LIFE+

LIFE+
Environment Policy and Governance
LIFE CONOPS:
Development & demonstration of management plans
against -the climate change enhancedinvasive mosquitoes in S. Europe
LIFE12 ENV/GR/000466
Quality Assurance – Quality Control
Reporting Manual
September 2013
The LIFE CONOPS project “Development & demonstration of management plans against - the
climate change enhanced - invasive mosquitoes in S. Europe” (LIFE12 ENV/GR/000466) is co-funded
by the EU Environmental Funding Programme LIFE+ Environment Policy and Governance.
Implementation period:
1.7.2013 until 31.12.2017
Project budget:
Total budget:
2,989,314 €
EU financial contribution:
1,480,656 €
LIFE CONOPS’ Participating Beneficiaries:
Benaki Phytopathological Institute
Agricultural University of Athens
Azienda Sanitaria Locale Cesena
Azienda Unità Sanitaria Locale Ravenna
Centro Agricoltura Ambiente “G.NICOLI” S.R.L.
NCSR Demokritos
ONEX S.A.
Regione Emilia-Romagna Public Health Service
TERRA NOVA Environmental Engineering Consultancy Ltd.
Urban Environment and Human Resources Institute of Panteion University
The LIFE CONOPS’ QA/QC Committee consists of the following representatives of the project beneficiaries:
1. Machera Kyriaki
BENAKI PHYTOPATHOLOGICAL INSTITUTE
BPI
2. Serko Haroutounian
AGRICULTURAL UNIVERSITY OF ATHENS
AUA
3. Rafaella Sotiropoulou
NCSR DEMOKRITOS
DEMOKRITOS
4. Ioannis Spanos
TERRA NOVA Environmental Engineering Consultancy Ltd.
TERRA NOVA
5. Clive Richardson
URBAN ENVIRONMENT & HUMAN RESOURCES INSTITUTE
UEHR
6. Nickolaos Bossinas
ONEX S.A.
ONEX
7. Romeo Bellini
CENTRO AGRICOLTURA AMBIENTE “G.NICOLI” S.R.L.
CAA
8. Andrea Mattivi
REGIONE EMILIA-ROMAGNA PUBLIC HEALTH SERVICE
PH E-R
9. Davide Bianchi
AZIENDA SANITARIA LOCALE CESENA
AUS Cesena
10. Sara Giovannini
AZIENDA UNITA SANITARIA LOCALE RAVENNA
AUS Ravenna
The present QA/QC Reporting Manual was developed by:
TERRA NOVA Environmental Engineering Consultancy Ltd.
39 Kaisareias str., 115 27 Athens, Greece
Tel.: +30 210 7775597
Website: www.terranova.gr
TERRA NOVA’s scientific team that developed the QA/QC Reporting Manual consists of:
-
Ioannis Spanos, Chemical Engineer MSc.
Andreas Sotiropoulos, Environmental Scientist, MSc. Oceanography
Manual’s Preface
The successful implementation of a project requires significant effort to monitor and control its various
activities in order to ensure the optimum performance and homogeneity of the methods and actions
applied.
Towards this direction, the development and application of a Quality Assurance / Quality Control
(QA/QC) system is required. The operation of a QA/QC system will provide early warning in cases of
deviations of the designed project’s performance so as the necessary corrective measures to be
promptly applied.
The present Manual provides the guidelines for the conduction of the QA/QC Reports that will cover
the whole duration of LIFE CONOPS’ implementation, monitoring its progress.
Each QA/QC Report consists of the following 2 parts:


The Management Part, which will examine the following parameters:

milestones achievement

deliverables completion

consistency with the reporting schedule

consistency with the implementation timetable

performed expenditures and consistency with the approved budget’s cost breakdown
The Technical Part, which will examine the performance of the project’s implementation according
to its targets.
Every 9 months during the entire LIFE CONOPS’ implementation period, the QA/QC Committee will
conduct a QA/QC Report based on the present Reporting Manual and will deliver it to the Management
Committees of the project to be informed and to decide, if required, correction or improvement
actions.
A.
Management Part
Milestones
I nstruction: The consistency of the Milestones accomplished during LIFE CONOPS’ implementation until the date of the QA/QC Report, with the Milestones set by LIFE CONOPS’
approved Proposal for the same period, will be checked by filling in the green cells of the following table.
No.
Description of Approved Milestones
Associated
Action
Approved Accomplished? Accomplishment
Deadline
(Yes/No)
Date
1
CONOPS’s kick-off meeting
E1
31/07/2013
2
Development of 4 alternative logos
D1
31/08/2013
3
CONOPS’s website launching
D2
30/09/2013
4
Carbon Footprint Monitoring Manual development
E5
30/09/2013
5
Development of the QA/QC Manual
E2
30/09/2013
6
Environmental/ climatic data collection for Greece and Italy
A2
30/09/2013
7
Establishment of ovitrap networks in selected areas
A1
30/09/2013
D1
30/09/2013
A2
31/12/2013
E3
31/12/2013
8
9
10
Finalization of CONOPS’s logo
Completion of Spatial risk databases for the establishment
of IMS in Greece and Italy
Detection of other relevant EU projects
11
Organisation of stakeholder workshop in Greece
D3
31/12/2013
12
Organisation of stakeholder workshop in Italy
D3
31/12/2013
13
System specifications and architecture definition
B1
31/12/2013
B3
31/01/2014
A3
31/03/2014
A3
31/03/2014
A2
31/03/2014
E1
31/03/2014
E5
31/03/2014
E2
31/03/2014
B4
31/03/2014
14
15
16
17
18
19
20
21
Production of 18 Essential Oils derived from citrus fruits
Collection of data of the private (households)impacts and
costs caused by the ‘IMS problem’
Collection of data of the public impacts and costs caused by
the “IMS problem”
Collection of land uses data of high risk regions in Greece
and Italy
Compilation of Inception Report
st
Compilation of the 1 Carbon Footprint Report
Compilation of the 1st QA/QC Report
Completion of Spatial risk databases for the establishment
of IMS in Greece and Italy
Comments
22
Establishment of communication
E3
31/03/2014
23
Forecasting of future climatic conditions
B4
31/03/2014
B1
31/03/2014
B3
30/06/2014
A1
30/06/2014
A2
30/06/2014
B1
30/06/2014
D3
30/06/2014
D3
30/06/2014
B3
31/07/2014
B3
30/09/2014
D4
30/09/2014
B2
30/09/2014
B2
30/09/2014
B2
30/09/2014
B1
30/09/2014
E5
31/12/2014
E2
31/12/2014
B5
31/12/2014
C1
31/12/2014
C1
31/12/2014
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
Integrated prototype development
Chemical composition and bioactivity data for the 18 EOs
derived from citrus fruits
Collecting man-biting adult IMS with human bait method
(assembled data for monitoring and virus status)
Completion of spatial databases of suitable places/ areas
for the pilot monitoring of IMS in Greece and Italy
Development of the NMS system for the prototype IMS
monitoring devices
Production of informative Leaflets
Production of informative Posters
Production of 36 EOs derived from Juniperus taxa
Chemical composition and bioactivity data for the 36 EOs
derived from Juniperus taxa
Design of Boards informative content
Field installation of prototype IMS monitoring devices (for
Pilot Monitoring)
Operation initiation of prototype IMS monitoring devices
(for Pilot Monitoring)
Operation of the prototype NMS of the IMS monitoring
devices
Test and evaluation on the operational performance of the
entire system
Compilation of the 2nd Carbon Footprint Report
nd
Compilation of the 2 QA/QC Report
Involvement of the major stakeholders for the design of
IMS management plans
Performance test initiation regarding the prototype IMS
monitoring devices
Performance test initiation regarding the trap NMS
prototype
Large amount of Juniperus taxa EO produced and certified
B3
31/03/2015
44
Large amount of citrus fruit EO produced and certified
B3
31/03/2015
45
Organisation of Mid-Term Conference in Greece
D3
31/03/2015
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
Collection and analysis of the current situation concerning
the control actions for the control of mosquitoes in Pilot
areas
Reproduction and installation of Boards
B6
30/06/2015
D4
30/06/2015
E1
30/09/2015
rd
E5
30/09/2015
rd
E2
30/09/2015
B6
30/09/2015
C2
31/12/2015
C2
31/12/2015
C2
31/03/2016
C3
30/06/2016
E5
30/06/2016
E2
30/06/2016
B6
30/09/2016
E1
31/12/2016
D3
31/12/2016
D3
31/12/2016
C3
30/03/2017
C3
31/03/2017
Compilation of Mid-term Report
Compilation of the 3 Carbon Footprint Report
Compilation of the 3 QA/QC Report
Implementation of management plans in the pilot areas in
summer 2015
Collection of environmental/ micro-climatic of the pilot
implementation areas of management plans in Greece and
Italy
Spatial mapping of the characteristics of the pilot
implementation areas of management plans in Greece and
Italy
1st Report of the assessment of the environmental impacts
from the pilot implementation of the management plans
1st set of interviews for public authorities, officials and
experts, concerning the public benefits and costs initiated by
the management plans
Compilation of the 4th Carbon Footprint Report
Compilation of the 4th QA/QC Report
Implementation of management plans in the pilot areas in
summer 2016
Compilation of Progress Report
Organisation of Final Conference in Greece
Organisation of Final Conference in Italy
Creation of database including results from structured
interview for public authorities, officials and experts
2nd set of interviews for public authorities, officials and
experts, concerning the public benefits and costs initiated by
the management plans
Compilation of the 5th Carbon Footprint Report
E5
31/03/2017
65
Compilation of the 5th QA/QC Report
E2
31/03/2017
66
Creation of database including structured survey’s results
C3
30/06/2017
67
68
69
70
71
72
73
74
Project’s DVD production
Creation of integrated report with the socioeconomic
evaluation of the management plans
Finalization of the Environmental Impact Assessment of the
management plans
Implementation of management plans in the pilot areas in
summer 2017
Completion of CONOPS’s Layman’s Report compilation
Upload of CONOPS’s Layman’s Report 1st version on
CONOPS’s website
Compilation of Audit Report
th
Compilation of the 6 QA/QC Report
th
D3
30/06/2017
C3
30/09/2017
C2
30/09/2017
B6
30/09/2017
D5
30/11/2017
D5
30/11/2017
E6
31/12/2017
E2
31/12/2017
75
Compilation of the Final (6 ) Carbon Footprint Report
E5
31/12/2017
76
Continuous update and maintenance
D2
31/12/2017
E4
31/12/2017
D5
31/12/2017
E3
31/12/2017
E1
31/03/2018
77
78
79
80
Design of the After-LIFE Communication Plan
Finalization of CONOPS’s Layman’s Report and upload on
the website
Maintenance of networking
Compilation of Final Report
Deliverables
I nstruction: The consistency of the Deliverables produced during LIFE CONOPS’ implementation until the date of the QA/QC Report, with the Deliverables set by LIFE CONOPS’
approved Proposal for the same period, will be checked by filling in the green cells of the following table.
No.
Description of Approved Deliverables
Associated
Action
Approved
Deadline
1
CONOPS logo
D1
30/09/2013
2
CONOPS’s website designed, developed and launched
D2
30/09/2013
3
QA/QC Manual
E2
30/09/2013
4
Carbon Footprint Monitoring Manual
E5
30/09/2013
5
Spatial risk database for the establishment of IMS in Greece
A2
31/12/2013
6
Spatial risk database for the establishment of IMS in Italy
A2
31/12/2013
B1
31/12/2013
B1
31/12/2013
D3
31/12/2013
10 Stakeholder workshop in Italy
D3
31/12/2013
11 List and data of other relevant EU projects
E3
31/12/2013
A3
31/03/2014
A3
31/03/2014
B1
31/03/2014
15 Integrated prototype IMS monitoring device(demonstrator)
B1
31/03/2014
16 Inception Report
E1
31/03/2014
17 1st QA/QC Report
E2
31/03/2014
18 Contact data list of persons involved in relevant efforts
E3
31/03/2014
7
8
9
Report on the detailed functional specifications of the
prototype IMS monitoring device and its sub-systems
(including performance criteria)
Report on the technology state-of-the-art and the feasibility
of the prototype IMS monitoring device and its sub-systems
Stakeholder workshop in Greece
Report of the private (households) impacts and costs caused
12
by the ‘IMS problem’
Report of the public impacts and costs caused by the “IMS
13
problem”
Detailed description of the prototype IMS monitoring device
14 architecture (specification of the various sensor node H/W &
S/W sub-systems, their interfaces and interdependencies)
Implemented?
(Yes/No)
Completion
Date
Comments
19 1st Carbon Footprint Report
E5
31/03/2014
A1
30/06/2014
A1
30/06/2014
A1
30/06/2014
A2
30/06/2014
A2
30/06/2014
B1
30/06/2014
B1
30/06/2014
B3
30/06/2014
28 Climate Evolution Report
B4
30/06/2014
Spatial risk database for future establishment of IMS in
29
Greece
B4
30/06/2014
30 Spatial risk database for future establishment of IMS in Italy
B4
30/06/2014
31 Informative Leaflets
D3
30/06/2014
32 Informative Posters
D3
30/06/2014
B1
30/09/2014
B1
30/09/2014
B2
30/09/2014
B3
30/09/2014
D4
30/09/2014
D4
30/09/2014
B3
31/10/2014
20
21
22
23
24
Database with the Dengue and Chikungunya virus status in
adult females of IMS in Greece and Italy
Database with the resistance status of the IMS in Greece and
Italy
Report of the current state of the problem targeted in Greece
and Italy
Spatial database of suitable places/ areas for the pilot
monitoring of IMS in Greece
Spatial database of suitable places/ areas for the pilot
monitoring of IMS in Italy
25 NMS prototype (including S/W and H/W)
Test and Validation Report regarding the prototype IMS
26
monitoring device demonstrator
Technical report with the characteristics(yield, composition,
27 mosquito biocide-repellant activities) of 18 EOs derived from
citrus fruits
33
Detailed description of the NMS architecture of the prototype
IMS monitoring device and its subsystems
34 Test and Validation Report regarding the NMS prototype
Report on the Prototype IMS monitoring devices developed in
35
terms of Pilot Monitoring
Technical report with the characteristics(yield, composition,
36 mosquito biocide-repellant activities) of 36 EOs derived from
two Juniperus taxa
Notice boards installed at the areas where Pilot monitoring
37
will be performed
38 Production of project’s notice boards
39
Technical report for the selection of the most suitable (yieldbioactivity-price) EOs for use in pilot experiments
40
Report on the NMS prototype developed in terms of Pilot
Monitoring
B2
31/12/2014
41 2nd QA/QC Report
E2
31/12/2014
42 2nd Carbon Footprint Report
E5
31/12/2014
B2
31/03/2015
B2
31/03/2015
B2
31/03/2015
B3
31/03/2015
B3
31/03/2015
B5
31/03/2015
B6
30/06/2015
D4
30/06/2015
43
44
45
46
47
Database with the Dengue and Chikungunya virus status in
adult females IMS in pilot areas (1st Report)
Database with the collected IMS along with their seasonal
abundance in pilot areas (1st Report)
Database with the oviposition activity of female IMS in pilot
areas (1st Report)
Technical report for the pilot-scale production of the selected
Juniperus taxa EO
Technical report for the pilot-scale production of the selected
citrus fruit EO
48 Management plans for IMS control
List of management actions for the control of IMS, in the
49
pilot areas according to the proposed management plans
Notice boards installed at the areas where Pilot
50
implementation of management plans will be performed
51 Mid-term Report
E1
30/09/2015
rd
E2
30/09/2015
rd
E5
30/09/2015
B6
31/12/2015
C2
31/12/2015
C2
31/12/2015
D3
31/12/2015
B2
31/03/2016
B2
31/03/2016
B2
31/03/2016
52 3 QA/QC Report
53 3 Carbon Footprint Report
Report on plan activities for 2015 according to the designed
management plans
Database of environmental and micro-climatic data of the
55 pilot implementation areas of management plans in Greece
and Italy
Spatial mapping of the characteristics of the pilot
56 implementation areas of management plans in Greece and
Italy
54
57 Mid-Term workshop in Greece
Database with the Dengue and Chikungunya virus status in
58
adult females IMS in pilot areas (2nd Report)
Database with the collected IMS along with their seasonal
59
abundance in pilot areas (2nd Report)
Database with the oviposition activity of female IMS in pilot
60
areas (2nd Report)
61
1st Report of the Assessment of the environmental impacts
from the pilot implementation of the management plans
C2
31/03/2016
62 4th QA/QC Report
E2
30/06/2016
63 4th Carbon Footprint Report
E5
30/06/2016
Report on plan activities for 2016 according to the designed
64
management plans
B6
31/12/2016
65 Final Conference in Greece
D3
31/12/2016
66 Final Conference in Italy
D3
31/12/2016
67 Presentations in workshops and conferences
D3
31/12/2016
68 Published articles, press releases, interviews
D3
31/12/2016
69 Progress Report
E1
31/12/2016
C3
30/03/2017
E2
31/03/2017
72 5 Carbon Footprint Report
E5
31/03/2017
73 A Database including structured survey’s results
C3
30/06/2017
74 Project’s DVD production
D3
30/06/2017
B6
30/09/2017
B6
30/09/2017
C1
30/09/2017
C1
30/09/2017
79 Report for mosquito and mosquito-borne disease surveillance
C1
30/09/2017
80 Report for mosquito control
C1
30/09/2017
C2
30/09/2017
C3
30/09/2017
D5
30/11/2017
70
A Database including results from structured interview for
public authorities, officials and experts
71 5th QA/QC Report
th
75
76
77
78
Final Report on plan activities for the period 2015-2017
according to the designed management plans
Report on plan activities for 2017 according to the designed
management plans
Performance Test and Validation Report regarding the
prototype IMS monitoring device in terms of the Pilot
implementations
Performance Test and Validation Report regarding the trap
NMS prototype in the Pilot implementations
Final Report of the Assessment of the environmental impacts
81
of the management plans
Integrated report with the socioeconomic evaluation of the
82
management plans
83 1st version of CONOPS’s Layman’s Report
Database with the Dengue and Chikungunya virus status in
adult females IMS in pilot areas (final report)
Database with the collected IMS along with their seasonal
85
abundance in pilot areas (final report)
Database with the oviposition activity of female IMS in pilot
86
areas (final report)
84
B2
31/12/2017
B2
31/12/2017
B2
31/12/2017
87 Final report of integrated management plans to control IMS
B7
31/12/2017
88 Final version of CONOPS’s Layman’s Report
D5
31/12/2017
E2
31/12/2017
E3
31/12/2017
E4
31/12/2017
92 6 (Final) Carbon Footprint Report
E5
31/12/2017
93 Independent Auditor’s Report
E6
31/12/2017
94 Final Report
E1
31/03/2018
th
89 6 QA/QC Report
90
Report on networking with other relevant EU projects and its
results
91 After-LIFE Communication Plan
th
Reporting Schedule
I nstruction: The consistency of the LIFE CONOPS’ implementation progress reporting until the date of the QA/QC Report, with the reporting schedule set by LIFE CONOPS’
approved Proposal for the same period, will be checked by filling in the green cells of the following table.
No.
Type of Report
Submission
Deadline
31/03/2014
1
Inception Report
2
Mid-term Report (with payment request)
30/09/2015
3
Progress Report
31/12/2016
4
Final Report
(with payment request)
31/03/2018
Submitted?
(Yes/No)
Submission
Date
Comments
Project’s implementation consistency with the approved Timetable
I nstruction: LIFE CONOPS’ implementation consistency with the approved Timetable until the date of the QA/QC Report, is illustrated by drawing the Actual progress of LIFE
CONOPS until this date into the approved Timetable.
Action No
A1
A2
A3
B1
B2
B3
B4
B5
B6
B7
C1
C2
C3
D1
D2
D3
D4
D5
E1
E2
E3
E4
E5
E6
III
Legend 1
Approved progress:
Actual progress:
Reporting Date:
2013
IV
I
II
2014
III
IV
I
II
2015
III
IV
I
II
2016
III
IV
I
II
2017
III
IV
Legend 2
Action No
A1
A2
A3
B1
B2
B3
B4
B5
B6
B7
C1
C2
C3
D1
D2
D3
D4
D5
E1
E2
E3
E4
E5
E6
Name of Action
Current state of the problem targeted
Analysis of climatic & environmental parameters influencing the invasive mosquitoes introduction & establishment
Socio-economic impacts of the problem targeted
Design and development of the prototype IMS monitoring (surveillance) devices
Pilot implementation of the surveillance plan
Development and production of biodegradable substances to control invasive mosquitoes
Future climatic and environmental data projection
Design of management plans to control IMS
Pilot implementation of management plans to control IMS
Development of integrated management plans to control IMS
Monitoring of the performance of the pilot implementations
Assessment of the environmental impacts of the management plans
Assessment of the socio-economic impacts of the management plans
Creation of project’s logo
Development, launching and maintenance of project’s website
Dissemination of project’s progress and results
Development of project’s notice boards
Development of Layman’s Report
Project management by BPI
Monitoring of project progress
Networking activities with other relevant EU projects
Development of project’s After-LIFE Communication Plan
Monitoring of project’s Carbon footprint
Audit of project’s financials
Consistency of project’s expenditures with the approved Cost Breakdown
I nstructions:
The evaluation of the consistency of the expenditures performed during the implementation of the LIFE CONOPS
project until the date of the QA/QC Report will be performed based on the approved Proposal’s Cost Breakdown
(Financial Form R2 - Costs per Action).
In the following “Summarised LIFE CONOPS’ implementation expenditures cost” Table the grey cells present the
approved budget per expenditure category, while the green ones present the so far status.
LIFE CONOP’s Coordinator ten days before the end of each nine month reporting period will send to all
Beneficiaries the “QA-QC - Expenditures per Beneficiary” excel file in order to be filled-in.
Important notes for all Beneficiaries for the use of the above excel file:
(a) The costs which are filled-in are the Total Costs and not the Eligible Costs.
(b) The budget figures do not include Overheads, which are calculated on a flat rate basis (7%) of the
eligible costs. The result is presented in a separate cell for the total of the expenditures of all Actions.
(c) Fill-in the costs of the expenditures performed by your organisation since the beginning of the project's
implementation until the QA/QC Reporting date.
The Coordinator after receiving the filled-in excel files from all Beneficiaries, transfers the data in the “QA-QC Expenditures Summary” excel file. The data resulting from summing-up the Beneficiaries’ data are then imported
into the following “Summarised LIFE CONOPS’ implementation expenditures cost” Table.
Summarised LIFE CONOPS’ implementation expenditures cost
Budget line
Personnel
Action No
A1
A2
A3
B1
B2
B3
B4
B5
B6
B7
C1
C2
C3
D1
D2
D3
D4
D5
E1
E2
E3
E4
E5
E6
Approved
60.310,00
45.200,00
102.890,00
91.060,00
108.030,00
62.430,00
88.600,00
99.125,00
446.540,00
84.355,00
99.230,00
27.800,00
114.140,00
2.050,00
16.700,00
74.050,00
3.550,00
10.625,00
206.720,00
46.610,00
39.565,00
1.100,00
32.390,00
7.625,00
Total Cost
per budget
line
1.870.695,00
So far
Travel
Approved
So far
External
Assistance
Approved
So far
Equipment
Approved
So far
Prototype
Approved
So far
Consumables
Approved
15.000,00
So far
Other Costs
Approved
6.000,00
7.560,00
2.000,00
28.000,00
3.000,00
5.000,00
25.500,00
32.100,00
1.500,00
7.000,00
2.000,00
90.170,00
40.000,00
2.500,00
22.110,00
13.720,00
4.000,00
2.000,00
108.440,00
4.550,00
274.000,00
25.000,00
104.521,00
200,00
3.000,00
10.000,00
41.500,00
2.350,00
17.300,00
12.700,00
4.200,00
8.000,00
374.371,00
62.500,00
56.000,00
274.000,00
127.850,00
30.200,00
So far
Total Cost
per Action
Approved
So far
81.310,00
52.760,00
104.890,00
398.060,00
251.970,00
101.080,00
90.100,00
124.125,00
579.210,00
84.355,00
123.340,00
41.520,00
118.340,00
5.050,00
26.700,00
235.121,00
3.550,00
10.625,00
228.220,00
46.610,00
39.565,00
1.100,00
32.390,00
15.625,00
2.795.616,00
Overheads 193.698,00
Total 2.989.314,00
B.
Technical Part
I nstructions: The evaluation of the implementation of the Technical part of the LIFE CONOPS project until the
date of the current QA/QC Report, will be performed according to the methodologies and specifications which are
set at the “Description and methods employed” section presented under each individual Action in the approved
Proposal of the project.
Comments, suggestions, proposed actions and corrective measures must be presented, where it is required,
towards the improvement and optimisation of the performance of each individual Action and consequently of the
whole project in total.