NYHAMNA EXPANSION STATUS OG FOKUS FREMOVER

NYHAMNA EXPANSION
STATUS OG FOKUS FREMOVER
Kontaktpunkt Nyhamna
10.02.2015
Stein Inge Rakvåg
Interface Manager
Norway Projects
Februar 2015
1
LANDFALL
Polarled pipeline trekkes inn i starten av mars. Dette utføres av
Statoil/Halliburton og Allseas‘ største rørleggingsfartøy Solitaire
Norway Projects
11. februar 2015
2
CIVIL
 Civil = excavations and ground work, columns, plinths, paving, cable
culverts, weir boxes, u.g. piping, etc.
 Mesteparten av Civil-arbeid vil ferdigstilles i 2015, knapt 40% nå
 Mye forarbeid for å plassere nye moduler. Første kom 1.12
 Neste «test» er installasjon av piperack no 4 i P35, i Mars.
 Ser på samtidig arbeid i perioden hvor vi har nedstengt anlegg
Norway Projects
11. februar 2015
3
GRUNNARBEID, ARMERING OG STØPING
Norway Projects
11. februar 2015
4
CONSTRUCTION – AREA P45 SUBSTATION S-130
Casting of roof and all walls above level 2 in Substation S-130
Concrete casting and anchoring of foundations
5
Norway Projects
5
CONSTRUCTION – AREA P35 & SLUG CATCHER AREA P 37
New Firewater & Open drain line tested and lived up
Completion of last foundation for Pre TA FDR-110- completed during January
Piling for extension of S-070 completed- start concrete work at S-070
Concrete casting of foundations
6
Norway Projects
6
CONSTRUCTION – AREA P46 & MEG AREA P 53
Ground work, lean concrete and form work started
Casting of foundations started
Demolishing work completed
7
Norway Projects
7
P35
Norway Projects
11. februar 2015
8
NYHAMNA SITE CONSTRUCTION
Norway Projects
9
NYHAMNA SITE CONSTRUCTION
Norway Projects
10
Nyhamna Expansion: Loadout of first module at MPG, Gdansk....
On 20 and 22 of January the first Steel pre-fabricated module ‘R45V01’ (A main pipe rack with a total weight 113 tons) was safely and successfully
loaded-out at the Mostostal Pormorze (MPG) fabrication facility in Gdansk, Poland. After a 3-day transit though the Baltic and North Seas, the module
arrived safely at the Kværner Stord Construction yard on the 26th of Jan.
R45V01 is the Nyhamna Expasion Project’s first module to be transported from MPG to Kvaerner Stord for further outfitting i.e. piping, E&I
etc and will be followed by 5 more major module structures in the coming months.
Well done to the Nyhamna Expansion Module Construction Team!
Offload at Kværner Stord....
M, E & I : Main activities
R35HV01
R37TV01
N244V01
R37SV01
17 modules delivered
Inst. of Pre-Turnaround modules (4)
in P37N, P35E and U24
Installation EIT equipment :
• Breakers 132kv, 22kV & 11kV in S30
• LV (690+400) switchboards in S40, S50, S60, S70, S80,
S100
• Cabinets in S040
• Cable pulling to E94, in S40, U24, P37
Stick-built and welding in habitats
Pipe support installation
PFP, insulation, Heat tracing act.
TURNAROUND 2015 – BASIS FOR NEW BASELINE
Jan.
All Workorders
And duration
In SAP
Febr.
Training plan
established
TAR3
Mar.
Apr.
May
June
July
List of
All tools / EQ Comm. Proc. all personnel
ordered
Completed
Job-Pack’s
PtW
SJA
Modules to be MC
Complete in TA2015
Receive, pack and bag installation material
N355V01
N336V01
Receive, and mark all piping spool’s
Modules to be installed
In front of TA2015
M
S
6
R35HV01
Receive modules at site
N244V01
Modules to be lifted in TA2015
N338V01/02
N335V01
Inst. of Pre-Turnaround modules
N336V02
Measuring
Prefabr. HU Spools
R37TV01
M
S
6
R37TV01
Pre-Turnround Work
Remove insulation
Remove Heat-tracing
Remove PFP
Scaffolding
Turnaround
Piping Tie-in
Electro Piping Tie-in
Electro Tie-in
Modification Mechanical equipm.
ESD / SAS system upgrading
Stick-built for TA2015 (FAV75)
Jan.
1
Febr.
Norway Projects
Mar.
Apr.
N337V01
May
June
July
VOLUM TA
 Moduler, tanker, internals
 220 tonn Rørinstallasjon
 250 Piping tie-ins
 151 Pipe supports

33 E,I&T tie-ins
Norway Projects
11. februar 2015
14
HOVEDKOMPONENTENE
Norway Projects
11. februar 2015
15