TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING MATERIALS May 11, 2015 CALTRANS BAY AREA TOLL AUTHORITY CALIFORNIA TRANSPORTATION COMMISSION Letter of Transmittal TO: Toll Bridge Program Oversight Committee (TBPOC) DATE: May 10, 2015 FR: Program Management Team (PMT) RE: TBPOC Meeting Materials Packet – May 11, 2015 Herewith is the TBPOC Meeting Materials Packet for the May 11th meeting. The packet includes memoranda and reports that will be presented at the meeting. Contents is provided following the Agenda to help locate specific topics. A Table of Final Agenda TBPOC REGULAR MEETING May 11, 2015 Executive Session (Loma Prieta Conference Room): 1:30 PM – 2:30 PM Regular Session (Room 1906): 2:30 PM – 4:30 PM Pier 7, Mission Bay Office, 325 Burma Road, Oakland, CA Dial-in Number: 1(866) 803-2146; Access Code: 2474385 Item Number/ Topic 1. 2. 3. 4. 5. 6. 7. EXECUTIVE SESSION a. SAS Outstanding Work* b. YBITS 2 Contract – CCO No. 111 USCG Additional Scope* CHAIR’S REPORT Presenter S. Heminger, BATA CONSENT CALENDAR a. TBPOC Regular/ Urgent Meeting Minutes A. Fremier, BATA 1. TBPOC March 5, 2015 Regular Meeting Minutes* 2. TBPOC April 17, 2015 Regular Meeting Minutes* 3. TBPOC May 4, 2015 Urgent Meeting Minutes* PROGRAM ISSUES a. Budget Forecast and Risk Assessment Update** Brian Maroney, CT b. 2015 First Quarter Project Progress and Financial P. Lee, BATA Update** SAN FRANCISCO-OAKLAND BAY BRIDGE UPDATES a. YBITS 2 Contract D. Vilcheck, CT 1. Project Update** 2. CCO No. 97 – Contract Time Extension* 3. CCO No. 111 – USCG Additional Scope* b. Pier E3 Demonstration Contract and Permits S. Whipple, CT/ Update* S. Galvez, CT c. 504/288 Demolition Update* S. Whipple, CT d. SAS Update 1. Construction Update** S. Whipple, CT 2. Tower Anchor Rod Testing Plan** Brian Maroney, CT OTHER BUSINESS a. Report on matters discussed and actions taken at NA Urgent Meeting S. Heminger, BATA b. Report on matters discussed and actions taken during Executive Session GENERAL PUBLIC COMMENT Next TBPOC Regular Meeting: June 23, 2015 - TBD * Attachments ** Attachments to be sent out under separate cover Time Desired Outcome Information 5 min Approval 20 min 5 min Approval Approval 15 min 5 min Information Approval Approval Information 10 min Information 5 min 30 min Information Approval NA NA 5 min Information Accessibility and Title VI: TBPOC provides services/accommodations upon request to persons with disabilities and individuals who are limited-English proficient who wish to address Committee matters. For accommodations or translations assistance, please call the Metropolitan Transportation Commission (MTC) at 510.817.5757 or 510.817.5769 for TDD/TTY. We require three working days' notice to accommodate your request. Acceso y el Titulo VI: El TBPOC puede proveer asistencia/facilitar la comunicacion a las personas discapacitadas y los individuos con conocimiento limitado del ingles quienes quieran dirigirse a la Comité. Para solicitar asistencia, por favor llame a la Comisiớn Metropolitano de Transporte (MTC) al numero 510.817.5757 o al 510.817.5769 para TDD/TTY. Requerimos que solicite asistencia con tres dias habiles de anticipacion para poderle proveer asistencia. Meeting Conduct: In the event that any public meeting conducted by TBPOC is willfully interrupted or disrupted by a person or by a group or groups of persons so as to render the orderly conduct of the meeting unfeasible, the Chair may order the removal of those individuals who are willfully disrupting the meeting. Such individuals may be subject to arrest. If order cannot be restored by such removal, the members of the committee may direct that the meeting room be cleared (except for representatives of the press or other news media not participating in the disturbance), and the session may continue on matters appearing on the agenda. Table of Contents TBPOC MEETING May 11, 2015 INDEX TAB AGENDA ITEM 1 1 2 2 3 3 4 4 5 5 6 6 DESCRIPTION EXECUTIVE SESSION a. SAS Outstanding Work* b. YBITS 2 Contract – CCO No. 111 USCG Additional Scope* CHAIR’S REPORT CONSENT CALENDAR a. TBPOC Regular/Urgent Meeting Minutes 1. TBPOC March 5, 2015 Regular Meeting Minutes* 2. TBPOC April 17, 2015 Regular Meeting Minutes* 3. TBPOC May 4, 2015 Urgent Meeting Minutes* PROGRAM ISSUES a. Budget Forecast and Risk Assessment Update** b. 2015 First Quarter Project Progress and Financial Update** SAN FRANCISCO-OAKLAND BAY BRIDGE UPDATES a. YBITS 2 Contract 1. Project Update** 2. CCO No. 97 – Contract Time Extension* 3. CCO No. 111 – USCG Additional Scope* b. Pier E3 Demolition Contract and Permits Update* c. 504/288 Demolition Update* d. SAS Update 1. Construction Update** 2. Tower Anchor Rod Testing Plan** OTHER BUSINESS a. Report on matters discussed and actions taken at Urgent Meeting b. Report on matters discussed and actions taken during Executive Session 7 7 GENERAL PUBLIC COMMENT * Attachments ** Attachments to be sent out under separate cover Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) FR: Dan McElhinney, Caltrans Chief Deputy District 4 Director/ Brian Maroney, SFOBB Project Chief Engineer , Caltrans RE: Agenda No. - 1a DATE: May 11, 2015 Item- Self‐Anchored Suspension (SAS) Outstanding Work Recommendation: For Information Only Cost: NA Schedule Impacts: NA Discussion: An update on the Self‐Anchored Suspension (SAS) outstanding work will be provided at the TBPOC May 11th meeting executive session. 1 of 1 Item 1a_SAS_memo-11May15.doc Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) FR: Dan McElhinney, Caltrans Chief Deputy District 4 Director/ Deanna Vilcheck, SFOBB Area Construction Manager , Caltrans RE: Agenda No. - 1b Item- DATE: May 8, 2015 Yerba Buena Island Transition Span (YBITS) 2 Contract Contract Change Order (CCO) No. 111 – USCG Additional Scope Recommendation: For Information Only Cost: NA Schedule Impacts: NA Discussion: Information on the YBITS 2 Contract Change Order 111 (USCG Additional Scope) will be presented at the TBPOC May 11th meeting executive session. 1 of 1 Item 1b_YBITSCCO111_memo-11May15.doc ITEM 2: CHAIR’S REPORT Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) DATE: FR: Andrew Fremier, Deputy Executive Director, Operations, MTC/BATA RE: Agenda No. - 3a1 May 8, 2015 Item- TBPOC March 5, 2015 Regular Meeting Minutes Recommendation: Approval Cost: NA Schedule: NA Discussion: The Program Management Team has reviewed and requests TBPOC approval of the March 5, 2015 Regular Meeting Minutes. 1 of 1 Item 3a1_Memo-11May15-v0.doc TBPOC REGULAR MEETING MINUTES March 5, 2015, 10:00am – 2:30pm Pier 7, Mission Bay Office, 325 Burma Road, Oakland, CA Attendees: TBPOC Members: Steve Heminger (Chair), Malcolm Dougherty, Will Kempton PMT Members: Dan McElhinney, Andrew Fremier, Stephen Maller Participants: Ade Akinsanya, Rosalynn Chongchaikit, Rich Foley, Peter Lee, Brian Maroney, Bijan Sartipi, Deanna Vilcheck, Bill Casey, Karen Wang, Stefan Galvez, Leah Robinson-Leach, Gary Thomas Convened: 1:50 PM 1. Items EXECUTIVE SESSION Action a. SFOBB Self-Anchored Suspension (SAS) Outstanding Work 2. CHAIR’S REPORT The Chair thanked the Department for the tour of the new bridge earlier in the day. The Chair discussed proposed AB 1284 legislation by Assembly Member Baker that would make the TBPOC subject to the Bagley-Keene Open Meeting Act. 3. CONSENT CALENDAR a. TBPOC Regular/Urgent Meeting Minutes 1. TBPOC December 19, 2014 Minutes* 2. TBPOC January 27, 2015 Minutes* 3. TBPOC February 6, 2015 Minutes* 4. TBPOC February 19, 2015 Minutes* 4. The Chair requested that the PMT draft a letter addressed to Assembly Member Baker on the topic that TBPOC will continue to conduct open public meetings for the remaining years the TBPOC oversees the last of the projects of the Toll Bridge Program. The TBPOC APPROVED the Consent Calendar, as presented. PROGRAM ISSUES a. Capital Outlay Support (COS) Update** Dan McElhinney, Caltrans District 4 Chief Deputy District Director, presented an overall work plan for fiscal 1 of 7 TBPOC_030515MtgMin-final-rev1 2.docx (Continued) Items year 2014-15 with updated expenditure data now available thru January 2015. Discussion included March 2015 unanticipated work related to the SAS tower anchor rod grouting issue and the continual evaluation of COS budget impact for the current fiscal year. It was noted that the COS budget risks ahead include the on-going METS A&E rod investigation. Dan McElhinney said he would return next month with a COS update and forecast of SAS tower anchor rod investigation capital outlay and COS costs. The Department is currently tracking the $41.4M budget. There is no action required by the POC at today’s March meeting. b. Risk Management Update** Rich Foley, SFOBB Risk Manager, presented a risk management process update. An extensive risk assessment is underway to include scope, schedule, and capital outlay/support cost impacts for a range of project risks to develop an updated risk register and a review of the overall program funding and expenditures for the current and future fiscal years. Challenges going forward included project close-out, ongoing SAS, YBITS2, Marine Foundations and 504/288 demolition work. o Pier E3 will have a separate risk register including an updated estimate for the conventional method of marine foundation removal and recognizing the implosion risk opportunity. o The Department will focus on the mitigation effort moving forward with risk assessment process. The approach to assessing risks will be adjusted to account for various variables including optimistic and pessimistic potential outcomes. Action Dan McElhinney to provide a COS update and forecast of SAS tower anchor rod investigation CO and COS next month. The Chair asked for the Department to look at possibilities within the existing overall Toll Bridge Program budget to address risks due to unanticipated work. Rich Foley will provide a comprehensive risk update next quarter. 2 of 7 TBPOC_030515MtgMin-final-rev1 2.docx (Continued) 5. Items SAN FRANCISCO-OAKLAND BAY BRIDGE UPDATES a. YBITS 2 Update** Deanna Vilcheck, SFOBB Area Construction Manager, provided an update on the latest construction activities and progress on the YBITS 2 contract. It was noted that the gate at the end of the bike path will stop public access to the island. Andrew Fremier, BATA Deputy Executive Director, reported they are currently circulating a contract to support their staff in the conceptual planning of the temporary improvements around the gate area for public weekend use when there is no construction activity. Improvements will also provide for bike and pedestrian protection during the week when construction activity is present. Action Deanna Vilcheck will present an updated schedule and contract change order as part of the YBITS 2 update for the next April TBPOC meeting. b. Pier E3 Demolition Permits Update** Stefan Galvez, Caltrans District 4 Chief Office of Environmental Analysis, provided an update on the Pier E3 Demolition Permits. Preliminary meetings have been completed and detailed packages are under development to request various agency approvals of the Pier E3 Demonstration project. o Will Kempton, CTC Executive Director, inquired if they would process the revalidation of the environmental document ahead of receiving any permits. Stefan Galvez responded that once they have the Biological Opinion from NOAA fisheries they can do the revalidation. o Stefan Galvez said the permits are on the critical path and if they are not approved by July/August, the project will have to wait another year. o There was discussion about engaging the Tri-Agency Partnership executive 3 of 7 TBPOC_030515MtgMin-final-rev1 2.docx (Continued) Items level forums to coordinate resource agencies for expedient resolution of permits for the Pier E3 demonstration project. Action c. 504/288 Demolition Bid Open Update** Bob Finney, Caltrans District 4 Deputy District Director Construction presented the results of the recent 504/288 Demolition Bid Opening. The lowest bid came in at $69,470,000 from C California Engineering Contractors/Silverado Joint Venture. o Work is anticipated to start as early as May 2015. o The Chair inquired about the demolition methodology. Bob Finney responded the Department is still reviewing the bids and the different methods provided by each contractor. o The engineer’s estimate was $93M. The risk for the bids ranged from -$11M and + $24M in risk. d. SAS Update** Brian Maroney, Toll Bridge Deputy Program Manager, presented an update on the SAS remaining contract items including tower seismic anchor rods grouting procedures field progress and lab activities. o Discussion items included: complimentary system of rods and dowels in the tower; various stages of protection of rods during construction; water sample testing (absence of bay water); tower base grout status verification; field cleaning operation; verification testing of tower rods; rod removal and testing program; microcracks; corrosion modeling; tower pull back operations (lasting about 1 year) in Sept 2011; and a comparison of Seismic Demands with Varying Anchor Rod Configurations. Department (Malcolm/Stefan) will follow up on process to engage the Tri-Agency Partnership executive level forums. Staff to provide a presentation on the proposed demolition methodology at a future TBPOC meeting. 4 of 7 TBPOC_030515MtgMin-final-rev1 2.docx (Continued) o o o o o o o o Items Malcolm Dougherty inquired if the recent testing on the rods were more thorough than the QA required in the contract documents. Brian Maroney confirmed the recent testing was beyond contract specifications and the mechanical testing results are all within contract compliance. The Chair requested for Caltrans to perform investigation of the current condition of the anchor rods through ultrasonic testing (UT) inspection. Will Kempton and Malcolm Dougherty concurred with the statement. The Chair inquired if the micro-cracks could lead to fracture, Brian Maroney did not expect the micro-cracks to propagate. Brian Maroney will return in the next month with more information. The Chair asked if there was water at the tower when a rod was removed in 2013 and if any corrosion was observed. Bill Casey, Caltrans SAS Resident Engineer, confirmed that once extracted the mass of balled up denso tape was wet indicating that there was moisture trapped between the denso tape system and the grout. It was not full of standing water. The Chair inquired about dehumidification and other techniques to keep the holes dry. Brian Maroney discussed the various options to keep the holes dry. The Chair inquired if the Peer Review is involved in the review of the tower seismic anchor rods. Brian Maroney responded he would like them to be on board as soon as possible and has a proposal in process to do so. Will Kempton asked for more information and actions taken in regards to the missing QA documents. Will Kempton requested if the residue and stains on the structure could be cleaned up so future observations would Action Caltrans Construction/METS to perform investigation of the current condition of all tower anchor rods through UT inspection in response to the Chair’s request. CT Construction will provide pictures around the base of the tower in 2013 when an initial rod was removed for testing. Construction will have residue and stains on the SAS cleaned. 5 of 7 TBPOC_030515MtgMin-final-rev1 2.docx (Continued) Items be more noticeable. Bill Casey confirmed this could be done. Malcolm Dougherty concurred with this request. o Malcolm Dougherty summarized his concurrence to further investigate the second rod removed, perform additional scanning electron microscope (SEM) analysis on rod 136-2-3. The requested for the Department to consider extracting a third rod for testing. o The Chair requested Seismic Safety Peer Review Panel confirmation on the decision to not grout the inspection holes of the tower anchor rods. 6. Action Brian Maroney to obtain concurrence from Seismic Peer Review Panel on the proposed decision of not grouting the tower anchor rod inspection holes. OTHER BUSINESS a. Report on matters discussed and actions taken at Urgent Meeting NA b. Report on matters discussed and actions taken during Executive Session o The Chair reported that they discussed the outstanding work on the SAS and no action was taken. 7. Next TBPOC Meeting The next TBPOC regular meeting is scheduled on April 17, 2015 at Sacramento. GENERAL PUBLIC COMMENT There was a public comment about the misaligned main cable PWS anchor rods that presented last May 2014 and the outstanding request for information on how the issue was resolved. The Chair requested staff to include the item on the agenda for the next TBPOC meeting in April. Information will be on the web for those unable to attend. * Reference memo provided in the TBPOC March 5th TBPOC Packet **Reference supplemental information in the TBPOC March 5th TBPOC Supplemental Packet Adjourned: 4:15 PM 6 of 7 TBPOC_030515MtgMin-final-rev1 2.docx (Continued) TBPOC REGULAR MEETING MINUTES March 5, 2015, 10:00am – 2:30pm APPROVED BY: ______________________________________ STEVE HEMINGER, TBPOC Chair Executive Director, Bay Area Toll Authority ______________ Date ______________________________________ ______________ WILL KEMPTON Date Executive Director, California Transportation Commission ______________________________________ MALCOLM DOUGHERTY Director, California Department of Transportation ______________ Date 7 of 7 TBPOC_030515MtgMin-final-rev1 2.docx Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) DATE: FR: Andrew Fremier, Deputy Executive Director, Operations, MTC/BATA RE: Agenda No. - 3a2 May 10, 2015 Item- TBPOC April 17, 2015 Regular Meeting Minutes Recommendation: Approval Cost: NA Schedule: NA Discussion: The Program Management Team has reviewed and requests TBPOC approval of the April 17, 2015 Regular Meeting Minutes. 1 of 1 Item 3a2_Memo-17Apr15Min-11May15-v0.doc TBPOC REGULAR MEETING MINUTES April 17, 2015, 1:00pm – 4:00pm 1120 N Street, Conference Room 2116, Sacramento, CA Attendees: TBPOC Members: Steve Heminger (Chair), Malcolm Dougherty, Will Kempton PMT Members: Dan McElhinney, Andrew Fremier, Stephen Maller Participants: Rosalynn Chongchaikit, Rich Foley, Brian Maroney, Bijan Sartipi, Deanna Vilcheck, Bill Casey, Chris Traina, Stefan Galvez, Bob Finney, Steven Whipple, Karen Wang, Mike Foerder Convened: 2:28 PM 1. 2. 3. 5. Items Action EXECUTIVE SESSION a. SAS Outstanding Work b. YBITS 2 Contract CHAIR’S REPORT CONSENT CALENDAR a. TBPOC Regular/ Urgent Meeting Minutes 1. TBPOC March 5, 2015 Regular Meeting Minutes* 2. TBPOC March 19, 2015 Urgent Meeting Minutes* 3. TBPOC April 1, 2015 Urgent Meeting Minutes* • • PMT recommended that agenda item 3.a.1 be removed from the agenda and action be deferred on this item to the next TBPOC meeting. The TBPOC APPROVED the remaining Consent Calendar items 3.a.2 and 3.a.3. PROGRAM ISSUES a. Capital Outlay Support Update** Dan McElhinney, Caltrans District 4 Chief Deputy District Director, presented the COS update. COS expenditures data through March 2015 is $31.8M for construction contracts. The ongoing unanticipated SAS tower anchor rod initial investigation relatedwork has expended$1.7M through March for this fiscal year. The total COS expenditures data through March 2015 1 of 11 TBPOC_041715MtgMin-final.docx (Continued) • • • • • • Items is $33.5M. The PMT will meet to review the FY 14/15 work plan of staffing and consultant contracts to further define options to maintain the current approved budget of $42.4M, and review the additional tower anchor rod investigation testing plan proposal cost estimates S. Whipple, Caltrans District 4 Principal • Construction Engineer, discussed on site staff reductions and workload. As of May 1st, Caltrans has reduced consultants and state staff. Caltrans is looking at staff assignments and reassigning staff to locations of need and priorities. Challenges ahead requiring staff support include work with Coast Guard, YBI ramps and TIDA work. Discussion included upcoming opportunity milestones that influence staffing assignments: completion of SAS contract and SAS tower anchor rod testing, and continued progress of cantilever demolition, and 504/288 contractor-suggested alternate construction methods. W. Kempton, CTC Director, inquired about the forecast of staying in budget. S. Whipple mentioned that the field site staff forecast is below than what was presented in January 2015. Dan outlined that he would ask the PMT to review the COS FY forecast when available and an updated program COS forecast will be presented at the May TBPOC meeting. M. Dougherty, Caltrans Director, noted the biggest influence is what they decide to do for the testing program of tower base rods. Dan McElhinney noted that the cost of the tower anchor rods testing can be an additional $3-5M, which will be part of Brian Maroney’s presentation in today’s agenda. Once costs are confirmed, it Action Dan McElhinney, will provide an update to the PMT for review and present at May TBPOC meeting. 2 of 11 TBPOC_041715MtgMin-final.docx (Continued) • • • Items will be presented at the May TBPOC meeting. M. Dougherty noted that with the 504/288 being awarded and it has a positive implication to the overall budget and he looks forward to seeing the COS breakdown with this new information. W. Kempton noted the longer the TBPOC waits for the information, it reduces the opportunity to help with the budget. Providing info in May only allows the TBPOC 6-7 weeks left in the fiscal year. Dan McElhinney plans to present updated FY 14/15 COS forecast information to the PMT for their review. Item will be presented at the May TBPOC meeting. Action b. Risk Management Update* • S. Whipple, introduced the risk management agenda item. The project team initiated an extensive risk assessment to include scope, schedule, and capital outlay/support cost impacts for a range of project risks to develop an updated risk register for all East Span contracts. The full update will be presented at the May TBPOC meeting. • R. Foley, SFOBB Risk Manager, presented a slide presentation on the current status of risk management preliminary findings. Discussion included analysis of risks in the 504/288, YBITS 2, and Marine Foundations contracts. The cable traveler was removed from corridor risk register (as a toll bridge maintenance item). The potential need for additional de-humidification system at the tower base was added to the corridor risk register. • The Chair commented there was a big change in the Marine Foundation 3 of 11 TBPOC_041715MtgMin-final.docx (Continued) • • • Items number. The cost estimates shown on the RM slide presentation for Marine Foundation Contract are different from the official 12/2014 quarterly report numbers. The Chair inquired if the numbers in the quarterly report was based on implosion or conventional method. R. Foley responded that the number reflected a hybrid of the two methods. Currently, Caltrans has updated the numbers with new engineer’s estimate for both the conventional and implosion method. The Chair and W. Kempton concurred with the request to have complete information on budget spent and forecast for the COS and the risk management update presentations. Information should be provided in quarterly report format. D. McElhinney stated that next month Caltrans will come back with full data of expenditures to date and forecast for the entire program with the updated risk management estimates. The Chair noted that they are not use to seeing the numbers changing so drastically. He requested a line item comparison with explanation on why the numbers are different from the current estimate shown in the quarterly report. Action • Caltrans to present a line item comparison with explanation on why numbers are different from the current estimate shown in the quarterly report for the Marine Foundation Contract. c. East Span Permits* • S. Galvez, Caltrans District 4 Chief Office of Environmental Analysis, presented a summary of East Span Environmental Permits including their expiration dates. A number of resource agency regulatory permits and authorizations have been issued for the SFOBB Project. These permits were originally issued in 2001, shortly after the approval of the final Environmental Impact Statement for the project. These permits and authorizations have been 4 of 11 TBPOC_041715MtgMin-final.docx (Continued) Items amended on numerous occasions throughout the life of the SFOBB project. • Three permits without expiration daterun through project completion. The remaining permits with expiration dates were reviewed with the TBPOC. • The Chair inquired whether any permits require a demolition certain date? Can someone force us to do the demolition sooner? • S. Galvez noted if we go past the expiration date we will request to extend the expiration date. • M. Dougherty inquired whether the permits related to (marine foundation) demolition are based on traditional mechanisms and changing the construction method (to implosion method) will require a permit amendment. S. Galvez confirmed the change will require an amendment to the permit. 5. Action SAN FRANCISCO-OAKLAND BAY BRIDGE UPDATES a. YBITS 2 Contract Project Update* • S. Whipple provided an update on the latest construction activities and progress on the YBITS 2 contract. • On-going issues include: pile delay, differing site conditions related to demolition of existing structures, resequencing of bike path handrail and beam modifications. CT has approached USCG because they will not be out of their area until end of the year instead of the original plan of Summer 2015. CT has been in negotiations with the USCG. Coastguard work will be completed by the end of 2016. • The current budget allotment for the Demo portion of cantilevers is $65M as part of YBITS 2 contract. • Chair requested construction progress 5 of 11 TBPOC_041715MtgMin-final.docx (Continued) Items photos for next month’s update. Action b. Pier E3 Demolition Contract and Permits Update* • S. Galvez, provided an update on the Pier E3 Demolition Underwater Implosion Plan Permits. • Caltrans has submitted application packages to all state and federal regulatory agencies with jurisdiction over the proposed Pier E3 removal. Permits are expected by July 2015. Permit not-approval for implosion activities will result in additional contract work and schedule delays that will impact the contract cost significantly. • No significant concerns at this time other than Cal Wild longfin smelt. They believe strongly we should provide some mitigation. The question is the magnitude of mitigation and Cal Wild is still working on this. • The strategy is to brief that panel, but not elevate it yet in a conflict resolution matter. Reach out and do a proactive briefing. • S. Galvez hoping to do something in early May, Cal Wild elevating within their chain of command. • M. Dougherty inquired if this is for E3 only and S. Galvez confirmed. • M. Dougherty inquired if the smelt issue was just for E3. • Galvez responded that there is an option to defer discussion after they see how E3 goes. • The Chair inquired if this is the same tri-agency that can override a permit decision. The Chair plans to look into the tri-agency statutes. • The Chair inquired if Caltrans has completed negotiations with Pier E3 CMGC contractor. • Dan McElhinney mentioned that 6 of 11 TBPOC_041715MtgMin-final.docx (Continued) • Items Caltrans is in process of finalizing contract approval and is within the approved allocation budget. Mechanical demo to as early as June 2015 to maintain schedule. E3 implosion is not included in the $160M discussed during risk discussion since they are still in the middle of negotiations. Action c. SAS Contract* c1. Project update** • B. Casey, Resident Engineer SAS contract provided a contract update. Elevator work is complete and is in service. De-humidifier for the tower head is not operational due to blower going out. Still under warranty (2yr) thru Aug 2015. Tower base unit is off because of on-going work in the area. East and West sides and west loop still working fine. Welding data base received April 10, resolving functionality issues so not accepted just yet. • B. Maroney, Toll Bridge Deputy Program Manager, presented an update on the Ultrasonic testing of tower anchor rods, micro-testing of extracted rods Ultrasonic Testing (UT) of Tower Anchor Rod for Length Verification o Pulse-echo UT was used to determine the length of each installed tower anchor rod o Procedure carried out on each anchor rod from March 16 to 18, 2015 o B. Maroney reported that UT specialists went out in field and 421 rods confirmed to be fine. 1 rod has a UT reading showing a length about 6 inches short. o B. Casey presented the summary of the survey data of the rod lengths 7 of 11 TBPOC_041715MtgMin-final.docx (Continued) o o o o o Items and the location of the 6” shorter rod. Construction read through all available construction information (RFI’s, shop drawings and field information) to determine the possible locations of the bottom of the rod in relation to the nut. Further investigation, such as a load test, can confirm if it is carrying load as designed. The results will tell if the rod is engaged in the nut and carrying the load or if for some reason it is not engaged into the nut, it may be held down by concrete grout. If during the load test, the rod comes free, then Caltrans would need to extract the rod to further investigate. A demonstration of the ultrasonic testing (UT) of a sample rod was made by materials engineer and testing specialist, Mike Foerder. If the rod was partially broken, the UT reading would show an indication. Chair commented that the connection was originally designed to be welded, then was changed to some kind of duct tape and plumbers putty. It was once designed to be water tight and now it is designed to be water resistant. Why was that change made? B. Maroney responded that Kiewit thought they had difficulty getting access for welding. Chair asked if it is fair to say that the welded connection is a better water protection strategy. B. Maroney responded, yes. Chair commented that there may have been a tradeoff for constructability. Casey noted that the difference between the welded connection and the duct tape/plumber’s putty is that one is more of a rigid connection and the other one is not. Action 8 of 11 TBPOC_041715MtgMin-final.docx (Continued) Items o The Chair asked if the duct tape/plumber putty connection could have been damaged by water jetting. B. Casey responded, yes it would have torn the plumber’s putty. Water jetting caused a changed condition. Micro-Crack Investigation o B. Maroney presented a summary of the proposed testing program for the micro-crack investigation. Some tests have started from the recent approved $1M budget to start some of the testing. o Maroney reported that the proposed testing plan is roughly $5M order of magnitude. o The Chair asked if it was possible if we can live with fewer of these tests. Chair opened comments to other POC members. o W. Kempton added that perhaps the tests can be spread out over time such that the important tests are performed now to satisfy your concerns. If there were questions, then proceed with other tests. o M. Dougherty mentioned that it is desirable to see a testing plan that satisfies engineers that are involved making the decisions to have a high confidence level of the performance and life of the rod that we expect. Action • B. Maroney to provide an iteration of the proposed testing scope and cost for PMT review and present at next TBPOC meeting for approval. Water in the Tower Base o Chair mentioned of the ABF letter regarding the dewatering operation stating that for three-quarters of the hole locations, water is gone. 80 locations, water is cleared and then reappears. Chair questioned why and where is this occurring? o B. Casey responded that water in the hole is from water jetting, water flowing through nooks and crannies, 9 of 11 TBPOC_041715MtgMin-final.docx (Continued) Items some water absorbed in the denso tape and may still have water filtering down. CT is observing dewatering and water is still filtering down into the holes. It takes time to drain the water out. When ABF is done, there may be moisture but CT plans on addressing through dehumidification. ABF states that they have pumped out 125% of the water out that they had placed in, but we do not agree with that statement. o Chair- any strategy to identify sources of water? Did we track how much water went in? o B. Casey- no way to track how much water went in. No volume controls. o Chair requested to test a sample of the water for its chemistry. c2.East Anchorage PWS Anchor Rod Clearance* • 6. Action • Caltrans construction to test a sample of the water to confirm the water chemistry. Chair noted that the information is included on the website and in the agenda package OTHER BUSINESS a. Report on matters discussed and actions taken at Urgent Meeting • NA b. Report on matters discussed and actions taken during Executive Session • The Chair reported that they discussed the outstanding work on the SAS and YBITS 2 Contract and no action was taken. Next TBPOC Meeting • The next TBPOC regular meeting is on May 11, 2015 location TBD 7. GENERAL PUBLIC COMMENT 10 of 11 TBPOC_041715MtgMin-final.docx (Continued) Items • Public comment #1 - Any way to get official notification of the meetings? Response - Chair noted meeting information are posted on the project website (www.baybridgeinfo.org) • Public comment #2 (phone) – Can the public submit questions to B. Maroney in writing related to the East Anchorage PWS Anchor Rod Clearance. Response - Yes Adjourned: 4:04 PM Action TBPOC REGULAR MEETING MINUTES April 17, 2015, 1:00pm – 4:00pm APPROVED BY: ______________________________________ STEVE HEMINGER, TBPOC Chair Executive Director, Bay Area Toll Authority ______________ Date ______________________________________ ______________ WILL KEMPTON Date Executive Director, California Transportation Commission ______________________________________ MALCOLM DOUGHERTY Director, California Department of Transportation ______________ Date 11 of 11 TBPOC_041715MtgMin-final.docx Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) DATE: FR: Andrew Fremier, Deputy Executive Director, Operations, MTC/BATA RE: Agenda No. - 3a3 May 7, 2015 Item- TBPOC May 4, 2015 Urgent Meeting Minutes Recommendation: Approval Cost: NA Schedule: NA Discussion: The Program Management Team has reviewed and requests TBPOC approval of the May 4, 2015 Urgent Meeting Minutes. 1 of 1 Item 3a3_Memo-04May15-v0.doc TBPOC URGENT MEETING MINUTES May 4, 2015, 2:00pm – 3:00pm Attendees: TBPOC Members: Steve Heminger (Chair), Malcolm Dougherty, Will Kempton PMT Members: Andrew Fremier, Dan McElhinney, Stephen Maller Participants: Bijan Sartipi, Bob Finney, Steven Whipple, Rosalynn Chongchaikit, Karen Wang, Peter Lee Convened: 6:15 PM 1. 2. Items EXECUTIVE SESSION Action a. SFOBB Self-Anchored Suspension (SAS) Closeout Strategy OTHER BUSINESS a. Report on matters discussed and actions taken at Urgent Meeting • NA b. Report on matters discussed and actions taken during Executive Session • The Chair reported on an action taken during the Executive Session. o The TBPOC approved supplemental funding to perform additional water testing at the base of the tower in an amount to not exceed $440,000. • The next TBPOC regular meeting is on May 11, 2015, in Oakland, 1:30pm – 4:30pm. 3. GENERAL PUBLIC COMMENT • No public comment received. Adjourned: 6:16 PM 1 of 2 TBPOC_050415_CCMin-final.docx (Continued) TBPOC URGENT MEETING MINUTES May 4, 2015, 5:00pm – 6:00pm APPROVED BY: ______________________________________ STEVE HEMINGER, TBPOC Chair Executive Director, Bay Area Toll Authority ______________ Date ______________________________________ WILL KEMPTON Executive Director, California Transportation Commission ______________ Date ______________________________________ MALCOLM DOUGHERTY Director, California Department of Transportation ______________ Date 2 of 2 TBPOC_050415_CCMin-final.docx Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) FR: Dan McElhinney, Chief Deputy District Director, Caltrans District 4 Brian Maroney, SFOBB Project Chief Engineer , Caltrans RE: Agenda No. - 4a Item- DATE: May 8, 2015 Budget Forecast and Risk Assessment Update Recommendation: Approval Cost: $2.7 million Schedule: Completing FY 14/15 staffing/consultant support of contracts and anchor rod work Discussion: During the first quarter, the Department requested a thorough risk assessment of the existing east span marine foundations removal demolition related to pier demolition by conventional cofferdam installation, mechanically removing the piers, or by controlled charges underwater implosion of the piers E2-E22. A full risk assessment and updated cost estimate process was initiated to evaluate the time and cost benefits of demolition by implosion for portions of the twenty piers. The previous cost estimates and risk management reviews had updated the Cantilever demolition segment and the 504/288 demolition segment independently of the marine foundations segment for capital funding allocation. The process of updating the marine foundations demolition segment cost and schedule forecast, for either the cofferdam or implosion options, took into account project experience since the original estimates, knowledge of environmental permit restrictions to pile driving in the bay, and recent design information and cost data developed as part of the CMGC E3 Pier Demonstration Contract work with industry. The TBPOC budget history for FY14-15 is summarized below for reference, and a program look-ahead chart handout on total CO and COS forecast through 2018 will be 1 of 4 Item 4a_Memo-BudgetForecast-11May15-final.doc Memorandum provided at the meeting. For this FY 14/15 the COS expenditures data now available through April 2015 totals for construction contracts support is $34.8M. In addition, the COS expenditures data through April 2015 is at least $2.0M for the ongoing unanticipated SAS tower anchor rod initial investigation, which includes TBPOC approved field and lab rod testing, expert peer reviews, staffing, and consultant support. Therefore, the total COS expenditures data through April 2015 is $36.8M. The FY budget approved by the TBPOC to date is $42.84M. Considering the expanded scope of work on tower anchor rod investigation, including load testing all 422 rods and the additional field and lab testing expected, the updated forecast to finish FY14/15 is currently $45.5M. It is recommended to supplement the FY 14/15 COS budget with $2.7M to a TBPOC approved budget level of $45.5M - which includes continued reduction of East Span contracts staff and consultant support, the additional tower seismic anchor rod investigation testing plan, and about $1M contingency based on developing workload needs anticipated in May and June 2015. An updated forecast will be presented weekly at PMT meetings and at the scheduled TBPOC meeting June 23, 2015. Below is a summary of activities documented from past TBPOC meetings and decisions for reference relating to the 2014/15 FY capital outlay support budget: May 4, 2015 (TBPOC Urgent Meeting) During the May 4, 2015 TBPOC urgent meeting, during contract completion strategy discussions the Department presented the possible need for additional tower anchor rod investigation testing, related water level and water quality testing, and impacts to the 2014/15 FY approved budget. The TBPOC approved an additional 2014/15FY COS budget of $440,000 for the TBSRP Program supplementing the approved budget from $42.4M to $42.84M. The Department is to present a full testing plan with scope, updated cost estimates, and timelines to be presented at the next TBPOC meeting for consideration. April 17, 2015 (TBPOC Regular Monthly Meeting) At the April 17, 2015 TBPOC meeting in Sacramento, Caltrans presented the COS update with COS expenditures data through March 2015 of $31.8M for construction contracts and an additional $1.7M expended for the ongoing unanticipated SAS tower anchor rod initial investigation related-work through March for this fiscal year. The total COS expenditures data through March 2015 is $33.5M. The PMT planned to review the FY 14/15 work plan of staffing and consultant contracts to further define options to maintain the current approved budget of $42.4M, and review the additional tower 2 of 4 Item 4a_Memo-BudgetForecast-11May15-final.doc Memorandum anchor rod investigation testing plan proposal cost estimates and cost risks. Caltrans has reduced consultants and state staff, reducing staff assignments and reassigning staff to locations of need and priorities. Challenges ahead that require additional staff support include work with anchor rod investigation, with Coast Guard, YBI ramps and TIDA work. Discussion included upcoming opportunity milestones that influence staffing assignments: completion of SAS contract and SAS tower anchor rod testing, and continued progress of cantilever demolition, and 504/288 contractor-suggested alternate construction methods. The TBPOC noted the biggest influence on change on COS depends on what is decided for the testing program of the tower base rods, which can be an additional $3-5M. Confirmed costs are to be presented at May TBPOC meeting. April 1, 2015 (TBPOC Urgent Meeting) During the April 1, 2015 TBPOC urgent meeting, the Department presented the possible need for additional tower anchor rod investigation testing, related peer reviews, and impacts to the 2014/15 FY approved budget. The TBPOC approved an additional 2014/15FY COS budget of $1M for the TBSRP Program from $41.4M to $42.4M. The Department is to present a full testing plan with scope, updated cost estimates, and timelines to be presented at the next TBPOC meeting for consideration. March 5, 2015 (TBPOC Regular Monthly Meeting) As requested, the Department presented an overall work plan for 2014/15 FY to match the $41.4M approved in January 2015, with updated expenditure data of $26.8M through to January 2015 including new expenditures data and budget impacts of unanticipated workload for the SAS anchor rod investigation. The discussion clarified the new work would need to initially utilize a portion of the current COS contingency to proceed with METS contract anchor rod UT and SEM testing- the Department was still in the process of evaluating the additional cost risks and planned to present updated information at the April TBPOC meeting. The Department was tracking the $41.4M approved budget. January 27, 2015 (TBPOC Regular Monthly Meeting) BATA, representing the PMT, presented the updated proposed COS mitigation plan, recommending a $3M augmentation to the existing approved COS 2014/15 FY budget from $38.4M to $41.4M. The TBPOC approved the updated proposed budget. The TBPOC requested for the PMT to return to the March TBPOC meeting to present a work plan to match the $41.4M with $1M in unallocated contingency. December 1, 2014 (TBPOC Urgent Meeting) 3 of 4 Item 4a_Memo-BudgetForecast-11May15-final.doc Memorandum The Department presented the COS mitigation plan to reduce overall COS 2014/15 FY forecast from $49.8M to $44.8M ($6.4M above the approved COS budget). The chair noted that BATA will present a counter offer to the Department’s COS mitigation plan for 2014/15 FY and for the rest of the program in an effort to result in a better forecasted figure. November 4, 2014 (TBPOC Regular Monthly Meeting) The Department presented the third quarter 2014 COS update that provided information on the 2014/15 FY forecasted amount of $49.8M against the 2014/15 FY approved budget of $38.4M ($11.4M above the approved COS budget). A number of unanticipated additional work was discussed that resulted in the budget variance. The TPBOC requested the Department to present a COS mitigation plan at a TBPOC conference call prior to the December 3rd TBPOC monthly meeting. (Conference call was held on December 1, 2014.) April 11, 2014 (TBPOC Regular Monthly Meeting) During the April 11th 2014 TBPOC Monthly meeting, the TBPOC approved a 2014/15FY COS budget of $38.4M for the TBSRP Program. The TBPOC also approved the Department’s request for an additional increase of $84.4M to the TBSRP COS total budget, resulting from $1221.6M to $1306M. Attachments: (to be provided at the meeting) 1. Capital Outlay and Capital Outlay Support Expenditures and Forecast Charts 2. Budget Forecast and Risk Management Update (1st Quarter 2015) 4 of 4 Item 4a_Memo-BudgetForecast-11May15-final.doc Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) DATE: FR: Peter Lee, Principal, BATA RE: Agenda No. - 4b Progress Reports Item- 2015 First Quarter Project Progress and Financial Update May 7, 2015 Recommendation: APPROVAL Cost: NA Schedule Impacts: NA Discussion: The Program Management Team has reviewed and requests TBPOC approval of the 2015 First Quarter Project Progress and Financial Update Report. Attachment(s): To be provided at the meeting 1 of 1 Item 4b_2015 1stQtrRept_11May15-v0.doc Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) FR: Deanna Vilcheck, SFOBB Area Construction Manager RE: Agenda No. Item- DATE: May 7, 2015 5a1 Yerba Buena Island Transition Span (YBITS) 2 Update Recommendation: Information Cost: NA Schedule: NA Discussion: The Department plans to provide an update on the latest construction activities and progress on the YBITS 2 contract during the May 11h TBPOC meeting. 1 of 1 Item 5a1_Memo-YBITS2Update_11May15.docx Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) DATE: FR: Deanna Vilcheck, Supervising Bridge Engineer, Caltrans Construction Manager RE: Agenda No. - 5a2 May 8, 2015 Item- Consent Calendar – Contract Change Orders (CCOs) Yerba Buena Island Transition Structures (YBITS) No. 2 – CCO No. 97 – 213 Day Contract Time Extension Recommendation: APPROVAL Cost: CCO 97 $2,982,000.00 Pending Approval Associated COS costs (15% of CCO amount) $447,000 Pending Approval Schedule Impacts: 213 Working Day Time Extension Discussion: CCO 97-S0 in the amount of $2,982,000.00 will provide for a contract time extension of 213 working days. The extension will resolve all delay impacts incurred to date along with all known and contemplated future impacts as of April 30, 2015. The direct costs for CCO Nos. 43, 52, 75, 84s0, 93, 94, 95, 100, 101, 102, 308, 309 are covered in each respective CCO; CCO 97-S0 resolves previously deferred time consideration, and pays for the time related overhead (TRO) for these CCOs. These past and future impacts are extrapolated upon below. In addition to the change order costs, COS costs of $447,000 (based on 15% of the $2,982,000 CCO) are also requested. Impacts Incurred To Date: The contract has incurred a 3 ½ month delay due to impacts to the column demolition on the YBI Detour structure and due to pile driving impacts on the cantilever temporary supports. Steel guying beams that were placed in the concrete reinforced columns during their construction to support the steel reinforcing cages on the YBI Detour contract were not identified in the YBITS2 contract plans. The presence of these beams resulted in the contractor having to demolish a significant portion of the 50 meter high columns and bent caps where they stood in lieu of the planned operation to knock the columns over and demolish them at grade. 1 of 2 Item 5a2_YBITSCCO97_memo-11May15-v1.doc Memorandum Delays to the pile driving for the cantilever temporary supports were incurred due to the work being pushed out of the contractually specified environmental work window. This resulted in multiple mobilizations and work stoppages which delayed the construction of the temporary supports. Current & Contemplated Future Impacts: Access restrictions and utility conflicts pertaining to the construction of the East Bound YBI On Ramp along with modifications being made to the bike path structure are anticipated to result in an additional 3 ½ months of delay. Access from the north of the EB On Ramp will be restricted due to congestion concerns with the adjacent CCSF Ramps project and concerns from the U.S. Coast Guard about additional disruptions to accessing their base. The restrictions will result in a resequencing of the construction of the On Ramp structure. Concurrently, modifications to the bike path concerning the railing and polyester concrete on the On Ramp structure and the YBI bike path landing will delay the construction of the bike path structure. Exclusive of weather and future delays, CCO 97 extends the completion of the entire project to June 2, 2017. CCO 97 does not close out contract time for CCO 76, a deferred time CCO for fabrication of new bikepath beams in Korea. CCO 76 is not expected to delay completion of the entire project, but may delay opening of the bikepath. Compensation for this CCO will provide for time related overhead (TRO) costs as bid by the contractor. If appropriate, additional time related costs (i.e. labor escalation) will be addressed under a separate or supplemental CCO. Risk Management: The issues to be addressed were previously covered under several risk headings in the Risk Register, but the pending Change Order Log was revised to carry $3.5M to fund the changes contemplated as of the end of 2015 Q1. As such, this scope of work was removed from the Risk Register. Attachment(s): 1. Draft CCO: 97-S0 (pending) 2. Draft CCO Memo: 97-S0 (pending) 2 of 2 Item 5a2_YBITSCCO97_memo-11May15-v1.doc Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) DATE: FR: Steven Hulsebus, Principal Transportation Engineer , Caltrans Toll Bridge Design RE: Agenda No. - 5a3 Item- May 7, 2015 Yerba Buena Island Transition Span (YBITS) 2 Contract Contract Change Order (CCO) No. 111 – USCG Additional Scope Recommendation: Approval Cost: Not to exceed $170,000 (Capital Outlay Support) Schedule Impacts: Acceleration may be needed to meet USCG request, coordination between Construction and the Contractor ongoing. Discussion: Acceleration may be needed to meet USCG request, coordination between Construction and the Contractor ongoing. Approval is requested to proceed with the preparation of CCOs for the work identified below. This work is being requested by the USCG as a result of recent USCG projects on YBI that are either completed or planned to be in construction before the completion of YBITS2. 1. Updating YBITS2 as-built plans to reflect changes from USCG Electrical Distribution Replacement Project 2. Install new fiber optic line and connections to USCG buildings 3. Replace sanitary sewer laterals to USCG buildings 4. Eliminate planned parking and replace with landscaping 5. Finish all landscaping on USCG property by 12/31/16 The original USCG license, allowing construction on USCG property, expires on June 30, 2015. The USCG extended this license, through an amendment, to December 31, 2016. The USCG is working on a lease to keep the Quarters 9 property vacant for state use for the 1 of 2 Item 5a3_YBITSCCO111_memo-11May15-v1.doc Memorandum remaining construction work on YBI and possible use in conjunction with the landing area of the bicycle/pedestrian path on YBI (at no cost to the state except for state costs to secure and maintain the property). In return, the USCG is requesting the above items of work be completed as part of the YBITS2 contract by June 1, 2016. There are two letters from the USCG (attached) requesting the above work. The current (amended) license allowing construction of YBITS2 on USCG property will terminate on 12/31/16. However, recently the USCG has asked that the above work be completed in June 2016. After completion of the CCOs for the above work, we will return to the TBPOC and seek approval to proceed with construction of these items. At that time, impacts to construction operations will be better understood and those impacts will be included in the approval request. Attachment(s): USCG letters YBI exhibit 2 of 2 Item 5a3_YBITSCCO111_memo-11May15-v1.doc Quarters 9 Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) FR: Steven Whipple, SFOBB Principal Construction Manager, Caltrans/ Stefan Galvez, Chief, Office of Environmental Analysis RE: Agenda No. Item- DATE: May 7, 2015 5b Pier E3 Demolition Contract and Permits Update Recommendation: Information Cost: $18.5 million capital outlay (CO) funds Schedule: Begin construction in June 2015 and implosion in November 2015 (permits pending). Discussion: Pier E3 Demonstration Contract The CMGC Contract Approval for the Old East Span Marine Foundation Demolition Pier E3 Demonstration Contract with Kiewit/Manson, A Joint Venture was signed on April 27, 2015 on schedule. The $18.5 million contract allotment (COS not included) is within the April 1 TBPOC approved budget allocation for the Pier E3 Demonstration contract. Funds will be allocated from the TBPOC approved budget ($246.5 million CO) for Existing East Span Dismantling, which currently has a $74 million CO balance per the 2014 Toll Bridge Seismic Retrofit 4th Quarterly Report (released February 2015), based on the previously awarded Cantilever segment ($69 million CO) and the recently awarded 504/288 segment ($103.5 million CO) budget allocation approvals. A risk assessment and cost estimate update for the remaining Existing East Span Dismantling marine foundations project work was requested for the 2015 1st Quarter Report and risk management plan. The Contractor is expected to start work in the field on June 2015 and permits for the implosion are expected on August 2015. 1 of 2 Item 5b_Memo-E3_11May15-final.doc Memorandum Pier E3 Demolition Underwater Implosion Plan Permit Update - Issues: Department staff continues to work closely with its partner agencies to ensure expeditious issuance of permits and authorizations for the proposed Pier E3 Demonstration project. During the months of April and May Department staff met and conferred with NOAA Fisheries, NOAA office of Protected Resources (Marine Mammals), BCDC, CDFW, USCG, and RWQCB and received valuable input on Pier E3’s permit packages. In addition, the Department has had discussions with various stakeholders, including the Marine Mammal Center, Audubon Society, Sierra Club and Bay Keeper. The Department continues to address issues of interests by agencies and stakeholders listed above. Elevating Issues: The Department is in active communication with State Transportation Agency staff to set a date for a briefing the Secretary of Transportation and Secretary of Resources in either May or June 2015. The goals of the meeting will be outlining a path for ensuring timely issuance of a take permit for the Demonstration project by August 2015, and a mechanism for obtaining such take. Any delays in decisions and permit from CDFW may impact the Pier E3 contract schedule for underwater demolition by implosion in November 2015, possibly delaying work up to a year. - Permit updates: Caltrans staff has submitted application packages to all state and federal regulatory agencies with jurisdiction over the proposed Pier E3 removal. Agencies include: - National Oceanic and Atmospheric Administration/National Marine Fisheries Service - U.S. Army Corps of Engineers - U.S. Fish and Wildlife Service - U.S. Coast Guard - California Department of Fish and Wildlife - San Francisco Bay Conservation and Development Commission - Regional Water Quality Control Board Permits are expected by July/August 2015. Permit non-approval for implosion activities will result in additional contract work and schedule delays that will impact the contract cost significantly. 2 of 2 Item 5b_Memo-E3_11May15-final.doc Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) DATE: FR: Steven Whipple, SFOBB Principal Construction Manager, Caltrans RE: Agenda No. - 5c Item- 504/288 Superstructure Dismantling Contract Update May 7, 2015 Recommendation: INFORMATION Cost: NA Schedule Impacts: NA Discussion: The Department has recently awarded the 504/288 Superstructure Dismantling Contract No. 04-013524 to California Engineering Contractors, Inc. and Silverado Contractors, Inc., JV. The Department will present a brief update. 1 of 1 Item 5c_504-288_2015-0511-final.doc Memorandum DATE: TO: Toll Bridge Program Oversight Committee (TBPOC) FR: Steven Whipple, SFOBB Principal Construction Manager, Caltrans RE: Agenda No. - 5d1 May 7, 2015 Item- Self-Anchored Suspension Span (SAS) Construction Update Recommendation: For Information Only Cost: Potential cost impacts to be determined. Schedule Impacts: Potential schedule impacts to be determined. Discussion: The Department will present an update on the SFOBB East Span SAS contract remaining work by contractor American Bridge/Fluor Enterprises, Inc., A Joint Venture, including the tower seismic anchor rod grout work, related field and lab testing activities, and final project database and documents. Attachments: None 1 of 1 Item 5d1_Memo-SASUpdate-11May15-final.doc Memorandum TO: Toll Bridge Program Oversight Committee (TBPOC) DATE: FR: Brian Maroney, SFOBB Project Chief Engineer, Caltrans RE: Agenda No. – 5d2 May 8, 2015 Item – SAS Tower Base Seismic Anchor Rod Testing Plan Recommendation: Approval Costs: Supplemental funding requested is in the range of $2-3 million depending on tests approved. Schedule: Field and lab testing is ongoing and will continue through June 2015, with additional lab work, peer reviews, and final report development continuing through Fall 2015. Discussion: As requested during the April 17, 2015 Toll Bridge Program Oversight Committee (TBPOC) meeting presentation, the Department plans to present the updated SAS tower base seismic anchor rod testing program proposal at the May 11th TBPOC meeting. Tests that have been ongoing as approved or tests that are planned include the chemistry of water from water jetting operations and rod mechanical testing, chemical analysis, microscopic examination, measurements, and stress corrosion testing on samples of two rods previously removed (rod 1 in 2013 and rod 2 in 2014). Also, an update will be presented about field load testing by hydraulic jacks currently ongoing in partnership with prime contractor ABFJV to load test in place all 422 tower seismic anchor rods including the single short rod (155-1-1). A proposed scope, estimated costs, and the planned schedule of supplemental testing will be recommended for discussion and approvals to proceed. 1 of 1 Item 5d2_Memo-SAS_TowerAnch_11May15-final.docx ITEM 6: OTHER BUSINESS a. Report on matters discussed and actions taken at Urgent Meeting b. Report on matters discussed and actions taken during Executive Session ITEM 7: GENERAL PUBLIC COMMENT
© Copyright 2024