[Skriv text] TIDSPLAN FÖR STAMRENOVERING PÅ NYPONET (hus B) Timeplan for the pipe refurbishment at Nyponet (building B) Vi har delat upp arbetet i nio olika etapper och nedan kan du se vilken etapp din lägenhet tillhör. We have divided the renovation into nine parts and below you can see which part your apartment belongs to. Etapp Part NUMMER Number START Start AVSLUT End 10 2501, 2502, 2503, 2504 2401, 2402, 2403, 2404 2017-01-16 2017-03-17 11 12 2301, 2302, 2303, 2304 2201, 2202, 2203, 2204 2017-01-30 2017-03-31 2101, 2102, 2103, 2104 2001, 2002, 2003, 2004 2017-02-13 2017-04-18 13 14 1901, 1902, 1903, 1904 1801, 1802, 1803, 1804 2017-02-27 2017-05-03 1701, 1702, 1703, 1704 1601, 1602, 1603, 1604 2017-03-13 2017-05-12 15 16 1501, 1502, 1503, 1504 1401, 1402, 1403, 1404 2017-03-27 2017-05-29 1301, 1302, 1303, 1304 1201, 1202, 1203, 1204 2017-04-10 2017-06-12 17 1101, 1102, 1103, 1104 1001, 1002, 1003, 1004 2017-04-24 2017-06-26 18 0901, 0902, 0903, 0904 0905, 0906, 0801, 0802 0803, 0804 2017-05-08 2017-07-07