Ongoing construction projects in Lister region

NordLink and Vestre korridor;
Ongoing construction projects in Lister region
Fremtiden er elektrisk
Who is who – Statnett team
Contract responsible main contracts:
• Rune Øverås – Converter station
• Miro Radojcic – Transmission lines
• Jørgen Thon – Cable contract
• Morten Snaprud – Station contract
Other Statnett staff:
• Per Husebø – Contract responsible site prep
• André Strand – Communication advisor
• Robert S. Hansen – Procurement Manager
• Øystein Fure – HSE-advisor
• Frode Rudolfsen – Sub-project Manager Nexans-contract
Fremtiden er elektrisk
What to do in NordLink and Phase 1
Vestre korridor?
Vollesfjord
Til Tyskland
3
17.06.2015
Contractors NordLink and phase 1
Vestre korridor • Site preparation
•
•
•
•
•
•
Kvinesdal station (TT Anlegg)
Ertsmyra station (Risa)
Sauda (not decided yet)
Saurdal (Risa)
Upgrading roads Tonstad+Vollesfjord
(Risa)
Construction of forest roads and base
stations (Frame agreement 11
contractors)
• Stations (the four above)
• Converter station Ertsmyra
• Vollesfjord station in cable
contract
Vollesfjord
Til Tyskland
• Upgrade of old lines from 300
kV to 420 kV
• Transmission lines TonstadKvinesdal-Vollesfjord
4
17.06.2015
Distribution Ertsmyra station
\ 5
Ertsmyra now
\ 6
Transmission lines TonstadKvinesdal-Vollesfjord
Distribution Kvinesdal station
\ 8
Distribution Vollesfjord transition
station
\ 9
Upgrade and new forest roads, base
stations
• Approx. 30 km forest roads are
considered to be built
• Approx. 6 km forest road is applied
for according to regulation
«landbruksforskriften» by local
landowners
• (Frame agreement:
11 contractors)
The contractors will explain more
about their scope of supply and need
for local services
Thank you for your attention!
Fremtiden er elektrisk