TIDSPLAN FÖR STAMRENOVERING PÅ NYPONET (hus B)

[Skriv text]
TIDSPLAN FÖR STAMRENOVERING PÅ NYPONET (hus B)
Timeplan for the pipe refurbishment at Nyponet (building B)
Vi har delat upp arbetet i nio olika etapper och nedan kan du se vilken etapp din lägenhet tillhör.
We have divided the renovation into nine parts and below you can see which part your apartment belongs to.
Etapp Part
NUMMER Number
START Start
AVSLUT End
10
2501, 2502, 2503, 2504
2401, 2402, 2403, 2404
2017-01-16
2017-03-17
11
12
2301, 2302, 2303, 2304
2201, 2202, 2203, 2204
2017-01-30
2017-03-31
2101, 2102, 2103, 2104
2001, 2002, 2003, 2004
2017-02-13
2017-04-18
13
14
1901, 1902, 1903, 1904
1801, 1802, 1803, 1804
2017-02-27
2017-05-03
1701, 1702, 1703, 1704
1601, 1602, 1603, 1604
2017-03-13
2017-05-12
15
16
1501, 1502, 1503, 1504
1401, 1402, 1403, 1404
2017-03-27
2017-05-29
1301, 1302, 1303, 1304
1201, 1202, 1203, 1204
2017-04-10
2017-06-12
17
1101, 1102, 1103, 1104
1001, 1002, 1003, 1004
2017-04-24
2017-06-26
18
0901, 0902, 0903, 0904
0905, 0906, 0801, 0802
0803, 0804
2017-05-08
2017-07-07