How to reduce maintenance impacts on natural gas transmission? Ňukovič

How to reduce maintenance
impacts on natural gas
transmission?
Ing. Rastislav Ňukovič
EFG2008, Bratislava, 18.9.2008
Content of the presentation
• Introduction of eustream
• Description of eustream‘s pipeline system
• New challenges for maintenance and how to tackle with
them
• Possibilities for maintenance of pipelines - preparatory
phase
• Possibilities for maintenance of pipelines - performance
phase
• Conclusions
Description of eustream´s transmission system
Lengths of Pipelines:
Diameter of Pipelines:
Transport Capacity:
Maximum Daily Capacity:
Installed Power:
Over 2200 km
Mostly 1 200, 1 400 mm
Over 93 bcm/Year
Over 290 mcm
Almost 1 050 MW
New challenges for maintenance
• new trends in the gas business environment
–
–
–
–
–
increasing competition
increasing number of short-term contracts
increasing number of customers
pressure to shorten maintenance periods
pressure on costs
• need to respond to new legislation
–
–
gas legislation packages
new environmental legislation
transmissionflow
Changing nature of transmission environment
2004
2007
I
II
III
IV
V
VI
VII
VIII
IX
X
XI
XII
month
2004
2005
2006
2007
Average Difference [Nm3/day]
4 419 573
6 005 701
6 753 148
8 240 272
Max/Min Transportation Ratio
1,59
1,96
2,52
2,35
Year
Consequences:
• Increased number of starts of turbo-compressors and auxiliary
technology
• Increased number of manipulations with technological devices
• Higher probability of failures
• Limited time for maintenance activities
How to tackle the new challenges ?
• to shorten the maintenance periods
–
–
preparatory phase (safe stopping and depressurizing of
transmission network technology)
performance phase
• to introduce new maintenance technologies
–
–
improving effectiveness of performance
reducing maintenance impacts on operation - minimizing of
disruptions to the system
Possibilities for maintenance of pipelines
The preparatory phase of the work :
• depressurizing – entire gas discharge to the air
• use of Stopple fittings to isolate the affected section
• using the mobile pumping compressor
– flaring of waste gas
– pre-boosting of the pumping compressor
The performance phase of the work (new technologies):
• orbital welding technology
• non destructive defectoscopy - ultrasonic girth weld
inspection system
Entire gas discharge to the atmosphere
Advantages:
• the quickest way to depressurise the pipeline
• minimal direct costs (personnel, material, services)
Disadvantages:
• large indirect costs (loss of the discharged natural gas)
• large environmental impact
• safety risks – possible dangerous concentration
of the natural gas
• high noise
Conclusions:
• the method is used only in case of emergency
when other methods are not feasible
Use of Stopple fittings
• to isolate the affected pipeline section without flow stoppage
• to build pipeline branch or pipeline looping without flow stoppage
Hot tapping
Stoppling
Plugging
Closed fitting
Example – works schedule for the Stopple fitting DN1200:
Fitting position selection – 1 day
Welding on of the fitting:
longitudinal welds
– 3 days
girth welds
– 4 days
Hot tapping
Stoppling
Plugging
– 3 days
– 2 days
– 3 days
Use of Stopple fittings
Use of Stopple fittings
Advantages:
• low losses of discharged gas
• very low environmental impact – minimum amount of gas
discharged into the atmosphere
• time for maintenance is shortened – hot tapping can be
performed in advance under full operation
• fittings can be re-used for Stoppling in the future
Disadvantages:
• high demands for positioning of fittings (e.g. problems
with existing welds in the pipeline)
• the need to stop the gas flow during the welding phase
• expensive technology
• limited application during emergencies
Use of mobile pumping compressor
Technical parameters
KOA2 – older type
CFA34 – new type
CATERPILLAR
CAT 3412
CATERPILLAR
CAT G3412 TA 130
75 Nm3/hod.,
150 Nm3/hod.,
DRESSER RAND USA
RVM KOA2
CAMERON USA
C-FORCE 34
Technical design
two-stage, double-acting
two-stage, double-acting
Working pistons
1 x 5,25“ a 1 x 7“,
2 x 3,75“ a 2 x 4,125“
Suction pressure
0,7 – 7 MPa
0,5 – 7,5 MPa
7,24 MPa
7,3 MPa
2500 – 24000 Nm3/h
2500 – 38000 Nm3/h
40 t FLOOR
40 t SVAN
Gas engine
Fuel consumption (gas)
Compressor
Max. discharge pressure
Power output
(Dependent on the level and the
ratio of suction / discharge
pressure)
chassis
Use of mobile pumping compressor
Dresser Rand KOA2
Cameron C-Force 34
Use of mobile pumping compressor
Comparison of mobile compressors:
7
KOA
6
CFA
KOA+CFA
Pressure [MPa]
5
4
3
2
1
0
1
2
3
4
5
6
7
8
9
10
Length of repumping [Days]
Evacuation of the pipeline DN1200:
L= 22 000 m ; Psuction= 6,5 MPa; Pdischarge= 6,5Mpa
11
Flaring of waste gas
Advantages:
• environmentally-friendly solution –
reduction of CH4 emissions
• no luminous flame, no heat radiation
• low noise
Disadvantages:
• prolongation of the preparatory
phase
• additional cost
CEB4500
Capacity
100 000 Nm3/day
Power
45 MW
Footprint and Height
3 x 2,6 x 6,2 m
Weight
7500 kg
Inlet pressure
0.8 barg - 8 barg
Electrical power consumption
5 kW
Battery limit
3’’ ANSI 150 lbs RF
Operating Temperature
900 - 1200°C
Ground Temperature
Ambient during operation
Example:
• pipeline DN1200; L= 22 000 m
• start pressure flaring: 8 bar(g)
• stop pressure flaring: 1 bar(g)
Flaring configuration:
2 x CEB4500
3 x CEB4500
Flare time:
41 hours
28 hours
Use of mobile pumping compressor
Pre-boosting of the mobile compressor:
Objectives:
• to shorten evacuation period
• to achieve lower suction pressures
MC – mobile compressor
BC – boosting compressor
PV – pressure vessel
Reasons:
• to improve effectiveness of the
mobile pumping compressor
• to develop environmentally-friendly
solution
Use of mobile pumping compressor
Advantages:
• relatively low direct costs (price of the compressor rent,
personnel, average consumption – 75 m3/h)
• low environmental impact (only a small amount of the gas is
discharged)
• possible solutions for further decrease of the environmental
impacts
Disadvantages:
• length of pumping time – prolongation of the maintenance
activity
• technical limit - minimal suction pressure 0,7/0,5 MPa –
below this limit operation is not possible
• high initial investment to buy the mobile pumping
compressor
Performance phase - Orbital welding
Objective:
• to speed up the welding works
Features:
• automated solution
• about 50% time reduction
compared to the manual welding
• difficulties to use the technology in
complex conditions
Performance phase – Non Destructive Defectoscopy
NDT – ultrasonic girth weld inspection
system
Objective:
• to speed up the defectoscopy works
Features:
• comparable method to X-ray
• about 30%-50% time reduction
compared to X-ray
• difficulties with welds on pipelines
with different wall thickness
Summary
Maintenance of pipelines – preparatory phase:
Impact on the
length of
maintenance
Safety
risks
Environmen
tal impacts
Used technology
Direct costs
Indirect
costs
Discharge to the
atmosphere
minimal
high
low
high
high
Mobile pumping
compressor
medium
low
high
medium
medium
Stopple fittings
high
minimal
medium
medium
minimal
Maintenance of pipelines – performance phase:
• orbital welding technology – to speed up the welding works by
50%
• non-destructive defectoscopy – ultrasonic girth weld inspection
system
Thank you for your attention