Cost valuation reconciliation

Cost valuation reconciliation
When
• Usually commences after the external
valuation
• Time dependent upon the complexity and size
of project
• Usually takes two weeks to complete
• Discussed at Monthly CVR meeting
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
2
Fundamental principle
• Prudence
• Match expenditure with income
• Uses the application for payment and the
architects certificate to substantiate the
valuation/Net sales value of the works
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
3
Documentation used
• External valuation
– Identification of:
•
•
•
•
•
•
Overmeasure
Undermeasure
Variations in dispute
Claims in dispute
Materials on site
Undercertification
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
4
Information flows
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
5
Documentation (contd.)
•
•
•
•
•
Overmeasure schedule
Undermeasure schedule
Subcontractor liability build-up
Architects/Engineers certificates
Contra charge invoices
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
6
Definitions
• Overmeasure
– Claimed-Unpaid
– Claimed-Paid
• Definition-“Application for monies in advance of their eligibility”
• Undermeasure
• Definition-“Work completed that costs have been incurred for but
haven’t been included in the application for payment”
– Measured works
– Variations
• Work in Progress
• Definition-“Work that has been carried out in the period between
the cost cut-off date and the valuation date”
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
7
Basic principle
• Net sales value uses the application for
payment as the baseline
• Application adjusted as follows:
– Overmeasure – Deducted
– Undermeasure - Added
– Materials on site - Deleted
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
8
Basic principle
• Net sales value uses the application for
payment as the baseline
• Application adjusted as follows:
– Overmeasure – Deducted
– Undermeasure - Added
– Materials on site - Deleted
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
9
Documentation supporting the CVR
•
•
•
•
•
•
•
•
•
•
•
Internal valuation broken down into a set of allowances
Overmeasure schedule
Undermeasure schedule
Cost statement
Subcontractor liabilities
Buying reconciliation
Materials reconciliation
Cost to complete exercise
Estimated final account/profit margin
Architects/Engineers certificate
Narrative explaining variances
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
10
Cost statement
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
11
Adjustments for work in progress
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
12
When to report a loss?
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
13
Internal and external bills
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
14
Adjustments
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
15
Simplified CVR pro forma
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
16
A more complex example
17
Discussions at CVR meeting
•
•
•
•
Profit release
Cash flow
Turnover
Items in dispute
– Variations
– Claims
• Items for management action
© 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.
18