CCC Pipeline Capabilities Istanbul 2012 Pipeline Record up to 2011 CCC has constructed approximately 16,500 kilometers of pipeline which is equivalent to more than 1.5 times the circumference of the MOON. Pipeline Construction Number of Pipeline Spreads Manual Spreads Fully Automatic Spreads 18 Nos. 12 Nos. Pipeline Statistics 16,500 KMS Pipelines Diameter greater than 36 in: Diameter greater than 16 and smaller than 36: Diameter smaller or equal to 16 in: 4,900 kms 7,000 kms 4,600 kms CCC Group Manpower CCC currently employs approximately 125,000 people in its worldwide operations CCC Plant & Equipment CCC owns a large fleet of construction equipment valued at over USD 1bn 1,100 pieces of Pipe laying & Earthmoving Equipment ELECTRIC GENERATORS & LIGHTING TOWERS EARTHMOVING EQUIPMENT 906 675 PIPELAYING EQUIPMENT 201 CIVIL ENGINEERING & CONSTRUCTION EQUIPMENT 1,345 AIR COMPRESSORS 454 WORK/SURVEY BOATS & STANDARD FACILITIES HEAVY DUTY VEHICLES 168 2,319 CRANES 977 VEHICLES & LIGHT TRUCKS 2,625 TOTAL NO. OF EQUIPMENT: TOTAL VALUE OF EQUIPMENT: WELDING MACHINES 8,131 17,800 US$ 1,050 MILLION Current Pipeline Projects CCC Scope of Work Contract Value (US$ MILL) Project Location Client EPC Contractor Qusahwira Field 1.8 MMBOPD Project ‐ 20", 14“, 8“ totaling 286 km of Pipelines, Transfer Lines and Flowlines ‐ EPC new central degassing station ‐ EPC New remote degassing station ‐ Water injection clusters ‐ Well tie ins Abu Dhabi ADCO Nat'l. Petroleum Construction Co. (NPCC) C 518 Bab Thammama G & Habshan 2 Development 1.88 MM BOPD Project Fabrication and erection, laying flow lines and pipelines, EPC field erected tanks, 4 remote degassing stations and BCDS with all associated works, mechanical and E&I works. Abu Dhabi ADCO Nat'l. Petroleum Construction Co. (NPCC) C 610 Sahil, Asab & Shah (SAS) Full Fields Development Construction of 315 km trunklines and flowlines 16" ‐ 30". Construction and EPC Main Oil Lines to Asab and 8 no. buildings. Upgrade existing CDS and 2 RDS at Shah. Upgrade existing CDS and 1 RDS at Sahil. Demolition of 31 km of pipelines 6" ‐ 30". Connections to well heads at Sahil and Shah. Abu Dhabi ADCO CCC/Tecnicas Reunidas Consortium EPC 1,200 Current Pipeline Projects CCC Scope of Work Contract Value (US$ MILL) Project Location Client EPC Contractor QCLNG Export Pipeline & Collection Header Detailed design and construction of 528 km 42“ Natural Gas Pipeline Laterals of 12 ‐ 24“ Pigging facilities Receipt station Australia QCLNG Pipeline Co. Ltd. (a BG Group Co.) McConnell Dowell / CCC JV with KBR E&P Services S/C EPC 750 Australia Pacific LNG (APLNG) Pipeline 360 km 42“ Gas Pipeline 77 km 36“ Gas Pipeline 90 km 30" Gas Pipeline Australia Australia Pacific LNG PTY Ltd. (APLNG) McConnell Dowell / CCC JV with KBR E&P Services S/C EPC 940 QCLNG Export Pipeline ‐ Narrows Crossing EPC of 2 Nos. 13 km each 42" Natural Gas Pipeline Delivery station 2 Nos. 1.3 km HDD drives 1.5 km cofferdam in marine clays 2.4 km of dredged trench and tow Australia QCLNG Pipeline Co. Ltd. (a BG Group Co.) McConnell Dowell / CCC JV with KBR E&P Services S/C EPC 320 CCC Performance in EPC Pipelines CCC has a premium record of performance in the execution of EPC Pipeline Projects Selection of Completed Major EPC Pipeline Projects Pipelines (Oil & Gas) Location Client 24” Ambatovy Slurry Pipeline Installation 30” OAG Onshore Pipelines & Habshan Facilities 24”/30” Eastern Gas Distribution System Upgrade 36” Bu Hasa – Habshan Gas 50 km 36” Ras Laffan/Mesaieed Sweet Gas 126 km 24” Mina Al Fahl – Sohar Crude 266km 32 ”Fahud – Suhar (Oman) 302 km 48” Maqta – Jebel Ali (UAE) 112 km 42” Baku-Tbilisi-Ceyhan (Oil) 443 km 42” Georgia Border - Baku (Gas) 443 km 26” Mozambique – RSA (Gas) 860 km Ras Laffan Common Cooling Water Phase I 18” Bab- Umm Al Nar Crude Oil Pipeline Project Madagascar Ambatovy Minerals UAE GASCO UAE Dolphin UAE GASCO Qatar QP Oman ORC Oman OGC UAE GASCO Azerbaijan BTC Azerbaijan SCPC Mozambique Sasol Qatar QP UAE GASCO Start Date 2008 2006 2006 2006 2004 2004 2001 2000 2002 2002 2001 2001 2002 Pipeline Projects Around the World Ambatovy Project Pipeline projects have taken CCC into many distinguished areas around the globe. However, few have been as exotic and challenging as the Madagascar Pipeline Ambatovy Project Madagascar is an island in the Indian ocean. Its located 400 KM to the east of Africa Madagascar is the world's 47th largest country and the 4th largest island. Madagascar is the largest producer of Vanilla in the world Madagascar is referred to as the red island due to the color of its soil Ambatovy Project Madagascar has 5% of the worlds plant and animal Species, 80% of which are not found anywhere else Ambatovy Project Madagascar is home to as many as 12,000 plant species, 70%-80% of which are endemic. This makes it one of the most diverse floras on the planet! Ambatovy Project Major Exports include Vanilla, coffee, sugar cane, cocoa, peanuts, etc. Major Imports include Petroleum, Consumer goods and food Ambatovy Project Ambatovy Slurry Pipeline Installation Location: Madagascar Client: Ambatovy Minerals SA EPCM: SNC Lavalin Contract Value: US$ 250 Million Completion Date: December 2010 Contract Duration: 34 Months Ambatovy Project The Ambatovy Nickel Mining Project is a world-class, project in Madagascar that is positioned to be the world’s biggest nickel mine by 20132014 The mine site consists of an open-pit mining operation and an ore preparation plant Slurried laterite ore is delivered from the mine site via pipeline to a process plant and refinery located near Tomasina Ambatovy Project – CCC Scope of Work CCC Scope for the Ambatovy Project was the Construction of : 248 km 24" Carbon Steel ore slurry pipeline from the Ore Preparation Plant to Tomasina Valve stations Pressure monitoring stations Water pipelines Terminal facility tailings pipelines (HDPE) Fiber Optic Cable Ambatovy Project – SCOPE OF WORK Ambatovy Project – Design Basis Slurry was transmitted through the pipeline by means of gravity 15% slope was required to be maintained A water pipeline was required for purifying the slurry. The water was of high salinity, as such an HDPE liner was used All welds were tested by Automatic Ultrasonic Testing Ambatovy Project – Major Quantities No. Major Activity Description UOM QTY. at COMPLETION 1 Total Earthworks - Cut / Fill m³ 11,200,000 2 Total Rock Drilled & Blasted m³ 300,000 3 Total length of pipes Welded & laid, CS Km 248 4 Total length of pipes Welded & laid, HDPE Km 21 5 Total Length of Horizontal Directional Drilling Km 4 6 Total Major Road / Railroad Crossings No 10 7 Total River / Stream / Minor Road Crossings Nos. 330 8 Total Reinstatement / Revegetation Km. 530 9 Total Quantity of Saddles [24”,30,36”] No 16,000 10 Total Quantity of Concrete Coated Pipes Km 14 11 Total Quantity of Fiber Optic Cable laid Km 215 Ambatovy Project – Major Subcontracts No. Subcontractor Name Scope of Work 1 Sicon Oil & Gas Completed Detailed & Field Engineering Works 2 Essar Construction Limited Pipelay on the East Section Slurry Pipeline 3 Flowtex Egypt Horizontal Directional Drilling 4 UT Quality Inc. Automated Ultrasonic Welding Ambatovy Project – Challenges The challenges of constructing a pipeline through the exotic Madagascar region was an extraordinary experience for CCC Many challenges were encountered, such as: – – – – – – – – – – Climate Mobilization Early Site Survey Logistics Site conditions Terrain Local communities Schedule IT and Communication Environmental Protection Measures Ambatovy Project – Challenges cont’d Climate Madagascar has two seasons, a hot wet season and a dry cool season CCC’s experience was none of the above! It was only rain, or pour or rain! Cyclones were frequent (at least 3 major ones per year) The above resulted in CCC revising the execution plan, i.e. Utilization of mini spreads Increased number of camps and site facilities and storage yards Special clothing and boots provided for crews to overcome the mud and access the site by means of walking in some areas Ambatovy Project – Challenges cont’d Mobilization / Logistics Non-availability of scheduled shipping lines All shipping through the crowded South African Durban port Chartering flights and vessels for manpower, equipment and material to be used specifically for this job Inland Transportation for personnel and equipment Distances in Madagascar are measured in Hours not Kilometers Non continuous access to site restricted maneuvering between construction site fronts, camps and storage yards Utilization of huge amount of military trucks to transport our staff and crews Utilization of articulated trucks to transport project and earthwork material Delivery of all line pipe material to many stockpiles along the ROW Ambatovy Project – Challenges cont’d Early Site Survey Access to the pipeline was impossible Route alignment sheets were prepared as a desktop exercise LiDAR data was not enough for the construction works CCC carried out the early site survey to define the Center Line utilizing bush rangers along with our survey team Ambatovy Project – Challenges cont’d Site Conditions Adding to the complexity of the construction works was the unusual site conditions encountered such as: All-year round muddy and slippery ROW Rocky mountains Canyons and gulley Dense tropical forests Major Rivers Wetlands Swamps Environmentally sensitive areas Civil unrest To overcome most of the site conditions challenges, CCC utilized: HDD for non-accessible areas Erosion control techniques Utilization of specialized equipment to work in muddy and swampy areas Ambatovy Project – Challenges cont’d Terrain Getting through the harsh and rugged terrains was a major challenge: The gravity driven design and the 15% slope required deep cuts into the mountains often exceeding 80 meters (equivalent to a 30 story building) Huge amount of earthwork (in excess of 11 million m3) was required to be removed to achieve the ROW The terrain restrictions required CCC to utilize pre-welded pipeline strings in short sections and excessive cold bending Ambatovy Project – Challenges cont’d Project Schedule Overall tight Schedule: Start Date Completion Date Mar 2008 Dec 2010 Ambatovy Project – Challenges cont’d IT and Communications Communication facilities in Madagascar are limited CCC made our own facilities to cater for communication between all site fronts, head office, CCC Area Office, Client and Engineer to ensure all voice and data links are working and reliable at all times Ambatovy Project – Challenges cont’d Environmental Protection Measures 1. Environmental Protection Steps during the construction phase: a) b) c) d) Sloping & benching to prevent landslip and minimize soil erosion Moving and reservation of top soil for rehabilitation works Building bridges using flume pipes & rocks to cross over streams Protecting the stream banks by stones, upstream & downstream (rip rap) e) Installation of silt fence & grass filters down stream of the rivers f) Installation of Geotextile fence along the rice fields & water crossing g) Cut & stock pile trees according to the Environmental Protection Procedure h) Mobilization of large number of specialized environmental officers with knowledge on Madagascar flora and fauna Ambatovy Project – Challenges cont’d Environmental Protection Measures 2. Water Management a) Drain Channels and Crown Ditches along ROW to control water movement during rainy seasons b) Installation of Decantation Basins at ponds Ambatovy Project – Challenges cont’d Environmental Protection Measures 3. Soil stabilization and Re-vegetation a) Soil compaction embankments re-profiled and compacted b) Re-vegetation and manual seeding of the entire ROW including slopes c) Mulching and spreading of trees along the ROW Ambatovy Project – Construction Highlights Unconventional Pipeline execution strategies To overcome all challenges, the execution strategy had to be tackled as follows: 1. Continuous survey team on site 2. Splitting the pipeline into East and West Portions 3. Mobilizing a very strong planning team 4. Open as many fronts as possible utilizing self-sufficient mini spreads 5. Utilizing articulated trucks at all times 6. Utilizing environmental specialists at all times 7. Long term agreements with Airline and Shipping companies 8. Mobilizing community liaison officers for every village, town and city 9. Utilizing of local security services 10. Full coordination team to interact with the local authorities Ambatovy Project – Conclusion Madagascar was a true out of this world challenge and a unique pipeline experience The obstacles encountered only served to empower CCC dedicated teams CCC proved to successfully overcome all challenges CCC Delivered Consolidated Contractors Company Ambatovy Project – Conclusion THANK YOU! Consolidated Contractors Company
© Copyright 2024