Mohammed Hammad, Execution Director, Saudi Aramco

E
n
e
r
g
y
t
o
t
h
e
W
o
r
May 11, 2015
ABU Dhabi Downstream
l
d
Agenda
• Facts & Figures
• Key Success Strategies
2
Ships are loaded directly
from the refinery
Jubail -2
SATORP Refinery
Jubail -1
I. ISBL – Segment
II. OSBL – Segment
III. Port Facility - Segment
Petcoke
Handling
Berth
Ships are
loaded directly
from the
Refinery
King Fahd Industrial Port
3
Saudi ARAMCO TOTAL Refinery
and Petrochemicals
400 MBD of Arabian Heavy
Refinery
Product
90 MBD Gasoline
50 MBD Kerosene
190 MBD Diesel (10 ppm)
2,200 KTA Coke
450 KTA Sulfur
700 KTA Paraxylene
140 KTA Benzene
205 KTA Propylene
NO FUEL OIL
Full Conversion
Integrated with
Petrochemical
Refined High Value Product
Complying with most
Stringent International
Specification
Complying with
Royal Commission
Environmental
Regulation
Very sophisticated and Complex Refinery with high
level of Automation
EDCI = 5550 kbd. Solomon Benchmark Ranking #7 in
complexity index among more than 300 Refineries worldwide
4
4
Facts and Figures
• 45,000 employees at the peak
Piping
• 147,000 tones of pipe
• 80,000 tones of steel
Pipe rack
• 4,500 pieces of equipment
FO Pump
• 1 million kilometers of electrical
cable
Electrical Cables
5
Facts and Figures
(Special Presentation)
• Execution started July 2009. 1st
Piping
product shipment was made in
Sept 2013.
• Project came under budget
Pipe rack
• Over 350 Million safe man hours, 7
LTIs
FO Pump
• Average PQI 89%
Electrical Cables
6
Pkg Description
1
Distillation & Hydrotreating
(TR)
2A Conversion (Technip)
2B
Acid Gas Treatment
(Daelim)
3
Aromatics (Samsung)
4
Coker & Merox
(Chiyoda/Samsung)
5A
Interconnecting/PCS/Elect.
(Technip)
5B Plant Utilities (SK)
5C
Auxiliary Utilities
(Al Khathlan)
6
Refinery Tank Farm
(Rotary Engineering)
7
Permanent Infrastructure
(Al Osais)
8
Pipelines & Off Plot
Facilities (GCC)
9
Port Tank Farm
(Dayim Punj loyd)
10
Permanent Communication
(Sumitomo)
7
Main Milestone
16.9% Construction 2010 only
Start Concrete
Foundations
Start
Cable Pulling
Electrical
Start
U/G Piping
Start
A/G Installation
2010
Jan
Feb
Mar
Apr
May
Start of Construction
June
July
Aug
Sept
Oct
Nov
Dec
Complete Mobilization
on site
Start of Site Grading
TCF Construction Activities
Construction Activities Plot 9 Bridge
8
Main Milestone
44.2% Construction 2011 only
50%
Concrete
Pouring
50%
Steel Structure
First SS
Energization
50%
Eq. Erection
2011
Jan
Feb
Mar
Apr
May
June
July
Aug
Sept
Oct
Nov
Dec
50%
Construction
50%
U/G Piping
50%
A/G Piping
Fab. & Erection
Peak of
Construction
5.3%
9
Main Milestone
35.7% Construction 2012 only
Slop Pipelines
& Tanks
Utilities Distr.
Sales Gas
P5A, 5B, 8
P5A
P5A, 6, 8
2012
Sept
Oct
Nov
Dec
Diesel Import
Fire Water
Flare Tr1
RFISU
P5A
P5C
WWT
P5C
10
Main Milestone
2013
CRUDE IMPORT MAY 20
CRUDE IN CDU1 MAY 23
FIRST EXPORT
FUEL OIL
CRUDE in
CDU/VDU2
ALKY and DHC
ALL UNITS
IN OPERATION
TRAIN 1
OPERATION
COKER and MHC
in
OPERATION
Diesel in
CDU/VDU1
PX OPERATION
2013
Apr
May
June
July
Aug
Sept
Oct
Nov
Dec
Jan
FCC in OPERATION
CCR
TRAIN 2
OPERATION
11
12
Key Success Strategies
• Strong FEED documents for all units in plot 9.
No significant changes in process
• Strong Shareholder alignment
• Oversight by BOD & Project Committee
– Governance & immediate decision making
• Strong teamwork within PMT, with Operation &
with EPC’s.
(photo)
• Strong Material procurement Monitoring and Intervention
13
Key Success Strategies
• Adequate PMT Resources
– Overseeing
performance ensuring compliance to schedule,
quality & safety requirements
– 120 Secondees All Key Positions
– 650 SMPs
– 150 Quality
– 30 Safety
• Independency & Agility to Mitigate poor
performance
EPCCs
- Signed (unit rates) Services Contracts &
mobilized resources to support schedule
14
Key Success Strategies
• Subcontractor Award Strategy
– 2 Subcontractors for all major
packages
– Prequalification of all
subcontractors by PMT
• Strong visibility through
appropriate Planning and
Reporting tools
• Risk mapping and management
of mitigation plans
Commissioning Report
15
Lessons Learned
• Small/Medium Contractor not prone to EPCC
• Commissioning activities in complex project must
weight more (5 ÷ 7%) sometimes it was 0.5%
• 3rd Party Interface: SR PM needed
–
–
–
–
New Off plot access Procedures
Marafiq
RC & Other Utilities
KFIP
16
ICAPS & Phases of the work
DETAIL ENG.
CONSTRUCTION
/ PRE-COMMISSIONING
COMMISSIONING
Mobilization of: Comm. Manager
General Preparation
Pre-commissioning Preparation
Preparation team
Commissioning Preparation
PRE COM
EXECUTION
PREPARATION
OPERCOM
COM
EXECUTION
FORMS
PROGRESS
FORMS
PRE COM
PUNCH LIST
COM
PUNCH LIST
PROGRESS
ICAPS
ENGINEERING
POPULATION
REPORTING
REPORTING
Integrated Commissioning and Progress System
17
ICAPS

Process Units
38

Non Process Units
76

Electrical Substations
40

RFC
5,325

RFSU
4,596

RFISU

Total Pre Comm. Tasks
788,078

Total Comm. Tasks
121,859

Total Punch Items (A/B/C/D)
449,416
114
18
E
n
e
r
g
y
t
o
t
h
e
W
o
r
l
d