ECI: WHAT IS IT, WHY USE IT CONSTRUCTION

December 2012
CONSTRUCTION
ECI: WHAT IS IT, WHY USE IT
AND WHERE IS IT GOING?
Increasingly, the market is embracing alternative contracting models to
deliver complex and large projects. One such model is ECI - Early Contractor
Involvement.
BUT WHAT IS ECI?
The “traditional” construction contract model involves the
Principal engaging a designer to design the works and an
engineer to oversee the project. The Principal subsequently
engages the contractor to build the works and the Contractor
enters into subcontracts with sub trades. The problem with this
“traditional” contracting is that it leads to adversarial behaviours
given the conflicting objectives of the parties.
stage. The rationale being that it is during this early stage of
project planning that the greatest influence on capital costs and
project outcomes is possible.
It is essentially a form of collaborative contracting. Like
alliancing, ECI envisages the early involvement of the Contractor
and the adoption of “best for project” attitudes by all parties.
HOW DOES ECI WORK?
ECI attempts to optimise risk management, risk allocation, price
and control for the Principal.
Similar to a project alliance, ECI contractors are selected usually
through a non-price selection process where significant
emphasis is placed on the capability of the proposed team
(although depending on the ECI model selected, margins and
selected rates may also be requested). The tender process is
frequently interactive allowing the Principal to get a feel for the
contracting behaviours of the tenderers. The contract when
awarded can be a standalone “preconstruction” agreement or
one contract with two distinct stages. While collaborative
behaviours are motivated and encouraged throughout, Stage 1
is where good collaboration and communication can reap the
greatest benefits.
ECI is effectively a first cousin to the Design Build contract
model. It seeks to exploit a Contractor’s specialist knowledge of
construction processes to the benefit of the design process. The
key difference between Design Build and ECI is that ECI, as its
name suggests, seeks to obtain this benefit at a much earlier
In Stage 1 of an ECI contract model, the Contractor proceeds
with design development up to outline design phase or even
preliminary design. This development is usually undertaken on
a cost reimbursement basis which can encourage the
exploration and assessment of innovative design alternatives.
Under a “traditional” model the Principal can seek to minimise
its risk exposure by adopting variants such as Design Build or
Turnkey contracts, however the trade-off is that it can lose
control over the project. Also, such contract models can result in
a reliance on risk allocation rather than risk identification and
mitigation (ie risk management). In such circumstances, the
lack of pre-contract risk management can be exacerbated by
inappropriate apportionment of risk or inappropriate pricing of
risk.
www.simpsongrierson.com
01
It is during this phase that value engineering and issues with
constructability can be addressed and risks properly identified,
mitigated and apportioned.
Stage 1 concludes with the submission of detailed design and
pricing for Stage 2 from the Contractor. ECI contracts tend to
have differing degrees of discretion for the Principal with regard
to the transition from Stage 1 and Stage 2. Price tension is better
maintained by making the transition discretionary.
Stage 2 in ECI contracts tends to be a fairly traditional Design
Build contract. This is the key difference from alliancing. Stage 2
in an ECI contract is usually lump sum. In most cases, the
traditional design build model works well as a base document in
Stage 2 because the scope of work will have been well defined
as a result of the efforts undertaken in Stage 1. The most
significant construction issues should have been identified,
resolved or mitigated. Key ‘extras’ which should also be included
are the continuation of the flavours of collaboration and
cooperation engendered at Stage 1 and incentivisation of the
Contractor by way of potential risk sharing/performance reward.
WHY USE IT?
ECI includes the Contractor at the stage where most value can
be extracted. It reduces the cost of tendering as only one design
process is undertaken, therefore avoiding inherent duplication
of effort. It enables risk to be identified, mitigated and/or
properly allocated (and priced). Importantly, relational and
collaborative behaviours are motivated for the benefit of the
project. From the Principal’s perspective, it retains control
through collaborative working with the Contractor and its
consultants at Stage 1. Control by the Principal is further
maintained by ensuring that ultimate discretion to proceed to
Stage 2 is retained.
Contractors like the ECI approach because at the early stages
they can often provide genuine value and it allows them to have
early “buy in” to the project. The collaboration in Stage 1 creates
a feeling of ownership which encourages greater commitment
to performance and quality. Also, incentives included at Stage 2
can be attractive motivators. The risk management benefits of
course apply equally to the Contractor as to the Principal.
Some detractors consider ECI takes the edge off competitive
pricing. However, proper management and transparency should
ensure that pricing is competitive with no hidden gains. Such
risks can also be mitigated firstly, by ensuring that there is
sufficient time allowed for value engineering in Stage 1 and
secondly, by providing that the transition to Stage 2 is conditional
upon satisfactory pricing having been negotiated. An
independent audit and/or ‘sign off’ of the pricing can also be
incorporated into the procurement process.
WHERE IS IT GOING?
ECI contracts in their current form had their genesis in the boom
markets of the last decade but despite the cooler current
market, interest in ECI remains constant. There is growing
interest in ECI given its collaborative nature combined with
benefits of greater certainty and control over design outcomes,
and greater price certainty than other collaborative models.
ECI is being increasingly adopted on major projects in New
Zealand. NZTA have adopted ECI on at least five major projects
including the Papakura Interchange Upgrade and in the Rangiriri
Section of the Waikato Expressway and have produced an ECI
template (see http://nzta.govt.nz/resources/state-highwayconstruction-contract-proforma-manual/docs/sm031-h1.pdf).
Our expectation is that ECIs will also be a useful tool in the
rebuilding of Christchurch where it is increasingly apparent that
parties will need to be creative with the use of resources, time
and funding.
CONTACT DETAILS
MICHAEL WEATHERALL - PARTNER
T. 09 977 5097 M. 029 977 5097 E. [email protected]
GRAEME CHRISTIE - PARTNER
T. 09 977 5074 M. 021 960 493 E. [email protected]
SONIA VITAS – SENIOR ASSOCIATE
T. 09 977 5317 M. 021 221 6304 E. [email protected]
LISA CURRAN - SENIOR ASSOCIATE
T. 09 977 5143 M. 021 498 641 E. [email protected]
CHARLOTTE FOX - SENIOR ASSOCIATE
T. 03 365 0971 M. 021 242 1602 E. [email protected]
SHANTI DAVIES - ASSOCIATE
T. 09 977 5273 M. 021 242 6821 E. [email protected]
A SIMPSON GRIERSON PUBLICATION
This newsletter is produced by Simpson Grierson. It is intended to provide general information in summary form. The contents do not constitute legal advice and should not be relied on as such.
Specialist legal advice should be sought in particular matters. © Copyright Simpson Grierson 2012.
www.simpsongrierson.com
02