How to activate resources and human potential of our region village.

How to activate resources and human
potential of our region
or
The village´s money shall remain to the
village.
Using the example of
Friedrich-Wilhelm Raiffeisen Energie eG
Is the province of little value?
Shareholder of the Agrokraft GmbH
Rhön-Grabfeld e.V.
50 %
50 %
Assignment:
Projecting (development), initiation/instigation,
implementation, optimalization of independent
companies in the range of renewable energies
photovoltaik
energy-supply
Bürgersolarkraftwerke
Großbardorf GmbH & Co KG
Bürgersolarkraftwerke
Rhön-Grabfeld GmbH & Co KG
Biomasse-Wärmeversorgung Bad
Königshofen
GmbH & Co KG
Biomethan Rhön-Grabfeld
GmbH & Co KG
FWR Energie eG
biogas
+
hydrothermal
carbonation
other
projects
eco-bees-project
administrative software FWR
The villages
money shall
remain to the
village!
Save your
money at your
savings
and loan
association.
Anual acquisition of financial assets within
the area of Rhön-Grabfeld
(approximately 84.000 inhabitants)
125,000,000 €
at an anual income of households of
1,047,000,000 €
private financial assets within the area of
Rhön-Grabfeld in the year 2009
4,410,900,000 €
total investment
between 2005 and 2010
approximately 50 million €
„All for each and each for all.“
„Something that might not be achievable by one
individual can be done by the community.“
Friedrich Wilhelm Raiffeisen
(1818-1888)
Principles:
• involvement of as many people as
possible
• using the principles of the onionskin/the
church steeple
foundation meeting at 25th of June 2008
project 001: building yard Bad Neustadt
project 003: citizens photovoltaik power plant in Ostheim
project 005: Mathias Klöffel
project 006: Christuskirche Bad Neustadt
PROJECT
Performance
Total Investment
Participants
Activation
001 Bauhof Bad Neustadt
271,00 kWp
1.088.000 €
39
Dez 08
002 DJK Weisbach
20,43 kWp
87.000 €
10
Apr 09
003 BSA Ostheim
144,63 kWp
570.000 €
30
Jun 09
004 BSA Sondheim
210,96 kWp
811.000 €
27
Aug 09
005 M. Klöffel
111,00 kWp
384.000 €
13
Jun 09
006 Christuskirche
8,10 kWp
28.000 €
6
Aug 09
007 DJK Sondernau
11,76 kWp
42.000 €
20
Aug 09
008 Realschule NES
81,30 kWp
275.000 €
15
Okt 09
009 BSA Hohenroth
117,88 kWp
376.000 €
27
Jun 10
010 BSA Hildburghausen II
259,30 kWp
682.000 €
16
im Bau
011 BSA Hildburghausen
259,40 kWp
830.000 €
30
Dez 09 / Apr 10
012 E. Edelmann
12,96 kWp
44.000 €
1
Nov 09
013 BSA Möhrendorf
75,90 kWp
190.000 €
noch in Entwicklung
noch in Entwicklung
014 VfR Bibergau
26,22 kWp
71.000 €
11
Aug 10
015 BSA Trappstadt
115,18 kWp
328.000 €
20
Dez 10
016 MW Heustreu
99,9 kWp
243.000 €
5
im Bau
TOTAL:
1726,02 kWp
6.049.000 €
some of them take share in more than
one project
216 members,
project „roofing of the stands“ in Großbardorf
Aim of the development of the
Friedrich Wilhelm Raiffeisen Energie eG
create a new structure which includes
• technology
• size of the solar power plants
• rentability
of different projects in the range of renewable energies with
lots of members/shareholders.
Structure of organisation of a
Friedrich-Wilhelm Raiffeisen
Energie eG
•
•
•
executive board:
2
supervisory board:
3/5
as much members/participators/shareholders of the
population as possible
Energy-savings / bank book
(project 001 Bauhof Bad Neustadt/S.)
The Village Association
Associations create the foundation for all
projects in the range of renewable energies
in the village (many projects are possible
under one umbrella)!
Project 001: PV on the schools roof
Project 002: PV on the roof of the clubhouse
Project 003: District heating network
Project 004: Windfarm
Project 005: …
Sheme of Investment
2000 EUR
Investment
1900 EUR
Subordinated Loan
100 EUR
Cooperative Shares
Administration
own software – based on the internet
• member‘s administration
• hour journal
• cost finding
• administration of interests
• administration of projects
• administration of documents
• mail merge function
Administration
Administration
foundation meeting at 4th of November 2009
Projects of the FWR Energie eG Großbardorf:
project 001: a solar power plant as a roofing of the stands
Projects of the FWR Energie eG Großbardorf:
project 002: solar power plant on the roof of the building yard
Projects of the FWR Energie eG Großbardorf:
project 003: heat grid
Projects of the FWR Energie eG Großbardorf:
Start of the building of the biogas power plant
Vision:
To any village, to any city, to any area/region
their own Friedrich-Wilhelm Raiffeisen eG.
„Village Life“ eG
www.agrokraft.de
www.raiffeisen-energie-eg.de