiber manufactured
as a water heater blanket with vinyl or foil facing. The insulation must conform to ASTM C592-80 and
ASTM 892-79 with a flame spread rating no higher than 25.
Water heater insulation shall not obstruct pressure relief valves, thermostat, high-limit switch, plumbing
pipes or access plates.
Insulation shall be secured to the water heater utilizing:
•
•
•
A minimum of three vinyl straps or belts commercially available for water heater jackets,
A minimum of three metal banding straps or wires, or
A minimum of three strips of vinyl tape commercially available for water heater jackets. Each
strip shall form two complete wraps around the water heater jacket.
Fasteners should not compress insulation more than 50 percent of its normal thickness.
Insulation shall be cut and removed around all controls, service panels (including electrical access
panels), air inlets, temperature/pressure relief valves, drain valves specifications and instruction panels.
No insulation should come in contact with the floor.
•
•
Set both upper and lower thermostat to keep water at 120°F before insulating water heater.
Insulation may cover the water heater’s top if the insulation will not obstruct the pressure relief
valve.
• Access holes must be left in the insulation for the heating-element thermostats.
Pipe Insulation
•
•
Insulate first 6 feet of both hot- and cold-water pipes.
Cover elbows, unions and other fittings to same thickness as pipe.
XIV.71
February 2013
• Keep pipe insulation at least 3 inches away from flue pipe.
• Interior diameter of pipe sleeve must match exterior diameter of pipe.
Water Heater Replacement
Water heaters may be replaced only if the SIR is 1.0 or greater.
All water heater work must be in compliance with: the Uniform Mechanical Code, the National Fire
Prevention Association (NFPA), local codes (where they exist), and the water heater manufacturer’s
specification.
No used water heaters may be installed.
All replacement water heaters must have a pressure relief valve and a discharge pipe extending within 6
inches of the floor.
Electric Water Heaters
Electric storage tank type water heaters must have a minimum Energy Factor (EF) of
0.92. Electric heat pump water heaters must have an EF greater than or equal to 2.0 and must be
ENERGY STAR rated.
Gas and Propane Water Heaters
Gas and propane storage tank type water heaters must have a minimum Energy Factor (EF) of 0.67 and
be ENERGY STAR rated. Gas and propane tankless water heaters must have a minimum EF of 0.82 and
be ENERGY STAR rated. Gas and propane condensing water heaters must have a minimum EF of 0.80
and be ENERGY STAR rated.
In tight homes or homes where the mechanical room is located in living areas, replacement gas water
heaters must be either power-draft or sealed-combustion. Sealed- combustion water heaters are
preferred in tight homes where the water heater is located in the living space.
Gas Ranges
•
Inspect the stove for gas leaks at the fittings using gas leak detector.
Contractor Checklist
The HVAC Contractor Checklist is to be completed on each home where mechanical work was
completed. This document must be signed and dated by the contractor who completes the work. The
Contractor Checklist is located in the Post-Work Audit Exhibit Section IX.
•
All information requested on the contractor checklist for the particular heating system serviced
must be provided.
XIV.72
February 2013
•
All readings are to be obtained directly from the heating system serviced and are not to be
estimates derived from the contractor service manuals.
•
The Contractor Checklist must be provided to the Grantee as indicated in Section IX of the
Procedure Manual for inclusion as a permanent part of the applicant file.
•
Payment for services rendered by the HVAC contractor shall not be made until the Contractor
Checklist is completed, signed, and dated by the contractor who serviced the heating system.
XIV.73
February 2013
Section XIV
Diagnostic, Architectural, and Mechanical System Standards
Exhibits
Appendix A Part 440—Standards for Weatherization Materials
February 2013
Appendix A to Part 440—Standards for Weatherization Materials
The following Government standards are produced by the Consumer Product Safety Commission
and are published in title 16, Code of Federal Regulations:
Thermal Insulating Materials for Building Elements Including Walls, Floors, Ceilings, Attics, and
Roofs Insulation—organic fiber—conformance to Interim Safety Standard in 16 CFR part 1209;
Fire Safety Requirements for Thermal Insulating Materials According to Insulation Use—Attic
Floor—insulation materials intended for exposed use in attic floors shall be capable of meeting the same
flammability requirements given for cellulose insulation in 16 CFR part 1209;
Enclosed spaces—insulation materials intended for use within enclosed stud or joist spaces shall be
capable of meeting the smoldering combustion requirements in 16 CFR part 1209.
The following standards which are not otherwise set forth in part 440 are incorporated by reference
and made a part of part 440. The following standards have been approved for incorporation by reference
by the Director of the Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. These
materials are incorporated as they exist on April 5, 1993 and a notice of any change in these materials
will be published in the FEDERAL REGISTER. The standards incorporated by reference are available for
inspection at the National Archives and Records Administration (NARA). For information on the
availability of this material at NARA, call 202-741-6030, or go to:
http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
The standards incorporated by reference in part 440 can be obtained from the following sources:
Air Conditioning and Refrigeration Institute, 1501 Wilson Blvd., Arlington, VA 22209; (703) 524-8800.
American Gas Association, 1515 Wilson Blvd., Arlington, VA 22209; (703) 841-8400.
American National Standards Institute, Inc., 1430 Broadway, New York, NY 10018; (212) 642-4900.
American Society of Mechanical Engineers, United Engineering Center, 345 East 47th Street, New York,
NY 10017; (212) 705-7800.
American Society for Testing and Materials, 1916 Race Street, Philadelphia, PA 19103; (215) 299-5400.
American Architectural Manufacturers Association, 1540 East Dundee Road, Palatine, IL 60067; (708)
202-1350.
Federal Specifications, General Services Administration, Specifications Section, Room 6654, 7th and D
Streets, SW, Washington, DC 20407; (202) 708-5082.
Gas Appliance Manufacturers Association, 1901 Moore St., Arlington, VA 22209; (703) 525-9565.
National Electrical Manufacturers Association, 2101 L Street, NW, Suite 300, Washington, DC 20037;
(202) 457-8400.
National Fire Protection Association, Batterymarch Park, P.O. Box 9101, Quincy, MA 02269; (617) 7703000.
National Standards Association, 1200 Quince Orchard Blvd., Gaithersburg, MD 20878; (301) 590-2300.
(NSA is a local contact for materials from ASTM).
February 2013
National Wood Window and Door Association, 1400 East Touhy Avenue, Des Plaines, IL 60018; (708)
299-5200.
Sheet Metal and Air Conditioning Contractors Association, P.O. Box 221230, Chantilly, VA 22022-1230;
(703) 803-2980.
Steel Door Institute, 712 Lakewood Center North, 14600 Detroit Avenue, Cleveland, OH 44107; (216)
899-0100.
Steel Window Institute, 1230 Keith Building, Cleveland, OH 44115; (216) 241-7333.
Tubular Exchanger Manufacturers Association, 25 North Broadway, Tarrytown, NY 10591; (914) 3320040.
Underwriters Laboratories, Inc., P.O. Box 75530, Chicago, IL 60675-5330; (708) 272-8800.
More information regarding the standards in this reference can be obtained from the following
sources:
Environmental Protection Agency, 401 M Street, NW, Washington, DC 20006; (202) 554-1080.
National Institute of Standards and Technology, U.S. Department of Commerce, Gaithersburg, MD
20899, (301) 975-2000
Weatherization Assistance Programs Division, Conservation and Renewable Energy, Mail Stop 5G-023,
Forrestal Bldg, 1000 Independence Ave, SW, Washington, DC 20585; (202) 586-2207.
THERMAL INSULATING M ATERIALS FOR BUILDING ELEMENTS INCLUDING WALLS, FLOORS, CEILINGS,
ATTICS, AND ROOFS
[Standards for conformance]
Insulation—mineral fiber:
1
Blanket insulation
ASTM C665-88.
Roof insulation board
ASTM C726-88.
Loose-fill insulation
ASTM C764-88.
Insulation—mineral cellular:
Vermiculite loose-fill insulation
ASTM C516-80 (1990).
Perlite loose-fill insulation
ASTM C549-81 (1986).
Cellular glass insulation block
ASTM C552-88.
Perlite insulation board
ASTM C728-89a.
Insulation—organic fiber:
Cellulosic fiber insulating board
ASTM C208-72 (1982).
Cellulose loose-fill insulation
ASTM C739-88.
Insulation-organic cellular:
Preformed block-type polystyrene insulation
ASTM C578-87a.
February 2013
Rigid preformed polyurethane insulation board
ASTM C591-85.
Polyurethane or polyisocyanurate insulation board faced
with aluminum foil on both sides
FS HH-I-1972/1 (1981).
Polyurethane or polyisocyanurate insulation board faced
with felt on both sides
FS HH-I-1972/2 (1981). And Amendment
1, October 3, 1985.
2
Insulation—composite boards:
Mineral fiber and rigid cellular polyurethane composite roof ASTM C726-88.
insulation board
Perlite board and rigid cellular polyurethane composite
roof insulation
ASTM C984-83.
Gypsum board and polyurethane or polisocyanurate
composite board
FS HH-I-1972/4 (1981).
Materials used as a patch to reduce infiltration through the
building envelope
Commercially available.
1
ASTM indicates American Society for Testing and Materials.
2
FS indicates Federal Specifications.
THERMAL INSULATING M ATERIALS FOR PIPES, DUCTS, AND EQUIPMENT SUCH AS BOILERS AND FURNACES
[Standards for conformance]
Insulation—mineral fiber:
1
Preformed pipe insulation
ASTM C547-77.
Blanket and felt insulation (industrial type)
ASTM C553-70 (1977).
Blanket insulation and blanket type pipe insulation (metalmesh covered) (industrial type)
ASTM C592-80.
Block and board insulation
ASTM C612-83.
Spray applied fibrous insulation for elevated temperature
ASTM C720-89.
High-temperature fiber blanket insulation
ASTM C892-89.
Duct work insulation
Selected and applied according to
ASTM C971-82.
Insulation—mineral cellular:
Diatomaceous earth block and pipe insulation
ASTM C517-71 (1979)
Calcium silicate block and pipe insulation
ASTM C533-85 (1990).
Cellular glass insulation
ASTM C552-88.
Expanded perlite block and pipe insulation
ASTM C610-85.
Insulation—Organic Cellular:
Preformed flexible elastomeric cellular insulation in sheet and ASTM C534-88.
February 2013
tubular form
Unfaced preformed rigid cellular polyurethane insulation
Insulation skirting
ASTM C591-85.
Commercially available.
1
ASTM indicates American Society for Testing and Materials.
FIRE SAFETY REQUIREMENTS FOR INSULATING M ATERIALS ACCORDING TO INSULATION USE
[Standards for conformance]
Attic floor
Insulation materials intended for exposed use in attic floors shall be capable of
meeting the same smoldering combustion requirements given for cellulose insulation
1
in ASTM C739-88.
Enclosed space
Insulation materials intended for use within enclosed stud or joist spaces shall be
capable of meeting the smoldering combustion requirements in ASTM C739-88.
Exposed interior
walls and ceilings
Insulation materials, including those with combustible facings, which remain exposed
and serve as wall or ceiling interior finish, shall have a flame spread classification not
to exceed 150 (per ASTM E84-89a).
Exterior envelope
walls and roofs
Exterior envelope walls and roofs containing thermal insulations shall meet applicable
local government building code requirements for the complete wall or roof assembly.
Pipes, ducts, and
equipment
Insulation materials intended for use on pipes, ducts and equipment shall be capable
of meeting a flame spread classification not to exceed 150 (per ASTM E84-89a).
1
ASTM indicates American Society for Testing and Materials.
STORM WINDOWS
[Standards for conformance]
Storm windows:
1
Aluminum insulating storm windows ANSI/AAMA 1002.10-83.
Aluminum frame storm windows
ANSI/AAMA 1002.10-83.
Wood frame storm windows
ANSI/NWWDA I.S. 2-87. (Section 3)
Rigid vinyl frame storm windows
ASTM D4099-89.
Frameless plastic glazing storm
Required minimum thickness windows is 6 mil (.006 inches).
Movable insulation systems for windows
1
2
3
Commercially available.
ANSI/AAMA indicates American National Standards Institute/American Architectural Manufacturers
Association.
2
ANSI/NWWDA indicates American National Standards Institute/National Wood Window & Door
Association.
February 2013
3
ASTM indicates American Society for Testing and Materials.
STORM DOORS
[Standards for conformance]
Storm doors—Aluminum:
1
Storm Doors
ANSI/AAMA 1102.7-89.
Sliding glass storm doors
ANSI/AAMA 1002.10-83.
2
Wood storm doors
ANSI/NWWDA I.S. 6-86.
Rigid vinyl storm doors
ASTM D3678-88.
3
Vestibules:
Materials to construct
vestibules
Commercially available.
Replacement windows:
Aluminum frame windows
ANSI/AAMA 101-88.
Steel frame windows
Steel Window Institute recommended specifications for steel windows,
1990.
Wood frame windows
ANSI/NWWDA I.S. 2-87.
Rigid vinyl frame windows
ASTM D4099-89.
1
ANSI/AAMA indicates American National Standards Institute/American Architectural Manufacturers
Association.
2
ANSI/NWWDA indicates American National Standards Institute/National Wood Window & Door
Association.
3
ASTM indicates American Society for Testing and Materials.
REPLACEMENT DOORS
[Standards for conformance]
Replacement doors—Hinged doors:
Steel doors
1
ANSI/SDI 100-1985.
Wood doors:
2
Flush doors
ANSI/NWWDA I.S. 1-87. (exterior door provisions)
Pine, fir, hemlock and spruce doors
ANSI/NWWDA I.S. 6-86.
Sliding patio doors:
3
Aluminum doors
ANSI/AAMA 101-88.
Wood doors
NWWDA I.S. 3-83.
February 2013
1
2
3
ANSI/SDI indicates American National Standards Institute/Steel Door Institute.
ANSI/NWWDA indicates American National Standards Institute/National Wood Window & Door
Association.
ANSI/AAMA indicates American National Standards Institute/American Architectural Manufacturers
Association.
CAULKS AND SEALANTS:
[Standards for conformance]
Caulks and sealants:
1
Putty
FS TT-P-00791B, October 16, 1969 and
Amendment 2, March 23, 1971.
Glazing compounds for metal sash
ASTM C669-75 (1989).
Oil and resin base caulks
ASTM C570-72 (1989).
Acrylic (solvent types) sealants
FS TT-S-00230C, February 2, 1970 and
Amendment 2, October 9, 1970.
Butyl rubber sealants
FS TT-S-001657, October 8, 1970.
Chlorosulfonated polyethylene sealants
FS TT-S-00230C, February 2, 1970 and
Amendment 2, October 9, 1970.
Latex sealing compounds
ASTM C834-76 (1986).
Elastomeric joint sealants (normally considered to
include polysulfide, polyurethane, and silicone)
ASTM C920-87.
Preformed gaskets and sealing materials
ASTM C509-84.
1
2
2
FS indicates Federal Specifications.
ASTM indicates American Society for Testing and Materials.
WEATHERSTRIPPING
[Standards for conformance]
Weatherstripping
Commercially available.
Vapor retarders
Selected according to the provisions cited in ASTM C755-85 (1990). Permeance
not greater than 1 perm when determined according to the desiccant method described in ASTM E96-90.
1
Items to improve attic Commercially available.
ventilation
Clock thermostats
2
NEMA DC 3-1989.
1
ASTM indicates American Society for Testing and Materials.
February 2013
2
NEMA indicates National Electrical Manufacturers Association.
HEAT EXCHANGERS
[Standards for conformance]
1
Heat exchangers, water- ASME Boiler and Pressure Vessel Code, 1992, Sections II, V, VIII, IX, and X,
to-water and steam-toas applicable to pressure vessels. Standards of Tubular Exchanger
water
Manufacturers Association, Seventh Edition, 1988.
3
Heat exchangers with
2
gas-fired appliances
Conformance to AGA Requirements for Heat Reclaimer Devices for Use with
Gas-Fired Appliances No. 1-80, June 1, 1980. AGA Laboratories Certification
Seal.
Heat pump water heating Electrical components to be listed by UL.
heat recovery systems
1
4
ASME indicates American Society of Mechanical Engineers.
2
The heat reclaimer is for installation in a section of the vent connector from appliances equipped
with draft hoods or appliances equipped with powered burners or induced draft and not equipped with a
draft hood.
3
AGA indicates American Gas Association.
4
UL indicates Underwriters Laboratories.
BOILER/FURNACE CONTROL SYSTEMS
[Standards for conformance]
1
2
Automatic set back thermostats
Listed by UL. Conformance to NEMA DC 3-1989.
Line voltage or low voltage room
thermostats
NEMA DC 3-1989.
Automatic gas ignition systems
ANSI Z21.21-1987 and Z21.21a-1989. AGA Laboratories
Certification Seal.
Energy management systems
Listed by UL.
Hydronic boiler controls
Listed by UL.
Other burner controls
Listed by UL.
3
1
2
4
UL indicates Underwriters Laboratories.
NEMA indicates National Electrical Manufacturers Association.
3
ANSI indicates American National Standards Institute.
4
AGA indicates American Gas Association.
WATER HEATER MODIFICATIONS
February 2013
[Standards for conformance]
Insulate tank and distribution piping
(See insulation section of this appendix).
Install heat traps on inlet and outlet
piping
Applicable local plumbing code.
Install/replace water heater heating
elements
Listed by UL.
1
Electric, freeze-prevention tape for pipes Listed by UL.
Reduce thermostat settings
State or local recommendations.
Install stack damper, gas-fueled
ANS1 Z21.66-1988, including Exhibits A&B, and ANSI Z223.11988.
Install stack damper, oil-fueled
UL 17, November 28, 1988, and NFPA 31-1987.
Install water flow modifiers
Commercially available.
2
3
1
UL indicates Underwriters Laboratories.
2
ANSI indicates American National Standards Institute.
3
NFPA indicates National Fire Prevention Association.
WASTE HEAT RECOVERY DEVICES
[Standards for conformance]
1
Desuperheater/water
heaters
ARI 470-1987.
Condensing heat
exchangers
Commercially available components and in new heating furnace systems to
manufacturers' specifications.
Condensing heat
exchangers
Commercially available (Commercial, multi-story building, with teflon-lined tubes
institutional) to manufacturers' specifications.
Energy recovery
equipment
Energy Recovery Equipment and Systems Air-to-Air (1978) Sheet Metal and
2
Air-Conditioning Contractors National Association (SMACNA).
1
2
ARI indicates Air Conditioning and Refrigeration Institute.
SMACNA denotes Sheet Metal and Air Conditioning Contractors' National Association.
BOILER REPAIR AND MODIFICATIONS/EFFICIENCY IMPROVEMENTS
[Standards for conformance]
Install gas conversion burners
1
ANSI Z21.8-1984, (for gas or oil-fired systems) ANSI
Z21.17-1984, ANSI Z21.17a-1990, and ANSI Z223.12
1988. AGA Laboratories Certification seal.
February 2013
3
4
Replace oil burner
UL 296, February 28, 1989 Revision and NFPA 311987.
Install burners (oil/gas)
ANSI Z223.1-1988 for gas equipment and NFPA 311987 for oil equipment.
Re-adjust boiler water temperature or install
automatic boiler temperature reset control
ASME CSD-1-1988, ASME CSD-1a-1989, ANSI
Z223.1-1988, and NFPA 31-1987.
Replace/modify boilers
ASME Boiler and Pressure Vessel Code, 1992, Sections
II, IV, V, VI, VIII, IX, and X. Boilers must be Institute of
Boilers and Radiation Manufacturers (IBR) equipment.
Clean heat exchanger, adjust burner air
shutter(s), check smoke no. on oil-fueled
equipment. Check operation of pump(s) and
replacement filters
Per manufacturers' instructions.
Repair combustion chambers
Refractory linings may be required for conversions.
Replace heat exchangers, tubes
Protection from flame contact with conversion burners
by refractory shield.
Install/replace thermostatic radiator valves
Commercially available. One pipe steam systems
require air vents on each radiator; see manufacturers'
requirements.
Install boiler duty cycle control system
Commercially available. NFPA 70, National Electrical
Code (NEC) 1993 and local electrical codes provisions
for wiring.
1
ANSI indicates American National Standards Institute.
2
AGA indicates American Gas Association.
3
4
5
5
UL indicates Underwriters Laboratories.
NFPA indicates National Fire Prevention Association.
ANSI/ASME indicates American National Standards Institute/American Society of Mechanical
Engineers.
HEATING AND COOLING SYSTEM REPAIRS AND TUNE-UPS/EFFICIENCY IMPROVEMENTS
[Standards for conformance]
1
Install duct insulation
FS HH-I-558C, January 7, 1992 (see insulation
sections of this appendix).
Reduce input of burner; derate gas-fueled
equipment
Local utility company and procedures if applicable for
2
gas-fueled furnaces and ANSI Z223.1-1988
3
(NFPA 54-1988) including appendix H.
Repair/replace oil-fired equipment
NFPA 31-1987.
Replace combustion chamber in oil-fired furnaces NFPA 31-1987.
or boilers
February 2013
Clean heat exchanger and adjust burner: adjust ANSI Z223.1-1988 (NFPA 54-1988) including appendix
air shutter and check CO2and stack temperature. H.
Clean or replace air filter on forced air furnace
Install vent dampers for gas-fueled heating
systems
Applicable sections of ANSI Z223.1-1988 (NFPA 541988) including appendices H, I, J, and K. ANSI
Z21.66-1988 and exhibits A & B for electrically
operated dampers.
Install vent dampers for oil-fueled heating
systems
Applicable sections of NFPA 31-1987 for installation
4
and in conformance with UL 17, November 28, 1988.
Reduce excess combustion air:
A: Reduce vent connector size of gas-fueled ANSI Z223.1-1988 (NFPA 54-1988) part 9 and
appliances
appendices G & H.
B: Adjust barometric draft regulator for oil
fuels
Replace constant burning pilot with electric
ignition device on gas-fueled furnaces or boilers
NFPA 31-1987 and per manufacturers' (furnace or
boiler) instructions.
ANSI Z21.71-1981, Z21.71a-1985, and Z21.71b-1989.
Readjust fan switch on forced air gas or oil-fueled Applicable sections and appendix H of ANSI Z223.1furnaces
1988 (NFPA 54-1988) for gas furnaces and NFPA 311987 for oil furnaces.
Replace burners
See power burners (oil/gas).
Install/replace duct furnaces (gas)
ANSI Z223.1-1988 (NFPA 54-1988).
Install/replace heat pumps
Listed by UL.
Replace air diffusers, intakes, registers, and
grilles
Commercially available.
Install/replace warm air heating metal ducts
Commercially available.
Filter alarm units
Commercially available.
1
FS indicates Federal Specifications.
2
ANSI indicates American National Standards Institute.
3
NFPA indicates National Fire Prevention Association.
4
UL indicates Underwriters Laboratories.
REPLACEMENT FURNACES, BOILERS, AND WOOD STOVES
[Standards for conformance]
1
Chimneys, fireplaces, vents and solid fuel NFPA 211-1988.
burning appliances
Gas-fired furnaces
2
ANS1 Z21.47-1987, Z21.47a-1988, and Z21.47b-1989. ANSI
Z223.1-1988 (NFPA 54-1988).
February 2013
3
Oil-fired furnaces
UL 727, August 27, 1991 Revision and NFPA 31-1987.
Liquified petroleum gas storage
NFPA 58-1989.
Ventilation fans:
Including electric attic, ceiling, and
whole house fans
UL 507, August 23, 1990 Revision.
1
NFPA indicates National Fire Prevention Association.
2
ANSI indicates American National Standards Institute.
3
UL indicates Underwriters Laboratories.
AIR CONDITIONERS AND COOLING EQUIPMENT
[Standards for conformance]
Air conditioners:
1
Central air conditioners
ARI 210/240-1989.
Room size units
ANSI/AHAM RAC-1-1982.
2
Other cooling equipment:
Including evaporative coolers, heat pumps and other equipment
1
2
3
UL 1995, November 30, 1990.
4
ARI indicates Air Conditioning and Refrigeration Institute.
AHAM/ANSI indicates American Home Appliance Manufacturers/American National Standards
Institute.
3
4
UL indicates Underwriters Laboratories.
This standard is a general standard covering many different types of heating and cooling
equipment.
SCREENS, WINDOW FILMS, AND REFLECTIVE M ATERIALS
[Standards for conformance]
Insect screens
Commercially
available.
Window films
Commercially
available.
Shade screens:
Fiberglass shade screens
Commercially
available.
Polyester shade screens
Commercially
February 2013
available.
Rigid awnings:
Wood rigid awnings
Commercially
available.
Metal rigid awnings
Commercially
available.
Louver systems:
Wood louver systems
Commercially
available.
Metal louver systems
Commercially
available.
Industrial-grade white paint used as a heat-reflective measure on awnings, window
louvers, doors, and exterior duct work (exposed)
Commercially
available.
[58 FR 12529, Mar. 4, 1993, as amended at 69 FR 18803, Apr. 9, 2004]
February 2013