solar power CENTER FOR STUDY OF SCIENCE TECHNOLOGY AND POLICY (CSTEP) LARGE GRID-CONNECTED SOLAR PLANTS SAPTAK GHOSH AND NAGALAKSHMI PUTTASWAM ROOFTOP PV SYSTEMS NAGALAKSHMI PUTTASWAMY, POOJA VIJAY RAMAMURTHI AND SAPTAK GHOSH OFF-GRID AND DECENTRALISED PV VAISHALEE DASH, POOJA VIJAY RAMAMURTHI, SAPTAK GHOSH Making 100 GW Solar Target a Reality In the recent budget speech, the government announced that out of a national renewable energy target of 175 GW by 2022, solar will contribute 100 GW. This means that the target for the Jawaharlal Nehru National Solar Mission (JNNSM) will increase by almost five times. At a state level, this target translates to 10.5% of solar Renewable Purchase Obligation (RPO). Although these targets are extremely ambitious, with proper administration and supporting policy frameworks, they are achievable. The authors have attempted to address the key issues in achieving these ambitious targets through a series of articles including an overview of the challenges and possible measures to overcome them. Large grid-connected Solar Plants Currently, large solar PV plants comprise more than 90% of the installed capacity and developers have received consistent support from the Ministry of New and Renewable Energy (MNRE) in terms of the bundling mechanism and Viability Gap Funding under JNNSM. To enable developers further, MNRE has identified 12 states for setting up solar parks with a total capacity of 20 GW between 2014-15 and 2018-19. Details of these locations and associated planned capacity are shown in Table 1 below. The total proposed outlay in the form of Central Financial Assistance (CFA) for setting up the infrastructure for the solar parks is Rs. 4050 crore. In spite of these advantages for large developers, reaching the revised target in 7 years remains an uphill task. The following sections elaborate upon the various challenges and how they can be addressed. Table 1: Proposed Locations and Capacities of Solar Parks in Indian States. 4 Technical Challenges Solar energy, being intermittent in nature, leads to grid instability. Scaling up the installed capacity to the revised target will magnify the concerns of grid operators and load dispatch centres in regulating the frequency and voltage fluctuations. Each region/state will need Renewable Energy Load Dispatch Centres to predict the fluctuations from both solar and wind. They will work closely with grid operators, developers and state load dispatch centres to develop accurate load balancing algorithms using appropriate storage mechanisms such as pumped storage hydropower systems or large battery systems (which are capital intensive), or other systems with fast ramp up capabilities such as gas plants. A major challenge of large solar parks is the associated evacuation infrastructure requirement. Heavy investments are required to upgrade the national grid and construct new sub-stations, transformers and transmission lines. International financial institutions such as the Asian Development Bank (ADB) are already lending to the Indian Government for this cause. The energética india · MAR|APR15 solar power issue here is that newly constructed transmission lines will remain idle after sunset. To increase the utility of the evacuation infrastructure, large storage systems need to be in place to supply 24/7 power. Concentrated Solar Power (CSP) with molten salt storage systems is an option, albeit an expensive one. The other choices are to have biogas plants with local biomass resources or dedicated biomass plantations within the solar park vicinity or hybrid plants with wind turbines. Optimisation algorithms will be needed to determine the capacity of the solar park considering biomass or wind resource availability and techno-economics of other storage systems. Resource Availability Large-scale solar installations in the revised target will impose strains on resources in terms of water and land availability. In arid and semi-arid states, water availability is a growing concern. Solar parks in these states will directly compete with societal demands. To reduce this impact, established linkages of water with power plants need to be constructed, which do not infringe on the needs of society. PV plants energetica india · MAR|APR15 – which require lesser amounts of water as compared to CSP plants–with more efficient cleaning or recycling mechanisms need to be explored to conserve water. Solar plants have large land footprints and this constraint is likely to play an important role in India since it is very difficult to find large uninhabited contiguous parcels of land. For solar parks, rehabilitation and relocation measures must be undertaken after grassroots level stakeholder interactions to compensate for displacement. Human resources are vital for the success of solar parks. Although solar parks guarantee job creation, local participation remains a concern. The government’s plan to train 50,000 people in areas related to solar power need to include local capacity building strategies to ensure growth in local income. Financial Challenges Although the cost of solar PV has witnessed a decreasing trend in the past few years with Levelized Cost of Electricity (LCOE) reaching as low as Rs. 5.25/unit and the capital cost hovering around Rs. 7 crore/MW, approximately Rs. 2,80,000 crore will be required to achieve the large grid-connected solar plants target. In the past, the biggest financial challenge faced by developers has been access to low cost finance. While developers using imported modules and cheaper EXIM bank loans (10% interest rate with hedging for 18 years) have thrived, developers using indigenously manufactured modules have had to avail costlier loans (at 13% interest rate with a shorter tenure of 10 years). This has led to a reduced growth in the Indian manufacturing sector. To drive down the cost of debt, innovative financial instruments must be introduced in the market. One option is to introduce Green Bonds (issued by World Bank across the globe to finance Renewable Energy projects). The Solar Energy Corporation of India (SECI) can issue bonds at 8% interest rate to the public with a maturity period of 18 years. The corpus collected can be made available to developers at around 9.5-10% for the same time period. This will lead to higher returns for developers using domestic modules. Another option is to create a corpus using foreign funds with a lower hedge 5 solar power rate. Historically, India has procured considerable amounts of foreign debt to build infrastructure at low interest rates and the credit rating of the country has been good. Hence, developed countries continue to lend finance for Indian infrastructure projects. This works in the favour of a low hedging rate if a credible national institution like the Reserve Bank of India secures the debt. Since developed countries expect around 3-5% interest on their investments, India can take advantage of this by investing in the solar sector. On the other side, distribution utilities that are the purchasers of solar power across the country have ailing finances. It is a heavy burden on them to enter into 25 year Power Purchase Agreements (PPA) at Rs. 5.25/unit because they will need to pay for 66 billion units generated from large solar plants per year. One way to keep both the developers and the utilities happy is to have a rational tariff setting mechanism. Since the price of coal-based electricity is increasing, the solar PPA can be dynamic and start at an average pool purchase cost for the utility and increase annually at the same rate of coal before being capped once grid parity is achieved. Research has shown that this mechanism leads to better returns on investment for the developer than a fixed PPA at Rs. 5.25/ unit. The rising costs of electricity will ultimately get passed on to the end user, so the utility is also protected in this scheme. If all of these challenges are dealt in a structured manner by the government with appropriate policy frameworks within which RPOs are enforced along with timely integrated resource planning and single window clearances for land procurement, there is no reason why India cannot achieve the target for large-scale solar plants by 2021-22. Rooftop PV Systems The second part focuses on the Rooftop PV (RTPV) sector in the country. Till date, large solar plants have dominated the Indian solar landscape, with more than 90% of the 3.3 GW installed capacity. However, decentralised solar generation provides benefits such as low land footprint and reduced Transmissions and Distribution (T&D) losses. The new government appears to have realised these benefits and 6 Till date, large solar plants have dominated the Indian solar landscape, with more than 90% of the 3.3 GW installed capacity. However, decentralised solar generation provides benefits such as low land footprint and reduced Transmissions and Distribution (T&D) losses has allotted 40% of the100 GW target (by 2021-22) to RTPV systems. CSTEP’s research shows that the RTPV potential in India ranges between 40-92 GW, and hence the national target seems to be technically feasible. RTPV systems (~60 MW installed till date) typify decentralised power generation and thus pose a unique set of challenges for policy makers and distribution utilities. These systems are end-user oriented and have more transactional and institutional layers as compared to large solar plants. The major obstacles include lack of economies of scale, weak local distribution infrastructure and poor social outlook. Major institutional reforms, social awareness programmes, technology up-gradation and innovative policy mechanisms need to be implemented to reach the ambitious targets in the next seven years. A “systems engineering” approach needs to be adopted which takes social, economic and technical aspects into consideration while designing a successful RTPV policy framework. Technical Challenges Intermittency in radiation profiles leads to fluctuations in energy generation from PV panels, which have implications on the power quality and stability of the low tension distribution grid. States like Delhi, Tamil Nadu and Punjab have recommended that the threshold limit for penetration of PV distributed power be 15-30% of the distribution transformer’s rated capacity. It becomes a challenge to manage fluctuations at higher penetration levels of distributed solar power. Therefore with 40 GW of installed RTPV systems, at a decentralised level, where load balancing algorithms are weak, intermittency could have severe implications on grid stability in the form of voltage fluctuations. In simpler terms, assume that there are 70 houses with grid interactive RTPV systems on a street with one distribution transformer. During the daytime, when these RTPV systems are generating electricity, a large passing cloud will cause an instant drop in the generation which will need to be compensated by the local transformer. Owing to the voltage and frequency mismatch, the transformer might fail leading to power outages and maintenance issues. Financial Challenges One of the major reasons behind RTPV’s slow uptake in India is high initial investment costs. The price of RTPV systems hovers between Rs. 70,000-1 lac/kWp depending on the inclusion of battery storage and tracking systems [Most RTPV systems are constrained by available rooftop area. Hence, to maximise yield, tracking systems are used to follow the trajectory of the sun. Although this leads to higher initial investment, the IRR increases by a higher margin, thereby making a stronger business case for the consumer]. The capital subsidy offered by the Ministry of New and Renewable Energy (MNRE) has recently been reduced from 30% to 15%. A typical urban RTPV system with a capacity of 4 kWp with a net-metering scheme [In this scheme, electricity consumption and total generation from the RTPV system are measured on a monthly basis. If consumption is more than generation, the consumer pays the difference to the utility and vice-versa. In the case of Bengaluru, the net-metering rate is Rs. 9.56/unit without MNRE subsidy and Rs. 7.2/unit with the subsidy]. (availing a commercial bank loan; Interest rate = 13% and loan tenure = 10 years) yields an Internal Rate of Return (IRR) and payback period of 12%and 8 years respectively. The German RTPV model was immensely successful with the Feed-in-Tariff (FiT) mechanism which yielded IRRs of 5% energetica india · MAR|APR15 solar power (the discount rate was around 1.5% in the last two decades) with payback periods of more than 10 years. However in the Indian context, these numbers are not economically viable to the quintessential middle class family, which comprises a major portion of urban demography. Normally, in Indian society, expected returns on any investment are more than 13%. To encourage domestic RTPV uptake, some commercial banks are now providing loans for RTPV systems clubbed with home loans at lower interest rates. Industrial and commercial consumers depend heavily on diesel-based electricity which costs around Rs. 11/unit. Using RTPV systems, they can reduce this dependency and obtain cheaper power between Rs. 6-7/unit (without capital subsidy). To make a more robust business case with IRRs above 15%, they need to gain additional revenue by selling their accrued Renewable Energy Certificates (RECs) in the market. However, at the moment, the Renewable Purchase Obligations (RPOs) are not stringently enforced, thereby making REC sales a major challenge. Additionally, the financial implications of 40 GW of RTPV systems on the country’s distribution utilities will be quite severe. The already cash-strapped utilities will lose revenue as customers increasingly meet their electricity needs through RTPV systems. Utilities will have to procure excess electricity generated by RTPV systems, through the net-metering mechanism or FiT mechanism, at rates which are considerably higher than their Average Pool Purchase Price (APPC). Utilities will also have to invest in grid balancing and network up-gradation to ensure effective last-mile connectivity. Holistic System Design A generic policy and regulatory framework needs to be developed to enhance the rate of RTPV uptake in India. This framework can be implemented across the country with tweaks, which take local aspects into account. To begin with, stakeholder interactions need to be held between the renewable energy development agency, electricity regulatory commission and distribution utilities in each state. Once the financial health of utilities has been assessed, a roadmap needs to be charted energetica india · MAR|APR15 out which sets annual capacity addition targets and provides guidelines for utilities to upgrade their existing infrastructure. Appropriate net-metering and FiT rates should be implemented after calculating revenue losses of utilities and compensating for the Cross Subsidy Charges (CSS) of industrial and commercial consumers. To be able to exploit the rooftops of those who cannot afford the initial investment, an innovative scheme involving the use of an “aggregator” can be devised. The aggregator system is an institutional innovation that improves the efficiency of interaction between government schemes and numerous individual households. An aggregator can consist of a solar developer and a retail company with a proven track record of customer interaction. The aggregator will be responsible for setting up RTPV systems on customer’s roof tops as well as Operation and Maintenance (O&M). The customer will not own the RTPV system (thereby saving the initial investment), but will only pay the aggregator for the electricity generated at a rate lower than the utility tariff. Based on the customer’s credit rating, the aggregator will also charge a down payment which will adjust itself with future electricity sales. The aggregator can gain additional revenue by selling RECs (once RPOs are enforced) gained from their RTPV portfolio, and availing tax holidays for the first 10 years. Therefore, instead of direct interaction with customers, the government can take on an administrative role of enforcing RPOs (which are essential for this scheme to succeed) and performing energy audits. Urban areas can be divided into zones, which can be allotted up to two aggregators to ensure that there is an initial level of competition. After a few years, these zones can be opened to all aggregators to create a free market with perfect competition. In conclusion, in order for India to achieve its ambitious 40 GW RTPV targets by 2021-22, it is imperative to examine innovative schemes and policies such as the ones discussed in this article. Off-grid and Decentralised PV This part of the article examines the offgrid sector. Currently, there are more than 300 million Indians without access to electricity and a significant population, which gets less than six hours of power supply per day. A primary reason for poor electrification in India has been the slow expansion of central grid systems. Till date, the solar energy landscape has been dominated by large-scale plants, which make up more that 90% of the 3.3 GW installed capacity. However, remote locations and low incomes of rural population make the extension of centralised grids uneconomical. Small-scale solutions can be effective in such situations, which is the key driver behind the government’s plans to strongly promote this technology as part of its 100 GW solar target (by 2022). 7 solar power Popularly used decentralised solar systems include Solar Home Lighting Systems (SHS), Solar Lanterns (SL), micro-grids and pumps. Capital costs of off-grid solar micro-grids with storage systems are about Rs. 2 lakh/ kWp and the Levelized Cost of Electricity (LCOE) is Rs. 19-24/kWh. This is high as compared to Rs. 6-9/kWh for large gridconnected plants and RTPV systems; however it can be low compared to the cost of extending the grid to remote areas, which Agarwal et al. (2014) claim becomes prohibitively high at Rs. 26-228/kWh if the village is 5-25 km away from the grid. Despite several attractive schemes being introduced by central and state governments, off-grid systems aren’t as popular as grid-connected projects. They face major obstacles which include high capital costs, complicated disbursal procedures of central subsidies, minimal guarantee of returns on investment and difficulty in local Operation and Maintenance (O&M). In addition, varying location, needs and preferences of consumers render a ‘one size fits all’ approach infeasible. Hence these systems face higher costs and increased challenges. Ramping up the existing installed off-grid capacity will require meticulous planning and innovation. Policy Gaps In the past decade, multiple decentralised electrification schemes from various ministries have led to unclear directives and mixed results in the sector. Complicated processes have led to capital subsidies being doled out after long periods of time, even up to 2-3 years. Bringing these schemes under one authority and streamlining the associated processes would provide more transparency and efficiency in the overall processes. Previously, subsidies on diesel and kerosene made investing in relatively more expensive solar systems unattractive. However, with diesel prices already deregulated and kerosene subsidies most likely to be scrapped, global declining solar prices could make solar solutions increasingly economical. A recently proposed scheme includes giving rural households the option to choose between cash subsidies for kerosene or upfront capital subsidies for SHS. Once in effect, the scheme will be a game changer for the off-grid solar sector. 8 Financial Challenges Established developers prefer to invest in large-scale and RTPV systems because they are able to raise finance, are assured of payment (utilities or open-access consumers) and O&M is required at a single point. Raising finance for off-grid however is a challenge with a dearth of interest debt schemes. Benchmark prices set out for availing subsidies offered in central schemes are often considerably lower than the actual costs for project implementation; this leads to tenders being met with disinterest. In order to achieve the proposed targets, innovative schemes need to be devised to drive down the cost of debt and increase returns on investments. Public-private partnerships with rural entrepreneurs as well as community and Electricity Supply Company (ESCOM)/government entity owned projects can be encouraged. Based on the model followed, appropriate soft loans can be availed. To encourage private developers, incentives such as long tax holidays and partial risk guarantee mechanisms (from the state government) can be provided. Further, since the Internal Rate of Return (IRR) in such projects is typically low, large multinational companies can dedicate Corporate Social Responsibility (CSR) investments to off-grid solar projects. Often, under capital subsidy based models, once the system is installed, they fall into disuse due to lack of long-term financial incentives. In some extreme cases, panels have been stolen and meters have been vandalised. Hence, apart from interest rate subsidies, revenue models such as Generation- based Incentives (GBI) using prepaid meters should be implemented. The lack of a roadmap for rural electrification implies that there is no certainty on when a village could be electrified. Therefore, villagers might be unwilling to pay developers for expensive electricity, in the hope that the grid will reach them. The same uncertainty makes developers reluctant to set up a system. The government should mandate micro-grid based systems to be grid-interactive (with bi-directional meters) and create a risk mitigation plan, where developers can be compensated if the grid is extended to their area of operation. Technical Challenges While SHS and SL systems are simple to implement, they can only satisfy lighting needs. In order to encourage income generation activities, micro-grids are invariably more suitable; however they are more complicated in terms of technology. This is because micro-grids need to counter intermittency using load balancing algorithms (typically using battery storage). Not only does this add to the cost, but it also leads to more maintenance issues. Innovative storage mechanisms (such as flow battery instead of lead-acid and lithium ion technologies) and hybridising solar plants with either wind, pumped hydro or biomass can make load balancing more robust. As skilled human resource is scarcely available in these areas, O&M poses a huge concern. Local participation and capacity building measures undertaken by state authorities, Non-Governmental Organisations (NGOs) and developers should be encouraged. In addition, solar off-grid training programmes should be conducted in industrial training institutes and similar local bodies, which include ‘training of trainers’. The present lack of regulations and guidelines for micro-grid systems makes verification of designs and performance parameters uncommon. In order to ensure sustainable rural electrification, the government should establish guidelines and enforce strict quality standards for these systems. Effective planning of small-scale projects requires conducting site-specific pre-feasibility analysis and assessments of local households and agricultural demands. This can be a cumbersome process, leading to added expenditure, but it helps in checking long term costs associated with maintenance. Further, this analysis can be done by involving local NGOs and the village community. This increased participation and engagement will ensure that the villagers feel a sense of ownership and keep the system functioning effectively. If these challenges are addressed in a structured and phased manner, then significantly increasing our off-grid solar power is achievable. However, attaining success in this sector will be an arduous task compared to grid-connected systems 7 The views expressed in this article are those of CSTEP. energetica india · MAR|APR15
© Copyright 2024