Last ned - Jernbaneverket

UUT 23 Existing Ulriken tunnel
March 2021 – January 2022
Katrine Sælensminde Erstad – Project Manager Tunnel
Eksisterende Ulriken tunnel
Existing Ulriken tunnel
•
•
•
•
•
•
Åpnet i 1964
7,8 km lang
Tverrsnitt på 25-30 m2
Opened in 1964
Length of 7,8 km
Cross sections of 25-30 m2
Eksisterende Ulriken tunnel
Existing Ulriken tunnel
•
•
Flekkvis udekket PE-skumplater som
vann- og frostsikring
Patches of uncovered PE-foam as water
and frost proofing
Eksisterende Ulriken tunnel
• Enkeltspor
• KL-anlegg
• Dreneringssystem
• Kabeltrasé
• Ledebelysning
• Diverse installasjoner signal og tele
Existing Ulriken tunnel
• Single track
• Catenary system
• Drainage system
• Cable ducts
• Emergency lighting
• Various installations for signalling and
telecommunications
Scope of work
Arbeidsomfang
• Tunneldriving: gjennomslag for to
diagonaltunneler mellom eksisterende og
ny tunnel i Arna
Scope of work
• Tunneling: Breakthrough for two diagonal
tunnels between existing and new tunnel
in Arna
Arbeidsomfang
Scope of work
•
•
Tunneldriving gjennomslag for
adkomsttunnel i Fløen (kun til
eksisterende tunnel)
Tunneling: Breakthrough for access tunnel
at Fløen (only to existing tunnel)
Arbeidsomfang
Scope of work
•
Strossing for viftepar i heng i Fløen
•
Back-ripping (enlargement of profile) for
fans in the tunnel roof in Fløen
•
Rive eksisterende PE-skumplater gjennom
hele tunnelen
•
Dismanteling of existing PE-foam
•
Back-ripping for new water and frost
proofing at different locations through the
tunnel
•
Punktvis strossing for vann- og frostsikring
gjennom hele tunnelen
•
Erstatte eksisterende PE-skumplater og
brannsikre med sprøytebetong
•
Replacement of existing PE-foam,
fireproofing with shotcrete
Kompletterende arbeid ved tverrpassasjer
(sprenging/pigging/kabelkanaler)
•
Complimentary work in cross passages
(blasting/road heading/cable ducts)
Montere bolter for oppheng av skilt og
vifter
•
Installation of bolts for signs and fans
•
Maintenance/adjustment of existing
drainage system, emergency lighting and
cable ducts
•
•
•
Ivareta/tilpasse eksisterende drenering,
ledelys og kabelkanaler
Interfaces with other contracts
UUT 21 Nye Ulriken tunnel
• Rive eksisterende bro og etablere ny bro i
Fløen
• Etablere ny portal i Fløen
UUT 21 New Ulriken tunnel
• Dismantling of existing bridge and
construction of new bridge in Fløen
• Construction of new portal in Fløen
UUT 31 Jernbaneteknikk
UUT 31 Railway engineering
•
•
Fjerne skinner og KL i Arna (1 km)
Dismantling of tracks and catenary system
in Arna (1 km)
UUT 25 Arna stasjon
UUT 25 Arna station
•
•
Etablere ny portal i Arna
Construction of new portal in Arna
Timetable
Rigging areas
Arna
Fløen
Nøkkeltall
Key figures
•
Riving av eksisterende PE-skum 2 400 m2
•
Dismantling of existing PE-foam 2 400 m2
•
Sprenging 27 000 m3
•
Blasting 27 000 m3
•
Ny vann- og frostsikring 18 000 m2
•
New water and frost proofing 18 000 m2